DAFTAR HARGA SATUANKEGIATAN PEKERJAAN

: :

PEMBANGUNAN TOWER MESJID JAMI'

NO.UPAH 1 Mandor 2 Kepala tukang

URAIAN UPAH / BAHAN

SATUAN

HARGA SATUAN

hari hari hari hari

Rp. Rp. Rp. Rp.

90,000.00 80,000.00 70,000.00 60,000.00

3 Tukang (batu, kayu, besi, cat) 4 Pekerja BAHAN 1 Ampelas 2 Bt.belah 15/20 cm 3 Batu bata 4 Bataco 5 Batu cor/kerikil Rantau 6 Batu Kali/Batu Gunung Rantau 7 Bendrat/kawat besi beton 8 Baut/Beugel/besi strip 9 Besi beton polos 10 Besi beton ulir 11 Pasir Beton 12 Pasir Beton/Cor 13 Pasir Urug 14 Tanah urug 15 Koral beton 16 Besi beton 17 Kawat beton 18 Kayu 5/7 19 Kayu Lanan 20 Papan lanan 21 Kayu bekisting ( Balok ) 22 Kayu ulin 23 Papan ulin 24 Kayu profil 25 Btg dolken ky galam dia 8-10/4m 26 Minyak bekisting 27 Plywood tebal 4 mm 28 Plywood tebal 2,7 mm 29 Multiplek tebal 9 mm 30 Paku/Angker 31 Paku biasa 32 Paku plywood 33 Paku ulin 34 Paku Genteng Metal 35 Paku payung 36 Paku sekrup 37 Kunci tanam biasa kualitas sedang 2 slaag 38 Kunci tanam biasa kualitas baik 39 Kunci tanam kamar mandi 40 Engsel Nylon 4" kualitas Baik 41 Engsel jendela 42 Grendel 43 Kait angin kualitas baik 44 Closed jongkok porselin 45 Closet duduk monoblok

lbr m3 bj bj m3 m3 kg kg kg kg m3 m3 m3 m3 m3 kg kg m3 m3 m3 m3 m3 m3 m' ltr lbr lbr lbr kg kg kg kg kg Kg Kg bh bh bh bh bh bh bh bh bh

Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

2,000.00 250,000.00 1,200.00 2,400.00 270,000.00 220,000.00 15,000.00 12,500.00 8,400.00 9,000.00 340,000.00 350,000.00 200,000.00 200,000.00 350,000.00 8,400.00 15,000.00 2,000,000.00 2,000,000.00 4,000,000.00 1,500,000.00 5,000,000.00 6,000,000.00 2,000.00 5,000.00 2,500.00 60,000.00 44,000.00 120,000.00 10,000.00 10,000.00 12,000.00 10,000.00 19,500.00 15,000.00 12,000.00 75,000.00 125,000.00 40,000.00 11,500.00 6,000.00 11,000.00 2,000.00 165,000.00 1,250,000.00

NO.

URAIAN UPAH / BAHAN

SATUANbh bh bh bh lbr bh m2 m2 lbr kg kg kg kg kg kg kg kg ltr bh bh m2 m2 m2 m2 m2 lbr m2 m2 m2 m2 m3 m3 set set set titik bh bh bh bh bh bh bh bh bh bh bh bh zak kg bh bh Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

HARGA SATUAN15,000.00 17,250.00 15,000.00 195,000.00 28,500.00 16,000.00 7,500.00 9,000.00 37,500.00 10,000.00 34,500.00 13,800.00 10,000.00 7,000.00 10,000.00 30,000.00 13,000.00 7,500.00 225,000.00 185,000.00 57,500.00 71,500.00 95,000.00 110,000.00 92,650.00 55,000.00 54,000.00 40,000.00 31,500.00 45,000.00 57,445.00 25,000.00 114,000.00 90,000.00 100,000.00 115,000.00 17,250.00 17,250.00 15,000.00 6,000.00 9,000.00 50,000.00 90,000.00 80,000.00 125,000.00 1,600,000.00 3,000,000.00 4,500,000.00 46,500.00 2,750.00 250,000.00 550,000.00

46 Kran air dia 3/4 atau 1/2 " 47 Kran ledeng stainless 48 Floordrain 49 Bak cuci piring stainlesstell 50 Genteng Metal setara "Sakura" 51 Nok Atap Genteng Metal 52 Kawat harmonika 53 Kawat kassa 54 Seng gelombang BJLS 0,20 55 Cat dasar 56 Cat Kilap setara "Platon" 57 Cat Tembok setara "Dana Paint" 58 Cat Meni 59 Plamir 60 Dempul jadi 61 Cat penutup kilap 62 Cat penutup tembok/matex 63 Minyak Cat 64 Jendela ulin pabrikasi 65 Jendela lanan pabrikasi 66 Kaca polos tebal 3 mm 67 Kaca polos tebal 5 mm 68 Kaca one way tebal 5 mm 69 Kaca es tebal 5 mm 70 Kaca rayban tebal 5 mm 71 Kalsiboard 9 mm 72 Keramik uk. 10 x 20 73 Keramik uk. 20x20 74 Keramik uk. 30 x 30 75 Keramik warna 20 x 20 76 Keramik uk. 40 x 40 77 Ubin PC 30 x 30 78 Kunci pintu - Kunci Tanam 2 Slaag Kualitas Baik - Kunci Tanam 2 Slaag Kualitas Sedang - Kunci Tanam 1 Slaag Kualitas Baik Listrik 78 79 80 81 82 83 84 85 86 87 88 89 90 - Titik lampu - Saklar tunggal - Saklar ganda - Stop kontak - Lampu pijar 15 - 25 watt - Lampu pijar 40 - 60 watt - Lampu neon (TL) 20 watt - Lampu neon (TL) 40 watt - Lampu (TL) 20 watt Double - Lampu (TL) 40 watt Double - Sambungan ke PLN daya 900 watt - Sambungan ke PLN daya 2200 watt - Sambungan ke PLN daya 4400 watt

91 Portland Cement (PC) 92 Semen warna 93 Pintu panel kayu lanan pabrikasi 94 Pintu panel kayu ulin pabrikasi

27000 2700 29700

DAFTAR ANALISA HARGA SATUAN PEKERJAANDAFTAR : HARGA SATUAN PEKERJAAN ( UNIT PRICE )

NO.

URAIAN

SATUAN

UPAH

BAHAN

JUMLAH

I

PEKERJAAN PERSIAPAN 1 Pengukuran dan Pemasangan Bouwplank 0.01200 M3 Kayu 5/7 0.02000 Kg Paku 0.00400 M3 Kayu Papan 2/20 0.10000 Oh Pekerja 0.00500 Oh Mandor 0.10000 Oh Tukang Kayu 0.01000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. 1 M1 2,000,000.00 10,000.00 2,000,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 2 Membersihkan Lapangan dan Perataan 0.10000 Oh Pekerja 0.00500 Oh Mandor Rp. Rp. 1 M2 60,000.00 Rp. 90,000.00 Rp. Rp. 3 Bongkar Beton Bertulang 6.66700 Oh Pekerja 0.33300 Oh Mandor Rp. Rp. 1M3

Rp. Rp. Rp. 6,000.00 450.00 7,000.00 800.00 14,250.00 Rp.

24,000.00 200.00 8,000.00

32,200.00 Rp.

46,450.00

6,000.00 450.00 6,450.00 Rp. Rp. 6,450.00

60,000.00 Rp. 90,000.00 Rp. Rp.

400,020.00 29,970.00 429,990.00 Rp. Rp. 429,990.00

II

PEKERJAAN TANAH 1 Galian Tanah Biasa sedalam 1 M 0.40000 Oh Pembantu Tukang 0.04000 Oh Mandor Rp. Rp. 1 M3 60,000.00 Rp. 90,000.00 Rp. Rp. 2 Urugan Kembali 0.19200 Oh Pembantu Tukang 0.01900 Oh Mandor Rp. Rp. 1M3

24,000.00 3,600.00 27,600.00 Rp. Rp. 27,600.00

60,000.00 Rp. 90,000.00 Rp. Rp.

