rab selasar radiologi

17
DAFTAR KUANTITAS DAN HARGA K E G I A T A N : REHABILITASI GEDUNG RS MARGONO SOEKARDJO P E K E R J A A N : PENAMBAHAN SELASAR DEPAN RUANG RADIOLOGI L O K A S I : RSMS B I A Y A : Rp 144,143,000.00 TAHUN ANGGARAN : 2 0 1 3 NO. MACAM PEKERJAAN ANALISA VOLUME SAT. A. PEKERJAAN PERSIAPAN 1 Pengukuran & Pas.Bouwplank Kayu Albasia SNI - A.6.4 47.74 M' 39,105.00 ### 2 Membersihkan Lapangan dan Perataan SNI - A.6.8 214.75 M2 5,750.00 ### 3 Pemb. Bak Adukan Uk.(40x50x20)cm Ky.Alba SNI - A.6.1 2.00 Bh 86,537.50 ### 4 steger dari bambu SNI - A.6.11 67.11 m2 27,647.50 ### 5 Bongkaran beton bertulang SNI - A.6.13 0.32 M3 ### 78,223.95 6 Bongkaran rangka atap DP 1.00 Unit ### ### 7 Perbaikan atap lama DP 1.00 Unit ### ### B. PEKERJAAN TANAH 1 Galian Tanah Biasa Sedalam 1 M SNI - B.6.1 14.55 M3 27,375.00 ### 2 Pemadatan Tanah per 20 cm SNI - B.6.10 36.70 M3 19,750.00 ### 3 Urugan Pasir SNI - B.6.1 14.46 M3 ### ### 4 Urugan Sirtu SNI - B.6.15 36.70 M3 ### ### C. PEKERJAAN PONDASI BATU KALI 1 Pas. Pondasi Batu Belah 1 PC : 5 Psr SNI - C.6.3 3.36 M3 ### ### D. PEKERJAAN DINDING 1 Pas. Batu Merah tb. 1/2 bata 1 PC : 5 P SNI - D.6.1 42.65 M2 77,345.00 ### 2 Pas. Batu alam motif DP 33.00 M2 ### ### E. PEKERJAAN PLESTERAN 1 Plesteran 1 PC : 3 PP tb. 1,5 cm SNI - E.6.14 14.88 M2 38,047.00 ### 2 Plesteran 1 PC : 5 PP tb. 1,5 cm SNI - E.6.5 58.30 M2 28,861.00 ### F. PEKERJAAN BETON 1 Footplat (FP1) Membuat Beton Tumbuk 1Pc:3Ps:5Kr SNI - G.6.1 0.37 M3 ### ### Membuat Beton Cor 1Pc:2Ps:3Kr SNI - G.6.1 1.67 M3 ### ### Pembesian dengan Besi Beton Polos SNI - G.6.2 271.65 Kg 12,929.50 ### Cetakan beton Kayu Albasia BOW - F.8 7.80 M2 ### ### 2 Kolom FP1 (30x30) Membuat Beton Cor 1Pc:2Ps:3Kr SNI - G.6.1 0.27 M3 ### ### Pembesian dengan Besi Beton Polos SNI - G.6.2 64.20 Kg 12,929.50 ### Cetakan beton Kayu Albasia BOW - F.8 2.70 M2 ### ### 3 Kolom 20 x 20 Membuat Beton Cor 1Pc:2Ps:3Kr SNI - G.6.1 4.28 M3 ### ### Pembesian dengan Besi Beton Polos SNI - G.6.2 272.70 Kg 12,929.50 ### Cetakan beton Kayu Albasia BOW - F.8 19.05 M2 ### ### 4 Sloof 15 x 20 Membuat Beton Cor 1Pc:2Ps:3Kr SNI - G.6.1 2.70 M3 ### ### Pembesian dengan Besi Beton Polos SNI - G.6.2 480.60 Kg 12,929.50 ### Cetakan beton Kayu Albasia BOW - F.8 1.80 M2 ### ### lantai kerja beton tumbuk 1 : 3 : 5 SNI - G.6.1 0.68 M3 ### ### 5 Balok tarik 15 x 20 Membuat Beton Cor 1Pc:2Ps:3Kr SNI - G.6.1 1.34 M3 ### ### Pembesian dengan Besi Beton Polos SNI - G.6.2 238.94 Kg 12,929.50 ### Cetakan beton Kayu Albasia BOW - F.8 13.12 M2 ### ### Steger sebagai perancah SNI - A.6.1 13.12 M2 27,647.50 ### 6 Balok Konsol 20 x 30 Membuat Beton Cor 1Pc:2Ps:3Kr SNI - G.6.1 4.00 M3 ### ### Pembesian dengan Besi Beton Polos SNI - G.6.2 455.31 Kg 12,929.50 ### Cetakan beton Kayu Albasia BOW - F.8 26.52 M2 ### ### Steger sebagai perancah SNI - A.6.1 26.52 M2 27,647.50 ### G. PEKERJAAN LANGIT - LANGIT 1 Pasang Eternit 100 x 100 DP 199.09 M2 38,155.00 ### H. PEKERJAAN SANITASI 1 Pas. Saluran U 30 dengan buis beton DP 44.47 M' 32,523.75 ### I. PEKERJAAN LANTAI 1 Pasang beton tumbuk 1:3:5 SNI - G.6.1 3.35 M3 ### ### 2 Pas. Lt.Keramik 30x30 cm (Klas A) SNI-L.6.47e 54.00 M2 ### ### HARGA SATUAN ( Rp ) JML HRG SAT. ( Rp )

