rab margorejo
TRANSCRIPT
DAFTAR HARGA SATUAN UPAH, BAHAN DAN ALAT
DESA : MARGO REJOKECAMATAN : TEGINENENGKABUPATEN : PESAWARANPROPINSI : LAMPUNGPROGRAM : RIS-PNPMTAHUN ANGGARAN : 2011
NO. URAIAN SATUAN
HARGA SATUAN (Rp.)
KETERANGAN Hasil Survey
Supl. I Supl. II Supl. III
I UPAH1 Tukang HOK 54,500.00 53,500.00 52,000.00 52,000.00 2 Kepala Tukang HOK 57,500.00 56,500.00 55,000.00 55,000.00 3 Pekerja HOK 41,000.00 40,000.00 38,500.00 38,500.00 4 Mandor HOK 61,000.00 60,000.00 58,500.00 58,500.00
5 Operator Terampil HOK 54,500.00 53,500.00 52,000.00 52,000.00
II BAHAN
1 Batu Belah M3 117,500.00 116,500.00 115,000.00 115,000.00
2 Semen PC Kg 1,250.00 1,350.00 1,200.00 1,200.00 3 Pasir Beton M3 162,500.00 161,500.00 160,000.00 160,000.00 4 Pasir Pasang M3 157,500.00 156,500.00 155,000.00 155,000.00 5 Pasir Urug M3 99,500.00 98,500.00 97,000.00 97,000.00 6 Batu Pecah 15 - 20 cm M3 117,500.00 116,500.00 115,000.00 115,000.00 7 Batu Pecah 10 - 15 cm M3 146,500.00 145,500.00 144,000.00 144,000.00 8 Batu Pecah 5 - 7 cm M3 156,500.00 155,500.00 154,000.00 154,000.00 9 Batu 1 - 2 cm M3 262,500.00 261,500.00 260,000.00 260,000.00 9 Besi Beton Kg 16,500.00 15,500.00 14,000.00 14,000.00 10 Kawat Ikat Kg 15,500.00 14,500.00 13,000.00 13,000.00 11 Paku Kg 17,500.00 16,500.00 15,000.00 15,000.00 12 Kayu Klas III M3 1,425,000.00 1,415,000.00 1,400,000.00 1,400,000.00
III ALAT1 Mesin Gilas 3 Roda 6-8 T Jam 127,500.00 126,500.00 125,000.00 125,000.00 2 Alat Bantu Set 102,500.00 101,500.00 100,000.00 100,000.00
DIVERIFIKASI OLEH: DIPERIKSA OLEH : DIBUAT OLEH ; TAMK OMS
JANTUAHMAN SARAGIH ST RUDY SARMANTO ST PONIDI
Realisasi Pelaksanaan
A N A L I S A B I A Y A P E K E R J A A N K O D E
KONSTRUKSI LAPIS PONDASI ATAS ( L P B ) TELFORD K 516( MENGGUNAKAN BURUH )
PROPINSI KODE KABUPATEN KODE DISIAPKAN OLEH TAHUN
2011
PROSES : ANGGAPAN / ASUMSI :1. Material disiapkan di lokasi pekerjaan. 1. Menggunakan tenaga manusia 400 m2/hari2. Menghampar pasir setebal 5 cm. 2. Material dikirim ke lokasi pekerjaan oleh supplier.3. Batu pecah berukuran besar ( 10-15 cm ) 3. Material sudah di pecah/batu pecah. disusun berdiri. 4. Tanah Dasar sudah dipersiapkan.4. Batu pecah yang lebih kecil mengisi 5. Dipadatkan sampai tebal 15 cm rongga-rongga diatasnya kemudian dipadatkan/digilas mesin gilas
P E K E R J A VOL HARI KODE JUMLAH UPAH BIAYA SUB.TOTAL
HARI-ORANG (Rp./org/hr) ( Rp. ) ( Rp. )
P Mandor Lapangan 3 1 3.00 58,500.00 175,500.00 E Operator Terlatih 1 1 1.00 52,000.00 52,000.00 K Pekerja 99 1 99.00 38,500.00 3,811,500.00 E R J A
PEKERJA 4,039,000.00
M A T E R I A L JUMLAH VOLUME KODE HARGA BIAYA SUB.TOTAL
SATUAN Rp./Unit ( Rp. ) ( Rp. )
M Batu Pecah 10 - 15 cm 50 m3 144,000.00 7,200,000.00 A Batu Pecah 5 - 7 cm 20 m3 154,000.00 3,080,000.00 T Pasir Urug 30 m3 97,000.00 2,910,000.00 E Alat bantu 4 set 100,000.00 400,000.00 R I A L
MATERIAL 13,590,000.00
P E R A L A T A N JUMLAH HARI KODE JAM HARGA BIAYA SUB.TOTAL
ALAT KERJA KERJA (Rp./JAM) ( Rp. ) ( Rp. )
P E Mesin Gilas 6 - 8 T 1 1 5 125,000.00 625,000.00 R A L A T A N
PERALATAN 625,000.00 TOTAL (Rp.) 18,254,000.00
VOLUME : 60 SATUAN : m3304,233.33
HARGA SATUAN Rp. 304,233.33 per m3
DIREKTORAT JENDRAL BINA MARGA DIREKTORAT BNA PROGRAM
JALAN SUB DIT. PERENCANAAN JALAN LOKAL &
KABUPATEN
A N A L I S A H A R G A S A T U A N KODE
