total kehilangan prategang (tl ) tl= tet +cr + sh=33 +26,75 + 47,3 = 107,5 mpa
DESCRIPTION
Total Kehilangan Prategang (TL ) TL= TET +CR + SH=33 +26,75 + 47,3 = 107,5 Mpa fst (1095 ) (belum termasuk akbt beban sediri WG+ WS ) = fst (30 ) - TL = 1111 Mpa - 107,5 Mpa = 1003,5 Mpa Ft (1095 ) = 1003,5 x 1975 = 1981912,5 N = 1981, 912 KN - PowerPoint PPT PresentationTRANSCRIPT
Total Kehilangan Prategang (TL )
TL= TET +CR + SH=33 +26,75 + 47,3 = 107,5 Mpa
fst (1095 ) (belum termasuk akbt beban sediri WG+ WS ) = fst (30 ) - TL
= 1111 Mpa - 107,5 Mpa = 1003,5 Mpa
Ft (1095 ) = 1003,5 x 1975 = 1981912,5 N = 1981, 912 KN
fst (0) = 0,75 x 1862 Mpa = 1397 Mpa
Ft (0) = 1397 x1975 = 2759075 N = 2759, 075 KN
Terjadi Penurunan :
fst = 1397 - 1003 ,5 = 393, 5 Mpa
F = 2759,075 - 1981,912 = 777,163 KN
Sarat Kehilangan fst maksimal = 345 Mpa (jg dipakai ) ( ACI-ASCE}
Pembatasan Kehilangan Maksimum ( Komisi ACI - ASCE )
Kehilangan Maksimum ( Mpa )
Jenis Strand Beton normal Beton ringan
Strand stress- relieved 345 380
Strand relaksasi- rendah 275 310