REKAPITULASI HARGA PENAWARAN PEKERJAAN PERLUASAN WORKSHOP BELAWAN INTERNATIONAL CONTAINER TERMINAL NO. URAIAN PEKERJAAN Jumlah Harga ( Rp) Upah Bahan Upah + Bahan 1 2 3 4 5 I PEKERJAAN PERSIAPAN DAN PENDAHULUAN 24,550,000.00 24,550,000.00 II PEKERJAAN TANAH DAN PONDASI 112,149,854.22 164,974,501.20 277,124,355.42 III PEKERJAAN TIANG DAN BALOK 76,836,417.22 179,505,979.94 256,342,397.16 IV PEKERJAAN ATAP 40,647,746.94 132,864,280.43 173,512,027.37 V PEKERJAAN DRAINASE 30,361,464.16 47,214,253.64 77,575,717.80 VI PEKERJAAN LAIN - LAIN 9,048,000.00 9,048,000.00 Jumlah : 818,152,497.751 PPN 10 % : 81,815,249.775 Total : 899,967,747.526 Dibulatkan : 899,967,000.000 Terbilang : delapan ratus sembilan puluh sembilan juta sembilan ratus enam puluh tujuh ribu Belawan, Ok Disetujui oleh, Dibuat o MANAJER TEKNIK ASISTEN MANAJE SADARUDDIN INGGU SAR Ditetapkan oleh, GENERAL MANAGER SYAMSUL BAHRI KAUTJIL

Upload: jnababan78

Post on 10-Aug-2015

1.025 views

Category:

Documents


260 download

TRANSCRIPT

Page 1: RAB perluasan workshop br.xls

REKAPITULASI HARGA PENAWARAN

PEKERJAAN PERLUASAN WORKSHOP

BELAWAN INTERNATIONAL CONTAINER TERMINAL

URAIAN PEKERJAANJumlah Harga ( Rp)

KeteranganUpah Bahan Upah + Bahan

1 2 3 4 5 6

I PEKERJAAN PERSIAPAN DAN PENDAH 24,550,000.00 24,550,000.00

II PEKERJAAN TANAH DAN PONDASI ### ### 277,124,355.42

III PEKERJAAN TIANG DAN BALOK 76,836,417.22 ### 256,342,397.16

IV PEKERJAAN ATAP 40,647,746.94 ### 173,512,027.37

V PEKERJAAN DRAINASE 30,361,464.16 47,214,253.64 77,575,717.80

VI PEKERJAAN LAIN - LAIN 9,048,000.00 9,048,000.00

Jumlah : 818,152,497.751

PPN 10 % : 81,815,249.775

Total : 899,967,747.526

Dibulatkan : ###

Terbilang : delapan ratus sembilan puluh sembilan juta sembilan ratus enam puluh tujuh ribu rupiah

Belawan, Oktober 2010

Disetujui oleh, Dibuat oleh,

MANAJER TEKNIK ASISTEN MANAJER FASILITAS

SADARUDDIN INGGU SARNAINI

Ditetapkan oleh,

GENERAL MANAGER

SYAMSUL BAHRI KAUTJIL

NO.

Page 2: RAB perluasan workshop br.xls

RINCIAN HARGA PENAWARAN PEKERJAAN PERLUASAN WORKSHOP

BELAWAN INTERNATIONAL CONTAINER TERMINAL

NO. URAIAN PEKERJAAN Satuan Volume Harga Satuan ( Rp) Jumlah Harga ( Rp)

Upah Bahan Upah + Bahan Upah Bahan

1 2 3 4 5 6 7 8 9

I PEKERJAAN PERSIAPAN DAN PENDAHULUAN1 Survey lokasi ls 1.00 300,000.00 300,000.00 300,000.002 Mobilisasi dan Demobilisasi Alat ls 1.00 5,000,000.00 5,000,000.00 5,000,000.003 Pekerjaan Bowplank ls 1.00 2,000,000.00 2,000,000.00 2,000,000.004 Gudang bahan dan peralatan ls 1.00 6,000,000.00 6,000,000.00 6,000,000.005 Pekerjaan Perancah ls 1.00 11,250,000.00 11,250,000.00 11,250,000.00

Jumlah I ### 24,550,000.00 24,550,000.00

II PEKERJAAN TANAH DAN PONDASI1 Galian tanah keras m³ 15.78 54,664.80 54,664.80 862,776.722 Urugan kembali galian m³ 14.62 13,666.20 13,666.20 199,863.263 Urugan pasir bawah pondasi m³ 0.77 16,406.00 84,000.00 100,406.00 12,599.81 64,512.004 lantai kerja cor 1 : 3 : 5 m³ 0.39 378,675.00 498,596.00 877,271.00 147,834.72 194,651.885

m¹ 216.00 220,000.00 220,000.00 47,520,000.00

6 Mobilisasi dan demobilisasi untuk pemancangan ls 1.00 12,000,000.00 12,000,000.00 12,000,000.007 Pengadaan crane bantu ls 1.00 13,000,000.00 13,000,000.00 13,000,000.008 Pile cap beton bertulang (195,5 kg) K 300 + sumbu m³ 5.79 2,589,339.75 3,205,228.75 5,794,568.50 14,989,169.94 18,554,428.199 Pekerjaan sloof 30 x 40 beton bertulang (93,64 kg) K 300 m³ 16.32 2,317,496.36 2,001,778.10 4,319,274.46 37,821,540.60 32,669,018.59

