FAKULTAS TEKNIK JURUSAN / PROGRAM STUDI TEKNIK SIPIL TUGAS BESAR RENCANA ANGGARAN BANGUNAN Halaman: 1 UNIVERSITAS PALANGKA RAYA FANDRIE DAB 108 045 NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUME HASIL & SATUAN I I.1 I.2 PEKERJAAN PERSIAPAN Pembersihan Lokasi Uraian pekerjaan : Panjang Lebar Volume pekerjaan = 26 m = 17,5 m = 26 x 17,5 = 455 m 2 Pemasangan Bouwplank Uraian pekerjaan : Panjang Lebar Keliling Ukuran papan Ukuran tiang Tinggi tiang Jarak antar tiang Banyak tiang = 24 m = 15,5 m = 2 x ( panjang + lebar ) = 2 x ( 24 m + 15,5 m ) = 79 m = 2 x 20 = 5 x7 = 1 m = 2 m = 79 m / 2 m = 39,5 = 40 455 m 2 79 m 2 0,456 m 3 30 m 2 22m 2 m 2 m 2 m 2 m 26m 13,5 22m 13,5 1,0 24m 1,0 1,0 1,0 15,5m 17,5m

Upload: richardo-f-menggang

Post on 22-Dec-2015

258 views

Category:

Documents


0 download

DESCRIPTION

hitungan rab

TRANSCRIPT

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARAN BANGUNAN

Halaman:1

UNIVERSITAS PALANGKA RAYA FANDRIE DAB 108 045

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

II.1

I.2

I.3

PEKERJAAN PERSIAPANPembersihan Lokasi

Uraian pekerjaan :Panjang Lebar Volume pekerjaan

= 26 m= 17,5 m= 26 x 17,5 = 455 m2

Pemasangan Bouwplank

Uraian pekerjaan :Panjang Lebar Keliling

Ukuran papanUkuran tiangTinggi tiangJarak antar tiangBanyak tiangVolume papanVolume tiang

Jumlah volume kayu

= 24 m= 15,5 m= 2 x ( panjang + lebar )= 2 x ( 24 m + 15,5 m )= 79 m= 2 x 20= 5 x7= 1 m= 2 m= 79 m / 2 m = 39,5 = 40 buah= 79 x 0,02 x 0,2 = 0,316 m3

= 40 x 1 x 0,05 x 0,07 = 0,14 m3

= 0,456 m3

Dreksi Ket dan Los KerjaLuas direksi ket = 3 x 4 = 12 m2

Luas los kerja = 3 x 6 = 18 m2

Total direksi ket dan los kerja = 30 m2

455 m2

79 m2

0,456 m3

30 m2

22m

2 m 2 m

2 m

2 m

26m

13,5 m

22m

13,5 m

1,0 m

24m

1,0 m

1,0 m

1,0 m

15,5m

17,5m

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:2

UNIVERSITAS PALANGKA RAYA FANDRIE DAB 108 045

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

II II.1

II.2

PEKERJAAN TANAH DAN PONDASIGalian tanaha). Pondasi Foot Plate (20 titik)

Uraian perhitungan :- Banyak lubang pondasi - X - Lebar atas * Luas atas- Luas bawah* Volume galian

= 20 buah= 1/5 x 1,7 = 0,34= 1,7 + (2 x 0,34) = 2,38 m= 2,38 x 2,38 = 5,6644 m2

= 1,7 x 1,7 = 2,890 m2

= [(5,6644 + 2,890) /2] x 1,7 x 20 = 145,425 m3

b). Pondasi menerus

Uraian perhitungan :- Panjang pondasi - X - Lebar atas* Volume

galian

= 105,2 m= 1/5 x 0,8 =0,16 m= 0,8 + (2 x 0,16) = 1,12 m= [ (0,8 + 1,12) /2} x 0,8 x 105,2 = 80,794 m3

Urugan pasir bawah lantai (pasir pasang)a. Pondasi Foot plat

- Banyak lubang pondasi - X - Lebar atas * Luas atas- Luas bawah* Volume galian

= 20 buah= 1/5 x 0,15 = 0,03 m= 1,7 + (2 x 0,03) = 1,76 m= 1,76 x 1,76 =3,098 m2

= 1,7 x 1,7 = 2,890 m2

= [(3,098 + 2,890) /2] x 0,15 x 20 = 8,981 m3

b. Pondasi Menerus- Panjang pondasi - X - Lebar atas* Volume

galian

= 105,2 m= 1/5 x 0,1 =0,02 m= 0,8 + (2 x 0,02) = 0,84 m= [ (0,8 + 0,84) /2} x 0,1 x 105,2 = 8,626 m3

Volume total urugan pasir = 8,981+8,626=17,607 m3

145,425 m3

80,794 m3

8,981 m3

8,626 m3

17,607 m3

Panjang sloof =

X X

5 : 1 1,7 m

( 1, 7+ 2X ) m

1,4 mX X

5 : 1 0,8 m

0,8 m

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARAN BANGUNAN

Halaman:3

UNIVERSITAS PALANGKA RAYA FANDRIE DAB 108 045

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

II.3 Pekerjaan pondasi

a). Pondasi Foot Plate

Uraian perhitungan :- Banyak pondasi Volume pondasi I Volume pondasi II

Volume pondasi III Volume pondasi IV- Vol.total pondasi foot plate- Volume cor beton bwh pondasi

= 20= 0,35 x 0,35 x 1,3 = 0,159 m3

=

= 1,5 x 1,5 x 0,15 = 0,338m3

= 1,7 x 1,7 x 0,1 = 0,289 m3

= ( 0,159 + 0,1 + 0,338 ) x 20 = 11,94 m3

= 0,289 x 20 = 5,78 m3

35/35

Pondasi plat

1,5 m

0,1 m

0,1 m

1,5 m 0,1 m0,1 m

35/35

0,15 m

1,3 m

1,5 m

Pondasi plat foot

Cor beton bawah pondasi

1,7 m

0,1 m

0,1 m

11,94 m3

5,78 m3

I

III

IV

II

15/15

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARAN BANGUNAN

Halaman:4

UNIVERSITAS PALANGKA RAYA FANDRIE DAB 108 045

NO.

URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

II.4

b). Pondasi menerus

Uraian perhitungan :- Aanstampang batu kali

Luas penampang Volume aanstampang

- Pondasi batu kali Luas Penampang

Volume pondasi

= 0,1 x 0,8 = 0,08 m2

= panjang pondasi x luas penampang= 105,2 x 0,08 = 8,416 m3

= { (0,25 + 0,7) / 2 } x 0,55 = 0,2613 m2

= panjang pondasi x luas penampang= 105,2x 0,2613 = 36,321 m3

Urugan kembali

Uraian perhitungan :Volume urugan kembali = Volume galian – volume pondasi

= 145,425+80,794-17,607-18,1-8,626-36,321-8,416= 167,281 m3

8,416 m3

36,321 m3

167,281 m3

0,55 m

0,1 m

0,25 m

0,7 m

0,8 m

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARAN BANGUNAN

Halaman :5

UNIVERSITAS PALANGKA RAYA FANDRIE DAB 108 045

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

III PEKERJAAN DINDING DAN PLESTERAN Kusen Pintu jendela(P2-J1)

Kusen Pintu 1

Kusen jendela 1

Kusen Jendela 2

Kusen ventilasi

31,613 m2

30,029 m2

9,494 m2

6,337 m2

5,357 m2

Banyak P2-J1 = 4 buahLuas bukaan P2-J1 = 4 x (( 1,78 x 3,5 ) + ( 0,94 x 1,78 )) = 31,613 m2

0,92 m

2,72 m

Banyak P1 = 12buah

Luas P1 = 12x(2,72 x 0,92) = 30,029 m2

1,78 m

0,92 m

Banyak kusen = 2 buah

Luas J1=2x (1,78 x 0,92) = 3,275 m2

Banyak rolling door = 2 buah

Luas J2 = 2x(1,78 x 1,78) = 6,337 m2

1,78 m

0,72 m

0,62 m

Banyak Ventilasi = 12 buah

Luas V1 = 12x(0,62 x 0,72) = 5,357 m2

1,78 m

1,78

0,94m

0,86 m 0,86 m

1,78 m

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARAN BANGUNAN

Halaman :6

UNIVERSITAS PALANGKA RAYA FANDRIE DAB 108 045

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

III.1

III.2

III.3

III.4

Panjang dinding lantai I =104 m

Panjang dinding lantai II = 218 m

Panjang dinding trasram = 28 m

Pasangan bata merah tebal ½ bata campuran 1 pc : 3 ps ( trasram )Volume = (28x1,5)-8( 0,92x1,5 ) = 30,96 m2

Pasangan bata merah tebal ½ bata campuran 1 pc : 5 psVolume = luas dinding lantai Idan II – luas PJ 1 – luas P1 – Luas P2 – Luas rolling door – glass

box – luas pasangan trasram – Luas kolom praktis & utama = (( 104 x 4 ) + ( 218 x 3,5 )) –31,613 – 30,029 – 3,275 – 6,337 – 5,357 –30,96 = 1071,429 m2

Plesteran campuran 1 pc : 3 ps tebal 15 mm ( trasram ) Volume = ( tinggi trasram x panjang dinding x tebal plesteran ) = ( 1,5x 28 x 0,015m ) = 0,630 m3

Plesteran campuran 1 pc : 5 ps tebal 15 mmVolume = (1071,429m2 x 0,015m) x 2 = 32,143 m3

30,96 m2

1071,429 m2

0,630 m3

32,143 m3

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:7

UNIVERSITAS PALANGKA RAYA FANDRIE DAB 108 045

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

IV

4.1

PEKERJAAN BETON BERTULANG

Koloma). Kolom Praktis (15/15)

Jumlah kolom praktis

Tinggi 4m = 12 buah

Tinggi 2m = 12 buah

Tinggi 3,5m= 20 buah

Volume beton = (0,15x 0,15) x((12x2)+(12x4)+(20x3,5)) = 3,195 m 3

Volume bekisting = 2 (0,15 + 0,15 ) x((12x2)+(12x4)+(20,3,5))= 85,2 m2

Volume tulangan

Volume besi 4 Ø 15 = {20(3,5 + (5 x0,015x 2)+ 12(2+(5x0,015x2))+12(4+(5x0,015x2))}x 4 = 589,12 m

Berat besi = 589,12x152x0,0062 = 181,005 kg Jumlah sengkang (n) = 20 (( 350 / 8 ) + 1) +12(200/8)+1)+12((400/8)+1)

= 1819 buah Volume sengkang = 928 x (4x0,15+(5x0,012x2)) = 1309,68 m Berat besi Ø 15 = 589,12(152x0,0062) = 821,655 kg Berat besi Ø 6 = 1309,68(62x0,0062) = 292,321 kg

b). Kolom utama (40/40)

Jumlah kolom utama = 20 buah

Tinggi kolom = 7,5 m

Volume beton = 035x 0,35 x 7,5 x 20 = 18,375 m 3

Volume bekisting = 2 (0,35x2) x 7,5 x 20 = 210 m2

Volume tulangan

Volume besi 12 Ø 15 = {20 (7,5 + (5 x 0,015 x 2 )}x 12 = 1838,4 m Berat besi Ø 15 = Vbesi x (152 x 0,0062) = 1838,4 x 1,3950 = 2564,568 kg Jumlah sengkang (n) = 20 [( 750 / 15 ) + 1] = 1020 buah Volume sengkang = 1020(0,35x4+(5x0,015x2) = 1550,4m Berat besi Ø 6 =1550,4(62x0,0062)

= 346,049 kg

181,005 kg

103,008 kg284,013 kg

5377,600 kg

790,988 kg6168,648 kg

40

15

15 4 Ø 15

Ø 6 – 8

40

40

Ø 8 - 15

12 Ø 15

40

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:9

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

4.2 Pembalokan

a. Sloof (15/20)

Panjang sloof = 146 m

Volume beton = 0,15 x 0,20 x 146 = 4,38 m 3

Volume bekisting = (0,2 + 0,2) x 146 = 58,4 m2

Volume tulangan

Volume besi 6 Ø 12 = {( 146 + (5 x 0,012 x 5 )} x 6 = 876,72 m Berat besi Ø 12 = Vbesi x (122x0,0062) = 876,72 x 0,893 = 782,737 kg Jumlah sengkang = (14600/10)+1 = 1461 Volume sengkang = 1461(2(0,15+0,20)+(5x0,012)

= 1198,02 m Berat besi Ø 12 = 876,72(122x0,0062)

