DAFTAR HARGA SATUAN UPAH DAN BAHAN PEKERJAAN PEMBANGUNAN GEDUNG NEGARA TAHUN ANGGARAN 2012 NO. URAIAN HARGA UPAH HARGA SATUAN 1 2 3 4 1 Pekerja @Rp. 55,000.00 Org/Hari 2 Mandor -"- 80,000.00 OH 3 Tukang Batu -"- 80,000.00 OH 4 Tukang Kayu -"- 80,000.00 OH 5 Tukang Besi -"- 80,000.00 OH 6 Tukang Keramik -"- 80,000.00 OH 7 Tukang Plafond -"- 80,000.00 OH 8 Tukang Pasang Pipa -"- 80,000.00 OH 9 Tukang Cat -"- 80,000.00 OH 10 Kepala Tukang -"- 90,000.00 OH 11 Jaga Malam -"- 40,000.00 OM NO. URAIAN HARGA BAHAN-BAHAN HARGA SATUAN 1 2 3 4 A. TIMBUNAN / GALIAN 1 Tanah Timbun/Merah @Rp. 79,600.00 M3 2 Pasir Timbun / urug -"- 79,600.00 M3 3 Pasir Pasang -"- ### M3 4 Pasir Beton -"- ### M3 5 S i r t u -"- ### M3 6 Tanah Humus -"- 71,500.00 M3 B. BAHAN PEREKAT 1 Portland Cement (PC) @Rp. 1,225.00 Kg 2 Cement Putih -"- ### Zak 3 Lem Kayu -"- 15,000.00 Kg 4 Lem Vinyl / Karet -"- 20,000.00 Kg 5 Perekat Kaca -"- 76,500.00 Kg 6 Waterfroof -"- 52,300.00 Kg C. BATU / BATU CETAKAN 1 Batu Kerikil/koral 3 - 5 cm @Rp. 160,500.00 M3 2 Batu Kerikil/koral 5 - 7 cm -"- 145,500.00 M3 3 Batu Kerikil/Koral 7 - 10 cm -"- 130,500.00 M3 4 Batu Belah/Kali 10 - 15 cm -"- 115,500.00 M3 5 Batu Belah/Kali 15 - 20 cm -"- 100,500.00 M3 6 Batu Pecah 1 - 2 cm -"- 217,400.00 M3 7 Batu Pecah 2 - 3 cm -"- 204,900.00 M3 8 Batu Pecah 3 - 5 cm -"- 192,400.00 M3 9 Batu Pecah 5 - 7 cm -"- 177,400.00 M3 10 Batu Kacang/jagung 0,5 - 1 cm -"- 229,900.00 M3 11 Batu Splyt -"- 239,900.00 M3 12 Batu Bata Biasa 5x10x20 cm -"- 625.00 Bh 13 Batu Bata Mesin 5x10x20 cm -"- 875.00 Bh 14 Batu Bataco 6x12x24 cm -"- 4,180.00 Bh 15 Batu Krawang 10x10x20 cm -"- 8,070.00 Bh 16 Batu Krawang 10x15x15 c -"- 6,070.00 Bh 17 Batu Krawang 10x20x20 cm -"- 6,070.00 Bh 18 Concrete Block (CB) 10 -"- 740.00 Bh 19 Concrete Block (CB) 15 -"- 1,600.00 Bh 20 Concrete Block (CB) 20 -"- 2,920.00 Bh 21 Bondbeam 40x20x20 cm -"- 30,250.00 Bh 22 Con Block Warna type Hollan tbl 6 cm -"- 1,720.00 Bh 23 Con Block Warna type Uni Pave tbl 6 cm -"- 1,600.00 Bh 24 Con Block Warna type Dosex Six tbl 6 cm -"- 1,840.00 Bh 25 Con Block Warna type Hexagon tbl 6 cm -"- 1,710.00 Bh 26 Con Block K 125 -"- 2,000.00 Bh 27 Con Block K 175 -"- 2,200.00 Bh

Upload: dayatce

Post on 24-Oct-2015

826 views

Category:

Documents


4 download

DESCRIPTION

analisa

TRANSCRIPT

Page 1: Daftar Analisa Pu 2013

DAFTAR HARGA SATUAN UPAH DAN BAHAN

PEKERJAAN PEMBANGUNAN GEDUNG NEGARATAHUN ANGGARAN 2012

NO. URAIAN HARGA UPAH HARGA SATUAN

1 2 3 41 Pekerja @Rp. 55,000.00 Org/Hari2 Mandor -"- 80,000.00 OH3 Tukang Batu -"- 80,000.00 OH4 Tukang Kayu -"- 80,000.00 OH5 Tukang Besi -"- 80,000.00 OH6 Tukang Keramik -"- 80,000.00 OH7 Tukang Plafond -"- 80,000.00 OH8 Tukang Pasang Pipa -"- 80,000.00 OH9 Tukang Cat -"- 80,000.00 OH

10 Kepala Tukang -"- 90,000.00 OH11 Jaga Malam -"- 40,000.00 OM

NO. URAIAN HARGA BAHAN-BAHAN HARGA SATUAN

1 2 3 4

A. TIMBUNAN / GALIAN1 Tanah Timbun/Merah @Rp. 79,600.00 M32 Pasir Timbun / urug -"- 79,600.00 M33 Pasir Pasang -"- 101,000.00 M34 Pasir Beton -"- 101,000.00 M35 S i r t u -"- 114,000.00 M36 Tanah Humus -"- 71,500.00 M3B. BAHAN PEREKAT1 Portland Cement (PC) @Rp. 1,225.00 Kg2 Cement Putih -"- 137,600.00 Zak3 Lem Kayu -"- 15,000.00 Kg4 Lem Vinyl / Karet -"- 20,000.00 Kg5 Perekat Kaca -"- 76,500.00 Kg6 Waterfroof -"- 52,300.00 KgC. BATU / BATU CETAKAN1 Batu Kerikil/koral 3 - 5 cm @Rp. 160,500.00 M32 Batu Kerikil/koral 5 - 7 cm -"- 145,500.00 M33 Batu Kerikil/Koral 7 - 10 cm -"- 130,500.00 M34 Batu Belah/Kali 10 - 15 cm -"- 115,500.00 M35 Batu Belah/Kali 15 - 20 cm -"- 100,500.00 M36 Batu Pecah 1 - 2 cm -"- 217,400.00 M37 Batu Pecah 2 - 3 cm -"- 204,900.00 M38 Batu Pecah 3 - 5 cm -"- 192,400.00 M39 Batu Pecah 5 - 7 cm -"- 177,400.00 M3

10 Batu Kacang/jagung 0,5 - 1 cm -"- 229,900.00 M311 Batu Splyt -"- 239,900.00 M312 Batu Bata Biasa 5x10x20 cm -"- 625.00 Bh13 Batu Bata Mesin 5x10x20 cm -"- 875.00 Bh14 Batu Bataco 6x12x24 cm -"- 4,180.00 Bh15 Batu Krawang 10x10x20 cm -"- 8,070.00 Bh16 Batu Krawang 10x15x15 cm -"- 6,070.00 Bh17 Batu Krawang 10x20x20 cm -"- 6,070.00 Bh18 Concrete Block (CB) 10 -"- 740.00 Bh19 Concrete Block (CB) 15 -"- 1,600.00 Bh20 Concrete Block (CB) 20 -"- 2,920.00 Bh21 Bondbeam 40x20x20 cm -"- 30,250.00 Bh22 Con Block Warna type Hollan tbl 6 cm -"- 1,720.00 Bh23 Con Block Warna type Uni Pave tbl 6 cm -"- 1,600.00 Bh24 Con Block Warna type Dosex Six tbl 6 cm -"- 1,840.00 Bh25 Con Block Warna type Hexagon tbl 6 cm -"- 1,710.00 Bh26 Con Block K 125 -"- 2,000.00 Bh27 Con Block K 175 -"- 2,200.00 Bh

Page 2: Daftar Analisa Pu 2013

1 2 3 4

D. KAYU / LANGIT-LANGIT1 Balok Kayu Jati @Rp. 23,925,000.00 M32 Papan Kayu Jati -"- 24,104,440.00 M33 Balok Kayu Damar Laut -"- 11,414,250.00 M34 Papan Kayu Damar Laut -"- 12,615,750.00 M35 Balok Kayu Meranti Batu -"- 9,075,000.00 M36 Papan Kayu Meranti Batu -"- 9,729,000.00 M37 Balok Kayu Kapur -"- 6,490,000.00 M38 Papan Kayu Kapur -"- 6,790,000.00 M39 Balok Kayu Meranti Kls.II -"- 7,809,750.00 M3

10 Papan Kayu Meranti Kls.II -"- 8,410,500.00 M311 Kayu Sembarang/Bekisting -"- 4,500,000.00 M312 Kayu Bakar -"- 187,000.00 M313 Papan Lambsering/Rider -"- 225,000.00 M214 Kayu Lat Asbes 5x30x400 mm -"- 8,500.00 Btg15 Kayu Kaso 5 - 7 / 400 cm -"- 87,780.00 Btg16 Kayu Dolken / kayu laut Ø 4" / 4 m -"- 60,600.00 Btg17 Bambu Ø 6 - 8 / 600 cm -"- 13,750.00 Btg18 Bilik bambu -"- 16,340.00 M219 Kayu Profil 1" -"- 6,270.00 M'20 Kayu Profil 2" -"- 12,540.00 M'21 Kayu Profil 3" -"- 18,810.00 M'22 Kayu Profil 4" -"- 25,080.00 M'23 Profil Gypsum 2" -"- 4,600.00 M'24 Profil Gypsum 3" -"- 5,450.00 M'25 Profil Gypsum 4" -"- 6,660.00 M'26 Profil Gypsum 6" -"- 10,450.00 M'27 Playwood 120 x 240 tbl.18 mm -"- 243,200.00 Lbr28 Playwood 120 x 240 tbl.12 mm -"- 207,860.00 Lbr29 Playwood 120 x 240 tbl. 9 mm -"- 168,210.00 Lbr30 Playwood 120 x 240 tbl. 6 mm -"- 127,700.00 Lbr31 Playwood 120 x 240 tbl. 4 mm -"- 91,070.00 Lbr32 Teakwood 120 x 240 tbl. 3 mm -"- 54,450.00 Lbr33 Triplek Jati 120 x 240 tbl. 3 mm -"- 132,170.00 Lbr34 TriplekSungkai 120 x 240 tbl.3 mm -"- 144,180.00 Lbr35 Formica 120 x 240 cm -"- 74,250.00 Lbr36 Soft Board 120 x 240 tbl. 4 mm -"- 55,990.00 Lbr37 Soft Board 120 x 240 tbl. 6 mm -"- 84,150.00 Lbr38 Soft Board 120 x 240 tbl. 9 mm -"- 126,230.00 Lbr39 Soft Board 120 x 240 tbl.12 mm -"- 80,200.00 Lbr40 Gypsum 120 x 240 tbl. 6 mm -"- 65,100.00 Lbr41 Gypsum 120 x 240 tbl. 9 mm -"- 71,500.00 Lbr42 Gypsum 120 x 240 tbl.12 mm -"- 93,500.00 Lbr43 Asbes Lokal 100 x 100 cm -"- 13,400.00 Lbr44 Asbes Atrisco 100 x 100 cm t= 4 mm -"- 11,550.00 Lbr45 Asbes Atrisco 100 x 100 cm t= 5 mm -"- 15,200.00 Lbr46 Asbes Atrisco 100 x 100 cm t= 6 mm -"- 17,330.00 Lbr47 Akustik 30 x 30 cm -"- 8,540.00 Lbr48 Akustik 30 x 60 cm -"- 17,070.00 Lbr49 Akustik 60 x 120 cm -"- 68,290.00 Lbr50 Rangka Furing Celling Gypsum -"- 52,250.00 M²51 Rangka Furing Dinding Gypsum -"- 63,800.00 M²52 Tepung Dempul -"- 10,450.00 Kg53 Kain Kasa/Paper Tape -"- 57,750.00 Roll

Page 3: Daftar Analisa Pu 2013

1 2 3 4

E. BESI / ALLUMINIUM 1 Besi Beton Polos @Rp. 15,000.00 Kg2 Besi Beton Ulir -"- 15,000.00 Kg3 Besi Profil WF/INP -"- 23,500.00 Kg4 Besi Siku -"- 11,990.00 Kg5 Besi CNP -"- 13,090.00 Kg6 Besi Plat Strip -"- 11,880.00 Kg7 Besi Plat Polos -"- 13,630.00 Kg8 Kawat Besi Beton -"- 22,000.00 Kg9 Kawat Licin / seng polos -"- 16,140.00 Kg

10 Kawat Duri -"- 8,500.00 M'11 Kawat Nyamuk -"- 18,200.00 M212 Kawat Kasa -"- 13,920.00 M213 Kawat Harmonika # 1" -"- 30,400.00 M214 Kawat Burung -"- 12,710.00 M215 Pagar Kawat BRC 120 polos -"- 235,950.00 Lbr16 Pintu Besi -"- 590,000.00 M217 Pintu Gulung Besi -"- 500,000.00 M218 Pintu Lipat Besi -"- 940,000.00 M2

20 Pintu Rolling Door -"- 465,850.00 M221 Jerajak Besi Bermotif -"- 347,270.00 M222 Jerajak Besi Strip -"- 336,420.00 M223 Rangka Baja Ringan -"- 186,230.00 M224 Kosen Pintu Alluminium ( 80 x 210 ) Coklat -"- 405,350.00 Bh25 Kosen Pintu Alluminium ( 80 x 210 ) putih -"- 371,470.00 Bh26 Kosen Jendela Alluminium ( 120 x 60 ) coklat -"- 287,380.00 Bh27 Kosen Jendela Alluminium ( 120 x 60 ) putih -"- 248,050.00 Bh28 Pintu Alluminium ( 80 x 210 ) Coklat -"- 711,480.00 Bh29 Pintu Alluminium ( 80 x 210 ) putih -"- 609,840.00 Bh30 Jendela Alluminium + Kaca 5 mm ( 120 x 60 ) coklat -"- 304,920.00 Bh31 Jendela Alluminium + Kaca 5 mm ( 120 x 60 ) putih -"- 261,360.00 Bh32 Kosen Pintu / Jendela Alluminium Coklat -"- 78,650.00 M'33 Kosen Pintu / Jendela Alluminium putih -"- 66,550.00 M'34 Daun Jendela Alluminium coklat -"- 54,450.00 M'35 Daun Jendela Alluminium putih -"- 48,400.00 M'36 Profil Alluminium T -"- 8,470.00 M'37 Vention Blinds -"- 163,350.00 M238 Verticals Blinds -"- 175,450.00 M239 Bingkai Naco Niki hitam -"- 201,660.00 M240 Bingkai Naco Niki putih -"- 168,060.00 M241 Paku Beton 0,5 - 2" -"- 310.00 Bh42 Paku Beton 2" - 5" -"- 530.00 Bh43 Paku Biasa 0,5 - 2" -"- 18,000.00 Kg44 Paku Biasa 2 - 5" -"- 14,520.00 Kg45 Sekrup macam Ukuran -"- 25,650.00 Kg46 Sekrup 0,5 - 2" -"- 420.00 Bh47 Sekrup fisher -"- 25,650.00 Bh48 -"- 19,970.00 Bh49 -"- 45,380.00 Bh50 Bout Ramset / Dina bolt -"- 720.00 Bh51 Rangka Atap Twin light -"- 302,500.00 M²

Bout Ø 5/8" - 8"Bout Angker Ø 3/4" - 10"

Page 4: Daftar Analisa Pu 2013

1 2 3 4

F. PENUTUP LANTAI DAN DINDING1 Ubin granito 30 x 30 cm @Rp. 26,260.00 Bh2 Ubin granito 40 x 40 cm -"- 46,700.00 Bh3 Ubin granito 60 x 60 cm -"- 104,670.00 Bh4 Ubin Mosaik 30 x 30 cm -"- 14,500.00 Bh5 Ubin Marmer Ex.DN -"- 261,970.00 M26 Ubin teralux marmer 30 x 30 cm -"- 29,700.00 Bh7 Ubin teralux marmer 40 x 40 cm -"- 49,200.00 Bh8 Ubin teralux marmer 60 x 60 cm -"- 112,000.00 Bh9 Ubin keramik 10 x 20 cm -"- 900.00 Bh

10 Ubin keramik 15 x 15 cm -"- 1,400.00 Bh11 Ubin keramik 20 x 20 cm -"- 2,200.00 Bh12 Ubin keramik 20 x 25 cm -"- 2,500.00 Bh13 Ubin keramik 25 x 25 cm -"- 3,870.00 Bh14 Ubin keramik 30 x 30 cm -"- 5,500.00 Bh15 Ubin keramik 30 x 30 cm anti slip -"- 6,290.00 Bh16 Ubin keramik 40 x 40 cm -"- 9,900.00 Bh17 Ubin keramik artistik 5 x 20 cm -"- 1,100.00 Bh18 Ubin keramik artistik 10 x 10 cm -"- 1,300.00 Bh19 Ubin keramik artistik 10 x 20 cm -"- 1,850.00 Bh20 Ubin keramik Essenza 30 x 30 cm -"- 21,180.00 Bh21 Ubin keramik Essenza 40 x 40 cm -"- 57,700.00 Bh22 Porselin 11 x 11 cm putih -"- 1,100.00 Bh23 Porselin 11 x 11 cm, warna -"- 1,200.00 Bh24 Porselin 15 x 15 cm, putih -"- 2,250.00 Bh25 Porselin 15 x 15 cm, warna -"- 2,900.00 Bh26 Plint ubin teralux marmer 10 x 30 cm -"- 17,500.00 Bh27 Plint ubin teralux marmer 10 x 40 cm -"- 30,500.00 Bh28 Plint ubin teralux marmer 10 x 60 cm -"- 66,800.00 Bh29 Plint ubin granito 10 x 30 cm -"- 2,400.00 Bh30 Plint ubin granito 10 x 40 cm -"- 62,800.00 Bh31 Plint ubin granito 10 x 60 cm -"- 157,180.00 Bh32 Plint ubin keramik 10 x 30 cm -"- 2,400.00 Bh33 Plint ubin keramik 10 x 40 cm -"- 4,200.00 Bh34 Plint ubin keramik 10 x 60 cm -"- 8,110.00 Bh35 Plint ubin keramik 15 x 30 cm -"- 3,400.00 Bh36 Plint ubin keramik 15 x 40 cm -"- 7,740.00 Bh37 Plint ubin keramik 15 x 60 cm -"- 11,620.00 Bh38 Batu Lapis Dinding 7x3x24 -"- 2,040.00 Bh39 Batu tempel hitam -"- 104,500.00 M240 Batu Poros -"- 114,680.00 M241 Carpet -"- 90,750.00 M242 Carpet 80 % wool, 20 % nylon -"- 87,450.00 M243 Feltex carpet 100 % wool-T-21 -"- 85,250.00 M244 Underlyer tebal 6 mm / rubber corrugated -"- 104,500.00 M245 Vynil asbes 30 x 30 cm -"- 8,230.00 Bh46 Vynil karet 30 x 30 cm KL I -"- 9,800.00 Bh47 Vynil karet 30 x 30 cm KL II -"- 9,080.00 Bh48 Vynil motif kembang ex DN 30 x 30 cm -"- 9,440.00 Bh49 Vynil wall covering lebar 50 cm -"- 63,250.00 M250 Perquet Jati -"- 368,500.00 M251 Gymfloor -"- 79,750.00 M252 Paku Pancing 60 - 230 -"- 720.00 Bh53 Sekrup 3,5" -"- 410.00 Kg54 Sekrup 3,5" -"- 20,350.00 Kg

Page 5: Daftar Analisa Pu 2013

1 2 3 4

G. PENUTUP ATAP1 Atap Genteng Palentong @Rp. 1,670.00 Bh2 Atap Genteng Palentong super -"- 3,980.00 Bh3 Atap Genteng Kodok -"- 2,170.00 Bh4 Atap Genteng Beton -"- 5,970.00 Bh5 Atap Genteng Keramik -"- 10,400.00 Bh6 Atap Genteng Aspal -"- 11,320.00 Lbr7 Atap Sirap -"- 1,030.00 Bh8 Atap Genteng Metal/Multi Roof 35 -"- 73,100.00 Lbr9 Atap Genteng Asbes Cement 0,35 -"- 66,790.00 Lbr

10 Atap Aluminium gelombang tebal 0,55 -"- 98,180.00 Lbr11 Atap Seng Alumi Zinc warna 0,35 -"- 62,040.00 Lbr12 Atap Twin Light -"- 74,250.00 Lbr13 Atap Seng gelombang 3' x 6' bjls 35 -"- 73,890.00 Lbr14 Atap Seng Super Deck 3' x 6' tbl.0,30 -"- 68,750.00 Lbr15 Roof light fibreglass gelombang 180 x 90 cm -"- 46,390.00 Lbr16 Atap Asbes gelombang 1,8 x 1,05 tbl.4 mm -"- 28,840.00 Lbr17 Atap Asbes gelombang 2,1 x 1,05 tbl.4 mm -"- 93,170.00 Lbr18 Atap Asbes gelombang 2,4 x 1,05 tbl.4 mm -"- 108,130.00 Lbr19 Atap Asbes gelombang 2,7 x 1,05 tbl.4 mm -"- 113,300.00 Lbr20 Atap Asbes gelombang 1,8 x 0,92 tbl.5 mm -"- 70,950.00 Lbr21 Atap Asbes gelombang 2,1 x 0,92 tbl.5 mm -"- 88,770.00 Lbr22 Atap Asbes gelombang 2,4 x 0,92 tbl.5 mm -"- 97,020.00 Lbr23 Atap Asbes gelombang 2,7 x 0,92 tbl.5 mm -"- 106,810.00 Lbr24 Atap Asbes gelombang 1,8 x 1,08 tbl.6 mm -"- 103,620.00 Lbr25 Atap Asbes gelombang 2,1 x 1,08 tbl.6 mm -"- 120,450.00 Lbr26 Atap Asbes gelombang 2,4 x 1,08 tbl.6 mm -"- 128,370.00 Lbr27 Atap Asbes gelombang 2,7 x 1,08 tbl.6 mm -"- 155,430.00 Lbr28 Genteng bubung palentong -"- 9,350.00 Bh29 Genteng bubung palentong super -"- 12,740.00 Bh30 Genteng bubung kodok -"- 9,560.00 Bh31 Nok genteng Beton -"- 8,410.00 Bh32 Nok genteng Keramik -"- 16,220.00 Bh33 Nok genteng Aspal -"- 29,350.00 Bh34 Nok genteng Metal/Multi Roof (Decra bond) -"- 41,140.00 Bh35 Nok genteng Asbes gelomang Cement 0,35 -"- 33,770.00 Lbr36 Nok Alluminium standard 40 cm 18 swg 22 -"- 47,890.00 M237 Bubung/Nok Stel Gelombang 0,92 m' tbl.5 mm -"- 19,590.00 Lbr38 Bubung/Nok Stel Gelombang 1,05 m' tbl.4 mm -"- 25,990.00 Lbr39 Bubung/Nok Stel Gelombang 1,08 m' tbl.6 mm -"- 28,510.00 Lbr40 Bubung/Nok Paten 0,92 m' tbl.5 mm -"- 36,810.00 Lbr41 Bubung/Nok Paten 1,05 m' tbl.4 mm -"- 30,950.00 Lbr42 Bubung/Nok Paten 1,08 m' tbl.6 mm -"- 42,960.00 Lbr43 Bubung/Nok Stel Rata 0,92 m' tbl.5 mm -"- 36,080.00 Lbr44 Bubung/Nok Stel Rata 1,05 m' tbl.4 mm -"- 30,250.00 Lbr45 Bubung/Nok Stel Rata 1,08 m' tbl.6 mm -"- 40,600.00 Lbr46 Seng plat 3" x 6" bjls 35 -"- 115,500.00 Lbr47 Seng plat 3" x 6" bjls 30 -"- 103,950.00 Lbr48 Plastic aerator -"- 27,500.00 Bh49 Sisalation / aluminium foil -"- 77,200.00 M250 Paku Seng + Ring karet -"- 20,350.00 Kg51 Paku Seng + Ring karet -"- 510.00 Bh52 Paku hak panjang 15 cm -"- 30,530.00 Kg

Page 6: Daftar Analisa Pu 2013

1 2 3 4

H. KUNCI DAN KACA1 Kunci tanam antik @Rp. 214,500.00 Bh2 Kunci tanam biasa -"- 57,800.00 Bh3 Kunci tanam kamar mandi -"- 35,300.00 Bh4 Kunci silinder -"- 34,490.00 Bh5 Kunci selot -"- 27,230.00 Bh6 Kunci lemari -"- 12,340.00 Bh7 Engsel pintu 4" -"- 12,020.00 Bh8 Engsel jendela 3" -"- 11,250.00 Bh9 Engsel angin -"- 25,050.00 Bh

10 Kait angin -"- 19,120.00 Bh11 Rel pintu dorong -"- 160,330.00 Bh12 Sealent -"- 39,330.00 Kg13 Spring knip -"- 9,080.00 Bh14 Door closer -"- 109,750.00 Bh15 Door handle -"- 113,010.00 Bh16 Door stop -"- 38,120.00 Bh17 Espanyolet -"- 88,450.00 Bh18 Kaca Block 20 x 20 cm -"- 26,020.00 Bh19 Kaca Polos tbl. 3 mm -"- 87,120.00 M220 Kaca Polos tbl. 5 mm -"- 145,000.00 M221 Kaca Polos tbl. 8 mm -"- 232,000.00 M222 Kaca Reyben tbl. 5 mm -"- 176,900.00 M223 Kaca Reyben tbl. 8 mm -"- 308,980.00 M224 Kaca buram tbl.3 mm -"- 72,600.00 M225 Kaca buram tbl.5 mm -"- 111,320.00 M226 Kaca buram tbl.8 mm -"- 193,600.00 M227 Kaca cermin tebal 5 mm -"- 161,700.00 M228 Kaca cermin tebal 6 mm -"- 194,040.00 M229 Kaca cermin tebal 8 mm -"- 258,720.00 M230 Kaca patri -"- 169,400.00 M231 Kaca wireglass -"- 151,250.00 M232 Kaca Reyben Naco 30 x 60 cm tbl.5 mm -"- 13,590.00 Lbr33 Kaca Bening Naco 30 x 60 cm tbl.5 mm -"- 10,730.00 Lbr

I. CAT / MINYAK1 Cat Dasar @Rp. 21,400.00 Kg2 Cat Tembok setara Vinilex -"- 21,400.00 Kg3 Cat Minyak untuk Kayu -"- 48,600.00 Kg4 Cat Minyak untuk Besi -"- 48,060.00 Kg5 Cat Menie Kayu -"- 22,830.00 Kg6 Cat Menie Besi -"- 22,830.00 Kg7 Cat Sending -"- 54,450.00 Kg8 Cat Melamix -"- 45,000.00 Kg9 Cat Vernis Jadi -"- 37,850.00 Kg

10 Plamir -"- 23,230.00 Kg11 Dempul Gypsum -"- 7,700.00 Kg12 Dempul Cat -"- 17,000.00 Kg13 Minyak Cat -"- 17,000.00 Kg14 Minyak Bekisting -"- 6,290.00 Ltr15 Residu / Kolter -"- 25,230.00 Ltr16 Soda Api -"- 12,100.00 Kg17 Sabun -"- 10,290.00 Kg19 Kuas -"- 15,000.00 Bh20 Ampelas/Kertas Pasir -"- 3,800.00 Lbr22 Wall paper -"- 30,610.00 M2

Page 7: Daftar Analisa Pu 2013

1 2 3 4

J. SANITASI / PIPA1 Kloset duduk / monoblok Lengkap tangki @Rp. 2,197,200.00 Bh2 Kloset duduk / monoblok tanpa tangki -"- 1,391,500.00 Bh3 Kloset jongkok porselin -"- 159,300.00 Bh4 Bakkif Porselen -"- 3,025,000.00 Bh5 Wastafel -"- 510,640.00 Bh6 Urinoir -"- 557,480.00 Bh7 -"- 15,000.00 Bh8 -"- 77,200.00 Bh9 Kran Shower -"- 92,570.00 Bh

10 Kran Cebok -"- 72,240.00 Bh11 Bak fibreglass 0,3 M3 -"- 181,500.00 Bh12 Bak fibreglass 1 M3 -"- 522,720.00 Bh13 Bak cuci piring steinless 2 Lobang -"- 466,700.00 Bh14 Bak cuci piring teraso 2 Lobang -"- 282,250.00 Bh15 Tempat sabun keramik -"- 56,270.00 Bh16 -"- 15,000.00 Bh17 -"- 27,500.00 Bh18 -"- 12,500.00 Bh19 Instalasi air Bersih -"- 100,000.00 Ttk20 Instalasi air Kotor/Limbah -"- 125,000.00 Ttk21 -"- 11,250.00 M'22 -"- 17,790.00 M'23 -"- 20,090.00 M'24 -"- 19,240.00 M'25 -"- 27,350.00 M'26 -"- 56,270.00 M'27 -"- 63,400.00 M'28 -"- 95,950.00 M'29 -"- 136,000.00 M'30 -"- 201,100.00 M'31 -"- 345,820.00 M'32 Bodem 30 X 60 cm -"- 25,300.00 Bh33 -"- 5,540.00 M'34 -"- 7,440.00 M'35 -"- 13,620.00 M'36 -"- 19,670.00 M'37 -"- 23,190.00 M'38 -"- 26,620.00 M'39 -"- 29,840.00 M'40 -"- 49,920.00 M'41 -"- 14,770.00 M'42 -"- 20,140.00 M'43 -"- 29,520.00 M'44 -"- 37,580.00 M'45 -"- 47,600.00 M'46 -"- 50,220.00 M'47 -"- 14,770.00 M'48 -"- 20,520.00 M'49 -"- 29,520.00 M'50 -"- 33,560.00 M'51 -"- 37,580.00 M'52 -"- 47,600.00 M'53 -"- 52,440.00 M'54 55 Fitting Knee AW 1" -"- 5,230.00 Bh56 Fitting Tee AW 1" -"- 7,150.00 Bh57 Fitting Socht AW 1" -"- 4,680.00 Bh58 Bocht LL-D 1" -"- 24,750.00 Bh59 Union Socht 1" -"- 7,430.00 Bh60 D-Nipple 1" -"- 18,150.00 Bh

Kran air Ø 1/2" - 3/4"Kran air leher angsa Ø 1/2"

Floor Drain Ø 4" steinleesStop Kran Ø 3/4" Tutup Bak air Ø 1" Kuningan

Buis Beton 1/2 Ø 15 cmBuis Beton 1/2 Ø 20 cmBuis Beton 1/2 Ø 30 cmBuis Beton Ø 15 cmBuis Beton Ø 20 cmBuis Beton Ø 30 cmBuis Beton Ø 40 cmBuis Beton Ø 50 cmBuis Beton Ø 60 cmBuis Beton Ø 80 cmBuis Beton Ø 100 cm

Pipa PVC Tipe AW Ø 1/2"Pipa PVC Tipe AW Ø 3/4"Pipa PVC Tipe AW Ø 1"Pipa PVC Tipe AW Ø 11/2"Pipa PVC Tipe AW Ø 2"Pipa PVC Tipe AW Ø 21/2"Pipa PVC Tipe AW Ø 3"Pipa PVC Tipe AW Ø 4"Pipa Besi Hitam Ø 1/2"Pipa Besi Hitam Ø 3/4"Pipa Besi Hitam Ø 1"Pipa Besi Hitam Ø 11/2"Pipa Besi Hitam Ø 2"Pipa Besi Hitam Ø 21/2"Pipa Galvanis Ø 1/2"Pipa Galvanis Ø 3/4"Pipa Galvanis Ø 1"Pipa Galvanis Ø 11/4"Pipa Galvanis Ø 11/2"Pipa Galvanis Ø 2"Pipa Galvanis Ø 21/2"Fitting Pipa AW Ø 1" yang terdiri dari :

Page 8: Daftar Analisa Pu 2013

### 1 2 3 4

K. LISTRIK / ACSESORIES1 Lampu TL 1 x 20 W Lengkap kotak @Rp. 54,450.00 Set2 Lampu TL 1 x 40 W Lengkap kotak -"- 60,500.00 Set3 Lampu TL 2 x 20 W Lengkap kotak -"- 163,350.00 Set4 Lampu TL 2 x 40 W Lengkap kotak -"- 183,920.00 Set5 Lampu TL Bambu 1 x 20 W Lengkap -"- 108,900.00 Set6 Lampu TL Bambu 1 x 40 W Lengkap -"- 123,420.00 Set7 Lampu XL 5 W + Fitting -"- 25,410.00 Set8 Lampu XL 8 W + Fitting -"- 27,230.00 Set9 Lampu XL10 W + Fitting -"- 29,040.00 Set

10 Lampu XL14 W + Fitting -"- 33,280.00 Set11 Lampu XL18 W + Fitting -"- 33,880.00 Set12 Lampu XL24 W + Fitting -"- 38,720.00 Set13 Lampu Downlight 5 W Lengkap -"- 54,450.00 Set14 Lampu Pijar 5 w + Fitting -"- 8,250.00 Set15 Lampu Pijar 10 w + Fitting -"- 8,800.00 Set16 Lampu Pijar 15 w + Fitting -"- 9,350.00 Set17 Lampu Pijar 20 w + Fitting -"- 9,900.00 Set18 Lampu Pijar 25 w + Fitting -"- 10,450.00 Set19 Lampu Pijar 40 w + Fitting -"- 11,550.00 Set20 Stop Kontak Tanam -"- 10,290.00 Bh21 Saklar Tunggal -"- 14,520.00 Bh22 Saklar Ganda -"- 15,730.00 Bh23 Saklar Triple -"- 18,150.00 Bh24 Zekring box 1 grup -"- 26,620.00 Unt25 Zekring box 2 grup -"- 31,350.00 Unt26 Zekring box 3 grup -"- 38,500.00 Unt27 Zekring box 4 grup -"- 46,200.00 Unt28 MCB 2 Ampere -"- 35,200.00 Unt29 MCB 4 Ampere -"- 42,900.00 Unt30 MCB 6 Ampere -"- 67,760.00 Unt31 MCB 8 Ampere -"- 99,220.00 Unt32 -"- 1,120.00 M'33 -"- 1,930.00 M'34 -"- 8,250.00 M'35 -"- 4,020.00 M'36 -"- 9,990.00 M'37 -"- 15,970.00 M'38 Instalasi listrik titik api / Lampu Nyala -"- 101,750.00 Ttk

Medan, Maret 2008

DIKETAHUI OLEH : DIBUAT OLEH : TIM TEKNIS

Kepala Dinas Penataan Ruang dan 1. Ir. Jeremias Sinaga, MAP (……..….…….…)

Permukiman Prov. Sumatera Utara 2. Ir. Herimas (……..….…….…)

3. H. Sugiarto Bharata, ST (……..….…….…)

4. H. Ali Muhar, ST (……..….…….…)

Ir. H. Syafruddin Siregar, MSi 5. Sakula Karo karo, ST (……..….…….…)

Pembina Utama Muda 6. Ebenser Saragih, SE (……..….…….…)

NIP. 400025884 7. Sahat Hasudungan, ST (……..….…….…)

8. Ir. Tanogara Siahaan (……..….…….…)

9. Ali Fauzan, ST (……..….…….…)

10. Ir. Naimul Ahmad R. ST (……..….…….…)

11. Chandra, ST (……..….…….…)

Kabel Listrik NYA Ø 1,5 mmKabel Listrik NYA Ø 2,5 mmKabel Listrik NYA Ø 4 mmKabel Listrik NYM 2 Ø 1,5 mmKabel Listrik NYM 2 Ø 2,5 mmKabel Listrik NYM 2 Ø 4 mm

Page 9: Daftar Analisa Pu 2013

315 #REF! Rp. #REF!316 #REF! Rp. #REF!317 #REF! Rp. #REF!318 #REF! Rp. #REF!319 #REF! Rp. #REF!320 #REF! Rp. #REF!321 #REF! Rp. #REF!322 #REF! Rp. #REF!323 #REF! Rp. #REF!324 #REF! Rp. #REF!325 #REF! Rp. #REF!326 #REF! Rp. #REF!327 #REF! Rp. #REF!328 #REF! Rp. #REF!329 #REF! Rp. #REF!330 Keramik 20 x 20 Rp. 2,400.00331 0 Rp. 0.00 332 URAIAN HARGA UPAH Rp. 0.00 333 2 Rp. 0.00 334 Tukang Kayu Rp. ###335 Tukang Besi Rp. ###336 #REF! Rp. #REF!337 #REF! Rp. #REF!338 0 Rp. 0.00 339 BAHAN PEREKAT Rp. 0.00 340 Portland Cement (PC) Rp. 1,225.00 341 Memasang 1 buah kloset duduk Rp. 0342 Pasir Pasang Rp. ###343 #REF! Rp. #REF!344 #REF! Rp. #REF!345 #REF! Rp. #REF!346 #REF! Rp. #REF!347 #REF! Rp. #REF!348 #REF! Rp. #REF!349 #REF! Rp. #REF!350 #REF! Rp. #REF!351 #REF! Rp. #REF!352 #REF! Rp. #REF!353 #REF! Rp. #REF!354 #REF! Rp. #REF!

Diketahui Oleh :KEPALA DINAS PENATAAN RUANG DAN

PERMUKIMAN PROVINSI SUMATERA UTARA

Ir. KHAIRUL ANWAR, M.SIPEMBINA Tk.I

NIP.19630421 198602 1 002

Page 10: Daftar Analisa Pu 2013

#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!#REF!

0SATUANOrg/Hari

OHOHOHOHBhBhBhBhBhKgBhBhBhM2M2M2LbrLbrLbr

#REF!#REF!

Diketahui Oleh :KEPALA DINAS PENATAAN RUANG DAN

PERMUKIMAN PROVINSI SUMATERA UTARA

PEMBINA Tk.INIP.19630421 198602 1 002

Page 11: Daftar Analisa Pu 2013

Daftar Harga Satuan Upah dan Bahan 2013 11

DAFTAR HARGA SATUAN UPAH DAN BAHAN 2013

NO JENIS TENAGA KERJA HARGA (Rp) Satuan

1 Pekerja 75,000.00 Oh2 Tukang 100,000.00 Oh3 Mandor 100,000.00 Oh4 Operator 120,000.00 Oh5 Pembantu operator 80,000.00 Oh6 Supir / Driver 110,000.00 Oh7 Pembantu supir / driver 70,000.00 Oh8 Mekanik 120,000.00 Oh9 Pembantu mekanik 70,000.00 Oh

10 Kepala tukang 110,000.00 Oh

NO URAIAN / JENIS BAHAN BANGUNAN HARGA (Rp) Satuan

BAHAN GALIAN, BATU DAN SEMEN1 Batu gunung 158,230.00 m32 Batu kali 153,230.00 m33 Batu koral 168,320.00 m34 Batu Pecah 15/20 cm 225,000.00 m35 Batu pecah 5 - 7 cm 228,000.00 m36 Batu pecah 3 - 5 cm 232,000.00 m37 Batu pecah 2 - 3 cm 240,000.00 m38 Batu kelapa / belah 168,520.00 m39 Batu bata cetak mesin 875.00 Bh

10 Batu Terawang roster 8,170.00 Bh11 Batako 350.00 Bh12 Conblock tbl 6 cm mutu K-125 2,000.00 Bh13 Conblock tbl 8 cm mutu K-175 2,300.00 Bh14 Kerikil beton 2-3 cm 210,900.00 m315 Material pilihan 218,000.00 m316 Pasir pasang 106,050.00 m317 Pasir urug 83,380.00 m318 Semen portland (PC) 1,362.00 Kg19 Semen Mortar 4,400.00 Kg20 Semen warna 40 kg 144,480.00 Zak21 Sirtu /pasir batu 119,700.00 m322 Tanah timbun 83,850.00 m323 Urugan Humus 150,000.00 m324 Urugan porus 86,100.00 m3

BAHAN KAYU1 Gedek/ tepas bambu 31,500.00 Lbr2 Gedek/ tepas kelapa sawit 31,500.00 Lbr3 Ijuk 31,500.00 m24 Kayu kelas I 9,236,430.00 m35 Kayu kelas II 6,818,590.00 m36 Kayu kelas III 3,633,730.00 m37 Kayu dolken/bulat Ø 3" - 4" 20,000.00 Btg8 Kayu Profil (List) (Rp. 5000,- \M') 21,000.00 Btg9 Kayu setara dolken 21,000.00 Btg

10 Triplek 4 mm 70,350.00 Lbr11 Triplek 6 mm 105,000.00 Lbr12 Triplek 9 mm 129,150.00 Lbr13 Triplek Sungkai 3 mm 100,000.00 Lbr14 Plywood 120 x 240 tbl. 4 mm 75,800.00 Lbr

Page 12: Daftar Analisa Pu 2013

Daftar Harga Satuan Upah dan Bahan 2013 12

NO URAIAN / JENIS BAHAN BANGUNAN HARGA (Rp) Satuan

15 Plywood 120 x 240 tbl. 6 mm 103,600.00 Lbr16 Plywood 120 x 240 tbl. 9 mm 142,800.00 Lbr17 Plywood 120 x 240 tbl. 12 mm 188,400.00 Lbr18 Plywood 120 x 240 tbl. 18 mm 253,700.00 Lbr

BAHAN BESI, KACA, ALUMINIUM1 Aluminium Foil 37,000.00 M22 Besi beton polos 15,300.00 Kg3 Besi beton ulir 17,000.00 Kg4 Besi profil 23,500.00 Kg5 Besi baja IWF 23,500.00 Kg6 Besi plat strip 20,000.00 Kg7 Frame Aluminium Hollow 55,000.00 M'8 Jerjak besi 353,240.00 m29 Jerjak besi bermotif 380,000.00 m2

10 Jendela Besi 353,240.00 m211 Jendela nako (rangka + Kaca 5 mm) 192,500.00 m212 Kawat licin / Bronjong 16,940.00 Kg13 Kawat beton 23,100.00 Kg14 Kawat las 9,450.00 Dos15 Kawat Nyamuk 19,600.00 M216 Kawat jaring galvanis/BRC 320,000.00 Lbr17 Kaca jendela naco + rangka 126,000.00 m218 Kaca block/glass block 25,000.00 Bh19 Kaca Polos tbl. 3 mm 90,000.00 M220 Kaca Polos tbl. 5 mm 120,000.00 M221 Kaca Polos tbl. 8 mm 250,000.00 M222 Kaca buram/rayban tbl.5 mm 125,000.00 M223 Kaca cermin tebal 5 mm 160,000.00 M224 Kaca cermin tebal 8 mm 258,720.00 M225 Kaca patri 169,400.00 M226 Pintu gulung besi 525,000.00 m227 Pintu besi 619,500.00 m228 Pintu besi lipat harmonika 987,000.00 m229 Pagar besi strip 315,000.00 m230 Pagar BRC 120 polos 500,000.00 m231 Pintu KM/ WC PVC 391,650.00 Set32 Pintu alluminium 875,000.00 Set33 Profil alluminium 28,600.00 M'34 Plat Baja 24,670.00 Kg35 Paku Biasa 18,900.00 Kg36 Paku Skrup 26,250.00 Kg37 Paku Skrup 500.00 Bh38 Paku Beton 105.00 Bh39 Paku Ramset 3,040.00 Bh40 Paku Seng 42,380.00 Kg41 Paku hak panjang 15 cm 30,530.00 Kg42 Rolling Door Aluminium 665,500.00 M243 Sunscreen Aluminium 600,000.00 M244 Sealant 39,300.00 tube45 Sekrup Fixer 1,250.00 bh46 Verticals Blinds 185,000.00 M247 Venetion Blinds 175,000.00 M2

1 BAHAN PENUTUP LANTAI DAN DINDING2 Batu Templek 157,500.00 m23 Batu Palimanan 170,000.00 m24 Batu Marmo 180,000.00 m25 Batu Andhesit Polos 220,000.00 m26 Batu Andhesit Motif 255,000.00 m2

Page 13: Daftar Analisa Pu 2013

Daftar Harga Satuan Upah dan Bahan 2013 13

NO URAIAN / JENIS BAHAN BANGUNAN HARGA (Rp) Satuan

7 Batu Paras 210,000.00 m28 Batu Kacang Lokal (1 Zak = 40 kg) 80,000.00 Zak9 Batu Kacang Hitam (1 Zak = 20 kg) 120,000.00 Zak

10 Batu Kacang Warna (1 Zak = 20 kg) 85,000.00 Zak11 Batu Kacang Putih Salju, Maron (1 Zak = 20 kg) 165,000.00 Zak12 Keramik standart 10 x 20 cm 1,150.00 Bh13 Keramik standart 20 x 20 cm 2,400.00 Bh14 Keramik standart 20 x 25 cm 3,750.00 Bh15 Keramik standart 30 x 30 cm 6,360.00 Bh16 Keramik standart 40 x 40 cm 12,500.00 Bh17 Keramik standart 60 x 60 cm 50,000.00 Bh18 Keramik 40 x 40 cm setara granito 54,070.00 Bh19 Keramik 60 x 60 cm setara granito 89,600.00 Bh20 Keramik 40 x 40 cm setara Esenza 67,200.00 Bh21 Keramik 30 x 30 cm anti slip (KM) 7,800.00 Bh22 Granit 40 x 40 cm setara Indogress 42,500.00 Bh23 Granit 60 x 60 cm setara Indogress 81,700.00 Bh24 Geotextille non woven 52,500.00 m225 Gebalan rumput 21,000.00 m226 Keramik siku (bon bon) 9,890.00 m'27 Karpet wool 65,000.00 m228 Karpet wool + nylon 50,000.00 m229 Kanstin 15 x 30 x 45 cm 26,250.00 Bh30 Kanstin 15 x 30 x 60 cm 66,400.00 Bh31 Lantai Kayu Sintetis (gym floor) 210,000.00 m232 Porselin polos 30 x 30 cm 9,450.00 Bh33 Plint Keramik 10 x 30 cm 2,120.00 Bh34 Plint Keramik 10 x 40 cm 3,125.00 Bh35 Plint Keramik 10 x 60 cm 8,333.00 Bh36 Plint Granito 10 x 40 cm 18,400.00 Bh37 Plint Granito 10 x 60 cm 22,600.00 Bh38 Parquet kayu solid 315,500.00 m238 Ubin PC abu-abu 40 x 40 8,600.00 m239 Vynil asbes 30 x 30 cm 8,230.00 Bh40 Vynil karet 30 x 30 cm KL I 9,800.00 Bh41 Vynil karet 30 x 30 cm KL II 9,080.00 Bh42 Vynil motif kembang ex DN 30 x 30 cm 9,440.00 Bh43 Vynil wall covering lebar 50 cm 63,250.00 M244 Wallpaper 75,000.00 M'

BAHAN ATAP1 Atap asbes gelombang 35,280.00 Lbr2 Atap Zincalum Gelombang tbl 0.35 mm 13,650.00 Kaki3 Atap Super Dex 21,000.00 Kaki4 Atap plastik gelbang fiber 63,000.00 Lbr5 Atap genteng metal tbl 0,35 mm 86,000.00 m25 Atap Polycarbonate 250,000.00 m26 Atap Genteng Aspal 11,320.00 Bh7 Atap Aluminium gelombang tebal 0,55 98,180.00 Lbr8 Atap Sirap 1,030.00 Bh9 Genteng keramik 15,000.00 Kpg

10 Genteng Beton warna 8,070.00 Kpg11 Rabung genteng metal tbl 0,35 43,050.00 m'12 Rabung zinzcalum tbl 0,35 21,000.00 m'13 Rabung seng lbr 30 cm 23,940.00 Lbr14 Rabung genteng keramik 16,800.00 Kpg15 Rabung Genteng Beton 8,400.00 Kpg16 Rabung Alluminium standard 40 cm 18 swg 22 47,890.00 M217 Rangka atap zincalum 227,010.00 m218 Rangka atap baja ringan atap seng 190,000.00 m2

Page 14: Daftar Analisa Pu 2013

Daftar Harga Satuan Upah dan Bahan 2013 14

NO URAIAN / JENIS BAHAN BANGUNAN HARGA (Rp) Satuan

19 Rangka atap baja ringan atap genteng metal 220,000.00 m220 Rangka atap baja ringan genteng keramik/beton 275,000.00 m221 Rangka atap Polycarbonate 450,000.00 m222 Rabung asbes panjang 0,5m 11,550.00 Lbr23 Roof light fibreglass 46,390.00 Lbr24 Seng gelombang 7 kaki BJLS 20 56,510.00 Lbr25 Seng gelombang 7 kaki BJLS 35 76,650.00 Lbr26 Seng plat BJLS 35 76,650.00 lbr27 Talang kantong seng bjls 152,250.00 m'28 Lisplank GRC 50,000.00 m'29 List profil gypsum 13,450.00 m'30 Motif/Ornamen Lisplank (bunga) 14 x 40 cm 9,240.00 Bh

BAHAN PLAFOND/LANGIT-LANGIT1 Akustik 30 x 30 cm 8,540.00 Lbr2 Akustik 30 x 60 cm 17,070.00 Lbr3 Akustik 60 x 120 cm 68,290.00 Lbr4 Asbes 17,640.00 Kpg5 Dempul Gypsum 8,700.00 Kg6 Gypsum 120 x 240 tbl. 9 mm 71,500.00 Lbr7 Gypsum 120 x 240 tbl. 6 mm 62,000.00 Lbr8 Gypsum 120 x 240 tbl. 12 mm 93,000.00 Lbr9 Profil Gypsum 6" 12,000.00 M'

10 Profil Gypsum 4" 10,000.00 M'11 Profil Gypsum 3" 7,000.00 M'12 Profil Gypsum 2" 5,000.00 M'13 Panel Plafond Akustik Tbl 9 mm 33,600.00 Lbr14 Rangka furing plafond gypsum 79,800.00 m2

BAHAN SANITARI1 Bak air fiberglass 0,3 m3 186,000.00 Bh2 Bak air fiberglass 438,370.00 Bh3 Bak cuci piring 2 lobang komplet 816,900.00 Unt4 Filter plastik 15,750.00 m25 Floor drain 21,180.00 Bh6 Floor hardener 4,090.00 Kg7 Instalasi air bersih 70,000.00 Ttk8 Kloset duduk + bak air kwalitas Biasa 1,650,000.00 Bh9 Kloset duduk + bak air setara TOTO 2,500,000.00 Bh