Upload: aura1003

Post on 14-Dec-2015

247 views

Category:

Documents


36 download

DESCRIPTION

RS Margono - Purwokerto

TRANSCRIPT

Page 1: Rab Selasar Radiologi

DAFTAR KUANTITAS DAN HARGAK E G I A T A N : REHABILITASI GEDUNG RS MARGONO SOEKARDJOP E K E R J A A N : PENAMBAHAN SELASAR DEPAN RUANG RADIOLOGIL O K A S I : RSMSB I A Y A : Rp 144,143,000.00 TAHUN ANGGARAN : 2 0 1 3

NO. MACAM PEKERJAAN ANALISA VOLUME SAT. JUMLAH TOTAL (Rp.)

A. PEKERJAAN PERSIAPAN 7,397,419.38 1 Pengukuran & Pas.Bouwplank Kayu Albasia SNI - A.6.4a 47.74 M' 39,105.00 1,866,872.70 2 Membersihkan Lapangan dan Perataan SNI - A.6.8 214.75 M2 5,750.00 1,234,824.00 3 Pemb. Bak Adukan Uk.(40x50x20)cm Ky.Albasia SNI - A.6.10 2.00 Bh 86,537.50 173,075.00 4 steger dari bambu SNI - A.6.11 67.11 m2 27,647.50 1,855,423.73 5 Bongkaran beton bertulang SNI - A.6.13 0.32 M3 248,330.00 78,223.95 6 Bongkaran rangka atap DP 1.00 Unit 1,565,000.00 1,565,000.00 7 Perbaikan atap lama DP 1.00 Unit 624,000.00 624,000.00

B. PEKERJAAN TANAH 7,129,080.751 Galian Tanah Biasa Sedalam 1 M SNI - B.6.1 14.55 M3 27,375.00 398,306.25 2 Pemadatan Tanah per 20 cm SNI - B.6.10 36.70 M3 19,750.00 724,825.00 3 Urugan Pasir SNI - B.6.11 14.46 M3 100,950.00 1,459,737.00 4 Urugan Sirtu SNI - B.6.15 36.70 M3 123,875.00 4,546,212.50

C. PEKERJAAN PONDASI BATU KALI 1,757,162.4000 1 Pas. Pondasi Batu Belah 1 PC : 5 Psr SNI - C.6.3 3.36 M3 522,965.00 1,757,162.40

D. PEKERJAAN DINDING 9,923,877.25 1 Pas. Batu Merah tb. 1/2 bata 1 PC : 5 Psr SNI - D.6.10 42.65 M2 77,345.00 3,298,764.25 2 Pas. Batu alam motif DP 33.00 M2 200,761.00 6,625,113.00

E. PEKERJAAN PLESTERAN 2,248,735.66 1 Plesteran 1 PC : 3 PP tb. 1,5 cm SNI - E.6.14 14.88 M2 38,047.00 566,139.36 2 Plesteran 1 PC : 5 PP tb. 1,5 cm SNI - E.6.5 58.30 M2 28,861.00 1,682,596.30

F. PEKERJAAN BETON 44,918,814.20 1 Footplat (FP1)

Membuat Beton Tumbuk 1Pc:3Ps:5Kr SNI - G.6.1 0.37 M3 653,900.00 241,943.00 Membuat Beton Cor 1Pc:2Ps:3Kr SNI - G.6.13 1.67 M3 837,950.00 1,399,376.50 Pembesian dengan Besi Beton Polos SNI - G.6.25 271.65 Kg 12,929.50 3,512,298.68 Cetakan beton Kayu Albasia BOW - F.8 7.80 M2 114,550.00 893,490.00

2 Kolom FP1 (30x30)Membuat Beton Cor 1Pc:2Ps:3Kr SNI - G.6.13 0.27 M3 837,950.00 226,246.50 Pembesian dengan Besi Beton Polos SNI - G.6.25 64.20 Kg 12,929.50 830,073.90 Cetakan beton Kayu Albasia BOW - F.8 2.70 M2 114,550.00 309,285.00

3 Kolom 20 x 20Membuat Beton Cor 1Pc:2Ps:3Kr SNI - G.6.13 4.28 M3 837,950.00 3,586,426.00 Pembesian dengan Besi Beton Polos SNI - G.6.25 272.70 Kg 12,929.50 3,525,874.65 Cetakan beton Kayu Albasia BOW - F.8 19.05 M2 114,550.00 2,182,177.50

4 Sloof 15 x 20Membuat Beton Cor 1Pc:2Ps:3Kr SNI - G.6.13 2.70 M3 837,950.00 2,262,465.00 Pembesian dengan Besi Beton Polos SNI - G.6.25 480.60 Kg 12,929.50 6,213,917.70 Cetakan beton Kayu Albasia BOW - F.8 1.80 M2 114,550.00 206,190.00 lantai kerja beton tumbuk 1 : 3 : 5 SNI - G.6.1 0.68 M3 653,900.00 441,382.50