= 782,737 kg Berat besi Ø 8 = 1198,02(82x0,0062)

= 475,374 kg

b. Balok Utama (25/35)

esi

Panjang balok atap = 144,5 m

Volume beton = 0,35x 0,25 x 144,5 = 12,644 m 3

Volume bekisting = ((2x0,35)+ 0,25) x 144,5 = 137,275 m2

Volume tulangan

Volume besi 8 Ø 16 = (144,5 + (5 x 0,016 x 2 ) x 8 = 1157,28 m Jumlah sengkang (n) = (14450/20) + 1= 724 buah Volume sengkang = 724 (2(0,35+0,25)+(5x0,012x2))

= 955,68 m Berat besi Ø 16 = 1157,28(162x0,0062) = 1836,835 kg Berat besi Ø 10= 955,68(102x0,0062) = 592,522 kg

2090,967 kg

327,416 kg2418,383 kg

3135,210 kg

500,722 kg3635,932 kg

15

6 Ø 12

20 Ø 8 - 15

35Ø 10 - 20

8 Ø 16

25

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:10

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

c. Balok Anak (15/20)

Panjang balok = 284 m

Volume beton = 0,15x 0,25 x 284 = 8,52 m 3

Volume bekisting = (0,15 + 0,25 + 0,25) x 284 = 156,2 m2

Volume tulangan

Volume besi 6 Ø 12 = { 284 + (2 x 0,012 x 5 )}x 6 = 1704,72 m Jumlah sengkang = (28400/10)+1 = 2841 buah Berat besi Ø 12 = Vbesi x (122x0,0062) = 1704,72 x 0,893 = 1521 kg Volume sengkang = { 284 + (2( 0,15x 0,25 )+(5x0,012x2)} = 2329,62 m Berat besi Ø 8 = Vbesi x(82x0,0062) = 922,012 kg Total berat besi = 1521 + 922,012 = 2443,012 k

d. ring balk (25/35)

4262,400 kg

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:11

15

25

6 Ø 12

Ø 10-20 Ø 10-20

Ø 10-20

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

4.7 Pekerjaan Plat Lantai Tebal 12cm (4buah)

Volume beton = ((7,8m x 13,3m) – (1,8m x 3,8m)) x 0,12m x 4 = 46,512 m3

Volume bekisting = (7,8m x 13,3m) – (1,8m x 3,8m) x 4 = 387,6 m2

Luasan bekisting per 1 m3 beton = 387,6 / 46,512 = 8,333m

Panjang tulangan pendek horizontal Ø12=(11500/200) + 1 x (¼ x 8 + 5 x 0,012 x 2) x 2 x 4 = 992,160m

Panjang tulangan pendek horizontal Ø12=(200/200) + 1 x (¼ x 4 + 5 x 0,012 x 2) x 2 x 4 = 17,920m

Panjang tulangan pendek vertikal Ø12=(400/200) + 1 x (¼ x 11,5 + 5 x 0,012 x 2) x 2 x 4 = 71,880m

Panjang tulangan pendek vertikal Ø12=(400/200) + 1 x (¼ x 13,5 + 5 x 0,012 x 2) x 2 x 4 = 83,880m

Panjang tulangan menerus horizontal Ø12=(11500/200) + 1 x (½ x 8 + 5 x 0,012 x 2) x 4 + (10 x 0,012 x 4) x 4 = 3968,640m

Panjang tulangan menerus horizontal Ø12=(200/200) + 1 x (½ x 4 + 5 x 0,012 x 2) x 4 + (10 x 0,012 x 4) x 4 = 35,840m

Panjang tulangan menerus vertikal Ø12=(400/200) + 1 x (½ x 11,5 + 5 x 0,012 x 2) x 4 + (10 x 0,012 x 4) x 4 = 431,280m

Panjang tulangan menerus vertikal Ø12 =(400/200) + 1 x (½ x 13,5 + 5 x 0,012 x 2) x 4 + (10 x 0,012 x 4) x 4 = 503,280m

Panjang tulangan bawah menerus horizontal Ø12=(11500/200) + 1 x 8 + 5 x 0,012 x 2 x 4= 1900,08m

Panjang tulangan bawah menerus horizontal Ø12=(200/200) + 1 x 4 + 5 x 0,012 x 2 x 4= 32,960m

46,512 m3

387,6 m2

13,5m

4m4m

Ø 12-20

Ø 12-20

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:12

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

Panjang tulangan bawah menerus vertikal Ø12=(400/200) + 1 x 11,5 + 5 x 0,012 x 2 x 4= 139,440m

Panjang tulangan bawah menerus vertikal Ø12 =(400/200) + 1 x 13,5 + 5 x 0,012 x 2 x 4= 163,440m

Berat besi Ø12 = (992,160 + 17,920 + 71,880 + 83,880 + 3968,640 +35,840 + 431,280 + 503,280 + 1900,08 + 32,960 + 139,440 + 163,440) x 0,888

= 8340,8 x 0,888 = 7406,630 kg 7406,630 kg

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:13

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

4.8 Pekerjaan Plat Atap Tebal 10cm (4 buah)

Volume beton = ((7,8m x 13,3m) – (1,8m x 3,8m)) x 0,10m x 4 = 38,76 m3

Volume bekisting = 7,8m x 13,3m x 4 = 414,96 m2

Luasan bekisting per 1 m3 beton = 387,6 / 46,512 = 8,333m

Panjang tulangan pendek horizontal Ø12 =(13500/200) + 1 x (¼ x 8 + 5 x 0,012 x 2) x 2 x 4 = 1161,760m

Panjang tulangan pendek vertikal Ø12 =8000/200) + 1 x (¼ x 13,5 + 5 x 0,012 x 2) x 2 x 4 = 1146,360m

Panjang tulangan menerus horizontal Ø12 =(13500/200) + 1 x (½ x 8 + 5 x 0,012 x 2) x 4 + (10 x 0,012 x 4) x 4 = 4647,040m

Panjang tulangan menerus vertikal Ø12 =(8000/200) + 1 x (½ x 13,5 + 5 x 0,012 x 2) x 6 + (10 x 0,012 x 6) x 4 = 1896,66m

Panjang tulangan bawah menerus vertikal Ø12 =(8000/200) + 1 x 13,5 + 5 x 0,012 x 2 x 4= 2233,6m