PENGUPASAN TANAH DAN PEMBERSIHAN BADAN JALAN(MENGGUNAKAN BURUH) K - 210
PROPINSI LAMPUNG KODE KABUPATEN KODE DISIAPKAN OLEH : Tahun2011
URAIAN ANGGAPAN / ASUMSI 1. Mengupas dan membuang semak 1. Menggunakan tenaga manusia ( 1200 m2 / hari = 12 Are / hari )
dengan tenaga manusia pada DAMIJA 2. Tidak ada pohon besar pada DAMIJA (Hanya Semak)( Daerah Milik Jalan ) 3. DAMIJA 12 m
2. Lebar pengupasan dan pembersihan = 4. Pembersihan DAMIJA 100m per hariDAMIJA minus lebar badan jalan 5. Bakar sampah dilokasi pekerjaan
6. Hasil kerja 25 m2/orang/hari 7. Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat
PEKERJA JUMLAH HARI KODE TOTAL VOL UPAH BIAYA SUB TOTALORANG (Orang-hari) (Rp/Org/Hari) (Rp) (Rp)
P Pekerja 48 1 48.00 38,500.00 1,848,000.00E Mandor 1 1 1.00 58,500.00 58,500.00KERJA
JUMLAH BIAYA UNTUK PEKERJA PEKERJA (I+II) 1,906,500.00MATERIAL SATUAN KODE TOTAL VOL HARGA SATUAN BIAYA SUB TOTAL
(Rp) (Rp) (Rp)
M Alat Bantu @ 3 alat Ls 1.92 100,000.00 192,000.00ATERIAL
JUMLAH BIAYA UNTUK MATERIAL MATERIAL (I+II) 192,000.00PERALATAN JUMLAH HARI KODE JAM KERJA HARGA BIAYA SUB TOTAL
ALAT KERJA (Rp/Jam) (Rp) (Rp)
PERALATAN
JUMLAH BIAYA UNTUK PERALATAN PERALATAN (I+II) 0.00 T O T A L (Rp) 2,098,500.00
VOLUME : 1,200.00 SATUAN : m2 HARGA SATUAN : 1,748.75 per m2
A N A L I S A H A R G A S A T U A N KODE
GALIAN TANAH UNTUK PEMBENTUKAN DRAINASE(MENGGUNAKAN BURUH) K - 224
PROPINSI LAMPUNG KODE KABUPATEN KODE DISIAPKAN OLEH : Tahun2011
URAIAN ANGGAPAN / ASUMSI 1. Digali dengan tenaga masnusia 1. Menggunakan Tenaga Manusia (40m3/hari) 2. Membuang tanah galian sejauh 30 meter 2. Kapasitas Kerja /orang 1,3 m3/hari
dari lubang galian 3. Kedalaman rata-rata galian sampai dengan 3,00 meter 4. Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat
PEKERJA JUMLAH HARI KODE TOTAL VOL UPAH BIAYA SUB TOTALORANG (Orang hari) (Rp/Org/Hari) (Rp) (Rp)
P Buruh tak terampil 30 1 30.00 38,500.00 1,155,000.00E Mandor 1 1 1.00 58,500.00 58,500.00KERJA
JUMLAH BIAYA UNTUK PEKERJA PEKERJA (I+II) 1,213,500.00MATERIAL JUMLAH SATUAN KODE TOTAL VOL HARGA SATUAN BIAYA SUB TOTAL
MATERIAL (Rp) (Rp) (Rp)
M Alat bantu (set @ 3 set) Set 1.20 100,000.00 120,000.00ATERIAL
JUMLAH BIAYA UNTUK MATERIAL MATERIAL (I+II) 120,000.00PERALATAN JUMLAH HARI KODE JAM KERJA HARGA BIAYA SUB TOTAL
ALAT KERJA (Rp/Jam) (Rp) (Rp)
PERALATAN
JUMLAH BIAYA UNTUK PERALATAN PERALATAN (I+II) 0.00 T O T A L (Rp) 1,333,500.00
VOLUME : 40.00 SATUAN : M 3 HARGA SATUAN : 33,337.50 per M 3
A N A L I S A H A R G A S A T U A N KODE
KONSTRUKSI PASANGAN BATU HITAM(MENGGUNAKAN BURUH) K - 705
PROPINSI LAMPUNG KODE KABUPATEN KODE DISIAPKAN OLEH : Tahun2011
URAIAN ANGGAPAN / ASUMSI 1. Material disiapkan ke lokasi oleh pekerjaan oleh 1. Dilakukan untuk pekerjaan gorong-gorong, jembatan, dinding penahan tanah
Pemasok dan struktur lainnya, yang menggunakan konstruksi pasangan batu 2. Pekerja membawa batu belah ketempat 2. Material-material dikirim ketempat pekerjaan oleh pemasok
tukang batu bekerja 3. Tidak termasuk galian/Timbunan 3. Tukang batu memasang batu belah dengan 4. Biaya alat bantu tambahan sudah termasuk biaya kira-kira ekivalen dari
adukan pasir dan semen. bambu untuk lubang drainase
PEKERJA JUMLAH HARI KODE TOTAL VOL UPAH BIAYA SUB TOTALORANG (Orang hari) (Rp/Org/Hari) (Rp) (Rp)
