PERUSAHAAN : stance construction consultant DIREKTUR : Kristianus Behar, ST JABATAN : Engineer Engineer - stance construction consultant NIP : Perwakilan Sumba Barat CONSULTAN TEKNIK : Engineering Consultan ALAMAT : Jln. Veteran No. 05, Telp.(0387) - Waikabubak - Sumba Bar TELEPON : (0387) - RPOGRAM : PROGRAM KONSERVASI KEANEKARAGAMAN HAYATI DAN PERLINDUNGAN KEGIATAN : PENGADAAN SARANA PERKANTORAN BALAI PAKET PEKERJAAN : PEMBANGUNAN LANJUTAN KANTOR STPN 2 LOKASI : DESA LEWA PAKU - KEC. LEWA - KABUPATEN SUMBA TIMUR NILAI FISIK : Rp - TAHUN ANGGARAN : 2014 TAHUN ANGGARAN 2014 JENIS PEKERJAAN REDESIGN PERENCANA KOTA : WAIKABUBAK Waikabubak,....................2014 LOAKSI PROYEK : Jln. Adyaksa Km.03 - Waikabubak - Sumba Barat, Nusa Teng SUMBER DANA : APBN Kecamatan : Kabupaten/Kota : INSTANSI : KEMENTERIAN KEHUTANAN DIREKTORAT JENDERAL PERLINDUNGAN HUTAN DAN KONSERVASI ALA BALAI TAMAN NASIONAL MANUPEU TANAH DARU DIREKTORAT JENDERAL PERLINDUNGAN HUTAN DAN KONSERVASI ALA ALSINTAN : Jln. Adyaksa Km.03 PO.Box 103 (0387) 22286 Fax. 22163 Wai NAMA PPK : Claudius Herry, ST NIP : Inspector NIP 19730109 199903 1 002 PPK : PEJABAT PEMBUAT KOMITMEN PENGADAAN SARANA PERKANTORAN BAL ALAMAT PPK : PA. : KUASA PENGGUNA ANGARAN BALAI TAMAN NASIONAL MANUPEU TANAH DARU TAMAN NASIONAL MANUPEU TANAH DARU KEPALA : Bp. Marthen Bili Lende NIP : Pemilik Tim Teknis Kabid Cipta Karya DINAS PEKERJAAN UMUM PERTAMBANGAN DAN ENERGI KABUPATEN SUMBA BARAT KABID CK : YEANETTE ERNYATI KONDI, ST. NIP : NIP.19780102 200312 2 011 KEPALA DINAS PEKERJAAN UMUM PERTAMBANGAN DAN ENERGI KABUPATEN SUMBA BARAT KADIS PU. : Ir. FREDRIK GAH NIP : NIP.19650216 199403 1 004 PEJABAT PEMBUAT KOMITMEN KEGIATAN PENGADAAN SARANA PERK KEMENTERIAN KEHUTANAN - Jln. Adyaksa Km.03 PO.Box 103 22163 Waikabubak 87212 - Sumba Barat, Nusa Tenggara Timur

Upload: claudius-herry

Post on 27-Dec-2015

322 views

Category:

Documents


27 download

DESCRIPTION

Berikut RAB dari perencanaan Gudang milik perseorangan dengan struktur beton di Sumba Barat

TRANSCRIPT

Page 1: RAB Gudang Bahan Pangan

PERUSAHAAN : stance construction consultantDIREKTUR : Kristianus Behar, ST

JABATAN : Engineer Engineer - stance construction consultantNIP : Perwakilan Sumba Barat

CONSULTAN TEKNIK : Engineering ConsultanALAMAT : Jln. Veteran No. 05, Telp.(0387) - Waikabubak - Sumba Barat

TELEPON : (0387) -

RPOGRAM : PROGRAM KONSERVASI KEANEKARAGAMAN HAYATI DAN PERLINDUNGAN HUTANKEGIATAN : PENGADAAN SARANA PERKANTORAN BALAI

PAKET PEKERJAAN : PEMBANGUNAN LANJUTAN KANTOR STPN 2LOKASI : DESA LEWA PAKU - KEC. LEWA - KABUPATEN SUMBA TIMUR

NILAI FISIK : Rp -

TAHUN ANGGARAN : 2014 TAHUN ANGGARAN 2014JENIS PEKERJAAN REDESIGN PERENCANA

KOTA : WAIKABUBAK Waikabubak,....................2014LOAKSI PROYEK : Jln. Adyaksa Km.03 - Waikabubak - Sumba Barat, Nusa Tenggara Timur

SUMBER DANA : APBNKecamatan :

Kabupaten/Kota :INSTANSI : KEMENTERIAN KEHUTANAN

DIREKTORAT JENDERAL PERLINDUNGAN HUTAN DAN KONSERVASI ALAMBALAI TAMAN NASIONAL MANUPEU TANAH DARUDIREKTORAT JENDERAL PERLINDUNGAN HUTAN DAN KONSERVASI ALAM KEMENTERIAN KEHUTANAN BALAI TAMAN NASIONAL MANUPEU TANAH DARU