5 Balok tarik 15 x 20Membuat Beton Cor 1Pc:2Ps:3Kr SNI - G.6.13 1.34 M3 837,950.00 1,122,853.00 Pembesian dengan Besi Beton Polos SNI - G.6.25 238.94 Kg 12,929.50 3,089,374.73 Cetakan beton Kayu Albasia BOW - F.8 13.12 M2 114,550.00 1,502,896.00 Steger sebagai perancah SNI - A.6.11 13.12 M2 27,647.50 362,735.20

6 Balok Konsol 20 x 30Membuat Beton Cor 1Pc:2Ps:3Kr SNI - G.6.13 4.00 M3 837,950.00 3,351,800.00 Pembesian dengan Besi Beton Polos SNI - G.6.25 455.31 Kg 12,929.50 5,886,930.65 Cetakan beton Kayu Albasia BOW - F.8 26.52 M2 114,550.00 3,037,866.00 Steger sebagai perancah SNI - A.6.11 26.52 M2 27,647.50 733,211.70

G. PEKERJAAN LANGIT - LANGIT 7,596,278.95 1 Pasang Eternit 100 x 100 DP 199.09 M2 38,155.00 7,596,278.95

H. PEKERJAAN SANITASI 1,446,331.16 1 Pas. Saluran U 30 dengan buis beton DP 44.47 M' 32,523.75 1,446,331.16

I. PEKERJAAN LANTAI 9,059,635.00 1 Pasang beton tumbuk 1:3:5 SNI - G.6.1 3.35 M3 653,900.00 2,190,565.00 2 Pas. Lt.Keramik 30x30 cm (Klas A) SNI-L.6.47e 54.00 M2 127,205.00 6,869,070.00

HARGA SATUAN ( Rp

) JML HRG SAT.

( Rp )

Page 2: Rab Selasar Radiologi

J. PEKERJAAN PENGECATAN 8,835,961.87 1 Mengecat kayu 3 x jadi (Sek. Avian) SNI - M.6.9 69.80 M2 36,605.00 2,555,029.00 2 Mengecat Tembok Baru (sek.Catylac) SNI - M.6.14b 110.50 M2 11,313.50 1,250,141.75 3 Mengecat Tembok lama (sek.Catylac) SNI - M.6.15b 101.13 M2 8,766.50 886,573.68 4 Mengecat Plafond ( sek. Decolith) BOW-K6+23a 199.09 M2 19,068.75 3,796,397.44 5 pelapisan couting batu alam BOW-Supl.IV.c 26.40 m2 13,175.00 347,820.00

K. PEKERJAAN ATAP 30,726,038.02 1 Konstruksi gording, kayu Kruing SNI - F.6.16b 2.15 M3 7,299,800.00 15,694,570.00

2 SNI - F.6.18b 63.53 M2 80,865.00 5,137,353.45

3 Pas. Atap Genteng Plentong Kecil SNI - H.6.1 63.53 M2 46,657.50 2,964,150.98

4 BOW - F.16 134.22 M2 11,925.00 1,600,573.50

5 Pas. Atap Genteng Plentong Kecil ( bahan dari rsms) DP 134.22 M2 10,282.50 1,380,117.15 6 Pasang talang miring seng BJLS SNI - H.6.41 8.84 M' 111,048.50 981,668.74 7 Pas. Lisplank Kayu Kruing Uk. 2 ( 2 x 20 ) cm SNI - F.6.29c 44.74 M' 66,330.00 2,967,604.20

JUMLAH KONSTRUKSI 131,039,334.63 PPN 10 % X NILAI KONSTRUKSI 13,103,933.46 JUMLAH TOTAL 144,143,268.09

JUMLAH DIBULATKAN 144,143,000.00

Terbilang : SERATUS EMPAT PULUH EMPAT JUTA SERATUS EMPAT PULUH TIGA RIBU RUPIAH

Purwokerto, 2013

P E N A W A R CV RAHAYU JAYA SANTOSA

EDY WIWOHO Direktur

Pas. Kaso dan Reng genteng (kodok, plentong, vlams dan sejenisnya) Kayu Kruing

Pas. Kaso dan Reng genteng (kodok, plentong, vlams dan sejenisnya) Kayu Kruing ( bahan dari rsms)

Page 3: Rab Selasar Radiologi

ANALISA HARGA SATUAN PEKERJAAN

K E G I A T A N : REHABILITASI GEDUNG RS MARGONO SOEKARDJOP E K E R J A A N : PENAMBAHAN SELASAR DEPAN RUANG RADIOLOGIL O K A S I : RSMSB I A Y A : Rp 144,143,000.00 TAHUN ANGGARAN : 2 0 1 3

KODE ANALIS JENIS & URAIAN PEKERJAAN KOEFISIEN SATUAN HRG. STN ( Rp ) HARGA ( Rp )