P Buruh tak terampil 12 1 12.00 38,500.00 462,000.00E Kepala Tukang 1 1 1.00 55,000.00 55,000.00K Tukang Batu 4 1 4.00 52,000.00 208,000.00ERJA
JUMLAH BIAYA UNTUK PEKERJA PEKERJA (I+II) 725,000.00MATERIAL JUMLAH SATUAN KODE TOTAL VOL HARGA SATUAN BIAYA SUB TOTAL
MATERIAL (Rp) (Rp) (Rp)
M Batu Belah Hitam M3 5.00 115,000.00 575,000.00A Pasir ayak untuk beton M3 1.25 155,000.00 193,750.00T Semen 50 kg 15.20 1,200.00 18,240.00E Alat Bantu (set @ 3 alat) Set 0.75 100,000.00 75,000.00RIAL
JUMLAH BIAYA UNTUK MATERIAL MATERIAL (I+II) 861,990.00PERALATAN JUMLAH HARI KODE JAM KERJA HARGA BIAYA SUB TOTAL
ALAT KERJA (Rp/Jam) (Rp) (Rp)
P Pompa air diameter 5 cm/ 30 m3 perjam 1 1 2.00ERALATAN
JUMLAH BIAYA UNTUK PERALATAN PERALATAN (I+II) T O T A L (Rp) 1,586,990.00
VOLUME : 5.00 SATUAN : M 3 HARGA SATUAN : 317,398.00 per M 3
RENCANA JADWAL PELAKSANAAN DAN KURVA-SPROPINSI : LAMPUNG Program : RIS-PNPM KABUPATEN : PESAWARAN Jenis Kegiatan : 1. PEKERJAAN PERKERASAN JALAN TELFORD KECAMATAN : TEGINENENG - 2. PEKERJAAN GORONG-GORONG PLAT DESA : MARGO REJO Ukuran/Dimensi : 1. Telford ( 1615 M x 3 M )
2. Gorong2 Plat (Uk 0,8 x 0,8 M) P. 4 M ( 3 Buah)
No. Uraian Kegiatan Volume SatuanHarga Satuan Jumlah Harga Bobot
Jangka Waktu Pelaksanaan Pekerjaan Bulan 1 Bulan 2 Bulan 3 Bulan 4
1 2 3 4 5 6 7 8 9 10 11 12 13 14
(Rp.) (Rp.) %
I BIAYA OPERASIONAL OMS
1 Pengukuran dan Pematokan 1.000 Ls 500,000.00 500,000.00 0.193 0.097 0.097 100
2 ATK dan Pelaporan 1.000 Ls 3,500,000.00 3,500,000.00 1.354 0.226 0.226 0.226 0.226 0.226 0.226
3 Transportasi OMS 1.000 Ls 1,000,000.00 1,000,000.00 0.387 0.097 0.097 0.097 0.097
II PEKERJAAN PEMBERSIHAN DAN PEKERJAAN TANAH
1 Pengupasan Tanah dan Pembersihan Badan Jalan 4,835.000 M2 1,748.75 8,455,206.25 3.271 1.090 1.090 1.090
III PEKERJAAN PERKERASAN JALAN
1 Lapis Pondasi Bawah (LPB) / Telford 726.751 M3 304,233.33 221,101,848.81 85.547 8.555 8.555 8.555 8.555 8.555 8.555 8.555 8.555 8.555 8.555
50IV PEKERJAAN PASANGAN
Pas. Gorong2 Plat ( uk 0,8 x 0,8 m ) P 5 m. 3 buah
1 Pas. Batu Belah Hitam 8.230 M3 519,462.50 4,275,176.38 1.654 0.551 0.551 0.551
2 Pembuatan Plat Beton
( P = 5 M; L = 1,4 M ; T = 0,20 M )
- Plat Beton bertulang 3.360 M3 4,383,742.50 14,729,374.80 5.699 2.849 2.849
3 - Plesteran 31.440 M2 28,430.50 893,854.92 0.346 0.043 0.043 0.043 0.043 0.043 0.043 0.043 0.043
V PEKERJAAN LAIN-LAIN
1 Mobilisasi dan Demobilisasi Alat Berat 1.000 Ls 3,000,000.00 3,000,000.00 1.161 0.580 0.580
2 Prasasti 5.000 Bh 200,000.00 1,000,000.00 0.387 0.387 0
JUMLAH 258,455,461.15 100.00
SUMBER DANA DANA BLM RIS-PNPM 250,000,000.00
DANA SWADAYA 8,455,000.00
RENCANA FISIKBOBOT/MINGGU ( % ) 1.510 1.510 1.090 8.555 9.106 9.149 12.225 11.673 8.695 8.695 8.824 9.404 8.598 0.967
BOBOT KUMULATIF ( % ) - 1.510 3.019 4.110 12.664 21.771 30.920 43.144 54.818 63.512 72.207 81.031 90.435 99.033 100.00
REALISASIBOBOT/MINGGU ( % ) - - - - - - - - - - - - - -
BOBOT KUMULATIF ( % ) - - - - - - - - - - - - - - -
DEVIASI ( % )
Diperiksa Oleh: Dibuat Oleh : Fasilitator OMS Kader Desa
RUDY SARMANTO.ST PONIDI PAIMAN
Ket. ( % )
A.1.P
REKAPITULASIRENCANA ANGGARAN BIAYA
PROPINSI : LAMPUNGKABUPATEN : PESAWARAN Program : RIS-PNPM KECAMATAN : TEGINENENG Jenis Kegiatan : 1. PEKERJAAN PERKERASAN JALAN TELFORD DESA : MARGO REJO 2. PEKERJAAN GORONG-GORONG PLAT
