ROLE OF PROGRAM MANAGEMENT CONSULTANT PROVINCIAL ROAD IMPROVEMENT & MAINTENANCE (PRIM) PROGRAM BRIEFING TO THE ASSOCIATION OF CONTRACTORS AND CONSULTANT 30 SEPTEMBER 2013

Upload: indonesia-infrastructure-initiative

Post on 13-Apr-2017

158 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

ROLE OF PROGRAM MANAGEMENT CONSULTANT PROVINCIAL ROAD IMPROVEMENT & MAINTENANCE (PRIM) PROGRAM

BRIEFING TO THE ASSOCIATION OF CONTRACTORS AND CONSULTANT

30 SEPTEMBER 2013

Page 2: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

PERAN KONSULTAN MANAJEMEN PROGRAMPROGRAM MANAGEMENT CONSULTANT (PMC)

PROVINCIAL ROAD IMPROVEMENT & MAINTENANCE (PRIM) PROGRAMBRIEFING KEPADA ASOSIASI PENYEDIA JASA BIDANG KONSTRUKSI

30 SEPTEMBER 2013

Page 3: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

3

Technical Assistance for PRIMTA will be provided by 3 Consultants:•Project Implementation Unit Consultant (PIUC) -

who will support the Program Implementation Unit in NTB•Program Management Consultant (PMC) - who

will support the DGH Technical Team (TT).•Monitoring and Evaluation (M&E) Consultant,

who will review progress and prepare an annual M&E report.

Page 4: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

4

BANTUAN TEKNIK PRIMUntuk Bantuan Teknik akan disiapkan 3 Konsultan

yang meliputi dengan anggaran 100% Hibah AusAID meliputi:•Project Implementation Unit Consultant (PIUC) –

membantu Unit Implementasi Program/Program Implementation Unit dalam hal ini Dinas PU NTB•Program Management Consultant (PMC) –

membantu Tim Teknis Ditjen Bina Marga.•Monitoring and Evaluation (M&E) Consultant-

melakukan evalusi kemajuan kegiatan dan menyiapkan Laporan Tahunan Monitoring dan Evaluasi atas capaian PRIM.

Page 5: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

5

Role of the PMCPRIM has been designed to ensure that the work funded by the AusAID grant is carried out in strict accordance with good practice and the specifications for the works and includes the following categories of work:• Technical Assessment of works carried out under

PRIM• Financial (Procurement) Assessment of the PRIM

contracts• Verification of the defined outputs and outcomes of

PRIM and reporting to the Technical Team in DGH – which will trigger grant payments to the Province.

• Independent assessor (if required) in case of disupute

Page 6: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

6

Tugas PMCPRIM telah di rancang bahwa pekerjaan yang sebagian dibiayai oleh dana Hibah AusAID akan dilaksanakan berdasarkan ketentuan spesifikasi yang menghasilkan hasil kerja yang baik dan dengan kegiatan sebagai berikut:• Melaksanakan pengujian atas hasil pekerjaan PRIM• Melaksanakan pengujian finansial (pengadaan baran

dan jasa) atas kontrak PRIM• Melaksanakan Verifikasi atas output dan outcome serta

melaporkan kepada Tim Teknis Ditjen Bina Marga dan sebagai dasar pembayaran dana hibah ke Provinsi.

• Penguji independen (jika ada) jika terjadi permasalahan

Page 7: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

7

Technical and Procurement AssessmentsTechnical and Procurement Assessment will be carried out for the following:• Contractor implemented packages which include routine

maintenance, backlog and minor works, periodic maintenance and rehabilitation;

• Contractor implemented backlog and minor works packages – anticipated to be contracted in 2014;

• Swakelola implemented ongoing routine maintenance progressively implemented on the provincial road network in NTB.

• Performance of the consultant in supervising the worksThe assessments and verification, are being carried out to oversight the performance of all parties to the grant and to provide recommendations on the verification of milestone grant payments to the DGH Technical Team

Page 8: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

8

Pengujian Teknik dan Pengadaan Barang/Jasa

Pengujian Teknik dan Pengadaan Barang/Jasa akan dilakukan dengan lingkup sebagai berikut:• Hasil pekerjaan Penyedia Jasa yang terkontrak untuk pekerjaan

pemeliharaan rutin, backlog dan pekerjaan minor, pemeliharaan berkala dan rehabilitasi;

• Hasil pekerjaan Penyedia Jasa yang terkontrak untuk pekerjaan backlog dan pekerjaan minor yang dilaksankan pada tahun 2014;

• Hasil pekerjaan Swakelola untuk Pemeliharaan Rutin yang akan meningkat panjang penanganan di jaringan jalan Provinsi NTB.

• Evaluasi Kinerja atas hasil pekerjaan Konsultan SupervisiPengujian dan Verifikasi akan dilakukan untuk pengawasan kinerja atas semua pihak atas kegiatan hibah dan memberikan rekomendasi atas hasil verifikasi kepada Tim Teknis dan dasar pembayaran dana hibah.

Page 9: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

9

Procurement AssessmentsAn assessment will be carried out for all contracts on the compliance with procurement process in accordance with current regulations and will include:• Available Integrity Pact signed by PPK, Service

Procurement and Provider Service Unit;• Available Minutes of Work Clarification;• Available Minutes of Bidding Result Evaluation and

Report on Bidding Evaluation Result;• Announcement of Bidding Winner; and• Document on Settlement and Response to

Protest/Appeal Protest.