ALSINTAN : Jln. Adyaksa Km.03 PO.Box 103 (0387) 22286 Fax. 22163 Waikabubak 87212 - Sumba Barat, Nusa Tenggara TimurNAMA PPK : Claudius Herry, ST

NIP : Inspector NIP 19730109 199903 1 002

PPK : PEJABAT PEMBUAT KOMITMEN PENGADAAN SARANA PERKANTORAN BALAI

ALAMAT PPK :

PA. : KUASA PENGGUNA ANGARANBALAI TAMAN NASIONAL MANUPEU TANAH DARUTAMAN NASIONAL MANUPEU TANAH DARU

KEPALA : Bp. Marthen Bili LendeNIP : Pemilik

Tim Teknis Kabid Cipta KaryaDINAS PEKERJAAN UMUM PERTAMBANGAN DAN ENERGIKABUPATEN SUMBA BARAT

KABID CK : YEANETTE ERNYATI KONDI, ST.NIP : NIP.19780102 200312 2 011

KEPALA DINAS PEKERJAAN UMUM PERTAMBANGAN DAN ENERGIKABUPATEN SUMBA BARAT

KADIS PU. : Ir. FREDRIK GAHNIP : NIP.19650216 199403 1 004

PEJABAT PEMBUAT KOMITMEN KEGIATAN PENGADAAN SARANA PERKANTORAN BALAI d/a KEMENTERIAN KEHUTANAN - Jln. Adyaksa Km.03 PO.Box 103 (0387) 22286 Fax. 22163 Waikabubak 87212 - Sumba Barat, Nusa Tenggara Timur

Page 2: RAB Gudang Bahan Pangan

PROGRAM KONSERVASI KEANEKARAGAMAN HAYATI DAN PERLINDUNGAN HUTAN

DIREKTORAT JENDERAL PERLINDUNGAN HUTAN DAN KONSERVASI ALAM KEMENTERIAN KEHUTANAN BALAI TAMAN NASIONAL MANUPEU TANAH DARUJln. Adyaksa Km.03 PO.Box 103 (0387) 22286 Fax. 22163 Waikabubak 87212 - Sumba Barat, Nusa Tenggara Timur

PEJABAT PEMBUAT KOMITMEN PENGADAAN SARANA PERKANTORAN BALAI

PEJABAT PEMBUAT KOMITMEN KEGIATAN PENGADAAN SARANA PERKANTORAN BALAI d/a KEMENTERIAN KEHUTANAN - Jln. Adyaksa Km.03 PO.Box 103 (0387) 22286

Page 3: RAB Gudang Bahan Pangan

Halaman : 3

DAFTAR HARGA SATUAN UPAH,BAHAN DAN SEWA PERALATANPROGRAM :

KEGIATAN :

PEKERJAAN :

LOKASI :

SUMBER DANA :

TAHUN ANGGARAN :