Panjang tulangan bawah menerus horizontal Ø12 =(135000/200) + 1 x 8 + 5 x 0,012 x 2 x 4= 2224,880m

Berat besi tulangan Ø12 = 1161,760 + 1146,360 + 4647,040 + 1896,66 + 2233,6 + 2224,880 = 13310,300 x 0,888 = 11819,546 kg

38,76 m3

414,96 m2

11819,546 kg

8m

Ø 12-20

13,5m

Ø 12-20

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:14

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

4.9 Pekerjaan Pondasi

a. Tulangan Kolom Pendek 40/40

Panjang tulangan 12 19 = 12 x (1,6 + 5 x 0,019 x 2) = 21,480m Berat tulangan = 21,480 x 2,226 = 47,814kg Banyak sengkang = (0,35 x 2) + (0,35 x 2) + (0,05 x 2) = 1,5m Berat sengkang = 1,5 x 12 x 0,395 = 7,110 kg

b. Tulangan Telapak Pondasi

130 cm

15 cm

15 cm

150 cm

40

40

8 Ø 19

Ø 8 - 15

4 Ø 19

Ø 10 - 130 Ø 10 - 130

3 Ø 10 – 150

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:15

UNIVERSITAS PALANGKA RAYA HANDY WIBOWO DAB 105 007

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

Perhitungan tulangan Tulangan 1 sumbu horizontal (Ø 10 – 130 )

Tebal selimut beton = 0,05 m

x = 0,25 / cos 60º =0,5 my = √ 0,32 + 0,32 = 0,424 mBanyak tulangan = [( 400 / 130 ) + 1] = 4,077 4 buah= 0,4 + 2x + 2y + ( 2 x 5 x D )= 0,4 + 2 . 0,5 + 2 . 0,424 + ( 2 x 5 x 0,010 ) = 2,348 mBerat tulangan 1 = 4 x 2,348 x 0,617 = 5,906 kg

Tulangan 1 sumbu vertikal (Ø 10 – 130 )Tebal selimut beton = 0,05 m

x = 0,25 / cos 60º =0,5 my = √ 0,32 + 0,32 = 0,424 mBanyak tulangan = [( 400 / 130 ) + 1] = 4,077 4 buah= 0,4 + 2x + 2y + ( 2 x 5 x D )= 0,4 + 2 . 0,5 + 2 . 0,424 + ( 2 x 5 x 0,010 ) = 2,348 mBerat tulangan 1 = 4 x 2,348 x 0,617 = 5,906 kg

Berat total tulangan 1 = 5, 906 kg + 5,906 kg = 11,812 kg

Tulangan 2 sumbu horizontal (Ø 10 – 130 )

x = √ 0,32 + 0,552 = 0,626 mBanyak tulangan = [( 1100 / 130 ) + 1] = 9,462 9 buah= 0,4 + 2x + ( 2 x 5 x D )= 0,4 + 2 . 0,626 + ( 2 x 5 x 0,010 ) = 1,752 mBerat tulangan 2 = 9 x 1,752 x 0,617 = 9,729 kg

Tulangan 2 sumbu vertikal (Ø 10 – 130 )

x = √ 0,32 + 0,552 = 0,626 mBanyak tulangan = [( 1100 / 130 ) + 1] = 9,462 9 buah= 0,4 + 2x + ( 2 x 5 x D )= 0,4 + 2 . 0,626 + ( 2 x 5 x 0,010 ) = 1,752 mBerat tulangan 2 = 9 x 1,752 x 0,617 = 9,729 kg

Beratn total tulangan 2 = 9,729 kg + 9,729 kg = 19,458 kg

0,4m 0,25m 0,3m

0,3m60º

1,5 m

5D

xy

0,4m 0,55m0,55m

x

5D

0,3m

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:16

UNIVERSITAS PALANGKA RAYA HANDY WIBOWO DAB 105 007

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

Tulangan 3 (Ø 10 – 150 ) ( 3 buah tul. horizontal + 3 buah tul. Vertikal,ukuran sama)

Banyak tulangan = [( 1500 / 150 ) + 1] = 11 buah = 1,5 + ( 2 x 5 x D )= 1,5 + ( 2 x 5 x 0,010 ) = 1,6 mBerat tulangan 3= ( 11 x 1,6 x 0,617) x 6 = 65,155 kg

Berat total = Berat tulangan 1 + tulangan 2 + tulangan 3 = 11,812 + 19,458 + 65,155 = 96,425 kg

Jumlah berat pondasi setempat = berat tulangan kolom pendek + berat total = (47,814 + 7,110) + 96,425 = 151,349 kg

Jumlah keseluruhan pondasi foot plat = 151,349 x 28 = 4237,772 kg

Bekisting pondasi foot plat = ( 0,4m x 1,3m) x 4 + ( (1,5m + 0,4m)/2 x 0,3m) x 4 + (1,5m x 0,15m) x 4

= 3,265 m2

4237,772 kg

3,265 m2

1,5 m

5D

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:17

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

4.10 Pekerjaan Tangga

a. Anak Tangga* Panjang besi Ø 10-15 arah x

= (1000/150) + 1 x 0,12 + 5 x 0,010 x 2 = 2,3m

* Panjang besi Ø 10-15 arah y= (1000/150) + 1 x 0,12 + 5 x 0,010 x 2 = 2,3m

* Panjang besi Ø 10-15 arah z= (200/150) + 1 x 1 + 5 x 0,010 x 2 = 2,567m

* Untuk 1 anak tangga= 2,3m + 2,3m +2,567m = 7,167m

* Maka panjang total keseluruhan anak tangga= 7,167m x 18 x 4 = 516m

* Berat besi untuk anak tangga = 516m x 0,617kg/m = 318,372kg

b. Induk Tangga* Panjang besi Ø 12-15 arah x

= (2343/150) + 1 x 1 + 5 x 0,010 x 2 = 18,614m

* Panjang besi Ø 12-15 arah y= (1000/150) + 1 x 2,343 + 5 x 0,010 x 2 = 18,883m

* Panjang total besi = (18,614 + 18,883) x 2 x 4 = 299,976m

* Maka berat besi=299,970m x 0,888 kg/m = 266,379 kg

Ø 10 - 150

Ø 12 - 15

Ø 10 - 15

2,343

Ø 12 - 15

20

20

100

xy

zØ 12 - 15

0,12

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:18

UNIVERSITAS PALANGKA RAYA HANDY WIBOWO DAB 105 007

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

c. Bordes

* Plat Bordes

Panjang besi Ø 10-30 arah x= (1500/300) + 1 x 0,9 + 5 x 0,010 x 2 x 2 = 12mBerat besi = 12m x 0,617kg/m x 4 = 29,616kg