10 Kloset jongkok kwalitas Biasa 167,790.00 Bh11 Kloset jongkok setara TOTO 250,000.00 Bh12 Kran air lokal 15,000.00 Bh13 Kran air bebek lokal 40,000.00 Bh14 Kran air setara san ei 117,600.00 Bh15 Kran air bebek setara SAN EI 147,000.00 Bh16 Kran Shower 150,000.00 Bh17 Pipa PVC Tipe AW Ø 1/2" 4,480.00 m'18 Pipa PVC Tipe AW Ø 3/4" 5,740.00 m'19 Pipa PVC Tipe AW Ø 1" 8,960.00 m'20 Pipa PVC Tipe AW Ø 11/2" 10,500.00 m'21 Pipa PVC Tipe AW Ø 2" 11,760.00 m'22 Pipa PVC Tipe AW Ø 21/2" 14,000.00 m'23 Pipa PVC Tipe AW Ø 3" 18,060.00 m'24 Pipa PVC Tipe AW Ø 4" 25,480.00 m'25 Pipa PVC Tipe AW Ø 6" 37,240.00 m'26 Pipa Galvanis 6 m Ø 1/2" 12,700.00 m'27 Pipa galvanis 6 m 3/4" 16,800.00 m'28 Pipa galvanis 6 m 1" 21,000.00 m'29 Pipa galvanis 6 m 1 1/2" 31,500.00 m'30 Pipa galvanis 6 m 2" 43,050.00 m'

Page 15: Daftar Analisa Pu 2013

Daftar Harga Satuan Upah dan Bahan 2013 15

NO URAIAN / JENIS BAHAN BANGUNAN HARGA (Rp) Satuan

31 Pipa galvanis 6 m 2 1/2" 52,500.00 m'32 Pipa porous 17,850.00 m'33 Riol uk. 1/2 Ø 150 mm panjang 1m 25,200.00 Bh34 Riol uk. 1/2 Ø 200 mm panjang 1m 47,250.00 Bh35 Riol uk. 1/2 Ø 300 mm panjang 1m 48,510.00 Bh36 Riol uk. Ø 150 mm panjang 1m 44,100.00 Bh37 Riol uk. Ø 200 mm panjang 1m 49,350.00 Bh38 Riol uk. Ø 300 mm panjang 1m 74,550.00 Bh39 Riol uk. Ø 400 mm panjang 1m 105,000.00 Bh40 Riol uk. Ø 500 mm panjang 1m 141,750.00 Bh41 Riol uk. Ø 600 mm panjang 1m 183,750.00 Bh42 Riol uk. Ø 800 mm panjang 1m 273,000.00 Bh43 Riol uk. Ø 1000 mm panjang 1m 498,750.00 Bh44 Stop Kran 3/4" 25,000.00 Bh45 Septictank kap. 3 M³ 3,832,500.00 unt46 Tempat sabun keramik 10 x 20 cm 38,850.00 Bh47 Urinoir 840,000.00 Bh48 Wastafel biasa 525,000.00 Bh49 Wastafel setara TOTO 1,000,000.00 Bh

BAHAN CAT1 Cat Minyak 52,500.00 Kg2 Cat tembok setara paragon 19,060.00 Kg3 Cat tembok setara vinilex 24,850.00 Kg4 Cat Vernish 56,500.00 Kg5 Cat meni besi 35,280.00 Kg6 Cat meni kayu 35,280.00 Kg7 Cat dasar 38,850.00 Kg8 Filler 22,050.00 Kg9 Kuas 15,750.00 Bh

10 Plamir 8,080.00 Kg11 Residu/colter 7,700.00 Ltr12 Soda Api 15,000.00 Kg

BAHAN KUNCI DAN ALAT PENGGANTUNG1 Door closer 210,000.00 Bh2 Door holder 105,000.00 Bh3 Door stop 38,120.00 Bh4 Engsel Pintu nylon 4 " 14,120.00 Psg5 Engsel jendela nylon 3 " 8,400.00 Psg6 Grendel besar 4" 25,000.00 Bh7 Grendel besar 3" 20,000.00 Bh8 Hak angin biasa 7,030.00 Psg9 Handle jendela biasa 5,250.00 Bh

10 Kunci tanam biasa 4" 65,000.00 Bh11 Kunci tanam antik 6" 165,000.00 Bh12 Kunci lock besar uk. 4 " 57,000.00 Bh13 Kunci silinder 36,000.00 Bh14 Kunci selot 27,230.00 Bh15 Kait angin 19,120.00 Bh16 Rel pintu dorong 160,330.00 Bh

BAHAN LISTRIK/ELECTRCAL1 Bok sekering 1 group 40,000.00 Set2 Bok sekering 2 group 50,000.00 Set3 Instalasi titik nyala 108,500.00 Ttk4 Instalasi stop kontak 108,500.00 Ttk5 Lampu XL 18 watt komplet 32,000.00 set6 Lampu XL 10 watt komplet 29,000.00 set7 Lampu XL 24 watt komplet 38,000.00 set

Page 16: Daftar Analisa Pu 2013

Daftar Harga Satuan Upah dan Bahan 2013 16

NO URAIAN / JENIS BAHAN BANGUNAN HARGA (Rp) Satuan

8 Lampu TL 1 x 20 watt komplet 80,000.00 set9 Lampu TL 1 x 40 watt komplet 120,000.00 set

10 Lampu TL 2 x 20 watt komplet 160,000.00 set11 Lampu TL 2 x 40 watt komplet 240,000.00 set12 Lampu Pijar 40 watt + fitting 35,000.00 set13 MCB 2A 35,000.00 Bh14 MCB 4A 42,000.00 Bh15 MCB 6A 65,000.00 Bh16 MCB 8A 90,000.00 Bh17 Saklar seri tanam 16,000.00 Bh18 Saklar tunggal tanam 12,500.00 Bh19 Saklar tripel tanam 19,000.00 Bh20 Stop Kontak 15,000.00 Bh

BAHAN MINYAK DAN PENDUKUNG LAINNYA1 Amplas 3,000.00 Lbr2 Bensin 4,500.00 Ltr3 Dempul 8,190.00 Kg4 Lem vinyl 25,000.00 Kg5 Lem kayu 15,750.00 Kg6 Lem Kuning 21,000.00 Kg7 Hot roll sheet 933,450.00 Ton8 Kipas angin Stainlesteal Lengkap 1,050,000.00 Bh9 Minyak pelumas / silinder 40,900.00 Ltr

10 Minyak gemuk 21,100.00 Ltr11 Minyak solar 4,500.00 Ltr12 Minyak lampu / tanah 8,820.00 Ltr13 Kerosene 8,820.00 Ltr14 Minyak bekisting 26,250.00 Kg15 Minyak gerdang 28,350.00 Ltr16 Minyak cat 12,700.00 Ltr17 Oxygen las 10,500.00 Kg18 Plastic aerator 27,500.00 Bh19 Sabun 10,290.00 Kg

Diketahui Oleh :KEPALA DINAS PENATAAN RUANG DAN

PERMUKIMAN PROVINSI SUMATERA UTARA

Ir. EDDY SAPUTRA SALIM, M.SiPEMBINA TK. I

NIP. 19570605 198703 1 012

Page 17: Daftar Analisa Pu 2013

Rekapitulasi Analisa Biaya Kanstruksi 2013 17

REKAPITULASI ANALISA HARGA SATUAN PEKERJAAN 2013

PEKERJAAN PERSIAPANPA 6.1 1 M' Pagar Sementara dari kayu tinggi 2 meter Rp 260,987.75PA 6.2 1 M' Pagar sementara dari seng gelombang tinggi 2 meter Rp 245,038.42PA 6.4 1 M' Pengukuran dan Pemasangan bouplank Rp 101,796.70PA 6.8 1 M² Membersihkan lapangan dan perataan Rp 14,375.00PA 6.12 1 M² Pembuatan jalan sementara Rp 155,630.08PA 6.13 1 M³ Bongkaran beton betulang Rp 613,323.75PA 6.14 1 M³ Bongkaran dinding tembok bata merah Rp 460,000.00PA 6.15 1 M' Pasangan pagar kawat jaring galvanis, tinggi 1.00 m Rp 168,900.50

PEKERJAAN TANAHPT 6.1 1 m³ Galian tanah biasa sedalam 1 meter Rp 67,562.50PT 6.2 1 m³ Galian tanah biasa sedalam 2 meter Rp 82,800.00PT 6.3 1 m³ Galian tanah biasa sedalam 3 meter Rp 98,267.50PT 6.4 1 m³ Galian tanah keras sedalam 1 meter Rp 89,930.00PT 6.5 1 m³ Galian tanah cadas sedalam 1 meter Rp 136,275.00PT 6.6 1 m³ Galian tanah lumpur sedalam 1 meter Rp 108,675.00PT 6.7 1 m² Pekerjaan stripping setinggi 1 meter Rp 4,887.50PT 6.8 1 m³ Pembuangan tanah sejauh 15 meter Rp 29,612.50PT 6.9 1 m³ Urugan kembali (1/3 dari koefisien galian) Rp 22,520.83PT 6.10 1 m³ Pemadatan tanah Rp 48,875.00PT 6.11 1 m³ Urugan pasir Rp 142,089.40PT 6.12 1 m³ Pasang lapisan pudel campuran 1:3:7 stabilisasi tanah Rp 268,943.88PT 6.13 1 m³ Pasang lapisan pudel campuran 1:5 stabilisasi tanah Rp 248,159.88PT 6.14 1 m³ Lapisan ijuk tebal 10 cm untuk bidang resapan Rp 232,012.50PT 6.15 1 m³ Urug sirtu padat untuk peninggian lantai bangunan Rp 189,623.50

PEKERJAAN PONDASIPP 6.1 1 M³ Pasang pondasi batu belah 1 Pc : 3 Pp Rp 919,779.49PP 6.2 1 M³ Pasang pondasi batu belah 1 Pc : 4 Pp Rp 862,962.30PP 6.3 1 M³ Pasang pondasi batu belah 1 Pc : 5 Pp Rp 823,599.18PP 6.4 1 M³ Pasang pondasi batu kosong Rp 460,809.60PP 6.5 1 M³ Pasang pondasi siklop 40 % batu kali Rp 2,175,646.82PP 6.6 1 M³ Pasang pondasi sumuran diameter 100 Cm Rp 889,483.03

PEKERJAAN DINDINGPD 6.1. 1 M² Pasang bata merah tebal 1 bata, 1 Pc : 2 Pp Rp 299,495.65PD 6.2 1M² Pasang bata merah tebal 1 bata, 1Pc : 3 Pp Rp 284,312.72PD 6.3 1 m² Pasang bata merah tebal 1 bata, 1Pc : 4 Pp Rp 274,532.31PD 6.6 1 m² Pasang bata merah tebal 1 bata, 1Pc : 3 Kp : 10 Pp Rp 248,674.37PD 6.7 1 m² Pasang bata merah tebal 1/2 bata, 1Pc : 2 Pp Rp 145,118.27PD 6.8 1 m² Pasang bata merah tebal 1/2 bata, 1Pc : 3 Pp Rp 138,188.53PD 6.9 1 m² Pasang bata merah tebal 1/2 bata, 1Pc : 4 Pp Rp 134,059.12PD 6.10 1 m² Pasang bata merah tebal 1/2 bata, 1Pc : 5 Pp Rp 131,452.37PD 6.11 1 m² Pasang bata merah tebal 1/2 bata, 1Pc : 6 Pp Rp 129,810.03PD 6.14 1 m² Pasang bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 1 Pp Rp 113,025.93PD 6.15 1 m² Pasang bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 2 Pp Rp 114,239.24PD 6.22 1 m² Pasang terawang (roster) 12 x 11 x 24 cm, 1 Pc : 3 Pp Rp 348,060.84PD 6.23 1 m² Pasang terawang (roster) 12 x 11 x 24 cm, 1 Pc : 4 Pp Rp 343,727.81

PEKERJAAN PLESTERANPL 6.1 1 M² Plesteran 1 Pc : 1 Pp, tebal 15 mm Rp 72,982.74PL 6.2 1 M² Plesteran 1 Pc : 2 Pp, tebal 15 mm Rp 65,200.50PL 6.3 1 M² Plesteran 1 Pc : 3 Pp, tebal 15 mm Rp 61,732.07PL 6.4 1 M² Plesteran 1 Pc : 4 Pp, tebal 15 mm Rp 59,448.19PL 6.5 1 M² Plesteran 1 Pc : 5 Pp, tebal 15 mm Rp 58,038.09PL 6.9 1 M² Plesteran 1 Pc : 3 Pp, tebal 15 mm Rp 59,045.34

Page 18: Daftar Analisa Pu 2013

Rekapitulasi Analisa Biaya Kanstruksi 2013 18

REKAPITULASI ANALISA HARGA SATUAN PEKERJAAN 2013

PL 6.10 1 M² Plesteran 1 Pc : 8 Pp, tebal 15 mm Rp 55,576.05PL 6.13 1 M² Plesteran 1 Pc : 2 Pp, tebal 20 mm Rp 87,204.65PL 6.14 1 M² Plesteran 1 Pc : 3 Pp, tebal 20 mm Rp 69,470.08PL 6.15 1 M² Plesteran 1 Pc : 4 Pp, tebal 20 mm Rp 79,494.26PL 6.16 1 M² Plesteran 1 Pc : 5 Pp, tebal 20 cm Rp 77,654.78PL 6.19 1 M² Berapen 1 Pc : 5 Pp, tebal 15 mm Rp 34,785.09PL 6.20 1 M² Plesteran skoning 1 Pc : 2 Pp, tebal 10 mm Rp 60,788.60PL 6.23 1 M² Plesteran Ciprat 1 Pc : 2 Pp Rp 47,863.16PL 6.24 1 M² Finishing siar pasangan dinding bata merah (= 20 m') Rp 28,362.56PL 6.25 1 M² Finishing siar psngn dinding conblock ekspose(=8 m') Rp 13,534.58PL 6.26 1 M² finishing siar pasangan batu kali adukan 1 Pc : 2 Pp Rp 58,141.33PL 6.27 1 M² Acian Rp 36,255.48

PEKERJAAN KAYUPK 6.1 1 M³ Pasang kusen pintu dan jendela kayu kelas I Rp 15,054,015.20PK 6.2 1 M³ Pasang kusen pintu dan jendela kayu kelas II Rp 12,304,635.45PK 6.3 1 M² Pasang pintu klamp standar, kayu kelas II Rp 481,031.89PK 6.4 1 M² Pasang pintu klamp sederhana, kayu kelas III Rp 334,528.33PK 6.5 1 M² Pasang daun pintu panel, kayu kelas I Rp 908,882.03PK 6.5.A 1 M² Pasang daun pintu panel, kayu kelas II Rp 797,661.39PK 6.6 1 M² Pasang pintu dan jendela kaca, kayu kelas I Rp 640,319.22PK 6.6.A 1 M² Pasang pintu dan jendela kaca, kayu kelas II Rp 573,586.83PK 6.7 1 M² Pasang pintu dan jendela jalusi, kayu kelas I Rp 1,163,807.50PK 6.7.A 1 M² Pasang pintu dan jendela jalusi, kayu kelas II Rp 985,854.47PK 6.8 1 M² Buat daun pintu kayu lapis tripleks rangkap, Rp 619,110.26

rangka tertutup kayu kelas IIPK 6.9 1 M² Buat pintu tripleks rangkap,rangka ekspose kayu kelas I Rp 742,491.30PK 6.9.A 1 M² Buat pintu tripleks rangkap,rangka ekspose kayu kelas II Rp 671,310.09PK 6.10 1 M² Pasang jalusi kusen, kayu kelas I Rp 992,186.42PK 6.10.A 1 M² Pasang jalusi kusen, kayu kelas II Rp 825,355.46PK 6.13 1 M³ Pasang kontruksi kuda2 konvensional kayu kelas II Rp 10,992,032.35PK 6.14 1 M³ Pasang kontruksi kuda2 ekspose kayu kelas I Rp 16,395,154.40PK 6.15 1 M³ Pasang kontruksi gordeng kayu kelas II Rp 10,175,601.35PK 6.16 1 M² Pasang rangka atap genteng keramik, kayu kelas II Rp 165,407.01PK 6.17 1 M² Pasang rangka atap genteng beton kayu kelas II Rp 193,635.97PK 6.18 1 M² Pasang rangka atap sirap, kayu kelas II Rp 1,324,532.45PK 6.19 1 M² Pasang rangka langit2 uk. 50 x 100 cm, kayu kelas II Rp 184,961.73PK 6.19.A 1 M² Pasang rangka langit2 uk. 50 x 100 cm, kayu kelas III Rp 128,557.86PK 6.20 1 M² Pasang rangka langit2 uk. 60 x 60 cm, kayu kelas II Rp 189,943.22PK 6.20.A 1 M² Pasang rangka langit2 uk. 60 x 60 cm, kayu kelas III Rp 130,243.02PK 6.21 1 M' Pasang lisplank uk. 3 x 20 cm, kayu kelas I Rp 151,619.96PK 6.21.A 1 M' Pasang lisplank uk. 3 x 20 cm, kayu kelas II Rp 121,590.39PK 6.22 1 M' Pasang lisplank uk. 3 x 30 cm, kayu kelas I Rp 152,657.59PK 6.22.A 1 M' Pasang lisplank uk. 3 x 30 cm, kayu kelas II Rp 122,071.91PK 6.23 1 M² Pasang rangka dinding pemisah 60x120 cm,kayu kelas II Rp 294,118.85PK 6.23.A 1 M² Pasang rangka dinding pemisah 60x120 cm, kayu kelas III Rp 191,566.36PK 6.24 1 M² Pasang dinding pemisah tripleks rangkap, Rp 271,285.51

rangka kayu kelas IIIPK 6.25 1 M² Pasang dinding pemisah tripleks rangkap, Rp 397,528.00

rangka kayu kelas IIPK 6.26 1 M² Pasang dinding lambriziring dari papan kayu kelas I Rp 366,024.89PK 6.27 1 M² Pasang dinding lambriziring dari tripleks uk. 120 x 140 cm Rp 45,356.00PK 6.28 1 M² Pasang dinding bilik, rangka kayu kelas III Rp 69,920.00

PEKERJAAN BETONPB 6.1 1 M³ Membuat beton mutu f'c = 7.4 Mpa (K 100), Rp 807,972.14

slump (12 ± 2) cm, w/c = 0.87 (1PC : 3,5PB : 4KR)

Page 19: Daftar Analisa Pu 2013

Rekapitulasi Analisa Biaya Kanstruksi 2013 19

REKAPITULASI ANALISA HARGA SATUAN PEKERJAAN 2013

PB 6.2 1 M³ Membuat beton mutu f'c = 9.8 Mpa (K 125), Rp 852,097.50slump (12 ± 2) cm, w/c = 0.78 (1PC : 3PB : 3,5KR)

PB 6.3 1 M³ Membuat beton mutu f'c = 12.2 Mpa (K 150), Rp 886,525.79slump (12 ± 2) cm, w/c = 0.72 (1PC : 2,5PB : 3,5KR)

PB 6.4 1 M³ Membuat lantai kerja beton mutu f'c=7.4 Mpa (K100), Rp 736,753.25slump(3-6)cm,w/c=0.87 (1PC : 3PB : 5KR)

PB 6.5 1 M³ Membuat beton mutu f'c = 14.5 Mpa (K 175), Rp 927,522.62slump (12 ± 2) cm, w/c = 0.66 (1PC : 2,5PB : 3KR)

PB 6.6 1 M³ Membuat beton mutu f'c = 16.9 Mpa (K 200), Rp 966,164.25slump (12 ± 2) cm, w/c = 0.61 (1PC : 1PB : 3KR)

PB 6.7 1 M³ Membuat beton mutu f'c = 19.3 Mpa (K 225), Rp 995,775.86slump (12 ± 2) cm, w/c = 0.58 (1PC : 2PB : 3KR)

PB 6.8 1 M³ Membuat beton mutu f'c = 21.7 Mpa (K 250), Rp 1,014,345.18slump (12 ± 2) cm, w/c = 0.56 (1PC : 2PB : 2,7KR)

PB 6.9 1 M³ Membuat beton mutu f'c = 24.0 Mpa (K 275), Rp 1,046,036.03slump (12 ± 2) cm, w/c = 0.53 (1PC : 1,5PB : 2,5KR)

PB 6.10 1 M³ Membuat beton mutu f'c = 26.4 Mpa (K 300), Rp 1,055,941.99slump (12 ± 2) cm, w/c = 0.52 (1PC : 1,5PB : 2,5KR)

PB 6.11 1 M³ Membuat beton mutu f'c = 28.8 Mpa (K 325), Rp 1,144,178.46slump (12 ± 2) cm, w/c = 0.49 (1PC : 1,5PB : 2KR)

PB 6.12 1 M³ Membuat beton mutu f'c = 31.2 Mpa (K 350), Rp 1,157,055.17slump (12 ± 2) cm, w/c = 0.48 (1PC : 1,5PB : 2KR)

PB 6.17 Pembesian 10 kg besi polos / besi ulir Rp 204,165.25PB 6.18 Pasang 10 kg kabel preetressed polos/strands Rp 199,772.25PB 6.20 Pasang 1 M² bekisting untuk pondasi Rp 257,719.83PB 6.21 Pasang 1 M² bekisting untuk sloof Rp 269,074.53PB 6.22 Pasang 1 M² bekisting untuk kolom Rp 500,331.13PB 6.23 Pasang 1 M² bekisting untuk balok Rp 523,855.27PB 6.24 Pasang 1 M² bekisting untuk plat lantai Rp 592,331.13PB 6.25 Pasang 1 M² bekisting untuk dinding Rp 520,750.13PB 6.26 Pasang 1 M² bekisting untuk tangga Rp 457,033.86PB 6.27 Pasang 1 M² jembatan untuk pengecoran beton Rp 155,101.04PB 6.28 Pasang 1 M³ pondasi beton bertulang (150kg besi + bekisting) Rp 5,322,624.35PB 6.29 Pasang 1 M³ sloof beton bertulang (200 kg besi + bekisting) Rp 6,685,829.87PB 6.30 Membuat 1 M³ kolom beton bertulang (300 kg besi + bekisting) Rp 11,587,933.03PB 6.31 Membuat 1 M³ balok beton bertulang (200 kg besi + bekisting) Rp 8,908,709.83PB 6.32 Membuat 1 M³ plat beton bertulang (150 kg besi + bekisting) Rp 7,990,461.51PB 6.33 Membuat 1 M³ dinding beton bertulang (150 kg besi+bekisting) Rp 7,785,433.99PB 6.34 Membuat 1 M³ dinding beton bertulang (200 kg besi+bekisting) Rp 8,158,752.57PB 6.35 Membuat 1 m' kolom praktis beton bertulang (11 x 11) cm Rp 95,954.11PB 6.36 Membuat 1 m' balok beton bertulang (10 x 15) cm Rp 130,982.86

PEKERJAAN PENUTUP ATAPPPA 6.7 1 M² Pasang roof light fiberglass ( 180 x 90 ) cm Rp 54,566.35PPA 6.11 1 M² Pasang atap asbes gelombang ( 1,80 x 0,92 m ) x 5 mm Rp 58,092.94PPA 6.22 1 M' Pasang bubung stel gelombang 0,92 m Rp 42,100.35PPA 6.30 1 M² Pasang atap genteng beton Rp 133,902.55PPA 6.31 1 M² Pasang atap genteng aspal Rp 330,952.18PPA 6.32 1 M² Pasang atap genteng metal / Multi Roof Rp 136,390.00PPA 6.33 1 M² Pasang atap sirap Rp 122,567.00PPA 6.34 1 M' Pasang nok genteng beton Rp 122,199.23PPA 6.35 1 M' Pasang nok genteng aspal Rp 139,420.32PPA 6.36 1 M' Pasang nok genteng metal Rp 95,333.85PPA 6.37 1 M' Pasang nok sirap Rp 112,399.11PPA 6.38 1 M2 Pasang atap seng gelombang Rp 82,351.73PPA 6.39 1 M' Pasang atap nok seng Rp 50,108.49PPA 6.40 1 M2 Pasang atap aluminium Rp 142,519.04

Page 20: Daftar Analisa Pu 2013

Rekapitulasi Analisa Biaya Kanstruksi 2013 20

REKAPITULASI ANALISA HARGA SATUAN PEKERJAAN 2013

PPA 6.41 1 M2 Pasang nok aluminium Rp 90,032.58PPA 6.42 1 M2 Pasang aluminium foil / sisalation Rp 64,917.50

PEKERJAAN KUNCI DAN KACAPKK 6.1 1 buah pasang kunci tanam antik Rp 328,785.00PKK 6.2 1 buah pasang kunci tanam biasa Rp 134,952.50PKK 6.3 1 buah pasang kunci tanam kamar mandi Rp 99,446.25PKK 6.4 1 buah pasang kunci silinder Rp 99,992.50PKK 6.5 1 buah pasang engsel pintu Rp 36,765.50PKK 6.6 1 buah pasang engsel jendela kupu-kupu Rp 23,345.00PKK 6.7 1 buah pasang engsel angin Rp 36,489.50PKK 6.9 1 buah pasang kait angin Rp 42,515.50PKK 6.10 1 buah pasang door closer Rp 309,925.00PKK 6.11 1 buah pasang kunci selot Rp 58,684.50PKK 6.12 1 buah pasang pegangan pintu / door holder Rp 189,175.00PKK 6.13 1 buah pasang door stop Rp 57,523.00PKK 6.14 1 buah pasang rel pintu dorong Rp 266,489.50PKK 6.15 1 buah pasang kunci lemari Rp 48,403.50PKK 6.16 1 M² pasang kaca, tebal 3 mm Rp 134,377.50PKK 6.17 1 M² pasang kaca, tebal 5 mm Rp 173,008.88PKK 6.18 1 M² pasang kaca, tebal 8 mm Rp 349,858.18PKK 6.19 1 M² pasang kaca buram, tebal 5 mm Rp 181,595.35PKK 6.20 1 M² pasang kaca cermin, tebal 5 mm Rp 223,608.88PKK 6.21 1 M² pasang kaca cermin, tebal 8 mm Rp 349,858.18PKK 6.23 1 M² pasang kaca "wireglass" , tebal 5 mm Rp 212,540.13PKK 6.24 1 M² pasang kaca patri, tebal 5 mm Rp 248,503.50PKK 6.24.A 1 M² pasang kaca Reyben, tebal 5 mm Rp 179,333.88

PEKERJAAN PENUTUP LANTAI DAN DINDINGPPL 6.1 1 M² Pasang lantai ubin abu-abu ukuran 40 x 40 cm Rp 125,485.53PPL 6.9 1 M² Pasang lantai ubin granit ukuran 40 x 40 cm Rp 389,356.02PPL 6.10 1 M² Pasang lantai ubin granit ukuran 30 x 30 cm Rp 426,358.42PPL 6.13 1 M² Pasang lantai ubin teralux marmer ukuran 60 x 60 cm Rp 463,433.27PPL 6.14 1 M² Pasang lantai ubin teralux marmer ukuran 40 x 40 cm Rp 440,440.17PPL 6.15 1 M² Pasang lantai ubin teralux marmer ukuran 30 x 30 cm Rp 473,316.14PPL 6.24 1 M' Pasang plint ubin granit uk. 10 x 40 cm Rp 78,466.83PPL 6.25 1 M' Pasang plint ubin granit uk. 10 x 30 cm Rp 93,434.08PPL 6.28 1 M' Pasang plint ubin teralux marmer uk. 10 x 60 cm Rp 152,986.83PPL 6.29 1 M' Pasang plint ubin teralux marmer uk. 10 x 40 cm Rp 115,341.58PPL 6.30 1 M' Pasang plint ubin teralux marmer uk 10 x 30 cm Rp 93,434.08PPL 6.32 1 M² Pasang lantai keramik artistik ukuran 10 x 20 cm Rp 125,988.54PPL 6.33 1 M² Pasang lantai keramik artistik uk. 5 x 20 cm Rp 127,857.75PPL 6.35 1 M² Pasang lantai keramik uk. 30 x 30 cm Rp 223,276.47PPL 6.36 1 M² Pasang lantai keramik uk 20 x 20 cm Rp 210,724.26PPL 6.38 1 M² Pasang Lantai mozaik uk. 30 x 30 cm, 1 PC : 3 PP Rp 342,236.84PPL 6.39 1 M' Pasang Plint keramik uk. 10 x 30 cm Rp 35,002.70PPL 6.40 1 M' Pasang plint keramik uk. 10 x 10 cm Rp 38,032.14PPL 6.41 1 M' Pasang plint keramik uk. 5 x 20 cm Rp 32,231.48PPL 6.43 1 M² Pasang lantai granito uk. 60 x 60 cm Rp 414,483.95PPL 6.44 1 M² Pasang lantai karpet Rp 124,338.00PPL 6.45 1 M² Pasang underlayer/pelapis bawah karpet Rp 160,994.25PPL 6.46 1 M² Pasang lantai parquit kayu Rp 504,533.75PPL 6.47 1 M² Pasang lantai kayu (gymfloor) Rp 377,142.50PPL 6.48 1 M² Pasang dinding porselen uk. 11 x 11 cm Rp 287,607.53PPL 6.49 1 M² Pasang dinding porselin uk. 15 x 15 cm Rp 284,864.78PPL 6.51 1 M² Pasang dinding keramik artistik uk. 10 x 20 cm Rp 281,184.78PPL 6.52 1 M² Pasang dinding keramik artistik uk. 5 x 20 cm Rp 303,140.35

Page 21: Daftar Analisa Pu 2013

Rekapitulasi Analisa Biaya Kanstruksi 2013 21

REKAPITULASI ANALISA HARGA SATUAN PEKERJAAN 2013

PPL 6.53 1 M² Pasang dinding keramik uk. 10 x 20 cm Rp 281,184.78PPL 6.54 1 M² Pasang dinding keramik uk. 20 x 20 cm Rp 238,202.70PPL 6.55 1 M² Pasang dinding marmer uk. 60 x 60 cm Rp 648,564.38PPL 6.56 1 M² Pasang dinding bata pelapis uk. 3 x 7 x 24 cm Rp 337,579.66PPL 6.57 1 M² Pasang dinding batu poros Rp 397,400.04PPL 6.58 1 M² Pasang dinding batu tempel hitam Rp 330,987.54PPL 6.59 1 M² Pasang lantai vinyl uk. 30 x 30 cm Rp 176,842.40PPL 6.60 1 M² Pasang wallpaper, lebar 50 cm Rp 248,480.50PPL 6.61 1 M² Pasang floor hardener Rp 49,875.50PPL 6.62 1 M' Pasang plint vinyl uk. 30 x 30 cm dengan perekat Rp 38,249.92PPL 6.63 1 M' Pasang plint kayu kelas II tebal 2 cm, lebar 10 cm Rp 51,391.51

PEKERJAAN CATPC 6.1 1M² Mengikis/ mengerok permukaan cat tembok lama Rp 14,087.50PC 6.2 1M² Mencuci bidang permukaan tembok yang pernah di cat Rp 13,816.68PC 6.3 1M² Mengerok karat cat lama permukaan baja dengan Rp 13,215.95

cara manualPC 6.4 1M² Menyabun permukaan tembok lama Rp 13,816.68PC 6.6 1M² Mendempul dan menggosok kayu Rp 14,788.08PC 6.7 1M² Pengecatan bidang kayu lama Rp 30,039.15PC 6.8 1M² Pengecatan bidang kayu baru 1 lps Plamir, 1 lps cat dasar, Rp 50,614.38

2 lps cat minyak PC 6.9 1M² Pengecatan bidang kayu baru 1 lps Plamir, 1 lps cat dasar, Rp 57,962.88

3 lps cat minyakPC 6.12 1M² Pelaburan kayu dengan Residu Rp 12,414.25PC 6.13 1M² Peleburan bidang kayu dan vernis Rp 45,254.80PC 6.14 1M² Pengecatan tembok baru (1 lps plamir,1 lps cat dasar, Rp 32,904.49

2 lps cat penutup)PC 6.15 1M² Pengecatan tembok lama ( 1 lapis cat dasar, Rp 27,039.95

2 lapis cat penutup )PC 6.19 1M² Pemasangan wall paper Rp 133,595.50PC 6.20 1M² Pengecatan permukaan baja dengan meni besi Rp 11,943.33PC 6.21 1M² Pengecatan permukaan baja dengan meni besi Rp 71,067.33

dan perancahPC 6.23 1M² Pengecatan permukaan baja lapis seng (galbani) Rp 46,057.50

secara manual sistem 1 lapis cat konvensional dengan tebal 200 um. PC 6.24 1M² Pengecatan permukaan baja lapis seng (galbani) Rp 212,716.77

secara manual sistem 3 lapis cat konvensional dengan tebal 200 um. PC 6.25 1M² Pengecatan permukaan baja lapis seng (galbani) Rp 176,703.25

secara semprot (airless spray) dengan sistem 1 lapis cat konvensional dengan tebal 200 um.

PEKERJAAN SANITASIPS 6.1 Memasang 1 buah kloset duduk/monoblok Rp 2,505,850.00PS 6.2 Memasang 1 buah kloset jongkok porselen Rp 502,575.88PS 6.4 Memasang 1 buah urinoir Rp 1,346,917.38PS 6.5 Memasang 1 buah wastafel Rp 987,542.38PS 6.7 Memasang 1 buah bak mandi fibreglass volume 0,30 m³ Rp 489,233.00PS 6.8 Memasang 1 buah bak mandi batu bata volume 0,30 m³ Rp 1,245,941.05PS 6.11 Memasang 1 buah bak mandi fibreglass volume 1 m³ Rp 1,558,220.56PS 6.16. Memasang 1 buah Bak Kontrol pasangan batu bata Rp 670,562.13

uk.(30 x 30) cm tinggi 35 cmPS 6.17 Memasang 1 buah Bak Kontrol pasangan batu bata Rp 640,576.45

uk.(45 x 45) cm tinggi 50 cmPS 6.18 Memasang 1 buah Bak Kontrol pasangan batu bata Rp 979,928.52

uk.(60 x 60) cm tinggi 65 cmPS 6.19 Memasang 1 m' pipa galvanis diameter ½" Rp 41,888.75

Page 22: Daftar Analisa Pu 2013

Rekapitulasi Analisa Biaya Kanstruksi 2013 22

REKAPITULASI ANALISA HARGA SATUAN PEKERJAAN 2013

PS 6.20 Memasang 1 m' pipa galvanis diameter 3/4" Rp 49,197.00PS 6.21 Memasang 1 m' pipa galvanis diameter 1" Rp 56,683.50PS 6.22 Memasang 1 m' pipa galvanis diameter 1 ½" Rp 89,061.75PS 6.23 Memasang 1 m' pipa galvanis diameter 2" Rp 109,649.63PS 6.25 Memasang 1 m' pipa PVC tipe AW diameter ½" Rp 18,956.60PS 6.26 Memasang 1 m' pipa PVC tipe AW diameter ¾" Rp 21,202.55PS 6.27 Memasang 1 m' pipa PVC tipe AW diameter 1" Rp 26,942.20PS 6.28 Memasang 1 m' pipa PVC tipe AW diameter 1 ½" Rp 29,687.25PS 6.29 Memasang 1 m' pipa PVC tipe AW diameter 2" Rp 37,418.70PS 6.30 Memasang 1 m' pipa PVC tipe AW diameter 2 ½" Rp 35,926.00PS 6.31 Memasang 1 m' pipa PVC tipe AW diameter 3" Rp 56,882.45PS 6.32 Memasang 1 m' pipa PVC tipe AW diameter 4" Rp 70,108.60PS 6.33 Memasang 1 bh bak cuci piring stainles steel Rp 980,490.00PS 6.34 Memasang 1 bh bak cuci piring teraso Rp 430,436.38PS 6.35 Memasang 1 bh kran diameter ¾" atau ½" Rp 31,452.50PS 6.36 Memasang 1 bh Floor drain Rp 38,559.50

PEKERJAAN BESI DAN ALUMINIUMPBA 6.1 1 Kg Pasang besi profil Rp 43,947.25PBA 6.2 1 Kg Pasang rangka kuda kuda baja IWF Rp 44,257.75PBA 6.3 100 Kg Pekerjaan perakitan Rp 92,805.00PBA 6.4 1 M² Pasang pintu besi plat baja tebal 2 mm rangkap, Rp 1,506,670.78

rangkap baja sikuPBA 6.5 10 Cm Pengelasan dengan las listrik Rp 27,210.15PBA 6.7 1 M² Pasang pintu rolling door besi Rp 861,120.00PBA 6.8 1 M² Pasang pintu lipat (Folding door) bahan plastik/ PVC Rp 174,846.00PBA 6.10 1 M² Pasang rollingdoor alluminium Rp 984,975.00PBA 6.11 1 M' Pasang kusen pintu aluminium Rp 48,493.20PBA 6.14 1 M² Pasang venetions blinds dan vertical blinds Rp 289,685.00PBA 6.15 1 M² Pasang terali besi strip 2 x 3 mm Rp 508,829.00PBA 6.16 1 M² Pasang kawat nyamuk Rp 91,362.90PBA 6.17 1 M² Pasang Jendela nako dan teralis Rp 453,157.50

PEKERJAAN LANGIT-LANGITPLL 6.1 1 M² Pasang langit langit asbes semen, 5 mm Rp 37,964.95PLL 6.2 1 M² Pasang langi langit akustik uk. 30 x 30 cm Rp 145,296.75PLL 6.3 1 M² Pasang langi langit akustik uk. 30 x 60 cm Rp 136,908.65PLL 6.4 1 M² Pasang langit langit akustik uk. 60 x 120 cm Rp 140,852.00PLL 6.5 1 M² Pasang langit langit triplek uk. 120 x 240 cm, tebal 4 mm Rp 52,955.49PLL 6.6 1 M² Pasang langit langit lambriziring kayu tebal 9 mm Rp 293,558.03PLL 6.7 1 M² Pasang langit langit gipsum board 1200 x 2400 x 9 mm Rp 54,525.53PLL 6.8 1 M' Pasang list plapon gypsum profil Rp 31,222.50PLL 6.9 1 M² Pasang langit langit akustik uk. 60 x 120 cm Rp 231,151.15

+ rangka aluminiumPLL 6.10 1 M' Pasang list langit langit kayu profil Rp 36,614.85

Page 23: Daftar Analisa Pu 2013

Pekerjaan Langit-langit 23

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN LANGIT - LANGIT

PLL 6.1 1 M² Pasang langit langit asbes semen, tbl 5 mm6.1.1 Bahan

Asbes 1.100 Kpg x Rp 17,640 = Rp 19,404.00 Paku biasa 0.010 Kg x Rp 18,900 = Rp 189.00

Jumlah (1) = Rp 19,593.006.1.2 Tenaga

Pekerja 0.070 Oh x Rp 75,000 = Rp 5,250.00 Tukang kayu 0.070 Oh x Rp 100,000 = Rp 7,000.00 Kepala tukang 0.007 Oh x Rp 110,000 = Rp 770.00 Mandor 0.0040 Oh x Rp 100,000 = Rp 400.00

Jumlah (2) = Rp 13,420.00A. Jumlah (1) + (2) = Rp 33,013.00B. Overhead dan Profit 15% x A = Rp 4,951.95

Harga Satuan Pekerjaan (A+B) = Rp 37,964.95

PLL 6.2 1 M² Pasang langi langit akustik uk. 30 x 30 cm6.2.1 Bahan

Akustik uk. 30 x 30 cm 12.000 Lbr x Rp 8,540 = Rp 102,480.00 Paku biasa 0.050 Kg x Rp 18,900 = Rp 945.00

Jumlah (1) = Rp 103,425.006.2.2 Tenaga

Pekerja 0.120 Oh x Rp 75,000 = Rp 9,000.00 Tukang kayu 0.120 Oh x Rp 100,000 = Rp 12,000.00 Kepala tukang 0.012 Oh x Rp 110,000 = Rp 1,320.00 Mandor 0.0060 Oh x Rp 100,000 = Rp 600.00

Jumlah (2) = Rp 22,920.00A. Jumlah (1) + (2) = Rp 126,345.00B. Overhead dan Profit 15% x A = Rp 18,951.75

Harga Satuan Pekerjaan (A+B) = Rp 145,296.75

PLL 6.3 1 M² Pasang langi langit akustik uk. 30 x 60 cm6.3.1 Bahan

Akustik uk. 30 x 60 cm 5.800 Lbr x Rp 17,070 = Rp 99,006.00 Paku biasa 0.050 Kg x Rp 18,900 = Rp 945.00

Jumlah (1) = Rp 99,951.006.3.2 Tenaga

Pekerja 0.100 Oh x Rp 75,000 = Rp 7,500.00 Tukang kayu 0.100 Oh x Rp 100,000 = Rp 10,000.00 Kepala tukang 0.010 Oh x Rp 110,000 = Rp 1,100.00 Mandor 0.0050 Oh x Rp 100,000 = Rp 500.00

Jumlah (2) = Rp 19,100.00A. Jumlah (1) + (2) = Rp 119,051.00B. Overhead dan Profit 15% x A = Rp 17,857.65

Harga Satuan Pekerjaan (A+B) = Rp 136,908.65

PLL 6.4 1 M² Pasang langit langit akustik uk. 60 x 120 cm6.4.1 Bahan

Akustik uk. 60 x 120 cm 1.500 Lbr x Rp 68,290 = Rp 102,435.00 Paku biasa 0.050 Kg x Rp 18,900 = Rp 945.00

Jumlah (1) = Rp 103,380.006.4.2 Tenaga

Pekerja 0.100 Oh x Rp 75,000 = Rp 7,500.00 Tukang kayu 0.100 Oh x Rp 100,000 = Rp 10,000.00 Kepala tukang 0.010 Oh x Rp 110,000 = Rp 1,100.00 Mandor 0.0050 Oh x Rp 100,000 = Rp 500.00

Jumlah (2) = Rp 19,100.00A. Jumlah (1) + (2) = Rp 122,480.00B. Overhead dan Profit 15% x A = Rp 18,372.00

Harga Satuan Pekerjaan (A+B) = Rp 140,852.00

Page 24: Daftar Analisa Pu 2013

Pekerjaan Langit-langit 24

PEKERJAAN LANGIT - LANGIT

PLL 6.5 1 M² Pasang langit langit triplek uk. 120 x 240 cm, tebal 4 mm6.5.1 Bahan

Triplek tebal 4 mm 0.375 Lbr x Rp 70,350 = Rp 26,381.25 Paku biasa 0.030 Kg x Rp 18,900 = Rp 567.00

Jumlah (1) = Rp 26,948.256.5.2 Tenaga

Pekerja 0.100 Oh x Rp 75,000 = Rp 7,500.00 Tukang kayu 0.100 Oh x Rp 100,000 = Rp 10,000.00 Kepala tukang 0.010 Oh x Rp 110,000 = Rp 1,100.00 Mandor 0.005 Oh x Rp 100,000 = Rp 500.00

Jumlah (2) = Rp 19,100.00A. Jumlah (1) + (2) = Rp 46,048.25B. Overhead dan Profit 15% x A = Rp 6,907.24

Harga Satuan Pekerjaan (A+B) = Rp 52,955.49

PLL 6.6 1 M² Pasang langit langit lambriziring kayu tebal 9 mm6.6.1 Bahan

Kayu papan kelas II 0.015 Lbr x Rp 6,818,590 = Rp 102,278.85 Paku biasa 0.010 Kg x Rp 18,900 = Rp 189.00

Jumlah (1) = Rp 102,467.856.6.2 Tenaga

Pekerja 0.800 Oh x Rp 75,000 = Rp 60,000.00 Tukang kayu 0.800 Oh x Rp 100,000 = Rp 80,000.00 Kepala tukang 0.080 Oh x Rp 110,000 = Rp 8,800.00 Mandor 0.040 Oh x Rp 100,000 = Rp 4,000.00

Jumlah (2) = Rp 152,800.00A. Jumlah (1) + (2) = Rp 255,267.85B. Overhead dan Profit 15% x A = Rp 38,290.18

Harga Satuan Pekerjaan (A+B) = Rp 293,558.03

PLL 6.7 1 M² Pasang langit langit gipsum board 1200 x 2400 x 9 mm6.7.1 Bahan

Gypsum 120 x 240 tbl. 9 mm 0.364 Lbr x Rp 71,500 = Rp 26,026.00 Paku skrup 0.110 Kg x Rp 26,250 = Rp 2,887.50

Jumlah (1) = Rp 28,913.506.7.2 Tenaga

Pekerja 0.100 Oh x Rp 75,000 = Rp 7,500.00 Tukang kayu 0.050 Oh x Rp 100,000 = Rp 5,000.00

Kepala tukang 0.050 Oh x Rp 110,000 = Rp 5,500.00 Mandor 0.005 Oh x Rp 100,000 = Rp 500.00

Jumlah (2) = Rp 18,500.00A. Jumlah (1) + (2) = Rp 47,413.50B. Overhead dan Profit 15% x A = Rp 7,112.03

Harga Satuan Pekerjaan (A+B) = Rp 54,525.53

PLL 6.8 1 M' Pasang list plapon gypsum profil6.8.1 Bahan

List profil gypsum 1.050 m' x Rp 13,450 = Rp 14,122.50 Tepung gypsum 0.150 Kg x Rp 10,450 = Rp 1,567.50

Jumlah (1) = Rp 15,690.006.8.2 Tenaga

Pekerja 0.060 Oh x Rp 75,000 = Rp 4,500.00 Tukang kayu 0.060 Oh x Rp 100,000 = Rp 6,000.00 Kepala tukang 0.006 Oh x Rp 110,000 = Rp 660.00 Mandor 0.0030 Oh x Rp 100,000 = Rp 300.00

Jumlah (2) = Rp 11,460.00A. Jumlah (1) + (2) = Rp 27,150.00B. Overhead dan Profit 15% x A = Rp 4,072.50

Harga Satuan Pekerjaan (A+B) = Rp 31,222.50

Page 25: Daftar Analisa Pu 2013

Pekerjaan Langit-langit 25

PEKERJAAN LANGIT - LANGIT

PLL 6.9 1 M² Pasang langit langit akustik uk. 60 x 120 cm + rangka aluminium6.9.1 Bahan

Profil alluminium "T" 3.600 M' x Rp 28,600 = Rp 102,960.00 Kawat licin / Bronjong 0.150 Kg x Rp 16,940 = Rp 2,541.00

Akustik 60 x 120 cm 1.500 Lbr x Rp 68,290 = Rp 102,435.00Jumlah (1) = Rp 105,501.00

6.9.2 Tenaga Pekerja 0.500 Oh x Rp 75,000 = Rp 37,500.00 Tukang kayu 0.500 Oh x Rp 100,000 = Rp 50,000.00 Kepala tukang 0.050 Oh x Rp 110,000 = Rp 5,500.00 Mandor 0.0250 Oh x Rp 100,000 = Rp 2,500.00

Jumlah (2) = Rp 95,500.00A. Jumlah (1) + (2) = Rp 201,001.00B. Overhead dan Profit 15% x A = Rp 30,150.15

Harga Satuan Pekerjaan (A+B) = Rp 231,151.15

Page 26: Daftar Analisa Pu 2013

Pekerjaan Langit-langit 26

PEKERJAAN LANGIT - LANGIT

PLL 6.10 1 M' Pasang list langit langit kayu profil6.10.1 Bahan

List kayu profil 1.050 Btg x Rp 21,000 = Rp 22,050.00 Paku biasa 0.010 Kg x Rp 18,900 = Rp 189.00

Jumlah (1) = Rp 22,239.006.10.2 Tenaga

Pekerja 0.050 Oh x Rp 75,000 = Rp 3,750.00 Tukang kayu 0.050 Oh x Rp 100,000 = Rp 5,000.00 Kepala tukang 0.005 Oh x Rp 110,000 = Rp 550.00 Mandor 0.0030 Oh x Rp 100,000 = Rp 300.00

Jumlah (2) = Rp 9,600.00A. Jumlah (1) + (2) = Rp 31,839.00B. Overhead dan Profit 15% x A = Rp 4,775.85

Harga Satuan Pekerjaan (A+B) = Rp 36,614.85

Page 27: Daftar Analisa Pu 2013

Pekerjaan Besi dan Aluminium 27

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN BESI DAN ALUMINIUM

PBA 6.1 1 Kg Pasang besi profil6.1.1 Bahan

Besi profil 1.150 Kg x Rp 23,500 = Rp 27,025.00Jumlah (1) = Rp 27,025.00

6.1.2. Tenaga Pekerja 0.060 Oh x Rp 75,000 = Rp 4,500.00 Tukang las kontruksi 0.060 Oh x Rp 100,000 = Rp 6,000.00 Kepala tukang 0.006 Oh x Rp 110,000 = Rp 660.00 Mandor 0.0003 Oh x Rp 100,000 = Rp 30.00

Jumlah (2) = Rp 11,190.00A. Jumlah (1) + (2) = Rp 38,215.00B. Overhead dan Profit 15% x A = Rp 5,732.25

Harga Satuan Pekerjaan (A+B) = Rp 43,947.25

PBA 6.2 1 Kg Pasang rangka kuda kuda baja IWF6.2.1 Bahan

Besi baja IWF 1.150 Kg x Rp 23,500 = Rp 27,025.00Jumlah (1) = Rp 27,025.00

6.2.2. Tenaga Pekerja 0.060 Oh x Rp 75,000 = Rp 4,500.00 Tukang las Kontruksi 0.060 Oh x Rp 100,000 = Rp 6,000.00

Kepala tukang 0.006 Oh x Rp 110,000 = Rp 660.00 Mandor 0.003 Oh x Rp 100,000 = Rp 300.00

Jumlah (2) = Rp 11,460.00A. Jumlah (1) + (2) = Rp 38,485.00B. Overhead dan Profit 15% x A = Rp 5,772.75

Harga Satuan Pekerjaan (A+B) = Rp 44,257.75

PBA 6.3 100 Kg Pekerjaan perakitan6.3.1 Bahan

Solar 1.000 Ltr x Rp 4,500 = Rp 4,500.00Minyak pelumas 0.100 Ltr x Rp 40,900 = Rp 4,090.00

Jumlah (1) = Rp 8,590.006.3.2. Tenaga

Pekerja 0.100 Oh x Rp 75,000 = Rp 7,500.00 Tukang las Kontruksi 0.100 Oh x Rp 100,000 = Rp 10,000.00 Kepala tukang 0.001 Oh x Rp 110,000 = Rp 110.00

Mandor 0.00500 Oh x Rp 100,000 = Rp 500.00Jumlah (2) = Rp 18,110.00

6.3.3. AlatSewa alat 0.800 Jam x Rp 67,500 = Rp 54,000.00

Jumlah (3) = Rp 54,000.00A. Jumlah (1) + (2) + (3) = Rp 80,700.00B. Overhead dan Profit 15% x A = Rp 12,105.00