10 Bongkar pas. Coneblok 192.00 15,228.00 15,228.00 2,923,776.00 0.0011 Base Coarse A m³ 75.10 23,542.00 210,240.00 233,782.00 1,767,910.03 15,788,183.0412 Urugan pasir bawah Lantai m³ 19.44 16,406.00 84,000.00 100,406.00 318,932.64 1,632,960.0013 Pasang Kembali Pas. Coneblok 192.00 10,700.00 10,700.00 2,054,400.00 0.0014 Pekerjaan Pelat Lantai (60,3 Kg) Beton Bertulang tebal 25 m³ 30.00 868,368.35 1,618,358.25 2,486,726.60 26,051,050.50 48,550,747.50

Jumlah II ### 7,922,201.10 39,226,693.56 ### ###

III PEKERJAAN TIANG DAN BALOK1 Penyambungan balok untuk bangunan baru kg 288.45 7,482.00 19,140.00 26,622.00 2,158,182.90 5,520,933.00

2 Pekerjaan pasangan bata m² 133.16 55,505.20 74,830.00 130,335.20 7,391,119.61 9,964,426.413 Pekerjaan lobang angin m² 35.41 9,025.00 67,500.00 76,525.00 319,587.89 2,390,269.504 Pekerjaan plesteran m² 266.32 39,910.00 11,441.00 51,351.00 10,628,899.05 3,046,986.575 Pekerjaan pengecatan ( 2 x cat) m² 266.32 9,552.25 18,445.00 27,997.25 2,543,971.46 4,912,303.766 Pekerjaan tiang Profil WF 350 x 175 (49,6 kg/m)+ sambun kg 3,958.08 7,482.00 19,140.00 26,622.00 29,614,354.56 75,757,651.207 Pekerjaan balok Profil WF 350 x 175 (49,6 kg/m)+ sambun kg 2,708.16 7,482.00 19,140.00 26,622.00 20,262,453.12 51,834,182.408 Pekerjaan tiang beton 30 x 60 kg 13.67 170,125.00 1,132,440.00 1,302,565.00 2,326,222.63 15,484,541.109 Pekerjaan balok beton 30 x 60 kg 9.36 170,125.00 1,132,440.00 1,302,565.00 1,591,626.01 10,594,686.01

Jumlah III 476,688.45 2,494,516.00 2,971,204.45 76,836,417.22 ###

Pengadaan material,pemancangan dan penyambungan V pile 28.28.28

Page 3: RAB perluasan workshop br.xls

NO. URAIAN PEKERJAAN Satuan Volume Harga Satuan ( Rp) Jumlah Harga ( Rp)

Upah Bahan Upah + Bahan Upah Bahan1 2 3 4 5 6 7 8 9

IV PEKERJAAN ATAP1 Pekerjan kuda - kuda profil WF 300 x 150 Kg 1,572.23 7,482.00 19,140.00 26,622.00 11,763,409.90 30,092,443.922 Gording kanal profil C 150 x 65 x 20 Kg 1,056.00 7,482.00 19,140.00 26,622.00 7,900,992.00 20,211,840.003 Ikatan angin besi bulat Ø 14 mm + klem Kg 181.40 8,955.40 10,120.00 19,075.40 1,624,538.22 1,835,800.384 Trackstang besi bulat Ø 14 mm + klem Kg 96.80 8,955.40 10,120.00 19,075.40 866,882.72 979,616.005 Besi siku 110.110.10 untuk dudukan gording Kg 72.48 6,555.63 14,800.00 21,355.63 475,152.24 1,072,704.006 Pelat besi 3 mm untuk pengait atap Kg 31.09 8,692.40 14,900.00 23,592.40 270,211.95 463,181.40