Panjang besi Ø 10-30 arah x= (900/300) + 1 x 1,5 + 5 x 0,010 x 2 x 2 = 12,8mBerat besi = 12,8m x 0,617kg/m x 4 = 31,590kg

Maka berat besi = 29,616 + 31,590 = 61,206kg

* Penulangan Bordes Volume besi 6 Ø 19

= {1,5 + (5 x 0,019 x 2 )x 6 x 2 = 20,28 mBerat besi = Vbesi x 2,226 = 20,28 x 2,226 = 45,143 kg

Volume besi 2 Ø 12 = {0,9 + (5 x 0,012x 2 ) x 2 x 2 = 4,08 mBerat besi = Vbesi x 0,888 = 4,08 x 0,888 = 3,623 kg

Maka berat besi = 45,143 + 3,623 = 48,766 kg

Jumlah sengkang balok 1,5m (n) = (1500 / 100 ) + 1 x 2 = 32 buah

Jumlah sengkang balok 0,9m (n) = (900 / 100 ) + 1 x 2 = 20 buah

Panjang sengkang = (0,25 x 2) + (0,35 x 2) + (0,05 x 2) = 1,3m

Berat sengkang balok 1,5m = 32 x 1,3 x 0,395 = 16,432 kg

Berat sengkang balok 0,9m = 20 x 1,3 x 0,395 = 10,27 kg

Total berat sengkang = 16,432 + 10,27 = 26,702 kg

Total berat tulangan tangga = 318,172 + 266,379 + 61,206 + (48,766 + 26,702) x 4= 947,829 kg

947,829 kg

Lantai Bordes

Ø 10-30

Balok Bordes 30/40

90cm

150cmy

x Plat Bordes2 Ø 12

6 Ø 19

Ø 8-10

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:19

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 0247

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

* Bekisting Tangga

Luas I = (½ x 0,2 x 0,2) = 0,02 m2

Luas II = (0,12 x 2,343) = 0,281 m2

Volume beton = (0,02 m2 x 1m x 18) + (0,281 m2 x 1m x 2) = 0,922m3 x 4 = 3,688 m3

Volume bekisting = Volume Induk tangga + volume anak tangga = ( 1m x 2,343m) + ( 2,343m x 0,12m) x 2 (1m x 0,2m) + (½ x 0,2m x 0,2m) x 18 = 2 x 2,624 m2 + 18 x 0,220 m2 = 9,208 m2 x 4 = 36,832 m2

* Bekisting Bordes

Volume bekisting = 1,5 m x 0,9 m x 4 = 5,4 m2

* Pengaman Tangga

Volume tangga=3 x (0,1 x 0,1 x 1) + (0.05 x 0,1 x 2,343)

+ 2 x (0,02 x 0,1 x 2,343)= 0,086 m3 x 4 buah= 0,345 m3

36,832 m2

5,4 m2

0,345 m3

0,20m

0,20m

2,343m

1m

II

I 0,12m

150

90

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:20

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

* Pondasi TanggaPondasi tangga = pondasi foot plata. Tulangan kolom pendek 40/40

Panjang tulangan 12 19 = 12 x (1,6 + 5 x 0,019 x 2) = 21,480m Berat tulangan = 21,480 x 2,226 = 47,814kg Banyak sengkang = (0,35 x 2) + (0,35 x 2) + (0,05 x 2) = 1,5m Berat sengkang = 1,5 x 12 x 0,395 = 7,110 kg

b. Perhitungan tulangan Tulangan 1 sumbu horizontal (Ø 10 – 130 )

Tebal selimut beton = 0,05 m

x = 0,25 / cos 60º =0,5 my = √ 0,32 + 0,32 = 0,424 mBanyak tulangan = [( 400 / 130 ) + 1] = 4,077 4 buah= 0,4 + 2x + 2y + ( 2 x 5 x D )= 0,4 + 2 . 0,5 + 2 . 0,424 + ( 2 x 5 x 0,010 ) = 2,348 mBerat tulangan 1 = 4 x 2,348 x 0,617 = 5,906 kg

Tulangan 1 sumbu vertikal (Ø 10 – 130 )Tebal selimut beton = 0,05 m

x = 0,25 / cos 60º =0,5 my = √ 0,32 + 0,32 = 0,424 mBanyak tulangan = [( 400 / 130 ) + 1] = 4,077 4 buah= 0,4 + 2x + 2y + ( 2 x 5 x D )= 0,4 + 2 . 0,5 + 2 . 0,424 + ( 2 x 5 x 0,010 ) = 2,348 mBerat tulangan 1 = 4 x 2,348 x 0,617 = 5,906 kg

Tulangan 2 sumbu horizontal (Ø 10 – 130 )

x = √ 0,32 + 0,552 = 0,626 mBanyak tulangan = [( 1100 / 130 ) + 1] = 9,462 9 buah= 0,4 + 2x + ( 2 x 5 x D )= 0,4 + 2 . 0,626 + ( 2 x 5 x 0,010 ) = 1,752 mBerat tulangan 2 = 9 x 1,752 x 0,617 = 9,729 kg

0,4m 0,25m 0,3m

0,3m60º

1,5 m

5D

x y

0,4m 0,55m0,55m

x

5D

0,3m

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:21

UNIVERSITAS PALANGKA RAYA HANDY WIBOWO DAB 105 007

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

Tulangan 2 sumbu vertikal (Ø 10 – 130 )

x = √ 0,32 + 0,552 = 0,626 mBanyak tulangan = [( 1100 / 130 ) + 1] = 9,462 9 buah= 0,4 + 2x + ( 2 x 5 x D )= 0,4 + 2 . 0,626 + ( 2 x 5 x 0,010 ) = 1,752 mBerat tulangan 2 = 9 x 1,752 x 0,617 = 9,729 kg

Berat total tulangan 2 = 9,729 kg + 9,729 kg = 19,458 kg

Tulangan 3 (Ø 10 – 150 ) ( 3 buah tul. horizontal + 3 buah tul. Vertikal,ukuran sama)