Ukuran/Dimensi : 1. Telford ( 1615 M x 3 M ) 2. Gorong2 Plat (Uk 0,8 x 0,8 M) P. 4 M ( 3 Buah)
NO URAIAN PEKERJAAN JUMLAH HARGA
I. BIAYA OPERASIONAL OMS Rp. 5,000,000.00
II. PEKERJAAN PEMBERSIHAN DAN PEKERJAAN TANAH Rp. 8,455,206.25
III. PEKERJAAN PERKERASAN JALAN Rp. 221,101,848.81
IV. PEKERJAAN PASANGAN Rp. 19,898,406.10
V. PEKERJAAN LAIN-LAIN Rp. 4,000,000.00
JUMLAH Rp. 258,455,461.15
DIBULATKAN Rp. 258,455,000.00
SUMBER DANA DANA BLM RIS PNPM Rp. 250,000,000.00
DANA SWADAYA Rp. 8,455,000.00
DIPERIKSA OLEH: DIBUAT OLEH : FASILITATOR KETUA OMS KADER DESA
RUDY SARMANTO. ST PONIDI PAIMAN
MENGETAHUI : TAMK
JANTUAHMAN SARAGIH ST
A.1.P
RENCANA ANGGARAN BIAYA
PROPINSI : LAMPUNGKABUPATEN : PESAWARAN Program : RIS-PNPM KECAMATAN : TEGINENENG Jenis Kegiatan : 1. PEKERJAAN PERKERASAN JALAN TELFORD DESA : MARGO REJO 2. PEKERJAAN GORONG-GORONG PLAT
Ukuran/Dimensi : 1. Telford ( 1615 M x 3 M ) 2. Gorong2 Plat (Uk 0,8 x 0,8 M) P. 4 M ( 3 Buah)
VOLUME HARGA JUMLAHNo. URAIAN PEKERJAAN
TOTAL DARI SWADAYA SATUAN SATUAN HARGA
(Rp) (Rp)
I. BIAYA OPERASIONAL OMS1 Pengukuran dan Pematokan 1.00 1.00 Ls 500,000.00 500,000.00 2 ATK dan Pelaporan 1.00 1.00 Ls 3,500,000.00 3,500,000.00 3 Transportasi OMS 1.00 1.00 Ls 1,000,000.00 1,000,000.00
SUB TOTAL I. 5,000,000.00
II. PEKERJAAN PEMBERSIHAN DAN PEKERJAAN TANAH1 Pengupasan Tanah dan Pembersihan Badan Jalan K 210 4835.00 4835.00 M2 1,748.75 8,455,206.25
SUB TOTAL II. 8,455,206.25
III. PEKERJAAN PERKERASAN JALAN
1 Lapis Pondasi Bawah (LPB) / Telford K 516 726.75 726.75 M3 304,233.33 221,101,848.81
SUB TOTAL III. 221,101,848.81
IV. PEKERJAAN PASANGAN
Pas. Gorong2 Plat ( uk 0,8 x 0,8 m ) P 5 m. 3 buah1 Pas. Batu Belah Hitam C.4 8.23 8.23 M3 519,462.50 4,275,176.38 2 Pembuatan Plat Beton
( P = 5 M; L = 1,4 M ; T = 0,20 M ) - Plat Beton bertulang G,29 3.36 3.36 M3 4,383,742.50 14,729,374.80
3 Plesteran E.27 31.44 31.44 M2 28,430.50 893,854.92
SUB TOTAL IV. 19,898,406.10
V. PEKERJAAN LAIN-LAIN1 Mobilisasi dan Demobilisasi Alat Berat 1.00 1.00 Ls 3,000,000.00 3,000,000.00 2 Prasasti 5.00 5.00 Bh 200,000.00 1,000,000.00
SUB TOTAL V. 4,000,000.00
TOTAL BIAYA 258,455,461.15
DIBULATKAN 258,455,000.00
SUMBER DANA DANA BLM RIS-PNPM 250,000,000.00
DANA SWADAYA 8,455,000.00
DIPERIKSA OLEH: DIBUAT OLEH : FASILITATOR KETUA OMS KADER DESA
RUDY SARMANTO. ST PONIDI PAIMAN
DARI DANA BLM
REKAPITULASI RENCANA ANGGARAN BIAYA
SWADAYA MASYARAKAT
Propinsi : Lampung
Kabupaten : Pesawaran Program : RIS-PNPM
Kecamatan : Tegineneng
Desa : Margo Rejo
Pekerjaan : Pembersihan dan Pengupasan Tanah
Lokasi : Dusun V
NO. URAIAN
VOLUME HARGA SATUAN JUMLAH HARGA
VOLUME SATUAN (Rp.) (Rp.)
I BAHAN
-
SUB TOTAL I -
II UPAH
1 Pekerja 193.40 HOK 38,500.00 7,445,900.00
2 Mandor 4.03 HOK 58,500.00 235,706.25
SUB TOTAL II 7,681,606.25
III ALAT
1 Alat bantu 7.74 Set 100,000.00 773,600.00
SUB TOTAL III 773,600.00
TOTAL BIAYA 8,455,206.25
DIPERIKSA OLEH: DIBUAT OLEH:
FASILITATOR KETUA OMS KADER DESA
RUDY SARMANTO.ST PONIDI PAIMAN
RENCANA ANGGARAN BIAYA
SWADAYA MASYARAKAT
Propinsi : Lampung No. RAB :
Kabupaten : Pesawaran Program : RIS-PNPM
Kecamatan : Tegineneng
Desa : Margo Rejo
Pekerjaan : Pengupasan Tanah dan Pembersihan Badan Jalan 4,835.00 M2
Lokasi : Dusun V
NO. URAIAN
VOLUME HARGA SATUAN JUMLAH HARGA
VOLUME SATUAN (Rp.) (Rp.)