1 2 3 4 5 6 = 3 x 5

SNI - A.6.4a Pengukuran dan Pemas.Bouwplank ( Ky Tahun ) M' 39,105.00

Usuk 5/7 Kayu Tahun 0.0120 m3 1,600,000.00 19,200.00

Paku Biasa ( 2'" - 5 " ) 0.0200 kg 14,000.00 280.00

Papan Kayu Tahun 3/20 0.0070 m3 1,600,000.00 11,200.00

P e k e r j a 0.1000 oh 35,000.00 3,500.00

Tukang kayu 0.1000 oh 42,500.00 4,250.00

Kepala Tukang 0.0100 oh 45,000.00 450.00

Mandor 0.0050 oh 45,000.00 225.00

SNI - A.6.8 Membersihkan Lapangan dan Perataan M2 5,750.00

P e k e r j a 0.1000 oh 35,000.00 3,500.00

Mandor 0.0500 oh 45,000.00 2,250.00

SNI - A.6.10 Pembuatan Bak Adukan Uk. ( 40x50x20 ) cm Kayu Tahun 86,537.50

Kayu tahun 0.0360 m3 1,600,000.00 57,600.00

Paku Biasa ( 2'" - 5 " ) 0.0800 kg 14,000.00 1,120.00

Usuk 5/7 Kayu Tahun 1.0000 btg 15,000.00 15,000.00

Tukang Batu 0.3000 oh 42,500.00 12,750.00

Mandor 0.0015 oh 45,000.00 67.50

SNI - A.6.11 Pembuatan Steger dari Bambu M2 27,647.50

Bambu diameter 6 - 8 / 6 m' 1.0000 btg 14,000.00 14,000.00

Tali Ijuk 0.2500 kg 14,000.00 3,500.00

P e k e r j a 0.2500 oh 35,000.00 8,750.00

Tukang kayu 0.0170 oh 42,500.00 722.50

Kepala Tukang 0.0020 oh 45,000.00 90.00

Mandor 0.0130 oh 45,000.00 585.00

SNI - A.6.13 Bongkaran Beton Bertulang M3 248,330.00 P e k e r j a 6.667 OH 35,000.00 233,345.00 M a n d o r 0.333 OH 45,000.00 14,985.00

SNI - B.6.1 Galian Tanah Biasa Sedalam 1 m M3 27,375.00

P e k e r j a 0.7500 oh 35,000.00 26,250.00

Mandor 0.0250 oh 45,000.00 1,125.00

SNI - B.6.9 Urugan Kembali M3 9,123.50

P e k e r j a 0.2500 oh 35,000.00 8,750.00

Mandor 0.0083 oh 45,000.00 373.50

SNI - B.6.10 Pemadatan Tanah (per 20 cm) M3 19,750.00

P e k e r j a 0.5 OH 35,000.00 17,500.00

M a n d o r 0.05 OH 45,000.00 2,250.00

SNI - B.6.11 Urugan Pasir M3 100,950.00

Pasir urug 1.2000 m3 75,000.00 90,000.00

P e k e r j a 0.3000 oh 35,000.00 10,500.00

M a n d o r 0.0100 oh 45,000.00 450.00

SNI - B.6.15 Urugan Sirtu M3 123,875.00

S i r t u 1.2 M3 95,000.00 114,000.00

P e k e r j a 0.25 OH 35,000.00 8,750.00

M a n d o r 0.025 OH 45,000.00 1,125.00 SNI - C.6.3 Pas. Pondasi Batu Belah 1 PC : 5 Psr M3 522,965.00

Batu Kali Belah 1.2000 M3 140,000.00 168,000.00 Portland Cement 136.00 Kg 1,500.00 204,000.00 Pasir Pasang 0.5440 M3 110,000.00 59,840.00 P e k e r j a 1.5000 OH 35,000.00 52,500.00 Tukang Batu 0.7500 OH 42,500.00 31,875.00 Kepala Tukang 0.0750 OH 45,000.00 3,375.00 M a n d o r 0.0750 OH 45,000.00 3,375.00

SNI - E.6.14 Plesteran 1 PC : 3 PP tb. 2 cm M2 38,047.00 Portland Cement 10.3680 Kg 1,500.00 15,552.00 Pasir Pasang 0.0310 M3 110,000.00 3,410.00 P e k e r j a 0.2600 OH 35,000.00 9,100.00 Tukang Batu 0.2000 OH 42,500.00 8,500.00 Kepala Tukang 0.0200 OH 45,000.00 900.00 M a n d o r 0.0130 OH 45,000.00 585.00

Page 4: Rab Selasar Radiologi

SNI - E.6.5 Plesteran 1 PC : 5 PP tb. 1,5 cm M2 28,861.00 Portland Cement 5.1840 Kg 1,500.00 7,776.00 Pasir Pasang 0.0260 M3 110,000.00 2,860.00 P e k e r j a 0.3000 OH 35,000.00 10,500.00 Tukang Batu 0.1500 OH 42,500.00 6,375.00 Kepala Tukang 0.0150 OH 45,000.00 675.00 M a n d o r 0.0150 OH 45,000.00 675.00