11,520.00 1,710.00 13,230.00 Rp. Rp. 13,230.00

3 Pemadatan Tanah 0.50000 Oh Pembantu Tukang 0.05000 Oh Mandor Rp. Rp.

1 M3 60,000.00 Rp. 90,000.00 Rp. Rp. 30,000.00 4,500.00 34,500.00 Rp. Rp. 34,500.00

4 Urugan Pasir 1.20000 M3 Pasir Urug 0.30000 Oh Pembantu Tukang 0.01000 Oh Mandor Rp. Rp. Rp.

1M

3

200,000.00 60,000.00 Rp. 90,000.00 Rp. Rp. 18,000.00 900.00

Rp.

240,000.00

18,900.00 Rp.

240,000.00 Rp.

258,900.00

NO.

URAIAN

HARGA SATUAN

BIAYA UPAH

BIAYA BAHAN

JUMLAH

5 Urugan Tanah Merah ( BOW ) 1.25000 M3 Tanah Urug 0.25000 Oh Pembantu Tukang 0.01000 Oh Mandor Rp. Rp. Rp.

1 M3 200,000.00 60,000.00 Rp. 90,000.00 Rp. Rp. 15,000.00 900.00 15,900.00 Rp. 250,000.00 Rp. 265,900.00 Rp. 250,000.00

III

PEKERJAAN PONDASI 1 Pasangan Pondasi Batu Kali camp. 1 : 3 1.10000 M3 Bt. Belah 15/20 cm 4.04000 Zak Semen Portland 50 kg 0.48500 M3 Pasir Pasang 1.50000 Oh Pekerja 0.07500 Oh Mandor 0.60000 Oh Tukang Batu 0.06000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. 1 M3 250,000.00 46,500.00 350,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 2 Pasangan Pondasi Batu Kosong 1.20000 M3 Bt. Belah 15/20 cm 0.30000 M3 Pasir Urug 0.78000 Oh Pekerja 0.03900 Oh Mandor 0.39000 Oh Tukang Batu 0.03900 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. 1M3

Rp. Rp. Rp. 90,000.00 6,750.00 42,000.00 4,800.00 143,550.00 Rp.

275,000.00 187,860.00 169,750.00

632,610.00 Rp.

776,160.00

220,000.00 200,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 46,800.00 3,510.00 27,300.00 3,120.00

Rp. Rp.

264,000.00 60,000.00

80,730.00 Rp.

324,000.00 Rp.

404,730.00

DAFTAR ANALISA HARGA SATUAN PEKERJAANDAFTAR : HARGA SATUAN PEKERJAAN ( UNIT PRICE )

NO.

URAIAN

SATUAN

UPAH

BAHAN

JUMLAH

VI PEKERJAAN KAYU 1 Pasangan Kusen Pintu dan Jendela Kayu Ulin 1.10000 M3 Kayu Ulin 6.00000 Oh Pekerja 0.30000 Oh Mandor 20.00000 Oh Tukang Kayu 2.00000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. 1 M3 5,000,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 360,000.00 27,000.00 1,400,000.00 160,000.00 1,947,000.00 Rp. 5,500,000.00 Rp. 7,447,000.00 Rp. 5,500,000.00

2 Pasangan Konstruksi Kuda-kuda Kayu Ulin 1.10000 M3 Kayu Ulin 0.80000 Kg Paku 15.00000 Kg Besi Strip 4.00000 Oh Pekerja 0.20000 Oh Mandor 12.00000 Oh Tukang Kayu 1.20000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M3 5,000,000.00 10,000.00 12,500.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 240,000.00 18,000.00 840,000.00 96,000.00 1,194,000.00 Rp. 5,695,500.00 Rp. 6,889,500.00 Rp. Rp. Rp. 5,500,000.00 8,000.00 187,500.00

3 Pasangan Konstruksi Kuda-kuda Kayu Lanan 1.10000 M3 Kayu Lanan 0.80000 Kg Paku 15.00000 Kg Besi Strip 4.00000 Oh Pekerja 0.20000 Oh Mandor 12.00000 Oh Tukang Kayu 1.20000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1M

3

2,000,000.00 10,000.00 12,500.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 240,000.00 18,000.00 840,000.00 96,000.00

Rp. Rp. Rp.

2,200,000.00 8,000.00 187,500.00

1,194,000.00 Rp.

2,395,500.00 Rp.

3,589,500.00

4 Pasangan Gording Kayu Lanan 1.10000 M3 Kayu Lanan 2.20000 Kg Beugel, Baut 2.40000 Oh Pekerja 0.12000 Oh Mandor 7.00000 Oh Tukang Kayu 0.70000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp.

1M

3

2,000,000.00 12,500.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 144,000.00 10,800.00 490,000.00 56,000.00

Rp. Rp.

2,200,000.00 27,500.00

700,800.00 Rp.

2,227,500.00 Rp.

2,928,300.00

5 Pasangan Kaso + Reng Kayu Lanan 0.01400 M3 Kayu Lanan 0.15000 Kg Paku 0.10000 Oh Pekerja 0.00500 Oh Mandor 0.10000 Oh Tukang Kayu 0.01000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp.

1 M2 2,000,000.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 6,000.00 450.00 7,000.00 800.00 14,250.00 Rp. 29,500.00 Rp. 43,750.00 Rp. Rp. 28,000.00 1,500.00

6 Pasangan Listplank 2 x 2/20 cm Kayu Ulin 0.00880 M3 Kayu Ulin 0.06000 Kg Paku 0.10000 Oh Pekerja 0.05000 Oh Mandor 0.10000 Oh Tukang Kayu 0.01000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp.

1M

1

6,000,000.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 6,000.00 4,500.00 7,000.00

Rp. Rp.

52,800.00 600.00

800.00 18,300.00 Rp.

53,400.00 Rp.

71,700.00

NO.

URAIAN

HARGA SATUAN

BIAYA UPAH

BIAYA BAHAN

JUMLAH

7 Pasangan Listplank 2 x 2/20 cm Kayu Lanan 0.00880 M3 Kayu Lanan 0.06000 Kg Paku 0.10000 Oh Pekerja 0.05000 Oh Mandor 0.10000 Oh Tukang Kayu 0.01000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp.

1 M1 4,000,000.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 6,000.00 4,500.00 7,000.00 800.00 18,300.00 Rp. 35,800.00 Rp. 54,100.00 Rp. Rp. 35,200.00 600.00

8 Pasangan List Plafond Kayu Profil 1.05000 M' Kayu Profil 0.02100 Oh Pekerja 0.00100 Oh Mandor 0.02100 Oh Tukang Kayu 0.00200 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp.

1M

1

2,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 1,260.00 90.00 1,470.00 160.00

Rp.

2,100.00

2,980.00 Rp.

2,100.00 Rp.

5,080.00

9 Pasangan Rangka Dinding Pemisah Kayu Lanan 0.00700 M3 Kayu, Papan Lanan 0.01950 M3 Kayu, Balok Lanan 0.10000 Kg Paku 0.15000 Oh Pekerja 0.07500 Oh Mandor 0.45000 Oh Tukang Kayu 0.04500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M2 4,000,000.00 2,000,000.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 9,000.00 6,750.00 31,500.00 3,600.00 50,850.00 Rp. 68,000.00 Rp. 118,850.00 Rp. Rp. Rp. 28,000.00 39,000.00 1,000.00

10 Pasangan Plywood T=4 mm untuk Dinding 0.33600 Lbr Plywood 0.05000 Kg Paku 0.02500 Oh Pekerja 0.00130 Oh Mandor 0.07500 Oh Tukang Kayu 0.00750 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp.