7 Rangka listplank L 45.45.5 Kg 332.76 6,555.63 14,800.00 21,355.63 2,181,458.83 4,924,862.80

8 Atap zinkalum warna standart 0.5 mm m² 428.40 21,338.00 138,000.00 159,338.00 9,141,199.20 59,119,200.00

9 Listplank zinkalum 0.5 mm m² 24.12 21,338.00 138,000.00 159,338.00 514,672.56 3,328,560.00

10 Rabung Rabung seng BJLS 35 K m¹ 24.12 3,512.25 23,645.00 27,157.25 84,715.47 570,317.40

11 Pekerjaan plafond m² 160.00 27,890.00 49,568.12 77,458.12 4,462,400.00 7,930,899.20

12 Pelat buhul tebal 6 mm Kg 156.70 8,692.40 14,900.00 23,592.40 1,362,113.86 2,334,855.33

Jumlah IV 137,449.12 467,133.12 604,582.24 40,647,746.94 ###

V PEKERJAAN DRAINASE1 Galian tanah keras m³ 31.65 54,664.80 54,664.80 1,730,272.122 Timbunan kembali m³ 13.74 13,666.20 13,666.20 187,718.923 Beton bertulang K 300 m³ 16.32 1,243,810.68 1,940,038.10 3,183,848.78 20,294,512.58 31,654,437.654 lantai kerja pasir urug m³ 1.60 16,406.00 84,000.00 100,406.00 26,249.60 134,400.005 Penutup parit pelat 3 mm kg 616.52 8,692.40 14,900.00 23,592.40 5,359,039.84 9,186,150.386 Besi siku 45.45.5 kg 421.57 6,555.63 14,800.00 21,355.63 2,763,671.10 6,239,265.60

Jumlah V 1,343,795.71 2,053,738.10 3,397,533.81 30,361,464.16 47,214,253.64

VI PEKERJAAN LAIN - LAIN1 Pembersihan akhir ls 1.00 3,000,000.00 3,000,000.00 3,000,000.002 Tes kuat tekan beton ls 1.00 3,500,000.00 3,500,000.00 3,500,000.003 Dokumentasi dan laporan ls 1.00 2,548,000.00 2,548,000.00 2,548,000.00

Jumlah VI 9,048,000.00 9,048,000.00 9,048,000.00

Page 4: RAB perluasan workshop br.xls
Page 5: RAB perluasan workshop br.xls

RINCIAN HARGA PENAWARAN PEKERJAAN PERLUASAN WORKSHOP

BELAWAN INTERNATIONAL CONTAINER TERMINAL

Jumlah Harga ( Rp)

Upah + Bahan

10

300,000.005,000,000.002,000,000.006,000,000.00

11,250,000.000.00

24,550,000.00

862,776.72199,863.2677,111.81

342,486.60

47,520,000.00

12,000,000.0013,000,000.0033,543,598.1370,490,559.192,923,776.00

17,556,093.071,951,892.642,054,400.00

74,601,798.00

277,124,355.42

7,679,115.9017,355,546.022,709,857.39

13,675,885.627,456,275.22

105,372,005.7672,096,635.5217,810,763.7312,186,312.02

256,342,397.16

Page 6: RAB perluasan workshop br.xls

Jumlah Harga ( Rp)

Upah + Bahan 10

41,855,853.8228,112,832.003,460,338.601,846,498.721,547,856.24

733,393.35

7,106,321.63

68,260,399.20

3,843,232.56

655,032.87

12,393,299.20

3,696,969.19

173,512,027.37

1,730,272.12187,718.92

51,948,950.23160,649.60

14,545,190.229,002,936.70

77,575,717.80

3,000,000.003,500,000.002,548,000.00

9,048,000.00

Page 7: RAB perluasan workshop br.xls
Page 8: RAB perluasan workshop br.xls

DAFTAR HARGA UPAH, BAHAN, DAN PERALATAN

PEKERJAAN PERLUASAN WORKSHOP

BELAWAN INTERNATIONAL CONTAINER TERMINAL

DAFTAR HARGA UPAH

No. Uraian Satuan

1 Pekerja Org/Hari 52,500.00

2 Mandor Org/Hari 65,600.00

3 Tukang batu Org/Hari 78,800.00

4 Tukang kayu Org/Hari 78,800.00

5 Tukang besi Org/Hari 78,800.00

6 Kepala Tukang Org/Hari 91,900.00

DAFTAR HARGA BAHAN

No.Uraian Satuan

1 Semen PC @ 40 Kg Zak 48,000.00

2 Semen Putih Zak 79,800.00

3 Pasir Pasang 85,000.00

4 Pasir Urug 70,000.00

5 Kerikil 156,000.00

6 Ready mix K 300 635,000.00

7 Besi Profil WF kg 17,400.00

8 Besi pelat polos kg 14,900.00

9 Baut kg 14,900.00

10 Baut atap bh 2,000.00

11 Triplek 4mm 47,000.00

12 Atap zinkalump 2,4 t 0.5 120,000.00

13 Paku Kg 10,906.00

14 Kayu sembarang 4,462,500.00

15 Besi Beton Kg 9,375.00

16 Kawat Besi Kg 14,500.00

17 besi siku kg 14,800.00

18 V pile 32.32.32 bottom file 233,000.00

19 V pile 32.32.33 upper vile 263,000.00

20 Tali Manila 15,000.00

21 Cat tembok Kg 41,000.00

22 minyak cat ltr 18,000.00

23 Kawat las Kg 15,000.00

24 Cerucuk Kayu Laut 4", l= 4m btg 25,000.00

25 Rabung atap seng 39,400.00

26 Paku seng bh 500.00

27 Batu bata bh 650.00

28 Lobang angin bh 2,500.00

29 Base Coarse A 175,200.00

30 Biaya gilas ls 26,760,000.00

31m¹ 220,000.00

Belawan, Oktober 2010

Dibuat oleh,

ASISTEN MANAJER FASILITAS

INGGU SARNAINI

Harga satuan Bahan (Rp)