SNI - D.6.8 Pas. Batu merah Tb.1/2 bata 1 Pc : 3 Ps M2 84,530.00

Batu Merah (5x11x22cm) 70.0000 Bh 600.00 42,000.00 Portland Cement 14.3700 Kg 1,500.00 21,555.00

Pasir Pasang 0.0400 M3 110,000.00 4,400.00

P e k e r j a 0.3200 OH 35,000.00 11,200.00

Tukang Batu 0.1000 OH 42,500.00 4,250.00

Kepala Tukang 0.0100 OH 45,000.00 450.00

M a n d o r 0.0150 OH 45,000.00 675.00 SNI - D.6.10 Pas. Batu Merah tb. 1/2 bata 1 PC : 5 Psr M2 77,345.00

Batu Merah 70.0000 Bh 600.00 42,000.00 Portland Cement 9.6800 Kg 1,500.00 14,520.00 Pasir Pasang 0.0450 M3 110,000.00 4,950.00 P e k e r j a 0.3000 OH 35,000.00 10,500.00 Tukang Batu 0.1000 OH 42,500.00 4,250.00 Kepala Tukang 0.0100 OH 45,000.00 450.00 M a n d o r 0.0150 OH 45,000.00 675.00

SNI - F.6.16 b Konstruksi Gording Kayu Kruing M3 7,299,800.00

Kayu Kruing Balok 1.1000 m3 6,100,000.00 6,710,000.00

Besi strip tebal 5 mm 15.0000 kg 8,000.00 120,000.00

Paku 12 cm 3.0000 kg 14,000.00 42,000.00

P e k e r j a 2.4000 oh 35,000.00 84,000.00

Tukang Kayu 7.2000 oh 42,500.00 306,000.00

Kepala Tukang 0.7200 oh 45,000.00 32,400.00

Mandor 0.1200 oh 45,000.00 5,400.00

SNI - F.6.18b Pasang Kaso dan Reng Genteng ( Kodok,plentong,-M2

80,865.00

vlams dan sejenisnya ) kayu KruingUsuk Kruing 5/7 cm 0.0090 m3 5,700,000.00 51,300.00