I BAHAN
-
SUB TOTAL I -
II UPAH
1 Pekerja 193.40 HOK 38,500.00 7,445,900.00
2 Mandor 4.03 HOK 58,500.00 235,706.25
SUB TOTAL II 7,681,606.25
III ALAT
1 Alat bantu 7.74 Set 100,000.00 773,600.00
SUB TOTAL III 773,600.00
TOTAL BIAYA 8,455,206.25
DIPERIKSA OLEH: DIBUAT OLEH:
FASILITATOR KETUA OMS KADER DESA
RUDY SARMANTO.ST PONIDI PAIMAN
REKAPITULASI RENCANA ANGGARAN BIAYA
BANTUAN LANGSUNG MASYARAKAT (BLM)
Propinsi : Lampung
Kabupaten : Pesawaran Program : RIS-PNPM
Kecamatan : Tegineneng
Desa : Margo Rejo
Pekerjaan : Perkerasan Jalan Telford dan Gorong2 Plat
Lokasi : Dusun V
NO. URAIAN
VOLUME HARGA SATUAN JUMLAH HARGA
VOLUME SATUAN (Rp.) (Rp.)
A. BIAYA OPERASIONAL OMS
1 Pengukuran Pematokan 1.00 Ls 500,000.00 500,000.00
2 ATK dan Pelaporan 1.00 Ls 3,500,000.00 3,500,000.00
3 Transportasi OMS 1.00 Ls 1,000,000.00 1,000,000.00
SUB TOTAL 5,000,000.00
B. PEKERJAAN PERKERASAN JALAN
I BAHAN
1 Batu belah 10 - 15 cm 606.00 M3 144,000.00 87,264,000.00
2 Batu pecah 5 - 7 cm 242.00 M3 154,000.00 37,268,000.00
3 Pasir Urug / Timbun 363.00 M3 97,000.00 35,211,000.00
4 Alat bantu 49.00 Set 100,000.00 4,900,000.00
SUB TOTAL 164,643,000.00
II UPAH
1 Pekerja 1,199.00 HOK 38,500.00 46,161,500.00
2 Mandor 36.00 HOK 58,500.00 2,106,000.00
3 Operator terlatih 12.00 HOK 52,000.00 624,000.00
SUB TOTAL 48,891,500.00
III ALAT
1 Mesin Gilas 3 Roda 6 - 8 ton 61.00 Jam 125,000.00 7,625,000.00
7,625,000.00
C. PEKERJAAN PASANGAN GORONG-GORONG PLAT
I BAHAN
1 Pasir pasang 5.00 M3 155,000.00 775,000.00
2 Pasir Beton 2.00 M3 160,000.00 320,000.00
3 Semen 2,640.00 Kg 1,200.00 3,168,000.00
4 Batu belah hitam 10.00 M3 115,000.00 1,150,000.00
5 Kawat Ikat 8.00 Kg 13,000.00 104,000.00
6 Paku 11.00 Kg 15,000.00 165,000.00
7 Kayu Klas III 1.00 M3 1,400,000.00 1,400,000.00
8 Batu pecah 1 - 2 cm 3.00 M3 260,000.00 780,000.00
9 Baja Tulangan 504.00 Kg 14,000.00 7,056,000.00
SUB TOTAL 14,918,000.00
II UPAH
1 Mandor 2.00 HOK 58,500.00 117,000.00
2 Kepala tukang 9.00 HOK 55,000.00 495,000.00
3 Pekerja 62.00 HOK 38,500.00 2,387,000.00
4 Tukang batu 37.00 HOK 52,000.00 1,924,000.00
SUB TOTAL 4,923,000.00
III ALAT
1 Alat bantu - Set 100,000.00 -
SUB TOTAL -
D PEKERJAAN LAIN-LAIN
1 Mobilisasi dan Demobilisasi Alat Berat 1.00 Ls 3,000,000.00 3,000,000.00
2 Prasasti 5.00 Bh 200,000.00 1,000,000.00
SUB TOTAL 4,000,000.00
TOTAL BIAYA 250,000,000.00
DIPERIKSA OLEH: DIBUAT OLEH:
FASILITATOR KETUA OMS KADER DESA
RUDY SARMANTO.ST PONIDI PAIMAN
RENCANA PENGGUNAAN DANA IBANTUAN LANGSUNG MASYARAKAT (BLM)
Propinsi : Lampung
Kabupaten : Pesawaran Program : RIS-PNPM
Kecamatan : Tegineneng
Desa : Margo Rejo
Pekerjaan : Perkerasan Jalan Telford dan Gorong2 Plat
Lokasi : Dusun V
NO. URAIAN
VOLUME HARGA SATUAN JUMLAH HARGA
VOLUME SATUAN (Rp.) (Rp.)