Banyak tulangan = [( 1500 / 150 ) + 1] = 11 buah = 1,5 + ( 2 x 5 x D )= 1,5 + ( 2 x 5 x 0,010 ) = 1,6 mBerat tulangan 3= ( 11 x 1,6 x 0,617) x 6 = 65,155 kg

Berat total = Berat tulangan 1 + tulangan 2 + tulangan 3 = 11,812 + 19,458 + 65,155 = 96,425 kg

Jumlah berat pondasi setempat = berat tulangan kolom pendek + berat total = (47,814 + 7,110) + 96,425 = 151,349 kg

Jumlah keseluruhan pondasi foot plat = 151,349 x 4 = 605,396 kg

Bekisting pondasi foot plat = ( 0,4m x 1,3m) x 4 + ( (1,5m + 0,4m)/2 x 0,3m) x 4 + (1,5m x 0,15m) x 4

= 3,265 m2 X 4 buah = 14,5 m2

605,396 kg

14,5 m2

1,5 m

5D

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:22

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

V

5.1

5.2

PEKERJAAN BETON TIDAK BERTULANG

Pekerjaan Lantai* Urugan tanah bawah pondasi

Volume = luas lantai dasar x tebal cor beton = (384 - 12) x 0,1 = 37,2 m3

* Spesi lantai I & IIVolume = luas lantai x tebal spasi = (384 – 12) + (384 – 12 – 32) x 0,03 = 21,360 m3

* Cor beton bawah pondasi setempatVolume = 1,6 x 1,6 x 0,15 x 28 = 10,752 m3

* Cor beton lantaiVolume = (384 – 12) x 0,05 = 18,6 m3

* Jadi total cor beton lantai + cor beton bawah pondasi= 18,6 + 10,752 = 29,352 m3

Pekerjaan Lantai Keramik * Pekerjaan lantai keramik 30 / 30

Luas lantai = 2 x luas bangunan – 2 x luas KM/WC – luas lubang tangga = 2 (384) – 2(12) -32 = 717 m2 Banyak keramik = 717 / (0,3 x0,3) = 7911,11 7911 buah

* Pekerjaan lantai keramik 20 / 20 pada KM / WCLuas lantai = 2 x 1,5 x 8 = 24 m2

Banyak keramik = 24 / (0,2 x 0,20) = 600 buah* Pekerjaan keramik 20 / 20 pada dinding KM / WC

Luas dinding = tinggi dinding x keliling dinding = 1 x (1,08 + 1,5 + 2 + 1,5) x 8 = 48,640 m2 Banyak keramik = 48,640 / (0,2 x 0,2) = 1216 buah

* Pekerjaan keramik 20 / 20 pada anak tanggaLuas lantai = banyak anak tangga x (0,2 x 1,5) x 2 = 18 x (0,2 x 1,5) x 2 x 4 = 43,2 m2 Banyak keramik = 43,2 / (0,2 x 0,2) = 1080 buah

37,2 m3

21,360 m3

29,352 m3

717 m2

7911 buah

24 m2

600 buah

48,640 m2 1216 buah

43,2 m2

1080 buah

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:23

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

VI PEKERJAAN KUSEN PINTU, JENDELA,DAN VENTILASI

a) Kusen Pintu Jendela ( 4 buah )Pasangan daun pintu dan kaca jendela

Pintu ( PJ 1 ) Luas = 1,6m x 2m x 4 = 12,8 m2

Jendela ( PJ 1 ) Luas = 0,7m x 1m x 2 x 4 = 5,6 m2

Volume pasangan kayu untuk pintu Vertikal = 2m x 3 = 6 m

Volume pasangan kayu untuk jendela Horizontal = 0,7m x 2 = 1,4 m Vertikal = 1m x 2 = 2 m Kuping kusen =0,06m x 2 = 0,12 m

Total panjang kusen = (6m + 1,4m + 2m + 0,12m) x 4 = 38,08m Volume kusen pintu = (0,06m x 0,12m) x 6m x 4 = 0,173 m3 Volume kusen jendela = (0,06m x 0,12m) x (1,4m + 2m + 0,12m) x 4 = 0,274 m3

b ) Kusen Pintu 1 ( 8 buah ) KM/WCPasangan daun pintu

Pintu ( P 1 ) Luas = 0,8m x 2m x 8 = 12,8 m2

Volume pasangan kayu untuk pintu Horizontal = 0,8 x 1= 0,8 m Vertikal = 2m x 2 = 4 m Kuping kusen =0,06m x 2 = 0,12 m

Total panjang kusen = (0,8m + 4m + 0,12m) x 8 = 39,36m Volume kusen pintu =( 0,06m x 0,12m) x 39,36m = 0,283 m3

c) Kusen Pintu 2 ( 4 buah )Pasangan daun pintu

Pintu ( P 2 ) Luas = 0,8m x 2m x 4 = 6,4 m2

Volume pasangan kayu untuk pintu Vertikal = 2m x 2 = 4 m Kuping kusen =0,06m x 2 = 0,12 m

Total panjang kusen = (4m + 0,12m) x 4 = 16,48m Volume kusen = (0,06m x 0,12m) x 16,48m = 0,119 m3

Vertikal = 0,4m x 2 = 0,8 m Total panjang kusen = (1,4m + 0,8m) x 8 = 17,6 m Volume kusen = (0,06m x 0,12m) x 17,6 = 0,127 m3

d) Ventilasi (12 buah dengan ukuran 80 cm x 40cm )

Pasangan kaca ventilasi Ventilasi

Luas = 0,8m x 0,4m x 12 = 3,84m2

Horizontal = 0,8m x 2 = 1,6 m Vertikal = 0,4m x 2 = 0,8 m

Total panjang kusen = (1,6m + 0,8m) x 12 = 28,8m Volume kusen = (0,06m x 0,12m) x 28,8m = 0,207 m3

e) Ventilasi (8 buah dengan ukuran 70 cm x 40cm ) Pasangan kaca ventilasi

Ventilasi Luas = 0,7 x 0,4 x 6 = 1,68m2

Horizontal = 0,7m x 2 = 1,4 m Vertikal = 0,4m x 2 = 0,8 m

Total panjang kusen = (1,4m + 0,8m) x 8 = 17,6 m

Volume kusen = (0,06m x 0,12m) x 17,6 = 0,127 m3

12,8 m2

5,6m2

0,274 m3

12,8 m2

0,283 m3

6,4 m2

0,119 m3

0,127 m3

3,84m2

0,207 m3

1,68m2

0,127 m3

80 80 70706 6

40 40

100

200

6806

200

6806

40

200

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA

ANGGARANBANGUNAN

Halaman:24

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

6.1

6.2

6.3

f) Ventilasi (8 buah dengan ukuran 60cm x 40m) Panjang kaca ventilasi

VentilasiLuas = 0,6m x 0,4m x 8 = 1,920m2

Horizontal = 0,6m x 2 = 1,2m Vertikal = 0,4m x 2 = 0,8m Kuping kusen = 0,06m x 4 = 0,24m