Harga Satuan Pekerjaan (A+B) = Rp 92,805.00

PBA 6.4 1 M² Pasang pintu besi plat baja tebal 2 mm rangkap, rangkap baja siku6.4.1 Bahan

Besi siku 15.000 Kg x Rp 20,000 = Rp 300,000.00Plat Baja 32.800 Kg x Rp 24,670 = Rp 809,176.00Kawat las 0.050 Dos x Rp 9,450 = Rp 472.50

Jumlah (1) = Rp 1,109,648.506.4.2 Tenaga

Pekerja 1.050 Oh x Rp 75,000 = Rp 78,750.00Tukang las biasa 1.050 Oh x Rp 100,000 = Rp 105,000.00Kepala tukang 0.105 Oh x Rp 110,000 = Rp 11,550.00Mandor 0.052 Oh x Rp 100,000 = Rp 5,200.00

Jumlah (2) = Rp 200,500.00A. Jumlah (1) + (2) = Rp 1,310,148.50

Page 28: Daftar Analisa Pu 2013

Pekerjaan Besi dan Aluminium 28

PEKERJAAN BESI DAN ALUMINIUM

B. Overhead dan Profit 15% x A = Rp 196,522.28Harga Satuan Pekerjaan (A+B) = Rp 1,506,670.78

PBA 6.5 10 Cm Pengelasan dengan las listrik6.5.1 Bahan

Kawat las 0.400 Kg x Rp 9,450 = Rp 3,780.00 Solar 0.300 Ltr x Rp 4,500 = Rp 1,350.00

Minyak pelumas 0.040 Ltr x Rp 40,900 = Rp 1,636.00Jumlah (1) = Rp 6,766.00

6.5.2 Tenaga Pekerja 0.040 Oh x Rp 75,000 = Rp 3,000.00 Tukang las Kontruksi 0.020 Oh x Rp 100,000 = Rp 2,000.00 Kepala tukang 0.002 Oh x Rp 110,000 = Rp 220.00

Mandor 0.00200 Oh x Rp 100,000 = Rp 200.00Jumlah (2) = Rp 5,420.00

6.5.3 AlatSewa alat 0.170 Jam x Rp 67,500 = Rp 11,475.00

Jumlah (3) = Rp 11,475.00A. Jumlah (1)+(2)+(3) = Rp 23,661.00B. Overhead dan Profit 15% x A = Rp 3,549.15

Harga Satuan Pekerjaan (A+B) = Rp 27,210.15

PBA 6.7 1 M² Pasang pintu rolling door besi6.7.1 Bahan

Pintu gulung besi 1.000 x Rp 525,000 = Rp 525,000.00Jumlah (1) = Rp 525,000.00

6.7.2 TenagaPekerja 1.200 Oh x Rp 75,000 = Rp 90,000.00Tukang las biasa 1.200 Oh x Rp 100,000 = Rp 120,000.00Kepala tukang 0.120 Oh x Rp 110,000 = Rp 13,200.00Mandor 0.006 Oh x Rp 100,000 = Rp 600.00

Jumlah (2) = Rp 223,800.00A. Jumlah (1) + (2) = Rp 748,800.00B. Overhead dan Profit 15% x A = Rp 112,320.00

Harga Satuan Pekerjaan (A+B) = Rp 861,120.00

PBA 6.8 1 M² Pasang pintu lipat (Folding door) bahan plastik/ PVC6.8.1 Bahan

Pintu lipat plastik 1.000 x Rp 68,000 = Rp 68,000.00Jumlah (1) = Rp 68,000.00

6.8.2 TenagaPekerja 0.440 Oh x Rp 75,000 = Rp 33,000.00Tukang 0.440 Oh x Rp 100,000 = Rp 44,000.00Kepala tukang 0.044 Oh x Rp 110,000 = Rp 4,840.00Mandor 0.022 Oh x Rp 100,000 = Rp 2,200.00

Jumlah (2) = Rp 84,040.00A. Jumlah (1) + (2) = Rp 152,040.00B. Overhead dan Profit 15% x A = Rp 22,806.00

Harga Satuan Pekerjaan (A+B) = Rp 174,846.00

PBA 6.10 1 M² Pasang rollingdoor alluminium6.10.1 Bahan

Rolling door alluminium 1.000 x Rp 665,500 = Rp 665,500.00Jumlah (1) = Rp 665,500.00

6.10.2 TenagaPekerja 1.000 Oh x Rp 75,000 = Rp 75,000.00Tukang khusus alluminium 1.000 Oh x Rp 100,000 = Rp 100,000.00Kepala tukang 0.100 Oh x Rp 110,000 = Rp 11,000.00Mandor 0.050 Oh x Rp 100,000 = Rp 5,000.00

Jumlah (2) = Rp 191,000.00A. Jumlah (1) + (2) = Rp 856,500.00

Page 29: Daftar Analisa Pu 2013

Pekerjaan Besi dan Aluminium 29

PEKERJAAN BESI DAN ALUMINIUM

B. Overhead dan Profit 15% x A = Rp 128,475.00Harga Satuan Pekerjaan (A+B) = Rp 984,975.00

Page 30: Daftar Analisa Pu 2013

Pekerjaan Besi dan Aluminium 30

PEKERJAAN BESI DAN ALUMINIUM

PBA 6.11 1 M' Pasang kusen pintu aluminium6.11.1 Bahan

Profil Aluminium 1.100 M' x Rp 28,600 = Rp 31,460.00Skrup fixer 2.000 Bh x Rp 1,250 = Rp 2,500.00Sealant 0.060 tube x Rp 39,300 = Rp 2,358.00

Jumlah (1) = Rp 33,960.006.11.2 Tenaga

Pekerja 0.043 Oh x Rp 75,000 = Rp 3,225.00Tukang khusus alluminium 0.043 Oh x Rp 100,000 = Rp 4,300.00Kepala tukang 0.004 Oh x Rp 110,000 = Rp 473.00Mandor 0.002 Oh x Rp 100,000 = Rp 210.00

Jumlah (2) = Rp 8,208.00A. Jumlah (1) + (2) = Rp 42,168.00B. Overhead dan Profit 15% x A = Rp 6,325.20

Harga Satuan Pekerjaan (A+B) = Rp 48,493.20

PBA 6.14 1 M² Pasang venetions blinds dan vertical blinds6.14.1 Bahan

Venetions/vertical blinds 1.000 x Rp 185,000 = Rp 185,000.00Jumlah (1) = Rp 185,000.00

6.14.2 TenagaPekerja 0.350 Oh x Rp 75,000 = Rp 26,250.00Tukang 0.350 Oh x Rp 100,000 = Rp 35,000.00Kepala tukang 0.035 Oh x Rp 110,000 = Rp 3,850.00Mandor 0.018 Oh x Rp 100,000 = Rp 1,800.00

Jumlah (2) = Rp 66,900.00A. Jumlah (1) + (2) = Rp 251,900.00B. Overhead dan Profit 15% x A = Rp 37,785.00

Harga Satuan Pekerjaan (A+B) = Rp 289,685.00

PBA 6.156.15.1 Bahan

Besi plat strip 6.177 Kg x Rp 20,000 = Rp 123,540.00Jumlah (1) = Rp 123,540.00

6.15.2 TenagaPekerja 1.670 Oh x Rp 75,000 = Rp 125,250.00Tukang las 1.670 Oh x Rp 100,000 = Rp 167,000.00Kepala tukang 0.167 Oh x Rp 110,000 = Rp 18,370.00Mandor 0.083 Oh x Rp 100,000 = Rp 8,300.00

Jumlah (2) = Rp 318,920.00A. Jumlah (1) + (2) = Rp 442,460.00B. Overhead dan Profit 15% x A = Rp 66,369.00

Harga Satuan Pekerjaan (A+B) = Rp 508,829.00

PBA 6.166.16.1 Bahan

Kawat nyamuk 1.100 x Rp 18,200 = Rp 20,020.00Besi plat strip 1.716 Kg x Rp 23,500 = Rp 40,326.00

Jumlah (1) = Rp 60,346.006.16.2 Tenaga

Pekerja 0.100 Oh x Rp 75,000 = Rp 7,500.00Tukang 0.100 Oh x Rp 100,000 = Rp 10,000.00Kepala tukang 0.010 Oh x Rp 110,000 = Rp 1,100.00Mandor 0.005 Oh x Rp 100,000 = Rp 500.00

Jumlah (2) = Rp 19,100.00A. Jumlah (1) + (2) = Rp 79,446.00B. Overhead dan Profit 15% x A = Rp 11,916.90

Harga Satuan Pekerjaan (A+B) = Rp 91,362.90

1 M² Pasang terali besi strip 2 x 3 mm

1 M² Pasang kawat nyamuk

Page 31: Daftar Analisa Pu 2013

Pekerjaan Besi dan Aluminium 31

PEKERJAAN BESI DAN ALUMINIUM

PBA 6.176.17.1 Bahan

Jendela nako 1.100 x Rp 192,500 = Rp 211,750.00Paku skrup 1 - 2,5 cm 10.000 Bh x Rp 500 = Rp 5,000.00Besi strip 7.000 Kg x Rp 20,000 = Rp 140,000.00

Jumlah (1) = Rp 356,750.006.17.2 Tenaga

Pekerja 0.200 Oh x Rp 75,000 = Rp 15,000.00Tukang 0.200 Oh x Rp 100,000 = Rp 20,000.00Kepala tukang 0.020 Oh x Rp 110,000 = Rp 2,200.00Mandor 0.001 Oh x Rp 100,000 = Rp 100.00

Jumlah (2) = Rp 37,300.00A. Jumlah (1) + (2) = Rp 394,050.00B. Overhead dan Profit 15% x A = Rp 59,107.50

Harga Satuan Pekerjaan (A+B) = Rp 453,157.50

*********LANJUT PEKERJAAN LANGIT LANGIT

1 M² Pasang Jendela nako dan teralis

Page 32: Daftar Analisa Pu 2013

Pekerjaan Sanitasi 32

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN SANITASI

PS 6.1 Memasang 1 buah kloset duduk6.1.1. Bahan

Kloset duduk + bak air kwalitas Biasa 1.000 Bh x Rp. 1,650,000 = Rp. 1,650,000.00 Perlengkapan 6% harga klosed x Rp. 1,650,000 = Rp. 99,000.00

Jumlah (1) = Rp. 1,749,000.006.1.2 Tenaga

Pekerja 3.300 Oh x Rp. 75,000 = Rp. 247,500.00 Tukang batu 1.500 Oh x Rp. 100,000 = Rp. 150,000.00 Kepala tukang 0.150 Oh x Rp. 110,000 = Rp. 16,500.00 Mandor 0.160 Oh x Rp. 100,000 = Rp. 16,000.00

Jumlah (2) = Rp. 430,000.00A. Jumlah (1) + (2) = Rp 2,179,000.00B. Overhead dan Profit 15% x A = Rp 326,850.00

Harga Satuan Pekerjaan (A+B) = Rp 2,505,850.00

PS 6.2 Memasang 1 buah kloset jongkok porselen 6.2.1 Bahan

Klosed jongkok porselin 1.000 Bh x Rp. 167,790 = Rp. 167,790.00 Semen portland 6.000 Kg x Rp. 1,362 = Rp. 8,172.00 Pasir pasang 0.010 x Rp. 106,050 = Rp. 1,060.50

Jumlah (1) = Rp. 177,022.506.2.2 Tenaga

Pekerja 1.100 Oh x Rp. 75,000 = Rp. 82,500.00 Tukang batu 1.500 Oh x Rp. 100,000 = Rp. 150,000.00

Kepala tukang 0.150 Oh x Rp. 110,000 = Rp. 16,500.00 Mandor 0.110 Oh x Rp. 100,000 = Rp. 11,000.00

Jumlah (2) = Rp. 260,000.00A. Jumlah (1) + (2) = Rp 437,022.50B. Overhead dan Profit 15% x A = Rp 65,553.38

Harga Satuan Pekerjaan (A+B) = Rp 502,575.88

PS 6.4 Memasang 1 buah urinoir 6.4.1 Bahan

Urinoir 1.000 Bh x Rp. 840,000 = Rp. 840,000.00 Perlengkapan 15% harga urinoir x Rp. 840,000 = Rp. 126,000.00 Semen portland 6.000 Kg x Rp. 1,362 = Rp. 8,172.00 Pasir pasang 0.010 x Rp. 106,050 = Rp. 1,060.50

Jumlah (1) = Rp. 975,232.506.4.2 Tenaga

Pekerja 1.000 Oh x Rp. 75,000 = Rp. 75,000.00 Tukang batu 1.000 Oh x Rp. 100,000 = Rp. 100,000.00 Kepala tukang 0.100 Oh x Rp. 110,000 = Rp. 11,000.00 Mandor 0.100 Oh x Rp. 100,000 = Rp. 10,000.00

Jumlah (2) = Rp. 196,000.00A. Jumlah (1) + (2) = Rp 1,171,232.50B. Overhead dan Profit 15% x A = Rp 175,684.88

Harga Satuan Pekerjaan (A+B) = Rp 1,346,917.38

PS 6.5 Memasang 1 buah wastafel6.5.1 Bahan

Wastafel biasa 1.000 Bh x Rp. 525,000 = Rp. 525,000.00 Perlengkapan 12% harga wastafel x Rp. 525,000 = Rp. 63,000.00

Semen portland 6.000 Kg x Rp. 1,362 = Rp. 8,172.00 Pasir pasang 0.010 x Rp. 106,050 = Rp. 1,060.50

Jumlah (1) = Rp. 597,232.506.5.2 Tenaga

Pekerja 1.200 Oh x Rp. 75,000 = Rp. 90,000.00Tukang batu 1.450 Oh x Rp. 100,000 = Rp. 145,000.00Kepala tukang 0.150 Oh x Rp. 110,000 = Rp. 16,500.00Mandor 0.100 Oh x Rp. 100,000 = Rp. 10,000.00

Jumlah (2) = Rp. 261,500.00A. Jumlah (1) + (2) = Rp 858,732.50

Page 33: Daftar Analisa Pu 2013

Pekerjaan Sanitasi 33

PEKERJAAN SANITASI

B. Overhead dan Profit 15% x A = Rp 128,809.88Harga Satuan Pekerjaan (A+B) = Rp 987,542.38

PS 6.7 Memasang 1 buah bak mandi fibreglass volume 0,30 m³6.7.1 Bahan

Bak fibreglass 0,3 M3 1.000 Bh x Rp. 186,000 = Rp. 186,000.00 Perlengkapan 18% Harga bak x Rp. 186,000 = Rp. 33,480.00

Jumlah (1) = Rp. 219,480.006.7.2 Tenaga

Pekerja 1.800 Oh x Rp. 75,000 = Rp. 135,000.00Tukang batu 0.540 Oh x Rp. 100,000 = Rp. 54,000.00Kepala tukang 0.054 Oh x Rp. 110,000 = Rp. 5,940.00Mandor 0.110 Oh x Rp. 100,000 = Rp. 11,000.00

Jumlah (2) = Rp. 205,940.00A. Jumlah (1) + (2) = Rp 425,420.00B. Overhead dan Profit 15% x A = Rp 63,813.00

Harga Satuan Pekerjaan (A+B) = Rp 489,233.00

PS 6.8 Memasang 1 buah bak mandi batu bata volume 0,30 m³6.8.1 Bahan

Batu bata cetak mesin 44.000 Bh x Rp. 875 = Rp. 38,500.00Semen portland 120.000 Kg x Rp. 1,362 = Rp. 163,440.00Pasir pasang 0.300 x Rp. 106,050 = Rp. 31,815.00Keramik standart 20 x 20 cm 100.000 Bh x Rp. 2,400 = Rp. 240,000.00Semen warna 40 kg 6.000 Kg x Rp. 3,612 = Rp. 21,672.00

Jumlah (1) = Rp. 495,427.006.8.2 Tenaga

Pekerja 3.000 Oh x Rp. 75,000 = Rp. 225,000.00Tukang batu 3.000 Oh x Rp. 100,000 = Rp. 300,000.00Kepala tukang 0.300 Oh x Rp. 110,000 = Rp. 33,000.00Mandor 0.300 Oh x Rp. 100,000 = Rp. 30,000.00

Jumlah (2) = Rp. 588,000.00A. Jumlah (1) + (2) = Rp 1,083,427.00B. Overhead dan Profit 15% x A = Rp 162,514.05

Harga Satuan Pekerjaan (A+B) = Rp 1,245,941.05

PS 6.11 Memasang 1 buah bak fibreglass volume 1 m³ air 6.11.1 Bahan

Bak fibreglass 1 m3 1.000 Bh x Rp. 438,370 = Rp. 438,370.00Perlengkapan 12% Harga bak x Rp. 438,370 = Rp. 52,604.40

Jumlah (1) = Rp. 490,974.406.11.2 Tenaga

Pekerja 3.000 Oh x Rp. 75,000 = Rp. 225,000.00Tukang batu 4.500 Oh x Rp. 100,000 = Rp. 450,000.00Kepala tukang 0.900 Oh x Rp. 110,000 = Rp. 99,000.00Mandor 0.900 Oh x Rp. 100,000 = Rp. 90,000.00

Jumlah (2) = Rp. 864,000.00A. Jumlah (1) + (2) = Rp 1,354,974.40B. Overhead dan Profit 15% x A = Rp 203,246.16

Harga Satuan Pekerjaan (A+B) = Rp 1,558,220.56

PS 6.16 Memasang 1 buah Bak Kontrol pasangan batu bata uk.(30 x 30) cm tinggi 35 cm6.16.1 Bahan

Batu bata 145.000 Bh x Rp. 875 = Rp. 126,875.00Semen portland 44.000 Kg x Rp. 1,362 = Rp. 59,928.00Pasir pasang 0.070 x Rp. 106,050 = Rp. 7,423.50Batu kerikil 0.070 M³ x Rp. 210,900 = Rp. 14,763.00Besi beton 1.600 Kg x Rp. 15,300 = Rp. 24,480.00Pasir beton 0.060 x Rp. 106,050 = Rp. 6,363.00

Jumlah (1) = Rp. 239,832.50

Page 34: Daftar Analisa Pu 2013

Pekerjaan Sanitasi 34

PEKERJAAN SANITASI

6.16.2 TenagaPekerja 3.200 Oh x Rp. 75,000 = Rp. 240,000.00Tukang batu 1.015 Oh x Rp. 100,000 = Rp. 101,500.00Kepala tukang 0.0015 Oh x Rp. 110,000 = Rp. 165.00Mandor 0.016 Oh x Rp. 100,000 = Rp. 1,600.00

Jumlah (2) = Rp. 343,265.00A. Jumlah (1) + (2) = Rp 583,097.50B. Overhead dan Profit 15% x A = Rp 87,464.63

Harga Satuan Pekerjaan (A+B) = Rp 670,562.13

PS 6.17 Memasang 1 buah Bak Kontrol pasangan batu bata uk.(45 x 45) cm tinggi 50 cm6.17.1 Bahan

Batu bata 250.000 Bh x Rp. 875 = Rp. 218,750.00Semen portland 77.000 Kg x Rp. 1,362 = Rp. 104,874.00Pasir pasang 0.130 x Rp. 106,050 = Rp. 13,786.50Batu kerikil 0.020 M³ x Rp. 210,900 = Rp. 4,218.00Besi beton 2.600 Kg x Rp. 15,300 = Rp. 39,780.00Pasir beton 0.090 x Rp. 106,050 = Rp. 9,544.50

Jumlah (1) = Rp. 390,953.006.17.2 Tenaga

Pekerja 1.420 Oh x Rp. 75,000 = Rp. 106,500.00Tukang batu 0.473 Oh x Rp. 100,000 = Rp. 47,300.00Kepala tukang 0.047 Oh x Rp. 110,000 = Rp. 5,170.00Mandor 0.071 Oh x Rp. 100,000 = Rp. 7,100.00

Jumlah (2) = Rp. 166,070.00A. Jumlah (1) + (2) = Rp 557,023.00B. Overhead dan Profit 15% x A = Rp 83,553.45

Harga Satuan Pekerjaan (A+B) = Rp 640,576.45

PS 6.18 Memasang 1 buah Bak Kontrol pasangan batu bata uk.(60 x 60) cm tinggi 65 cm6.18.1 Bahan

Batu bata 371.000 Bh x Rp. 875 = Rp. 324,625.00Semen portland 114.000 Kg x Rp. 1,362 = Rp. 155,268.00Pasir pasang 0.184 x Rp. 106,050 = Rp. 19,513.20Batu koral 0.033 M³ x Rp. 168,320 = Rp. 5,554.56Besi beton 4.850 Kg x Rp. 15,300 = Rp. 74,205.00Pasir beton 0.120 x Rp. 106,050 = Rp. 12,726.00

Jumlah (1) = Rp. 591,891.766.18.2 Tenaga

Pekerja 2.160 Oh x Rp. 75,000 = Rp. 162,000.00Tukang batu 0.720 Oh x Rp. 100,000 = Rp. 72,000.00Kepala tukang 0.072 Oh x Rp. 110,000 = Rp. 7,920.00Mandor 0.108 Oh x Rp. 100,000 = Rp. 10,800.00Tukang gali 0.100 Oh x Rp. 75,000 = Rp. 7,500.00

Jumlah (2) = Rp. 260,220.00A. Jumlah (1) + (2) = Rp 852,111.76B. Overhead dan Profit 15% x A = Rp 127,816.76

Harga Satuan Pekerjaan (A+B) = Rp 979,928.52

PS 6.19 Memasang 1 m' pipa galvanis diameter ½"6.19.1 Bahan

Pipa Galvanis Ø 1/2" 1.200 x Rp. 12,700 = Rp. 15,240.00Perlengkapan 35% harga pipa x Rp. 12,700 = Rp. 4,445.00

Jumlah (1) = Rp. 19,685.006.19.2 Tenaga

Pekerja 0.054 Oh x Rp. 75,000 = Rp. 4,050.00Tukang batu 0.090 Oh x Rp. 100,000 = Rp. 9,000.00Kepala tukang 0.009 Oh x Rp. 110,000 = Rp. 990.00Mandor 0.027 Oh x Rp. 100,000 = Rp. 2,700.00

Jumlah (2) = Rp. 16,740.00A. Jumlah (1) + (2) = Rp 36,425.00B. Overhead dan Profit 15% x A = Rp 5,463.75

Harga Satuan Pekerjaan (A+B) = Rp 41,888.75

Page 35: Daftar Analisa Pu 2013

Pekerjaan Sanitasi 35

PEKERJAAN SANITASI

PS 6.20 Memasang 1 m' pipa galvanis diameter 3/4"6.20.1 Bahan

Pipa galvanis 6 m 3/4" 1.200 x Rp. 16,800 = Rp. 20,160.00Perlengkapan 35% harga pipa x Rp. 16,800 = Rp. 5,880.00

Jumlah (1) = Rp. 26,040.006.20.2 Tenaga

Pekerja 0.054 Oh x Rp. 75,000 = Rp. 4,050.00Tukang batu 0.090 Oh x Rp. 100,000 = Rp. 9,000.00Kepala tukang 0.009 Oh x Rp. 110,000 = Rp. 990.00Mandor 0.027 Oh x Rp. 100,000 = Rp. 2,700.00

Jumlah (2) = Rp. 16,740.00A. Jumlah (1) + (2) = Rp 42,780.00B. Overhead dan Profit 15% x A = Rp 6,417.00

Harga Satuan Pekerjaan (A+B) = Rp 49,197.00

PS 6.21 Memasang 1 m' pipa galvanis diameter 1"6.21.1 Bahan

Pipa galvanis 6 m 1" 1.200 x Rp. 21,000 = Rp. 25,200.00Perlengkapan 35% harga pipa x Rp. 21,000 = Rp. 7,350.00

Jumlah (1) = Rp. 32,550.006.21.2. Tenaga

Pekerja 0.054 Oh x Rp. 75,000 = Rp. 4,050.00Tukang batu 0.090 Oh x Rp. 100,000 = Rp. 9,000.00Kepala tukang 0.009 Oh x Rp. 110,000 = Rp. 990.00Mandor 0.027 Oh x Rp. 100,000 = Rp. 2,700.00

Jumlah (2) = Rp. 16,740.00A. Jumlah (1) + (2) = Rp 49,290.00B. Overhead dan Profit 15% x A = Rp 7,393.50

Harga Satuan Pekerjaan (A+B) = Rp 56,683.50

PS 6.22 Memasang 1 m' pipa galvanis diameter 1 ½"6.22.1 Bahan

Pipa galvanis 6 m 1 1/2" 1.200 x Rp. 31,500 = Rp. 37,800.00Perlengkapan 35% harga pipa x Rp. 31,500 = Rp. 11,025.00

Jumlah (1) = Rp. 48,825.006.22.2 Tenaga

Pekerja 0.108 Oh x Rp. 75,000 = Rp. 8,100.00Tukang batu 0.180 Oh x Rp. 100,000 = Rp. 18,000.00Kepala tukang 0.018 Oh x Rp. 110,000 = Rp. 1,980.00Mandor 0.0054 Oh x Rp. 100,000 = Rp. 540.00

Jumlah (2) = Rp. 28,620.00A. Jumlah (1) + (2) = Rp 77,445.00B. Overhead dan Profit 15% x A = Rp 11,616.75

Harga Satuan Pekerjaan (A+B) = Rp 89,061.75

PS 6.23 Memasang 1 m' pipa galvanis diameter 2"6.23.1 Bahan

Pipa galvanis 6 m 2" 1.200 x Rp. 43,050 = Rp. 51,660.00Perlengkapan 35% harga pipa x Rp. 43,050 = Rp. 15,067.50

Jumlah (1) = Rp. 66,727.506.23.2 Tenaga

Pekerja 0.108 Oh x Rp. 75,000 = Rp. 8,100.00Tukang batu 0.180 Oh x Rp. 100,000 = Rp. 18,000.00Kepala tukang 0.018 Oh x Rp. 110,000 = Rp. 1,980.00Mandor 0.0054 Oh x Rp. 100,000 = Rp. 540.00

Jumlah (2) = Rp. 28,620.00A. Jumlah (1) + (2) = Rp 95,347.50B. Overhead dan Profit 15% x A = Rp 14,302.13

Harga Satuan Pekerjaan (A+B) = Rp 109,649.63

Page 36: Daftar Analisa Pu 2013

Pekerjaan Sanitasi 36

PEKERJAAN SANITASI

PS 6.25 Memasang 1 m' pipa PVC tipe AW diameter ½"6.25.1 Bahan

Pipa PVC Tipe AW Ø 1/2" 1.200 x Rp. 4,480 = Rp. 5,376.00Perlengkapan 35% harga pipa x Rp. 4,480 = Rp. 1,568.00

Jumlah (1) = Rp. 6,944.006.25.2 Tenaga

Pekerja 0.036 Oh x Rp. 75,000 = Rp. 2,700.00Tukang batu 0.060 Oh x Rp. 100,000 = Rp. 6,000.00Kepala tukang 0.006 Oh x Rp. 110,000 = Rp. 660.00Mandor 0.0018 Oh x Rp. 100,000 = Rp. 180.00

Jumlah (2) = Rp. 9,540.00A. Jumlah (1) + (2) = Rp 16,484.00B. Overhead dan Profit 15% x A = Rp 2,472.60

Harga Satuan Pekerjaan (A+B) = Rp 18,956.60

PS 6.266.26.1 Bahan

Pipa PVC Tipe AW Ø 3/4" 1.200 x Rp. 5,740 = Rp. 6,888.00Perlengkapan 35% harga pipa x Rp. 5,740 = Rp. 2,009.00

Jumlah (1) = Rp. 8,897.006.26.2 Tenaga

Pekerja 0.036 Oh x Rp. 75,000 = Rp. 2,700.00Tukang batu 0.060 Oh x Rp. 100,000 = Rp. 6,000.00Kepala tukang 0.006 Oh x Rp. 110,000 = Rp. 660.00Mandor 0.0018 Oh x Rp. 100,000 = Rp. 180.00

Jumlah (2) = Rp. 9,540.00A. Jumlah (1) + (2) = Rp 18,437.00B. Overhead dan Profit 15% x A = Rp 2,765.55

Harga Satuan Pekerjaan (A+B) = Rp 21,202.55

PS 6.27 Memasang 1 m' pipa PVC tipe AW diameter 1"6.27.1 Bahan

Pipa PVC Tipe AW Ø 1" 1.200 x Rp. 8,960 = Rp. 10,752.00Perlengkapan 35% harga pipa x Rp. 8,960 = Rp. 3,136.00

Jumlah (1) = Rp. 13,888.006.27.2 Tenaga

Pekerja 0.036 Oh x Rp. 75,000 = Rp. 2,700.00Tukang batu 0.060 Oh x Rp. 100,000 = Rp. 6,000.00Kepala tukang 0.006 Oh x Rp. 110,000 = Rp. 660.00Mandor 0.0018 Oh x Rp. 100,000 = Rp. 180.00

Jumlah (2) = Rp. 9,540.00A. Jumlah (1) + (2) = Rp 23,428.00B. Overhead dan Profit 15% x A = Rp 3,514.20

Harga Satuan Pekerjaan (A+B) = Rp 26,942.20

PS 6.28 Memasang 1 m' pipa PVC tipe AW diameter 1 ½"6.28.1 Bahan

Pipa PVC Tipe AW Ø 11/2" 1.200 x Rp. 10,500 = Rp. 12,600.00Perlengkapan 35% harga pipa x Rp. 10,500 = Rp. 3,675.00

Jumlah (1) = Rp. 16,275.006.28.2 Tenaga

Pekerja 0.036 Oh x Rp. 75,000 = Rp. 2,700.00Tukang batu 0.060 Oh x Rp. 100,000 = Rp. 6,000.00Kepala tukang 0.006 Oh x Rp. 110,000 = Rp. 660.00Mandor 0.0018 Oh x Rp. 100,000 = Rp. 180.00

Jumlah (2) = Rp. 9,540.00A. Jumlah (1) + (2) = Rp 25,815.00B. Overhead dan Profit 15% x A = Rp 3,872.25

Harga Satuan Pekerjaan (A+B) = Rp 29,687.25

Memasang 1 m' pipa PVC tipe AW diameter ¾"

Page 37: Daftar Analisa Pu 2013

Pekerjaan Sanitasi 37

PEKERJAAN SANITASI

PS 6.29 Memasang 1 m' pipa PVC tipe AW diameter 2"6.29.1 Bahan

Pipa PVC Tipe AW Ø 2" 1.200 x Rp. 11,760 = Rp. 14,112.00Perlengkapan 35% harga pipa x Rp. 11,760 = Rp. 4,116.00

Jumlah (1) = Rp. 18,228.006.29.2 Tenaga

Pekerja 0.054 Oh x Rp. 75,000 = Rp. 4,050.00Tukang batu 0.090 Oh x Rp. 100,000 = Rp. 9,000.00Kepala tukang 0.009 Oh x Rp. 110,000 = Rp. 990.00Mandor 0.0027 Oh x Rp. 100,000 = Rp. 270.00

Jumlah (2) = Rp. 14,310.00A. Jumlah (1) + (2) = Rp 32,538.00B. Overhead dan Profit 15% x A = Rp 4,880.70

Harga Satuan Pekerjaan (A+B) = Rp 37,418.70

PS 6.30 Memasang 1 m' pipa PVC tipe AW diameter 2 ½"6.30.1 Bahan

Pipa PVC Tipe AW Ø 21/2" 1.200 x Rp. 14,000 = Rp. 16,800.00Perlengkapan 35% harga pipa x Rp. 14,000 = Rp. 4,900.00

Jumlah (1) = Rp. 21,700.006.30.2 Tenaga

Pekerja 0.036 Oh x Rp. 75,000 = Rp. 2,700.00Tukang batu 0.060 Oh x Rp. 100,000 = Rp. 6,000.00Kepala tukang 0.006 Oh x Rp. 110,000 = Rp. 660.00Mandor 0.0018 Oh x Rp. 100,000 = Rp. 180.00

Jumlah (2) = Rp. 9,540.00A. Jumlah (1) + (2) = Rp 31,240.00B. Overhead dan Profit 15% x A = Rp 4,686.00

Harga Satuan Pekerjaan (A+B) = Rp 35,926.00

PS 6.31 Memasang 1 m' pipa PVC tipe AW diameter 3"6.31.1 Bahan

Pipa PVC Tipe AW Ø 3" 1.200 x Rp. 18,060 = Rp. 21,672.00Perlengkapan 35% harga pipa x Rp. 18,060 = Rp. 6,321.00

Jumlah (1) = Rp. 27,993.006.31.2 Tenaga

Pekerja 0.081 Oh x Rp. 75,000 = Rp. 6,075.00Tukang batu 0.135 Oh x Rp. 100,000 = Rp. 13,500.00Kepala tukang 0.0135 Oh x Rp. 110,000 = Rp. 1,485.00Mandor 0.0041 Oh x Rp. 100,000 = Rp. 410.00

Jumlah (2) = Rp. 21,470.00A. Jumlah (1) + (2) = Rp 49,463.00B. Overhead dan Profit 15% x A = Rp 7,419.45

Harga Satuan Pekerjaan (A+B) = Rp 56,882.45

PS 6.32 Memasang 1 m' pipa PVC tipe AW diameter 4"6.32.1 Bahan

Pipa PVC Tipe AW Ø 4" 1.200 x Rp. 25,480 = Rp. 30,576.00Perlengkapan 35% harga pipa x Rp. 25,480 = Rp. 8,918.00

Jumlah (1) = Rp. 39,494.006.32.2 Tenaga

Pekerja 0.081 Oh x Rp. 75,000 = Rp. 6,075.00Tukang batu 0.135 Oh x Rp. 100,000 = Rp. 13,500.00Kepala tukang 0.0135 Oh x Rp. 110,000 = Rp. 1,485.00Mandor 0.0041 Oh x Rp. 100,000 = Rp. 410.00

Jumlah (2) = Rp. 21,470.00A. Jumlah (1) + (2) = Rp 60,964.00B. Overhead dan Profit 15% x A = Rp 9,144.60

Harga Satuan Pekerjaan (A+B) = Rp 70,108.60

Page 38: Daftar Analisa Pu 2013

Pekerjaan Sanitasi 38

PEKERJAAN SANITASI

PS 6.33 Memasang 1 bh bak cuci piring stainles steel6.33.1 Bahan

Bak cuci piring 2 lobang komplet 1.000 Bh x Rp. 816,900 = Rp. 816,900.00Jumlah (1) = Rp. 816,900.00

6.33.2 TenagaPekerja 0.030 Oh x Rp. 75,000 = Rp. 2,250.00Tukang batu 0.300 Oh x Rp. 100,000 = Rp. 30,000.00Kepala tukang 0.030 Oh x Rp. 110,000 = Rp. 3,300.00Mandor 0.0015 Oh x Rp. 100,000 = Rp. 150.00

Jumlah (2) = Rp. 35,700.00A. Jumlah (1) + (2) = Rp 852,600.00B. Overhead dan Profit 15% x A = Rp 127,890.00

Harga Satuan Pekerjaan (A+B) = Rp 980,490.00

PS 6.34 Memasang 1 bh bak cuci piring teraso6.34.1 Bahan

Bak cuci piring 2 lobang komplet 1.000 Bh x Rp. 282,250 = Rp. 282,250.00Semen portland 20.000 Kg x Rp. 1,362 = Rp. 27,240.00

Pasir pasang 0.050 M³ x Rp. 106,050 = Rp. 5,302.50Jumlah (1) = Rp. 314,792.50

6.34.2 TenagaPekerja 0.050 Oh x Rp. 75,000 = Rp. 3,750.00Tukang batu 0.500 Oh x Rp. 100,000 = Rp. 50,000.00Kepala tukang 0.050 Oh x Rp. 110,000 = Rp. 5,500.00Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 59,500.00A. Jumlah (1) + (2) = Rp 374,292.50B. Overhead dan Profit 15% x A = Rp 56,143.88

Harga Satuan Pekerjaan (A+B) = Rp 430,436.38

PS 6.356.35.1 Bahan

Kran air Ø 1/2" - 3/4" 1.000 Bh x Rp. 15,000 = Rp. 15,000.00Jumlah (1) = Rp. 15,000.00

6.35.2 TenagaPekerja 0.010 Oh x Rp. 75,000 = Rp. 750.00Tukang batu 0.100 Oh x Rp. 100,000 = Rp. 10,000.00Kepala tukang 0.010 Oh x Rp. 110,000 = Rp. 1,100.00Mandor 0.005 Oh x Rp. 100,000 = Rp. 500.00

Jumlah (2) 12,350.00A. Jumlah (1) + (2) = Rp 27,350.00B. Overhead dan Profit 15% x A = Rp 4,102.50

Harga Satuan Pekerjaan (A+B) = Rp 31,452.50

PS 6.36 Memasang 1 bh Floor drain6.36.1 Bahan

Floor drain 1.000 Bh x Rp. 21,180 = Rp. 21,180.00Jumlah (1) = Rp. 21,180.00

6.36.2 Tenaga Pekerja 0.010 Oh x Rp. 75,000 = Rp. 750.00Tukang batu 0.100 Oh x Rp. 100,000 = Rp. 10,000.00Kepala tukang 0.010 Oh x Rp. 110,000 = Rp. 1,100.00Mandor 0.005 Oh x Rp. 100,000 = Rp. 500.00

Jumlah (2) 12,350.00A. Jumlah (1) + (2) = Rp 33,530.00B. Overhead dan Profit 15% x A = Rp 5,029.50

Harga Satuan Pekerjaan (A+B) = Rp 38,559.50

******LANJUT PEKERJAAN BESI ALUMINIUM

Memasang 1 bh kran diameter ¾" atau ½"

Page 39: Daftar Analisa Pu 2013

Pekerjaan Pengecatan 39

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN PENGECATAN

PC 6.1 1M² Mengikis/ mengerok permukaan cat tembok lama6.1.1 Bahan

Soda api 0.050 Kg x Rp. 15,000 = Rp. 750.00Jumlah (1) = Rp. 750.00

6.1.2 Tenaga Pekerja 0.150 Oh x Rp. 75,000 = Rp. 11,250.00 Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 11,500.00A. Jumlah (1) + (2) = Rp 12,250.00B. Overhead dan Profit 15% x A = Rp 1,837.50

Harga Satuan Pekerjaan (A+B) = Rp 14,087.50

PC 6.2 1M² Mencuci bidang permukaan tembok yang pernah di cat6.2.1 Bahan

Sabun 0.050 Kg x Rp. 10,290 = Rp. 514.50 Jumlah (1) = Rp. 514.50

6.2.2 Tenaga Pekerja 0.150 Oh x Rp. 75,000 = Rp. 11,250.00 Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 11,500.00A. Jumlah (1) + (2) = Rp 12,014.50B. Overhead dan Profit 15% x A = Rp 1,802.18

Harga Satuan Pekerjaan (A+B) = Rp 13,816.68

PC 6.3 1M² Mengerok karat cat lama permukaan baja dengan cara manual6.3 .1 Bahan

Sabun 0.050 Kg x Rp. 10,290 = Rp. 514.50 Jumlah (1) = Rp. 514.50

6.3.2 Tenaga Pekerja 0.150 Oh x Rp. 75,000 = Rp. 11,250.00 Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 11,500.00A. Jumlah (1) + (2) = Rp 12,014.50B. Overhead dan Profit 10% x A = Rp 1,201.45

Harga Satuan Pekerjaan (A+B) = Rp 13,215.95

PC 6.4 1M² Menyabun permukaan tembok lama6.4 .1 Bahan

Sabun 0.050 Kg x Rp. 10,290 = Rp. 514.50 Jumlah (1) = Rp. 514.50

6.4.2 Tenaga Pekerja 0.150 Oh x Rp. 75,000 = Rp. 11,250.00 Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 11,500.00A. Jumlah (1) + (2) = Rp 12,014.50B. Overhead dan Profit 15% x A = Rp 1,802.18

Harga Satuan Pekerjaan (A+B) = Rp 13,816.68

PC 6.6 1M² Mendempul dan menggosok kayu6.6 .1 Bahan

Dempul 0.080 Kg x Rp. 8,190 = Rp. 655.20Minyak cat 0.020 Kg x Rp. 12,700 = Rp. 254.00Amplas 0.100 Lbr x Rp. 3,000 = Rp. 300.00

Jumlah (1) = Rp. 1,209.206.6.2 Tenaga

Pekerja 0.040 Oh x Rp. 75,000 = Rp. 3,000.00Tukang cat 0.040 Oh x Rp. 100,000 = Rp. 4,000.00Kepala tukang 0.040 Oh x Rp. 110,000 = Rp. 4,400.00Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 11,650.00A. Jumlah (1) + (2) = Rp 12,859.20

Page 40: Daftar Analisa Pu 2013

Pekerjaan Pengecatan 40

PEKERJAAN PENGECATAN

B. Overhead dan Profit 15% x A = Rp 1,928.88Harga Satuan Pekerjaan (A+B) = Rp 14,788.08

PC 6.7 1M² Pengecatan bidang kayu lama 6.7.1 Bahan

Plamir 0.150 Kg x Rp. 8,080 = Rp. 1,212.00Minyak cat 0.170 Kg x Rp. 12,700 = Rp. 2,159.00Cat Minyak 0.170 Kg x Rp. 52,500 = Rp. 8,925.00

Jumlah (1) = Rp. 12,296.006.7.2 Tenaga

Pekerja 0.070 Oh x Rp. 75,000 = Rp. 5,250.00Tukang cat 0.075 Oh x Rp. 100,000 = Rp. 7,500.00Kepala tukang 0.0075 Oh x Rp. 110,000 = Rp. 825.00Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 13,825.00A. Jumlah (1) + (2) = Rp 26,121.00B. Overhead dan Profit 15% x A = Rp 3,918.15

Harga Satuan Pekerjaan (A+B) = Rp 30,039.15

PC 6.8 1M² Pengecatan bidang kayu baru 1 lps Plamir, 1 lps cat dasar, 2 lps cat minyak 6.8.1 Bahan

Cat menie kayu 0.200 Kg x Rp. 35,280 = Rp. 7,056.00Plamir 0.150 Kg x Rp. 8,080 = Rp. 1,212.00Cat dasar 0.170 Kg x Rp. 38,850 = Rp. 6,604.50Cat Minyak 0.260 Kg x Rp. 52,500 = Rp. 13,650.00

Jumlah (1) = Rp. 28,522.506.8.2 Tenaga

Pekerja 0.070 Oh x Rp. 75,000 = Rp. 5,250.00Tukang cat 0.090 Oh x Rp. 100,000 = Rp. 9,000.00Kepala tukang 0.0090 Oh x Rp. 110,000 = Rp. 990.00Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 15,490.00A. Jumlah (1) + (2) = Rp 44,012.50B. Overhead dan Profit 15% x A = Rp 6,601.88

Harga Satuan Pekerjaan (A+B) = Rp 50,614.38

PC 6.9 1M² Pengecatan bidang kayu baru 1 lps Plamir, 1 lps cat dasar, 3 lps cat minyak 6.9.1 Bahan

Cat menie kayu 0.200 Kg x Rp. 35,280 = Rp. 7,056.00Plamir 0.150 Kg x Rp. 8,080 = Rp. 1,212.00Cat dasar 0.170 Kg x Rp. 38,850 = Rp. 6,604.50Cat Minyak 0.350 Kg x Rp. 52,500 = Rp. 18,375.00

Jumlah (1) = Rp. 33,247.506.9.2 Tenaga

Pekerja 0.070 Oh x Rp. 75,000 = Rp. 5,250.00Tukang cat 0.105 Oh x Rp. 100,000 = Rp. 10,500.00Kepala tukang 0.0105 Oh x Rp. 110,000 = Rp. 1,155.00Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 17,155.00A. Jumlah (1) + (2) = Rp 50,402.50B. Overhead dan Profit 15% x A = Rp 7,560.38

Harga Satuan Pekerjaan (A+B) = Rp 57,962.88

PC 6.12 1M² Pelaburan kayu dengan Residu6.12.1 Bahan

Residu / Kolter 0.350 Ltr x Rp. 7,700 = Rp. 2,695.00 Jumlah (1) = Rp. 2,695.00

6.12.2 Tenaga Pekerja 0.100 Oh x Rp. 75,000 = Rp. 7,500.00 Mandor 0.006 Oh x Rp. 100,000 = Rp. 600.00

Jumlah (2) = Rp. 8,100.00A. Jumlah (1) + (2) = Rp 10,795.00

Page 41: Daftar Analisa Pu 2013

Pekerjaan Pengecatan 41

PEKERJAAN PENGECATAN

B. Overhead dan Profit 15% x A = Rp 1,619.25Harga Satuan Pekerjaan (A+B) = Rp 12,414.25

Page 42: Daftar Analisa Pu 2013

Pekerjaan Pengecatan 42

PEKERJAAN PENGECATAN

PC 6.13 1M² Peleburan bidang kayu dan vernis6.13.1 Bahan

Cat Vernish 0.150 Kg x Rp. 56,500 = Rp. 8,475.00Dempul 0.050 Kg x Rp. 8,190 = Rp. 409.50Amplas 0.100 Lbr x Rp. 3,000 = Rp. 300.00Kuas 0.010 bh x Rp. 15,750 = Rp. 157.50

Jumlah (1) = Rp. 9,342.006.13.2 Tenaga

Pekerja 0.160 Oh x Rp. 75,000 = Rp. 12,000.00Tukang cat 0.160 Oh x Rp. 100,000 = Rp. 16,000.00Kepala tukang 0.016 Oh x Rp. 110,000 = Rp. 1,760.00Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 30,010.00A. Jumlah (1) + (2) = Rp 39,352.00B. Overhead dan Profit 15% x A = Rp 5,902.80

Harga Satuan Pekerjaan (A+B) = Rp 45,254.80

PC 6.14 1M² Pengecatan tembok baru (1 lapis plamir,1 lapis cat dasar,2 lapis cat penutup)6.14.1 Bahan

Plamir 0.120 Kg x Rp. 8,080 = Rp. 969.60Cat dasar 0.120 Kg x Rp. 38,850 = Rp. 4,662.00Cat Tembok setara Vinilex 0.260 Kg x Rp. 24,850 = Rp. 6,461.00

Jumlah (1) = Rp. 12,092.606.14.2 Tenaga

Pekerja 0.040 Oh x Rp. 75,000 = Rp. 3,000.00Tukang cat 0.120 Oh x Rp. 100,000 = Rp. 12,000.00Kepala tukang 0.0120 Oh x Rp. 110,000 = Rp. 1,320.00Mandor 0.002 Oh x Rp. 100,000 = Rp. 200.00

Jumlah (2) = Rp. 16,520.00A. Jumlah (1) + (2) = Rp 28,612.60B. Overhead dan Profit 15% x A = Rp 4,291.89

Harga Satuan Pekerjaan (A+B) = Rp 32,904.49

PC 6.15 1M² Pengecatan tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup )6.15.1 Bahan

Cat dasar 0.120 Kg x Rp. 38,850 = Rp. 4,662.00Cat Tembok setara Vinilex 0.260 Kg x Rp. 24,850 = Rp. 6,461.00

Jumlah (1) = Rp. 11,123.006.15.2 Tenaga

Pekerja 0.030 Oh x Rp. 75,000 = Rp. 2,250.00 Tukang cat 0.090 Oh x Rp. 100,000 = Rp. 9,000.00 Kepala tukang 0.0090 Oh x Rp. 110,000 = Rp. 990.00 Mandor 0.0015 Oh x Rp. 100,000 = Rp. 150.00

Jumlah (2) = Rp. 12,390.00A. Jumlah (1) + (2) = Rp 23,513.00B. Overhead dan Profit 15% x A = Rp 3,526.95

Harga Satuan Pekerjaan (A+B) = Rp 27,039.95

PC 6.19 1M² Pemasangan wall paper 6.19.1 Bahan

Wallpaper 1.200 M' x Rp. 75,000 = Rp. 90,000.00Lem Vinyl / Karet 0.200 Kg x Rp. 21,000 = Rp. 4,200.00

Jumlah (1) = Rp. 94,200.006.19.2 Tenaga

Pekerja 0.020 Oh x Rp. 75,000 = Rp. 1,500.00Tukang cat 0.200 Oh x Rp. 100,000 = Rp. 20,000.00Kepala tukang 0.002 Oh x Rp. 110,000 = Rp. 220.00Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 21,970.00A. Jumlah (1) + (2) = Rp 116,170.00B. Overhead dan Profit 15% x A = Rp 17,425.50

Harga Satuan Pekerjaan (A+B) = Rp 133,595.50

Page 43: Daftar Analisa Pu 2013

Pekerjaan Pengecatan 43

PEKERJAAN PENGECATAN

PC 6.20 1M² Pengecatan permukaan baja dengan meni besi 6.20.1 Bahan

Cat meni besi 0.100 Kg x Rp. 35,280 = Rp. 3,528.00Kuas 0.010 Bh x Rp. 15,750 = Rp. 157.50

Jumlah (1) = Rp. 3,685.506.20.2 Tenaga

Pekerja 0.020 Oh x Rp. 75,000 = Rp. 1,500.00Tukang cat 0.020 Oh x Rp. 100,000 = Rp. 2,000.00Kepala tukang 0.02 Oh x Rp. 110,000 = Rp. 2,200.00Mandor 0.01 Oh x Rp. 100,000 = Rp. 1,000.00

Jumlah (2) = Rp. 6,700.00A. Jumlah (1) + (2) = Rp 10,385.50B. Overhead dan Profit 15% x A = Rp 1,557.83

Harga Satuan Pekerjaan (A+B) = Rp 11,943.33

PC 6.21 1M² Pengecatan permukaan baja dengan meni besi dan perancah 6.21.1 Bahan

Cat meni besi 0.100 Kg x Rp. 35,280 = Rp. 3,528.00 Kuas 0.010 Bh x Rp. 15,750 = Rp. 157.50 Peranca kayu (kayu kelas II) 0.002 x Rp. 6,818,590 = Rp. 13,637.18

Jumlah (1) = Rp. 17,322.686.21.2 Tenaga

Pekerja 0.250 Oh x Rp. 75,000 = Rp. 18,750.00 Tukang cat 0.225 Oh x Rp. 100,000 = Rp. 22,500.00 Kepala tukang 0.0225 Oh x Rp. 110,000 = Rp. 2,475.00 Mandor 0.0075 Oh x Rp. 100,000 = Rp. 750.00

Jumlah (2) = Rp. 44,475.00A. Jumlah (1) + (2) = Rp 61,797.68B. Overhead dan Profit 15% x A = Rp 9,269.65

Harga Satuan Pekerjaan (A+B) = Rp 71,067.33

PC 6.23 1M² Pengecatan permukaan baja lapis seng (galbani) secara manual sistem 1 lapis cat konvensional dengan tebal 200 um.