A. BIAYA OPERASIONAL OMS
1 Pengukuran Pematokan 0.40 Ls 500,000.00 200,000.00
2 ATK dan Pelaporan 0.40 Ls 3,500,000.00 1,400,000.00
3 Transportasi OMS 0.40 Ls 1,000,000.00 400,000.00
SUB TOTAL 2,000,000.00
B. PEKERJAAN PERKERASAN JALAN TELFORD
I BAHAN
1 Batu belah 10 - 15 cm 242.00 M3 144,000.00 34,848,000.00
2 Batu pecah 5 - 7 cm 52.00 M3 154,000.00 8,008,000.00
3 Pasir Urug / Timbun 145.00 M3 97,000.00 14,065,000.00
4 Alat bantu 19.00 Set 100,000.00 1,900,000.00
SUB TOTAL 58,821,000.00
II UPAH
1 Pekerja 481.00 HOK 38,500.00 18,518,500.00
2 Mandor 15.00 HOK 58,500.00 877,500.00
3 Operator terlatih - HOK 52,000.00 -
SUB TOTAL 19,396,000.00
III ALAT
1 Roller 3 wheel 6 - 8 ton - Jam 125,000.00 -
SUB TOTAL -
C. PEKERJAAN PASANGAN GORONG-GORONG PLAT
I BAHAN
1 Pasir pasang 5.00 M3 155,000.00 775,000.00
2 Pasir beton 2.00 M3 160,000.00 320,000.00
3 Semen 2,600.00 Kg 1,200.00 3,120,000.00
4 Batu belah hitam 10.00 M3 115,000.00 1,150,000.00
5 Kawat Ikat 8.00 Kg 13,000.00 104,000.00
6 Paku 11.00 Kg 15,000.00 165,000.00
7 Kayu Klas III 1.00 M3 1,400,000.00 1,400,000.00
8 Batu pecah 1 - 2 cm 3.00 M3 260,000.00 780,000.00
9 Baja Tulangan 504.00 Kg 14,000.00 7,056,000.00
SUB TOTAL 14,870,000.00
II UPAH
1 Mandor 2.00 HOK 58,500.00 117,000.00
2 Kepala tukang 9.00 HOK 55,000.00 495,000.00
3 Pekerja 62.00 HOK 38,500.00 2,387,000.00
4 Tukang batu 37.00 HOK 52,000.00 1,924,000.00
SUB TOTAL 4,923,000.00
D PEKERJAAN LAIN-LAIN
1 Mobilisasi dan Demobilisasi Alat Berat - Ls 3,000,000.00 -
2 Prasasti - Bh 200,000.00 -
SUB TOTAL -
TOTAL BIAYA 100,000,000.00
DIPERIKSA OLEH: DIBUAT OLEH:
FASILITATOR KETUA OMS BENDAHARA
RUDY SARMANTO.ST PONIDI WAGIRAN
RENCANA PENGGUNAAN DANA IIBANTUAN LANGSUNG MASYARAKAT (BLM)
Propinsi : Lampung
Kabupaten : Pesawaran Program : RIS-PNPM
Kecamatan : Tegineneng
Desa : Margo Rejo
Pekerjaan : Perkerasan Jalan Telford dan Gorong2 Plat
Lokasi : Dusun V
NO. URAIAN
VOLUME HARGA SATUAN JUMLAH HARGA
VOLUME SATUAN (Rp.) (Rp.)
A. BIAYA OPERASIONAL OMS
1 Pengukuran Pematokan 0.30 Ls 500,000.00 150,000.00
2 ATK dan Pelaporan 0.30 Ls 3,500,000.00 1,050,000.00
3 Transportasi OMS 0.30 Ls 1,000,000.00 300,000.00
SUB TOTAL 1,500,000.00
B. PEKERJAAN PERKERASAN JALAN
I BAHAN
1 Batu belah 10 - 15 cm 182.00 M3 144,000.00 26,208,000.00
2 Batu pecah 5 - 7 cm 95.00 M3 154,000.00 14,630,000.00
3 Pasir Urug / Timbun 157.00 M3 97,000.00 15,229,000.00
4 Alat bantu 30.00 Set 100,000.00 3,000,000.00
SUB TOTAL 59,067,000.00
II UPAH
1 Pekerja 357.00 HOK 38,500.00 13,744,500.00
2 Mandor 11.00 HOK 58,500.00 643,500.00
3 Operator terlatih - HOK 52,000.00 -
SUB TOTAL 14,388,000.00
III ALAT
1 Roller 3 wheel 6 - 8 ton - Jam 125,000.00 -
SUB TOTAL -
C. PEKERJAAN PASANGAN GORONG-GORONG PLAT
I BAHAN
1 Pasir pasang - M3 155,000.00 -
2 Semen 40.00 Kg 1,200.00 48,000.00
3 Batu belah hitam - M3 115,000.00 -
4 Kawat Ikat - Kg 13,000.00 -
5 Paku - Kg 15,000.00 -
6 Kayu Klas III - M3 1,400,000.00 -
7 Batu pecah 1 - 2 cm - M3 260,000.00 -
8 Baja Tulangan - Kg 14,000.00 -
SUB TOTAL 48,000.00
II UPAH
1 Mandor - HOK 58,500.00 -
2 Kepala tukang - HOK 55,000.00 -
3 Pekerja - HOK 38,500.00 -
4 Tukang batu - HOK 52,000.00 -
SUB TOTAL -
III ALAT
1 Alat bantu - Set - -
SUB TOTAL -
D PEKERJAAN LAIN-LAIN
1 Mobilisasi dan Demobilisasi Alat Berat - Ls 3,000,000.00 -
2 Prasasti - Bh 200,000.00 -
SUB TOTAL -
TOTAL BIAYA 75,000,000.00
DIPERIKSA OLEH: DIBUAT OLEH:
FASILITATOR KETUA OMS BENDAHARA
RUDY SARMANTO.ST PONIDI WAGIRAN
RENCANA PENGGUNAAN DANA IIIBANTUAN LANGSUNG MASYARAKAT (BLM)
Propinsi : Lampung
Kabupaten : Pesawaran Program : RIS-PNPM
Kecamatan : Tegineneng
Desa : Margo Rejo
Pekerjaan : Perkerasan Jalan Telford dan Gorong2 Plat
Lokasi : Dusun V
NO. URAIAN
VOLUME HARGA SATUAN JUMLAH HARGA
VOLUME SATUAN (Rp.) (Rp.)