Total panjang kusen = (1,2m + 0,8m + 0,24m) x 8 = 17,92m Volume kusen = (0,06m x 0,12m) x 17,92m = 0,129m3

TOTAL VOLUME KUSEN = 0,274 m3 + 0,283 m3 + 0,119 m3 + 0,207 m3 + 0,129 m3

= 1,139 m3

TOTAL VOLUME DAUN PINTU = 12,8 m2 + 12,8 m2 + 6,4 m2 = 32m2

TOTAL VOLUME KACA = 5,6m2 + 3,84m2 + 2,24m2 + 1,920 m2 = 13,6 m2

1,920m2

0,129m3

1,139 m3

32m2

13,6 m2

6 60 6

40

6 660

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA

ANGGARANBANGUNAN

Halaman:25

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

VII PEKERJAAN KUNCI PENGANTUNG a. Pasangan Engsel jendela

PJ1 (8 buah) * 1 jendela menggunakan 2 engsel jadi jumlah engsel yang digunakan

= 8 buah x 2 = 16 engselb. Pasangan engsel pintu

PJ1 (4 buah) = 1 pintu menggunakan 3 engsel,terdapat 2 pintu

jadi jumlah engsel yang digunakan = 2x 3 = 6 engsel x 4 buah = 24 engsel

P1 (8 buah) = 1 pintu menggunakan 3 engsel

jadi jumlah engsel yang digunakan = 8 buah x 3 engsel= 24 engsel

P2 (4 buah) = 1 pintu menggunakan 3 engsel

jadi jumlah engsel yang digunakan = 4 buah x 3 engsel = 12 engsel

c. Pasangan ventilasi (20 buah) 1 ventilasi

menggunakan 2 buah engsel , jadi jumlah engsel yang digunakan = 20 buah x 2 engsel =40 engsel

d. Pasangan kunci tanam P1 + P2 + PJ1 =

20 buah kunci tanam

e. Pasangan kunci grendel PJ1 = 4 kunci

f. pasangan pegangan pintu = jumlah pintu 20 buah x 1 buah pegangan

= 20 buah pegangan

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA

ANGGARANBANGUNAN

Halaman:26

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

VIII

IX

X

XI

PEKERJAAN FINISHING * Pengecetan

Dinding Beton = Luas dinding = 1347,380 m2 x 2

= 2694,760 m2 Kusen pintu dan

jendela = 1,139 m2 Daun pintu dan

jendela = 32 m2 

PEKERJAAN LISTRIK Instalasi titik cahaya = 36 titik Lampu TL = 16 buah Lampu pijar = 20 buah Stop kontak = 12 buah Saklar ganda = 8 buah Kabel Listrik = 1 rol Saklar tunggal = 16 buah Sekring kost ganda = 4 unit Meteran listrik = 4 unit

PEKERJAAN SANITASI Pemasangan kloset jongkok = 8 buah Pemasangan bak mandi = 8 buah Pipa saluran air kotor = 8 buah Pipa saluran air bersih = 8 buah Kran air = 8 buah Westafel = 8 buah

PEKERJAAN SEPTIKTANK Galian tanah septiktank

V olume = 1,74 x 2,78 x 2,07 x 4 = 40,052 m3

Galian tanah resapan V olume = 1,8 x 1,8 x 1,62 x 4

= 20,995 m3

Perhitung tulangan dan tulangan septiktank* Tulangan tutup septiktank dan lantai septiktank

Sumbu horizontal Ø 10-15 = (1740/150) + 1 x 2,78 + 5 x 0,010 x 2 x 2 = 72,576 mBerat besi = 72,576 m x 0,617kg/m = 44,779 kg

Sumbu vertikal Ø 10-15 = (2780/150) + 1 x 1,74 + 5 x 0,010 x 2 x 2 = 71,883 mBerat besi = 71,883 m x 0,617kg/m = 44,352 kg

Berat total = 44,779 kg + 44,352 kg = 89,131 kg

* Tulangan 4 sisi septiktank Sumbu horizontal Ø 10-15

= (2070/150) + 1 x 1,74 + 5 x 0,010 x 2 x 2 = 54,464 mBerat besi = 54,464 m x 0,617kg/m = 33,604 kg

Sumbu vertikal Ø 10-15= (1740/150) + 1 x 2,07 + 5 x 0,010 x 2 x 2 = 54,684 mBerat besi = 54,684 m x 0,617kg/m = 33,740 kg

Sumbu horizontal Ø 10-15= (2070/150) + 1 x 2,78 + 5 x 0,010 x 2 x 2 = 85,248 mBerat besi = 85,248 m x 0,617kg/m = 52,598 kg

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA

ANGGARANBANGUNAN

Halaman:27

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

Sumbu vertikal Ø 10-15= (2780/150) + 1 x 2,07 + 5 x 0,010 x 2 x 2 = 84,775 mBerat besi = 84,775 m x 0,617kg/m = 52,306 kg

Berat total = 33,604 + 33,740 + 52,598 + 52,306 = 172,248 kg

* Tulangan sisi dalam 1 Sumbu horizontal Ø 10-15

= (1160/150) + 1 x 1,74 + 5 x 0,010 x 2 = 16,069 mBerat besi = 16,069 m x 0,617kg/m = 9,915 kg

Sumbu horizontal Ø 10-15= (1740/150) + 1 x 1,16 + 5 x 0,010 x 2 = 15,876 mBerat besi = 15,876 m x 0,617kg/m = 9,795 kg

Berat total = 9,915 + 9,795 = 19,710 kg

* Tulangan sisi dalam 2 Sumbu horizontal Ø 10-15

= (300/150) + 1 x 1,74 + 5 x 0,010 x 2 = 5,520 mBerat besi = 5,520 m x 0,617kg/m = 3,406 kg