6.23.1 Bahan Cat minyak besi 0.300 Kg x Rp. 52,500 = Rp. 15,750.00

Jumlah (1) = Rp. 15,750.006.23.2 Tenaga

Pekerja 0.060 Oh x Rp. 75,000 = Rp. 4,500.00Tukang cat 0.060 Oh x Rp. 100,000 = Rp. 6,000.00Kepala tukang 0.1200 Oh x Rp. 110,000 = Rp. 13,200.00Mandor 0.006 Oh x Rp. 100,000 = Rp. 600.00

Jumlah (2) = Rp. 24,300.00A. Jumlah (1) + (2) = Rp 40,050.00B. Overhead dan Profit 15% x A = Rp 6,007.50

Harga Satuan Pekerjaan (A+B) = Rp 46,057.50

PC 6.24 1M² Pengecatan permukaan baja lapis seng (galbani) secara manual sistem 3 lapis cat konvensional dengan tebal 200 um.

6.24.1 BahanCat dasar 0.110 Kg x Rp. 38,850 = Rp. 4,273.50Cat Menie besi 0.170 Kg x Rp. 35,280 = Rp. 5,997.60Cat minyak besi 0.080 Kg x Rp. 52,500 = Rp. 4,200.00

Jumlah (1) = Rp. 14,471.106.24.2 Tenaga

Pekerja 0.500 Oh x Rp. 75,000 = Rp. 37,500.00Tukang cat 0.800 Oh x Rp. 100,000 = Rp. 80,000.00Kepala tukang 0.300 Oh x Rp. 110,000 = Rp. 33,000.00Mandor 0.200 Oh x Rp. 100,000 = Rp. 20,000.00

Jumlah (2) = Rp. 170,500.00A. Jumlah (1) + (2) = Rp 184,971.10B. Overhead dan Profit 15% x A = Rp 27,745.67

Harga Satuan Pekerjaan (A+B) = Rp 212,716.77

Page 44: Daftar Analisa Pu 2013

Pekerjaan Pengecatan 44

PEKERJAAN PENGECATAN

PC 6.25 1M² Pengecatan permukaan baja lapis seng (galbani) secara semprot(airless spray) dengan sistem 1 lapis cat konvensional dengan tebal 200 um.

6.25.1 Bahan Cat dasar 0.300 Kg x Rp. 38,850 = Rp. 11,655.00

Jumlah (1) = Rp. 11,655.006.25.2 Tenaga

Pekerja 0.400 Oh x Rp. 75,000 = Rp. 30,000.00Tukang cat 0.700 Oh x Rp. 100,000 = Rp. 70,000.00Kepala tukang 0.200 Oh x Rp. 110,000 = Rp. 22,000.00Mandor 0.200 Oh x Rp. 100,000 = Rp. 20,000.00

Jumlah (2) = Rp. 142,000.00A. Jumlah (1) + (2) = Rp 153,655.00B. Overhead dan Profit 15% x A = Rp 23,048.25

Harga Satuan Pekerjaan (A+B) = Rp 176,703.25

****LANJUT PEKERJAAN SANITASI

Page 45: Daftar Analisa Pu 2013

Pekerjaan Penutup Lantai dan Dinding 45

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN PENUTUP LANTAI DAN DINDING

PPL 6.1 1 M² Pasang lantai ubin PC abu-abu ukuran 40 x 40 cm6.1.1 Bahan

Ubin PC abu-abu 6.630 Bh x Rp. 8,600 = Rp. 57,018.00Semen portland 9.800 Kg x Rp. 1,362 = Rp. 13,347.60Pasir pasang 0.0450 x Rp. 106,050 = Rp. 4,772.25

Jumlah (1) = Rp. 75,137.856.1.2 Tenaga

Pekerja 0.250 Oh x Rp. 75,000 = Rp. 18,750.00Tukang batu 0.125 Oh x Rp. 100,000 = Rp. 12,500.00Kepala tukang 0.013 Oh x Rp. 110,000 = Rp. 1,430.00Mandor 0.0130 Oh x Rp. 100,000 = Rp. 1,300.00

Jumlah (2) = Rp. 33,980.00A. Jumlah (1) + (2) = Rp 109,117.85B. Overhead dan Profit 15% x A = Rp 16,367.68

Harga Satuan Pekerjaan (A+B) = Rp 125,485.53

PPL 6.96.9.1 Bahan

Granite 40 x 40 6.630 Bh x Rp. 42,500 = Rp. 281,775.00Semen portland 9.800 Kg x Rp. 1,362 = Rp. 13,347.60Pasir pasang 0.0450 x Rp. 106,050 = Rp. 4,772.25Semen warna 40 kg 1.300 Kg x Rp. 3,612 = Rp. 4,695.60

Jumlah (1) = Rp. 304,590.456.9.2 Tenaga

Pekerja 0.250 Oh x Rp. 75,000 = Rp. 18,750.00Tukang batu 0.125 Oh x Rp. 100,000 = Rp. 12,500.00Kepala tukang 0.013 Oh x Rp. 110,000 = Rp. 1,430.00Mandor 0.0130 Oh x Rp. 100,000 = Rp. 1,300.00

Jumlah (2) = Rp. 33,980.00A. Jumlah (1) + (2) = Rp 338,570.45B. Overhead dan Profit 15% x A = Rp 50,785.57

Harga Satuan Pekerjaan (A+B) = Rp 389,356.02

PPL 6.106.10.1 Bahan

Gtanite 30 x 30 11.870 Bh x Rp. 26,260 = Rp. 311,706.20Semen portland 10.000 Kg x Rp. 1,362 = Rp. 13,620.00Pasir pasang 0.0450 x Rp. 106,050 = Rp. 4,772.25Semen warna 1.500 Kg x Rp. 3,612 = Rp. 5,418.00

Jumlah (1) = Rp. 335,516.456.10.2 Tenaga

Pekerja 0.260 Oh x Rp. 75,000 = Rp. 19,500.00Tukang batu 0.130 Oh x Rp. 100,000 = Rp. 13,000.00Kepala tukang 0.013 Oh x Rp. 110,000 = Rp. 1,430.00Mandor 0.0130 Oh x Rp. 100,000 = Rp. 1,300.00

Jumlah (2) = Rp. 35,230.00A. Jumlah (1) + (2) = Rp 370,746.45B. Overhead dan Profit 15% x A = Rp 55,611.97

Harga Satuan Pekerjaan (A+B) = Rp 426,358.42

PPL 6.13 1 M² Pasang lantai ubin teralux marmer ukuran 60 x 60 cm6.13.1 Bahan

Teralux Marmer 60 x 60 3.100 Bh x Rp. 112,000 = Rp. 347,200.00Semen portland 9.600 Kg x Rp. 1,362 = Rp. 13,075.20Pasir pasang 0.045 x Rp. 106,050 = Rp. 4,772.25Semen warna 1.500 Kg x Rp. 3,612 = Rp. 5,418.00

Jumlah (1) = Rp. 370,465.456.13.2 Tenaga

Pekerja 0.240 Oh x Rp. 75,000 = Rp. 18,000.00Tukang batu 0.120 Oh x Rp. 100,000 = Rp. 12,000.00Kepala tukang 0.012 Oh x Rp. 110,000 = Rp. 1,320.00Mandor 0.012 Oh x Rp. 100,000 = Rp. 1,200.00

Jumlah (2) = Rp. 32,520.00A. Jumlah (1) + (2) = Rp 402,985.45B. Overhead dan Profit 15% x A = Rp 60,447.82

Harga Satuan Pekerjaan (A+B) = Rp 463,433.27

1 M² Pasang lantai ubin granit ukuran 40 x 40 cm

1 M² Pasang lantai ubin granit ukuran 30 x 30 cm

Page 46: Daftar Analisa Pu 2013

Pekerjaan Penutup Lantai dan Dinding 46

PEKERJAAN PENUTUP LANTAI DAN DINDING

PPL 6.146.14.1 Bahan

Teralux Marmer 40 x 40 6.630 Bh x Rp. 49,200 = Rp. 326,196.00Semen portland 9.800 Kg x Rp. 1,362 = Rp. 13,347.60Pasir pasang 0.0450 x Rp. 106,050 = Rp. 4,772.25Semen warna 1.300 Kg x Rp. 3,612 = Rp. 4,695.60

Jumlah (1) = Rp. 349,011.456.14.2 Tenaga

Pekerja 0.250 Oh x Rp. 75,000 = Rp. 18,750.00Tukang batu 0.125 Oh x Rp. 100,000 = Rp. 12,500.00Kepala tukang 0.013 Oh x Rp. 110,000 = Rp. 1,430.00Mandor 0.0130 Oh x Rp. 100,000 = Rp. 1,300.00

Jumlah (2) = Rp. 33,980.00A. Jumlah (1) + (2) = Rp 382,991.45B. Overhead dan Profit 15% x A = Rp 57,448.72

Harga Satuan Pekerjaan (A+B) = Rp 440,440.17

PPL 6.156.15.1 Bahan

Teralux Marmer 30 x 30 11.870 Bh x Rp. 29,700 = Rp. 352,539.00Semen portland 10.000 Kg x Rp. 1,362 = Rp. 13,620.00Pasir pasang 0.0450 x Rp. 106,050 = Rp. 4,772.25Semen warna 1.500 Kg x Rp. 3,612 = Rp. 5,418.00

Jumlah (1) = Rp. 376,349.256.15.2 Tenaga

Pekerja 0.260 Oh x Rp. 75,000 = Rp. 19,500.00Tukang batu 0.130 Oh x Rp. 100,000 = Rp. 13,000.00Kepala tukang 0.013 Oh x Rp. 110,000 = Rp. 1,430.00Mandor 0.0130 Oh x Rp. 100,000 = Rp. 1,300.00

Jumlah (2) = Rp. 35,230.00A. Jumlah (1) + (2) = Rp 411,579.25B. Overhead dan Profit 15% x A = Rp 61,736.89

Harga Satuan Pekerjaan (A+B) = Rp 473,316.14

PPL 6.24 1 M' Pasang plint ubin granit uk. 10 x 40 cm6.24.1 Bahan

Plint Granito 10 x 40 cm 2.650 Bh x Rp. 18,400 = Rp. 48,760.00Semen portland 1.140 Kg x Rp. 1,362 = Rp. 1,552.68Pasir pasang 0.003 x Rp. 106,050 = Rp. 318.15Semen warna 0.100 Kg x Rp. 3,612 = Rp. 361.20

Jumlah (1) = Rp. 50,992.036.24.2 Tenaga

Pekerja 0.090 Oh x Rp. 75,000 = Rp. 6,750.00Tukang batu 0.090 Oh x Rp. 100,000 = Rp. 9,000.00Kepala tukang 0.009 Oh x Rp. 110,000 = Rp. 990.00Mandor 0.005 Oh x Rp. 100,000 = Rp. 500.00

Jumlah (2) = Rp. 17,240.00A. Jumlah (1) + (2) = Rp 68,232.03B. Overhead dan Profit 15% x A = Rp 10,234.80

Harga Satuan Pekerjaan (A+B) = Rp 78,466.83

PPL 6.25 1 M' Pasang plint ubin granit uk. 10 x 30 cm6.25.1 Bahan

Plint Granito 10 x 30 cm 3.530 Bh x Rp. 17,500 = Rp. 61,775.00Semen portland 1.140 Kg x Rp. 1,362 = Rp. 1,552.68Pasir pasang 0.003 x Rp. 106,050 = Rp. 318.15Semen warna 0.100 Kg x Rp. 3,612 = Rp. 361.20

Jumlah (1) = Rp. 64,007.036.25.2 Tenaga

Pekerja 0.090 Oh x Rp. 75,000 = Rp. 6,750.00Tukang batu 0.090 Oh x Rp. 100,000 = Rp. 9,000.00Kepala tukang 0.009 Oh x Rp. 110,000 = Rp. 990.00Mandor 0.005 Oh x Rp. 100,000 = Rp. 500.00

Jumlah (2) = Rp. 17,240.00A. Jumlah (1) + (2) = Rp 81,247.03B. Overhead dan Profit 15% x A = Rp 12,187.05

Harga Satuan Pekerjaan (A+B) = Rp 93,434.08

1 M² Pasang lantai ubin teralux marmer ukuran 40 x 40 cm

1 M² Pasang lantai ubin teralux marmer ukuran 30 x 30 cm

Page 47: Daftar Analisa Pu 2013

Pekerjaan Penutup Lantai dan Dinding 47

PEKERJAAN PENUTUP LANTAI DAN DINDING

PPL 6.28 1 M' Pasang plint ubin teralux marmer uk. 10 x 60 cm6.28.1 Bahan

Plint Teralux Marmer 10 x 60 1.700 Bh x Rp. 66,800 = Rp. 113,560.00Semen portland 1.140 Kg x Rp. 1,362 = Rp. 1,552.68Pasir pasang 0.003 x Rp. 106,050 = Rp. 318.15Semen warna 0.100 Kg x Rp. 3,612 = Rp. 361.20

Jumlah (1) = Rp. 115,792.036.28.2 Tenaga

Pekerja 0.090 Oh x Rp. 75,000 = Rp. 6,750.00Tukang batu 0.090 Oh x Rp. 100,000 = Rp. 9,000.00Kepala tukang 0.009 Oh x Rp. 110,000 = Rp. 990.00Mandor 0.005 Oh x Rp. 100,000 = Rp. 500.00

Jumlah (2) = Rp. 17,240.00A. Jumlah (1) + (2) = Rp 133,032.03B. Overhead dan Profit 15% x A = Rp 19,954.80

Harga Satuan Pekerjaan (A+B) = Rp 152,986.83

PPL 6.29 1 M' Pasang plint ubin teralux marmer uk. 10 x 40 cm6.29.1 Bahan

Plint Teralux Marmer 10 x 40 2.650 Bh x Rp. 30,500 = Rp. 80,825.00Semen portland 1.140 Kg x Rp. 1,362 = Rp. 1,552.68Pasir pasang 0.003 x Rp. 106,050 = Rp. 318.15Semen warna 0.100 Kg x Rp. 3,612 = Rp. 361.20

Jumlah (1) = Rp. 83,057.036.29.2 Tenaga

Pekerja 0.090 Oh x Rp. 75,000 = Rp. 6,750.00Tukang batu 0.090 Oh x Rp. 100,000 = Rp. 9,000.00Kepala tukang 0.009 Oh x Rp. 110,000 = Rp. 990.00Mandor 0.005 Oh x Rp. 100,000 = Rp. 500.00

Jumlah (2) = Rp. 17,240.00A. Jumlah (1) + (2) = Rp 100,297.03B. Overhead dan Profit 15% x A = Rp 15,044.55

Harga Satuan Pekerjaan (A+B) = Rp 115,341.58

PPL 6.30 1 M' Pasang plint ubin teralux marmer uk 10 x 30 cm6.30.1 Bahan

Plint Teralux Marmer 10 x 30 3.530 Bh x Rp. 17,500 = Rp. 61,775.00Semen portland 1.140 Kg x Rp. 1,362 = Rp. 1,552.68Pasir pasang 0.003 x Rp. 106,050 = Rp. 318.15Semen warna 0.100 Kg x Rp. 3,612 = Rp. 361.20

Jumlah (1) = Rp. 64,007.036.30.2 Tenaga

Pekerja 0.090 Oh x Rp. 75,000 = Rp. 6,750.00Tukang batu 0.090 Oh x Rp. 100,000 = Rp. 9,000.00Kepala tukang 0.009 Oh x Rp. 110,000 = Rp. 990.00Mandor 0.005 Oh x Rp. 100,000 = Rp. 500.00

Jumlah (2) = Rp. 17,240.00A. Jumlah (1) + (2) = Rp 81,247.03B. Overhead dan Profit 15% x A = Rp 12,187.05

Harga Satuan Pekerjaan (A+B) = Rp 93,434.08

PPL 6.32 1 M² Pasang lantai keramik artistik ukuran 10 x 20 cm6.32.1 Bahan

Keramik Artistik 10 x 20 53.000 Bh x Rp. 1,850 = Rp. 98,050.00Semen portland 8.190 Kg x Rp. 1,362 = Rp. 11,154.78Pasir pasang 0.045 x Rp. 106,050 = Rp. 4,772.25Semen warna 2.750 Kg x Rp. 3,612 = Rp. 9,933.00

Jumlah (1) = Rp. 14,705.256.32.2 Tenaga

Pekerja 0.700 Oh x Rp. 75,000 = Rp. 52,500.00Tukang 0.350 Oh x Rp. 100,000 = Rp. 35,000.00Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00Mandor 0.0350 Oh x Rp. 100,000 = Rp. 3,500.00

Jumlah (2) = Rp. 94,850.00A. Jumlah (1) + (2) = Rp 109,555.25B. Overhead dan Profit 15% x A = Rp 16,433.29

Harga Satuan Pekerjaan (A+B) = Rp 125,988.54

Page 48: Daftar Analisa Pu 2013

Pekerjaan Penutup Lantai dan Dinding 48

PEKERJAAN PENUTUP LANTAI DAN DINDING

PPL 6.33 1 M² Pasang lantai keramik artistik uk. 5 x 20 cm6.33.1 Bahan

Keramik Artistik 5 x 20 106.000 Bh x Rp. 1,100 = Rp. 116,600.00Semen portland 8.190 Kg x Rp. 1,362 = Rp. 11,154.78Pasir pasang 0.045 x Rp. 106,050 = Rp. 4,772.25Semen warna 3.200 Kg x Rp. 3,612 = Rp. 11,558.40

Jumlah (1) = Rp. 16,330.656.33.2 Tenaga

Pekerja 0.700 Oh x Rp. 75,000 = Rp. 52,500.00Tukang 0.350 Oh x Rp. 100,000 = Rp. 35,000.00Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00Mandor 0.0350 Oh x Rp. 100,000 = Rp. 3,500.00

Jumlah (2) = Rp. 94,850.00A. Jumlah (1) + (2) = Rp 111,180.65B. Overhead dan Profit 15% x A = Rp 16,677.10

Harga Satuan Pekerjaan (A+B) = Rp 127,857.75

PPL 6.35 1 M² Pasang lantai keramik uk. 30 x 30 cm6.35.1 Bahan

Keramik 30 x 30 11.870 Bh x Rp. 6,360 = Rp. 75,493.20Semen portland 10.000 Kg x Rp. 1,362 = Rp. 13,620.00Pasir pasang 0.045 x Rp. 106,050 = Rp. 4,772.25Semen warna 1.500 Kg x Rp. 3,612 = Rp. 5,418.00

Jumlah (1) = Rp. 99,303.456.35.2 Tenaga

Pekerja 0.700 Oh x Rp. 75,000 = Rp. 52,500.00Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00Mandor 0.035 Oh x Rp. 100,000 = Rp. 3,500.00

Jumlah (2) = Rp. 94,850.00A. Jumlah (1) + (2) = Rp 194,153.45B. Overhead dan Profit 15% x A = Rp 29,123.02

Harga Satuan Pekerjaan (A+B) = Rp 223,276.47

PPL 6.36 1 M² Pasang lantai keramik uk 20 x 20 cm6.36.1 Bahan

Keramik 20 x 20 26.500 Bh x Rp. 2,400 = Rp. 63,600.00Semen portland 10.400 Kg x Rp. 1,362 = Rp. 14,164.80Pasir pasang 0.045 x Rp. 106,050 = Rp. 4,772.25Semen warna 1.620 Kg x Rp. 3,612 = Rp. 5,851.44

Jumlah (1) = Rp. 88,388.496.36.2 Tenaga

Pekerja 0.700 Oh x Rp. 75,000 = Rp. 52,500.00Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00Mandor 0.035 Oh x Rp. 100,000 = Rp. 3,500.00

Jumlah (2) = Rp. 94,850.00A. Jumlah (1) + (2) = Rp 183,238.49B. Overhead dan Profit 15% x A = Rp 27,485.77

Harga Satuan Pekerjaan (A+B) = Rp 210,724.26

PPL 6.38 1 M² Pasang Lantai mozaik uk. 30 x 30 cm, 1 PC : 3 PP6.38.1 Bahan

Mozaik 30 x 30 11.870 Bh x Rp. 14,500 = Rp. 172,115.00Semen portland 14.150 Kg x Rp. 1,362 = Rp. 19,272.30Pasir pasang 0.039 x Rp. 106,050 = Rp. 4,135.95Semen warna 2.000 Kg x Rp. 3,612 = Rp. 7,224.00

Jumlah (1) = Rp. 202,747.256.61.2 Tenaga

Pekerja 0.700 Oh x Rp. 75,000 = Rp. 52,500.00Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00Mandor 0.035 Oh x Rp. 100,000 = Rp. 3,500.00

Jumlah (2) = Rp. 94,850.00A. Jumlah (1) + (2) = Rp 297,597.25B. Overhead dan Profit 15% x A = Rp 44,639.59

Harga Satuan Pekerjaan (A+B) = Rp 342,236.84

Page 49: Daftar Analisa Pu 2013

Pekerjaan Penutup Lantai dan Dinding 49

PEKERJAAN PENUTUP LANTAI DAN DINDING

PPL 6.39 1 M' Pasang Plint keramik uk. 10 x 30 cm6.39.1 Bahan

Plint Keramik 10 x 30 cm 5.300 Bh x Rp. 2,120 = Rp. 11,236.00Portland Cement 1.140 Kg x Rp. 1,362 = Rp. 1,552.68Pasir pasang 0.003 x Rp. 106,050 = Rp. 318.15Semen warna 0.025 Kg x Rp. 3,612 = Rp. 90.30

Jumlah (1) = Rp. 13,197.136.39.2 Tenaga

Pekerja 0.090 Oh x Rp. 75,000 = Rp. 6,750.00Tukang batu 0.090 Oh x Rp. 100,000 = Rp. 9,000.00Kepala tukang 0.009 Oh x Rp. 110,000 = Rp. 990.00Mandor 0.005 Oh x Rp. 100,000 = Rp. 500.00

Jumlah (2) = Rp. 17,240.00A. Jumlah (1) + (2) = Rp 30,437.13B. Overhead dan Profit 15% x A = Rp 4,565.57

Harga Satuan Pekerjaan (A+B) = Rp 35,002.70

PPL 6.40 1 M' Pasang plint keramik uk. 10 x 10 cm6.40.1 Bahan

Plint Keramik 10 x 10 cm 10.600 Bh x Rp. 1,300 = Rp. 13,780.00Portland Cement 1.140 Kg x Rp. 1,362 = Rp. 1,552.68Pasir pasang 0.003 x Rp. 106,050 = Rp. 318.15Semen warna 0.050 Kg x Rp. 3,612 = Rp. 180.60

Jumlah (1) = Rp. 15,831.436.40.2 Tenaga

Pekerja 0.090 Oh x Rp. 75,000 = Rp. 6,750.00Tukang batu 0.090 Oh x Rp. 100,000 = Rp. 9,000.00Kepala tukang 0.009 Oh x Rp. 110,000 = Rp. 990.00Mandor 0.005 Oh x Rp. 100,000 = Rp. 500.00

Jumlah (2) = Rp. 17,240.00A. Jumlah (1) + (2) = Rp 33,071.43B. Overhead dan Profit 15% x A = Rp 4,960.71

Harga Satuan Pekerjaan (A+B) = Rp 38,032.14

PPL 6.41 1 M' Pasang plint keramik uk. 5 x 20 cm6.41.1 Bahan

Plint Keramik 10 x 20 cm 5.300 Bh x Rp. 1,850 = Rp. 9,805.00Portland Cement 0.570 Kg x Rp. 1,362 = Rp. 776.34Pasir pasang 0.002 x Rp. 106,050 = Rp. 159.08Semen warna 0.013 Kg x Rp. 3,612 = Rp. 46.96

Jumlah (1) = Rp. 10,787.376.41.2 Tenaga

Pekerja 0.090 Oh x Rp. 75,000 = Rp. 6,750.00Tukang batu 0.090 Oh x Rp. 100,000 = Rp. 9,000.00Kepala tukang 0.009 Oh x Rp. 110,000 = Rp. 990.00Mandor 0.005 Oh x Rp. 100,000 = Rp. 500.00

. Jumlah (2) = Rp. 17,240.00A. Jumlah (1) + (2) = Rp 28,027.37B. Overhead dan Profit 15% x A = Rp 4,204.11

Harga Satuan Pekerjaan (A+B) = Rp 32,231.48

PPL 6.436.43.1 Bahan

Granito 60 x 60 2.760 Bh x Rp. 89,600 = Rp. 247,296.00Portland Cement 8.190 Kg x Rp. 1,362 = Rp. 11,154.78Pasir pasang 0.045 x Rp. 106,050 = Rp. 4,772.25Semen warna 0.650 Kg x Rp. 3,612 = Rp. 2,347.80

Jumlah (1) = Rp. 265,570.836.43.2 Tenaga

Pekerja 0.700 Oh x Rp. 75,000 = Rp. 52,500.00Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00Mandor 0.035 Oh x Rp. 100,000 = Rp. 3,500.00

. Jumlah (2) = Rp. 94,850.00A. Jumlah (1) + (2) = Rp 360,420.83B. Overhead dan Profit 15% x A = Rp 54,063.12

Harga Satuan Pekerjaan (A+B) = Rp 414,483.95

1 M² Pasang lantai granito uk. 60 x 60 cm

Page 50: Daftar Analisa Pu 2013

Pekerjaan Penutup Lantai dan Dinding 50

PEKERJAAN PENUTUP LANTAI DAN DINDING

PPL 6.446.44.1 Bahan

Karpet wool 1.050 x Rp. 65,000 = Rp. 68,250.00Lem 0.350 Kg x Rp. 21,000 = Rp. 7,350.00

Jumlah (1) = Rp. 75,600.006.44.2 Tenaga

Pekerja 0.170 Oh x Rp. 75,000 = Rp. 12,750.00Tukang batu 0.170 Oh x Rp. 100,000 = Rp. 17,000.00Kepala tukang 0.017 Oh x Rp. 110,000 = Rp. 1,870.00Mandor 0.009 Oh x Rp. 100,000 = Rp. 900.00

. Jumlah (2) = Rp. 32,520.00A. Jumlah (1) + (2) = Rp 108,120.00B. Overhead dan Profit 15% x A = Rp 16,218.00

Harga Satuan Pekerjaan (A+B) = Rp 124,338.00

PPL 6.456.45.1 Bahan

Underlayer/Pelapis 1.050 x Rp. 104,500 = Rp. 109,725.00Lem 0.350 Kg x Rp. 21,000 = Rp. 7,350.00

Jumlah (1) = Rp. 117,075.006.45.2 Tenaga

Pekerja 0.120 Oh x Rp. 75,000 = Rp. 9,000.00Tukang batu 0.120 Oh x Rp. 100,000 = Rp. 12,000.00Kepala tukang 0.012 Oh x Rp. 110,000 = Rp. 1,320.00Mandor 0.006 Oh x Rp. 100,000 = Rp. 600.00

. Jumlah (2) = Rp. 22,920.00A. Jumlah (1) + (2) = Rp 139,995.00B. Overhead dan Profit 15% x A = Rp 20,999.25

Harga Satuan Pekerjaan (A+B) = Rp 160,994.25

PPL 6.466.46.1 Bahan

Parquet 1.050 x Rp. 315,500 = Rp. 331,275.00Lem 0.600 Kg x Rp. 21,000 = Rp. 12,600.00

Jumlah (1) = Rp. 343,875.006.46.2 Tenaga

Pekerja 0.700 Oh x Rp. 75,000 = Rp. 52,500.00Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00Mandor 0.035 Oh x Rp. 100,000 = Rp. 3,500.00

. Jumlah (2) = Rp. 94,850.00A. Jumlah (1) + (2) = Rp 438,725.00B. Overhead dan Profit 15% x A = Rp 65,808.75

Harga Satuan Pekerjaan (A+B) = Rp 504,533.75

PPL 6.476.47.1 Bahan

Gymfloor 1.050 x Rp. 210,000 = Rp. 220,500.00Lem 0.600 Kg x Rp. 21,000 = Rp. 12,600.00

Jumlah (1) = Rp. 233,100.006.47.2 Tenaga

Pekerja 0.700 Oh x Rp. 75,000 = Rp. 52,500.00Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00Mandor 0.035 Oh x Rp. 100,000 = Rp. 3,500.00

. Jumlah (2) = Rp. 94,850.00A. Jumlah (1) + (2) = Rp 327,950.00B. Overhead dan Profit 15% x A = Rp 49,192.50

Harga Satuan Pekerjaan (A+B) = Rp 377,142.50

1 M² Pasang lantai karpet

1 M² Pasang underlayer/pelapis bawah karpet

1 M² Pasang lantai parquit kayu

1 M² Pasang lantai kayu (gymfloor)

Page 51: Daftar Analisa Pu 2013

Pekerjaan Penutup Lantai dan Dinding 51

PEKERJAAN PENUTUP LANTAI DAN DINDING

PPL 6.486.48.1 Bahan

Porceline 11 x 11 86.000 Bh x Rp. 1,100 = Rp. 94,600.00Semen portland 9.300 Kg x Rp. 1,362 = Rp. 12,666.60Pasir pasang 0.018 x Rp. 106,050 = Rp. 1,908.90Semen warna 1.500 Kg x Rp. 3,612 = Rp. 5,418.00

Jumlah (1) = Rp. 114,593.506.48.2 Tenaga

Pekerja 1.000 Oh x Rp. 75,000 = Rp. 75,000.00Tukang batu 0.500 Oh x Rp. 100,000 = Rp. 50,000.00Kepala tukang 0.050 Oh x Rp. 110,000 = Rp. 5,500.00Mandor 0.050 Oh x Rp. 100,000 = Rp. 5,000.00

. Jumlah (2) = Rp. 135,500.00A. Jumlah (1) + (2) = Rp 250,093.50B. Overhead dan Profit 15% x A = Rp 37,514.03

Harga Satuan Pekerjaan (A+B) = Rp 287,607.53

PPL 6.496.49.1 Bahan

Porceline 15 x 15 45.000 Bh x Rp. 2,250 = Rp. 101,250.00Semen portland 9.300 Kg x Rp. 1,362 = Rp. 12,666.60Pasir pasang 0.018 x Rp. 106,050 = Rp. 1,908.90Semen warna 2.750 Kg x Rp. 3,612 = Rp. 9,933.00

Jumlah (1) = Rp. 125,758.506.49.2 Tenaga

Pekerja 0.900 Oh x Rp. 75,000 = Rp. 67,500.00Tukang batu 0.450 Oh x Rp. 100,000 = Rp. 45,000.00Kepala tukang 0.045 Oh x Rp. 110,000 = Rp. 4,950.00Mandor 0.045 Oh x Rp. 100,000 = Rp. 4,500.00

. Jumlah (2) = Rp. 121,950.00A. Jumlah (1) + (2) = Rp 247,708.50B. Overhead dan Profit 15% x A = Rp 37,156.28

Harga Satuan Pekerjaan (A+B) = Rp 284,864.78

PPL 6.516.51.1 Bahan

Porceline 10 x 20 53.000 Bh x Rp. 1,850 = Rp. 98,050.00Semen portland 9.300 Kg x Rp. 1,362 = Rp. 12,666.60Pasir pasang 0.018 x Rp. 106,050 = Rp. 1,908.90Semen warna 2.750 Kg x Rp. 3,612 = Rp. 9,933.00

Jumlah (1) = Rp. 122,558.506.51.2 Tenaga

Pekerja 0.900 Oh x Rp. 75,000 = Rp. 67,500.00Tukang batu 0.450 Oh x Rp. 100,000 = Rp. 45,000.00Kepala tukang 0.045 Oh x Rp. 110,000 = Rp. 4,950.00Mandor 0.045 Oh x Rp. 100,000 = Rp. 4,500.00

. Jumlah (2) = Rp. 121,950.00A. Jumlah (1) + (2) = Rp 244,508.50B. Overhead dan Profit 15% x A = Rp 36,676.28

Harga Satuan Pekerjaan (A+B) = Rp 281,184.78

PPL 6.526.52.1 Bahan

Keramik Artistik 5x20 106.000 Bh x Rp. 1,100 = Rp. 116,600.00Semen portland 9.300 Kg x Rp. 1,362 = Rp. 12,666.60Pasir pasang 0.018 x Rp. 106,050 = Rp. 1,908.90Semen warna 2.900 Kg x Rp. 3,612 = Rp. 10,474.80

Jumlah (1) = Rp. 141,650.306.52.2 Tenaga

Pekerja 0.900 Oh x Rp. 75,000 = Rp. 67,500.00Tukang batu 0.450 Oh x Rp. 100,000 = Rp. 45,000.00Kepala tukang 0.045 Oh x Rp. 110,000 = Rp. 4,950.00Mandor 0.045 Oh x Rp. 100,000 = Rp. 4,500.00

. Jumlah (2) = Rp. 121,950.00A. Jumlah (1) + (2) = Rp 263,600.30B. Overhead dan Profit 15% x A = Rp 39,540.05

Harga Satuan Pekerjaan (A+B) = Rp 303,140.35

1 M² Pasang dinding porselen uk. 11 x 11 cm

1 M² Pasang dinding porselin uk. 15 x 15 cm

1 M² Pasang dinding keramik artistik uk. 10 x 20 cm

1 M² Pasang dinding keramik artistik uk. 5 x 20 cm

Page 52: Daftar Analisa Pu 2013

Pekerjaan Penutup Lantai dan Dinding 52

PEKERJAAN PENUTUP LANTAI DAN DINDING

PPL 6.536.53.1 Bahan

Keramik Artistik 10 x 20 53.000 Bh x Rp. 1,850 = Rp. 98,050.00Semen portland 9.300 Kg x Rp. 1,362 = Rp. 12,666.60Pasir pasang 0.018 x Rp. 106,050 = Rp. 1,908.90Semen warna 2.750 Kg x Rp. 3,612 = Rp. 9,933.00

Jumlah (1) = Rp. 122,558.506.53.2 Tenaga

Pekerja 0.900 Oh x Rp. 75,000 = Rp. 67,500.00Tukang batu 0.450 Oh x Rp. 100,000 = Rp. 45,000.00Kepala tukang 0.045 Oh x Rp. 110,000 = Rp. 4,950.00Mandor 0.045 Oh x Rp. 100,000 = Rp. 4,500.00

. Jumlah (2) = Rp. 121,950.00A. Jumlah (1) + (2) = Rp 244,508.50B. Overhead dan Profit 15% x A = Rp 36,676.28

Harga Satuan Pekerjaan (A+B) = Rp 281,184.78

PPL 6.546.54.1 Bahan

Keramik 20x20 26.500 Bh x Rp. 2,400 = Rp. 63,600.00Semen portland 9.300 Kg x Rp. 1,362 = Rp. 12,666.60Pasir pasang 0.018 x Rp. 106,050 = Rp. 1,908.90Semen warna 1.940 Kg x Rp. 3,612 = Rp. 7,007.28

Jumlah (1) = Rp. 85,182.786.54.2 Tenaga

Pekerja 0.900 Oh x Rp. 75,000 = Rp. 67,500.00Tukang batu 0.450 Oh x Rp. 100,000 = Rp. 45,000.00Kepala tukang 0.045 Oh x Rp. 110,000 = Rp. 4,950.00Mandor 0.045 Oh x Rp. 100,000 = Rp. 4,500.00

. Jumlah (2) = Rp. 121,950.00A. Jumlah (1) + (2) = Rp 207,132.78B. Overhead dan Profit 15% x A = Rp 31,069.92

Harga Satuan Pekerjaan (A+B) = Rp 238,202.70

PPL 6.556.55.1 Bahan

Marmer 60x60 2.760 x Rp. 112,000 = Rp. 309,120.00Paku 12 cm 3.003 Bh x Rp. 18,900 = Rp. 56,756.70Semen portland 12.440 Kg x Rp. 1,362 = Rp. 16,943.28Pasir pasang 0.025 x Rp. 106,050 = Rp. 2,651.25Semen warna 0.650 Kg x Rp. 3,612 = Rp. 2,347.80

Jumlah (1) = Rp. 387,819.036.55.2 Tenaga

Pekerja 1.300 Oh x Rp. 75,000 = Rp. 97,500.00Tukang batu 0.650 Oh x Rp. 100,000 = Rp. 65,000.00Kepala tukang 0.065 Oh x Rp. 110,000 = Rp. 7,150.00Mandor 0.065 Oh x Rp. 100,000 = Rp. 6,500.00

. Jumlah (2) = Rp. 176,150.00A. Jumlah (1) + (2) = Rp 563,969.03B. Overhead dan Profit 15% x A = Rp 84,595.35

Harga Satuan Pekerjaan (A+B) = Rp 648,564.38

PPL 6.566.56.1 Bahan

Bata pelapis 3x7x24 63.000 Bh x Rp. 2,040 = Rp. 128,520.00Semen portland 12.440 Kg x Rp. 1,362 = Rp. 16,943.28Pasir pasang 0.025 x Rp. 106,050 = Rp. 2,651.25Semen warna 2.750 Kg x Rp. 3,612 = Rp. 9,933.00

Jumlah (1) = Rp. 158,047.536.56.2 Tenaga

Pekerja 1.000 Oh x Rp. 75,000 = Rp. 75,000.00Tukang batu 0.500 Oh x Rp. 100,000 = Rp. 50,000.00Kepala tukang 0.050 Oh x Rp. 110,000 = Rp. 5,500.00Mandor 0.050 Oh x Rp. 100,000 = Rp. 5,000.00

. Jumlah (2) = Rp. 135,500.00A. Jumlah (1) + (2) = Rp 293,547.53B. Overhead dan Profit 15% x A = Rp 44,032.13

Harga Satuan Pekerjaan (A+B) = Rp 337,579.66

1 M² Pasang dinding keramik uk. 10 x 20 cm

1 M² Pasang dinding keramik uk. 20 x 20 cm

1 M² Pasang dinding marmer uk. 60 x 60 cm

1 M² Pasang dinding bata pelapis uk. 3 x 7 x 24 cm

Page 53: Daftar Analisa Pu 2013

Pekerjaan Penutup Lantai dan Dinding 53

PEKERJAAN PENUTUP LANTAI DAN DINDING

PPL 6.576.57.1 Bahan

Batu Paras 1.100 M² x Rp. 210,000 = Rp. 231,000.00Semen portland 11.750 Kg x Rp. 1,362 = Rp. 16,003.50Pasir pasang 0.035 x Rp. 106,050 = Rp. 3,711.75

Jumlah (1) = Rp. 250,715.256.57.2 Tenaga

Pekerja 0.700 Oh x Rp. 75,000 = Rp. 52,500.00Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00Mandor 0.035 Oh x Rp. 100,000 = Rp. 3,500.00

. Jumlah (2) = Rp. 94,850.00A. Jumlah (1) + (2) = Rp 345,565.25B. Overhead dan Profit 15% x A = Rp 51,834.79

Harga Satuan Pekerjaan (A+B) = Rp 397,400.04

PPL 6.586.58.1 Bahan

Batu tempel hitam 1.100 x Rp. 157,500 = Rp. 173,250.00Semen portland 11.750 Kg x Rp. 1,362 = Rp. 16,003.50Pasir pasang 0.035 x Rp. 106,050 = Rp. 3,711.75

Jumlah (1) = Rp. 192,965.256.58.2 Tenaga

Pekerja 0.700 Oh x Rp. 75,000 = Rp. 52,500.00Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00Mandor 0.035 Oh x Rp. 100,000 = Rp. 3,500.00

. Jumlah (2) = Rp. 94,850.00A. Jumlah (1) + (2) = Rp 287,815.25B. Overhead dan Profit 15% x A = Rp 43,172.29

Harga Satuan Pekerjaan (A+B) = Rp 330,987.54

PPL 6.596.59.1 Bahan

Vynil karet 30 x 30 cm KL I 11.870 Bh x Rp. 9,800 = Rp. 116,326.00Lem vinyl 0.350 Kg x Rp. 25,000 = Rp. 8,750.00

Jumlah (1) = Rp. 125,076.006.59.2 Tenaga

Pekerja 0.150 Oh x Rp. 75,000 = Rp. 11,250.00Tukang batu 0.150 Oh x Rp. 100,000 = Rp. 15,000.00Kepala tukang 0.015 Oh x Rp. 110,000 = Rp. 1,650.00Mandor 0.008 Oh x Rp. 100,000 = Rp. 800.00

. Jumlah (2) = Rp. 28,700.00A. Jumlah (1) + (2) = Rp 153,776.00B. Overhead dan Profit 15% x A = Rp 23,066.40

Harga Satuan Pekerjaan (A+B) = Rp 176,842.40

PPL 6.606.60.1 Bahan

Wallpaper 2.200 M' x Rp. 75,000 = Rp. 165,000.00Lem 0.250 Kg x Rp. 21,000 = Rp. 5,250.00

Jumlah (1) = Rp. 170,250.006.60.2 Tenaga

Pekerja 0.350 Oh x Rp. 75,000 = Rp. 26,250.00Tukang batu 0.175 Oh x Rp. 100,000 = Rp. 17,500.00Kepala tukang 0.017 Oh x Rp. 110,000 = Rp. 1,870.00Mandor 0.002 Oh x Rp. 100,000 = Rp. 200.00

. Jumlah (2) = Rp. 45,820.00A. Jumlah (1) + (2) = Rp 216,070.00B. Overhead dan Profit 15% x A = Rp 32,410.50

Harga Satuan Pekerjaan (A+B) = Rp 248,480.50

1 M² Pasang dinding batu paras

1 M² Pasang dinding batu tempel hitam

1 M² Pasang lantai vinyl uk. 30 x 30 cm

1 M² Pasang wallpaper, lebar 50 cm

Page 54: Daftar Analisa Pu 2013

Pekerjaan Penutup Lantai dan Dinding 54

PEKERJAAN PENUTUP LANTAI DAN DINDING

PPL 6.616.61.1 Bahan

Floor hardener 5.000 Kg x Rp. 4,090 = Rp. 20,450.00Jumlah (1) = Rp. 20,450.00

6.61.2 TenagaPekerja 0.120 Oh x Rp. 75,000 = Rp. 9,000.00Tukang batu 0.120 Oh x Rp. 100,000 = Rp. 12,000.00Kepala tukang 0.012 Oh x Rp. 110,000 = Rp. 1,320.00Mandor 0.006 Oh x Rp. 100,000 = Rp. 600.00

. Jumlah (2) = Rp. 22,920.00A. Jumlah (1) + (2) = Rp 43,370.00B. Overhead dan Profit 15% x A = Rp 6,505.50

Harga Satuan Pekerjaan (A+B) = Rp 49,875.50Jumlah (1) + (2) = Rp. 43,370.00

PPL 6.626.62.1 Bahan

Vynil karet 30 x 30 cm KL II 1.760 Bh x Rp. 9,080 = Rp. 15,980.80Lem vinyl 0.080 Kg x Rp. 25,000 = Rp. 2,000.00

Jumlah (1) = Rp. 17,980.806.62.2 Tenaga

Pekerja 0.080 Oh x Rp. 75,000 = Rp. 6,000.00Tukang batu 0.080 Oh x Rp. 100,000 = Rp. 8,000.00Kepala tukang 0.008 Oh x Rp. 110,000 = Rp. 880.00Mandor 0.004 Oh x Rp. 100,000 = Rp. 400.00

. Jumlah (2) = Rp. 15,280.00A. Jumlah (1) + (2) = Rp 33,260.80B. Overhead dan Profit 15% x A = Rp 4,989.12

Harga Satuan Pekerjaan (A+B) = Rp 38,249.92

PPL 6.636.63.1 Bahan

Papan kayu kelas II 0.003 x Rp. 6,818,590 = Rp. 20,455.77Paku Skrup 0.050 Kg x Rp. 26,250 = Rp. 1,312.50

Jumlah (1) = Rp. 21,768.276.63.2 Tenaga

Pekerja 0.120 Oh x Rp. 75,000 = Rp. 9,000.00Tukang batu 0.120 Oh x Rp. 100,000 = Rp. 12,000.00Kepala tukang 0.012 Oh x Rp. 110,000 = Rp. 1,320.00Mandor 0.006 Oh x Rp. 100,000 = Rp. 600.00

. Jumlah (2) = Rp. 22,920.00A. Jumlah (1) + (2) = Rp 44,688.27B. Overhead dan Profit 15% x A = Rp 6,703.24

Harga Satuan Pekerjaan (A+B) = Rp 51,391.51

***********LANJUT PEKERJAAN CAT

1 M² Pasang floor hardener

1 M' Pasang plint vinyl uk. 30 x 30 cm dengan perekat

1 M' Pasang plint kayu kelas II tebal 2 cm, lebar 10 cm

Page 55: Daftar Analisa Pu 2013

Pekerjaan Kunci dan Kaca 55

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN KUNCI DAN KACA

PKK 6.1 1 buah pasang kunci tanam antik6.1.1 Bahan

Kunci tanam antik 1.000 Bh x Rp. 214,500 = Rp. 214,500.00Jumlah (1) = Rp. 214,500.00

6.1.2 TenagaPekerja 0.060 Oh x Rp. 75,000 = Rp. 4,500.00Tukang Kayu 0.600 Oh x Rp. 100,000 = Rp. 60,000.00Kepala Tukang 0.060 Oh x Rp. 110,000 = Rp. 6,600.00Mandor 0.003 Oh x Rp. 100,000 = Rp. 300.00

Jumlah (2) = Rp. 71,400.00A. Jumlah (1) + (2) = Rp 285,900.00B. Overhead dan Profit 15% x A = Rp 42,885.00

Harga Satuan Pekerjaan (A+B) = Rp 328,785.00

PKK 6.2 1 buah pasang kunci tanam biasa6.2.1 Bahan

Kunci tanam biasa 1.000 Bh x Rp. 65,000 = Rp. 65,000.00Jumlah (1) = Rp. 65,000.00

6.1.2 TenagaPekerja 0.010 Oh x Rp. 75,000 = Rp. 750.00Tukang Kayu 0.500 Oh x Rp. 100,000 = Rp. 50,000.00Kepala Tukang 0.010 Oh x Rp. 110,000 = Rp. 1,100.00Mandor 0.005 Oh x Rp. 100,000 = Rp. 500.00

Jumlah (2) = Rp. 52,350.00A. Jumlah (1) + (2) = Rp 117,350.00B. Overhead dan Profit 15% x A = Rp 17,602.50

Harga Satuan Pekerjaan (A+B) = Rp 134,952.50

PKK 6.3 1 buah pasang kunci tanam kamar mandi6.3.1 Bahan

Kunci tanam kamar mandi 1.000 Bh x Rp. 35,300 = Rp. 35,300.00Jumlah (1) = Rp. 35,300.00

6.3.2 TenagaPekerja 0.005 Oh x Rp. 75,000 = Rp. 375.00Tukang Kayu 0.500 Oh x Rp. 100,000 = Rp. 50,000.00Kepala Tukang 0.005 Oh x Rp. 110,000 = Rp. 550.00Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 51,175.00A. Jumlah (1) + (2) = Rp 86,475.00B. Overhead dan Profit 15% x A = Rp 12,971.25

Harga Satuan Pekerjaan (A+B) = Rp 99,446.25

PKK 6.4 1 buah pasang kunci silinder6.4.1 Bahan

Kunci silinder 1.000 Bh x Rp. 36,000 = Rp. 36,000.00Jumlah (1) = Rp. 36,000.00

6.4.2 TenagaPekerja 0.005 Oh x Rp. 75,000 = Rp. 375.00Tukang Kayu 0.500 Oh x Rp. 100,000 = Rp. 50,000.00Kepala Tukang 0.005 Oh x Rp. 110,000 = Rp. 550.00Mandor 0.00025 Oh x Rp. 100,000 = Rp. 25.00

Jumlah (2) = Rp. 50,950.00A. Jumlah (1) + (2) = Rp 86,950.00B. Overhead dan Profit 15% x A = Rp 13,042.50

Harga Satuan Pekerjaan (A+B) = Rp 99,992.50

Page 56: Daftar Analisa Pu 2013

Pekerjaan Kunci dan Kaca 56

PEKERJAAN KUNCI DAN KACA

PKK 6.5 1 buah pasang engsel pintu6.5.1 Bahan

engsel pintu 1.000 Bh x Rp. 14,120 = Rp. 14,120.00Jumlah (1) = Rp. 14,120.00

6.5.2 TenagaPekerja 0.015 Oh x Rp. 75,000 = Rp. 1,125.00Tukang Kayu 0.150 Oh x Rp. 100,000 = Rp. 15,000.00Kepala Tukang 0.015 Oh x Rp. 110,000 = Rp. 1,650.00Mandor 0.00075 Oh x Rp. 100,000 = Rp. 75.00

Jumlah (2) = Rp. 17,850.00A. Jumlah (1) + (2) = Rp 31,970.00B. Overhead dan Profit 15% x A = Rp 4,795.50

Harga Satuan Pekerjaan (A+B) = Rp 36,765.50

PKK 6.6 1 buah pasang engsel jendela kupu-kupu6.6.1 Bahan

Engsel jendela 1.000 Bh x Rp. 8,400 = Rp. 8,400.00Jumlah (1) = Rp. 8,400.00

6.6.2 TenagaPekerja 0.010 Oh x Rp. 75,000 = Rp. 750.00Tukang Kayu 0.100 Oh x Rp. 100,000 = Rp. 10,000.00Kepala Tukang 0.010 Oh x Rp. 110,000 = Rp. 1,100.00Mandor 0.0005 Oh x Rp. 100,000 = Rp. 50.00

Jumlah (2) = Rp. 11,900.00A. Jumlah (1) + (2) = Rp 20,300.00B. Overhead dan Profit 15% x A = Rp 3,045.00

Harga Satuan Pekerjaan (A+B) = Rp 23,345.00

PKK 6.7 1 buah pasang engsel angin6.7.1 Bahan

Engsel angin 1.000 Bh x Rp. 7,030 = Rp. 7,030.00Jumlah (1) = Rp. 7,030.00

6.7.2 TenagaPekerja 0.020 Oh x Rp. 75,000 = Rp. 1,500.00Tukang Kayu 0.200 Oh x Rp. 100,000 = Rp. 20,000.00Kepala Tukang 0.020 Oh x Rp. 110,000 = Rp. 2,200.00Mandor 0.010 Oh x Rp. 100,000 = Rp. 1,000.00

Jumlah (2) = Rp. 24,700.00A. Jumlah (1) + (2) = Rp 31,730.00B. Overhead dan Profit 15% x A = Rp 4,759.50

