RENCANA ANGGRAN BIAYAPENGADAAN JASA KONSULTASI
PEKERJAAN : PENYUSUNAN MASTERPLAN AIR BERSIH KOTA LHOKSEUMAWEBADAN PERENCANAAN PEMBANGUNAN DAERAH KOTA LHOKSEUMAWE
TAHUN ANGGARAN : 2013
No. URAIAN VOLUME SATUANHARGA JUMLAH HARGA
SATUAN (Rp) (Rp)I BIAYA LANGSUNG PERSONIL A TENAGA PROFESIONAL
1. Team Leader (Teknik Penyehatan Lingkungan) 1 Org x 4 Bln 4 OB 5,000,000.00 20,000,000.00 2. Ahli Teknik Hidrolika/Hidrologi 1 Org x 3 Bln 3 OB 4,000,000.00 12,000,000.00 3. Ahli Geologi 1 Org x 3 Bln 3 OB 4,000,000.00 12,000,000.00 4. Ahli Sipil Struktur 1 Org x 3 Bln 3 OB 4,000,000.00 12,000,000.00 5. Ahli Planologi 1 Org x 3 Bln 3 OB 4,000,000.00 12,000,000.00 6. Asisten Ahli 4 Org x 4 Bln 16 OB 3,500,000.00 56,000,000.00
124,000,000.00
B TENAGA PENDUKUNG SURVEYOR1. Chief Surveyor 1 Org x 2 Bln 2 OB 2,800,000.00 5,600,000.00 2. Surveyor 4 Org x 2 Bln 8 OB 1,800,000.00 14,400,000.00
20,000,000.00 C TENAGA PENDUKUNG
1. Operator Komputer 2 Org x 4 Bln 8 OB 1,200,000.00 9,600,000.00 2. Drafman (CAD Operator) 1 Org x 4 Bln 4 OB 2,000,000.00 8,000,000.00 3. Sekretaris 1 Org x 4 Bln 4 OB 1,500,000.00 6,000,000.00 4. Office Boy 1 Org x 4 Bln 4 OB 950,000.00 3,800,000.00
27,400,000.00
Sub Total I 171,400,000.00
II BIAYA LANGSUNG NON PERSONILA PERLENGKAPAN PENGUKURAN
1. Sewa Water Pass 1 Set x 40 Hr 40 Set/Bln 200,000.00 8,000,000.00 2. Sewa Theodolite 1 Set x 40 Hr 40 Set/Bln 150,000.00 6,000,000.00
14,000,000.00
B PERALATAN KANTOR1. Sewa Komputer & Printer 4 Unit x 4 Bln 16 Unit/Bln 300,000.00 4,800,000.00 2. ATK/Fhotocopy 1 Ls 3,000,000.00 3,000,000.00 3. Sewa Kantor 4 Bln4. Komunikasi/Telepon 4 Bln 1,900,000.00 7,600,000.00 5. Perlengkapan Kantor 1 Ls 5,000,000.00 5,000,000.00
20,400,000.00
C OPERASIONAL LAPANGAN 1. Sewa Kendaraan Roda 4 1 Unit x 50 Hr 50 Hari 400,000.00 20,000,000.00 2. Sewa Kendaraan Roda 2 2 Unit x 95 Hr 190 Hari 100,000.00 19,000,000.00
39,000,000.00
D BIAYA LABORATORIUM 1. Biaya Pemeriksaan Laboratorium 1 Ls 2,750,000.00 2,750,000.00
2,750,000.00
E BIAYA LAPORAN 1. Seminar dan Laporan Pendahuluan 1 Ls 400,000.00 400,000.00 2. Seminar dan Laporan Draf Akhir 1 Ls 500,000.00 500,000.00 3. Seminar dan Laporan Akhir 1 Ls 770,000.00 770,000.00 4. Album Peta A3 dan Hasil Survei 1 Ls 8,000,000.00 8,000,000.00
9,670,000.00
Sub Total II 85,820,000.00
TOTAL (Sub Tola I + II) 257,220,000.00 PPn 10% 25,722,000.00 TOTAL 282,942,000.00
Dibulatkan 282,942,000.00
Terbilang : Dua Ratus Delapan Puluh Dua Juta Sembilan Ratus Empat Puluh Dua Ribu Rupiah,-
Lhokseumawe, 14 Agustus 2013Penawar
CV. HEXAGON RAYA CONSULTANT
Ir. Cut YusnizarDirektris
REKAPITULASI RENCANA ANGGRAN BIAYA (RAB)RENCANA ANGGRAN BIAYA
PENGADAAN JASA KONSULTASI
PEKERJAAN : PENYUSUNAN MASTERPLAN AIR BERSIH KOTA LHOKSEUMAWEBADAN PERENCANAAN PEMBANGUNAN DAERAH KOTA LHOKSEUMAWE
TAHUN ANGGARAN : 2013
No. URAIANJUMLAH HARGA
(Rp)I BIAYA LANGSUNG PERSONIL
A TENAGA PROFESIONAL 124,000,000.00 B TENAGA PENDUKUNG SURVEYOR 20,000,000.00 C TENAGA PENDUKUNG 27,400,000.00
Sub Total I 171,400,000.00
II BIAYA LANGSUNG NON PERSONIL
A PERLENGKAPAN PENGUKURAN 14,000,000.00 B PERALATAN KANTOR 20,400,000.00 C OPERASIONAL LAPANGAN 39,000,000.00 D BIAYA LABORATORIUM 2,750,000.00 E BIAYA LAPORAN 9,670,000.00
Sub Total II 85,820,000.00
TOTAL (Sub Tola I + II) 257,220,000.00 PPn 10% 25,722,000.00 TOTAL 282,942,000.00
Dibulatkan 282,942,000.00
Terbilang : Dua Ratus Delapan Puluh Dua Juta Sembilan Ratus Empat Puluh Dua Ribu Rupiah,-
Lhokseumawe, 14 Agustus 2013Penawar
CV. HEXAGON RAYA CONSULTANT
Ir. Cut YusnizarDirektris