1 M2 60,000.00 12,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 1,500.00 117.00 5,250.00 600.00 7,467.00 Rp. 20,760.00 Rp. 28,227.00 Rp. Rp. 20,160.00 600.00

11 Pasangan Rangka Dinding Pemisah Doule Plywood Rangka Kayu Lanan 0.00700 M3 Kayu, Papan Lanan 0.01950 M3 Kayu, Balok Lanan 0.10000 Kg Paku 0.67200 Lbr Plywood 0.10000 Kg Paku 0.20000 Oh Pekerja 0.07760 Oh Mandor 0.60000 Oh Tukang Kayu 0.06000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1M

2

4,000,000.00 2,000,000.00 10,000.00 60,000.00 12,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 12,000.00 6,984.00 42,000.00 4,800.00

Rp. Rp. Rp. Rp. Rp.

28,000.00 39,000.00 1,000.00 40,320.00 1,200.00

65,784.00 Rp.

109,520.00 Rp.

175,304.00

12 Pasangan Rangka Langit-langit 1 x 1 m Kayu Lanan 0.01200 M3 Kayu Lanan 0.10000 Kg Paku 0.15000 Oh Pekerja 0.07500 Oh Mandor 0.25000 Oh Tukang Kayu 0.02500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp.

1M

2

2,000,000.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 9,000.00 6,750.00 17,500.00 2,000.00

Rp. Rp.

24,000.00 1,000.00

35,250.00 Rp.

25,000.00 Rp.

60,250.00

13 Rangka bawah kayu ulin/m3 F.1/m3 1.10000 M3 Kayu ulin 5.00000 Oh Pekerja 0.25000 Oh Mandor 15.00000 Oh Tukang Kayu 1.50000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. 5,000,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 300,000.00 22,500.00 1,050,000.00 120,000.00 1,492,500.00 Rp. 5,500,000.00 Rp. 6,992,500.00 Rp. 5,500,000.00

NO.

URAIAN

HARGA SATUAN

BIAYA UPAH

BIAYA BAHAN

JUMLAH

14 Rangka badan kayu ulin/m3 F.27/m3 1.10000 M3 Kayu ulin 3.00000 kg Paku/Angker 12.00000 Oh Pekerja 0.60000 Oh Mandor 36.00000 Oh Tukang Kayu 3.60000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. 5,000,000.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 3/4 Upah 15 Rangka badan kayu lanan/m3 3/4 F.27/m3 0.75000 Upah F.27 1.10000 kg kayu lanan 3.00000 kg paku Rp. Rp. Rp. 3,582,000.00 2,000,000.00 10,000.00 Rp. Rp. 16 Pek.lantai ulin/m2 0.01800 M3 Kayu ulin 0.20000 kg Paku 0.28000 Oh Pekerja 0.01000 Oh Mandor 0.80000 Oh Tukang Kayu 0.08000 Oh Kepala Tukang F.37/M2 Rp. Rp. Rp. Rp. Rp. Rp. 6,000,000.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 17 Pek.lantai papan/dinding lanan/m2 3/4 F.37 0.75000 Upah F.37 0.02400 m3 papan lanan 0.20000 kg paku Rp. Rp. Rp. 80,100.00 4,000,000.00 10,000.00 Rp. 60,075.00 Rp. Rp. 60,075.00 Rp. 96,000.00 2,000.00 98,000.00 Rp. 158,075.00 16,800.00 900.00 56,000.00 6,400.00 80,100.00 Rp. 110,000.00 Rp. 190,100.00 Rp. Rp. 108,000.00 2,000.00 30,000.00 30,000.00 Rp. 4,886,500.00 Rp. 4,916,500.00 Rp. Rp. 2,686,500.00 2,200,000.00 Rp. 720,000.00 54,000.00 2,520,000.00 288,000.00 3,582,000.00 Rp. 2,686,500.00 Rp. 5,530,000.00 Rp. 5,530,000.00 Rp. 9,112,000.00 8,216,500.00 Rp. Rp. 5,500,000.00 30,000.00

DAFTAR ANALISA HARGA SATUAN PEKERJAANDAFTAR : HARGA SATUAN PEKERJAAN ( UNIT PRICE )

NO.

URAIAN

SATUAN

UPAH

BAHAN

JUMLAH

VII PEKERJAAN BETON 1 Membuat Beton Tumbuk camp. 1Pc : 3Ps : 5Kr 4.36000 Zak Semen Portland 50 kg 0.52000 M3 Pasir Beton 0.87000 M3 Koral Beton 1.65000 Oh Pekerja 0.08000 Oh Mandor 0.25000 Oh Tukang Batu 0.02500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. 1 M3 46,500.00 350,000.00 270,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 2 Membuat Beton Bertulang camp. 1Pc : 2Ps : 3Kr 6.64000 Zak Semen Portland 50 kg 0.52000 M3 Pasir Beton 0.78000 M3 Koral Beton 1.65000 Oh Pekerja 0.08000 Oh Mandor 0.25000 Oh Tukang Batu 0.02500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. 1M3

Rp. Rp. Rp. 99,000.00 7,200.00 17,500.00 2,000.00 125,700.00 Rp.

202,740.00 182,000.00 234,900.00

619,640.00 Rp.

745,340.00

46,500.00 350,000.00 270,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 99,000.00 7,200.00 17,500.00 2,000.00

Rp. Rp. Rp.

308,760.00 182,000.00 210,600.00

125,700.00 Rp.

701,360.00 Rp.

827,060.00

3 Pembesian dengan Besi Polos 1.05000 Kg Besi Beton 0.01500 Kg Kawat Beton 0.00700 Oh Pekerja 0.00030 Oh Mandor 0.00700 Oh Tukang Besi 0.00070 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp.

1 Kg 8,400.00 15,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 420.00 27.00 490.00 56.00 993.00 Rp. 9,045.00 Rp. 10,038.00 Rp. Rp. 8,820.00 225.00

4 Pembesian dengan Besi Ulir 1.05000 Kg Besi Beton 0.01500 Kg Kawat Beton 0.00700 Oh Pekerja 0.00030 Oh Mandor 0.00700 Oh Tukang Besi 0.00070 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp.

1 Kg 9,000.00 15,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 420.00 27.00 490.00 56.00 993.00 Rp. 9,675.00 Rp. 10,668.00 Rp. Rp. 9,450.00 225.00

5 Pasang Bekisting untuk Pondasi 0.04000 M3 Kayu Bekisting 0.30000 Kg Paku 0.10000 Ltr Minyak Bekisting 0.30000 Oh Pekerja 0.00500 Oh Mandor 0.26000 Oh Tukang Kayu 0.02600 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M2 1,500,000.00 10,000.00 2,500.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 18,000.00 450.00 18,200.00 2,080.00 38,730.00 Rp. 63,250.00 Rp. 101,980.00 Rp. Rp. Rp. 60,000.00 3,000.00 250.00

6 Pasang Bekisting untuk Sloof 0.04500 M3 Kayu Bekisting 0.30000 Kg Paku 0.10000 Ltr Minyak Bekisting 0.30000 Oh Pekerja 0.00500 Oh Mandor 0.26000 Oh Tukang Kayu 0.02600 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M2 1,500,000.00 10,000.00 2,500.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 18,000.00 450.00 18,200.00 2,080.00 38,730.00 Rp. 70,750.00 Rp. 109,480.00 Rp. Rp. Rp. 67,500.00 3,000.00 250.00

NO.