Harga Satuan Pekerjaan (A+B) = Rp 36,489.50

PKK 6.9 1 buah pasang kait angin6.9.1 Bahan

Kait angin 1.000 Bh x Rp. 19,120 = Rp. 19,120.00Jumlah (1) = Rp. 19,120.00

6.9.2 TenagaPekerja 0.015 Oh x Rp. 75,000 = Rp. 1,125.00Tukang Kayu 0.150 Oh x Rp. 100,000 = Rp. 15,000.00Kepala Tukang 0.015 Oh x Rp. 110,000 = Rp. 1,650.00Mandor 0.00075 Oh x Rp. 100,000 = Rp. 75.00

Jumlah (2) = Rp. 17,850.00A. Jumlah (1) + (2) = Rp 36,970.00B. Overhead dan Profit 15% x A = Rp 5,545.50

Harga Satuan Pekerjaan (A+B) = Rp 42,515.50

Page 57: Daftar Analisa Pu 2013

Pekerjaan Kunci dan Kaca 57

PEKERJAAN KUNCI DAN KACA

PKK 6.10 1 buah pasang door closer6.10.1 Bahan

Door closer 1.000 Bh x Rp. 210,000 = Rp. 210,000.00Jumlah (1) = Rp. 210,000.00

6.10.2 TenagaPekerja 0.050 Oh x Rp. 75,000 = Rp. 3,750.00Tukang Kayu 0.500 Oh x Rp. 100,000 = Rp. 50,000.00Kepala Tukang 0.050 Oh x Rp. 110,000 = Rp. 5,500.00Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 59,500.00A. Jumlah (1) + (2) = Rp 269,500.00B. Overhead dan Profit 15% x A = Rp 40,425.00

Harga Satuan Pekerjaan (A+B) = Rp 309,925.00

PKK 6.11 1 buah pasang kunci selot6.11.1 Bahan

Kunci selot 1.000 Bh x Rp. 27,230 = Rp. 27,230.00Jumlah (1) = Rp. 27,230.00

6.11.2 TenagaPekerja 0.020 Oh x Rp. 75,000 = Rp. 1,500.00Tukang Kayu 0.200 Oh x Rp. 100,000 = Rp. 20,000.00Kepala Tukang 0.020 Oh x Rp. 110,000 = Rp. 2,200.00Mandor 0.001 Oh x Rp. 100,000 = Rp. 100.00

Jumlah (2) = Rp. 23,800.00A. Jumlah (1) + (2) = Rp 51,030.00B. Overhead dan Profit 15% x A = Rp 7,654.50

Harga Satuan Pekerjaan (A+B) = Rp 58,684.50

PKK 6.12 1 buah pasang pegangan pintu / door holder6.12.1 Bahan

Pegangan pintu/door holder 1.000 Bh x Rp. 105,000 = Rp. 105,000.00Jumlah (1) = Rp. 105,000.00

6.12.2 TenagaPekerja 0.050 Oh x Rp. 75,000 = Rp. 3,750.00Tukang Kayu 0.500 Oh x Rp. 100,000 = Rp. 50,000.00Kepala Tukang 0.050 Oh x Rp. 110,000 = Rp. 5,500.00Mandor 0.0025 Oh x Rp. 100,000 = Rp. 250.00

Jumlah (2) = Rp. 59,500.00A. Jumlah (1) + (2) = Rp 164,500.00B. Overhead dan Profit 15% x A = Rp 24,675.00

Harga Satuan Pekerjaan (A+B) = Rp 189,175.00

PKK 6.13 1 buah pasang door stop6.13.1 Bahan

Door stop 1.000 Bh x Rp. 38,120 = Rp. 38,120.00Jumlah (1) = Rp. 38,120.00

6.13.2 TenagaPekerja 0.010 Oh x Rp. 75,000 = Rp. 750.00Tukang Kayu 0.100 Oh x Rp. 100,000 = Rp. 10,000.00Kepala Tukang 0.010 Oh x Rp. 110,000 = Rp. 1,100.00Mandor 0.0005 Oh x Rp. 100,000 = Rp. 50.00

Jumlah (2) = Rp. 11,900.00A. Jumlah (1) + (2) = Rp 50,020.00B. Overhead dan Profit 15% x A = Rp 7,503.00

Harga Satuan Pekerjaan (A+B) = Rp 57,523.00

Page 58: Daftar Analisa Pu 2013

Pekerjaan Kunci dan Kaca 58

PEKERJAAN KUNCI DAN KACA

PKK 6.14 1 buah pasang rel pintu dorong6.14.1 Bahan

Rel pintu dorong 1.000 Bh x Rp. 160,330 = Rp. 160,330.00Jumlah (1) = Rp. 160,330.00

6.14.2 TenagaPekerja 0.060 Oh x Rp. 75,000 = Rp. 4,500.00Tukang Kayu 0.600 Oh x Rp. 100,000 = Rp. 60,000.00Kepala Tukang 0.060 Oh x Rp. 110,000 = Rp. 6,600.00Mandor 0.003 Oh x Rp. 100,000 = Rp. 300.00

Jumlah (2) = Rp. 71,400.00A. Jumlah (1) + (2) = Rp 231,730.00B. Overhead dan Profit 15% x A = Rp 34,759.50

Harga Satuan Pekerjaan (A+B) = Rp 266,489.50

PKK 6.15 1 buah pasang kunci lemari6.15.1 Bahan

Kunci lemari 1.000 Bh x Rp. 12,340 = Rp. 12,340.00Jumlah (1) = Rp. 12,340.00

6.15.2 TenagaPekerja 0.025 Oh x Rp. 75,000 = Rp. 1,875.00Tukang Kayu 0.250 Oh x Rp. 100,000 = Rp. 25,000.00Kepala Tukang 0.025 Oh x Rp. 110,000 = Rp. 2,750.00Mandor 0.00125 Oh x Rp. 100,000 = Rp. 125.00

Jumlah (2) = Rp. 29,750.00A. Jumlah (1) + (2) = Rp 42,090.00B. Overhead dan Profit 15% x A = Rp 6,313.50

Harga Satuan Pekerjaan (A+B) = Rp 48,403.50

PKK 6.16 1 M² pasang kaca, tebal 3 mm6.16.1 Bahan

Kaca Polos tbl. 3 mm 1.100 x Rp. 90,000 = Rp. 99,000.00Jumlah (1) = Rp. 99,000.00

6.16.2 TenagaPekerja 0.015 Oh x Rp. 75,000 = Rp. 1,125.00Tukang Kayu 0.150 Oh x Rp. 100,000 = Rp. 15,000.00Kepala Tukang 0.015 Oh x Rp. 110,000 = Rp. 1,650.00Mandor 0.00075 Oh x Rp. 100,000 = Rp. 75.00

Jumlah (2) = Rp. 17,850.00A. Jumlah (1) + (2) = Rp 116,850.00B. Overhead dan Profit 15% x A = Rp 17,527.50

Harga Satuan Pekerjaan (A+B) = Rp 134,377.50

PKK 6.17 1 M² pasang kaca, tebal 5 mm6.17.1 Bahan

Kaca Polos tbl. 5 mm 1.100 x Rp. 120,000 = Rp. 132,000.00Jumlah (1) = Rp. 132,000.00

6.17.2 TenagaPekerja 0.0155 Oh x Rp. 75,000 = Rp. 1,162.50Tukang Kayu 0.1550 Oh x Rp. 100,000 = Rp. 15,500.00Kepala Tukang 0.0155 Oh x Rp. 110,000 = Rp. 1,705.00Mandor 0.00075 Oh x Rp. 100,000 = Rp. 75.00

Jumlah (2) = Rp. 18,442.50A. Jumlah (1) + (2) = Rp 150,442.50B. Overhead dan Profit 15% x A = Rp 22,566.38

Harga Satuan Pekerjaan (A+B) = Rp 173,008.88

Page 59: Daftar Analisa Pu 2013

Pekerjaan Kunci dan Kaca 59

PEKERJAAN KUNCI DAN KACA

PKK 6.18 1 M² pasang kaca, tebal 8 mm6.18.1 Bahan

Kaca Polos tbl. 8 mm 1.100 x Rp. 258,720 = Rp. 284,592.00Jumlah (1) = Rp. 284,592.00

6.18.2 TenagaPekerja 0.0165 Oh x Rp. 75,000 = Rp. 1,237.50Tukang Kayu 0.165 Oh x Rp. 100,000 = Rp. 16,500.00Kepala Tukang 0.0165 Oh x Rp. 110,000 = Rp. 1,815.00Mandor 0.0008 Oh x Rp. 100,000 = Rp. 80.00

Jumlah (2) = Rp. 19,632.50A. Jumlah (1) + (2) = Rp 304,224.50B. Overhead dan Profit 15% x A = Rp 45,633.67

Harga Satuan Pekerjaan (A+B) = Rp 349,858.18

PKK 6.19 1 M² pasang kaca buram, tebal 5 mm6.19.1 Bahan

Kaca buram/rayban tbl.5 m 1.100 x Rp. 125,000 = Rp. 137,500.00 Sealent 0.050 Kg x Rp. 39,330 = Rp. 1,966.50

Jumlah (1) = Rp. 139,466.506.19.2 Tenaga

Pekerja 0.0155 Oh x Rp. 75,000 = Rp. 1,162.50Tukang Kayu 0.1550 Oh x Rp. 100,000 = Rp. 15,500.00Kepala Tukang 0.0155 Oh x Rp. 110,000 = Rp. 1,705.00Mandor 0.00075 Oh x Rp. 100,000 = Rp. 75.00

Jumlah (2) = Rp. 18,442.50A. Jumlah (1) + (2) = Rp 157,909.00B. Overhead dan Profit 15% x A = Rp 23,686.35

Harga Satuan Pekerjaan (A+B) = Rp 181,595.35

PKK 6.20 1 M² pasang kaca cermin, tebal 5 mm6.20.1 Bahan

Kaca cermin tebal 5 mm 1.100 x Rp. 160,000 = Rp. 176,000.00Jumlah (1) = Rp. 176,000.00

6.20.2 TenagaPekerja 0.0155 Oh x Rp. 75,000 = Rp. 1,162.50Tukang Kayu 0.1550 Oh x Rp. 100,000 = Rp. 15,500.00Kepala Tukang 0.0155 Oh x Rp. 110,000 = Rp. 1,705.00Mandor 0.00075 Oh x Rp. 100,000 = Rp. 75.00

Jumlah (2) = Rp. 18,442.50A. Jumlah (1) + (2) = Rp 194,442.50B. Overhead dan Profit 15% x A = Rp 29,166.38

Harga Satuan Pekerjaan (A+B) = Rp 223,608.88

PKK 6.21 1 M² pasang kaca cermin, tebal 8 mm6.21.1 Bahan

Kaca cermin tebal 8 mm 1.100 x Rp. 258,720 = Rp. 284,592.00Jumlah (1) = Rp. 284,592.00

6.21.2 TenagaPekerja 0.0165 Oh x Rp. 75,000 = Rp. 1,237.50Tukang Kayu 0.165 Oh x Rp. 100,000 = Rp. 16,500.00Kepala Tukang 0.0165 Oh x Rp. 110,000 = Rp. 1,815.00Mandor 0.0008 Oh x Rp. 100,000 = Rp. 80.00

Jumlah (2) = Rp. 19,632.50A. Jumlah (1) + (2) = Rp 304,224.50B. Overhead dan Profit 15% x A = Rp 45,633.67

Harga Satuan Pekerjaan (A+B) = Rp 349,858.18

Page 60: Daftar Analisa Pu 2013

Pekerjaan Kunci dan Kaca 60

PEKERJAAN KUNCI DAN KACA

PKK 6.23 1 M² pasang kaca "wireglass" , tebal 5 mm6.23.1 Bahan

Kaca Wireglass 1.100 x Rp. 151,250 = Rp. 166,375.00Jumlah (1) = Rp. 166,375.00

6.23.2 TenagaPekerja 0.0155 Oh x Rp. 75,000 = Rp. 1,162.50Tukang Kayu 0.1550 Oh x Rp. 100,000 = Rp. 15,500.00Kepala Tukang 0.0155 Oh x Rp. 110,000 = Rp. 1,705.00Mandor 0.00075 Oh x Rp. 100,000 = Rp. 75.00

Jumlah (2) = Rp. 18,442.50A. Jumlah (1) + (2) = Rp 184,817.50B. Overhead dan Profit 15% x A = Rp 27,722.63

Harga Satuan Pekerjaan (A+B) = Rp 212,540.13

PKK 6.24 1 M² pasang kaca patri, tebal 5 mm6.24.1 Bahan

Kaca Patri 1.100 x Rp. 169,400 = Rp. 186,340.00Jumlah (1) = Rp. 186,340.00

6.24.2 TenagaPekerja 0.0250 Oh x Rp. 75,000 = Rp. 1,875.00Tukang Kayu 0.2500 Oh x Rp. 100,000 = Rp. 25,000.00Kepala Tukang 0.0250 Oh x Rp. 110,000 = Rp. 2,750.00Mandor 0.00125 Oh x Rp. 100,000 = Rp. 125.00

Jumlah (2) = Rp. 29,750.00A. Jumlah (1) + (2) = Rp 216,090.00B. Overhead dan Profit 15% x A = Rp 32,413.50

Harga Satuan Pekerjaan (A+B) = Rp 248,503.50

PKK 6.24A 1 M² pasang kaca Reyben, tebal 5 mm6.24.1 Bahan

Kaca Reyben 1.100 x Rp. 125,000 = Rp. 137,500.00Jumlah (1) = Rp. 137,500.00

6.24.2 TenagaPekerja 0.0155 Oh x Rp. 75,000 = Rp. 1,162.50Tukang Kayu 0.1550 Oh x Rp. 100,000 = Rp. 15,500.00Kepala Tukang 0.0155 Oh x Rp. 110,000 = Rp. 1,705.00Mandor 0.00075 Oh x Rp. 100,000 = Rp. 75.00

Jumlah (2) = Rp. 18,442.50A. Jumlah (1) + (2) = Rp 155,942.50B. Overhead dan Profit 15% x A = Rp 23,391.38

Harga Satuan Pekerjaan (A+B) = Rp 179,333.88

******LANJUT PEKERJAAN LANTAI DAN DINDING

Page 61: Daftar Analisa Pu 2013

Pekerjaan Penutup Atap 61

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN PENUTUP ATAP

PPA 6.7 1 M² Pasang roof light fiberglass ( 180 x 90 ) cm6.7.1 Bahan

Roof light fibreglass 0.600 Lbr x Rp. 46,390 = Rp. 27,834.00 Paku biasa ½ " - 1" 0.050 Kg x Rp. 18,900 = Rp. 945.00

Jumlah (1) = Rp. 28,779.006.7.2 Tenaga

Pekerja 0.140 Oh x Rp. 75,000 = Rp. 10,500.00Tukang Kayu 0.067 Oh x Rp. 100,000 = Rp. 6,700.00Kepala Tukang 0.007 Oh x Rp. 110,000 = Rp. 770.00Mandor 0.007 Oh x Rp. 100,000 = Rp. 700.00

Jumlah (2) = Rp. 18,670.00A. Jumlah (1) + (2) = Rp 47,449.00B. Overhead dan Profit 15% x A = Rp 7,117.35

Harga Satuan Pekerjaan (A+B) = Rp 54,566.35

PPA 6.11 1 M² Pasang atap asbes gelombang6.11.1 Bahan

Atap asbes gelombang 0.750 Lbr x Rp. 35,280 = Rp. 26,460.00 Paku seng 0.120 Kg x Rp. 42,380 = Rp. 5,085.60

Jumlah (1) = Rp. 31,545.606.11.2 Tenaga

Pekerja 0.140 Oh x Rp. 75,000 = Rp. 10,500.00Tukang Kayu 0.070 Oh x Rp. 100,000 = Rp. 7,000.00Kepala Tukang 0.007 Oh x Rp. 110,000 = Rp. 770.00Mandor 0.007 Oh x Rp. 100,000 = Rp. 700.00

Jumlah (2) = Rp. 18,970.00A. Jumlah (1) + (2) = Rp 50,515.60B. Overhead dan Profit 15% x A = Rp 7,577.34

Harga Satuan Pekerjaan (A+B) = Rp 58,092.94

PPA 6.22 1 M' Pasang nok asbes6.22.1 Bahan

Nok Asbes 1.20 Lbr x Rp. 11,550 = Rp. 13,860.00 Paku seng 0.050 Bh x Rp. 42,380 = Rp. 2,119.00

Jumlah (1) = Rp. 15,979.006.22.2 Tenaga

Pekerja 0.084 Oh x Rp. 75,000 = Rp. 6,300.00Tukang Kayu 0.125 Oh x Rp. 100,000 = Rp. 12,500.00Kepala Tukang 0.013 Oh x Rp. 110,000 = Rp. 1,430.00Mandor 0.004 Oh x Rp. 100,000 = Rp. 400.00

Jumlah (2) = Rp. 20,630.00A. Jumlah (1) + (2) = Rp 36,609.00B. Overhead dan Profit 15% x A = Rp 5,491.35

Harga Satuan Pekerjaan (A+B) = Rp 42,100.35

PPA 6.30 1 M² Pasang atap genteng beton6.30.1 Bahan

Atap genteng beton 11.00 Bh x Rp. 8,070 = Rp. 88,770.00 Paku biasa 2" - 5" 0.03 Kg x Rp. 18,900 = Rp. 567.00

Jumlah (1) = Rp. 89,337.006.30.2 Tenaga

Pekerja 0.200 Oh x Rp. 75,000 = Rp. 15,000.00Tukang Kayu 0.100 Oh x Rp. 100,000 = Rp. 10,000.00Kepala Tukang 0.010 Oh x Rp. 110,000 = Rp. 1,100.00Mandor 0.010 Oh x Rp. 100,000 = Rp. 1,000.00

Jumlah (2) = Rp. 27,100.00A. Jumlah (1) + (2) = Rp 116,437.00B. Overhead dan Profit 15% x A = Rp 17,465.55

Harga Satuan Pekerjaan (A+B) = Rp 133,902.55

PPA 6.31 1 M² Pasang atap genteng aspal6.31.1 Bahan

Genteng Aspal 6.900 Lbr x Rp. 29,350 = Rp. 202,515.00Tripleks tebal 4 mm 0.350 Lbr x Rp. 70,350 = Rp. 24,622.50Paku biasa ½" - 1" 0.030 Kg x Rp. 18,900 = Rp. 567.00Plastic aerator 0.500 Bh x Rp. 27,500 = Rp. 13,750.00

Jumlah (1) = Rp. 241,454.50

Page 62: Daftar Analisa Pu 2013

Pekerjaan Penutup Atap 62

PEKERJAAN PENUTUP ATAP

6.31.2 TenagaPekerja 0.200 Oh x Rp. 75,000 = Rp. 15,000.00Tukang Kayu 0.300 Oh x Rp. 100,000 = Rp. 30,000.00Kepala Tukang 0.003 Oh x Rp. 110,000 = Rp. 330.00Mandor 0.010 Oh x Rp. 100,000 = Rp. 1,000.00

Jumlah (2) = Rp. 46,330.00A. Jumlah (1) + (2) = Rp 287,784.50B. Overhead dan Profit 15% x A = Rp 43,167.67

Harga Satuan Pekerjaan (A+B) = Rp 330,952.18

PPA 6.32 1 M² Pasang atap genteng Metal6.32.1 Bahan

Atap genteng Metal 1.02 Lbr x Rp. 86,000 = Rp. 87,720.00 Paku biasa 2" - 5" 0.200 Kg x Rp. 18,900 = Rp. 3,780.00

Jumlah (1) = Rp. 91,500.006.32.2 Tenaga

Pekerja 0.200 Oh x Rp. 75,000 = Rp. 15,000.00Tukang Kayu 0.100 Oh x Rp. 100,000 = Rp. 10,000.00Kepala Tukang 0.010 Oh x Rp. 110,000 = Rp. 1,100.00Mandor 0.010 Oh x Rp. 100,000 = Rp. 1,000.00

Jumlah (2) = Rp. 27,100.00A. Jumlah (1) + (2) = Rp 118,600.00B. Overhead dan Profit 15% x A = Rp 17,790.00

Harga Satuan Pekerjaan (A+B) = Rp 136,390.00

PPA 6.33 1 M² Pasang atap sirap6.33.1 Bahan

Atap Sirap 60.00 Bh x Rp. 1,030 = Rp. 61,800.00 Paku biasa ½" - 1" 0.200 Kg x Rp. 18,900 = Rp. 3,780.00

Jumlah (1) = Rp. 65,580.006.33.2 Tenaga

Pekerja 0.166 Oh x Rp. 75,000 = Rp. 12,450.00Tukang Kayu 0.250 Oh x Rp. 100,000 = Rp. 25,000.00Kepala Tukang 0.025 Oh x Rp. 110,000 = Rp. 2,750.00Mandor 0.008 Oh x Rp. 100,000 = Rp. 800.00

Jumlah (2) = Rp. 41,000.00A. Jumlah (1) + (2) = Rp 106,580.00B. Overhead dan Profit 15% x A = Rp 15,987.00

Harga Satuan Pekerjaan (A+B) = Rp 122,567.00

PPA 6.34 1 M' Pasang nok genteng beton6.34.1 Bahan

Nok atap Genteng beton 3.50 Bh x Rp. 8,400 = Rp. 29,400.00Paku biasa 2" x 5" 0.050 Kg x Rp. 18,900 = Rp. 945.00Semen PC 10.800 Kg x Rp. 1,362 = Rp. 14,709.60Pasir pasang 0.032 x Rp. 106,050 = Rp. 3,393.60Semen warna 1.000 Kg x Rp. 3,612 = Rp. 3,612.00

Jumlah (1) = Rp. 52,060.206.34.2 Tenaga

Pekerja 0.400 Oh x Rp. 75,000 = Rp. 30,000.00Tukang Kayu 0.200 Oh x Rp. 100,000 = Rp. 20,000.00Kepala Tukang 0.020 Oh x Rp. 110,000 = Rp. 2,200.00Mandor 0.020 Oh x Rp. 100,000 = Rp. 2,000.00

Jumlah (2) = Rp. 54,200.00A. Jumlah (1) + (2) = Rp 106,260.20B. Overhead dan Profit 15% x A = Rp 15,939.03

Harga Satuan Pekerjaan (A+B) = Rp 122,199.23

PPA 6.35 1 M' Pasang nok genteng aspal6.35.1 Bahan

Genteng Aspal 2.00 Bh x Rp. 29,350 = Rp. 58,700.00Paku biasa ½" - 1" 0.050 Kg x Rp. 18,900 = Rp. 945.00Kayu Papan kelas II 0.0035 x Rp. 6,818,590 = Rp. 23,865.07

Jumlah (1) = Rp. 83,510.07

Page 63: Daftar Analisa Pu 2013

Pekerjaan Penutup Atap 63

PEKERJAAN PENUTUP ATAP

6.35.2 TenagaPekerja 0.125 Oh x Rp. 75,000 = Rp. 9,375.00Tukang Kayu 0.250 Oh x Rp. 100,000 = Rp. 25,000.00Kepala Tukang 0.025 Oh x Rp. 110,000 = Rp. 2,750.00Mandor 0.006 Oh x Rp. 100,000 = Rp. 600.00

Jumlah (2) = Rp. 37,725.00A. Jumlah (1) + (2) = Rp 121,235.07B. Overhead dan Profit 15% x A = Rp 18,185.26

Harga Satuan Pekerjaan (A+B) = Rp 139,420.32

PPA 6.36 1 M' Pasang nok genteng metal6.36.1 Bahan

Nok Genteng Metal 1.10 Bh x Rp. 41,140 = Rp. 45,254.00 Paku biasa ½" - 1" 0.050 Kg x Rp. 18,900 = Rp. 945.00

Jumlah (1) = Rp. 46,199.006.36.2 Tenaga

Pekerja 0.250 Oh x Rp. 75,000 = Rp. 18,750.00Tukang Kayu 0.150 Oh x Rp. 100,000 = Rp. 15,000.00Kepala Tukang 0.015 Oh x Rp. 110,000 = Rp. 1,650.00Mandor 0.013 Oh x Rp. 100,000 = Rp. 1,300.00

Jumlah (2) = Rp. 36,700.00A. Jumlah (1) + (2) = Rp 82,899.00B. Overhead dan Profit 15% x A = Rp 12,434.85

Harga Satuan Pekerjaan (A+B) = Rp 95,333.85

PPA 6.37 1 M' Pasang nok sirap6.37.1 Bahan

Seng plat 3" x 6" BJLS 35 0.400 Lbr x Rp. 76,650 = Rp. 30,660.00Paku biasa ½" - 1" 0.060 Kg x Rp. 18,900 = Rp. 1,134.00Paku biasa 2" - 5" 0.050 Kg x Rp. 18,900 = Rp. 945.00Kayu Papan kelas II 0.004 x Rp. 6,818,590 = Rp. 27,274.36

Jumlah (1) = Rp. 60,013.366.37.2 Tenaga

Pekerja 0.125 Oh x Rp. 75,000 = Rp. 9,375.00Tukang Kayu 0.250 Oh x Rp. 100,000 = Rp. 25,000.00Kepala Tukang 0.025 Oh x Rp. 110,000 = Rp. 2,750.00Mandor 0.006 Oh x Rp. 100,000 = Rp. 600.00

Jumlah (2) = Rp. 37,725.00A. Jumlah (1) + (2) = Rp 97,738.36B. Overhead dan Profit 15% x A = Rp 14,660.75

Harga Satuan Pekerjaan (A+B) = Rp 112,399.11

PPA 6.38 1 M2 Pasang atap seng gelombang 6.38.1 Bahan

Seng Gelombang 3"x 6" BJLS 35 0.700 Lbr x Rp. 76,650 = Rp. 53,655.00 Paku seng 0.040 Kg x Rp. 42,380 = Rp. 1,695.20

Jumlah (1) = Rp. 55,350.206.38.2 Tenaga

Pekerja 0.120 Oh x Rp. 75,000 = Rp. 9,000.00Tukang Kayu 0.060 Oh x Rp. 100,000 = Rp. 6,000.00Kepala Tukang 0.006 Oh x Rp. 110,000 = Rp. 660.00Mandor 0.006 Oh x Rp. 100,000 = Rp. 600.00

Jumlah (2) = Rp. 16,260.00A. Jumlah (1) + (2) = Rp 71,610.20B. Overhead dan Profit 15% x A = Rp 10,741.53

Harga Satuan Pekerjaan (A+B) = Rp 82,351.73

PPA 6.39 1 M' Pasang Nok Atap Seng 6.39.1 Bahan

Seng plat 3" x 6" BJLS 35 0.300 Lbr x Rp. 76,650 = Rp. 22,995.00 Paku Seng 0.020 Kg x Rp. 42,380 = Rp. 847.60

Jumlah (1) = Rp. 23,842.606.39.2 Tenaga

Pekerja 0.150 Oh x Rp. 75,000 = Rp. 11,250.00Tukang Kayu 0.070 Oh x Rp. 100,000 = Rp. 7,000.00Kepala Tukang 0.008 Oh x Rp. 110,000 = Rp. 880.00Mandor 0.006 Oh x Rp. 100,000 = Rp. 600.00

Jumlah (2) = Rp. 19,730.00A. Jumlah (1) + (2) = Rp 43,572.60B. Overhead dan Profit 15% x A = Rp 6,535.89

Harga Satuan Pekerjaan (A+B) = Rp 50,108.49

Page 64: Daftar Analisa Pu 2013

Pekerjaan Penutup Atap 64

PEKERJAAN PENUTUP ATAP

PPA 6.40 1 M2 Pasang atap aluminium 6.40.1 Bahan

Atap Aluminium gelombang tebal 0,55 1.050 x Rp. 98,180 = Rp. 103,089.00 Paku hak panjang 15 cm 0.020 Kg x Rp. 30,530 = Rp. 610.60

Jumlah (1) = Rp. 103,699.606.40.2 Tenaga

Pekerja 0.150 Oh x Rp. 75,000 = Rp. 11,250.00Tukang Kayu 0.075 Oh x Rp. 100,000 = Rp. 7,500.00Kepala Tukang 0.008 Oh x Rp. 110,000 = Rp. 880.00Mandor 0.006 Oh x Rp. 100,000 = Rp. 600.00

Jumlah (2) = Rp. 20,230.00A. Jumlah (1) + (2) = Rp 123,929.60B. Overhead dan Profit 15% x A = Rp 18,589.44

Harga Satuan Pekerjaan (A+B) = Rp 142,519.04

PPA 6.41 1 M2 Pasang nok aluminium 6.41.1 Bahan

Rabung Alluminium standard 40 cm 18 swg 22 1.200 x Rp. 47,890 = Rp. 57,468.00 Paku hak panjang 15 cm 0.040 Kg x Rp. 30,530 = Rp. 1,221.20

Jumlah (1) = Rp. 58,689.206.41.2 Tenaga

Pekerja 0.100 Oh x Rp. 75,000 = Rp. 7,500.00Tukang Kayu 0.100 Oh x Rp. 100,000 = Rp. 10,000.00Kepala Tukang 0.010 Oh x Rp. 110,000 = Rp. 1,100.00Mandor 0.010 Oh x Rp. 100,000 = Rp. 1,000.00

Jumlah (2) = Rp. 19,600.00A. Jumlah (1) + (2) = Rp 78,289.20B. Overhead dan Profit 15% x A = Rp 11,743.38

Harga Satuan Pekerjaan (A+B) = Rp 90,032.58

PPA 6.42 1 M2 Pasang aluminium foil6.42.1 Bahan

Alluminium foil 1.050 x Rp. 37,000 = Rp. 38,850.00Jumlah (1) = Rp. 38,850.00

6.42.2 TenagaPekerja 0.150 Oh x Rp. 75,000 = Rp. 11,250.00Tukang Kayu 0.050 Oh x Rp. 100,000 = Rp. 5,000.00Kepala Tukang 0.005 Oh x Rp. 110,000 = Rp. 550.00Mandor 0.008 Oh x Rp. 100,000 = Rp. 800.00

Jumlah (2) = Rp. 17,600.00A. Jumlah (1) + (2) = Rp 56,450.00B. Overhead dan Profit 15% x A = Rp 8,467.50

Harga Satuan Pekerjaan (A+B) = Rp 64,917.50

*********LANJUT PEKERJAAN KUNCI KACA

Page 65: Daftar Analisa Pu 2013

Pekerjaan Beton 65

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN BETON

PB 6.1 1 M³ Membuat beton mutu f'c = 7.4 Mpa (K 100), slump (12 ± 2) cm, w/c = 0.87 (1PC : 3,5PB : 4KR)6.1.1 Bahan

Semen portland 247.000 Kg x Rp. 1,362 = Rp. 336,414.00Pasir beton 869.000 Kg x Rp. 72.14 = Rp. 62,689.66Kerikil beton 999.000 Kg x Rp. 140.74 = Rp. 140,599.26Air 215.000 Ltr x Rp. 1.17 = Rp. 251.55

Jumlah (1) = Rp. 539,954.476.1.2 Tenaga

Pekerja 1.650 Oh x Rp. 75,000 = Rp. 123,750.00Tukang batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Kepala tukang 0.028 Oh x Rp. 110,000 = Rp. 3,080.00Mandor 0.083 Oh x Rp. 100,000 = Rp. 8,300.00

Jumlah (2) = Rp. 162,630.00A. Jumlah (1) + (2) = Rp 702,584.47B. Overhead dan Profit 15% x A = Rp 105,387.67

Harga Satuan Pekerjaan (A+B) = Rp 807,972.14

PB 6.2 1 M³ Membuat beton mutu f'c = 9.8 Mpa (K 125), slump (12 ± 2) cm, w/c = 0.78 (1PC : 3PB : 3,5KR)6.2.1 Bahan

Semen portland 276.000 Kg x Rp. 1,362 = Rp. 375,912.00Pasir beton 828.000 Kg x Rp. 72.14 = Rp. 59,731.92Kerikil beton 1012.000 Kg x Rp. 140.74 = Rp. 142,428.88Air 215.000 Ltr x Rp. 1.17 = Rp. 251.55

Jumlah (1) = Rp. 578,324.356.2.2 Tenaga

Pekerja 1.650 Oh x Rp. 75,000 = Rp. 123,750.00Tukang batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Kepala tukang 0.028 Oh x Rp. 110,000 = Rp. 3,080.00

Mandor 0.083 Oh x Rp. 100,000 = Rp. 8,300.00Jumlah (2) = Rp. 162,630.00

A. Jumlah (1) + (2) = Rp 740,954.35B. Overhead dan Profit 15% x A = Rp 111,143.15

Harga Satuan Pekerjaan (A+B) = Rp 852,097.50

PB 6.3 1 M³ Membuat beton mutu f'c = 12.2 Mpa (K 150), slump (12 ± 2) cm, w/c = 0.72 (1PC : 2,5PB : 3,5KR)6.3.1 Bahan

Semen portland 299.000 Kg x Rp. 1,362 = Rp. 407,238.00Pasir beton 799.000 Kg x Rp. 72.14 = Rp. 57,639.86Kerikil beton 1017.000 Kg x Rp. 140.74 = Rp. 143,132.58Air 215.000 Ltr x Rp. 1.17 = Rp. 251.55

Jumlah (1) = Rp. 608,261.996.3.2 Tenaga

Pekerja 1.650 Oh x Rp. 75,000 = Rp. 123,750.00Tukang batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Kepala tukang 0.028 Oh x Rp. 110,000 = Rp. 3,080.00

Mandor 0.083 Oh x Rp. 100,000 = Rp. 8,300.00Jumlah (2) = Rp. 162,630.00

A. Jumlah (1) + (2) = Rp 770,891.99B. Overhead dan Profit 15% x A = Rp 115,633.80

Harga Satuan Pekerjaan (A+B) = Rp 886,525.79

PB 6.4 1 M³ Membuat lantai kerja beton mutu f'c = 7.4 Mpa (K 100), slump (3 - 6) cm, w/c = 0.87 (1PC : 3PB : 5KR)6.4.1 Bahan

Semen portland 230.000 Kg x Rp. 1,362 = Rp. 313,260.00Pasir beton 893.000 Kg x Rp. 72.14 = Rp. 64,421.02Kerikil beton 1027.000 Kg x Rp. 140.74 = Rp. 144,539.98Air 200.000 Ltr x Rp. 1.17 = Rp. 234.00

Jumlah (1) = Rp. 522,455.006.4.2 Tenaga

Pekerja 1.200 Oh x Rp. 75,000 = Rp. 90,000.00Tukang batu 0.200 Oh x Rp. 100,000 = Rp. 20,000.00Kepala tukang 0.020 Oh x Rp. 110,000 = Rp. 2,200.00

Mandor 0.060 Oh x Rp. 100,000 = Rp. 6,000.00Jumlah (2) = Rp. 118,200.00

A. Jumlah (1) + (2) = Rp 640,655.00B. Overhead dan Profit 15% x A = Rp 96,098.25

Harga Satuan Pekerjaan (A+B) = Rp 736,753.25

Page 66: Daftar Analisa Pu 2013

Pekerjaan Beton 66

PEKERJAAN BETON

PB 6.5 1 M³ Membuat beton mutu f'c = 14.5 Mpa (K 175), slump (12 ± 2) cm, w/c = 0.66 (1PC : 2,5PB : 3KR)6.5.1 Bahan

Semen portland 326.000 Kg x Rp. 1,362 = Rp. 444,012.00Pasir beton 760.000 Kg x Rp. 72.14 = Rp. 54,826.40Kerikil beton 1029.000 Kg x Rp. 140.74 = Rp. 144,821.46Air 215.000 Ltr x Rp. 1.17 = Rp. 251.55

Jumlah (1) = Rp. 643,911.416.5.2 Tenaga

Pekerja 1.650 Oh x Rp. 75,000 = Rp. 123,750.00Tukang batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Kepala tukang 0.028 Oh x Rp. 110,000 = Rp. 3,080.00

Mandor 0.083 Oh x Rp. 100,000 = Rp. 8,300.00Jumlah (2) = Rp. 162,630.00

A. Jumlah (1) + (2) = Rp 806,541.41B. Overhead dan Profit 15% x A = Rp 120,981.21

Harga Satuan Pekerjaan (A+B) = Rp 927,522.62

PB 6.6 1 M³ Membuat beton mutu f'c = 16.9 Mpa (K 200), slump (12 ± 2) cm, w/c = 0.61 (1PC : 1PB : 3KR)6.6.1 Bahan

Semen portland 352.000 Kg x Rp. 1,362 = Rp. 479,424.00Pasir beton 731.000 Kg x Rp. 72.14 = Rp. 52,734.34Kerikil beton 1031.000 Kg x Rp. 140.74 = Rp. 145,102.94Air 215.000 Ltr x Rp. 1.17 = Rp. 251.55

Jumlah (1) = Rp. 677,512.836.6.2 Tenaga

Pekerja 1.650 Oh x Rp. 75,000 = Rp. 123,750.00Tukang batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Kepala tukang 0.028 Oh x Rp. 110,000 = Rp. 3,080.00Mandor 0.083 Oh x Rp. 100,000 = Rp. 8,300.00

Jumlah (2) = Rp. 162,630.00A. Jumlah (1) + (2) = Rp 840,142.83B. Overhead dan Profit 15% x A = Rp 126,021.42

Harga Satuan Pekerjaan (A+B) = Rp 966,164.25

PB 6.7 1 M³ Membuat beton mutu f'c = 19.3 Mpa (K 225), slump (12 ± 2) cm, w/c = 0.58 (1PC : 2PB : 3KR)6.7.1 Bahan

Semen portland 371.000 Kg x Rp. 1,362 = Rp. 505,302.00Pasir beton 698.000 Kg x Rp. 72.14 = Rp. 50,353.72Kerikil beton 1047.000 Kg x Rp. 140.74 = Rp. 147,354.78Air 215.000 Ltr x Rp. 1.17 = Rp. 251.55

Jumlah (1) = Rp. 703,262.056.7.2 Tenaga

Pekerja 1.650 Oh x Rp. 75,000 = Rp. 123,750.00Tukang batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Kepala tukang 0.028 Oh x Rp. 110,000 = Rp. 3,080.00Mandor 0.083 Oh x Rp. 100,000 = Rp. 8,300.00

Jumlah (2) = Rp. 162,630.00A. Jumlah (1) + (2) = Rp 865,892.05B. Overhead dan Profit 15% x A = Rp 129,883.81

Harga Satuan Pekerjaan (A+B) = Rp 995,775.86

PB 6.8 1 M³ Membuat beton mutu f'c = 21.7 Mpa (K 250), slump (12 ± 2) cm, w/c = 0.56 (1PC : 2PB : 2,7KR)6.8.1 Bahan

Semen portland 384.000 Kg x Rp. 1,362 = Rp. 523,008.00Pasir beton 692.000 Kg x Rp. 72.14 = Rp. 49,920.88Kerikil beton 1039.000 Kg x Rp. 140.74 = Rp. 146,228.86Air 215.000 Ltr x Rp. 1.17 = Rp. 251.55

Jumlah (1) = Rp. 719,409.296.8.2 Tenaga

Pekerja 1.650 Oh x Rp. 75,000 = Rp. 123,750.00Tukang batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Kepala tukang 0.028 Oh x Rp. 110,000 = Rp. 3,080.00Mandor 0.083 Oh x Rp. 100,000 = Rp. 8,300.00

Jumlah (2) = Rp. 162,630.00A. Jumlah (1) + (2) = Rp 882,039.29B. Overhead dan Profit 15% x A = Rp 132,305.89

Harga Satuan Pekerjaan (A+B) = Rp 1,014,345.18

Page 67: Daftar Analisa Pu 2013

Pekerjaan Beton 67

PEKERJAAN BETON

PB 6.9 1 M³ Membuat beton mutu f'c = 24.0 Mpa (K 275), slump (12 ± 2) cm, w/c = 0.53 (1PC : 1,5PB : 2,5KR)6.9.1 Bahan

Semen portland 406.000 Kg x Rp. 1,362 = Rp. 552,972.00Pasir beton 684.000 Kg x Rp. 72.14 = Rp. 49,343.76Kerikil beton 1026.000 Kg x Rp. 140.74 = Rp. 144,399.24Air 215.000 Ltr x Rp. 1.17 = Rp. 251.55

Jumlah (1) = Rp. 746,966.556.9.2 Tenaga

Pekerja 1.650 Oh x Rp. 75,000 = Rp. 123,750.00Tukang batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Kepala tukang 0.028 Oh x Rp. 110,000 = Rp. 3,080.00Mandor 0.083 Oh x Rp. 100,000 = Rp. 8,300.00

Jumlah (2) = Rp. 162,630.00A. Jumlah (1) + (2) = Rp 909,596.55B. Overhead dan Profit 15% x A = Rp 136,439.48

Harga Satuan Pekerjaan (A+B) = Rp 1,046,036.03

PB 6.10 1 M³ Membuat beton mutu f'c = 26.4 Mpa (K 300), slump (12 ± 2) cm, w/c = 0.52 (1PC : 1,5PB : 2,5KR)6.10.1 Bahan

Semen portland 413.000 Kg x Rp. 1,362 = Rp. 562,506.00Pasir beton 681.000 Kg x Rp. 72.14 = Rp. 49,127.34Kerikil beton 1021.000 Kg x Rp. 140.74 = Rp. 143,695.54Air 215.000 Ltr x Rp. 1.17 = Rp. 251.55

Jumlah (1) = Rp. 755,580.436.10.2 Tenaga

Pekerja 1.650 Oh x Rp. 75,000 = Rp. 123,750.00Tukang batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Kepala tukang 0.028 Oh x Rp. 110,000 = Rp. 3,080.00Mandor 0.083 Oh x Rp. 100,000 = Rp. 8,300.00

Jumlah (2) = Rp. 162,630.00A. Jumlah (1) + (2) = Rp 918,210.43B. Overhead dan Profit 15% x A = Rp 137,731.56

Harga Satuan Pekerjaan (A+B) = Rp 1,055,941.99

PB 6.11 1 M³ Membuat beton mutu f'c = 28.8 Mpa (K 325), slump (12 ± 2) cm, w/c = 0.49 (1PC : 1,5PB : 2KR)6.11.1 Bahan

Semen portland 439.000 Kg x Rp. 1,362 = Rp. 597,918.00Pasir beton 670.000 Kg x Rp. 72.14 = Rp. 48,333.80Kerikil beton 1006.000 Kg x Rp. 140.74 = Rp. 141,584.44Air 215.000 Ltr x Rp. 1.17 = Rp. 251.55

Jumlah (1) = Rp. 788,087.796.11.2 Tenaga

Pekerja 2.100 Oh x Rp. 75,000 = Rp. 157,500.00Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00Mandor 0.105 Oh x Rp. 100,000 = Rp. 10,500.00

Jumlah (2) = Rp. 206,850.00A. Jumlah (1) + (2) = Rp 994,937.79B. Overhead dan Profit 15% x A = Rp 149,240.67

Harga Satuan Pekerjaan (A+B) = Rp 1,144,178.46

PB 6.12 1 M³ Membuat beton mutu f'c = 31.2 Mpa (K 350), slump (12 ± 2) cm, w/c = 0.48 (1PC : 1,5PB : 2KR)6.12.1 Bahan

Semen portland 448.000 Kg x Rp. 1,362 = Rp. 610,176.00Pasir beton 667.000 Kg x Rp. 72.14 = Rp. 48,117.38Kerikil beton 1000.000 Kg x Rp. 140.74 = Rp. 140,740.00Air 215.000 Ltr x Rp. 1.17 = Rp. 251.55

Jumlah (1) = Rp. 799,284.936.12.2 Tenaga

Pekerja 2.100 Oh x Rp. 75,000 = Rp. 157,500.00Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00Kepala tukang 0.035 Oh x Rp. 110,000 = Rp. 3,850.00Mandor 0.105 Oh x Rp. 100,000 = Rp. 10,500.00

Jumlah (2) = Rp. 206,850.00A. Jumlah (1) + (2) = Rp 1,006,134.93B. Overhead dan Profit 15% x A = Rp 150,920.24

Harga Satuan Pekerjaan (A+B) = Rp 1,157,055.17

Page 68: Daftar Analisa Pu 2013

Pekerjaan Beton 68

PEKERJAAN BETON

PB 6.17 Pembesian 10 kg besi polos / besi ulir6.17.1 Bahan

Besi beton (polos/ulir) 10.500 Kg x Rp. 15,300 = Rp. 160,650.00Kawat beton 0.150 Kg x Rp. 23,100 = Rp. 3,465.00

Jumlah (1) = Rp. 164,115.006.17.2 Tenaga

Pekerja 0.070 Oh x Rp. 75,000 = Rp. 5,250.00Tukang besi 0.070 Oh x Rp. 100,000 = Rp. 7,000.00Kepala tukang 0.007 Oh x Rp. 110,000 = Rp. 770.00Mandor 0.004 Oh x Rp. 100,000 = Rp. 400.00

Jumlah (2) = Rp. 13,420.00A. Jumlah (1) + (2) = Rp 177,535.00B. Overhead dan Profit 15% x A = Rp 26,630.25

Harga Satuan Pekerjaan (A+B) = Rp 204,165.25

PB 6.18 Pasang 10 kg kabel preetressed polos/strands6.18.1 Bahan

Besi beton (polos/ulir) 10.500 Kg x Rp. 15,300 = Rp. 160,650.00Kawat beton 0.100 Kg x Rp. 23,100 = Rp. 2,310.00

Jumlah (1) = Rp. 164,115.006.18.2 Tenaga

Pekerja 0.050 Oh x Rp. 75,000 = Rp. 3,750.00Tukang besi 0.050 Oh x Rp. 100,000 = Rp. 5,000.00Kepala tukang 0.005 Oh x Rp. 110,000 = Rp. 550.00Mandor 0.003 Oh x Rp. 100,000 = Rp. 300.00

Jumlah (2) = Rp. 9,600.00A. Jumlah (1) + (2) = Rp 173,715.00B. Overhead dan Profit 15% x A = Rp 26,057.25

Harga Satuan Pekerjaan (A+B) = Rp 199,772.25

PB 6.206.20.1 Bahan

Kayu kelas III 0.040 M³ x Rp. 3,633,730 = Rp. 145,349.20Paku biasa 0.300 Kg x Rp. 18,900 = Rp. 5,670.00Minyak bekisting 0.100 Kg x Rp. 26,250 = Rp. 2,625.00

Jumlah (1) = Rp. 153,644.206.20.2 Tenaga

Pekerja 0.520 Oh x Rp. 75,000 = Rp. 39,000.00Tukang kayu 0.260 Oh x Rp. 100,000 = Rp. 26,000.00Kepala tukang 0.026 Oh x Rp. 110,000 = Rp. 2,860.00Mandor 0.026 Oh x Rp. 100,000 = Rp. 2,600.00

Jumlah (2) = Rp. 70,460.00A. Jumlah (1) + (2) = Rp 224,104.20B. Overhead dan Profit 15% x A = Rp 33,615.63

Harga Satuan Pekerjaan (A+B) = Rp 257,719.83

PB 6.216.21.1 Bahan

Kayu kelas III 0.045 M³ x Rp. 3,633,730 = Rp. 163,517.85Paku biasa 0.300 Kg x Rp. 18,900 = Rp. 5,670.00Minyak bekisting 0.100 Kg x Rp. 26,250 = Rp. 2,625.00

Jumlah (1) = Rp. 163,517.856.21.2 Tenaga

Pekerja 0.520 Oh x Rp. 75,000 = Rp. 39,000.00Tukang kayu 0.260 Oh x Rp. 100,000 = Rp. 26,000.00Kepala tukang 0.026 Oh x Rp. 110,000 = Rp. 2,860.00Mandor 0.026 Oh x Rp. 100,000 = Rp. 2,600.00

Jumlah (2) = Rp. 70,460.00A. Jumlah (1) + (2) = Rp 233,977.85B. Overhead dan Profit 15% x A = Rp 35,096.68

Harga Satuan Pekerjaan (A+B) = Rp 269,074.53

PB 6.226.22.1 Bahan

Kayu kelas III 0.040 M³ x Rp. 3,633,730 = Rp. 145,349.20Paku biasa 0.400 Kg x Rp. 18,900 = Rp. 7,560.00Minyak bekisting 0.200 Kg x Rp. 26,250 = Rp. 5,250.00Balok (kayu kelas II) 0.015 M³ x Rp. 6,818,590 = Rp. 102,278.85Tripleks tebal 9 mm 0.350 Lbr x Rp. 129,150 = Rp. 45,202.50Kayu dolken/bulat Ø 3" - 4" 2.000 Btg x Rp. 20,000 = Rp. 40,000.00

Jumlah (1) = Rp. 345,640.55

Pasang 1 M² bekisting untuk pondasi

Pasang 1 M² bekisting untuk sloof

Pasang 1 M² bekisting untuk kolom

Page 69: Daftar Analisa Pu 2013

Pekerjaan Beton 69

PEKERJAAN BETON

6.22.2 TenagaPekerja 0.660 Oh x Rp. 75,000 = Rp. 49,500.00Tukang kayu 0.330 Oh x Rp. 100,000 = Rp. 33,000.00Kepala tukang 0.033 Oh x Rp. 110,000 = Rp. 3,630.00Mandor 0.033 Oh x Rp. 100,000 = Rp. 3,300.00

Jumlah (2) = Rp. 89,430.00A. Jumlah (1) + (2) = Rp 435,070.55B. Overhead dan Profit 15% x A = Rp 65,260.58

Harga Satuan Pekerjaan (A+B) = Rp 500,331.13

PB 6.236.23.1 Bahan

Kayu kelas III 0.040 M³ x Rp. 3,633,730 = Rp. 145,349.20Paku biasa 0.400 Kg x Rp. 18,900 = Rp. 7,560.00Minyak bekisting 0.200 Kg x Rp. 26,250 = Rp. 5,250.00Balok (kayu kelas II) 0.018 M³ x Rp. 6,818,590 = Rp. 122,734.62Tripleks tebal 9 mm 0.350 Lbr x Rp. 129,150 = Rp. 45,202.50Kayu dolken/bulat Ø 3" - 4" 2.000 Btg x Rp. 20,000 = Rp. 40,000.00

Jumlah (1) = Rp. 366,096.326.23.2 Tenaga

Pekerja 0.660 Oh x Rp. 75,000 = Rp. 49,500.00Tukang kayu 0.330 Oh x Rp. 100,000 = Rp. 33,000.00Kepala tukang 0.033 Oh x Rp. 110,000 = Rp. 3,630.00Mandor 0.033 Oh x Rp. 100,000 = Rp. 3,300.00

Jumlah (2) = Rp. 89,430.00A. Jumlah (1) + (2) = Rp 455,526.32B. Overhead dan Profit 15% x A = Rp 68,328.95