Harga satuan Upah (Rp)

Pengadaan material, pemancangan dan penyambungan v pile 28.28.28

Page 9: RAB perluasan workshop br.xls
Page 10: RAB perluasan workshop br.xls

DAFTAR ANALISA HARGA SATUAN PEKERJAAN

No. Anl Koef Uraian H. Satuan Upah Bahan Peralatan Total

1 A 2 Untuk tanah keras :

1.000 pekerja 52,500.00 52,500.00

0.033 mandor 65,600.00 2,164.80

54,664.80 0.00 0.00 54,664.80

2 1/4 A2 1 m3 Timbunan Kemba

0.250 54,664.8000 13,666.20 0.00 0.00 13,666.20

3 A 18 1 M3 pasir timbun dibawah lantai :

1.200 M3 Pasir T 70,000.00 84,000.00

0.300 Pekerja 52,500.00 15,750.00

0.010 Mandor 65,600.00 656.00

16,406.00 84,000.00 0.00 100,406.00

4 G 43 a 1 M3 beton camp. 1 : 3 : 5

1.000 m3 kerikil 156,000.00 156,000.00

6.252 zak semen 48,000.00 300,096.00

0.500 m3 pasir bet 85,000.00 42,500.00

6.000 pekerja 52,500.00 315,000.00

0.300 mandor 65,600.00 19,680.00

0.500 tukang batu 78,800.00 39,400.00

0.050 kepala tuka 91,900.00 4,595.00

378,675.00 498,596.00 0.00 877,271.00

5 1 M3 beton K - 300

1.200 ready mix K 635,000.00 762,000.00

0.00 762,000.00 0.00 762,000.00

6 I. 2 100 Kg pembesian untuk beton bertulang :

110.000 kg besi 9,375.00 1,031,250.00

2.000 kg kawat be 14,500.00 29,000.00

6.750 tukang besi 78,800.00 531,900.00

2.250 kepala tuka 91,900.00 206,775.00

6.750 pekerja 52,500.00 354,375.00

1,093,050.00 1,060,250.00 0.00 2,153,300.00

Untuk pekerjaan memasang dan menempatkan tiap 100 kg besi diperlukan :

0.500 tukang besi 78,800.00 39,400.00

2.000 pekerja 52,500.00 105,000.00

144,400.00 0.00 0.00 144,400.00

Biaya yang diperlukan untuk pek. 100 k 1,237,450.00 1,060,250.00 0.00 2,297,700.00