URAIAN

SATUAN

UPAH

BAHAN

JUMLAH

7 Pasang Bekisting untuk Kolom 0.04000 M3 Kayu Bekisting 0.40000 Kg Paku 0.20000 Ltr Minyak Bekisting 0.01500 M3 Kayu Bekisting 0.35000 Lbr Multiplek tebal 9 mm 2.00000 Btg Dolken Ky. Galam dia. 8-10 / 4 m 0.30000 Oh Pekerja 0.00600 Oh Mandor 0.33000 Oh Tukang Kayu 0.03300 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M2 1,500,000.00 10,000.00 2,500.00 1,500,000.00 120,000.00 5,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 18,000.00 540.00 23,100.00 2,640.00 44,280.00 Rp. 139,000.00 Rp. 183,280.00 Rp. Rp. Rp. Rp. Rp. Rp. 60,000.00 4,000.00 500.00 22,500.00 42,000.00 10,000.00

8 Pasang Bekisting untuk Balok 0.04000 M3 Kayu Bekisting 0.40000 Kg Paku 0.20000 Ltr Minyak Bekisting 0.01800 M3 Kayu Bekisting 0.35000 Lbr Multiplek tebal 9 mm 2.00000 Btg Dolken Ky. Galam dia. 8-10 / 4 m 0.30000 Oh Pekerja 0.00600 Oh Mandor 0.33000 Oh Tukang Kayu 0.03300 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M2 1,500,000.00 10,000.00 2,500.00 1,500,000.00 120,000.00 5,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 18,000.00 540.00 23,100.00 2,640.00 44,280.00 Rp. 143,500.00 Rp. 187,780.00 Rp. Rp. Rp. Rp. Rp. Rp. 60,000.00 4,000.00 500.00 27,000.00 42,000.00 10,000.00

9 Pasang Bekisting untuk Lantai 0.04000 M3 Kayu Bekisting 0.40000 Kg Paku 0.20000 Ltr Minyak Bekisting 0.01500 M3 Kayu Bekisting 0.35000 Lbr Multiplek tebal 9 mm 6.00000 Btg Dolken Ky. Galam dia. 8-10 / 4 m 0.32000 Oh Pekerja 0.00600 Oh Mandor 0.33000 Oh Tukang Kayu 0.03300 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1M

2

1,500,000.00 10,000.00 2,500.00 1,500,000.00 120,000.00 5,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 19,200.00 540.00 23,100.00 2,640.00

Rp. Rp. Rp. Rp. Rp. Rp.

60,000.00 4,000.00 500.00 22,500.00 42,000.00 30,000.00

45,480.00 Rp.

159,000.00 Rp.

204,480.00

10 Pasang Bekisting untuk Dinding 0.03000 M3 Kayu Bekisting 0.40000 Kg Paku 0.20000 Ltr Minyak Bekisting 0.02000 M3 Kayu Bekisting 0.35000 Lbr Multiplek tebal 9 mm 3.00000 Btg Dolken Ky. Galam dia. 8-10 / 4 m 4.00000 Bh Formtie/Penjaga Jarak Bekisting 0.32000 Oh Pekerja 0.00600 Oh Mandor 0.33000 Oh Tukang Kayu 0.03300 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M2 1,500,000.00 10,000.00 2,500.00 1,500,000.00 120,000.00 10,000.00 3,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 19,200.00 540.00 23,100.00 2,640.00 45,480.00 Rp. 163,500.00 Rp. 208,980.00 Rp. Rp. Rp. Rp. Rp. Rp. Rp. 45,000.00 4,000.00 500.00 30,000.00 42,000.00 30,000.00 12,000.00

11 Pasang Bekisting untuk Tangga 0.03000 M3 Kayu Bekisting 0.40000 Kg Paku 0.15000 Ltr Minyak Bekisting 0.01500 M3 Kayu Bekisting 0.35000 Lbr Multiplek tebal 9 mm 2.00000 Btg Dolken Ky. Galam dia. 8-10 / 4 m 0.32000 Oh Pekerja 0.00600 Oh Mandor 0.33000 Oh Tukang Kayu 0.03300 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M2 1,500,000.00 10,000.00 2,500.00 1,500,000.00 120,000.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 19,200.00 540.00 23,100.00 2,640.00 45,480.00 Rp. 133,875.00 Rp. 179,355.00 Rp. Rp. Rp. Rp. Rp. Rp. 45,000.00 4,000.00 375.00 22,500.00 42,000.00 20,000.00

NO.

URAIAN

SATUAN

UPAH

BAHAN

JUMLAH

12 Membuat Beton dengan Mutu K. 225 7.76000 Zak Semen Portland 50 kg 0.65000 M3 Pasir Beton 0.65000 M3 Koral Beton 6.00000 Oh Pekerja 0.30000 Oh Mandor 1.00000 Oh Tukang Batu 0.10000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M3 46,500.00 350,000.00 270,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 360,000.00 27,000.00 70,000.00 8,000.00 465,000.00 Rp. 763,840.00 Rp. 1,228,840.00 Rp. Rp. Rp. 360,840.00 227,500.00 175,500.00

13 Membuat Beton dengan Mutu K. 275 8.00000 Zak Semen Portland 50 kg 0.40000 M3 Pasir Beton 0.82000 M3 Koral Beton 6.00000 Oh Pekerja 0.30000 Oh Mandor 1.00000 Oh Tukang Batu 0.10000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M3 46,500.00 350,000.00 270,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 360,000.00 27,000.00 70,000.00 8,000.00 465,000.00 Rp. 733,400.00 Rp. 1,198,400.00 Rp. Rp. Rp. 372,000.00 140,000.00 221,400.00

14 Membuat Pondasi Beton Bertulang ( 150 Kg + Bekisting ) 0.20000 M3 Kayu Bekisting 1.50000 Kg Paku 0.50000 Ltr Minyak Bekisting 157.50000 Kg Besi Beton 2.25000 Kg Kawat Beton 6.64000 Zak Semen Portland 50 kg 0.52000 M3 Pasir Beton 0.78000 M3 Koral Beton 4.20000 Oh Pekerja 0.15000 Oh Mandor 0.25000 Oh Tukang Batu 1.30000 Oh Tukang Kayu 1.05000 Oh Tukang Besi 0.26000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M3

1,500,000.00 10,000.00 2,500.00 8,400.00 15,000.00 46,500.00 350,000.00 270,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 252,000.00 13,500.00 17,500.00 91,000.00 73,500.00 20,800.00

Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

300,000.00 15,000.00 1,250.00 1,323,000.00 33,750.00 308,760.00 182,000.00 210,600.00

468,300.00 Rp.

2,374,360.00 Rp.

2,842,660.00

15 Membuat Sloof Beton Bertulang ( 280 Kg + Bekisting ) 0.27000 M3 Kayu Bekisting 1.80000 Kg Paku 0.60000 Ltr Minyak Bekisting 294.00000 Kg Besi Beton 4.20000 Kg Kawat Beton 6.64000 Zak Semen Portland 50 kg 0.52000 M3 Pasir Beton 0.78000 M3 Koral Beton 5.41000 Oh Pekerja 0.19400 Oh Mandor 0.25000 Oh Tukang Batu 1.56000 Oh Tukang Kayu 1.96000 Oh Tukang Besi 0.37700 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M3

1,500,000.00 10,000.00 2,500.00 8,400.00 15,000.00 46,500.00 350,000.00 270,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 324,600.00 17,460.00 17,500.00 109,200.00 137,200.00 30,160.00

Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

405,000.00 18,000.00 1,500.00 2,469,600.00 63,000.00 308,760.00 182,000.00 210,600.00

636,120.00 Rp.

3,658,460.00 Rp.

4,294,580.00

NO.

URAIAN

SATUAN

UPAH

BAHAN

JUMLAH

16 Membuat Kolom Beton Bertulang ( 230 Kg + Bekisting ) 0.40000 M3 Kayu Bekisting 4.00000 Kg Paku 2.00000 Ltr Minyak Bekisting 241.50000 Kg Besi Beton 3.45000 Kg Kawat Beton 6.64000 Zak Semen Portland 50 kg 0.52000 M3 Pasir Beton 0.78000 M3 Koral Beton 0.15000 M3 Kayu Bekisting 3.50000 Lbr Multiplek tebal 9 mm 20.00000 Btg Dolken Ky. Galam dia. 8-10 / 4 m 6.26000 Oh Pekerja 0.20900 Oh Mandor 0.25000 Oh Tukang Batu 3.30000 Oh Tukang Kayu 1.61000 Oh Tukang Besi 0.51600 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M3

1,500,000.00 10,000.00 2,500.00 8,400.00 15,000.00 46,500.00 350,000.00 270,000.00 1,500,000.00 120,000.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 375,600.00 18,810.00 17,500.00 231,000.00 112,700.00 41,280.00

Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

600,000.00 40,000.00 5,000.00 2,028,600.00 51,750.00 308,760.00 182,000.00 210,600.00 225,000.00 420,000.00 200,000.00

796,890.00 Rp.