Harga Satuan Pekerjaan (A+B) = Rp 523,855.27

PB 6.246.24.1 Bahan

Kayu kelas III 0.040 M³ x Rp. 3,633,730 = Rp. 145,349.20Paku biasa 0.400 Kg x Rp. 18,900 = Rp. 7,560.00Minyak bekisting 0.200 Kg x Rp. 26,250 = Rp. 5,250.00Balok (kayu kelas II) 0.015 M³ x Rp. 6,818,590 = Rp. 102,278.85Tripleks tebal 9 mm 0.350 Lbr x Rp. 129,150 = Rp. 45,202.50Kayu dolken/bulat Ø 3" - 4" 6.000 Btg x Rp. 20,000 = Rp. 120,000.00

Jumlah (1) = Rp. 425,640.556.24.2 Tenaga

Pekerja 0.660 Oh x Rp. 75,000 = Rp. 49,500.00Tukang kayu 0.330 Oh x Rp. 100,000 = Rp. 33,000.00Kepala tukang 0.033 Oh x Rp. 110,000 = Rp. 3,630.00Mandor 0.033 Oh x Rp. 100,000 = Rp. 3,300.00

Jumlah (2) = Rp. 89,430.00A. Jumlah (1) + (2) = Rp 515,070.55B. Overhead dan Profit 15% x A = Rp 77,260.58

Harga Satuan Pekerjaan (A+B) = Rp 592,331.13

PB 6.256.25.1 Bahan

Kayu kelas III 0.030 M³ x Rp. 3,633,730 = Rp. 109,011.90Paku biasa 0.400 Kg x Rp. 18,900 = Rp. 7,560.00Minyak bekisting 0.200 Kg x Rp. 26,250 = Rp. 5,250.00Balok (kayu kelas II) 0.020 M³ x Rp. 6,818,590 = Rp. 136,371.80Tripleks tebal 9 mm 0.350 Lbr x Rp. 129,150 = Rp. 45,202.50Kayu dolken/bulat Ø 3" - 4" 3.000 Btg x Rp. 20,000 = Rp. 60,000.00

Jumlah (1) = Rp. 363,396.206.25.2 Tenaga

Pekerja 0.660 Oh x Rp. 75,000 = Rp. 49,500.00Tukang kayu 0.330 Oh x Rp. 100,000 = Rp. 33,000.00Kepala tukang 0.033 Oh x Rp. 110,000 = Rp. 3,630.00Mandor 0.033 Oh x Rp. 100,000 = Rp. 3,300.00

Jumlah (2) = Rp. 89,430.00A. Jumlah (1) + (2) = Rp 452,826.20B. Overhead dan Profit 15% x A = Rp 67,923.93

Harga Satuan Pekerjaan (A+B) = Rp 520,750.13

Pasang 1 M² bekisting untuk balok

Pasang 1 M² bekisting untuk plat lantai

Pasang 1 M² bekisting untuk dinding

Page 70: Daftar Analisa Pu 2013

Pekerjaan Beton 70

PEKERJAAN BETON

PB 6.266.26.1 Bahan

. Kayu kelas III 0.030 M³ x Rp. 3,633,730 = Rp. 109,011.90Paku biasa 0.400 Kg x Rp. 18,900 = Rp. 7,560.00Minyak bekisting 0.150 Kg x Rp. 26,250 = Rp. 3,937.50Balok (kayu kelas II) 0.015 M³ x Rp. 6,818,590 = Rp. 102,278.85Tripleks tebal 9 mm 0.350 Lbr x Rp. 129,150 = Rp. 45,202.50Kayu dolken/bulat Ø 3" - 4" 2.000 Btg x Rp. 20,000 = Rp. 40,000.00

Jumlah (1) = Rp. 307,990.756.26.2 Tenaga

Pekerja 0.660 Oh x Rp. 75,000 = Rp. 49,500.00Tukang kayu 0.330 Oh x Rp. 100,000 = Rp. 33,000.00Kepala tukang 0.033 Oh x Rp. 110,000 = Rp. 3,630.00Mandor 0.033 Oh x Rp. 100,000 = Rp. 3,300.00

Jumlah (2) = Rp. 89,430.00A. Jumlah (1) + (2) = Rp 397,420.75B. Overhead dan Profit 15% x A = Rp 59,613.11

Harga Satuan Pekerjaan (A+B) = Rp 457,033.86

PB 6.276.27.1 Bahan

. Kayu kelas III (papan) 0.026 M³ x Rp. 3,633,730 = Rp. 95,930.47Paku biasa 0.600 Kg x Rp. 18,900 = Rp. 11,340.00Kayu dolken/bulat Ø 3" - 4" 0.500 Btg x Rp. 20,000 = Rp. 10,000.00

Jumlah (1) = Rp. 117,270.476.27.2 Tenaga

Pekerja 0.150 Oh x Rp. 75,000 = Rp. 11,250.00Tukang kayu 0.050 Oh x Rp. 100,000 = Rp. 5,000.00Kepala tukang 0.005 Oh x Rp. 110,000 = Rp. 550.00Mandor 0.008 Oh x Rp. 100,000 = Rp. 800.00

Jumlah (2) = Rp. 17,600.00A. Jumlah (1) + (2) = Rp 134,870.47B. Overhead dan Profit 15% x A = Rp 20,230.57

Harga Satuan Pekerjaan (A+B) = Rp 155,101.04

PB 6.286.28.1 Bahan

. Kayu kelas III 0.200 M³ x Rp. 3,633,730 = Rp. 726,746.00Paku biasa 1.500 Kg x Rp. 18,900 = Rp. 28,350.00Minyak bekisting 0.400 Kg x Rp. 26,250 = Rp. 10,500.00Besi beton polos 157.500 Kg x Rp. 15,300 = Rp. 2,409,750.00Kawat beton 2.250 Kg x Rp. 23,100 = Rp. 51,975.00Semen Portland 336.000 Kg x Rp. 1,362 = Rp. 457,632.00Pasir beton 0.540 M³ x Rp. 106,050 = Rp. 57,267.00Kerikil beton 2-3 cm 0.810 M³ x Rp. 210,900 = Rp. 170,829.00

Jumlah (1) = Rp. 3,913,049.006.28.2 Tenaga

Pekerja 5.300 Oh x Rp. 75,000 = Rp. 397,500.00Tukang Batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Tukang Kayu 1.300 Oh x Rp. 100,000 = Rp. 130,000.00Tukang besi 1.050 Oh x Rp. 100,000 = Rp. 105,000.00Kepala tukang 0.262 Oh x Rp. 110,000 = Rp. 28,820.00Mandor 0.265 Oh x Rp. 100,000 = Rp. 26,500.00

Jumlah (2) = Rp. 715,320.00A. Jumlah (1) + (2) = Rp 4,628,369.00B. Overhead dan Profit 15% x A = Rp 694,255.35

Harga Satuan Pekerjaan (A+B) = Rp 5,322,624.35

PB 6.29 Pasang 1 M³ sloof beton bertulang (200 kg besi + bekisting)6.29.1 Bahan

. Kayu kelas III 0.270 M³ x Rp. 3,633,730 = Rp. 981,107.10Paku biasa 2.000 Kg x Rp. 18,900 = Rp. 37,800.00Minyak bekisting 0.600 Kg x Rp. 26,250 = Rp. 15,750.00Besi beton polos 210.000 Kg x Rp. 15,300 = Rp. 3,213,000.00kawat beton 3.000 Kg x Rp. 23,100 = Rp. 69,300.00Semen Portland 336.000 Kg x Rp. 1,362 = Rp. 457,632.00Pasir beton 0.540 M³ x Rp. 106,050 = Rp. 57,267.00Kerikil beton 2-3 cm 0.810 M³ x Rp. 210,900 = Rp. 170,829.00

Jumlah (1) = Rp. 5,002,685.10

Pasang 1 M² bekisting untuk tangga

Pasang 1 M² jembatan untuk pengecoran beton

Pasang 1 M³ pondasi beton bertulang (150kg besi + bekisting)

Page 71: Daftar Analisa Pu 2013

Pekerjaan Beton 71

PEKERJAAN BETON

6.29.2 TenagaPekerja 5.650 Oh x Rp. 75,000 = Rp. 423,750.00Tukang Batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Tukang Kayu 1.560 Oh x Rp. 100,000 = Rp. 156,000.00Tukang besi 1.400 Oh x Rp. 100,000 = Rp. 140,000.00Kepala tukang 0.323 Oh x Rp. 110,000 = Rp. 35,530.00Mandor 0.283 Oh x Rp. 100,000 = Rp. 28,300.00

Jumlah (2) = Rp. 811,080.00A. Jumlah (1) + (2) = Rp 5,813,765.10B. Overhead dan Profit 15% x A = Rp 872,064.77

Harga Satuan Pekerjaan (A+B) = Rp 6,685,829.87

PB 6.30 Membuat 1 M³ kolom beton bertulang (300 kg besi + bekisting)6.30.1 Bahan

. Kayu kelas III 0.400 M³ x Rp. 3,633,730 = Rp. 1,453,492.00Paku biasa 4.000 Kg x Rp. 18,900 = Rp. 75,600.00Minyak bekisting 2.000 Kg x Rp. 26,250 = Rp. 52,500.00Besi beton polos 315.000 Kg x Rp. 15,300 = Rp. 4,819,500.00kawat beton 4.500 Kg x Rp. 23,100 = Rp. 103,950.00Semen Portland 336.000 Kg x Rp. 1,362 = Rp. 457,632.00Pasir beton 0.540 M³ x Rp. 106,050 = Rp. 57,267.00Kerikil beton 2-3 cm 0.810 M³ x Rp. 210,900 = Rp. 170,829.00Kayu kelas II (balok) 0.150 M³ x Rp. 6,818,590 = Rp. 1,022,788.50Tripleks 9 mm 3.500 Lbr x Rp. 129,150 = Rp. 452,025.00Kayu dolken/bulat Ø 3" - 4" 20.000 Btg x Rp. 20,000 = Rp. 400,000.00

Jumlah (1) = Rp. 9,065,583.506.30.2 Tenaga

Pekerja 7.050 Oh x Rp. 75,000 = Rp. 528,750.00Tukang Batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Tukang Kayu 1.650 Oh x Rp. 100,000 = Rp. 165,000.00Tukang besi 2.100 Oh x Rp. 100,000 = Rp. 210,000.00Kepala tukang 0.403 Oh x Rp. 110,000 = Rp. 44,330.00Mandor 0.353 Oh x Rp. 100,000 = Rp. 35,300.00

Jumlah (2) = Rp. 1,010,880.00A. Jumlah (1) + (2) = Rp 10,076,463.50B. Overhead dan Profit 15% x A = Rp 1,511,469.53

Harga Satuan Pekerjaan (A+B) = Rp 11,587,933.03

PB 6.31 Membuat 1 M³ balok beton bertulang (200 kg besi + bekisting)6.31.1 Bahan

. Kayu kelas III 0.320 M³ x Rp. 3,633,730 = Rp. 1,162,793.60Paku biasa 3.200 Kg x Rp. 18,900 = Rp. 60,480.00Minyak bekisting 1.600 Kg x Rp. 26,250 = Rp. 42,000.00Besi beton polos 210.000 Kg x Rp. 15,300 = Rp. 3,213,000.00kawat beton 3.000 Kg x Rp. 23,100 = Rp. 69,300.00Semen Portland 336.000 Kg x Rp. 1,362 = Rp. 457,632.00Pasir beton 0.540 M³ x Rp. 106,050 = Rp. 57,267.00Kerikil beton 2-3 cm 0.810 M³ x Rp. 210,900 = Rp. 170,829.00Kayu kelas II (balok) 0.140 M³ x Rp. 6,818,590 = Rp. 954,602.60Tripleks 9 mm 2.800 Lbr x Rp. 129,150 = Rp. 361,620.00Kayu dolken/bulat Ø 3" - 4" 16.000 Btg x Rp. 20,000 = Rp. 320,000.00

Jumlah (1) = Rp. 6,869,524.206.31.2 Tenaga

Pekerja 6.350 Oh x Rp. 75,000 = Rp. 476,250.00Tukang Batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Tukang Kayu 1.650 Oh x Rp. 100,000 = Rp. 165,000.00Tukang besi 1.400 Oh x Rp. 100,000 = Rp. 140,000.00Kepala tukang 0.333 Oh x Rp. 110,000 = Rp. 36,630.00Mandor 0.318 Oh x Rp. 100,000 = Rp. 31,800.00

Jumlah (2) = Rp. 877,180.00A. Jumlah (1) + (2) = Rp 7,746,704.20B. Overhead dan Profit 15% x A = Rp 1,162,005.63

Harga Satuan Pekerjaan (A+B) = Rp 8,908,709.83

Page 72: Daftar Analisa Pu 2013

Pekerjaan Beton 72

PEKERJAAN BETON

PB 6.32 Membuat 1 M³ plat beton bertulang (150 kg besi + bekisting)6.32.1 Bahan

. Kayu kelas III 0.320 M³ x Rp. 3,633,730 = Rp. 1,162,793.60Paku biasa 3.200 Kg x Rp. 18,900 = Rp. 60,480.00Minyak bekisting 1.600 Kg x Rp. 26,250 = Rp. 42,000.00Besi beton polos 157.500 Kg x Rp. 15,300 = Rp. 2,409,750.00kawat beton 2.250 Kg x Rp. 23,100 = Rp. 51,975.00Semen Portland 336.000 Kg x Rp. 1,362 = Rp. 457,632.00Pasir beton 0.540 M³ x Rp. 106,050 = Rp. 57,267.00Kerikil beton 2-3 cm 0.810 M³ x Rp. 210,900 = Rp. 170,829.00Kayu kelas II (balok) 0.120 M³ x Rp. 6,818,590 = Rp. 818,230.80Tripleks 9 mm 2.800 Lbr x Rp. 129,150 = Rp. 361,620.00Kayu dolken/bulat Ø 3" - 4" 32.000 Btg x Rp. 20,000 = Rp. 640,000.00

Jumlah (1) = Rp. 6,232,577.406.32.2 Tenaga

Pekerja 5.300 Oh x Rp. 75,000 = Rp. 397,500.00Tukang Batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Tukang Kayu 1.300 Oh x Rp. 100,000 = Rp. 130,000.00Tukang besi 1.050 Oh x Rp. 100,000 = Rp. 105,000.00Kepala tukang 0.265 Oh x Rp. 110,000 = Rp. 29,150.00Mandor 0.265 Oh x Rp. 100,000 = Rp. 26,500.00

Jumlah (2) = Rp. 715,650.00A. Jumlah (1) + (2) = Rp 6,948,227.40B. Overhead dan Profit 15% x A = Rp 1,042,234.11

Harga Satuan Pekerjaan (A+B) = Rp 7,990,461.51

PB 6.33 Membuat 1 M³ dinding beton bertulang (150 kg besi + bekisting)6.33.1 Bahan

. Kayu kelas III 0.240 M³ x Rp. 3,633,730 = Rp. 872,095.20Paku biasa 3.200 Kg x Rp. 18,900 = Rp. 60,480.00Minyak bekisting 1.600 Kg x Rp. 26,250 = Rp. 42,000.00Besi beton polos 157.500 Kg x Rp. 15,300 = Rp. 2,409,750.00kawat beton 2.250 Kg x Rp. 23,100 = Rp. 51,975.00Semen Portland 336.000 Kg x Rp. 1,362 = Rp. 457,632.00Pasir beton 0.540 M³ x Rp. 106,050 = Rp. 57,267.00Kerikil beton 2-3 cm 0.810 M³ x Rp. 210,900 = Rp. 170,829.00Kayu kelas II (balok) 0.160 M³ x Rp. 6,818,590 = Rp. 1,090,974.40Tripleks 9 mm 2.800 Lbr x Rp. 129,150 = Rp. 361,620.00Kayu dolken/bulat Ø 3" - 4" 24.000 Btg x Rp. 20,000 = Rp. 480,000.00

Jumlah (1) = Rp. 6,054,622.606.33.2 Tenaga

Pekerja 5.300 Oh x Rp. 75,000 = Rp. 397,500.00Tukang Batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Tukang Kayu 1.300 Oh x Rp. 100,000 = Rp. 130,000.00Tukang besi 1.050 Oh x Rp. 100,000 = Rp. 105,000.00Kepala tukang 0.262 Oh x Rp. 110,000 = Rp. 28,820.00Mandor 0.265 Oh x Rp. 100,000 = Rp. 26,500.00

Jumlah (2) = Rp. 715,320.00A. Jumlah (1) + (2) = Rp 6,769,942.60B. Overhead dan Profit 15% x A = Rp 1,015,491.39

Harga Satuan Pekerjaan (A+B) = Rp 7,785,433.99

PB 6.34 Membuat 1 M³ dinding beton bertulang (200 kg besi + bekisting)6.34.1 Bahan

. Kayu kelas III 0.250 M³ x Rp. 3,633,730 = Rp. 908,432.50Paku biasa 3.000 Kg x Rp. 18,900 = Rp. 56,700.00Minyak bekisting 1.200 Kg x Rp. 26,250 = Rp. 31,500.00Besi beton polos 210.000 Kg x Rp. 15,300 = Rp. 3,213,000.00kawat beton 3.000 Kg x Rp. 23,100 = Rp. 69,300.00Semen Portland 336.000 Kg x Rp. 1,362 = Rp. 457,632.00Pasir beton 0.540 M³ x Rp. 106,050 = Rp. 57,267.00Kerikil beton 2-3 cm 0.810 M³ x Rp. 210,900 = Rp. 170,829.00Kayu kelas II (balok) 0.105 M³ x Rp. 6,818,590 = Rp. 715,951.95Tripleks 9 mm 2.500 Lbr x Rp. 129,150 = Rp. 322,875.00Kayu dolken/bulat Ø 3" - 4" 14.000 Btg x Rp. 20,000 = Rp. 280,000.00

Jumlah (1) = Rp. 6,283,487.45

Page 73: Daftar Analisa Pu 2013

Pekerjaan Beton 73

PEKERJAAN BETON

6.34.2 TenagaPekerja 5.650 Oh x Rp. 75,000 = Rp. 423,750.00Tukang Batu 0.275 Oh x Rp. 100,000 = Rp. 27,500.00Tukang Kayu 1.560 Oh x Rp. 100,000 = Rp. 156,000.00Tukang besi 1.400 Oh x Rp. 100,000 = Rp. 140,000.00Kepala tukang 0.323 Oh x Rp. 110,000 = Rp. 35,530.00Mandor 0.283 Oh x Rp. 100,000 = Rp. 28,300.00

Jumlah (2) = Rp. 811,080.00A. Jumlah (1) + (2) = Rp 7,094,567.45B. Overhead dan Profit 15% x A = Rp 1,064,185.12

Harga Satuan Pekerjaan (A+B) = Rp 8,158,752.57

PB 6.35 Membuat 1 m' kolom praktis beton bertulang (11 x 11) cm6.35.1 Bahan

. Kayu kelas III 0.002 M³ x Rp. 3,633,730 = Rp. 7,267.46Paku biasa 0.010 Kg x Rp. 18,900 = Rp. 189.00Besi beton polos 3.000 Kg x Rp. 15,300 = Rp. 45,900.00kawat beton 0.045 Kg x Rp. 23,100 = Rp. 1,039.50Semen Portland 4.000 Kg x Rp. 1,362 = Rp. 5,448.00Pasir beton 0.006 M³ x Rp. 106,050 = Rp. 636.30Kerikil beton 2-3 cm 0.009 M³ x Rp. 210,900 = Rp. 1,898.10

Jumlah (1) = Rp. 62,378.366.35.2 Tenaga

Pekerja 0.180 Oh x Rp. 75,000 = Rp. 13,500.00Tukang Batu 0.020 Oh x Rp. 100,000 = Rp. 2,000.00Tukang Kayu 0.020 Oh x Rp. 100,000 = Rp. 2,000.00Tukang besi 0.020 Oh x Rp. 100,000 = Rp. 2,000.00Kepala tukang 0.006 Oh x Rp. 110,000 = Rp. 660.00Mandor 0.009 Oh x Rp. 100,000 = Rp. 900.00

Jumlah (2) = Rp. 21,060.00A. Jumlah (1) + (2) = Rp 83,438.36B. Overhead dan Profit 15% x A = Rp 12,515.75

Harga Satuan Pekerjaan (A+B) = Rp 95,954.11

PB 6.36 Membuat 1 m' balok beton bertulang (10 x 15) cm6.36.1 Bahan

. Kayu kelas III 0.003 M³ x Rp. 3,633,730 = Rp. 10,901.19Paku biasa 0.020 Kg x Rp. 18,900 = Rp. 378.00Besi beton polos 3.600 Kg x Rp. 15,300 = Rp. 55,080.00kawat beton 0.050 Kg x Rp. 23,100 = Rp. 1,155.00Semen Portland 5.500 Kg x Rp. 1,362 = Rp. 7,491.00Pasir beton 0.009 M³ x Rp. 106,050 = Rp. 954.45Kerikil beton 2-3 cm 0.015 M³ x Rp. 210,900 = Rp. 3,163.50

Jumlah (1) = Rp. 79,123.146.36.2 Tenaga

Pekerja 0.297 Oh x Rp. 75,000 = Rp. 22,275.00Tukang Batu 0.033 Oh x Rp. 100,000 = Rp. 3,300.00Tukang Kayu 0.033 Oh x Rp. 100,000 = Rp. 3,300.00Tukang besi 0.033 Oh x Rp. 100,000 = Rp. 3,300.00Kepala tukang 0.010 Oh x Rp. 110,000 = Rp. 1,100.00Mandor 0.015 Oh x Rp. 100,000 = Rp. 1,500.00

Jumlah (2) = Rp. 34,775.00A. Jumlah (1) + (2) = Rp 113,898.14B. Overhead dan Profit 15% x A = Rp 17,084.72

Harga Satuan Pekerjaan (A+B) = Rp 130,982.86

*******LANJUT PEKERJAAN PENUTUP ATAP

Page 74: Daftar Analisa Pu 2013

Pekerjaan Kayu 74

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN KAYU

PK 6.1 1 M³ Pasang kusen pintu dan jendela kayu kelas I6.1.1 Bahan

Balok (kayu kelas I) 1.100 M³ x Rp. 9,236,430.00 = Rp. 10,160,073.00Paku biasa 1.250 Kg x Rp. 18,900.00 = Rp. 23,625.00

Lem kayu 1.000 Kg x Rp. 15,750.00 = Rp. 15,750.00Jumlah (1) = Rp. 10,199,448.00

6.1.2 TenagaPekerja 7.000 Oh x Rp. 75,000.00 = Rp. 525,000.00Tukang kayu 21.000 Oh x Rp. 100,000.00 = Rp. 2,100,000.00Kepala tukang 2.100 Oh x Rp. 110,000.00 = Rp. 231,000.00Mandor 0.350 Oh x Rp. 100,000.00 = Rp. 35,000.00

Jumlah (2) = Rp. 2,891,000.00A. Jumlah (1) + (2) = Rp 13,090,448.00B. Overhead dan Profit 15% x A = Rp 1,963,567.20

Harga Satuan Pekerjaan (A+B) = Rp 15,054,015.20

PK 6.2 1 M³ Pasang kusen pintu dan jendela kayu kelas II6.2.1 Bahan

Balok (kayu Kelas II) 1.200 M³ x Rp. 6,818,590.00 = Rp. 8,182,308.00Paku biasa 1.250 Kg x Rp. 18,900.00 = Rp. 23,625.00

Lem kayu 1.000 Kg x Rp. 15,750.00 = Rp. 15,750.00Jumlah (1) = Rp. 8,221,683.00

6.2.2 TenagaPekerja 6.000 Oh x Rp. 75,000.00 = Rp. 450,000.00Tukang kayu 18.000 Oh x Rp. 100,000.00 = Rp. 1,800,000.00Kepala tukang 1.800 Oh x Rp. 110,000.00 = Rp. 198,000.00Mandor 0.300 Oh x Rp. 100,000.00 = Rp. 30,000.00

Jumlah (2) = Rp. 2,478,000.00A. Jumlah (1) + (2) = Rp 10,699,683.00B. Overhead dan Profit 15% x A = Rp 1,604,952.45

Harga Satuan Pekerjaan (A+B) = Rp 12,304,635.45

PK 6.36.3.1 Bahan

Papan (kayu kelas II) 0.040 M³ x Rp. 6,818,590.00 = Rp. 272,743.60Paku biasa 0.050 Kg x Rp. 18,900.00 = Rp. 945.00

Jumlah (1) = Rp. 273,688.606.3.2 Tenaga

Pekerja 0.350 Oh x Rp. 75,000.00 = Rp. 26,250.00Tukang kayu 1.050 Oh x Rp. 100,000.00 = Rp. 105,000.00Kepala tukang 0.105 Oh x Rp. 110,000.00 = Rp. 11,550.00Mandor 0.018 Oh x Rp. 100,000.00 = Rp. 1,800.00

Jumlah (2) = Rp. 144,600.00A. Jumlah (1) + (2) = Rp 418,288.60B. Overhead dan Profit 15% x A = Rp 62,743.29

Harga Satuan Pekerjaan (A+B) = Rp 481,031.89

PK 6.46.4.1 Bahan

Papan (kayu kelas III) 0.040 M³ x Rp. 3,633,730.00 = Rp. 145,349.20Paku biasa 0.050 Kg x Rp. 18,900.00 = Rp. 945.00

Jumlah (1) = Rp. 146,294.206.4.2 Tenaga

Pekerja 0.350 Oh x Rp. 75,000.00 = Rp. 26,250.00Tukang kayu 1.050 Oh x Rp. 100,000.00 = Rp. 105,000.00Kepala tukang 0.105 Oh x Rp. 110,000.00 = Rp. 11,550.00Mandor 0.018 Oh x Rp. 100,000.00 = Rp. 1,800.00

Jumlah (2) = Rp. 144,600.00A. Jumlah (1) + (2) = Rp 290,894.20B. Overhead dan Profit 15% x A = Rp 43,634.13

Harga Satuan Pekerjaan (A+B) = Rp 334,528.33

PK 6.56.5.1 Bahan

Papan (kayu kelas I) 0.040 M³ x Rp. 9,236,430.00 = Rp. 369,457.20Lem kayu 0.500 Kg x Rp. 15,750.00 = Rp. 7,875.00

1 M² Pasang pintu klamp standar, kayu kelas II

1 M² Pasang pintu klamp sederhana, kayu kelas III untuk gudang sementara

1 M² Pasang daun pintu panel, kayu kelas I

Page 75: Daftar Analisa Pu 2013

Pekerjaan Kayu 75

PEKERJAAN KAYU

Jumlah (1) = Rp. 377,332.20

Page 76: Daftar Analisa Pu 2013

Pekerjaan Kayu 76

PEKERJAAN KAYU

6.5.2 TenagaPekerja 1.000 Oh x Rp. 75,000.00 = Rp. 75,000.00Tukang kayu 3.000 Oh x Rp. 100,000.00 = Rp. 300,000.00Kepala tukang 0.300 Oh x Rp. 110,000.00 = Rp. 33,000.00Mandor 0.050 Oh x Rp. 100,000.00 = Rp. 5,000.00

Jumlah (2) = Rp. 413,000.00A. Jumlah (1) + (2) = Rp 790,332.20B. Overhead dan Profit 15% x A = Rp 118,549.83

Harga Satuan Pekerjaan (A+B) = Rp 908,882.03

PK 6.5.A6.5.A.1 Bahan

Papan (kayu kelas II) 0.040 M³ x Rp. 6,818,590.00 = Rp. 272,743.60Lem kayu 0.500 Kg x Rp. 15,750.00 = Rp. 7,875.00

Jumlah (1) = Rp. 280,618.606.5.A.2 Tenaga

Pekerja 1.000 Oh x Rp. 75,000.00 = Rp. 75,000.00Tukang kayu 3.000 Oh x Rp. 100,000.00 = Rp. 300,000.00Kepala tukang 0.300 Oh x Rp. 110,000.00 = Rp. 33,000.00Mandor 0.050 Oh x Rp. 100,000.00 = Rp. 5,000.00

Jumlah (2) = Rp. 413,000.00A. Jumlah (1) + (2) = Rp 693,618.60B. Overhead dan Profit 15% x A = Rp 104,042.79

Harga Satuan Pekerjaan (A+B) = Rp 797,661.39

PK 6.66.6.1 Bahan

Papan (kayu kelas I) 0.024 M³ x Rp. 9,236,430.00 = Rp. 221,674.32Lem kayu 0.300 Kg x Rp. 15,750.00 = Rp. 4,725.00

Jumlah (1) = Rp. 226,399.326.6.2 Tenaga

Pekerja 0.800 Oh x Rp. 75,000.00 = Rp. 60,000.00Tukang kayu 2.400 Oh x Rp. 100,000.00 = Rp. 240,000.00Kepala tukang 0.240 Oh x Rp. 110,000.00 = Rp. 26,400.00Mandor 0.040 Oh x Rp. 100,000.00 = Rp. 4,000.00

Jumlah (2) = Rp. 330,400.00A. Jumlah (1) + (2) = Rp 556,799.32B. Overhead dan Profit 15% x A = Rp 83,519.90

Harga Satuan Pekerjaan (A+B) = Rp 640,319.22

PK 6.6.A6.6.A.1 Bahan

Papan (kayu kelas II) 0.024 M³ x Rp. 6,818,590.00 = Rp. 163,646.16Lem kayu 0.300 Kg x Rp. 15,750.00 = Rp. 4,725.00

Jumlah (1) = Rp. 168,371.166.6.A.2 Tenaga

Pekerja 0.800 Oh x Rp. 75,000.00 = Rp. 60,000.00Tukang kayu 2.400 Oh x Rp. 100,000.00 = Rp. 240,000.00Kepala tukang 0.240 Oh x Rp. 110,000.00 = Rp. 26,400.00Mandor 0.040 Oh x Rp. 100,000.00 = Rp. 4,000.00

Jumlah (2) = Rp. 330,400.00A. Jumlah (1) + (2) = Rp 498,771.16B. Overhead dan Profit 15% x A = Rp 74,815.67

Harga Satuan Pekerjaan (A+B) = Rp 573,586.83

PK 6.76.7.1 Bahan

Papan (kayu kelas I) 0.064 M³ x Rp. 9,236,430.00 = Rp. 591,131.52Lem kayu 0.500 Kg x Rp. 15,750.00 = Rp. 7,875.00

Jumlah (1) = Rp. 599,006.52

1 M² Pasang daun pintu panel, kayu kelas II

1 M² Pasang pintu dan jendela kaca, kayu kelas I

1 M² Pasang pintu dan jendela kaca, kayu kelas II

1 M² Pasang pintu dan jendela jalusi, kayu kelas I

Page 77: Daftar Analisa Pu 2013

Pekerjaan Kayu 77

PEKERJAAN KAYU

6.7.2 TenagaPekerja 1.000 Oh x Rp. 75,000.00 = Rp. 75,000.00Tukang kayu 3.000 Oh x Rp. 100,000.00 = Rp. 300,000.00Kepala tukang 0.300 Oh x Rp. 110,000.00 = Rp. 33,000.00Mandor 0.050 Oh x Rp. 100,000.00 = Rp. 5,000.00

Jumlah (2) = Rp. 413,000.00A. Jumlah (1) + (2) = Rp 1,012,006.52B. Overhead dan Profit 15% x A = Rp 151,800.98

Harga Satuan Pekerjaan (A+B) = Rp 1,163,807.50

PK 6.7.A6.7.A.1 Bahan

Papan (kayu kelas II) 0.064 M³ x Rp. 6,818,590.00 = Rp. 436,389.76Lem kayu 0.500 Kg x Rp. 15,750.00 = Rp. 7,875.00

Jumlah (1) = Rp. 444,264.766.7.A.2 Tenaga

Pekerja 1.000 Oh x Rp. 75,000.00 = Rp. 75,000.00Tukang kayu 3.000 Oh x Rp. 100,000.00 = Rp. 300,000.00Kepala tukang 0.300 Oh x Rp. 110,000.00 = Rp. 33,000.00Mandor 0.050 Oh x Rp. 100,000.00 = Rp. 5,000.00

Jumlah (2) = Rp. 413,000.00A. Jumlah (1) + (2) = Rp 857,264.76B. Overhead dan Profit 15% x A = Rp 128,589.71

Harga Satuan Pekerjaan (A+B) = Rp 985,854.47

PK 6.86.8.1 Bahan

Papan (kayu kelas II) 0.025 M³ x Rp. 6,818,590.00 = Rp. 170,464.75Paku biasa 0.030 Kg x Rp. 18,900.00 = Rp. 567.00Lem kayu 0.500 Kg x Rp. 15,750.00 = Rp. 7,875.00Tripleks tebal 4 mm 1.000 Lbr x Rp. 70,350.00 = Rp. 70,350.00

Jumlah (1) = Rp. 249,256.756.8.2 Tenaga

Pekerja 0.700 Oh x Rp. 75,000.00 = Rp. 52,500.00Tukang kayu 2.100 Oh x Rp. 100,000.00 = Rp. 210,000.00Kepala tukang 0.210 Oh x Rp. 110,000.00 = Rp. 23,100.00Mandor 0.035 Oh x Rp. 100,000.00 = Rp. 3,500.00

Jumlah (2) = Rp. 289,100.00A. Jumlah (1) + (2) = Rp 538,356.75B. Overhead dan Profit 15% x A = Rp 80,753.51

Harga Satuan Pekerjaan (A+B) = Rp 619,110.26

PK 6.96.9.1 Bahan

Papan (kayu kelas I) 0.026 M³ x Rp. 9,236,430.00 = Rp. 236,452.61Paku biasa 0.030 Kg x Rp. 18,900.00 = Rp. 567.00Lem kayu 0.500 Kg x Rp. 15,750.00 = Rp. 7,875.00Tripleks tebal 4 mm 1.000 Lbr x Rp. 70,350.00 = Rp. 70,350.00

Jumlah (1) = Rp. 315,244.616.9.2 Tenaga

Pekerja 0.800 Oh x Rp. 75,000.00 = Rp. 60,000.00Tukang kayu 2.400 Oh x Rp. 100,000.00 = Rp. 240,000.00Kepala tukang 0.240 Oh x Rp. 110,000.00 = Rp. 26,400.00Mandor 0.040 Oh x Rp. 100,000.00 = Rp. 4,000.00

Jumlah (2) = Rp. 330,400.00A. Jumlah (1) + (2) = Rp 645,644.61B. Overhead dan Profit 15% x A = Rp 96,846.69

Harga Satuan Pekerjaan (A+B) = Rp 742,491.30

PK 6.9.A6.9.A.1 Bahan

Papan (kayu kelas II) 0.026 M³ x Rp. 6,818,590.00 = Rp. 174,555.90Paku biasa 0.030 Kg x Rp. 18,900.00 = Rp. 567.00Lem kayu 0.500 Kg x Rp. 15,750.00 = Rp. 7,875.00Tripleks tebal 4 mm 1.000 Lbr x Rp. 70,350.00 = Rp. 70,350.00

Jumlah (1) = Rp. 253,347.90

1 M² Pasang pintu dan jendela jalusi, kayu kelas II

1 M² Buat daun pintu kayu lapis tripleks rangkap, rangka tertutup kayu kelas II

1 M² Buat pintu tripleks rangkap, rangka ekspose kayu kelas I

1 M² Buat pintu tripleks rangkap, rangka ekspose kayu kelas II

Page 78: Daftar Analisa Pu 2013

Pekerjaan Kayu 78

PEKERJAAN KAYU

6.9.A.2 TenagaPekerja 0.800 Oh x Rp. 75,000.00 = Rp. 60,000.00Tukang kayu 2.400 Oh x Rp. 100,000.00 = Rp. 240,000.00Kepala tukang 0.240 Oh x Rp. 110,000.00 = Rp. 26,400.00Mandor 0.040 Oh x Rp. 100,000.00 = Rp. 4,000.00

Jumlah (2) = Rp. 330,400.00A. Jumlah (1) + (2) = Rp 583,747.90B. Overhead dan Profit 15% x A = Rp 87,562.19

Harga Satuan Pekerjaan (A+B) = Rp 671,310.09

PK 6.106.10.1 Bahan

Papan (kayu kelas I) 0.060 M³ x Rp. 9,236,430.00 = Rp. 554,185.80Paku biasa 0.150 Kg x Rp. 18,900.00 = Rp. 2,835.00

Jumlah (1) = Rp. 557,020.806.10.2 Tenaga

Pekerja 0.670 Oh x Rp. 75,000.00 = Rp. 50,250.00Tukang kayu 2.000 Oh x Rp. 100,000.00 = Rp. 200,000.00Kepala tukang 0.200 Oh x Rp. 110,000.00 = Rp. 22,000.00Mandor 0.335 Oh x Rp. 100,000.00 = Rp. 33,500.00

Jumlah (2) = Rp. 305,750.00A. Jumlah (1) + (2) = Rp 862,770.80B. Overhead dan Profit 15% x A = Rp 129,415.62

Harga Satuan Pekerjaan (A+B) = Rp 992,186.42

PK 6.10.A6.10.A.1 Bahan

Papan (kayu kelas II) 0.060 M³ x Rp. 6,818,590.00 = Rp. 409,115.40Paku biasa 0.150 Kg x Rp. 18,900.00 = Rp. 2,835.00

Jumlah (1) = Rp. 411,950.406.10.A.2 Tenaga

Pekerja 0.670 Oh x Rp. 75,000.00 = Rp. 50,250.00Tukang kayu 2.000 Oh x Rp. 100,000.00 = Rp. 200,000.00Kepala tukang 0.200 Oh x Rp. 110,000.00 = Rp. 22,000.00Mandor 0.335 Oh x Rp. 100,000.00 = Rp. 33,500.00

Jumlah (2) = Rp. 305,750.00A. Jumlah (1) + (2) = Rp 717,700.40B. Overhead dan Profit 15% x A = Rp 107,655.06

Harga Satuan Pekerjaan (A+B) = Rp 825,355.46

PK 6.13 1 M³ Pasang kontruksi kuda2 konvensional bentang 6 m' kayu kelas II6.13.1 Bahan

Balok (kayu kelas II) 1.100 M³ x Rp. 6,818,590.00 = Rp. 7,500,449.00Besi plat strip 15.000 Kg x Rp. 20,000.00 = Rp. 300,000.00Paku biasa 5.600 Kg x Rp. 18,900.00 = Rp. 105,840.00

Jumlah (1) = Rp. 7,906,289.006.13.2 Tenaga

Pekerja 4.000 Oh x Rp. 75,000.00 = Rp. 300,000.00Tukang kayu 12.000 Oh x Rp. 100,000.00 = Rp. 1,200,000.00Kepala tukang 1.200 Oh x Rp. 110,000.00 = Rp. 132,000.00Mandor 0.200 Oh x Rp. 100,000.00 = Rp. 20,000.00

Jumlah (2) = Rp. 1,652,000.00A. Jumlah (1) + (2) = Rp 9,558,289.00B. Overhead dan Profit 15% x A = Rp 1,433,743.35

Harga Satuan Pekerjaan (A+B) = Rp 10,992,032.35

1 M² Pasang jalusi kusen, kayu kelas I

1 M² Pasang jalusi kusen, kayu kelas II

Page 79: Daftar Analisa Pu 2013

Pekerjaan Kayu 79

PEKERJAAN KAYU

PK 6.14 1 M³ Pasang kontruksi kuda2 ekspose kayu kelas I6.14.1 Bahan

Balok (kayu kelas I) 1.200 M³ x Rp. 9,236,430.00 = Rp. 11,083,716.00Besi plat strip 15.000 Kg x Rp. 20,000.00 = Rp. 300,000.00Paku biasa 5.600 Kg x Rp. 18,900.00 = Rp. 105,840.00

Jumlah (1) = Rp. 11,489,556.006.14.2 Tenaga

Pekerja 6.700 Oh x Rp. 75,000.00 = Rp. 502,500.00Tukang kayu 20.100 Oh x Rp. 100,000.00 = Rp. 2,010,000.00Kepala tukang 2.010 Oh x Rp. 110,000.00 = Rp. 221,100.00Mandor 0.335 Oh x Rp. 100,000.00 = Rp. 33,500.00

Jumlah (2) = Rp. 2,767,100.00A. Jumlah (1) + (2) = Rp 14,256,656.00B. Overhead dan Profit 15% x A = Rp 2,138,498.40

Harga Satuan Pekerjaan (A+B) = Rp 16,395,154.40

PK 6.15 1 M³ Pasang kontruksi gordeng kayu kelas II6.15.1 Bahan

Balok (kayu kelas II) 1.100 M³ x Rp. 6,818,590.00 = Rp. 7,500,449.00Besi plat strip 15.000 Kg x Rp. 20,000.00 = Rp. 300,000.00Paku biasa 3.000 Kg x Rp. 18,900.00 = Rp. 56,700.00

Jumlah (1) = Rp. 7,857,149.006.15.2 Tenaga

Pekerja 2.400 Oh x Rp. 75,000.00 = Rp. 180,000.00Tukang kayu 7.200 Oh x Rp. 100,000.00 = Rp. 720,000.00Kepala tukang 0.720 Oh x Rp. 110,000.00 = Rp. 79,200.00Mandor 0.120 Oh x Rp. 100,000.00 = Rp. 12,000.00

Jumlah (2) = Rp. 991,200.00A. Jumlah (1) + (2) = Rp 8,848,349.00B. Overhead dan Profit 15% x A = Rp 1,327,252.35

Harga Satuan Pekerjaan (A+B) = Rp 10,175,601.35

PK 6.166.16.1 Bahan

Balok (kayu kelas II) 0.014 M³ x Rp. 6,818,590.00 = Rp. 95,460.26Reng 2 x 3 cm (kayu kelas I 0.004 M³ x Rp. 6,818,590.00 = Rp. 24,546.92Paku biasa 0.250 Kg x Rp. 18,900.00 = Rp. 4,725.00

Jumlah (1) = Rp. 124,732.186.16.2 Tenaga

Pekerja 0.100 Oh x Rp. 75,000.00 = Rp. 7,500.00Tukang kayu 0.100 Oh x Rp. 100,000.00 = Rp. 10,000.00Kepala tukang 0.010 Oh x Rp. 110,000.00 = Rp. 1,100.00Mandor 0.005 Oh x Rp. 100,000.00 = Rp. 500.00

Jumlah (2) = Rp. 19,100.00A. Jumlah (1) + (2) = Rp 143,832.18B. Overhead dan Profit 15% x A = Rp 21,574.83

Harga Satuan Pekerjaan (A+B) = Rp 165,407.01

PK 6.176.17.1 Bahan

Balok (kayu kelas II) 0.014 M³ x Rp. 6,818,590.00 = Rp. 95,460.26Reng 2 x 3 cm (kayu kelas I 0.007 M³ x Rp. 6,818,590.00 = Rp. 49,093.85Paku biasa 0.250 Kg x Rp. 18,900.00 = Rp. 4,725.00

Jumlah (1) = Rp. 149,279.116.17.2 Tenaga

Pekerja 0.100 Oh x Rp. 75,000.00 = Rp. 7,500.00Tukang kayu 0.100 Oh x Rp. 100,000.00 = Rp. 10,000.00Kepala tukang 0.010 Oh x Rp. 110,000.00 = Rp. 1,100.00Mandor 0.005 Oh x Rp. 100,000.00 = Rp. 500.00

Jumlah (2) = Rp. 19,100.00A. Jumlah (1) + (2) = Rp 168,379.11B. Overhead dan Profit 15% x A = Rp 25,256.87

Harga Satuan Pekerjaan (A+B) = Rp 193,635.97

1 M² Pasang rangka atap genteng keramik, kayu kelas II

1 M² Pasang atap genteng beton kayu kelas II

Page 80: Daftar Analisa Pu 2013

Pekerjaan Kayu 80

PEKERJAAN KAYU

PK 6.186.18.1 Bahan

Kayu kelas II 0.165 M³ x Rp. 6,818,590.00 = Rp. 1,125,067.35Paku biasa 0.200 Kg x Rp. 18,900.00 = Rp. 3,780.00

Jumlah (1) = Rp. 1,128,847.356.18.2 Tenaga

Pekerja 0.120 Oh x Rp. 75,000.00 = Rp. 9,000.00Tukang kayu 0.120 Oh x Rp. 100,000.00 = Rp. 12,000.00Kepala tukang 0.012 Oh x Rp. 110,000.00 = Rp. 1,320.00Mandor 0.006 Oh x Rp. 100,000.00 = Rp. 600.00

Jumlah (2) = Rp. 22,920.00A. Jumlah (1) + (2) = Rp 1,151,767.35B. Overhead dan Profit 15% x A = Rp 172,765.10

Harga Satuan Pekerjaan (A+B) = Rp 1,324,532.45

PK 6.196.19.1 Bahan

Kayu kelas II 0.015 M³ x Rp. 6,818,590.00 = Rp. 105,006.29Paku biasa 0.200 Kg x Rp. 18,900.00 = Rp. 3,780.00

Jumlah (1) = Rp. 108,786.296.19.2 Tenaga

Pekerja 0.150 Oh x Rp. 75,000.00 = Rp. 11,250.00Tukang kayu 0.300 Oh x Rp. 100,000.00 = Rp. 30,000.00Kepala tukang 0.030 Oh x Rp. 110,000.00 = Rp. 3,300.00Mandor 0.075 Oh x Rp. 100,000.00 = Rp. 7,500.00

Jumlah (2) = Rp. 52,050.00A. Jumlah (1) + (2) = Rp 160,836.29B. Overhead dan Profit 15% x A = Rp 24,125.44

Harga Satuan Pekerjaan (A+B) = Rp 184,961.73

PK 6.19.A6.19.A.1 Bahan

Kayu kelas III 0.015 M³ x Rp. 3,633,730.00 = Rp. 55,959.44Paku biasa 0.200 Kg x Rp. 18,900.00 = Rp. 3,780.00

Jumlah (1) = Rp. 59,739.446.19.A.2 Tenaga

Pekerja 0.150 Oh x Rp. 75,000.00 = Rp. 11,250.00Tukang kayu 0.300 Oh x Rp. 100,000.00 = Rp. 30,000.00Kepala tukang 0.030 Oh x Rp. 110,000.00 = Rp. 3,300.00Mandor 0.075 Oh x Rp. 100,000.00 = Rp. 7,500.00

Jumlah (2) = Rp. 52,050.00A. Jumlah (1) + (2) = Rp 111,789.44B. Overhead dan Profit 15% x A = Rp 16,768.42

Harga Satuan Pekerjaan (A+B) = Rp 128,557.86

PK 6.206.20.1 Bahan

Kayu kelas II 0.016 M³ x Rp. 6,818,590.00 = Rp. 111,143.02Paku biasa 0.250 Kg x Rp. 18,900.00 = Rp. 4,725.00

Jumlah (1) = Rp. 115,868.026.20.2 Tenaga

Pekerja 0.200 Oh x Rp. 75,000.00 = Rp. 15,000.00Tukang kayu 0.300 Oh x Rp. 100,000.00 = Rp. 30,000.00Kepala tukang 0.030 Oh x Rp. 110,000.00 = Rp. 3,300.00Mandor 0.010 Oh x Rp. 100,000.00 = Rp. 1,000.00

Jumlah (2) = Rp. 49,300.00A. Jumlah (1) + (2) = Rp 165,168.02B. Overhead dan Profit 15% x A = Rp 24,775.20

Harga Satuan Pekerjaan (A+B) = Rp 189,943.22

1 M² Pasang rangka atap sirap, kayu kelas II

1 M² Pasang rangka langit2 uk. 50 x 100 cm, kayu kelas II

1 M² Pasang rangka langit2 uk. 50 x 100 cm, kayu kelas III

1 M² Pasang rangka langit2 uk. 60 x 60 cm, kayu kelas II

Page 81: Daftar Analisa Pu 2013

Pekerjaan Kayu 81

PEKERJAAN KAYU

PK 6.20.A6.20.A.1 Bahan

Kayu kelas III 0.016 M³ x Rp. 3,633,730.00 = Rp. 59,229.80Paku biasa 0.250 Kg x Rp. 18,900.00 = Rp. 4,725.00

Jumlah (1) = Rp. 63,954.806.20.A.2 Tenaga

Pekerja 0.200 Oh x Rp. 75,000.00 = Rp. 15,000.00Tukang kayu 0.300 Oh x Rp. 100,000.00 = Rp. 30,000.00Kepala tukang 0.030 Oh x Rp. 110,000.00 = Rp. 3,300.00Mandor 0.010 Oh x Rp. 100,000.00 = Rp. 1,000.00

Jumlah (2) = Rp. 49,300.00A. Jumlah (1) + (2) = Rp 113,254.80B. Overhead dan Profit 15% x A = Rp 16,988.22

Harga Satuan Pekerjaan (A+B) = Rp 130,243.02

PK 6.21 1 M' Pasang lisplank uk. 3 x 20 cm, kayu kelas I6.21.1 Bahan

Papan (kayu kelas I) 0.011 M³ x Rp. 9,236,430.00 = Rp. 99,753.44Paku biasa 0.100 Kg x Rp. 18,900.00 = Rp. 1,890.00

Jumlah (1) = Rp. 101,643.446.21.2 Tenaga

Pekerja 0.100 Oh x Rp. 75,000.00 = Rp. 7,500.00Tukang kayu 0.200 Oh x Rp. 100,000.00 = Rp. 20,000.00Kepala tukang 0.020 Oh x Rp. 110,000.00 = Rp. 2,200.00Mandor 0.005 Oh x Rp. 100,000.00 = Rp. 500.00

Jumlah (2) = Rp. 30,200.00A. Jumlah (1) + (2) = Rp 131,843.44B. Overhead dan Profit 15% x A = Rp 19,776.52

Harga Satuan Pekerjaan (A+B) = Rp 151,619.96

PK 6.21.A 1 M' Pasang lisplank uk. 3 x 20 cm, kayu kelas II6.21.A.1 Bahan

Papan (kayu kelas II) 0.011 M³ x Rp. 6,818,590.00 = Rp. 73,640.77Paku biasa 0.100 Kg x Rp. 18,900.00 = Rp. 1,890.00

Jumlah (1) = Rp. 75,530.776.21.A.2 Tenaga

Pekerja 0.100 Oh x Rp. 75,000.00 = Rp. 7,500.00Tukang kayu 0.200 Oh x Rp. 100,000.00 = Rp. 20,000.00Kepala tukang 0.020 Oh x Rp. 110,000.00 = Rp. 2,200.00Mandor 0.005 Oh x Rp. 100,000.00 = Rp. 500.00

Jumlah (2) = Rp. 30,200.00A. Jumlah (1) + (2) = Rp 105,730.77B. Overhead dan Profit 15% x A = Rp 15,859.62

