PENENTUAN RANCANGAN PENAMBANGAN DENGAN METODE LERCHS-GROSSMAN 18 Mei 2015
Mohammad Arief Wibowo | 112 .12.0135 Kelas :C 1
PENENTUAN RANCANGAN PENAMBANGAN DENGAN METODE LERCHS-GROSSMAN 18 Mei 2015
Mohammad Arief Wibowo | 112 .12.0135 Kelas :C 2
PENENTUAN RANCANGAN PENAMBANGAN DENGAN METODE LERCHS-GROSSMAN 18 Mei 2015
Mohammad Arief Wibowo | 112 .12.0135 Kelas :C 3
PENENTUAN RANCANGAN PENAMBANGAN DENGAN METODE LERCHS-GROSSMAN 18 Mei 2015
Mohammad Arief Wibowo | 112 .12.0135 Kelas :C 4
PENENTUAN RANCANGAN PENAMBANGAN DENGAN METODE LERCHS-GROSSMAN 18 Mei 2015
Mohammad Arief Wibowo | 112 .12.0135 Kelas :C 5
Step 5
Net Value = 1198 x $1,000 = $ 1,198,000
Misal 1 blok = 10.000 ton/blok
Total Ton = 56 x 10.000 ton/blok = 560.000 ton
Ton ore = 50 blok x 10.000 ton/blok = 500.000 ton
Ton Waste = 6 x 10.000 ton/blok = 60.000 ton
SR =
Profitabilitas rata-rata per ton
2,139