Reng Kruing ( 2x3) cm 0.0036 m3 4,900,000.00 17,640.00

Paku 5 dan 10 cm 0.2500 kg 14,000.00 3,500.00

P e k e r j a 0.1000 oh 35,000.00 3,500.00

Tukang Kayu 0.1000 oh 42,500.00 4,250.00

Kepala Tukang 0.0100 oh 45,000.00 450.00

Mandor 0.0050 oh 45,000.00 225.00

SNI - F.6.29c Pas. Lisplank Kayu Kruing Uk. 2 ( 2 x 20 ) cm M' 66,330.00

Papan Kruing 0.0086 m3 6,400,000.00 55,040.00

Paku Biasa ( 2" - 5 " ) 0.0600 kg 14,000.00 840.00

P e k e r j a 0.1000 oh 35,000.00 3,500.00

Tukang Kayu 0.1000 oh 42,500.00 4,250.00

Kepala Tukang 0.0100 oh 45,000.00 450.00

Mandor 0.0500 oh 45,000.00 2,250.00

SNI - G.6.1 Membuat Beton Tumbuk 1 PC : 3 Ps : 5 Kr M3 653,900.00

Portland Cement 218.00 kg 1,500.00 327,000.00

Pasir Beton 0.5200 m3 120,000.00 62,400.00

Koral Beton ( Batu pecah 2/3 cm ) 0.8700 m3 220,000.00 191,400.00

P e k e r j a 1.6500 oh 35,000.00 57,750.00

Tukang Batu 0.2500 oh 42,500.00 10,625.00

Kepala Tukang 0.0250 oh 45,000.00 1,125.00

M a n d o r 0.0800 oh 45,000.00 3,600.00

SNI - G.6.13 Membuat Beton Cor 1 PC : 2 Ps : 3 Kr M3 837,950.00

Portland Cement 336.0000 kg 1,500.00 504,000.00

Pasir Beton 0.5400 m3 120,000.00 64,800.00

Koral Beton ( Batu Pecah 2/3 cm ) 0.8100 m3 220,000.00 178,200.00

P e k e r j a 2.0000 oh 35,000.00 70,000.00

Tukang Batu 0.3500 oh 42,500.00 14,875.00

Kepala Tukang 0.0350 oh 45,000.00 1,575.00

Mandor 0.1000 oh 45,000.00 4,500.00

SNI - G.6.25 Pembesian Dengan Besi Beton Polos Kg 12,929.50

Besi Beton Polos 1.0500 kg 11,500.00 12,075.00

Kawat Beton ( Bindrat ) 0.0150 kg 17,500.00 262.50

P e k e r j a 0.0070 oh 35,000.00 245.00

Tukang Besi 0.0070 oh 42,500.00 297.50

Kepala Tukang 0.0007 oh 45,000.00 31.50

Mandor 0.0004 oh 45,000.00 18.00

DP Pas. Atap Genteng Plentong Kecil ( Bahan Dari Rsms) M2 10,282.50

P e k e r j a 0.1500 oh 42,500.00 6,375.00

Tukang Kayu 0.0750 oh 42,500.00 3,187.50

Kepala Tukang 0.0080 oh 45,000.00 360.00

Mandor 0.0080 oh 45,000.00 360.00

SNI - H.6.1 Pas. Atap Genteng Plentong Kecil M2 46,657.50

Genteng Plentong 25.0000 bh 1,500.00 37,500.00

P e k e r j a 0.1500 oh 35,000.00 5,250.00

Tukang Kayu 0.0750 oh 42,500.00 3,187.50

Kepala Tukang 0.0080 oh 45,000.00 360.00

Mandor 0.0080 oh 45,000.00 360.00

Page 5: Rab Selasar Radiologi

SNI - H.6.41 Pas. Talang miring seng BJLS 30 ( kayu kruing ) M' 111,048.50

Seng plat 3" x 6" BJLS 30 0.5000 lbr 25,000.00 12,500.00

Paku seng ( 1/2" - 1" ) 0.0150 kg 31,000.00 465.00

Papan meranti 0.0190 m3 3,500,000.00 66,500.00

Meni besi 0.3000 kg 40,000.00 12,000.00

P e k e r j a 0.0400 oh 35,000.00 1,400.00

Tukang Kayu 0.4000 oh 42,500.00 17,000.00

Kepala Tukang 0.0250 oh 45,000.00 1,125.00

Mandor 0.0013 oh 45,000.00 58.50

DP Pas.Langit-langit Eternit (1,00x1,00 )m M2 38,155.00

Paku Plafond 0.0600 kg 14,000.00 840.00

Paku Eternit, Lis 0.0100 kg 17,000.00 170.00

Eternit ( 1.00 x 1.00 ) m 1.1000 lbr 14,000.00 15,400.00

P e k e r j a 0.1800 oh 35,000.00 6,300.00

Tukang Kayu 0.3200 oh 42,500.00 13,600.00

Kepala Tukang 0.0320 oh 45,000.00 1,440.00

Mandor 0.0090 oh 45,000.00 405.00

SNI - I.6.20 c Pas.Langit-langit Eternit (1,00x1,00 )m Rk.Ky Meranti M2 74,155.00

Usuk Meranti 5/7 0.0120 m3 3,000,000.00 36,000.00

Paku Plafond 0.0600 kg 14,000.00 840.00

Paku Eternit, Lis 0.0100 kg 17,000.00 170.00

Eternit ( 1.00 x 1.00 ) m 1.1000 lbr 14,000.00 15,400.00

P e k e r j a 0.1800 oh 35,000.00 6,300.00

Tukang Kayu 0.3200 oh 42,500.00 13,600.00

Kepala Tukang 0.0320 oh 45,000.00 1,440.00

Mandor 0.0090 oh 45,000.00 405.00 BOW-Supl.IV.c Pelapisan Coating 3 x ( sebelum dipasang ) M2 13,175.00

Cairan coating 0.4500 Ltr 21,000.00 9,450.00 P e k e r j a 0.1000 OH 35,000.00 3,500.00 M a n d o r 0.0050 OH 45,000.00 225.00

SNI - M.6.9 M2 36,605.00

Cat meni 0.2000 Kg 23,000.00 4,600.00

Plamir Kayu 0.1500 Kg 18,000.00 2,700.00

Cat dasar ( sek. Avian ) 0.1700 Kg 42,500.00 7,225.00

Cat Penutup ( sek. Avian ) 0.3500 Kg 42,500.00 14,875.00

P e k e r j a 0.0700 oh 35,000.00 2,450.00

Tukang Cat 0.1050 oh 42,500.00 4,462.50

Kepala Tukang 0.0040 oh 45,000.00 180.00

M a n d o r 0.0025 oh 45,000.00 112.50

SNI - M.6.14b M2 11,313.50

Plamir Tembok 0.1000 Kg 7,000.00 700.00 Cat dasar ( sek. Catylac ) 0.1000 Kg 19,000.00 1,900.00 Cat Penutup 2 kali ( sek. Catylac ) 0.2600 Kg 19,000.00 4,940.00 P e k e r j a 0.0200 OH 35,000.00 700.00 Tukang Cat 0.0630 OH 42,500.00 2,677.50 Kepala Tukang 0.0063 OH 45,000.00 283.50 M a n d o r 0.0025 OH 45,000.00 112.50