Biaya yang diperlukan untuk pek. 1 kg 12,374.50 10,602.50 0.00 22,977.00

Untuk file cap 195.5 2,419,214.75 2,072,788.75 0.00 4,492,003.50

Untuk Sloof 93.64 1,158,748.18 992,818.10 0.00 2,151,566.28

Untuk Lantai 63.3 783,305.85 671,138.25 0.00 1,454,444.10

Untuk Drainase 93.64 1,158,748.18 992,818.10 0.00 2,151,566.28

Page 11: RAB perluasan workshop br.xls

No. Anl Koef Uraian H. Satuan Upah Bahan Peralatan Total

7 F 8 10 M2 cetakan untuk 1 m3 beton :

5.000 Tukang kay 45,000.00 225,000.00

0.500 Kepala Tuk 60,500.00 30,250.00

0.400 M3 kayu se 1,735,200.00 694,080.00

2.000 Pekerja 40,000.00 80,000.00

0.100 Mandor 50,000.00 5,000.00

4.000 Kg paku 10,200.00 40,800.00

1.000 Ls Air bersi 6,000.00 6,000.00

340,250.00 740,880.00 0.00 1,081,130.00

untuk file cap ( 2 x p 0.5 170,125.00 370,440.00 0.00 540,565.00

untuk sloof ( 3 x pema 0.33 113,416.67 246,960.00 0.00 360,376.67

untuk kolom ( 2 x pe 0.50 170,125.00 370,440.00 0.00 540,565.00

untuklantai (4 x pemak 0.25 85,062.50 185,220.00 0.00 270,282.50

untuk drainase (4x pe 0.25 85,062.50 185,220.00 0.00 270,282.50

8 Supply 1 M3 beton K - 300 Untuk File Cap

1 M3 beton K - 300 762,000.00 0.00

Pembesian beton bertulang (195,5 kg) 2,419,214.75 2,072,788.75 0.00

Cetakan utk. 1 M3 beton & siram 170,125.00 370,440.00 0.00

total 2,589,339.75 3,205,228.75 0.00 5,794,568.50

9 Supply 1 M3 beton K - 300 Untuk Sloof

1 M3 beton K - 300 762,000.00 0.00

Pembesian beton bertulang (93.64 kg) 1,158,748.18 992,818.10 0.00

Cetakan utk. 1 M3 beton & siram 1,158,748.18 246,960.00 0.00

total 2,317,496.36 2,001,778.10 0.00 4,319,274.46

10 Supply 1 M3 beton K - 300 Untuk Lantai

1 M3 beton K - 300 762,000.00 0.00

Pembesian beton bertulang (60.3 kg) 783,305.85 671,138.25 0.00

Cetakan utk. 1 M3 beton & siram 85,062.50 185,220.00 0.00

total 868,368.35 1,618,358.25 0.00 2,486,726.60

11 Supply 1 M3 beton K - 300 Untuk drainase

1 M3 beton K - 300 762,000.00 0.00

Pembesian beton bertulang (93.64 kg) 1,158,748.18 992,818.10 0.00

Cetakan utk. 1 M3 beton & siram 85,062.50 185,220.00 0.00

total 1,243,810.68 1,940,038.10 0.00 3,183,848.78

12 Supply 1 M3 beton K - 300 Kolom dan Balok

1 M3 beton K - 300 762,000.00 0.00

Cetakan utk. 1 M3 beton & siram 170,125.00 370,440.00 0.00

total 170,125.00 1,132,440.00 0.00 1,302,565.00

13 1 m¹ Pengadaan material,pemancangan dan penyambungan V pile 28.28.28

1.000220,000.000 220,000.00

0.00 220,000.00 0.00 220,000.00

14 G 55b. 1 M2 membongkar conblok

0.060 tukang batu 78,800.00 4,728.00

0.200 pekerja 52,500.00 10,500.00

15,228.00 0.00 0.00 15,228.00

11. 1 M3 timbunan base coarse kelas A :