Harga Satuan Pekerjaan (A+B) = Rp 121,590.39

PK 6.22 1 M' Pasang lisplank uk. 3 x 30 cm, kayu kelas I6.22.1 Bahan

Papan (kayu kelas I) 0.011 M³ x Rp. 9,236,430.00 = Rp. 101,600.73Paku biasa 0.050 Kg x Rp. 18,900.00 = Rp. 945.00

Jumlah (1) = Rp. 102,545.736.22.2 Tenaga

Pekerja 0.100 Oh x Rp. 75,000.00 = Rp. 7,500.00Tukang kayu 0.200 Oh x Rp. 100,000.00 = Rp. 20,000.00Kepala tukang 0.020 Oh x Rp. 110,000.00 = Rp. 2,200.00Mandor 0.005 Oh x Rp. 100,000.00 = Rp. 500.00

Jumlah (2) = Rp. 30,200.00A. Jumlah (1) + (2) = Rp 132,745.73B. Overhead dan Profit 15% x A = Rp 19,911.86

Harga Satuan Pekerjaan (A+B) = Rp 152,657.59

1 M² Pasang rangka langit2 uk. 60 x 60 cm, kayu kelas III

Page 82: Daftar Analisa Pu 2013

Pekerjaan Kayu 82

PEKERJAAN KAYU

PK 6.22.A 1 M' Pasang lisplank uk. 3 x 30 cm, kayu kelas II6.22.A.1 Bahan

Papan (kayu kelas II) 0.011 M³ x Rp. 6,818,590.00 = Rp. 75,004.49Paku biasa 0.050 Kg x Rp. 18,900.00 = Rp. 945.00

Jumlah (1) = Rp. 75,949.496.22.A.2 Tenaga

Pekerja 0.100 Oh x Rp. 75,000.00 = Rp. 7,500.00Tukang kayu 0.200 Oh x Rp. 100,000.00 = Rp. 20,000.00Kepala tukang 0.020 Oh x Rp. 110,000.00 = Rp. 2,200.00Mandor 0.005 Oh x Rp. 100,000.00 = Rp. 500.00

Jumlah (2) = Rp. 30,200.00A. Jumlah (1) + (2) = Rp 106,149.49B. Overhead dan Profit 15% x A = Rp 15,922.42

Harga Satuan Pekerjaan (A+B) = Rp 122,071.91

PK 6.236.23.1 Bahan

Balok (kayu kelas II) 0.028 M³ x Rp. 6,818,590.00 = Rp. 190,920.52Paku biasa 0.150 Kg x Rp. 18,900.00 = Rp. 2,835.00

Jumlah (1) = Rp. 193,755.526.23.2 Tenaga

Pekerja 0.150 Oh x Rp. 75,000.00 = Rp. 11,250.00Tukang kayu 0.450 Oh x Rp. 100,000.00 = Rp. 45,000.00Kepala tukang 0.045 Oh x Rp. 110,000.00 = Rp. 4,950.00Mandor 0.008 Oh x Rp. 100,000.00 = Rp. 800.00

Jumlah (2) = Rp. 62,000.00A. Jumlah (1) + (2) = Rp 255,755.52B. Overhead dan Profit 15% x A = Rp 38,363.33

Harga Satuan Pekerjaan (A+B) = Rp 294,118.85

PK 6.23.A6.23.A.1 Bahan

Balok (kayu kelas III) 0.028 M³ x Rp. 3,633,730.00 = Rp. 101,744.44Paku biasa 0.150 Kg x Rp. 18,900.00 = Rp. 2,835.00

Jumlah (1) = Rp. 104,579.446.23.A.2 Tenaga

Pekerja 0.150 Oh x Rp. 75,000.00 = Rp. 11,250.00Tukang kayu 0.450 Oh x Rp. 100,000.00 = Rp. 45,000.00Kepala tukang 0.045 Oh x Rp. 110,000.00 = Rp. 4,950.00Mandor 0.008 Oh x Rp. 100,000.00 = Rp. 800.00

Jumlah (2) = Rp. 62,000.00A. Jumlah (1) + (2) = Rp 166,579.44B. Overhead dan Profit 15% x A = Rp 24,986.92

Harga Satuan Pekerjaan (A+B) = Rp 191,566.36

PK 6.246.24.1 Bahan

Balok (kayu kelas III) 0.028 M³ x Rp. 3,633,730.00 = Rp. 101,744.44Paku biasa 0.150 Kg x Rp. 18,900.00 = Rp. 2,835.00Tripleks tebal 4 mm 0.860 Lbr x Rp. 70,350.00 = Rp. 60,501.00Lem kayu 0.560 Kg x Rp. 15,750.00 = Rp. 8,820.00

Jumlah (1) = Rp. 173,900.446.24.2 Tenaga

Pekerja 0.150 Oh x Rp. 75,000.00 = Rp. 11,250.00Tukang kayu 0.450 Oh x Rp. 100,000.00 = Rp. 45,000.00Kepala tukang 0.045 Oh x Rp. 110,000.00 = Rp. 4,950.00Mandor 0.008 Oh x Rp. 100,000.00 = Rp. 800.00

Jumlah (2) = Rp. 62,000.00A. Jumlah (1) + (2) = Rp 235,900.44B. Overhead dan Profit 15% x A = Rp 35,385.07

Harga Satuan Pekerjaan (A+B) = Rp 271,285.51

1 M² Pasang rangka dinding pemisah 60 x 120 cm, kayu kelas II

1 M² Pasang rangka dinding pemisah 60 x 120 cm, kayu kelas III

1 M² Pasang dinding pemisah tripleks rangkap, rangka kayu kelas III

Page 83: Daftar Analisa Pu 2013

Pekerjaan Kayu 83

PEKERJAAN KAYU

PK 6.256.25.1 Bahan

Balok (kayu kelas II) 0.028 M³ x Rp. 6,818,590.00 = Rp. 190,920.52Paku biasa 0.150 Kg x Rp. 18,900.00 = Rp. 2,835.00Tripleks tebal 4 mm 0.860 Lbr x Rp. 70,350.00 = Rp. 60,501.00Lem kayu 0.560 Kg x Rp. 15,750.00 = Rp. 8,820.00

Jumlah (1) = Rp. 263,076.526.25.2 Tenaga

Pekerja 0.200 Oh x Rp. 75,000.00 = Rp. 15,000.00Tukang kayu 0.600 Oh x Rp. 100,000.00 = Rp. 60,000.00Kepala tukang 0.060 Oh x Rp. 110,000.00 = Rp. 6,600.00Mandor 0.010 Oh x Rp. 100,000.00 = Rp. 1,000.00

Jumlah (2) = Rp. 82,600.00A. Jumlah (1) + (2) = Rp 345,676.52B. Overhead dan Profit 15% x A = Rp 51,851.48

Harga Satuan Pekerjaan (A+B) = Rp 397,528.00

PK 6.266.26.1 Bahan

Papan (kayu kelas I) 0.007 M³ x Rp. 9,236,430.00 = Rp. 64,655.01Paku biasa 0.100 Kg x Rp. 18,900.00 = Rp. 1,890.00Paku skrup 10 cm 0.150 Kg x Rp. 26,250.00 = Rp. 3,937.50

Jumlah (1) = Rp. 70,482.516.26.2 Tenaga

Pekerja 0.600 Oh x Rp. 75,000.00 = Rp. 45,000.00Tukang kayu 1.800 Oh x Rp. 100,000.00 = Rp. 180,000.00Kepala tukang 0.180 Oh x Rp. 110,000.00 = Rp. 19,800.00Mandor 0.030 Oh x Rp. 100,000.00 = Rp. 3,000.00

Jumlah (2) = Rp. 247,800.00A. Jumlah (1) + (2) = Rp 318,282.51B. Overhead dan Profit 15% x A = Rp 47,742.38

Harga Satuan Pekerjaan (A+B) = Rp 366,024.89

PK 6.276.27.1 Bahan

Tripleks tbl 4 mm 0.400 Lbr x Rp. 70,350.00 = Rp. 28,140.00Paku biasa 0.050 Kg x Rp. 18,900.00 = Rp. 945.00

Jumlah (1) = Rp. 29,085.006.27.2 Tenaga

Pekerja 0.025 Oh x Rp. 75,000.00 = Rp. 1,875.00Tukang kayu 0.075 Oh x Rp. 100,000.00 = Rp. 7,500.00Kepala tukang 0.008 Oh x Rp. 110,000.00 = Rp. 880.00Mandor 0.001 Oh x Rp. 100,000.00 = Rp. 100.00

Jumlah (2) = Rp. 10,355.00A. Jumlah (1) + (2) = Rp 39,440.00B. Overhead dan Profit 15% x A = Rp 5,916.00

Harga Satuan Pekerjaan (A+B) = Rp 45,356.00

PK 6.286.28.1 Bahan

Tepas bambu 1.500 Lbr x Rp. 31,500.00 = Rp. 47,250.00Kayu kelas III 0.014 x Rp. 3,633,730.00 = Rp. 50,872.22Paku 0.012 Kg x Rp. 18,900.00 = Rp. 226.80List kayu 2/4 (kayu kelas III 0.003 M³ x Rp. 3,633,730.00 = Rp. 10,901.19

Jumlah (1) = Rp. 47,250.006.28.2 Tenaga

Pekerja 0.100 Oh x Rp. 75,000.00 = Rp. 7,500.00Tukang kayu 0.050 Oh x Rp. 100,000.00 = Rp. 5,000.00Kepala tukang 0.005 Oh x Rp. 110,000.00 = Rp. 550.00Mandor 0.005 Oh x Rp. 100,000.00 = Rp. 500.00

Jumlah (2) = Rp. 13,550.00A. Jumlah (1) + (2) = Rp 60,800.00B. Overhead dan Profit 15% x A = Rp 9,120.00

Harga Satuan Pekerjaan (A+B) = Rp 69,920.00

****LANJUT PEKERJAAN BETON

1 M² Pasang dinding pemisah tripleks rangkap, rangka kayu kelas II

1 M² Pasang dinding lambriziring dari papan kayu kelas I

1 M² Pasang dinding lambriziring dari tripleks uk. 120 x 140 cm

1 M² Pasang dinding bilik, rangka kayu kelas III

Page 84: Daftar Analisa Pu 2013

Pekerjaan Plesteran 84

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN PLESTERAN

PL 6.1 1 M² Plesteran 1 Pc : 1 Pp, tebal 15 mm6.1.1 Bahan

Semen portland 15.504 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.016 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.1.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.150 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.015 Oh x Rp. 110,000.00 = Rp.Mandor 0.015 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PL 6.2 1 M² Plesteran 1 Pc : 2 Pp, tebal 15 mm6.2.1 Bahan

Semen portland 10.224 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.020 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.2.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.150 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.015 Oh x Rp. 110,000.00 = Rp.Mandor 0.015 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PL 6.3 1 M² Plesteran 1 Pc : 3 Pp, tebal 15 mm6.3.1 Bahan

Semen portland 7.776 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.023 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.3.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.150 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.015 Oh x Rp. 110,000.00 = Rp.Mandor 0.015 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PL 6.4 1 M² Plesteran 1 Pc : 4 Pp, tebal 15 mm6.4.1 Bahan

Semen portland 6.240 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.024 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.4.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.150 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.015 Oh x Rp. 110,000.00 = Rp.Mandor 0.015 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

Page 85: Daftar Analisa Pu 2013

Pekerjaan Plesteran 85

PEKERJAAN PLESTERAN

PL 6.5 1 M² Plesteran 1 Pc : 5 Pp, tebal 15 mm6.5.1 Bahan

Semen Portland 5.184 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.026 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.5.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.150 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.015 Oh x Rp. 110,000.00 = Rp.Mandor 0.0150 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PL 6.9 1 M² Plesteran 1 Pc : 3 Pp, tebal 15 mm6.9.1 Bahan

Semen Portland 5.760 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.013 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.9.2 Tenaga

Pekerja 0.360 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.120 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.012 Oh x Rp. 110,000.00 = Rp.Mandor 0.018 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PL 6.10 1 M² Plesteran 1 Pc : 8 Pp, tebal 15 mm6.10.1 Bahan

Semen Portland 3.000 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.020 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.10.2 Tenaga

Pekerja 0.360 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.120 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.012 Oh x Rp. 110,000.00 = Rp.Mandor 0.018 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PL 6.13 1 M² Plesteran 1 Pc : 2 Pp, tebal 20 mm6.13.1 Bahan

Semen Portland 13.632 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.027 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.13.2 Tenaga

Pekerja 0.400 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.200 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.020 Oh x Rp. 110,000.00 = Rp.Mandor 0.022 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

Page 86: Daftar Analisa Pu 2013

Pekerjaan Plesteran 86

PEKERJAAN PLESTERAN

PL 6.14 1 M² Plesteran 1 Pc : 3 Pp, tebal 20 mm6.14.1 Bahan

Semen Portland 10.368 Kg x Rp. 1,362.00 = Rp.Pasir Pasang 0.031 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.14.2 Tenaga

Pekerja 0.260 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.200 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.020 Oh x Rp. 110,000.00 = Rp.Mandor 0.013 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PL 6.15 1 M² Plesteran 1 Pc : 4 Pp, tebal 20 mm6.15.1 Bahan

Semen Portland 8.320 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.032 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.15.2 Tenaga

Pekerja 0.400 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.200 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.020 Oh x Rp. 110,000.00 = Rp.Mandor 0.022 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PL 6.16 1 M² Plesteran 1 Pc : 5 Pp, tebal 20 cm 6.16.1 Bahan

Semen Portland 6.912 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.035 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.16.2 Tenaga

Pekerja 0.400 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.200 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.020 Oh x Rp. 110,000.00 = Rp.Mandor 0.022 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PL 6.19 1 M² Berapen 1 Pc : 5 Pp, tebal 15 mm6.19.1 Bahan

Semen portland 5.184 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.026 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.19.2 Tenaga

Pekerja 0.150 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.075 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.008 Oh x Rp. 110,000.00 = Rp.Mandor 0.008 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

Page 87: Daftar Analisa Pu 2013

Pekerjaan Plesteran 87

PEKERJAAN PLESTERAN

PL 6.20 1 M' Plesteran skoning 1 Pc : 2 Pp, tebal 10 mm6.20.1 Bahan

Semen portland 0.500 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.013 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.20.2 Tenaga

Pekerja 0.080 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.400 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.040 Oh x Rp. 110,000.00 = Rp.Mandor 0.004 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PL 6.23 1 M² Plesteran Ciprat 1 Pc : 2 Pp6.23.1 Bahan

Semen portland 4.320 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.006 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.23.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.100 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.010 Oh x Rp. 110,000.00 = Rp.Mandor 0.015 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PL 6.24 1 M² Finishing siar pasangan dinding bata merah (= 20 m')6.24.1 Bahan

Semen portland 3.108 Kg x Rp. 1,362.00 = Rp.Jumlah (1) = Rp.

6.24.2 TenagaPekerja 0.150 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.075 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.008 Oh x Rp. 110,000.00 = Rp.Mandor 0.008 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PL 6.25 1 M² Finishing siar pasangan dinding conblock ekspose (= 8 m')6.25.1 Bahan

Semen portland 1.600 Kg x Rp. 1,362.00 = Rp.Jumlah (1) = Rp.

6.25.2 TenagaPekerja 0.070 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.035 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.004 Oh x Rp. 110,000.00 = Rp.Mandor 0.004 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

Page 88: Daftar Analisa Pu 2013

Pekerjaan Plesteran 88

PEKERJAAN PLESTERAN

PL 6.26 1 M² finishing siar pasangan batu kali adukan 1 Pc : 2 Pp6.26.1 Bahan

Semen portland 6.340 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.012 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.26.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.150 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.015 Oh x Rp. 110,000.00 = Rp.Mandor 0.015 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PL 6.27 1 M² Acian6.27.1 Bahan

Semen portland 3.250 Kg x Rp. 1,362.00 = Rp.Jumlah (1) = Rp.

6.27.2 TenagaPekerja 0.200 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.100 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.010 Oh x Rp. 110,000.00 = Rp.Mandor 0.010 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

*****LANJUT PEKERJAAN KAYU

Page 89: Daftar Analisa Pu 2013

Pekerjaan Plesteran 89

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN PLESTERAN

21,116.451,696.80

22,813.25

22,500.0015,000.00

1,650.001,500.00

40,650.0063,463.25

9,519.4972,982.74

13,925.092,121.00

16,046.09

22,500.0015,000.00

1,650.001,500.00

40,650.0056,696.09

8,504.4165,200.50

10,590.912,439.15

13,030.06

22,500.0015,000.00

1,650.001,500.00

40,650.0053,680.06

8,052.0161,732.07

8,498.882,545.20

11,044.08

22,500.0015,000.00

1,650.001,500.00

40,650.0051,694.08

7,754.1159,448.19

Page 90: Daftar Analisa Pu 2013

Pekerjaan Plesteran 90

PEKERJAAN PLESTERAN

7,060.612,757.309,817.91

22,500.0015,000.00

1,650.001,500.00

40,650.0050,467.91

7,570.1958,038.09

7,845.121,378.659,223.77

27,000.0012,000.00

1,320.001,800.00

42,120.0051,343.77

7,701.5759,045.34

4,086.002,121.006,207.00

27,000.0012,000.00

1,320.001,800.00

42,120.0048,327.00

7,249.0555,576.05

18,566.782,863.35

21,430.13

30,000.0020,000.00

2,200.002,200.00

54,400.0075,830.1311,374.5287,204.65

Page 91: Daftar Analisa Pu 2013

Pekerjaan Plesteran 91

PEKERJAAN PLESTERAN

14,121.223,287.55

17,408.77

19,500.0020,000.00

2,200.001,300.00

43,000.0060,408.77

9,061.3169,470.08

11,331.843,393.60

14,725.44

30,000.0020,000.00

2,200.002,200.00

54,400.0069,125.4410,368.8279,494.26

9,414.143,711.75

13,125.89

30,000.0020,000.00

2,200.002,200.00

54,400.0067,525.8910,128.8877,654.78

7,060.612,757.309,817.91

11,250.007,500.00

880.00800.00

20,430.0030,247.91

4,537.1934,785.09

Page 92: Daftar Analisa Pu 2013

Pekerjaan Plesteran 92

PEKERJAAN PLESTERAN

681.001,378.652,059.65

6,000.0040,000.00

4,400.00400.00

50,800.0052,859.65

7,928.9560,788.60

5,883.84636.30

6,520.14

22,500.0010,000.00

1,100.001,500.00

35,100.0041,620.14

6,243.0247,863.16

4,233.104,233.10

11,250.007,500.00

880.00800.00

20,430.0024,663.10

3,699.4628,362.56

2,179.202,179.20

5,250.003,500.00

440.00400.00

9,590.0011,769.20

1,765.3813,534.58

Page 93: Daftar Analisa Pu 2013

Pekerjaan Plesteran 93

PEKERJAAN PLESTERAN

8,635.081,272.609,907.68

22,500.0015,000.00

1,650.001,500.00

40,650.0050,557.68

7,583.6558,141.33

4,426.504,426.50

15,000.0010,000.00

1,100.001,000.00

27,100.0031,526.50

4,728.9736,255.48

Page 94: Daftar Analisa Pu 2013

Pekerjaan Dinding 94

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN DINDING

PD 6.1 1 M² Pasang bata merah tebal 1 bata, 1 Pc : 2 Pp6.1.1 Bahan

Batu bata cetak mesin 140.000 Bh x Rp. 875 = Rp 122,500.00Semen portland 43.500 Kg x Rp. 1,362 = Rp 59,247.00Pasir pasang 0.080 M³ x Rp. 106,050 = Rp 8,484.00

Jumlah (1) = Rp 190,231.006.1.2 Tenaga

Pekerja 0.600 Oh x Rp. 75,000 = Rp 45,000.00Tukang batu 0.200 Oh x Rp. 100,000 = Rp 20,000.00Kepala tukang 0.020 Oh x Rp. 110,000 = Rp 2,200.00Mandor 0.030 Oh x Rp. 100,000 = Rp 3,000.00

Jumlah (2) = Rp 70,200.00A. Jumlah (1) + (2) = Rp 260,431.00B. Overhead dan Profit 15% x A = Rp 39,064.65

Harga Satuan Pekerjaan (A+B) = Rp 299,495.65

PD 6.2 1M² Pasang bata merah tebal 1 bata, 1Pc : 3 Pp 6.2.1 Bahan

Batu bata cetak mesin 140.000 Bh x Rp. 875 = Rp 122,500.00Semen portland 32.950 Kg x Rp. 1,362 = Rp 44,877.90Pasir pasang 0.091 M³ x Rp. 106,050 = Rp 9,650.55

Jumlah (1) = Rp 177,028.456.2.2 Tenaga

Pekerja 0.600 Oh x Rp. 75,000 = Rp 45,000.00Tukang batu 0.200 Oh x Rp. 100,000 = Rp 20,000.00Kepala tukang 0.020 Oh x Rp. 110,000 = Rp 2,200.00Mandor 0.030 Oh x Rp. 100,000 = Rp 3,000.00

Jumlah (2) = Rp 70,200.00A. Jumlah (1) + (2) = Rp 247,228.45B. Overhead dan Profit 15% x A = Rp 37,084.27

Harga Satuan Pekerjaan (A+B) = Rp 284,312.72

PD 6.3 1 m² Pasang bata merah tebal 1 bata, 1Pc : 4 Pp 6.3.1 Bahan

Batu bata cetak mesin 140.000 Bh x Rp. 875 = Rp 122,500.00Semen portland 26.550 Kg x Rp. 1,362 = Rp 36,161.10Pasir pasang 0.093 M³ x Rp. 106,050 = Rp 9,862.65

Jumlah (1) = Rp 168,523.756.3.2 Tenaga

Pekerja 0.600 Oh x Rp. 75,000 = Rp 45,000.00Tukang batu 0.200 Oh x Rp. 100,000 = Rp 20,000.00Kepala tukang 0.020 Oh x Rp. 110,000 = Rp 2,200.00Mandor 0.030 Oh x Rp. 100,000 = Rp 3,000.00

Jumlah (2) = Rp 70,200.00A. Jumlah (1) + (2) = Rp 238,723.75B. Overhead dan Profit 15% x A = Rp 35,808.56

Harga Satuan Pekerjaan (A+B) = Rp 274,532.31

PD 6.6 1 m² Pasang bata merah tebal 1 bata, 1Pc : 3 Kp : 10 Pp 6.6.1 Bahan

Batu bata cetak mesin 140.000 Bh x Rp. 875 = Rp 122,500.00Semen portland 10.080 Kg x Rp. 1,362 = Rp 13,728.96Pasir pasang 0.093 M³ x Rp. 106,050 = Rp 9,809.63

Jumlah (1) = Rp 146,038.596.6.2 Tenaga

Pekerja 0.600 Oh x Rp. 75,000 = Rp 45,000.00Tukang batu 0.200 Oh x Rp. 100,000 = Rp 20,000.00Kepala tukang 0.020 Oh x Rp. 110,000 = Rp 2,200.00Mandor 0.030 Oh x Rp. 100,000 = Rp 3,000.00

Jumlah (2) = Rp 70,200.00A. Jumlah (1) + (2) = Rp 216,238.59B. Overhead dan Profit 15% x A = Rp 32,435.79

Harga Satuan Pekerjaan (A+B) = Rp 248,674.37

Page 95: Daftar Analisa Pu 2013

Pekerjaan Dinding 95

PEKERJAAN DINDING

PD 6.7 1 m² Pasang bata merah tebal 1/2 bata, 1Pc : 2 Pp6.7.1 Bahan

Batu bata cetak mesin 70.000 Bh x Rp. 875 = Rp 61,250.00Semen portland 18.950 Kg x Rp. 1,362 = Rp 25,809.90Pasir pasang 0.038 M³ x Rp. 106,050 = Rp 4,029.90

Jumlah (1) = Rp 91,089.806.7.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000 = Rp 22,500.00Tukang batu 0.100 Oh x Rp. 100,000 = Rp 10,000.00Kepala tukang 0.010 Oh x Rp. 110,000 = Rp 1,100.00Mandor 0.015 Oh x Rp. 100,000 = Rp 1,500.00

Jumlah (2) = Rp 35,100.00A. Jumlah (1) + (2) = Rp 126,189.80B. Overhead dan Profit 15% x A = Rp 18,928.47

Harga Satuan Pekerjaan (A+B) = Rp 145,118.27

PD 6.8 1 m² Pasang bata merah tebal 1/2 bata, 1Pc : 3 Pp 6.8.1 Bahan

. Batu bata cetak mesin 70.000 Bh x Rp. 875 = Rp 61,250.00Semen portland 14.370 Kg x Rp. 1,362 = Rp 19,571.94Pasir pasang 0.040 M³ x Rp. 106,050 = Rp 4,242.00

Jumlah (1) = Rp 85,063.946.8.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000 = Rp 22,500.00Tukang batu 0.100 Oh x Rp. 100,000 = Rp 10,000.00Kepala tukang 0.010 Oh x Rp. 110,000 = Rp 1,100.00Mandor 0.015 Oh x Rp. 100,000 = Rp 1,500.00

Jumlah (2) = Rp 35,100.00A. Jumlah (1) + (2) = Rp 120,163.94B. Overhead dan Profit 15% x A = Rp 18,024.59

Harga Satuan Pekerjaan (A+B) = Rp 138,188.53

PD 6.9 1 m² Pasang bata merah tebal 1/2 bata, 1Pc : 4 Pp 6.9.1 Bahan

. Batu bata cetak mesin 70.000 Bh x Rp. 875 = Rp 61,250.00Semen portland 11.500 Kg x Rp. 1,362 = Rp 15,663.00Pasir pasang 0.043 M³ x Rp. 106,050 = Rp 4,560.15

Jumlah (1) = Rp 81,473.156.9.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000 = Rp 22,500.00Tukang batu 0.100 Oh x Rp. 100,000 = Rp 10,000.00Kepala tukang 0.010 Oh x Rp. 110,000 = Rp 1,100.00Mandor 0.015 Oh x Rp. 100,000 = Rp 1,500.00

Jumlah (2) = Rp 35,100.00A. Jumlah (1) + (2) = Rp 116,573.15B. Overhead dan Profit 15% x A = Rp 17,485.97

Harga Satuan Pekerjaan (A+B) = Rp 134,059.12

PD 6.10 1 m² Pasang bata merah tebal 1/2 bata, 1Pc : 5 Pp 6.10.1 Bahan

. Batu bata cetak mesin 70.000 Bh x Rp. 875 = Rp 61,250.00Semen portland 9.680 Kg x Rp. 1,362 = Rp 13,184.16Pasir pasang 0.045 M³ x Rp. 106,050 = Rp 4,772.25

Jumlah (1) = Rp 79,206.416.10.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000 = Rp 22,500.00Tukang batu 0.100 Oh x Rp. 100,000 = Rp 10,000.00Kepala tukang 0.010 Oh x Rp. 110,000 = Rp 1,100.00Mandor 0.015 Oh x Rp. 100,000 = Rp 1,500.00

Jumlah (2) = Rp 35,100.00A. Jumlah (1) + (2) = Rp 114,306.41B. Overhead dan Profit 15% x A = Rp 17,145.96

Harga Satuan Pekerjaan (A+B) = Rp 131,452.37

Page 96: Daftar Analisa Pu 2013

Pekerjaan Dinding 96

PEKERJAAN DINDING

PD 6.11 1 m² Pasang bata merah tebal 1/2 bata, 1Pc : 6 Pp 6.11.1 Bahan

. Batu bata cetak mesin 70.000 Bh x Rp. 875 = Rp 61,250.00Semen portland 8.320 Kg x Rp. 1,362 = Rp 11,331.84Pasir pasang 0.049 M³ x Rp. 106,050 = Rp 5,196.45

Jumlah (1) = Rp 77,778.296.11.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000 = Rp 22,500.00Tukang batu 0.100 Oh x Rp. 100,000 = Rp 10,000.00Kepala tukang 0.010 Oh x Rp. 110,000 = Rp 1,100.00Mandor 0.015 Oh x Rp. 100,000 = Rp 1,500.00

Jumlah (2) = Rp 35,100.00A. Jumlah (1) + (2) = Rp 112,878.29B. Overhead dan Profit 15% x A = Rp 16,931.74

Harga Satuan Pekerjaan (A+B) = Rp 129,810.03

PD 6.14 1 m² Pasang bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 1 Pp 6.14.1 Bahan

. Batu bata cetak mesin 70.000 Bh x Rp. 875 = Rp 61,250.00Semen portland 0.018 Kg x Rp. 1,362 = Rp 24.52Pasir pasang 0.018 M³ x Rp. 106,050 = Rp 1,908.90

Jumlah (1) = Rp 63,183.426.14.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000 = Rp 22,500.00Tukang batu 0.100 Oh x Rp. 100,000 = Rp 10,000.00Kepala tukang 0.010 Oh x Rp. 110,000 = Rp 1,100.00Mandor 0.015 Oh x Rp. 100,000 = Rp 1,500.00

Jumlah (2) = Rp 35,100.00A. Jumlah (1) + (2) = Rp 98,283.42B. Overhead dan Profit 15% x A = Rp 14,742.51

Harga Satuan Pekerjaan (A+B) = Rp 113,025.93

PD 6.15 1 m² Pasang bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 2 Pp 6.15.1 Bahan

. Batu bata cetak mesin 70.000 Bh x Rp. 875 = Rp 61,250.00Semen portland 0.014 M³ x Rp. 1,362 = Rp 19.07Pasir pasang 0.028 M³ x Rp. 106,050 = Rp 2,969.40

Jumlah (1) = Rp 64,238.476.15.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000 = Rp 22,500.00Tukang batu 0.100 Oh x Rp. 100,000 = Rp 10,000.00Kepala tukang 0.010 Oh x Rp. 110,000 = Rp 1,100.00Mandor 0.015 Oh x Rp. 100,000 = Rp 1,500.00

Jumlah (2) = Rp 35,100.00A. Jumlah (1) + (2) = Rp 99,338.47B. Overhead dan Profit 15% x A = Rp 14,900.77

Harga Satuan Pekerjaan (A+B) = Rp 114,239.24

PD 6.22 1 m² Pasang terawang (roster) 12 x 11 x 24 cm, 1 Pc : 3 Pp6.22.1 Bahan

. Batu Terawang roster 30.000 Bh x Rp. 8,170 = Rp 245,100.00Sement Portland 14.000 Kg x Rp. 1,362 = Rp 19,068.00Pasir pasang 0.032 M³ x Rp. 106,050 = Rp 3,393.60

Jumlah (1) = Rp 267,561.606.22.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000 = Rp 22,500.00Tukang batu 0.100 Oh x Rp. 100,000 = Rp 10,000.00Kepala tukang 0.010 Oh x Rp. 110,000 = Rp 1,100.00Mandor 0.015 Oh x Rp. 100,000 = Rp 1,500.00

Jumlah (2) = Rp 35,100.00A. Jumlah (1) + (2) = Rp 302,661.60B. Overhead dan Profit 15% x A = Rp 45,399.24

Harga Satuan Pekerjaan (A+B) = Rp 348,060.84

Page 97: Daftar Analisa Pu 2013

Pekerjaan Dinding 97

PEKERJAAN DINDING

PD 6.23 1 m² Pasang terawang (roster) 12 x 11 x 24 cm, 1 Pc : 4 Pp6.23.1 Bahan

. Batu Terawang roster 30.000 Bh x Rp. 8,170 = Rp 245,100.00Sement Portland 11.000 Kg x Rp. 1,362 = Rp 14,982.00Pasir pasang 0.035 M³ x Rp. 106,050 = Rp 3,711.75

Jumlah (1) = Rp 263,793.756.23.2 Tenaga

Pekerja 0.300 Oh x Rp. 75,000 = Rp 22,500.00Tukang batu 0.100 Oh x Rp. 100,000 = Rp 10,000.00Kepala tukang 0.010 Oh x Rp. 110,000 = Rp 1,100.00Mandor 0.015 Oh x Rp. 100,000 = Rp 1,500.00

Jumlah (2) = Rp 35,100.00A. Jumlah (1) + (2) = Rp 298,893.75B. Overhead dan Profit 15% x A = Rp 44,834.06

Harga Satuan Pekerjaan (A+B) = Rp 343,727.81

**********LANJUT PEKERJAAN PLESTERAN

Page 98: Daftar Analisa Pu 2013

Pekerjaan Pondasi 98

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN PONDASI

PP 6.1 1 M³ Pasang pondasi batu belah 1 Pc : 3 Pp6.1.1. Bahan :

Batu belah 1.200 M³ x Rp. 225,000.00 = Rp.Semen portland 202.000 Kg x Rp. 1,362.00 = Rp.Pasir pasang 0.485 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.1.2. Tenaga

Pekerja 1.500 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.750 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.075 Oh x Rp. 110,000.00 = Rp.Mandor 0.075 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PP 6.2 1 M³ Pasang pondasi batu belah 1 Pc : 4 Pp6.2.1. Bahan

Batu belah 1.200 M³ x Rp. 225,000.00 = Rp.Semen portland 163.000 Kg x Rp. 1,362.00 = Rp.Pasir Pasang 0.520 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.2.2. Tenaga

Pekerja 1.500 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.750 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.075 Oh x Rp. 110,000.00 = Rp.Mandor 0.075 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PP 6.3 1 M³ Pasang pondasi batu belah 1 Pc : 5 Pp6.3.1. Bahan

Batu belah 1.200 M³ x Rp. 225,000.00 = Rp.Semen portland 136.000 Kg x Rp. 1,362.00 = Rp.Pasir Pasang 0.544 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.3.2. Tenaga

Pekerja 1.500 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.750 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.075 Oh x Rp. 110,000.00 = Rp.Mandor 0.075 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PP 6.4 1 M³ Pasang pondasi batu kosong6.4.1 Bahan

Batu belah 1.200 M³ x Rp. 225,000.00 = Rp.Pasir urug 0.300 M³ x Rp. 83,380.00 = Rp.

Jumlah (1) = Rp.6.4.2 Tenaga

Pekerja 0.780 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.390 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.039 Oh x Rp. 110,000.00 = Rp.Mandor 0.039 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

Page 99: Daftar Analisa Pu 2013

Pekerjaan Pondasi 99

PEKERJAAN PONDASI

PP 6.5 1 M³ Pasang pondasi siklop 40 % batu kali6.5.1 Bahan

Besi beton polos 75.000 Kg x Rp. 15,300.00 = Rp.Semen portland 202.000 Kg x Rp. 1,362.00 = Rp.Pasir beton 0.320 Kg x Rp. 106,050.00 = Rp.Koral beton 0.490 M³ x Rp. 168,320.00 = Rp.Kawat beton 0.800 Kg x Rp. 23,100.00 = Rp.

Jumlah (1) = Rp.6.5.2 Tenaga

Pekerja 3.000 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.850 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.085 Oh x Rp. 110,000.00 = Rp.Mandor 0.150 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

PP 6.6 1 M³ Pasang pondasi sumuran diameter 100 Cm6.6.1 Bahan

Batu belah 0.450 M³ x Rp. 225,000.00 = Rp.Semen portland 280.000 Kg x Rp. 1,362.00 = Rp.Pasir Pasang 0.670 M³ x Rp. 106,050.00 = Rp.

Jumlah (1) = Rp.6.6.2 Tenaga

Pekerja 2.380 Oh x Rp. 75,000.00 = Rp.Tukang batu 0.300 Oh x Rp. 100,000.00 = Rp.Kepala tukang 0.030 Oh x Rp. 110,000.00 = Rp.Mandor 0.080 Oh x Rp. 100,000.00 = Rp.

Jumlah (2) = Rp.A. Jumlah (1) + (2) = RpB. Overhead dan Profit 15% x A = Rp

Harga Satuan Pekerjaan (A+B) = Rp

**********LANJUT PEKERJAAN DINDING

Page 100: Daftar Analisa Pu 2013

Pekerjaan Pondasi 100

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN PONDASI

270,000.00275,124.00

51,434.25596,558.25

112,500.0075,000.008,250.007,500.00

203,250.00799,808.25119,971.24919,779.49

270,000.00222,006.00

55,146.00547,152.00

112,500.0075,000.008,250.007,500.00

203,250.00750,402.00112,560.30862,962.30

270,000.00185,232.00

57,691.20512,923.20

112,500.0075,000.008,250.007,500.00

203,250.00716,173.20107,425.98823,599.18

270,000.0025,014.00

295,014.00

58,500.0039,000.004,290.003,900.00

105,690.00400,704.00

60,105.60460,809.60

Page 101: Daftar Analisa Pu 2013

Pekerjaan Pondasi 101

PEKERJAAN PONDASI

1,147,500.00275,124.00

33,936.0082,476.8018,480.00

1,557,516.80

225,000.0085,000.009,350.00

15,000.00334,350.00

1,891,866.80283,780.02

2,175,646.82

101,250.00381,360.00

71,053.50553,663.50

178,500.0030,000.003,300.008,000.00

219,800.00773,463.50116,019.53889,483.03

**********LANJUT PEKERJAAN DINDING

Page 102: Daftar Analisa Pu 2013

Pekerjaan Tanah 102

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN TANAH

PT 6.1 1 m³ Galian tanah biasa sedalam 1 meter6.1.1 Tenaga

Pekerja 0.750 Oh x Rp. 75,000 = Rp. 56,250.00Mandor 0.025 Oh x Rp. 100,000 = Rp. 2,500.00

A. Jumlah (1) = Rp 58,750.00B. Overhead dan Profit 15% x A = Rp 8,812.50

Harga Satuan Pekerjaan (A+B) = Rp 67,562.50

PT 6.2 1 m³ Galian tanah biasa sedalam 2 meter 6.2.1 Tenaga

Pekerja 0.900 Oh x Rp. 75,000 = Rp. 67,500.00Mandor 0.0450 Oh x Rp. 100,000 = Rp. 4,500.00

A. Jumlah (1) = Rp 72,000.00B. Overhead dan Profit 15% x A = Rp 10,800.00

Harga Satuan Pekerjaan (A+B) = Rp 82,800.00

PT 6.3 1 m³ Galian tanah biasa sedalam 3 meter6.3.1. Tenaga

Pekerja 1.050 Oh x Rp. 75,000 = Rp. 78,750.00Mandor 0.0670 Oh x Rp. 100,000 = Rp. 6,700.00

A. Jumlah (1) = Rp 85,450.00B. Overhead dan Profit 15% x A = Rp 12,817.50

Harga Satuan Pekerjaan (A+B) = Rp 98,267.50

PT 6.4 1 m³ Galian tanah keras sedalam 1 meter6.4. Tenaga

Pekerja 1.000 Oh x Rp. 75,000 = Rp. 75,000.00Mandor 0.032 Oh x Rp. 100,000 = Rp. 3,200.00

A. Jumlah (1) = Rp 78,200.00B. Overhead dan Profit 15% x A = Rp 11,730.00

Harga Satuan Pekerjaan (A+B) = Rp 89,930.00

PT 6.5 1 m³ Galian tanah cadas sedalam 1 meter6.5.1 Tenaga

Pekerja 1.500 Oh x Rp. 75,000 = Rp. 112,500.00Mandor 0.060 Oh x Rp. 100,000 = Rp. 6,000.00

A. Jumlah (1) = Rp 118,500.00B. Overhead dan Profit 15% x A = Rp 17,775.00

Harga Satuan Pekerjaan (A+B) = Rp 136,275.00

PT 6.6 1 m³ Galian tanah lumpur sedalam 1 meter6.6.1 Tenaga

Pekerja 1.200 Oh x Rp. 75,000 = Rp. 90,000.00Mandor 0.045 Oh x Rp. 100,000 = Rp. 4,500.00

A. Jumlah (1) = Rp 94,500.00B. Overhead dan Profit 15% x A = Rp 14,175.00

Harga Satuan Pekerjaan (A+B) = Rp 108,675.00

PT 6.7 1 m² Pekerjaan stripping setinggi 1 meter6.7.1 Tenaga

Pekerja 0.050 Oh x Rp. 75,000 = Rp. 3,750.00Mandor 0.005 Oh x Rp. 100,000 = Rp. 500.00

A. Jumlah (1) = Rp 4,250.00B. Overhead dan Profit 15% x A = Rp 637.50

Harga Satuan Pekerjaan (A+B) = Rp 4,887.50

PT 6.8 1 m³ Pembuangan tanah sejauh 15 meter6.8.1 Tenaga

Pekerja 0.330 Oh x Rp. 75,000 = Rp. 24,750.00Mandor 0.0100 Oh x Rp. 100,000 Rp. 1,000.00

A. Jumlah (1) = Rp 25,750.00B. Overhead dan Profit 15% x A = Rp 3,862.50

Harga Satuan Pekerjaan (A+B) = Rp 29,612.50

Page 103: Daftar Analisa Pu 2013

Pekerjaan Tanah 103

PEKERJAAN TANAH

PT 6.9 1 m³ Urugan kembali (1/3 dari koefisien galian)6.9.1 Tenaga

Pekerja 0.250 Oh x Rp. 75,000 = Rp. 18,750.00Mandor 0.008 Oh x Rp. 100,000 = Rp. 833.33

A. Jumlah (1) = Rp 19,583.33B. Overhead dan Profit 15% x A = Rp 2,937.50

Harga Satuan Pekerjaan (A+B) = Rp 22,520.83

PT 6.10 1 m³ Pemadatan tanah6.10.1.Tenaga

Pekerja 0.500 Oh x Rp. 75,000 = Rp. 37,500.00Mandor 0.050 Oh x Rp. 100,000 = Rp. 5,000.00

A. Jumlah (1) = Rp 42,500.00B. Overhead dan Profit 15% x A = Rp 6,375.00

Harga Satuan Pekerjaan (A+B) = Rp 48,875.00

PT 6.11 1 m³ Urugan pasir6.11.1.Bahan

Pasir urug 1.200 M³ x Rp. 83,380 = Rp. 100,056.00Jumlah (1) = Rp. 100,056.00

6.11.2.TenagaPekerja 0.300 Oh x Rp. 75,000 = Rp. 22,500.00Mandor 0.010 Oh x Rp. 100,000 = Rp. 1,000.00

Jumlah (2) = Rp. 23,500.00A. Jumlah (1) + (2) = Rp 123,556.00B. Overhead dan Profit 15% x A = Rp 18,533.40

Harga Satuan Pekerjaan (A+B) = Rp 142,089.40

PT 6.12 1 m³ Memasang lapisan pudel campuran 1 : 3 : 7 untuk stabilisasi tanah6.12.1 Bahan

Pasir pasang 0.400 M³ x Rp. 106,050 = Rp. 42,420.00Pasir urug 0.948 M³ x Rp. 83,380 = Rp. 79,044.24

Jumlah (1) = Rp. 121,464.246.12.2 Tenaga

Pekerja 0.800 Oh x Rp. 75,000 = Rp. 60,000.00Tukang batu 0.400 Oh x Rp. 100,000 = Rp. 40,000.00Kepala tukang 0.040 Oh x Rp. 110,000 = Rp. 4,400.00Mandor 0.080 Oh x Rp. 100,000 = Rp. 8,000.00

Jumlah (2) = Rp. 112,400.00A. Jumlah (1) + (2) = Rp 233,864.24B. Overhead dan Profit 15% x A = Rp 35,079.64

Harga Satuan Pekerjaan (A+B) = Rp 268,943.88

PT 6.13 1 m³ Memasang lapisan pudel campuran 1 : 5 untuk stabilisasi tanah6.13.1 Bahan

Pasir urug 1.240 M³ x Rp. 83,380 = Rp. 103,391.20Jumlah (1) = Rp. 103,391.20

6.13.2 TenagaPekerja 0.800 Oh x Rp. 75,000 = Rp. 60,000.00Tukang batu 0.400 Oh x Rp. 100,000 = Rp. 40,000.00Kepala tukang 0.040 Oh x Rp. 110,000 = Rp. 4,400.00Mandor 0.080 Oh x Rp. 100,000 = Rp. 8,000.00

Jumlah (2) = Rp. 112,400.00A. Jumlah (1) + (2) = Rp 215,791.20B. Overhead dan Profit 15% x A = Rp 32,368.68

Harga Satuan Pekerjaan (A+B) = Rp 248,159.88

Page 104: Daftar Analisa Pu 2013

Pekerjaan Tanah 104

PEKERJAAN TANAH

PT 6.14 1 m³ Lapisan ijuk tebal 10 cm untuk bidang resapan6.14.1 Bahan

Ijuk 6.000 M2 x Rp. 31,500 = Rp. 189,000.00Jumlah (1) = Rp. 189,000.00

6.14.2 TenagaPekerja 0.150 Oh x Rp. 75,000 = Rp. 11,250.00Mandor 0.015 Oh x Rp. 100,000 = Rp. 1,500.00

Jumlah (2) = Rp. 12,750.00A. Jumlah (1) + (2) = Rp 201,750.00B. Overhead dan Profit 15% x A = Rp 30,262.50

Harga Satuan Pekerjaan (A+B) = Rp 232,012.50

PT 6.15 1 m³ Mengurug sirtu padat untuk peninggian lantai bangunan6.15.1 Bahan

Sirtu /pasir batu 1.200 M³ x Rp. 119,700 = Rp. 143,640.00Jumlah (1) = Rp. 143,640.00

6.15.2 TenagaPekerja 0.250 Oh x Rp. 75,000 = Rp. 18,750.00Mandor 0.025 Oh x Rp. 100,000 = Rp. 2,500.00

Jumlah (2) = Rp. 21,250.00A. Jumlah (1) + (2) = Rp 164,890.00B. Overhead dan Profit 15% x A = Rp 24,733.50

Harga Satuan Pekerjaan (A+B) = Rp 189,623.50

*******LANJUT PEKERJAAN PONDASI

Page 105: Daftar Analisa Pu 2013

Pekerjaan Persiapan 105

ANALISA HARGA SATUAN PEKERJAAN 2013PEKERJAAN PERSIAPAN

PA 6.1 1 m' Pagar Sementara dari kayu tinggi 2 meter6.1.1 Bahan

Kayu dolken/bulat Ø 3" - 4" 1.250 Btg x Rp 20,000 = Rp 25,000.00Semen Portland 2.500 Kg x Rp 1,362 = Rp 3,405.00Pasir Beton 0.005 M3 x Rp 106,050 = Rp 530.25Koral Beton 0.009 M3 x Rp 168,320 = Rp 1,514.88Kayu Kelas III 0.038 M3 x Rp 3,633,730 = Rp 138,081.74Paku biasa 0.060 Kg x Rp 18,900 = Rp 1,134.00Residu/colter 0.400 Lt x Rp 7,700 = Rp 3,080.00

Jumlah (1) = Rp 172,745.876.1.2 Tenaga

Tukang kayu 0.200 Oh x Rp 100,000 = Rp 20,000.00Pekerja 0.400 Oh x Rp 75,000 = Rp 30,000.00Kepala tukang 0.020 Oh x Rp 110,000 = Rp 2,200.00Mandor 0.020 Oh x Rp 100,000 = Rp 2,000.00

Jumlah (2) = Rp 54,200.00A. Jumlah (1) + (2) = Rp 226,945.87B. Overhead dan Profit 15% x A = Rp 34,041.88

Harga Satuan Pekerjaan (A+B) = Rp 260,987.75

PA 6.2 1 m' Pagar sementara dari seng gelombang tinggi 2 meter6.2.1 Bahan

Kayu dolken/bulat Ø 3" - 4" 1.250 Btg x Rp 20,000 = Rp 25,000.00Semen Portland 2.500 Kg x Rp 1,362 = Rp 3,405.00Seng gelombang 7 kaki BJLS 1.200 Lbr x Rp 56,510 = Rp 67,812.00Pasir beton 0.005 M3 x Rp 106,050 = Rp 530.25Koral beton 0.009 M3 x Rp 168,320 = Rp 1,514.88Kayu Kelas III 0.012 M3 x Rp 3,633,730 = Rp 43,604.76Paku biasa 0.060 Kg x Rp 18,900 = Rp 1,134.00Cat meni besi 0.450 Kg x Rp 35,280 = Rp 15,876.00

Jumlah (1) = Rp 158,876.896.2.2 Tenaga

Tukang kayu 0.200 Oh x Rp 100,000 = Rp 20,000.00Pekerja 0.400 Oh x Rp 75,000 = Rp 30,000.00Kepala tukang 0.020 Oh x Rp 110,000 = Rp 2,200.00Mandor 0.020 Oh x Rp 100,000 = Rp 2,000.00

Jumlah (2) = Rp 54,200.00A. Jumlah (1) + (2) = Rp 213,076.89B. Overhead dan Profit 15% x A = Rp 31,961.53

Harga Satuan Pekerjaan (A+B) = Rp 245,038.42

PA 6.4 1 M' Pengukuran dan Pemasangan bouplank6.4.1 Bahan

Kayu Kelas III 0.012 M3 x Rp 3,633,730 = Rp 43,604.76Paku biasa 0.020 Kg x Rp 18,900 = Rp 378.00Kayu papan (Kayu Kelas III) 0.007 M3 x Rp 3,633,730 = Rp 25,436.11

Jumlah (1) = Rp 69,418.876.4.2 Tenaga

Tukang kayu 0.100 Oh x Rp 100,000 = Rp 10,000.00Pekerja 0.100 Oh x Rp 75,000 = Rp 7,500.00Kepala tukang 0.010 Oh x Rp 110,000 = Rp 1,100.00Mandor 0.005 Oh x Rp 100,000 = Rp 500.00

Jumlah (2) = Rp 19,100.00A. Jumlah (1) + (2) = Rp 88,518.87B. Overhead dan Profit 15% x A = Rp 13,277.83

Harga Satuan Pekerjaan (A+B) = Rp 101,796.70

PA 6.8 1 m² Membersihkan lapangan dan perataan6.8.1 Tenaga

Pekerja 0.100 Oh x Rp 75,000 = Rp 7,500.00Mandor 0.050 Oh x Rp 100,000 = Rp 5,000.00

A. Jumlah (1) = Rp 12,500.00B. Overhead dan Profit 15% x A = Rp 1,875.00

Page 106: Daftar Analisa Pu 2013

Pekerjaan Persiapan 106

PEKERJAAN PERSIAPAN

Harga Satuan Pekerjaan (A+B) = Rp 14,375.00

PA 6.12 1 m² Pembuatan jalan sementara6. 12.1 Bahan

Batu belah 0.150 M³ x Rp 225,000 = Rp 33,750.00Batu pecah 5 - 7 cm 0.090 M³ x Rp 228,000 = Rp 20,520.00Pasir pasang 0.010 M³ x Rp 106,050 = Rp 1,060.50

Jumlah (1) = Rp 55,330.506.12.2 Tenaga

Pekerja 1.000 Oh x Rp 75,000 = Rp 75,000.00Mandor 0.050 Oh x Rp 100,000 = Rp 5,000.00