SNI - M.6.15b M2 8,766.50

Cat dasar ( sek. Catylac ) 0.12 Kg 19,000.00 2,280.00

Cat Penutup 2 kali ( sek. Catylac ) 0.18 Kg 19,000.00 3,420.00

P e k e r j a 0.028 OH 35,000.00 980.00

Tukang Cat 0.042 OH 42,500.00 1,785.00

Kepala Tukang 0.0042 OH 45,000.00 189.00

M a n d o r 0.0025 OH 45,000.00 112.50

DP Pasang batu alam motif M2 200,761.00

Batu alam motif 1.1 m2 150,000.00 165,000.00

Portland Cement 10.224 Kg 1,500.00 15,336.00

Pasir Pasang 0.02 M3 110,000.00 2,200.00

P e k e r j a 0.3 OH 35,000.00 10,500.00

Tukang Batu 0.15 OH 42,500.00 6,375.00

Kepala Tukang 0.015 OH 45,000.00 675.00

M a n d o r 0.015 OH 45,000.00 675.00

BOW - F.8 Cetakan Beton Kayu Tahun M2 114,550.00

Kayu Tahun 0.0400 M3 1,600,000.00 64,000.00

Paku Biasa ( 2" - 5") 0.4000 Kg 14,000.00 5,600.00

Tukang Kayu 0.5000 oh 42,500.00 21,250.00

Kepala Tukang 0.0500 oh 45,000.00 2,250.00

P e k e r j a 0.2000 oh 35,000.00 7,000.00

M a n d o r 0.0100 oh 45,000.00 450.00

Pekerja Bongkar / Siram 0.4000 oh 35,000.00 14,000.00

BOW - F.16 Pasang Kembali Usuk dan Reng Bekas M2 11,925.00

Paku Biasa ( 2" - 5") 0.25 Kg 14,000.00 3,500.00

Tukang Kayu 0.1 OH 42,500.00 4,250.00

Kepala Tukang 0.01 OH 45,000.00 450.00

P e k e r j a 0.1 OH 35,000.00 3,500.00

M a n d o r 0.005 OH 45,000.00 225.00

Pengecatan Bidang Kayu Baru( 1 lps plamir, 1 lps cat dasar, 3 lps cat penutup ) Sek. Avian

Pengecatan Tembok Baru( 1 lps plamir, 1 lps cat dasar, 2 lps cat penutup ) Sek. Catylac

Pengecatan Tembok Lama ( 1 lps cat dasar, 2 lps cat penutup ) Sek. Catylac

Page 6: Rab Selasar Radiologi

BOW-K6+23a Pengecatan Plafond 3 x ( Sekualitas Decolithe ) M2 19,068.75

Cat Tembok ( Sek.Decolithe ) 0.4000 kg 14,000.00 5,600.00

Tukang Cat 0.1875 oh 42,500.00 7,968.75

Kepala Tukang 0.0188 oh 45,000.00 846.00

P e k e r j a 0.1250 oh 35,000.00 4,375.00

Mandor 0.0062 oh 45,000.00 279.00

SNI-L.6.47e Pas. Lantai Keramik Uk ( 30 x 30 ) cm ( Klas A ) M2 127,205.00

Ubin Keramik 30 x 30 cm ( klas A ) 11.8700 bh 4,000.00 47,480.00

Portland Cement 10.0000 kg 1,500.00 15,000.00

Pasir Pasang 0.0450 m3 110,000.00 4,950.00

Semen Warna 1.5000 kg 11,500.00 17,250.00

P e k e r j a 0.7000 oh 35,000.00 24,500.00

Tukang Batu 0.3500 oh 42,500.00 14,875.00

Kepala Tukang 0.0350 oh 45,000.00 1,575.00

M a n d o r 0.0350 oh 45,000.00 1,575.00

DP Pasang uis Beton U 20 M' 32,523.75

Urugan pasir 0.025 m3 100,950.00 2,523.75

Pas. Saluran U-20 1.000 bh 30,000.00 30,000.00

Purwokerto, 2013

Penawar,

CV RAHAYU JAYA SANTOSA

EDY WIWOHO

Direktur

Page 7: Rab Selasar Radiologi

DAFTAR HARGA SATUAN BAHAN DAN UPAH

K E G I A T A N : REHABILITASI GEDUNG RS MARGONO SOEKARDJOP E K E R J A A N : PENAMBAHAN SELASAR DEPAN RUANG RADIOLOGIL O K A S I : RSMSB I A Y A : Rp 144,143,000.00 TAHUN ANGGARAN : 2 0 1 3

NO URAIAN UPAH DAN BAHAN HRG SATUAN ( Rp ) SATUAN

1 2 4 5

UPAH

1 Tukang Batu 42,500.00 Oh2 Tukang Kayu 42,500.00 Oh3 Tukang Besi 42,500.00 Oh4 Tukang Cat 42,500.00 Oh5 Kepala Tukang 45,000.00 Oh6 Pekerja / Pekerja bongkar siram 35,000.00 Oh7 Mandor 45,000.00 Oh

BAHAN

1 Pasir Beton 120,000.00 m32 Pasir Pasang 110,000.00 m3 3 Pasir urug 75,000.00 m3 4 Tanah Urug 75,000.00 m3 5 Sirtu 95,000.00 m3 6 Kapur Pasang 296,600.00 m3 7 Batu Belah 15/20 cm 140,000.00 m3 8 Tali Ijuk 14,000.00 kg 9 Koral Beton ( Batu Pecah 2/3 cm ) 220,000.00 m3