4,271,710.00 Rp.

5,068,600.00

17 Membuat Balok Beton Bertulang ( 280 Kg + Bekisting ) 0.32000 M3 Kayu Bekisting 3.20000 Kg Paku 1.60000 Ltr Minyak Bekisting 294.00000 Kg Besi Beton 4.20000 Kg Kawat Beton 6.64000 Zak Semen Portland 50 kg 0.52000 M3 Pasir Beton 0.78000 M3 Koral Beton 0.14400 M3 Kayu Bekisting 2.80000 Lbr Multiplek tebal 9 mm 16.00000 Btg Dolken Ky. Galam dia. 8-10 / 4 m 6.01000 Oh Pekerja 0.21200 Oh Mandor 0.25000 Oh Tukang Batu 2.64000 Oh Tukang Kayu 1.96000 Oh Tukang Besi 0.48500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M3

1,500,000.00 10,000.00 2,500.00 8,400.00 15,000.00 46,500.00 350,000.00 270,000.00 1,500,000.00 120,000.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 360,600.00 19,080.00 17,500.00 184,800.00 137,200.00 38,800.00

Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

480,000.00 32,000.00 4,000.00 2,469,600.00 63,000.00 308,760.00 182,000.00 210,600.00 216,000.00 336,000.00 160,000.00

757,980.00 Rp.

4,461,960.00 Rp.

5,219,940.00

18 Membuat Balok Beton Bertulang ( 250 Kg + Bekisting ) 0.32000 M3 Kayu Bekisting 3.20000 Kg Paku 1.60000 Ltr Minyak Bekisting 252.00000 Kg Besi Beton 3.60000 Kg Kawat Beton 6.64000 Zak Semen Portland 50 kg 0.52000 M3 Pasir Beton 0.78000 M3 Koral Beton 0.14400 M3 Kayu Bekisting 2.80000 Lbr Multiplek tebal 9 mm 16.00000 Btg Dolken Ky. Galam dia. 8-10 / 4 m 5.73000 Oh Pekerja 0.20000 Oh Mandor 0.25000 Oh Tukang Batu 2.64000 Oh Tukang Kayu 1.68000 Oh Tukang Besi 0.45700 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1M

3

1,500,000.00 10,000.00 2,500.00 8,400.00 15,000.00 46,500.00 350,000.00 270,000.00 1,500,000.00 120,000.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 343,800.00 18,000.00 17,500.00 184,800.00 117,600.00 36,560.00

Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

480,000.00 32,000.00 4,000.00 2,116,800.00 54,000.00 308,760.00 182,000.00 210,600.00 216,000.00 336,000.00 160,000.00

718,260.00 Rp.

4,100,160.00 Rp.

4,818,420.00

NO.

URAIAN

SATUAN

UPAH

BAHAN

JUMLAH

19 Membuat Lantai Beton Bertulang ( 125 Kg + Bekisting ) 0.50000 M3 Kayu Bekisting 5.00000 Kg Paku 2.50000 Ltr Minyak Bekisting 131.25000 Kg Besi Beton 1.87500 Kg Kawat Beton 6.64000 Zak Semen Portland 50 kg 0.52000 M3 Pasir Beton 0.78000 M3 Koral Beton 0.18750 M3 Kayu Bekisting 4.37500 Lbr Multiplek tebal 9 mm 75.00000 Btg Dolken Ky. Galam dia. 8-10 / 4 m 6.52500 Oh Pekerja 0.19250 Oh Mandor 0.25000 Oh Tukang Batu 4.12500 Oh Tukang Kayu 0.87500 Oh Tukang Besi 0.52500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M3

1,500,000.00 10,000.00 2,500.00 8,400.00 15,000.00 46,500.00 350,000.00 270,000.00 1,500,000.00 120,000.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 391,500.00 17,325.00 17,500.00 288,750.00 61,250.00 42,000.00

Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

750,000.00 50,000.00 6,250.00 1,102,500.00 28,125.00 308,760.00 182,000.00 210,600.00 281,250.00 525,000.00 750,000.00

818,325.00 Rp.

4,194,485.00 Rp.

5,012,810.00

20 Membuat Dinding Beton Bertulang ( 95 Kg + Bekisting ) 0.24000 M3 Kayu Bekisting 3.20000 Kg Paku 1.60000 Ltr Minyak Bekisting 99.75000 Kg Besi Beton 1.42500 Kg Kawat Beton 6.64000 Zak Semen Portland 50 kg 0.52000 M3 Pasir Beton 0.78000 M3 Koral Beton 0.16000 M3 Kayu Bekisting 2.80000 Lbr Multiplek tebal 9 mm 24.00000 Btg Dolken Ky. Galam dia. 8-10 / 4 m 32.00000 Bh Formtie/Penjaga Jarak Bekisting 4.87500 Oh Pekerja 0.15650 Oh Mandor 0.25000 Oh Tukang Batu 2.64000 Oh Tukang Kayu 0.66500 Oh Tukang Besi 0.35550 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M3

1,500,000.00 10,000.00 2,500.00 8,400.00 15,000.00 46,500.00 350,000.00 270,000.00 1,500,000.00 120,000.00 10,000.00 3,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 292,500.00 14,085.00 17,500.00 184,800.00 46,550.00 28,440.00

Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

360,000.00 32,000.00 4,000.00 837,900.00 21,375.00 308,760.00 182,000.00 210,600.00 240,000.00 336,000.00 240,000.00 96,000.00

583,875.00 Rp.

2,868,635.00 Rp.

3,452,510.00

DAFTAR ANALISA HARGA SATUAN PEKERJAANDAFTAR : HARGA SATUAN PEKERJAAN ( UNIT PRICE )

NO.

URAIAN

SATUAN

UPAH

BAHAN

JUMLAH

VIII PEKERJAAN PENUTUP ATAP 1 Bongkaran atap 0.25000 Pekerja 0.00600 Mandor 0.13000 Tukang 0.01300 Kepala Tukang Rp. Rp. Rp. Rp. 1 m2 30,000.00 Rp. 45,000.00 Rp. 45,000.00 Rp. 50,000.00 Rp. Rp. 7,500.00 270.00 5,850.00 650.00 14,270.00 Rp. 0 Rp. 14,270.00

1 Pasang Atap Genteng Metal 1.65000 Lbr Genteng Metal 0.20000 Kg Paku 0.20000 Oh Pekerja 0.01000 Oh Mandor 0.10000 Oh Tukang Kayu 0.01000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp.

1 M2 28,500.00 19,500.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 12,000.00 900.00 7,000.00 800.00 20,700.00 Rp. 50,925.00 Rp. 71,625.00 Rp. Rp. 47,025.00 3,900.00

2 Pasang Atap Nok Genteng Metal 1.10000 Bh Nok Genteng Metal 0.05000 Kg Paku 0.25000 Oh Pekerja 0.01300 Oh Mandor 0.15000 Oh Tukang Kayu 0.01500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp.