1.200 M3 base coa 175,200.00 210,240.00

0.300 Pekerja 52,500.00 15,750.00

0.010 Mandor 65,600.00 656.00

0.000 Biaya gilas 26,760,000.00 7,136.00

23,542.00 210,240.00 0.00 233,782.00

m¹ material, pancang, penyambu

Page 12: RAB perluasan workshop br.xls

No. Anl Koef Uraian H. Satuan Upah Bahan Peralatan Total

12 G 55b. 1 M2 memasang kembali coneblok bekas bongkaran

0.060 tukang batu 45,000.00 2,700.00

0.200 pekerja 40,000.00 8,000.00

10,700.00 0.00 0.00 10,700.00

13 100 Kg Pekerjaan Besi profil WF/gording CNP

110.000 kg besi baja 17,400.000 1,914,000.00

1.500 tukang 78,800.000 118,200.00

2.000 kepala tuka 91,900.000 183,800.00

6.000 pekerja 52,500.000 315,000.00

2.000 mandor 65,600.000 131,200.00

748,200.00 1,914,000.00 0.00 2,662,200.00

Untuk 1 Kg 7,482.00 19,140.00 0.00 26,622.00

14 1 Kg Pekerjaan Track stang dan ikatan angin

1.000 kg besi baja 9,375.000 9,375.00

0.050 kg baut 14,900.000 745.00

1.000 ls alat bantu 1,000.000 1,000.00

0.080 tukang 78,800.000 6,304.00

0.006 kepala tuka 91,900.000 551.40

0.040 pekerja 52,500.000 2,100.00 1,000.00

8,955.40 10,120.00 2,000.00 21,075.40

15 1 Kg Pekerjaan besi siku

1.000 kg besi siku 14,800.000 14,800.00

0.067 tukang 78,800.000 5,253.99

0.001 mandor 65,600.000 77.08

0.023 pekerja 52,500.000 1,224.56 0.00

6,555.63 14,800.00 0.00 21,355.63

16 1 Kg Pekerjaan besi Pelat

1.000 kg besi siku 14,900.000 14,900.00

0.080 tukang 78,800.000 6,304.00

0.014 mandor 65,600.000 918.40

0.028 pekerja 52,500.000 1,470.00 0.00

8,692.40 14,900.00 0.00 23,592.40

17 G 28a.1 M² pemasangan tembok bata 1:2

0.323 Pekerja 52,500.00 16,957.50

0.250 Tukang batu 78,800.00 19,700.00

0.123 Kepala tuka 91,900.00 11,303.70

0.115 Mandor 65,600.00 7,544.00

0.180 Pasir pasan 85,000.00 15,300.00

0.360 Semen portl 48,000.00 17,280.00

65.000 Batu bata j 650.00 42,250.00

55,505.20 74,830.00 0.00 130,335.20

18 1 m² Pekerjaan lobang angin

27.000 bh lobang an 2,500.000 67,500.00

0.038 tukang 78,800.000 2,955.00

0.013 mandor 65,600.000 820.00

0.100 pekerja 52,500.000 5,250.00 0.00

9,025.00 67,500.00 0.00 76,525.00

Page 13: RAB perluasan workshop br.xls

No. Anl Koef Uraian H. Satuan Upah Bahan Peralatan Total

19 1 m2 atap zinkalum

1.050 m² atap zin 120,000.00 126,000.00

6.000 bh baut 2,000.00 12,000.00

0.200 tukang besi 78,800.00 15,760.00

0.100 pekerja 52,500.00 5,250.00

0.005 mandor 65,600.00 328.00

21,338.00 138,000.00 0.00 159,338.00

20 H 10 10 M' rabung atap seng:

6.000 lbr. rabung 39,400.00 236,400.00

0.100 Kg Paku sen 500.00 50.00

0.250 tukang besi 78,800.00 19,700.00

0.025 kepala tuka 91,900.00 2,297.50

0.250 pekerja 52,500.00 13,125.00

35,122.50 236,450.00 0.00 271,572.50

1 M' 3,512.25 23,645.00 0.00 27,157.25

21 1 m² lisplank zingnalum

1.050 m² atap zin 120,000.00 126,000.00

6.000 bh baut 2,000.00 12,000.00

0.200 tukang besi 78,800.00 15,760.00

0.100 pekerja 52,500.00 5,250.00

0.005 mandor 65,600.00 328.00

21,338.00 138,000.00 0.00 159,338.00

22 1 m² plafond triplek 4 mm

1.050 m² triplek 4 47,000.00 49,350.00

0.020 kg paku bias 10,906.00 218.12

0.500 pekerja 52,500.00 26,250.00

0.025 mandor 65,600.00 1,640.00

27,890.00 49,568.12 0.00 77,458.12

23 K 9 10 m2 (mengecat dasar 1x dan mengecat warna 2x)

4.250 kg cat 41,000.00 174,250.00

0.567 ltr minyak c 18,000.00 10,200.00

0.750 tukang cat 78,800.00 59,100.00

0.075 kep. tukang 91,900.00 6,892.50

0.500 pekerja 52,500.00 26,250.00

0.050 mandor 65,600.00 3,280.00

95,522.50 184,450.00 0.00 279,972.50

1 m² 9,552.25 18,445.00 0.00 27,997.25

24 G 50i. 1 M2 plesteran dengan perekat PC tbl 15 mm camp. 1:3

0.204 zak semen 48,000.00 9,792.00

0.019 M3 Pasir 85,000.00 1,649.00

0.200 Tukang bat 78,800.00 15,760.00

0.020 Kepala tuk 91,900.00 1,838.00

0.400 Pekerja 52,500.00 21,000.00

0.020 Mandor 65,600.00 1,312.00

39,910.00 11,441.00 0.00 51,351.00

Belawan, Oktober 2010

Dibuat oleh,

ASISTEN MANAJER FASILITAS

INGGU SARNAINI

Page 14: RAB perluasan workshop br.xls

No. Uraian Satuan Koefisien

161 m¹ Pengadaan material,pemancangan dan penyambungan V pile 28.28.28a. Upah , bahan dan peralatanm¹ 1.000 220,000.00 220,000.00

220,000.00

Jumlah 220,000.000ver head 0.1 22,000.00

###

1 m³ Base Coarse Aa. UpahPekerja Jam 0.1071 6,562.50 702.84

Mandor Jam 0.0178 8,200.00 145.96848.80

b. BahanBase coar m³ 1.200 175,200.00 210,240.00210,240.00

c. PeralatanDump Tru Jam 0.2463 #REF! #REF!Motor Gra Jam 0.0044 #REF! #REF!Vibratory Jam 0.0067 #REF! #REF!Air Pema Ls 1.0000 3,000.00 3,000.00Alat bant Ls 1.0000 1,000.00 1,000.00

#REF!

Jumlah #REF!0ver head 0.1 #REF!Harga satuan #REF!

171 m¹ Pekerjaan cerocok kayu lauta. UpahPekerja jam 0.063 6,562.50 410.16

410.16

b. BahanKayu Laut btg 1.000 25,000.00 25,000.0025,000.00

c. Peralatanexcavator jam 0.031 #REF! #REF!#REF!

Jumlah #REF!0ver head 0.1 #REF!Harga satuan 1 Kg #REF!

181m² memasang Kembali Pas. Conebloka. upahPekerja jam 1.400 6,562.50 9,187.50

Mandor jam 0.093 8,200.00 765.069,952.56

a. bahanPasir pas m³ 0.055 85,000.00 4,675.004,675.00

c. alat Vibratory jam 0.0040 #REF! #REF!Alat bant ls 1.0000 500.00 500.00

#REF!

Jumlah #REF!0ver head 0.1 #REF!Harga satuan #REF!