Page 10: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

10

Pengujian Pengdaan Barang/Jasa

Pengujian akan dilakukan atas semua kontrak untuk memastikan bahwa proses pengadaan barang/jasa sesuai dengan ketentuan yang meliputi :• Tersedianya Pakta Integritas yang sudah

ditandatangani PPK, Panitia Lelang dan penyedia barang/jasa;

• Tersedianya Notulen atas permintaan klarifikasi dokumen lelang;

• Tersedianya Berita Acara Hasil Pelelangan, Laporan Hasil Evaluasi Pelelangan dan;

• Telah dilaksankan Pengumuman atas Pemenang Lelang; dan

• Dokumen Sanggahan telah dijawab dan selesai.

Page 11: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

11

Purpose of the Technical AssessmentsThe PMC will carry out site reviews and material testing to determine: • If the work is being carried out in accordance with the

bidding documents / agreed programs and to determine where there are problems(Note if the work is sub-standard either in quality or quantity it will be found out)• To provide recommendations on corrective actions that will

achieve contractual standards and achieve verification. (Note PMC is not just a policeman but is trying to help achieve a successful outcome)• To check the adequacy of all the processes employed

during project implementation by all parties including PIU, PIUC, Contractors and Supervision Consultants

Page 12: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

12

Tujuan Pengujian Teknik

Konsultan PMC akan melakukan evaluasi di lapngan dan pengujian material untuk memastikan bahwa:• Hasil pekerjaan sudah sesuai dengan dokumen kontrak/program

yang telah disetujui dan memastikan bahwa hasil pekerjaan tidak ada masalah(Catatan: apakah diketemukan/ada hasil pekerjaan yang ternyata dibawah standard spesifikasi dalam hal kualitas dan atau kuantitas)• Menyiapkan rekomendasi atas hasil pekerjaan yang memerlukan

tindakan korektif/perbaikan agar supaya hasil pekerjaan dapat memenuhi spesifikasi dan kontrak dan bisa lulus verifikasi. (Catatan : Konsultan PMC tidak hanya sebagai polisi namun juga akan membantu agar tujuan outcome bisa tercapai)• Melakukan checking atas pemenuhan semua proses yang

digunakan dalam pelaksanaan oleh semua pihak termasuk PIU, PIUC, penyedia jasa dan konsultan supervisi

Page 13: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

13

Purpose of the VerificationThe PMC with the DGH Technical Team will verify if the following key areas have been achieved: • Governance components including:– Improved planning, programming introduced for maintenance;– APBD Budget allocated for the works– Details of the program are on the NTB website – Training program for stakeholders including PIU, Contractors and Consultants has

been carried out.• SOPs prepared and implemented for the RTTF• Physical works either contracted or swakelola have been completed

and achieved verifiable quality. • The achievement of verification will be determine the grant payments

to NTB provincial government(Note the grant is designed to pay for 40% of verified works. If works

do not meet the required standard then it will affect the grant payments to NTB – and this in turn will almost certainly affect payments of measured works)

Page 14: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

14

Tujuan Verifikasi atas Hasil Pekerjaan

Konsultan PMC bersma Tim Teknis Ditjen Bina Marga akan melaksanakan Verifikasi Hasil Pekerjaan yang harus dicapai dan mencakup: • Aspek Governance meliputi:– Peningkatan atas pelaksanaan perencanaan, program untuk pemeliharaan jalan;– Telah dialokasi dana APBD untuk kegiatan PRIM– Program yang terinci telah diunggah di website Provinsi NTB– Program Pelatihan untuk pemegang kepentingan termasuk PIU, penyedia

barang/jasa telah dilaksanakan.• SOPs telah disiapkan dan dilaksankan oleh FLLAJ• Pekerjaan Fisik yang di kontrakkan dan atau swakeloal telah selesai

dilaksanakan dan memenuhi verifikasi atas kualitas. • Pencapaian verifikasi akan menentukan pembayaran hibah kepada

pemerintah provinsi NTB(Catatan: hibah ini dirancang untuk penggantian dengan nilai sampai dengan 40% atas pekerjaan yang lulus verifikasi. Jika hasil pekerjaan tidak memenuhi standar yang disyaratkan maka hal itu akan mempengaruhi pembayaran hibah kepada NTB- dan ini pada gilirannya akan hampir pasti mempengaruhi pembayaran atas hasil volume yang dikerjakan)

Page 15: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

15

Timing of Assessments and Verification• It is anticipated that the verification will be undertaken

predominantly during four (4) separate phases. – End of 2013– May 2014– October 2014– May 2015

• Prior to verification technical assessments will be carried out over a period of approximately 2 months.• The assessments will recommend to the PIU / PIUC where

improvements are needed to be made to achieve verification• This is intended to allow the corrections to be undertaken to

achieve verification• The PMC will also undertake oversight of routine works and

carry out periodic site visits to the contracts throughout the implementation of PRIM

Page 16: Ind ii prim-briefing to association of contractors et al 25092013 pm-crv1 presentation 3 pmc

16

Jadual Waktu Pengujian dan Verifikasi

• Verifikasi direncanakan akan dilakukan 4 tahap sebagai berikut:– Akhir 2013– Mei 2014– Oktober 2014– Mei 2015

• Sebelum Verifikasi dilaksanakan, pengujian teknik akan dilakukan paling lambat 2 bulan sebelum pelakasanaan verifikasi• Hasil pengujian teknik akan memberikan rekomendasi kepada

PIU/PIUC atas hasil pekerjaan yang perlu diperbaiki sehingga dapat dicapai persyaratan untuk lulus verifikasi.• Hal tersebut diatas mempunyai tujuan agar penyedia jasa dapat

melakukan perbaikan yang diperlukan agar verifikasi dapat dicapai• Konsultan PMC akan melakukan pengawasan atas pelaksanaan

pemeliharaan rutin dan melakukan kunjungan lapangan secara periodik atas semua paket pekerjaan PRIM yang terkontrak.