1 M1 16,000.00 19,500.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 15,000.00 1,170.00 10,500.00 1,200.00 27,870.00 Rp. 18,575.00 Rp. 46,445.00 Rp. Rp. 17,600.00 975.00

IX PEKERJAAN LANGIT - LANGIT 1 Pasang Langit - langit Plywood 4 mm 0.37500 Lbr Plywood 4 mm 0.03000 Kg Paku 0.07000 Oh Pekerja 0.00350 Oh Mandor 0.10000 Oh Tukang Kayu 0.01000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. 1 M2 60,000.00 12,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 2 Pasang Langit - langit Kalsiboard Tb 9 mm 0.36000 Lbr Kalsiboard 120x240x0,9 cm 0.11000 Kg Paku Sekrup 0.10000 Oh Pekerja 0.05000 Oh Mandor 0.50000 Oh Tukang Kayu 0.05000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. 1 M2 55,000.00 12,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 3 Pasang Langit - langit Kayu Lanan 0.02400 M3 Kayu Lanan ( Papan ) 0.01000 Kg Paku 0.05000 Kg Paku Sekrup 0.20000 Oh Pekerja 0.01000 Oh Mandor 0.60000 Oh Tukang Kayu 0.06000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. 1 M2 4,000,000.00 10,000.00 12,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 12,000.00 900.00 42,000.00 4,800.00 59,700.00 Rp. 96,700.00 Rp. 156,400.00 Rp. Rp. Rp. 96,000.00 100.00 600.00 6,000.00 4,500.00 35,000.00 4,000.00 49,500.00 Rp. 21,120.00 Rp. 70,620.00 Rp. Rp. 19,800.00 1,320.00 4,200.00 315.00 7,000.00 800.00 12,315.00 Rp. 22,860.00 Rp. 35,175.00 Rp. Rp. 22,500.00 360.00

NO.

URAIAN

HARGA SATUAN

BIAYA UPAH

BIAYA BAHAN

JUMLAH

4 Pasang Langit - langit Plywood 4 mm Rangka Kayu Lanan 0.01200 M3 Kayu Lanan ( Balok ) 0.10000 Kg Paku 0.37500 Lbr Plywood 4 mm 0.03000 Kg Paku 0.22000 Oh Pekerja 0.07850 Oh Mandor 0.35000 Oh Tukang Kayu 0.03500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M2

2,000,000.00 10,000.00 60,000.00 12,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 13,200.00 7,065.00 24,500.00 2,800.00

Rp. Rp. Rp. Rp.

24,000.00 1,000.00 22,500.00 360.00

47,565.00 Rp.

47,860.00 Rp.

95,425.00

5 Pasang Langit - langit Kalsiboard Tb 9 mm + Rangka Kayu Lanan 0.01200 M3 Kayu Lanan ( Balok ) 0.10000 Kg Paku 0.36000 Lbr Kalsiboard 120x240x0,9 cm 0.11000 Kg Paku Sekrup 0.25000 Oh Pekerja 0.12500 Oh Mandor 0.75000 Oh Tukang Kayu 0.07500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M2

2,000,000.00 10,000.00 55,000.00 12,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 15,000.00 11,250.00 52,500.00 6,000.00

Rp. Rp. Rp. Rp.

24,000.00 1,000.00 19,800.00 1,320.00

84,750.00 Rp.

46,120.00 Rp.

130,870.00

6 Pasang Langit - langit Kayu Lanan + Rangka Kayu Lanan 0.01200 M3 Kayu Lanan ( Balok ) 0.11000 Kg Paku 0.02400 M3 Kayu Lanan ( Papan ) 0.05000 Kg Paku Sekrup 0.35000 Oh Pekerja 0.08500 Oh Mandor 0.85000 Oh Tukang Kayu 0.08500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M2

2,000,000.00 10,000.00 4,000,000.00 12,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 21,000.00 7,650.00 59,500.00 6,800.00

Rp. Rp. Rp. Rp.

24,000.00 1,100.00 96,000.00 600.00

94,950.00 Rp.

121,700.00 Rp.

216,650.00

7 Pasang kembali Langit - langit Kayu Lanan + Rangka Kayu Lanan 0.01200 M3 Kayu Lanan ( Balok ) 0.11000 Kg Paku 0.05000 Kg Paku Sekrup 0.35000 Oh Pekerja 0.08500 Oh Mandor 0.85000 Oh Tukang Kayu 0.08500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M2

2,000,000.00 10,000.00 12,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 21,000.00 7,650.00 59,500.00 6,800.00

Rp. Rp. Rp.

24,000.00 1,100.00 600.00

94,950.00 Rp.

25,700.00 Rp.

120,650.00

8 Pasang List Langit - langit Kayu Profil 1.10000 M1 List Kayu Profil 0.01000 Kg Paku 0.50000 Oh Pekerja 0.00300 Oh Mandor 0.05000 Oh Tukang Kayu 0.00500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp.

1 M1 2,000.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 30,000.00 270.00 3,500.00 400.00 34,170.00 Rp. 2,300.00 Rp. 36,470.00 Rp. Rp. 2,200.00 100.00

NO.

URAIAN

HARGA SATUAN

BIAYA UPAH

BIAYA BAHAN

JUMLAH

9 Pasang kawat harmonika 0.00180 M3 papan 1.10000 Kawat harmonika 0.02000 kg paku 0.10000 Pekerja 0.00100 Mandor 0.10000 Tk.kayu 0.01000 Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M2 4,000,000.00 7,500.00 10,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 6,000.00 90.00 7,000.00 800.00 13,890.00 Rp. 15,650.00 Rp. 29,540.00 Rp. Rp. Rp. 7,200.00 8,250.00 200.00

10 Pasang atap seng gelombang BJLS 0,20 0.75000 lbr seng gelombang 0.02000 Kg Paku payung 0.12000 Pekerja 0.00600 Mandor 0.06000 Tk.kayu 0.00600 Kepala tukang Rp. Rp. Rp. Rp. Rp. Rp.

1 M2 37,500.00 15,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 7,200.00 540.00 4,200.00 480.00 12,420.00 Rp. 28,425.00 Rp. 40,845.00 Rp. Rp. 28,125.00 300.00

11 Nok atap seng 0.30000 lbr seng plat 0.04000 kg paku payung 0.15000 Pekerja 0.00600 Mandor 0.05000 Tukang 0.00500 Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp.

1 M' 37,500.00 15,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 9,000.00 540.00 3,500.00 400.00 13,440.00 Rp. 11,850.00 Rp. 25,290.00 Rp. Rp. 11,250.00 600.00

12 Pas.bataco 1 : 4 12.50000 Bj.bataco 0.02700 M3 Pasir 0.15000 Zak semen 0.32000 Oh Pekerja 0.01500 Oh Mandor 0.10000 Oh Tukang Kayu 0.01000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp.

1 M2 2,400.00 340,000.00 46,500.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 19,200.00 1,350.00 7,000.00 800.00 28,350.00 Rp. 46,155.00 Rp. 74,505.00 Rp. Rp. Rp. 30,000.00 9,180.00 6,975.00

0.2700 0.0135 0.4000 0.0400

DAFTAR ANALISA HARGA SATUAN PEKERJAANDAFTAR : HARGA SATUAN PEKERJAAN ( UNIT PRICE )

NO.

URAIAN

SATUAN

UPAH

BAHAN

JUMLAH

XII PEKERJAAN KUNCI DAN KACA 1 Pasang Kunci Tanam Biasa Kualitas Sedang 1.00000 Bh Kunci Tanam 2 Slaag 0.01000 Oh Pekerja 0.00500 Oh Mandor 0.50000 Oh Tukang Kayu 0.01000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. 1 Bh 75,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 2 Pasang Kunci Tanam Biasa Kualitas Baik 1.00000 Bh Kunci Tanam 2 Slaag 0.01000 Oh Pekerja 0.00500 Oh Mandor 0.50000 Oh Tukang Kayu 0.01000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. 1 Bh 75,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 3 Pasang Kunci Tanam Kamar Mandi 1.00000 Bh Kunci Tanam 1 Slaag 0.00500 Oh Pekerja 0.00250 Oh Mandor 0.50000 Oh Tukang Kayu 0.00500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. 1 Bh 100,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 4 Pasang Engsel Pintu 1.00000 Bh Engsel Pintu (kuningan 4") 0.01500 Oh Pekerja 0.00075 Oh Mandor 0.15000 Oh Tukang Kayu 0.01500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. 1 Bh 11,500.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 5 Pasang Engsel Jendela 1.00000 Bh Engsel Jendela 0.01500 Oh Pekerja 0.00075 Oh Mandor 0.15000 Oh Tukang Kayu 0.01500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. 1 Bh 6,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 6 Pasang Kait Angin 1.00000 Bh Kait Angin 0.01500 Oh Pekerja 0.00075 Oh Mandor 0.15000 Oh Tukang Kayu 0.01500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. 1 Bh 2,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 900.00 67.50 10,500.00 1,200.00 12,667.50 Rp. 2,000.00 Rp. 14,667.50 Rp. 2,000.00 900.00 67.50 10,500.00 1,200.00 12,667.50 Rp. 6,000.00 Rp. 18,667.50 Rp. 6,000.00 900.00 67.50 10,500.00 1,200.00 12,667.50 Rp. 11,500.00 Rp. 24,167.50 Rp. 11,500.00 300.00 225.00 35,000.00 400.00 35,925.00 Rp. 100,000.00 Rp. 135,925.00 Rp. 100,000.00 600.00 450.00 35,000.00 800.00 36,850.00 Rp. 75,000.00 Rp. 111,850.00 Rp. 75,000.00 600.00 450.00 35,000.00 800.00 36,850.00 Rp. 75,000.00 Rp. 111,850.00 Rp. 75,000.00

NO.