Jumlah (2) = Rp 80,000.00A. Jumlah (1) + (2) = Rp 135,330.50B. Overhead dan Profit 15% x A = Rp 20,299.58

Harga Satuan Pekerjaan (A+B) = Rp 155,630.08

PA 6.13 1 m³ Bongkaran beton betulang6.13.1 Tenaga

Pekerja 6.667 Oh x Rp 75,000 = Rp 500,025.00Mandor 0.333 Oh x Rp 100,000 = Rp 33,300.00

A. Jumlah (1) = Rp 533,325.00B. Overhead dan Profit 15% x A = Rp 79,998.75

Harga Satuan Pekerjaan (A+B) = Rp 613,323.75

PA 6.14 1m³ Bongkaran dinding tembok bata merah6.14.1 Tenaga

Pekerja 5.000 Oh x Rp 75,000 = Rp 375,000.00Mandor 0.250 Oh x Rp 100,000 = Rp 25,000.00

A. Jumlah (1) = Rp 400,000.00B. Overhead dan Profit 15% x A = Rp 60,000.00

Harga Satuan Pekerjaan (A+B) = Rp 460,000.00

PA 6.15 1m´ Pasangan pagar kawat jaring galvanis, tinggi 1.00 m6.15.1 Bahan

Kawat jaring galvanis/BRC 0.434 Lbr x Rp 320,000 = Rp 138,880.00Jumlah (1) = Rp 138,880.00

6.15.2 TenagaPekerja 0.042 Oh x Rp 75,000 = Rp 3,150.00Kepala tukang 0.004 Oh x Rp 110,000 = Rp 440.00Tukang 0.042 Oh x Rp 100,000 = Rp 4,200.00Mandor 0.002 Oh x Rp 100,000 = Rp 200.00

Jumlah (2) = Rp 7,990.00A. Jumlah (1) + (2) = Rp 146,870.00B. Overhead dan Profit 15% x A = Rp 22,030.50

Harga Satuan Pekerjaan (A+B) = Rp 168,900.50

**************LANJUT KE PEKERJAAN TANAH

Page 107: Daftar Analisa Pu 2013

ANALISA BIAYA KONSTRUKSI ( ABK )BANGUNAN GEDUNG DAN PERUMAHAN

NO JENIS PEKERJAAN ANALISA VOLUMEHARGA HARGA JUMLAHBAHAN UPAH HARGA

( Rp ) ( Rp ) ( Rp )

A. PEKERJAAN PERSIAPAN

1 Pagar Sementara dari kayu tinggi 2 m PA 6. 1 1 M' 172,745.87 54,200.00 226,945.87

2 PA 6. 2 1 M' 158,876.89 54,200.00 213,076.89

3 Pengukuran dan Pemasangan Bouwplank PA 6. 4 1 M' 69,418.87 19,100.00 88,518.87

4 Membersihkan Lapangan dan Perataan PA 6. 8 1 M² 0.00 #REF! #REF!

5 Pembuatan Jalan Sementara PA 6. 12 1 M² 55,330.50 80,000.00 135,330.50

6 Bongkaran Beton Bertulang PA 6. 13 1 M³ 0.00 #REF! #REF!

7 Bongkaran Dinding Tembok Bata PA 6. 14 1 M³ 0.00 #REF! #REF!

8 Pas. Pagar Kawat Jaring Galvanis t = 1 m' PA 6. 15 1 M' 138,880.00 7,990.00 146,870.00

B. PEKERJAAN TANAH

1 Galian Tanah Biasa sedalam 1 m' PT 6. 1 1 M³ 0.00 #REF! #REF!

2 Galian Tanah Biasa sedalam 2 m' PT 6. 2 1 M³ 0.00 #REF! #REF!

3 Galian Tanah Biasa sedalam 3 m' PT 6. 3 1 M³ 0.00 #REF! #REF!

4 Galian Tanah Keras sedalam 1 m' PT 6. 4 1 M³ 0.00 #REF! #REF!

5 Galian Tanah Cadas sedalam 1 m' PT 6. 5 1 M³ 0.00 #REF! #REF!

6 Galian Tanah Lumpur sedalam 1 m' PT 6. 6 1 M³ 0.00 #REF! #REF!

7 Stripping setinggi 1 m' PT 6. 7 1 M³ 0.00 #REF! #REF!

8 Pembuangan Tanah sejauh 150 m' PT 6. 8 1 M³ 0.00 #REF! #REF!

9 Urugan Kembali PT 6. 9 1 M³ 0.00 #REF! #REF!

10 Pemadatan Tanah PT 6. 10 1 M³ 0.00 #REF! #REF!

11 Urugan Pasir PT 6. 11 1 M³ 100,056.00 23,500.00 123,556.00

12 Pembuatan jalan sementara tbl.25 cm PT 6. 16 1 M² #REF! #REF! #REF!

C. PEKERJAAN PONDASI

1 Pas. Pondasi Bt.Kali 1 Pc : 1 Ps PP 6. 1 1 M³ 596,558.25 203,250.00 799,808.25

2 Pas. Pondasi Bt.Kali 1 Pc : 2 Ps PP 6. 2 1 M³ 547,152.00 203,250.00 750,402.00

3 PP 6. 3 1 M³ 512,923.20 203,250.00 716,173.20

4 Pas. Pondasi Bt.Kali 1 Pc : 3 Ps PP 6. 4 1 M³ #REF! #REF! #REF!

5 Pas. Pondasi Bt.Kali 1 Pc : 4 Ps PP 6. 5 1 M³ #REF! #REF! #REF!

6 Pas. Pondasi Bt.Kali 1 Pc : 5 Ps PP 6. 6 1 M³ #REF! #REF! #REF!

7 Pas. Pondasi Bt.Kali 1 Pc : 6 Ps PP 6. 7 1 M³ #REF! #REF! #REF!

8 Pas. Pondasi Bato Kosong PP 6. 14 1 M³ #REF! #REF! #REF!

9 PP 6. 15 1 M³ #REF! #REF! #REF!

10 PP 6. 16 1 M³ #REF! #REF! #REF!

11 PP 6. 17 1 M³ #REF! #REF! #REF!

12 PP 6. 18 1 M³ #REF! #REF! #REF!

Pagar Sementara dari Seng Gelombang tinggi 2 m

Pas. Pondasi Bt.Kali 1 Pc : 2½ Ps

Pas. Pondasi Siklop 40% Bt.Kali

Pas. Pondasi Sumuran Ø 100 cm

Pembuatan tiang pancang 40 x 40 cm Beton bertulang

Pembuatan tiang pancang 30 x 30 cm Beton bertulang

Page 108: Daftar Analisa Pu 2013

1 2 3 4 5 6 7

D. PEKERJAAN DINDING

1 Pas. Bata Merah tbl.1 Bata, 1 Pc : 1 Ps PD 6. 1 1 190,231.00 70,200.00 260,431.00

2 Pas. Bata Merah tbl.1 Bata, 1 Pc : 2 Ps PD 6. 2 1 177,028.45 70,200.00 247,228.45

3 Pas. Bata Merah tbl.1 Bata, 1 Pc : 3 Ps PD 6. 3 1 168,523.75 70,200.00 238,723.75

4 Pas. Bata Merah tbl.1 Bata, 1 Pc : 4 Ps PD 6. 4 1 #REF! #REF! #REF!

5 PD 6. 8 1 #REF! #REF! #REF!

6 PD 6. 9 1 146,038.59 70,200.00 216,238.59

7 PD 6. 10 1 91,089.80 35,100.00 126,189.80

8 PD 6. 11 1 85,063.94 35,100.00 120,163.94

9 Pas. Dinding Conblock (HB.20) PD 6. 21 1 #REF! #REF! #REF!

10 Pas. Dinding Conblock (HB.15) PD 6. 22 1 #REF! #REF! #REF!

11 Pas. Dinding Conblock (HB.10) PD 6. 23 1 #REF! #REF! #REF!

12 Pas. Dinding Lantai PD 6. 24 1 #REF! #REF! #REF!

13 Pas. Dinding rooster / terawang PD 6. 25 1 #REF! #REF! #REF!

14 Pas. Bata berongga uk.5x10x20 cm PD 6. 26 1 #REF! #REF! #REF!

15 Pas. Dinding Anyaman Bambu, rangka kayu PD 6. 27 1 #REF! #REF! #REF!

E. PEKERJAAN PELESTERAN

1 Pas. Plesteran Tbl.15 mm, 1 Pc : 1 Ps PPL 6. 1 1 22,813.25 40,650.00 63,463.25

2 Pas. Plesteran Tbl.15 mm, 1 Pc : 2 Ps PPL 6. 2 1 16,046.09 40,650.00 56,696.09

3 Pas. Plesteran Tbl.15 mm, 1 Pc : 3 Ps PPL 6. 3 1 13,030.06 40,650.00 53,680.06

4 Pas. Plesteran Tbl.15 mm, 1 Pc : 4 Ps PPL 6. 4 1 11,044.08 40,650.00 51,694.08

5 Pas. Plesteran Tbl.20 mm, 1 Pc : 2 Ps PPL 6. 13 1 9,817.91 40,650.00 50,467.91

6 Pas. Plesteran Tbl.20 mm, 1 Pc : 3 Ps PPL 6. 14 1 #REF! #REF! #REF!

7 Pas. Plesteran Tbl.20 mm, 1 Pc : 4 Ps PPL 6. 15 1 #REF! #REF! #REF!

8 Pas. Plesteran Tbl.25 mm, 1 Pc : 2 Ps PPL 6. 19 1 #REF! #REF! #REF!

9 Pas. Plesteran Tbl.25 mm, 1 Pc : 3 Ps PPL 6. 20 1 9,223.77 42,120.00 51,343.77

10 Pas. Plesteran Tbl.25 mm, 1 Pc : 4 Ps PPL 6. 21 1 6,207.00 42,120.00 48,327.00

11 Pas. Plesteran Tbl.30 mm, 1 Pc : 2 Ps PPL 6. 23 1 #REF! #REF! #REF!

12 Pas. Plesteran Tbl.30 mm, 1 Pc : 3 Ps PPL 6. 24 1 #REF! #REF! #REF!

13 Pas. Plesteran Tbl.30 mm, 1 Pc : 4 Ps PPL 6. 25 1 21,430.13 54,400.00 75,830.13

14 Plesteran Beton T=15 mm, 1 Pc : 2 Ps PPL 6. 29 1 17,408.77 43,000.00 60,408.77

15 Plesteran Beton T=15 mm, 1 Pc : 3 Ps PPL 6. 30 1 14,725.44 54,400.00 69,125.44

16 Plesteran Skoning 1 Pc : 2 Ps PPL 6. 31 1 13,125.89 54,400.00 67,525.89

17 Plesteran Ciprat tbl.10 mm, 1 Pc : 2 Ps PPL 6. 34 1 #REF! #REF! #REF!

18 Plesteran Siar adukan, 1 Pc : 2 Ps PPL 6. 35 1 #REF! #REF! #REF!

Pas. Bata Merah tbl.½ Bata, 1 Pc : 1 Ps M²

Pas. Bata Merah tbl.½ Bata, 1 Pc : 2 Ps M²

Pas. Bata Merah tbl.½ Bata, 1 Pc : 3 Ps M²

Pas. Bata Merah tbl.½ Bata, 1 Pc : 4 Ps M²

Page 109: Daftar Analisa Pu 2013

1 2 3 4 5 6 7F. PEKERJAAN KAYU

1 Pas. Kosen Pintu dan Jendela, kayu Jati PK 6. 1 1 M³ 10,199,448.00 2,891,000.00 13,090,448.00

2 Pas. Kosen Pintu dan Jendela, kayu M.Batu PK 6. 2 1 M³ #REF! #REF! #REF!

3 Pas. Kosen Pintu dan Jendela, kayu Kapur PK 6. 3 1 M³ #REF! #REF! #REF!

4 Pas. Kosen Pintu dan Jendela, kayu D.Laut PK 6. 4 1 M³ #REF! #REF! #REF!

5 Pas.Pintu klamp, kayu Meranti Batu PK 6. 5 1 #REF! #REF! #REF!

6 Pas.Pintu klamp, kayu Jati PK 6. 6 1 #REF! #REF! #REF!

7 Pas.Pintu Panel, kayu Jati PK 6. 7 1 #REF! #REF! #REF!

8 Pas.Pintu Panel, kayu Meranti Batu PK 6. 8 1 #REF! #REF! #REF!

9 PK 6. 9 1 #REF! #REF! #REF!

10 PK 6. 10 1 #REF! #REF! #REF!

11 PK 6. 11 1 #REF! #REF! #REF!

12 Pas.Pintu dan Jendela Jalusi, kayu Jati PK 6. 12 1 #REF! #REF! #REF!

13 Pas.Pintu dan Jendela Jalusi, kayu M.Batu PK 6. 13 1 #REF! #REF! #REF!

14 Pas.Pintu Plywood, Rangka kayu Jati PK 6. 14 1 #REF! #REF! #REF!

15 Pas.Pintu Plywood, Rangka kayu M.Batu PK 6. 15 1 #REF! #REF! #REF!

16 Pas.Jalusi mati, kusen kayu Jati PK 6. 16 1 #REF! #REF! #REF!

17 Pas.Jalusi mati, kusen kayu D.Laut PK 6. 17 1 #REF! #REF! #REF!

18 Pas.Pintu Plywood, Rangka kayu Meranti PK 6. 18 1 #REF! #REF! #REF!

18 Pas.Pintu Teakwood, Rangka kayu Jati PK 6. 19 1 #REF! #REF! #REF!

19 Pas.Pintu Teakwood, Rangka kayu M.Batu PK 6. 20 1 #REF! #REF! #REF!

20 PK 6. 21 1 #REF! #REF! #REF!

21 PK 6. 22 1 #REF! #REF! #REF!

22 PK 6. 23 1 #REF! #REF! #REF!

23 PK 6. 24 1 #REF! #REF! #REF!

24 Pas.Konstruksi Kuda-kuda, kayu D.Laut PK 6. 29 1 M³ #REF! #REF! #REF!

25 Pas.Konstruksi Kuda-kuda, kayu Meranti PK 6. 30 1 M³ #REF! #REF! #REF!

26 PK 6. 31 1 #REF! #REF! #REF!

27 PK 6. 32 1 #REF! #REF! #REF!

28 Pas.Kaso + reng genteng monier, kayu Jati PK 6. 33 1 #REF! #REF! #REF!

29PK 6. 34 1 #REF! #REF! #REF!

30PK 6. 35 1 #REF! #REF! #REF!

31 Pas.Kaso + reng Atap Sirap, kayu D.Laut PK 6. 36 1 #REF! #REF! #REF!

32 Pas.Kaso + reng Atap Sirap, kayu Meranti PK 6. 37 1 #REF! #REF! #REF!

33 Pas.Rangka Langit2 1 x 1 m, kayu Jati PK 6. 38 1 #REF! #REF! #REF!

34 Pas.Rangka Langit2 1 x 1 m, kayu D.Laut PK 6. 38 A 1 #REF! #REF! #REF!

35 Pas.Rangka Langit2 1 x 1 m, kayu Meranti PK 6. 38 B 1 #REF! #REF! #REF!

Pas.Pintu dan Jendela kaca panel, Rangka kayu Jati

Pas.Pintu dan Jendela kaca panel, kayu Meranti Batu

Pas.Pintu dan Jendela kaca panel, kayu Meranti

Pas.Pintu Plywood + Formica, Rangka kayu Jati

Pas.Pintu Plywood + Formica, Rangka kayu Meranti Batu

Pas.Pintu Teakwood + Formica, Rangka kayu Jati

Pas.Pintu Teakwood + Formica, Rangka kayu Meranti Batu

Pas.Kaso + reng genteng kodok, kayu Meranti

Pas.Kaso + reng genteng kodok, kayu Damar Laut

Pas.Kaso + reng genteng monier, kayu Damar Laut

Pas.Kaso + reng Genteng beton, kayu Damar Laut

Page 110: Daftar Analisa Pu 2013

1 2 3 4 5 6 7

36 Pas.Rangka Langit2 30 x 30 cm, kayu Jati PK 6. 44 1 #REF! #REF! #REF!

37 PK 6. 45 1 #REF! #REF! #REF!

38Pas.Rangka Langit2 30 x 30 cm, kayu Meranti

PK 6. 46 1 #REF! #REF! #REF!

39 Pas.Lisplank 3 x 20 cm, kayu Meranti PK 6. 47 1 M' #REF! #REF! #REF!

40 Pas.Lisplank 3 x 20 cm, kayu Meranti Batu PK 6. 48 1 M' #REF! #REF! #REF!

41 Pas.Lisplank 3 x 30 cm, kayu Jati PK 6. 49 1 M' #REF! #REF! #REF!

42 Pas.Lisplank 3 x 30 cm, kayu Meranti Batu PK 6. 50 1 M' #REF! #REF! #REF!

43 PK 6. 51 1 M' #REF! #REF! #REF!

44 PK 6. 52 1 M' #REF! #REF! #REF!

45 Pas.Lisplank 2 x ( 2 x 20) cm, kayu Meranti PK 6. 53 1 M' #REF! #REF! #REF!

46 Pas.Rangka Dinding Pemisah, kayu D.Laut PK 6. 54 1 #REF! #REF! #REF!

47 Pas.Rangka Dinding Pemisah, kayu MerantiPK 6. 55 1 #REF! #REF! #REF!

48 PK 6. 56 1 #REF! #REF! #REF!

49 PK 6. 57 1 #REF! #REF! #REF!

50 Pas.Dinding Lambesring, kayu Jati PK 6. 58 1 #REF! #REF! #REF!

51 Pas.Plywood 4 mm utk Dinding PK 6. 59 1 #REF! #REF! #REF!

52 Pas.List Plafond, kayu profil PK 6. 60 1 M' #REF! #REF! #REF!

G. PEKERJAAN BETON

1 Pas. Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr PB 6. 1 1 M³ 539,954.47 162,630.00 702,584.47

2 Pas. Beton Tumbuk, 1 Pc : 3 Ps : 6 Kr PB 6. 2 1 M³ #REF! #REF! #REF!

3 Pas. Beton Tumbuk, 1 Pc : 4 Ps : 6 Kr PB 6. 3 1 M³ #REF! #REF! #REF!

4 PB 6. 4 1 #REF! #REF! #REF!

5 Pas. Beton Tumbuk, 1 Pc : 2 Ps : 3 Kr PB 6. 5 1 M³ #REF! #REF! #REF!

6 Pas. Beton Tumbuk, 1 Pc : 2 Ps : 4 Kr PB 6. 6 1 M³ #REF! #REF! #REF!

7 PB 6. 7 1 M³ #REF! #REF! #REF!

8 PB 6. 8 1 M³ #REF! #REF! #REF!

9 PB 6. 9 1 M³ #REF! #REF! #REF!

10 Pas. Beton Bertulang, 1 Pc : 1 Ps : 2 Kr PB 6. 10 1 M³ #REF! #REF! #REF!

11 Membuat Tiang Pancang Prestressed Beton PB 6. 11 1 M³ #REF! #REF! #REF!

12 Pas. Beton Bertulang, 1 Pc : 2 Ps : 3 Kr PB 6. 13 1 M³ #REF! #REF! #REF!

13 Pas. Beton Bertulang, 1 Pc : 2 Ps : 4 Kr PB 6. 14 1 M³ #REF! #REF! #REF!

14 PB 6. 15 1 M³ #REF! #REF! #REF!

15 PB 6. 16 1 M³ #REF! #REF! #REF!

16 Pas. Beton Bertulang, 1 Pc : 1 Ps : 1 Kr PB 6. 17 1 M³ #REF! #REF! #REF!

17 Pembesian dengan besi polos PB 6. 25 1 Kg #REF! #REF! #REF!

18 Kabel Prestressed polos / strends PB 6. 26 1 Kg #REF! #REF! #REF!

19 Pas. Bekisting untuk Pondasi PB 6. 28 1 #REF! #REF! #REF!

Pas.Rangka Langit2 30 x 30 cm, kayu Damar Laut

Pas.Lisplank 2 x ( 3 x 20) cm, kayu Meranti Batu

Pas.Lisplank 2 x ( 2 x 20) cm, kayu Meranti Batu

Pas.Dinding Pemisah Teakwood, kayu Damar Laut

Pas.Dinding Pemisah Plywood, kayu Damar Laut

Pas. Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr, tebal 5 cm

Pas. Beton Tumbuk, 1 Pc : 2 Ps : 2½ Kr

Pas. Beton Tumbuk, 1 Pc : 1½ Ps : 3 Kr

Pas. Beton Tumbuk, 1 Pc : 1½ Ps : 2½ Kr

Pas. Beton Bertulang, 1 Pc : 1½ Ps : 3 Kr

Pas. Beton Bertulang, 1 Pc : 1½ Ps : 2½ Kr

Page 111: Daftar Analisa Pu 2013

1 2 3 4 5 6 7

20 Pas. Bekisting untuk Sloof PB 6. 29 1 #REF! #REF! #REF!

21 Pas. Bekisting untuk Kolom PB 6. 30 1 #REF! #REF! #REF!

22 Pas. Bekisting untuk Balok PB 6. 31 1 #REF! #REF! #REF!

23 Pas. Bekisting untuk Lantai PB 6. 32 1 #REF! #REF! #REF!

24 Pas. Bekisting untuk Dinding PB 6. 33 1 #REF! #REF! #REF!

25 Pas. Bekisting untuk Tangga PB 6. 34 1 #REF! #REF! #REF!

26 Pas. Beton dengan Mutu K 225 PB 6. 35 1 M³ #REF! #REF! #REF!

27 Pas. Beton dengan Mutu K 275 PB 6. 36 1 M³ #REF! #REF! #REF!

28 Pas. Bekisting Jembatan Cor PB 6. 37 1 #REF! #REF! #REF!

29 PB 6. 38 1 M³ #REF! #REF! #REF!

30 PB 6. 39 1 M³ #REF! #REF! #REF!

31 PB 6. 40 1 M³ #REF! #REF! #REF!

32 PB 6. 41 1 M³ #REF! #REF! #REF!

33 PB 6. 42 1 M³ #REF! #REF! #REF!

34 PB 6. 43 1 M³ #REF! #REF! #REF!

35 PB 6. 44 1 M³ #REF! #REF! #REF!

36 Pas. Ringbalk Btn Bertulang, (10 x 15) cm PB 6. 46 1 M³ #REF! #REF! #REF!

H. PEKERJAAN PENUTUP ATAP

1 Pas. Atap Genteng Plantong kecil PPA 6 1 1 #REF! #REF! #REF!

2 Pas. Atap Genteng kodok / Glazzur PPA 6 2 1 #REF! #REF! #REF!

3 Pas. Atap Genteng Plantong Super / besar PPA 6 3 1 #REF! #REF! #REF!

4 Pas. Bubung Genteng Plantong kecil PPA 6 4 1 M' #REF! #REF! #REF!

5 Pas. Bubung Atap Genteng kodok PPA 6 5 1 M' #REF! #REF! #REF!

6 Pas. Bubung Genteng Plantong besar PPA 6 6 1 M' #REF! #REF! #REF!

7 Pas. Atap Roof light Fibreglass 180x90 cm PPA 6 7 1 28,779.00 18,670.00 47,449.00

8 PPA 6 8 1 #REF! #REF! #REF!

9 PPA 6 9 1 #REF! #REF! #REF!

10 PPA 6 10 1 #REF! #REF! #REF!

11 PPA 6 11 1 31,545.60 18,970.00 50,515.60

12 PPA 6 12 1 #REF! #REF! #REF!

13 PPA 6 13 1 #REF! #REF! #REF!

14 PPA 6 14 1 #REF! #REF! #REF!

15 PPA 6 18 1 #REF! #REF! #REF!

16 PPA 6 19 1 #REF! #REF! #REF!

17 PPA 6 20 1 #REF! #REF! #REF!

18 PPA 6 21 1 #REF! #REF! #REF!

19 Pas. Bubung/Nok stel gelombang 0,92 m PPA 6 22 1 M' 15,979.00 20,630.00 36,609.00

Membuat Pondasi beton bertulang ( 150 kg besi + bekisting )

Membuat Sloof beton bertulang ( 200 kg besi + bekisting )

Membuat Kolom beton bertulang ( 300 kg besi + bekisting )

Membuat Balok beton bertulang ( 200 kg besi + bekisting )

Membuat Balok beton bertulang ( 150 kg besi + bekisting )

Membuat Dinding beton bertulang ( 150 kg besi + bekisting )

Membuat Tangga beton bertulang ( 150 kg besi+bekisting )

Pas. Atap Asbes Gelombang (2,70 x 0,92 x 5 mm)

Pas. Atap Asbes Gelombang (2,40 x 0,92 x 5 mm)

Pas. Atap Asbes Gelombang (2,10 x 0,92 x 5 mm)

Pas. Atap Asbes Gelombang (1,80 x 0,92 x 5 mm)

Pas. Atap Asbes Gelombang (2,40 x 1,05 x 4 mm)

Pas. Atap Asbes Gelombang (2,10 x 1,05 x 4 mm)

Pas. Atap Asbes Gelombang (1,80 x 1,05 x 4 mm)

Pas. Atap Asbes Gelombang (2,70 x 1,08 x 6 mm)

Pas. Atap Asbes Gelombang (2,40 x 1,08 x 6 mm)

Pas. Atap Asbes Gelombang (2,10 x 1,08 x 6 mm)

Pas. Atap Asbes Gelombang (1,80 x 1,08 x 6 mm)

Page 112: Daftar Analisa Pu 2013

1 2 3 4 5 6 7

20 Pas. Bubung/Nok stel gelombang 1,05 m PPA 6 23 1 M' #REF! #REF! #REF!

21 Pas. Bubung/Nok stel gelombang 1,08 m PPA 6 24 1 M' #REF! #REF! #REF!

22 Pas. Nok Paten 0,92 m PPA 6 25 1 M' #REF! #REF! #REF!

23 Pas. Nok Paten 1,05 m PPA 6 26 1 M' #REF! #REF! #REF!

24 Pas. Nok Paten 1,08 m PPA 6 27 1 M' #REF! #REF! #REF!

25 Pas. Nok stel rata 0,92 m PPA 6 28 1 M' #REF! #REF! #REF!

26 Pas. Nok stel rata 1,05 m PPA 6 29 1 M' #REF! #REF! #REF!

27 Pas. Atap Genteng Beton PPA 6 30 1 89,337.00 27,100.00 116,437.00

28 Pas. Atap Genteng Aspal PPA 6 31 1 241,454.50 46,330.00 287,784.50

29 Pas. Atap Genteng Metal/Multi roof PPA 6 32 1 91,500.00 27,100.00 118,600.00

30 Pas. Atap Sirap PPA 6 33 1 65,580.00 41,000.00 106,580.00

31 Pas. Nok genteng Beton PPA 6 34 1 M' 52,060.20 54,200.00 106,260.20

32 Pas. Nok genteng Aspal PPA 6 35 1 M' 83,510.07 37,725.00 121,235.07

33 Pas. Nok genteng Metal PPA 6 36 1 M' 46,199.00 36,700.00 82,899.00

34 Pas. Nok genteng Sirap PPA 6 37 1 M' 60,013.36 37,725.00 97,738.36

35 Pas. Atap Seng Gelombang PPA 6 38 1 55,350.20 16,260.00 71,610.20

36 Pas. Nok Atap seng gelombang PPA 6 39 1 M' 23,842.60 19,730.00 43,572.60

37 Pas. Atap Alluminium PPA 6 40 1 103,699.60 20,230.00 123,929.60

38 Pas. Nok Alluminium PPA 6 41 1 M' 58,689.20 19,600.00 78,289.20

39 Pas. Alluminium foil / sisalation PPA 6 42 1 38,850.00 17,600.00 56,450.00

I. PEKERJAAN LANGIT LANGIT

Pas. Langit2 Asbes (1 x 1) m tbl.6 mm PLL 6 1 1 19,593.00 13,420.00 33,013.00

2 Pas. Langit2 Asbes (1 x 1) m tbl.5 mm PLL 6 2 1 103,425.00 22,920.00 126,345.00

3 Pas. Langit2 Asbes (1 x 1) m tbl.4 mm PLL 6 3 1 99,951.00 19,100.00 119,051.00

4 Pas. Langit2 Asbes (1 x 1) m tbl.3,5 mm PLL 6 4 1 103,380.00 19,100.00 122,480.00

5 Pas. Langit2 Akustik (30 x 30) cm PLL 6 5 1 26,948.25 19,100.00 46,048.25

6 Pas. Langit2 Akustik (30 x 60) cm PLL 6 6 1 102,467.85 152,800.00 255,267.85

7 Pas. Langit2 Akustik (60 x 120) cm PLL 6 7 1 28,913.50 18,500.00 47,413.50

8 Pas. Langit2 Plywood (30 x 60) cm t.4 mm PLL 6 8 1 15,690.00 11,460.00 27,150.00

9 Pas. Langit2 Plywood (30 x 60) cm t.6 mm PLL 6 9 1 105,501.00 95,500.00 201,001.00

10 Pas. Langit2 Plywood (60 x 120) cm t.4 mm PLL 6 10 1 22,239.00 9,600.00 31,839.00

11 Pas. Langit2 Plywood (60 x 120) cm t.6 mm PLL 6 11 1 #REF! #REF! #REF!

12 Pas. Langit2 Teakwood (30 x 60) cm t.4 mm PLL 6 12 1 #REF! #REF! #REF!

13 Pas. Langit2 Teakwood (60 x 120) cm 4 mm PLL 6 13 1 #REF! #REF! #REF!

14 Pas. Langit2 Kayu Jati PLL 6 14 1 #REF! #REF! #REF!

15 Pas. Langit2 Papan Rider PLL 6 16 1 #REF! #REF! #REF!

16 Pas. Langit2 Soft board PLL 6 17 1 #REF! #REF! #REF!

Page 113: Daftar Analisa Pu 2013

1 2 3 4 5 6 7

17 PLL 6 18 1 #REF! #REF! #REF!

18 Pas. List Langit2 Kayu Profil 3" PLL 6 19 1 M' #REF! #REF! #REF!

19 PLL 6 20 1 #REF! #REF! #REF!

20 PLL 6 21 1 #REF! #REF! #REF!

21 PLL 6 22 1 #REF! #REF! #REF!

22 PLL 6 23 1 #REF! #REF! #REF!

23 Pas. Langit2 Gypsum Board, tebal 9 mm PLL 6 24 1 #REF! #REF! #REF!

24 Pas. Langit2 Gypsum Board, tebal 6 mm PLL 6 24A 1 #REF! #REF! #REF!

25 Pas. Langit2 Gypsum Board, tebal 12 mm PLL 6 24B 1 #REF! #REF! #REF!

J. PEKERJAAN SANITASI

1 Kloset Duduk / monoblok PS 6 1 1 Bh 1,749,000.00 430,000.00 2,179,000.00

2 Kloset Jongkok Porselen PS 6 2 1 Bh 177,022.50 260,000.00 437,022.50

3 Kloset Jongkok Teraso PS 6 3 1 Bh #REF! #REF! #REF!

4 Urinoir PS 6 4 1 Bh 975,232.50 196,000.00 1,171,232.50

5 Washtafel PS 6 5 1 Bh 597,232.50 261,500.00 858,732.50

6 PS 6 6 1 Bh #REF! #REF! #REF!

7 PS 6 7 1 Bh 219,480.00 205,940.00 425,420.00

8 PS 6 8 1 Bh 495,427.00 588,000.00 1,083,427.00

9 Bak Kift Porselen PS 6 9 1 Bh #REF! #REF! #REF!

10 PS 6 10 1 Bh #REF! #REF! #REF!

11 PS 6 11 1 Bh 490,974.40 864,000.00 1,354,974.40

12 PS 6 15 1 M' #REF! #REF! #REF!

13 Bak Kontrol bt.bata (30 x30) cm, t= 35 cm PS 6 16 1 Bh 239,832.50 343,265.00 583,097.50

14 Bak Kontrol bt.bata (45 x45) cm, t= 50 cm PS 6 17 1 Bh 390,953.00 166,070.00 557,023.00

15 Bak Kontrol bt.bata (60 x60) cm, t= 65 cm PS 6 18 1 Bh 591,891.76 260,220.00 852,111.76

16 PS 6 19 1 M' 19,685.00 16,740.00 36,425.00

17 PS 6 20 1 M' 26,040.00 16,740.00 42,780.00

18 PS 6 21 1 M' 32,550.00 16,740.00 49,290.00

19 PS 6 22 1 M' 48,825.00 28,620.00 77,445.00

20 PS 6 23 1 M' 66,727.50 28,620.00 95,347.50

21 PS 6 24 1 M' #REF! #REF! #REF!

22 PS 6 25 1 M' 6,944.00 9,540.00 16,484.00

23 PS 6 26 1 M' 8,897.00 9,540.00 18,437.00

24 PS 6 27 1 M' 13,888.00 9,540.00 23,428.00

25 PS 6 28 1 M' 16,275.00 9,540.00 25,815.00

26 PS 6 29 1 M' 18,228.00 14,310.00 32,538.00

27 PS 6 30 1 M' 21,700.00 9,540.00 31,240.00

28 PS 6 31 1 M' 27,993.00 21,470.00 49,463.00

29 PS 6 32 1 M' 39,494.00 21,470.00 60,964.00

Pas. Langit2 Akustik 60 x 120 cm + Rangka Alluminium

Pas. Langit2 Asbes (1 x 1) m, tbl.3,2 mm, Rangka Kayu Meranti

Pas. Langit2 Plywood 4 mm + Rangka Kayu Meranti

Pas. Langit2 Akustik (30 x 60) cm + Rangka Kayu Meranti

Pas. Langit2 Akustik (30 x 30) cm + Rangka Kayu Meranti

Bak Mandi Teraso volume 0,3 m³

Bak Mandi Fibreglass volume 0,3 m³

Bak Mandi Batu bata volume 0,3 m³

Bak Beton volume 1 m³

Bak Fibreglass volume 1 m³

Pas. Pipa Beton Ø 30 - 100 cm

Pas. Pipa Galvanis Ø ½"

Pas. Pipa Galvanis Ø ¾"

Pas. Pipa Galvanis Ø 1"

Pas. Pipa Galvanis Ø 1½"

Pas. Pipa Galvanis Ø 2"

Pas. Pipa Galvanis Ø 3"

Pas. Pipa PVC type AW Ø ½"

Pas. Pipa PVC type AW Ø ¾"

Pas. Pipa PVC type AW Ø 1"

Pas. Pipa PVC type AW Ø 1½"

Pas. Pipa PVC type AW Ø 2"

Pas. Pipa PVC type AW Ø 2½"

Pas. Pipa PVC type AW Ø 3"

Pas. Pipa PVC type AW Ø 4"

Page 114: Daftar Analisa Pu 2013

1 2 3 4 5 6 7

30 Bak Cuci Piring Steinlees 2 lobang PS 6 33 1 Bh 816,900.00 35,700.00 852,600.00

31 Bak Cuci Piring Teraso 2 lobang PS 6 34 1 Bh 314,792.50 59,500.00 374,292.50

32 PS 6 35 1 Bh 15,000.00 12,350.00 27,350.00

33 Pas. Floor Drain # 4" PS 6 36 1 Bh 21,180.00 12,350.00 33,530.00

K. PEKERJAAN BESI DAN ALLUMINIUM

1 Pas. Rangka Atap baja PBA 6 1 1 Kg 27,025.00 11,190.00 38,215.00

2 Pas. Pintu besi PBA 6 2 1 27,025.00 11,460.00 38,485.00

3 Pas. Jendela besi PBA 6 3 1 8,590.00 18,110.00 26,700.00

4 Pas. Pintu Gulung besi PBA 6 5 1 1,109,648.50 200,500.00 1,310,148.50

5 Pas. Pintu Lipat besi PBA 6 6 1 #REF! #REF! #REF!

6 Pas. Sunscreen Alluminium PBA 6 7 1 #REF! #REF! #REF!

7 Pas. Rolling Door PBA 6 8 1 #REF! #REF! #REF!

8 Pas. Pintu Alluminium PBA 6 9 1 #REF! #REF! #REF!

9 Pas. Venetions blainds PBA 6 10 1 #REF! #REF! #REF!

10 Pas. Verticals blainds PBA 6 11 1 #REF! #REF! #REF!

11 Pas. Teralis besi PBA 6 12 1 #REF! #REF! #REF!

12 Pas. Kawat Harmonika # 2" PBA 6 13 1 #REF! #REF! #REF!

13 Pas. Kawat Nyamuk PBA 6 14 1 #REF! #REF! #REF!

14 Pas. Kawat Kassa PBA 6 15 1 #REF! #REF! #REF!

15 Pas. Kawat Burung PBA 6 16 1 #REF! #REF! #REF!

16 Pas. Jendela Naco dan Teralis PBA 6 17 1 #REF! #REF! #REF!

17 Pas. Talang Datar, Seng BJLS 35 PBA 6 18 1 M' #REF! #REF! #REF!

18 Pas. Talang Miring, Seng BJLS 35 PBA 6 19 1 M' #REF! #REF! #REF!

19 PBA 6 20 1 M' #REF! #REF! #REF!

20 PBA 6 21 1 M' #REF! #REF! #REF!

L. PEKERJAAN KUNCI DAN KACA

1 Pas. Kunci Tanam Antik PKK 6 1 1 Bh 214,500.00 71,400.00 285,900.00

2 Pas. Kunci Tanam Biasa PKK 6 2 1 Bh 65,000.00 52,350.00 117,350.00

3 Pas. Kunci Tanam Kmr.mandi PKK 6 3 1 Bh 35,300.00 51,175.00 86,475.00

4 Pas. Kunci Silinder PKK 6 4 1 Bh 36,000.00 50,950.00 86,950.00

5 Pas. Engsel Pintu PKK 6 5 1 Bh 14,120.00 17,850.00 31,970.00

6 Pas. Engsel Jendela Kupu-kupu PKK 6 6 1 Bh 8,400.00 11,900.00 20,300.00

7 Pas. Engsel Angin PKK 6 7 1 Bh 7,030.00 24,700.00 31,730.00

8 Pas. Spring Knip PKK 6 8 1 Bh #REF! #REF! #REF!

9 Pas. Kait Angin PKK 6 9 1 Bh 19,120.00 17,850.00 36,970.00

10 Pas. Door closer PKK 6 10 1 Bh 210,000.00 59,500.00 269,500.00

11 Pas. Kunci Selot PKK 6 11 1 Bh 27,230.00 23,800.00 51,030.00

12 Pas. Pegangan/Handle Pintu PKK 6 12 1 Bh 105,000.00 59,500.00 164,500.00

Pas. Kran air ½" atau ¾"

Pas. Talang 1/2 Ø 10 cm, Seng BJLS 35

Pas. Talang 1/2 Ø 10 cm, Seng BJLS 30

Page 115: Daftar Analisa Pu 2013

1 2 3 4 5 6 7

13 Pas. Door stop PKK 6 13 1 Bh 38,120.00 11,900.00 50,020.00

14 Pas. Rel pintu dorong PKK 6 14 1 Bh 160,330.00 71,400.00 231,730.00

15 Pas. Kunci Lemari PKK 6 15 1 12,340.00 29,750.00 42,090.00

16 Pas. Kaca Polos tbl.3 mm PKK 6 16 1 99,000.00 17,850.00 116,850.00

17 Pas. Kaca Polos tbl.5 mm PKK 6 17 1 132,000.00 18,442.50 150,442.50

18 Pas. Kaca Polos tbl.8 mm PKK 6 18 1 284,592.00 19,632.50 304,224.50

19 Pas. Kaca Buram tbl.5 mm PKK 6 19 1 139,466.50 18,442.50 157,909.00

20 Pas. Kaca Cermin tbl.5 mm PKK 6 20 1 176,000.00 18,442.50 194,442.50

21 Pas. Kaca Cermin tbl.8 mm PKK 6 21 1 284,592.00 19,632.50 304,224.50

22 Pas. Kaca Wireglass tbl.5 mm PKK 6 23 1 166,375.00 18,442.50 184,817.50

23 Pas. Kaca Patri tbl.5 mm PKK 6 24 1 186,340.00 29,750.00 216,090.00

23 Pas. Kaca Reyben tbl.5 mm PKK 6 24A 1 137,500.00 18,442.50 155,942.50

M. PEK. PENUTUP DINDING DAN LANTAI

1 Pas. Lantai Ubin Granito 40 x 40 cm PPL 6 9 1 75,137.85 33,980.00 109,117.85

2 Pas. Lantai Ubin Granito 30 x 30 cm PPL 6 10 1 #REF! #REF! #REF!

3 Pas. Lantai Ubin Terralux Marmar 60/60 cm PPL 6 13 1 #REF! #REF! #REF!

4 Pas. Lantai Ubin Terralux Marmar 40/40 cm PPL 6 14 1 #REF! #REF! #REF!

5 Pas. Lantai Ubin Terralux Marmar 30/30 cm PPL 6 15 1 #REF! #REF! #REF!

6 Pas. Plint Ubin Granito 10 x 40 cm PPL 6 24 1 M' #REF! #REF! #REF!

7 Pas. Plint Ubin Granito 10 x 30 cm PPL 6 25 1 M' #REF! #REF! #REF!

8 Pas. Plint Terralux Marmar 10 x 60 cm PPL 6 28 1 M' #REF! #REF! #REF!

9 Pas. Plint Terralux Marmar 10 x 40 cm PPL 6 29 1 M' 304,590.45 33,980.00 338,570.45

10 Pas. Plint Terralux Marmar 10 x 30 cm PPL 6 30 1 M' 335,516.45 35,230.00 370,746.45

11 Pas. Lantai Keramik Artistik 10 x 20 cm PPL 6 34 1 #REF! #REF! #REF!

12 Pas. Lantai Keramik Artistik 10 x 10 cm PPL 6 35 1 #REF! #REF! #REF!

13 Pas. Lantai Keramik Artistik 5 x 20 cm PPL 6 36 1 370,465.45 32,520.00 402,985.45

14 Pas. Plint Keramik Artistik 10 x 20 cm PPL 6 37 1 M' 349,011.45 33,980.00 382,991.45

15 Pas. Plint Keramik Artistik 10 x 10 cm PPL 6 38 1 M' 376,349.25 35,230.00 411,579.25

16 Pas. Plint Keramik Artistik 5 x 20 cm PPL 6 39 1 M' #REF! #REF! #REF!

17 Pas. Plint Keramik 10 x 20 cm PPL 6 39A 1 M' #REF! #REF! #REF!

18 Pas. Plint Keramik 10 x 30 cm PPL 6 39B 1 M' #REF! #REF! #REF!

19 Pas. Plint Keramik 10 x 40 cm PPL 6 39C 1 M' #REF! #REF! #REF!

20 Pas. Plint Vynil tanpa adukan PPL 6 41 1 M' #REF! #REF! #REF!

21 Pas. Lantai Keramik 10 x 20 cm PPL 6 42 1 #REF! #REF! #REF!

22 Pas. Lantai Keramik 15 x 15 cm PPL 6 43 1 #REF! #REF! #REF!

23 Pas. Lantai Keramik 20 x 20 cm PPL 6 44 1 #REF! #REF! #REF!

Page 116: Daftar Analisa Pu 2013

1 2 3 4 5 6 7

24 Pas. Lantai Keramik 20 x 25 cm PPL 6 45 1 50,992.03 17,240.00 68,232.03

25 Pas. Lantai Keramik 25 x 25 cm PPL 6 46 1 64,007.03 17,240.00 81,247.03

26 Pas. Lantai Keramik 30 x 30 cm PPL 6 47 1 #REF! #REF! #REF!

27 Pas. Lantai Keramik 30 x 30 cm anti slip PPL 6 48 1 #REF! #REF! #REF!

28 Pas. Lantai Keramik 40 x 40 cm PPL 6 49 1 115,792.03 17,240.00 133,032.03

29 Pas. Lantai Mosaik 30 x 30 cm Ex lokal PPL 6 50 1 83,057.03 17,240.00 100,297.03

30 Pas. Lantai Marmar PPL 6 51 1 64,007.03 17,240.00 81,247.03

31 PPL 6 52 1 #REF! #REF! #REF!

32 PPL 6 53 1 14,705.25 94,850.00 109,555.25

33 Pas. Lantai Karpet Vynil PPL 6 55 1 16,330.65 94,850.00 111,180.65

34 Pas. Lantai Parquet Jati PPL 6 56 1 #REF! #REF! #REF!

35 Pas. Dinding Porselen 11 x 11 cm, putih PPL 6 58 1 99,303.45 94,850.00 194,153.45

36 Pas. Dinding Porselen 11 x 11 cm, warna PPL 6 59 1 88,388.49 94,850.00 183,238.49

37 Pas. Dinding Porselen 15 x 15 cm, putih PPL 6 60 1 #REF! #REF! #REF!

38 Pas. Dinding Porselen 15 x 15 cm, warna PPL 6 61 1 202,747.25 94,850.00 297,597.25

39 Pas. Dinding Keramik artistik 10 x 20 cm PPL 6 64 1 13,197.13 17,240.00 30,437.13

40 Pas. Dinding Keramik artistik 5 x 20 cm PPL 6 65 1 15,831.43 17,240.00 33,071.43

41 Pas. Dinding Keramik 10 x 20 cm PPL 6 66 1 10,787.37 17,240.00 28,027.37

42 Pas. Dinding Keramik 15 x 15 cm PPL 6 67 1 #REF! #REF! #REF!

43 Pas. Dinding Keramik 20 x 20 cm PPL 6 68 1 265,570.83 94,850.00 360,420.83

44 Pas. Dinding Keramik 20 x 25 cm PPL 6 69 1 75,600.00 32,520.00 108,120.00

45 Pas. Dinding Marmar PPL 6 70 1 12,000.00 #REF! #REF!

46 Pas. Dinding Bata pelapis 7 x 3 x 20 cm PPL 6 71 1 0.00 #REF! #REF!

47 Pas. Dinding Batu Poros PPL 6 73 1 0.00 #REF! #REF!

48 Pas. Dinding Batu tempel hitam PPL 6 74 1 5,418.00 5,000.00 10,418.00

49 Pas. Lantai Vynil karet 30 x 30 cm Kls.I PPL 6 75 1 1,908.90 4,950.00 6,858.90

50 Pas. Lantai Vynil karet 30 x 30 cm Kls.II PPL 6 76 1 #REF! #REF! #REF!

51 Pas. Lantai Vynil asbes 30 x 30 cm PPL 6 77 1 1,908.90 4,950.00 6,858.90

52 Pas. Lantai Vynil motif kembang 30 x 30 cm PPL 6 78 1 1,908.90 4,950.00 6,858.90

53 Pas. Wall corverting lbr 50 cm PPL 6 79 1 1,908.90 4,950.00 6,858.90

54 Pas. Plint kayu jati 2 x 10 cm PPL 6 82 1 M' 1,908.90 4,950.00 6,858.90

55 Pas. Plint kayu Meranti Batu 2 x 10 cm PPL 6 82A 1 M' 2,651.25 7,150.00 9,801.25

Pas. Lantai Karpet 100% Wool M²

Pas. Lantai Karpet 80% Wool, 20% Nylon M²

Page 117: Daftar Analisa Pu 2013

1 2 3 4 5 6 7

N. PEKERJAAN PENGECATAN

1 Mengikis/mengerok permukaan cat lama PC 6 1 1 750.00 11,500.00 12,250.00

2PC 6 2 1 514.50 11,500.00 12,014.50

3PC 6 3 1 514.50 11,500.00 12,014.50

4 Menyabun permukaan tembok lama PC 6 4 1 514.50 11,500.00 12,014.50

5 Mendempul/menggosok permukaan kayu PC 6 6 1 1,209.20 11,650.00 12,859.20

6 Mengecat permukaan bidang kayu lama PC 6 7 1 12,296.00 13,825.00 26,121.00

7PC 6 8 1 28,522.50 15,490.00 44,012.50

8PC 6 9 1 21,642.60 11,840.00 33,482.60

9 Pelaburan kayu dengan politur PC 6 11 1 #REF! #REF! #REF!

10 Pelaburan kayu dengan Residu PC 6 12 1 2,695.00 8,100.00 10,795.00

11 Pelaburan bidang kayu dgn vernis PC 6 13 1 9,342.00 30,010.00 39,352.00

12PC 6 14 1 12,092.60 16,520.00 28,612.60

13PC 6 15 1 11,123.00 12,390.00 23,513.00

14 Pas. Wall paper PC 6 19 1 94,200.00 21,970.00 116,170.00

15 Pengecatan permukaan baja dgn menie besi PC 6 20 1 3,685.50 6,700.00 10,385.50

16 Pengecatan permukaan baja dgn cat menie PC 6 21 1 17,322.68 44,475.00 61,797.68

17PC 6 23 1 15,750.00 24,300.00 40,050.00

18PC 6 24 1 14,471.10 170,500.00 184,971.10

19PC 6 25 1 11,655.00 142,000.00 153,655.00

Medan, Maret 2008

DIKETAHUI OLEH : DIBUAT OLEH : TIM TEKNISKepala Dinas Penataan Ruang dan 1. Ir. Jeremias Sinaga, MAP ( ……………. )

Permukiman Prov. Sumatera Utara 2. Ir. Herimas ( ……………. )

3. H. Sugiarto Bharata, ST ( ……………. )

4. H. Ali Muhar, ST ( ……………. )

Ir. H. Syafruddin Siregar, MSi 5. Sakula Karo karo, ST ( ……………. )

Pembina Utama Muda 6. Ebenser Saragih, SE ( ……………. )

NIP. 400025884 7. Sahat Hasudungan, ST ( ……………. )

8. Ir. Tanogara Siahaan ( ……………. )

9. Ali Fauzan, ST ( ……………. )

10. Ir. Naimul Ahmad R. ST ( ……………. )

11. Chandra, ST ( ……………. )

Mencuci bidang permukaan tembok yang pernah di cat

Mengerok karat cat lama permukaan baja dengan cara manual

Pengecatan bidang kayu baru 1 lps plamir, 1lps cat dasar, 2lps cat minyak

Pengecatan bidang kayu baru 1 lps plamir, 1lps cat dasar, 3lps cat minyak

Pengecatan tembok baru ( 1 lapis plamir, 1 lps cat dasar, 2 lps cat penutup )

Pengecatan tembok lama ( 1 lps cat dasar, 2 lps cat penutup )

Pengecatan permukaan baja dgn cat menie besi dgn perancah

Pengecatan permukaan baja lapis seng (galbani), cara manual 1 lapis tbl.200

Pengecatan permukaan baja lapis seng (galbani), cara manual 3 lapis tbl.200