Harga Satuan (Rp)

Jlh. Harga (Rp)

Total Harga (Rp)

Page 15: RAB perluasan workshop br.xls

No. Uraian Satuan Koefisien

19100 Kg Pekerjaan Besi profil WF/gording CNPa. UpahPekerja jam 24 6,562.50 157,500.00

Tukang jam 24 9,850.00 236,400.00 Mandor jam 8 8,200.00 65,600.00

459,500.00

Kg 110 17,400.00 1,914,000.00

ls 1 30,000

30,000.00

1,944,000.00

Jumlah 2,403,500.00

Untuk 1 Kg 0.01 x 2,403,500.00 24,035.00

Jumlah 24,035.000ver head 0.1 2,403.50Harga satuan 26,438.50

201 Kg Pekerjaan Track stang dan ikatan angina. UpahPekerja jam 0.020 6,562.50 131.25

Tukang jam 0.040 9,850.00 394.00Mandor jam 0.003 8,200.00 24.60

549.85

b. BahanBesi beto Kg 1.050 9,375.00 9,843.75

Bahan ba ls 0.500 10,000.00 5,000.0014,843.75

Jumlah 15,393.600ver head 0.1 1,539.36Harga satuan 1 Kg 16,932.96

211 kg memasang besi siku

a. UpahPekerja jam 0.0933 6,562.50 612.50

Tukang jam 0.2667 9,850.00 2,626.67

Mandor jam 0.0047 8,200.00 38.27

3,277.43

kg 1.0000 14,800.00 14,800.00

14,800.00

Jumlah 18,077.43

0ver head 0.1 1,807.74

Harga satuan 19,885.18

Harga Satuan (Rp)

Jlh. Harga (Rp)

Total Harga (Rp)

b. Baha

n

Profil WFKawat Las & peralatan

b. Baha

n

besi siku

Page 16: RAB perluasan workshop br.xls

No. Uraian Satuan Koefisien

221 kg memasang pelat besi polos

a. UpahPekerja jam 0.0560 6,562.50 367.50

Tukang jam 0.1600 9,850.00 1,576.00

Mandor jam 0.0028 8,200.00 22.96

1,966.46

kg 1.0000 14,900.00 14,900.00

baut ls 1.0000 2,000.00 2,000.00

16,900.00

Jumlah 18,866.46

0ver head 0.1 1,886.65

Harga satuan 20,753.11

23 1 m2 Pekerjaan Atap Zinknalum

a. UpahPekerja jam 0.8000 6,562.50 5,250.00

Tukang jam 1.6000 9,850.00 15,760.00

Mandor jam 0.0400 8,200.00 328.00

21,338.00

b. Bahanbaut bh 6.0000 2,000.00 12,000.00

Atap Zink m² 1.0500 120,000.00 126,000.00

138,000.00

C. Peralatan

Alat bant ls 1.0000 500.00 500.00

500.00

Jumlah 159,838.00

0ver head 0.1 15,983.80

Harga satuan ###

241 m¹ Pasang Rabung Atap seng BJLS 35

a. UpahPekerja jam 0.2000 6,562.50 1,312.50

Tukang jam 0.1600 9,850.00 1,576.00

Mandor jam 0.0160 8,200.00 131.20

3,019.70

m¹ 1.1000 39,400.00 43,340.00

Paku sen bh 4.0000 500.00 2,000.00

45,340.00

Jumlah 48,359.70

0ver head 0.1 4,835.97

Harga satuan 53,195.67

Harga Satuan (Rp)

Jlh. Harga (Rp)

Total Harga (Rp)

b. Baha

n

besi pelat polos

b. Baha

n

Rabung Atap seng

Page 17: RAB perluasan workshop br.xls

No. Uraian Satuan Koefisien

251 m² lisplank zingnalum

a. UpahPekerja jam 0.4200 6,562.50 2,756.25

Tukang jam 1.2000 9,850.00 11,820.00

Mandor jam 0.0210 8,200.00 172.20

14,748.45

zinkalum m² 1.0500 120,000.00 126,000.00

baut bh 6.0000 2,000.00 12,000.00

126,000.00

C. Peralatan

Alat bant ls 1.0000 500.00 500.00

500.00

Jumlah 141,248.45

0ver head 0.1 14,124.85

Harga satuan ###

26100 m² cat tembok

a. UpahPekerja jam 40.0000 6,562.50 262,500.00

Tukang jam 60.0000 9,850.00 591,000.00

Mandor jam 2.0000 8,200.00 16,400.00

869,900.00

untuk 1m² 0.0100 869,900.00 8,699.00

b. BahanCat kg 0.1415 20,500.00 2900.75

jlh untuk 1m² 1 x cat 11,599.75

2.000 X cat 23,199.50

Jumlah 23,199.50

0ver head 0.1 2,319.95

Harga satuan 25,519.45

Harga Satuan (Rp)

Jlh. Harga (Rp)