A. BIAYA OPERASIONAL OMS
1 Pengukuran Pematokan 0.30 Ls 500,000.00 150,000.00
2 ATK dan Pelaporan 0.30 Ls 3,500,000.00 1,050,000.00
3 Transportasi OMS 0.30 Ls 1,000,000.00 300,000.00
SUB TOTAL 1,500,000.00
B. PEKERJAAN PERKERASAN JALAN
I BAHAN
1 Batu belah 10 - 15 cm 182.00 M3 144,000.00 26,208,000.00
2 Batu pecah 5 - 7 cm 95.00 M3 154,000.00 14,630,000.00
3 Pasir Urug / Timbun 61.00 M3 97,000.00 5,917,000.00
4 Alat bantu - Set 100,000.00 -
SUB TOTAL 46,755,000.00
II UPAH
1 Pekerja 361.00 HOK 38,500.00 13,898,500.00
2 Mandor 11.00 HOK 58,500.00 643,500.00
3 Operator terlatih 12.00 HOK 52,000.00 624,000.00
SUB TOTAL 15,166,000.00
III ALAT
1 Roller 3 wheel 6 - 8 ton 61.00 Jam 125,000.00 7,625,000.00
SUB TOTAL 7,625,000.00
C. PEKERJAAN PASANGAN GORONG-GORONG PLAT
I BAHAN
1 Pasir pasang - M3 155,000.00 -
2 Semen - Kg 1,200.00 -
3 Batu belah hitam - M3 115,000.00 -
4 Kawat Ikat - Kg 13,000.00 -
5 Paku - Kg 15,000.00 -
6 Kayu Klas III - M3 1,400,000.00 -
7 Batu pecah 1 - 2 cm - M3 260,000.00 -
8 Baja Tulangan - Kg 14,000.00 -
SUB TOTAL -
II UPAH
1 Mandor - HOK 58,500.00 -
2 Kepala tukang - HOK 55,000.00 -
3 Pekerja - HOK 38,500.00 -
4 Tukang batu - HOK 52,000.00 -
SUB TOTAL -
III ALAT
1 Alat bantu - Set - -
SUB TOTAL -
D PEKERJAAN LAIN-LAIN
1 Mobilisasi dan Demobilisasi Alat Berat 1.00 Ls 3,000,000.00 3,000,000.00
2 Prasasti 5.00 Bh 200,000.00 1,000,000.00
SUB TOTAL 4,000,000.00
TOTAL BIAYA 75,000,000.00
DIPERIKSA OLEH: DIBUAT OLEH:
FASILITATOR KETUA OMS BENDAHARA
RUDY SARMANTO.ST PONIDI WAGIRAN
RENCANA ANGGARAN BIAYA
BANTUAN LANGSUNG MASYARAKAT (BLM)
Propinsi : Lampung No. RAB :
Kabupaten : Pesawaran Program : RIS-PNPM
Kecamatan : Tegineneng
Desa : Margo Rejo
Pekerjaan : Lapis Pondasi Bawah (LPB) / Telford 726.75 M3
Lokasi : Dusun V
NO. URAIAN
VOLUME HARGA SATUAN JUMLAH HARGA
VOLUME SATUAN (Rp.) (Rp.)
I BAHAN
1 Batu belah 10 - 15 cm 605.63 M3 144,000.00 87,210,108.00
2 Batu pecah 5 - 7 cm 242.25 M3 154,000.00 37,306,546.20
3 Pasir Urug / Timbun 363.38 M3 97,000.00 35,247,418.65
4 Alat bantu 48.45 Set 100,000.00 4,845,006.00
SUB TOTAL I 164,609,078.85
II UPAH
1 Pekerja 1,199.14 HOK 38,500.00 46,166,850.92
2 Mandor 36.34 HOK 58,500.00 2,125,746.38
3 Operator terlatih 12.11 HOK 52,000.00 629,850.78
SUB TOTAL II 48,922,448.08
III ALAT
1 Mesin Gilas 3 Roda 6 - 8 T 60.56 Jam 125,000.00 7,570,321.87
SUB TOTAL III 7,570,321.87
TOTAL BIAYA 221,101,848.81
DIPERIKSA OLEH: DIBUAT OLEH:
FASILITATOR KETUA OMS KADER DESA
RUDY SARMANTO.ST PONIDI PAIMAN
RENCANA ANGGARAN BIAYA
BANTUAN LANGSUNG MASYARAKAT (BLM)
Propinsi : Lampung No. RAB :
Kabupaten : Pesawaran Program : RIS-PNPM
Kecamatan : Tegineneng
Desa : Margo Rejo
Pekerjaan : Pas. Batu Belah Hitam 8.23 M3
Lokasi : Dusun V
NO. URAIAN
VOLUME HARGA SATUAN JUMLAH HARGA
VOLUME SATUAN (Rp.) (Rp.)
I BAHAN
1 Batu belah hitam 9.88 M3 115,000.00 1,135,740.00
2 Pasir pasang 4.28 M3 155,000.00 663,338.00
3 Semen 1,341.49 Kg 1,200.00 1,609,788.00
SUB TOTAL I 3,408,866.00
II UPAH
1 Pekerja 12.35 HOK 38,500.00 475,282.50
2 Kepala tukang 0.62 HOK 55,000.00 33,948.75
3 Tukang Batu 6.17 HOK 52,000.00 320,970.00
4 Mandor 0.62 HOK 58,500.00 36,109.13
SUB TOTAL II 866,310.38
III ALAT
1 Alat bantu Set 100,000.00
SUB TOTAL III -
TOTAL BIAYA 4,275,176.38
DIPERIKSA OLEH: DIBUAT OLEH:
FASILITATOR KETUA OMS KADER DESA
RUDY SARMANTO.ST PONIDI PAIMAN
RENCANA ANGGARAN BIAYA
BANTUAN LANGSUNG MASYARAKAT (BLM)
Propinsi : Lampung No. RAB :
Kabupaten : Pesawaran Program : RIS-PNPM
Kecamatan : Tegineneng
Desa : Margo Rejo
Pekerjaan : Beton Bertulang 3.36 M3
Lokasi : Dusun V
NO. URAIAN
VOLUME HARGA SATUAN JUMLAH HARGA
VOLUME SATUAN (Rp.) (Rp.)