10 Batu Merah ( 5x11x22 cm ) 600.00 bh 11 Portland Cement ( PC ) 1,500.00 kg 12 Semen warna 11,500.00 kg 13 Besi Beton Polos 11,500.00 kg14 Kawat Beton ( Bindrat ) 17,500.00 kg15 Balok Kayu Tahun 1,600,000.00 m316 Kayu Tahun , Usuk 5/7 / Papan 3/20 1,600,000.00 m3 17 Usuk Kayu Tahun 5/7 cm Panjang = 3 m 15,000.00 btg 18 Usuk Kruing 5/7 5,700,000.00 m3 19 Reng Kruing 2/3 cm 4,900,000.00 m3 20 Kayu Kruing Balok 6,100,000.00 m321 Papan Kruing 6,400,000.00 m322 Kayu Kruing 5,500,000.00 m323 Kayu Meranti 5/7 cm 3,000,000.00 m324 Papan meranti 3,500,000.00 m325 kayu jati 12,000,000.00 m326 Kayu meranti balok 3,000,000.00 m327 Papan Bangkir 9,000,000.00 m328 Kayu bangkir balok 9,500,000.00 m329 Paku Biasa ( 2'" - 5 " ) 14,000.00 kg 30 Paku Lis, Plafond 14,000.00 kg 31 Paku eternit 17,000.00 kg 32 Paku Kait 29,000.00 kg33 Paku Seng ( 1/2" - 1" ) 31,000.00 kg 34 Paku 10 cm 14,000.00 kg

Page 8: Rab Selasar Radiologi

35 Lem kayu 9,000.00 kg 36 Besi Strip tebal 5 mm 8,000.00 kg 37 Paku 12 cm 14,000.00 kg 38 Bambu diameter 6 - 8 / 6 m' 14,000.00 btg 39 Paku Skrup 3,5" 14,000.00 kg 40 Paku Skrup 14,000.00 kg 41 Eternit ( 1.00 x 1.00 ) m 14,000.00 lbr 42 GRC (1,00x1,00)m 15,500.00 lbr 43 Lis Kayu 3,650.00 m' 44 Lis kayu profil 5,500.00 m' 45 Kaca Bening 3 mm 50,000.00 m246 Kaca Bening 5 mm 70,000.00 m247 Multiplek 9 mm 35,000.00 m248 Triplek 3mm 45,000.00 m249 Profil Allumunium sek. ALEXINDO 3' coklat 1 mm' 50,000.00 m'50 Sekrup fixer 1,500.00 bh51 Sealent 10,000.00 bh52 Genteng Morando 2,500.00 bh53 Genteng nok margase 4,000.00 bh54 Seng plat 25,000.00 m255 Pipa PCV 1/2: 3,000.00 m'56 Pipa PVC 4" 30,000.00 m'57 Pipa PVC 1 1/2" 11,000.00 m'58 PVC 3" 22,500.00 m'59 Kran air 1/2" 17,500.00 bh60 Seal tape 1,500.00 bh61 Wastafel 350,000.00 bh62 Paku 1-21/2cm 12,500.00 kg63 Bak cuci piring 240,000.00 bh64 Water drain + asesoris 25,000.00 bh65 Bak Fiber glas 175,000.00 bh66 Floor drain 15,000.00 bh67 Kloset jongkok 150,000.00 bh68 Paving blok natural tb 6cm 42,000.00 m269 Kalsiboar 16,000.00 m270 Buis Beton U 30cm 30,000.00 bh71 Genteng Plentong 1,500.00 bh72 Nok Genteng Plentong 4,000.00 bh73 Seng Plat 3 " x 6 " BJLS 20 25,000.00 m2 74 Cat Dasar ( Sek.Avian ) 42,500.00 kg 75 Cat Penutup ( Sek.Avian ) 42,500.00 kg 76 Cat Tembok ( Sek.Decolithe ) 14,000.00 kg 77 Cat Dasar ( Sek.Decolithe ) 14,000.00 kg 78 Cat Penutup 2 kali ( Sek.Decolithe ) 14,000.00 kg 79 Cat Tembok ( Sek.Maxilite ) 10,900.00 kg 80 Cat Dasar (Sek. Mollek) 11,000.00 kg 81 Cat Tembok (sek. Catylac) 19,000.00 kg 82 Cat Dasar (sek. Catylac) 19,000.00 kg 83 Cat Meni 23,000.00 kg 84 Soda api 20,000.00 kg 85 Meni Besi 40,000.00 kg 86 Plamir Tembok 7,000.00 kg 87 Plamir kayu 18,000.00 kg

cairan couting 21,000.00 ltr 88 Amplas 3,000.00 lbr 89 Kunci Selot 75,000.00 bh90 Kait angin model lipat 10,000.00 bh91 Engsel jendela kupu-kupu 10,000.00 bh92 Engsel Pintu 12,500.00 bh93 Grendel Pintu 10,000.00 bh94 Grendel jendela 10,000.00 bh95 Tarikan jendela 7,500.00 bh96 Besi Doog, Angkur 20,000.00 kg97 Ubin Keramik 30 x 30 cm ( klas A ) 4,000.00 bh98 Ubin Keramik 40x40 cm (Klas A) 9,000.00 bh99 Ubin keramik 20x20 cm (Klas A) 2,000.00 bh100 Keramik dinding 20x25 2,000.00 bh101 batu alam motif 150,000.00 m2

Page 9: Rab Selasar Radiologi

PERALATAN

1 Concrete mixer 27,493.88 jam2 Pompa Air 17,857.14 jam3 Stamper 21,428.57 jam

Purwokerto, 2013PenawarCV RAHAYU JAYA SANTOSA

EDY WIWOHODirektur