Total Harga (Rp)

b. Baha

n

Page 18: RAB perluasan workshop br.xls

No. Uraian Satuan Koefisien

27 1 m2 Plesteran 1

a. UpahPekerja jam 2.0020 6,562.50 13,138.12

Tukang jam 1.4980 9,850.00 14,755.30

Mandor jam 0.1400 8,200.00 1,148.00

29,041.42

b. BahanSemen Zak 0.2960 48,000.00 14,208.00

Pasir Pas 0.0190 85,000.00 1,615.00

15,823.00

C. Peralatan

Alat bant ls 1.0000 500.00 500.00

500.00

Jumlah 45,364.42

0ver head 0.1 4,536.44

Harga satuan 49,900.87

281 m² Pasangan lobang angin

a. UpahPekerja jam 0.8000 15,000.00 12,000.00

Tukang jam 0.3000 500.00 150.00

Mandor jam 0.1000 25,000.00 2,500.00

14,650.00

b. BahanLobang a Bh 27.0000 2,500.00 67,500.00

Semen Zak 0.2881 48,000.00 13,827.00

81,327.00

C. Peralatan

Alat bant ls 1.0000 500.00 500.00

500.00

Jumlah 96,477.00

0ver head 0.1 9,647.70

Harga satuan ###

Harga Satuan (Rp)

Jlh. Harga (Rp)

Total Harga (Rp)

M3

Page 19: RAB perluasan workshop br.xls

No. Uraian Satuan Koefisien

291 m² Pasangan plafond

a. UpahPekerja jam 2.6667 6,562.50 17,500.00

Mandor jam 0.1333 8,200.00 1,093.33

18,593.33

b. BahanTriplek 4 m² 1.0500 47,000.00 49,350.00

Paku Zak 0.2881 10,906.00 3,141.61

52,491.61

C. Peralatan

Alat bant ls 1.0000 500.00 500.00

500.00

Jumlah 71,584.94

0ver head 0.1 7,158.49

Harga satuan 78,743.44

301 m² Pasangan Dinding 1/2 Bata

a. UpahPekerja hr 0.3754 6,562.50 2,463.40

Tukang hr 0.1873 9,850.00 1,844.41

Mandor hr 0.0096 8,200.00 78.93

4,386.74

b. BahanBatu Bata Bh 70.0000 650.00 45,500.00

Semen Zak 0.5761 48,000.00 27,654.00

Pasir Pas M3 0.0470 85,000.00 3,995.00

77,149.00

C. Peralatan

Alat bant ls 1.0000 500.00 500.00

500.00

Jumlah 82,035.74

0ver head 0.1 8,203.57

Harga satuan 90,239.31

Belawan, September 2010

Dibuat oleh,

ASISTEN MANAJER FASILITAS

INGGU SARNAINI

Harga Satuan (Rp)

Jlh. Harga (Rp)

Total Harga (Rp)

Page 20: RAB perluasan workshop br.xls

PERHITUNGAN VOLUME BESI

PEKERJAAN PERLUASAN WORKSHOPBELAWAN INTERNATIONAL CONTAINER TERMINAL

No Ø Besi(mm) Jumlah Jumlah Berat Besi (Kg) Keterangan

a b b c = a x b d e = c x d

sloof beton bertulang k 300untuk 1m³

1 12 8.33333333333333 6 6 50 0.888 44.400 t.utama

2 10 0.3 0.4 1.4 56.55555556 57 79.8 0.617 49.237 sengkang

jumlah 93.637 kg

pjng 1 m volume 0.12 m³

Pjng untuk menghasilkan 1m³ beton 8.33333333333

Pondasi dan sumbu beton bertulang k 300 untuk 1 bh

1 16 2.2 9 9 19.8 1.580 31.284 tul melintang

2 16 2.2 6.333333333 7 15.4 1.580 24.332 tul memanjang

4 12 0.3 0.6 1.8 12.13333333 13 23.4 0.880 20.592 sengkang

5 16 2.27 8 8 18.16 2.140 38.862 tiang

jumlah 115.070 kg

1bh = 0.589 m³

1bh = 115.070 kg

jadi 1m³ beton pondasi, besi = 195.498 kg

Lebar (m¹) Tinggi (m¹) Panjang /keliling(m¹)Panjang Jumlah

(m¹)Koefisien Berat

(Kg/m¹)

Page 21: RAB perluasan workshop br.xls

ctt : 5% untuk sambungan, bhan terbuang,bengkoan

pondasi 1 bh volume 0.5886 m³

Page 22: RAB perluasan workshop br.xls

No Ø Besi(mm) Jumlah Jumlah Berat Besi (Kg) Keterangan

a b b c = a x b d e = c x d

Pelat Lantai Beton bertulang

1 10 0.416666666666667 81 81 33.75 0.617 20.824 melintang

2 10 16 3.083333333 4 64 0.617 39.488 mamanjang 16 m

jumlah 60.312 kg

pjg 24.3

lbr 16

pjng 1 m, lebar 16m volume 2.4 m³

Pjng untuk menghasilkan 1m³ beton 0.41666666667

Lebar (m¹) Tinggi (m¹) Panjang /keliling(m¹)Panjang Jumlah

(m¹)Koefisien Berat

(Kg/m¹)

Page 23: RAB perluasan workshop br.xls