URAIAN

HARGA SATUAN

BIAYA UPAH

BIAYA BAHAN

JUMLAH

7 Pasang Gerendel 1.00000 Bh Grendel 0.01500 Oh Pekerja 0.00075 Oh Mandor 0.15000 Oh Tukang Kayu 0.01500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp.

1 Bh 11,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 900.00 67.50 10,500.00 1,200.00 12,667.50 Rp. 11,000.00 Rp. 23,667.50 Rp. 11,000.00

8 Pasang Kaca tebal 3 mm 1.10000 M2 Kaca 0.01500 Oh Pekerja 0.00075 Oh Mandor 0.15000 Oh Tukang Kayu 0.01500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp.

1 M2 57,500.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 900.00 67.50 10,500.00 1,200.00 12,667.50 Rp. 63,250.00 Rp. 75,917.50 Rp. 63,250.00

9 Pasang Kaca tebal 5 mm 1.10000 M2 Kaca 0.01500 Oh Pekerja 0.00075 Oh Mandor 0.15000 Oh Tukang Kayu 0.01500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp.

1 M2 71,500.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 900.00 67.50 10,500.00 1,200.00 12,667.50 Rp. 78,650.00 Rp. 91,317.50 Rp. 78,650.00

10 Pasang Kaca one way tebal 5 mm 1.10000 M2 Kaca 0.01500 Oh Pekerja 0.00075 Oh Mandor 0.15000 Oh Tukang Kayu 0.01500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp.

1 M2 95,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 900.00 67.50 10,500.00 1,200.00 12,667.50 Rp. 104,500.00 Rp. 117,167.50 Rp. 104,500.00

DAFTAR ANALISA HARGA SATUAN PEKERJAANDAFTAR : HARGA SATUAN PEKERJAAN ( UNIT PRICE )

NO.

URAIAN

SATUAN

UPAH

BAHAN

JUMLAH

XIII PEKERJAAN PENUTUP LANTAI DAN DINDING 1 Pasang Lantai Keramik Uk. 20 x 20 cm 1.00000 M2 Ubin Keramik Uk. 20 x 20 cm 0.22760 Zak Semen Portland 50 kg 0.04200 M3 Pasir Beton 1.50000 Kg Semen Warna 0.62000 Oh Pekerja 0.03000 Oh Mandor 0.35000 Oh Tukang Batu 0.03500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. 1 M2 40,000.00 46,500.00 340,000.00 2,750.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 2 Pasang Lantai Keramik Uk. 30 x 30 cm 1.00000 M2 Ubin Keramik Uk. 30 x 30 cm 0.22760 Zak Semen Portland 50 kg 0.04200 M3 Pasir Beton 1.50000 Kg Semen Warna 0.62000 Oh Pekerja 0.03000 Oh Mandor 0.35000 Oh Tukang Batu 0.03500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. 1 M2 31,500.00 46,500.00 350,000.00 2,750.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 3 Pasang Dinding Keramik 20 x 20 cm warna 1.00000 M2 Keramik 20 x 20 cm warna 0.18300 Zak Semen Portland 50 kg 0.01800 M3 Pasir Beton 1.50000 Kg Semen Warna 0.60000 Oh Pekerja 0.03000 Oh Mandor 0.10000 Oh Tukang Batu 0.04500 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. 1 M2 45,000.00 46,500.00 350,000.00 2,750.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 4 Pasang Lantai Ubin PC Abu-abu Uk. 30x30 cm 1.06000 M2 Ubin Abu-abu Uk. 30x30 cm 0.20000 Zak Semen Portland 50 kg 0.02150 M3 Pasir Beton 0.26000 Oh Pekerja 0.01300 Oh Mandor 0.12500 Oh Tukang Batu 0.01250 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. 1 M2 25,000.00 46,500.00 350,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 5 Pasang Kawat Kassa 1.10000 M2 Kawat Kassa 0.02000 Kg Paku 0.00180 M3 Kayu Lanan, Papan 0.10000 Oh Pekerja 0.00050 Oh Mandor 0.10000 Oh Tukang Kayu 0.01000 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. 1M2

Rp. Rp. Rp. Rp. 37,200.00 2,700.00 24,500.00 2,800.00 67,200.00 Rp.

40,000.00 10,583.40 14,280.00 4,125.00

68,988.40 Rp.

136,188.40

Rp. Rp. Rp. Rp. 37,200.00 2,700.00 24,500.00 2,800.00 67,200.00 Rp.

31,500.00 10,583.40 14,700.00 4,125.00

60,908.40 Rp.

128,108.40

Rp. Rp. Rp. Rp. 36,000.00 2,700.00 7,000.00 3,600.00 49,300.00 Rp.

45,000.00 8,509.50 6,300.00 4,125.00

63,934.50 Rp.

113,234.50

Rp. Rp. Rp. 15,600.00 1,170.00 8,750.00 1,000.00 26,520.00 Rp.

26,500.00 9,300.00 7,525.00

43,325.00 Rp.

69,845.00

9,000.00 10,000.00 4,000,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 6,000.00 45.00 7,000.00 800.00

Rp. Rp. Rp.

9,900.00 200.00 7,200.00

13,845.00 Rp.

17,300.00 Rp.

31,145.00

DAFTAR ANALISA HARGA SATUAN PEKERJAANDAFTAR : HARGA SATUAN PEKERJAAN ( UNIT PRICE )

NO.

URAIAN

SATUAN

UPAH

BAHAN

JUMLAH

XIV PEKERJAAN CAT - CATAN 1 Mendempul dan Menggosok Kayu 0.08000 Kg Dempul Jadi 0.02000 Kg Minyak Cat 0.20000 Lbr Ampelas 0.04000 Oh Pekerja 0.00250 Oh Mandor 0.04000 Oh Tukang Cat 0.00400 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. 1 M2 10,000.00 7,500.00 2,000.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 2 Pengecatan Bidang Kayu Baru ( 1 Lapis Plamir 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup ) 0.20000 Kg Cat Meni 0.15000 Kg Plamir 0.17000 Kg Cat Dasar 0.26000 Kg Cat Penutup 2 Kali 0.07000 Oh Pekerja 0.00250 Oh Mandor 0.09000 Oh Tukang Cat 0.00600 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. 10,000.00 7,000.00 10,000.00 34,500.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 3 Pengecatan Bidang Kayu Baru ( 1 Lapis Plamir 1 Lapis Cat Dasar dan 3 Lapis Cat Penutup ) 0.20000 Kg Cat Meni 0.15000 Kg Plamir 0.17000 Kg Cat Dasar 0.35000 Kg Cat Penutup 3 Kali 0.07000 Oh Pekerja 0.00250 Oh Mandor 0.10500 Oh Tukang Cat 0.00400 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp. 10,000.00 7,000.00 10,000.00 34,500.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 4 Pelaburan Bidang Kayu dengan Cat Residu dan Ter 0.35000 Ltr Residu atau Ter 0.10000 Oh Pekerja 0.00600 Oh Mandor Rp. Rp. Rp. 1 M2 2,500.00 60,000.00 Rp. 90,000.00 Rp. Rp. 5 Pengecatan Tembok Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup ) 0.10000 Kg Plamir 0.10000 Kg Cat Dasar 0.26000 Kg Cat Penutup 2 Kali 0.02000 Oh Pekerja 0.00250 Oh Mandor 0.06300 Oh Tukang Cat 0.00630 Oh Kepala Tukang Rp. Rp. Rp. Rp. Rp. Rp. Rp. 7,000.00 10,000.00 13,800.00 60,000.00 Rp. 90,000.00 Rp. 70,000.00 Rp. 80,000.00 Rp. Rp. 1,200.00 225.00 4,410.00 504.00 6,339.00 Rp. 5,288.00 Rp. 11,627.00 Rp. Rp. Rp. 700.00 1,000.00 3,588.00 1 M2 6,000.00 540.00 6,540.00 Rp. 875.00 Rp. 7,415.00 Rp. 875.00 4,200.00 225.00 7,350.00 320.00 12,095.00 Rp. 16,825.00 Rp. 28,920.00 Rp. Rp. Rp. Rp. 2,000.00 1,050.00 1,700.00 12,075.00 1 M2 4,200.00 225.00 6,300.00 480.00 11,205.00 Rp. 13,720.00 Rp. 24,925.00 Rp. Rp. Rp. Rp. 2,000.00 1,050.00 1,700.00 8,970.00 1M2