I BAHAN
1 Besi Beton 504.00 Kg 14,000.00 7,056,000.00
2 Semen 1,128.96 Kg 1,200.00 1,354,752.00
3 Pasir Beton 1.81 M3 160,000.00 290,304.00
4 Split 1 - 2 2.76 M3 260,000.00 716,352.00
5 Kawat Ikat 7.56 Kg 13,000.00 98,280.00
6 Kayu Perancah 1.08 M3 1,400,000.00 1,505,280.00
7 Paku 10.75 Kg 15,000.00 161,280.00
SUB TOTAL I 11,182,248.00
II UPAH
1 Mandor 1.02 HOK 58,500.00 59,950.80
2 Kepala tukang 7.98 HOK 55,000.00 438,900.00
3 Tukang 26.88 HOK 52,000.00 1,397,760.00
4 Pekerja 42.87 HOK 38,500.00 1,650,633.60
SUB TOTAL II 3,547,244.40
III ALAT
1 Alat bantu - Set 100,000.00 -
SUB TOTAL III -
TOTAL BIAYA 14,729,374.80
DIPERIKSA OLEH: DIBUAT OLEH:
FASILITATOR KETUA OMS KADER DESA
RUDY SARMANTO.ST PONIDI PAIMAN
RENCANA ANGGARAN BIAYABANTUAN LANGSUNG MASYARAKAT (BLM)
Propinsi : Lampung No. RAB :
Kabupaten : Pesawaran Program : RIS-PNPM
Kecamatan : Tegineneng
Desa : Margo Rejo
Pekerjaan : Plesteran 31.44 M2
Lokasi : Dusun V
NO. URAIAN
VOLUME HARGA SATUAN JUMLAH HARGA
VOLUME SATUAN (Rp.) (Rp.)
I BAHAN
1 Pasir Pasang 0.88 M3 155,000.00 136,449.60
2 Semen 169.78 kg 1,200.00 203,731.20
SUB TOTAL I 340,180.80
II UPAH
1 Mandor 0.25 HOK 58,500.00 14,713.92
2 Pekerja 7.07 HOK 38,500.00 272,349.00
3 Kepala Tukang 0.31 HOK 55,000.00 17,292.00
4 Tukang 4.79 HOK 52,000.00 249,319.20
SUB TOTAL II 553,674.12
III ALAT
1 Alat bantu - Set 100,000.00 -
SUB TOTAL III -
TOTAL BIAYA 893,854.92
DIPERIKSA OLEH: DIBUAT OLEH:
FASILITATOR KETUA OMS KADER DESA
RUDY SARMANTO.ST PONIDI PAIMAN
ANALISA HARGA SATUAN
PROGRAM : RIS - PNPM
KEGIATAN : PEMBANGUNAN GORONG2
LOKASI : DESA MARGOREJO, KEC. TEGINENENG, KAB. PESAWARAN
TAHUN : 2011
ANALYSA URAIAN PEKERJAAN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
C.2 1 M 3 PASANG BATU BELAH Adk. 1 : 4
163 Kg Semen 1,200.00 195,600.00
1.2 m3 Bt. Belah 115,000.00 138,000.00
0.52 m3 Pasir 155,000.00 80,600.00
1.5 HOK Pekerja 38,500.00 57,750.00
0.75 HOK Tukang 52,000.00 39,000.00
0.075 HOK Kep. Tukang 55,000.00 4,125.00
0.075 HOK Mandor 58,500.00 4,387.50
Sub. Total 519,462.50
E.27 PEK. PLESTERAN adk. 1 : 5 + Acian
5.4 Kg Semen 1,200.00 6,480.00
0.028 m3 Pasir 155,000.00 4,340.00
0.225 HOK Pekerja 38,500.00 8,662.50
0.1525 HOK Tukang 52,000.00 7,930.00
0.01 HOK Kep. Tukang 55,000.00 550
0.008 HOK Mandor 58,500.00 468.00
Sub. Total 28,430.50
G.29 1 M3 COR BETON TAK BERTULANG Adk. 1:2:3
0.82 M3 Batu Pecah 1/2 260,000.00 213,200.00
0.54 M3 Pasir Beton 160,000.00 86,400.00
336 Kg Semen (PC) 1,200.00 403,200.00
1 HOK Tukang 52,000.00 52,000.00
0.1 HOK Kepala Tukang 55,000.00 5,500.00
6 HOK Pekerja 38,500.00 231,000.00
0.3 HOK Mandor 58,500.00 17,550.00
Sub. Total 1,008,850.00
PENULANGAN BESI TIAP 1 M3 BETON:
6.75 HOK Tukang 52,000.00 351,000.00
2.25 HOK Kepala Tukang 55,000.00 123,750.00
6.75 HOK Pekerja 38,500.00 259,875.00
BAHAN TIAP 1 M3 BETON :
150 Kg Besi beton 14,000.00 2,100,000.00
2.25 Kg Kawat beton 13,000.00 29,250.00
Sub. Total 2,863,875.00
CETAKAN BETON (BEKISTING ) UNTUK 1 M3
0.25 HOK Tukang 52,000.00 13,000.00
0.025 HOK Kepala Tukang 55,000.00 1,375.00
0.01 HOK Pekerja 35,000.00 350
0.005 HOK Mandor 58,500.00 292.5
Bahan-bahan
0.32 M3 Kayu Kls.III (Papan) 1,400,000.00 448,000.00
3.2 Kg Paku 15,000.00 48,000.00
Sub. Total 511,017.50
Total 1 m3 Beton Bertulang 4,383,742.50