Sumbu horizontal Ø 10-15= (1740/150) + 1 x 0,3 + 5 x 0,010 x 2 = 5,040 mBerat besi = 5,040 m x 0,617kg/m = 3,110 kg

Berat total = 3,406 + 3,110 = 6,516 kg

* Tulangan sisi dalam 3 Sumbu horizontal Ø 10-15

= (660/150) + 1 x 1,74 + 5 x 0,010 x 2 = 9,936 mBerat besi = 9,936 m x 0,617kg/m = 6,131 kg

Sumbu horizontal Ø 10-15= (1740/150) + 1 x 0,66 + 5 x 0,010 x 2 = 9,576 mBerat besi = 9,576 m x 0,617kg/m = 5,908 kg

Berat total = 6,131 + 5,908 = 12,039 kg

* Tulangan sisi dalam 4 Sumbu horizontal Ø 10-15

= (800/150) + 1 x 1,74 + 5 x 0,010 x 2 = 11,653 mBerat besi = 11,653 m x 0,617kg/m = 7,190 kg

Sumbu horizontal Ø 10-15= (1740/150) + 1 x 0,8 + 5 x 0,010 x 2 = 11,340 mBerat besi = 11,340 m x 0,617kg/m =6,997 kg

Berat total = 7,190 + 6,997 = 14,187 kg

Berat tulangan keseluruhan = 84,131 + 172,248 + 19,710 + 6,516 + 12,039 + 14,187= 313,831 kg x 4 buah = 1255,324 kg

Perhitungan volume beton septiktank* Volume beton tutup septiktank dan lantai septiktank

= 2,78 x 1,74 x 0,12 x 2 = 1,161 m3

* Volume beton 2 sisi septiktank= 2,07 x 1,74 x 0,12 x 2 = 0,864 m3

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA

ANGGARANBANGUNAN

Halaman:28

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO. URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

* Volume beton 2 sisi septiktank= 2,07 x 2,78 x 0,12 x 2 = 1,381 m3

* Volume beton sisi dalam 1= 1,16 x 1,74 x 0,12 = 0,242 m3

* Volume beton sisi dalam 2= 0,3 x 1,74 x 0,12 = 0,063 m3

* Volume beton sisi dalam 3= 0,66 x 1,74 x 0,12 = 0,138 m3

* Volume beton sisi dalam 1= 0,8 x 1,74 x 0,12 = 0,167 m3

* Volume beton keseluruhan= 1,16 + 0,864 + 0,242 + 0,063 + 0,138 + 0,167 + 1,381= 4,061 m3 x 4 buah = 16,064 m3

Perhitungan tulangan tutup sumur resapan* Tulangan tutup sumur resapan

Sumbu horizontal Ø 10-15= (1800/150) + 1 x 1,8 + 5 x 0,010 x 2 = 24,700 mBerat besi = 24,700 m x 0,617kg/m =15,240 kg

Sumbu horizontal Ø 10-15= (1800/150) + 1 x 1,8 + 5 x 0,010 x 2 = 24,700 m

Berat besi = 24,700 m x 0,617kg/m =15,240 kg

Berat besi = 15,240 + 15,240 = 30,480 kg x 4 buah = 121,920 kg

* Volume cor beton tumbuk sumur resapan Volume cor beton = volume cor beton 4 sisi sumur

= (0,15 x 1,8 x 1,5 x 4) = 1,62 m3

Volume beton tutup sumur resapan= 1,8 x 1,8 x 0,12 = 0,389 m3

Volume total = 1,62 + 0,389 = 2,009 m3 x 4 buah = 8,0352 m3

Perhitungan bekisting septiktank* Bekisting lantai septiktank

= 2,78 x 1,74 + (2,78 x 0,12) + 2 x (1,74 x 0,12) = 5,922 m2

* Bekisting 2 sisi septiktank= 2 x ( 0,12 + 1,74) x 1,78 x 2 = 13,243 m2

* Bekisting 2 sisi septiktank= 2 x (0,12 + 2,45) x 1,78 - 2 x (0,12x 1,16) + (0,12 x 0,3) + (0,12 x 0,66) + (0,12 x 0,8)= 18,939 – 0,701 = = 18,238 m2

* Bekisting sisi dalam 1= (0,12 x 1,74) + 2 x (0,12 +1,74) x 1,16 = 4,524 m2

* Bekisting sisi dalam 2 = 2 x (0,12 + 1,74) x 0,3 = 1,116 m2

* Bekisting sisi dalam 3= (0,12 x 1,74) + 2 x (0,12 + 1,74) x 0,66 = 2,664 m2

5023,265 kg

327,59 kg/m3

FAKULTAS TEKNIKJURUSAN / PROGRAM STUDI

TEKNIK SIPIL

TUGAS BESARRENCANA ANGGARANBANGUNAN

Halaman:28

UNIVERSITAS PALANGKA RAYA RETNO WULANDARI DAB 107 024

NO.

URAIAN PEKERJAAN DAN PERHITUNGAN VOLUMEHASIL & SATUAN

* Bekisting sisi dalam 4=2 x (0,12 + 1,74) x 0,8 = 2,976 m2

* Bekisting tutup septiktank= 2 x (2,78 x 0,12 ) + 2 x (1,74 x 0,12) + (2,78 x 1,74) – (4 x (0,12 x 1,74)= 5,087 m2

* Bekisting seluruh septiktank=5,922 + 13,243 + 4,524 + 1,116 + 2,664 + 2,976 + 5,087 + 18,238=56,746 m2 x 4 buah = 226,984 m2

Perhitungan bekisting sumur resapan* Bekisting 4 sisi sumur resapan

=2 x (0,15 + 1,8) x 1,5x 4 = 3,240 m2

* Bekisting tutup sumur resapan= 4 x (0,12 x 1,8) + (1,5 x 1,5) = 3,114 m2

* Bekisting seluruh sumur resapan=3,114 + 3,240= 6,354 m2 x 4 buah = 25,416 m2

Perhitungan volume isi sumur resapan* Ijuk

= (1,5 x 1,5 x 0,2 ) = 0,45 m2

* Kerikil= (1,5 x 1,5 x 1,1) = 2,475 m2

* Batu belah= (1,5 x 1,5 x 0,2) = 0,45 m2