Rp. Rp. Rp. 2,400.00 225.00 2,800.00 320.00 5,745.00 Rp.

800.00 150.00 400.00

1,350.00 Rp.

7,095.00

REKAPITULASI BIAYAKEGIATAN PEKERJAAN

: :

PENATAAN LINGKUNGAN PEMUKIMAN PENDUDUK PEDESAAN PEMBANGUNAN LINGKUNGAN PERMUKIMAN RUMAH ADAT MASYARAKAT PAL.13 PARAMASAN

NO I II III IV V VI VII VIII PEKERJAAN PERSIAPAN

URAIAN Rp. Rp. Rp. Rp. Rp. Rp. Rp. Rp.

SUB TOTAL 1,347,000.0 -

PEKERJAAN TANAH DAN PONDASI PEKERJAAN DINDING DAN LANTAI PEKERJAAN PINTU DAN JENDELA PEKERJAAN ATAP DAN PLAFOND PEKERJAAN KUNCI / ALAT PENGGANTUNG PEKERJAAN CAT - CATAN PEKERJAAN INSTALASI LISTRIK

JUMLAH PPn 10% IMB 1% TOTAL DIBULATKAN

Rp. Rp. Rp. Rp. Rp.

1,347,000.0 134,700.0 13,470.0 1,495,170.0 1,495,000.0

Terbilang

: Tiga Ratus Lima Puluh Juta Rupiah

Martapura, ,200.. PT. TATA BANJARAN LESTARI

MAKHYAR DIANA ANDITA Direktris

350,000,000.00 348,505,000.00

RENCANA ANGGARAN BIAYAKEGIATAN PEKERJAAN

: : URAIAN PEKERJAAN ANALIS NOMOR VOLUMEHARGA SATUAN (Rp) JUMLAH HARGA (Rp)

NO.

I 1 2 3

PEKERJAAN PERSIAPAN Pembersihan lokasi Pembongkaran Pengukuran dan bowplank I I 2 1 36.00 m2 0.00 ls 24.00 m1 6,450.00 6,750,000.00 46,450.00 Sub Total 232,200.00 1,114,800.00 1,347,000.00

II 1 2 3 4 5 6 7

PEKERJAAN TANAH DAN PONDASI Galian tanah pondasi Urugan tanah kembali Urugan pasir bawah pondasi tebal 10 cm Rabat beton bawah pondasi Pondasi poer 60 x 60 cm Beton bertulang kolom 20/20 camp. 1:2:3 (230 kg) Beton bertulang sloof 15/20 camp. 1:2:3 (280 kg) II II II VII VII VII VII 1 2 4 1 14 16 15 m3 m3 m3 m3 m3 m3 m3 27,600.00 13,230.00 258,900.00 745,340.00 2,842,660.00 5,219,940.00 4,294,580.00 Sub Total -

III 1 2 3 4 5 6 7 8 9 10

PEKERJAAN DINDING DAN LANTAI Tongkat ulin 6/12 Rangka bawah ulin 6/12 (gelagar ulin) Rangka badan ulin 6/12 (kolom+ringbalk) Pekerjaan lantai papan ulin 2/20 Pemasangan kawat kasa lantai Rabat beton lantai tbl. 5 cm Keramik lantai 30/30 Pekerjaan dinding papan lanan 2/20 Pekerjaan tawing layar papan lanan 2/20 Pembuatan tangga naik kayu ulin (4 buah) VI VI VI VI XIII VII XIII VI VI 13 13 14 16 5 1 2 17 17 m3 m3 m3 m2 m2 m3 m2 m2 m2 ls 6,992,500.00 6,992,500.00 8,216,500.00 190,100.00 31,145.00 745,340.00 128,108.40 158,075.00 158,075.00 2,600,000.00 Sub Total -

IV 1 2 3 4 5

PEKERJAAN PINTU DAN JENDELA Balok malang 5/10 ulin Jalusi papan lanan 1.5/13 Pintu panil papan lanan (P1) Pintu panil papan lanan (P2) Daun jendela lanan + kaca tbl. 5 mm VI 14 m3 m2 bh bh bh 8,216,500.00 45,000.00 350,000.00 350,000.00 190,000.00 Sub Total -

V 1 2 3 4 5 6 7 8 9 10

PEKERJAAN ATAP DAN PLAFOND Kuda-kuda Lanan Gording 6/12, suai 5/10 dan nok 6/12 kayu lanan Atap metal Sakura Pemu'ung Kasau reng lanan Plafond kalsiboard 9 mm + rangka List plafon profil Plafond kisi-kisi lanan Jamaang Ulin List plank ulin 2 x 2/20 VI VI VIII VIII VI IX IX IX VI 3 4 1 2 5 5 8 6 6 m3 m3 m2 m1 m2 m2 m1 m2 bh m1 3,589,500.00 2,928,300.00 71,625.00 46,445.00 43,750.00 130,870.00 36,470.00 216,650.00 500,000.00 71,700.00 Sub Total -

VI 1 2 3 4 5 6 7 8 9

PEKERJAAN KUNCI / ALAT PENGGANTUNG Engsel pintu Engsel jendela Kait angin jendela Kunci pintu tanam 2 slaag Pegangan pintu Pegangan jendela Gerendel jendela Gerendel pintu Espagnolette XII XII XII XII XII XII 4 5 6 2 7 7 bh bh bh bh bh bh bh bh bh 24,167.50 18,667.50 14,667.50 111,850.00 135,000.00 19,500.00 23,667.50 23,667.50 42,700.00 Sub Total -

NO.VII 1 2

URAIAN PEKERJAANPEKERJAAN CAT - CATAN Ter-teran Cat tembok+plamir pada : * Dinding * Plafond + list plafond

ANALIS NOMOR

VOLUME

HARGA SATUAN (Rp)

JUMLAH HARGA (Rp)

XIV XIV XIV XIV XIV 5 5 3 3 3

ls m2 m2 m2 m2 m2

1,000,000.00 11,627.00 11,627.00 28,920.00 28,920.00 28,920.00 Sub Total

-

3

Cat minyak pada : * Kusen + ventilasi + pintu + jendela * Plafond kisi-kisi * List Plank Ulin

VIII PEKERJAAN INSTALASI LISTRIK 1 2 3 4 5 6 7 Titik lampu Lampu TL 40 watt Lampu SL. 18 watt (setara philips) Stop kontak MCB Box + Pemasangan instalasi Saklar ganda Saklar tunggal ttk bh bh bh set bh bh 115,000.00 90,000.00 50,000.00 15,000.00 1,500,000.00 17,250.00 17,250.00 Sub Total -