No Tenaga Kerja Satuan Total Harga

1 Pekerja Hari 37,100.00

2 Mandor Hari 69,100.00

3 Tukang Hari 61,600.00

4 Kepala Tukang Hari 74,600.00

5 Senior Instalatur Hari 70,000.00

6 Alat Bantu Set 50,000.00

No Bahan/Material Satuan

Harga Jarak Ongkos

Di Angkut Angkut Total Harga Quary Rata - Rata per satuan

Rp Rp

1 Batu Karang 129,000.00 12.00 Km 58,936.57 187,936.57

2 Sirtu ( Urugan pilihan ) 110,000.00 12.00 Km 44,115.47 154,115.47

3 Urugan Tanah Timbunan Biasa 80,000.00 1.00 Km 15,587.38 95,587.38

4 Urugan Tanah Humus 50,000.00 15.00 Km 46,420.40 96,420.40

5 Pasir Urug 50,000.00 25.00 Km 96,800.30 146,800.30

6 Pasir Pasang/beton 220,000.00 25.00 Km 96,800.30 316,800.30

7 Batu Potong Bh 1,800.00 4.00 Km 248.43 2,048.43

8 Batu Kerikil Pecah 2/3 - 1/2 600,000.00 18.00 Km 79,069.20 679,069.20

9 Batu Kerikil Pecah 450,000.00 18.00 Km 79,069.20 529,069.20

10 Batu Alam Bertextur (10 x 20) M2 115,000.00 115,000.00

11 Kayu Balok Kls II 4,100,000.00 10.00 Km 78,976.27 4,178,976.27

12 Papan Begesting/kayu perancah 1,400,000.00 12.00 Km 78,976.27 1,478,976.27

13 Papan Kls II 4,200,000.00 10.00 Km 78,976.27 4,278,976.27

14 Kayu Usuk 5/7 cm Klas II 4,500,000.00 10.00 Km 78,976.27 4,578,976.27

15 Dolken Kayu Bulat Btg 10,000.00 10,000.00

16 Semen 50 kg Zak 75,000.00 3.00 Km 1,330.49 76,330.49

17 Benang Isolasi Bh 10,000.00 10,000.00

18 Benang Nilon Roll 10,000.00 10,000.00

19 Floor Drain Bh 20,000.00 20,000.00

20 Fitting Tempel Bh 17,500.00 17,500.00

21 Isolasi Bh 10,000.00 10,000.00

22 Isolator Cap Bh 3,500.00 3,500.00

23 Isolator Kecil Bh 2,000.00 2,000.00

24 Kabel Eterna 2x1,5 mm M1 15,000.00 15,000.00

25 Kabel Eterna 2x2,5 mm M1 17,500.00 17,500.00

26 T dos Bh 5,000.00 5,000.00

27 Amplas Lbr 4,500.00 4,500.00

28 Bak Cuci Stailess Steel Bh 425,000.00 425,000.00

29 Bak Mandi Fiber Glass 120 ltr.(Kotak) Bh 260,000.00 260,000.00

30 Besi Beton Polos Kg 14,000.00 14,000.00

31 Besi Beton Ulir Kg 17,000.00 17,000.00

32 M' 10,500.00 10,500.00

33 M' 3,200.00 3,200.00

34 Besi Siku 5cm x 5cm x 5mm M1 25,000.00 25,000.00

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

M3

Besi Beton Ø 12mm

Besi Beton Ø 6mm

Page 4: RAB Gudang Bahan Pangan

Halaman : 4

No Bahan/Material Satuan

Harga Jarak Ongkos

Di Angkut Angkut Total Harga Quary Rata - Rata per satuan

Rp Rp

35 Besi Siku 7cm x 7cm x 7mm M1 35,000.00 35,000.00

36 Cat Kilat/Warna (kayu-besi) Kg 50,000.00 50,000.00

37 Cat Menie/cat dasar (kayu-besi) Kg 30,000.00 30,000.00

38 Cat Tembok Kualitas "A" Kg 35,000.00 35,000.00

Page 5: RAB Gudang Bahan Pangan

Halaman : 5

No Bahan/Material Satuan

Harga Jarak Ongkos

Di Angkut Angkut Total Harga Quary Rata - Rata per satuan

Rp Rp

39 Closed Jongkok Bh 200,000.00 200,000.00

40 Closed Duduk Bh 600,000.00 600,000.00

41 Dumpul Kg 30,000.00 30,000.00

42 Exhaust fan Bh 800,000.00 800,000.00

43 Elbow/T 1/2" Bh 6,000.00 6,000.00

44 Engsel kuning jendela Bh 17,500.00 17,500.00

45 Engsel kuning pintu Bh 25,000.00 25,000.00

46 Gerendel Jendela Bh 15,000.00 15,000.00

47 Grendel Pintu Bh 17,500.00 17,500.00

48 Gagang/Handle Pintu Bh 250,000.00 250,000.00

49 Gedek Isi Lbr 30,000.00 30,000.00

50 Kusen Aluminium M1 185,000.00 185,000.00

51 Rangka Pintu & Jendela Aluminium M1 60,000.00 60,000.00

52 Main Truss C.75. - 75 0,8mm M1 22,000.00 22,000.00

53 Roof Batten/Reng (41.35. 0.45mm) M1 17,000.00 17,000.00

54 Bh 500.00 500.00

55 Bh 400.00 400.00

56 Dynabolt ǿ 12 x 120mm Bh 7,000.00 7,000.00

57 Atap Genteng Metal No 0.35 M2 105,000.00 105,000.00

58 Bubungan Genteng Metal No 0,30 M1 35,000.00 35,000.00

59 Jurai Multi Roof M1 16,000.00 16,000.00

60 Gypsum Board 9 mm Lbr 110,000.00 110,000.00

61 Calsiboard 6 mm M2 85,000.00 85,000.00

62 Rangka Plafon Metal M1 17,000.00 17,000.00

63 Baut/Sekrup Kg 35,000.00 35,000.00

64 Paku Sekrup Ø 4mm - 50mm Bj 1,000.00 1,000.00

65 Kaca Nako + Rangka 5 Daun Set 176,785.00 176,785.00

66 Kaca Nako + Rangka 7 Daun Set 247,500.00 247,500.00

67 Kaca Nako + Rangka 8 Daun Set 282,856.00 282,856.00

68 Kaca Polos 3 mm M2 175,000.00 175,000.00

69 Kaca Polos 5 mm M2 200,000.00 200,000.00

70 Kaca Reyben 5mm M2 250,000.00 250,000.00

71 Kait angin Type "c" Bh 7,500.00 7,500.00

72 Kait angin Type "a" Bh 20,000.00 20,000.00

73 Kawat Ikat Kg 25,000.00 25,000.00

74 Keramik anti slip 20 x 20 cm Dos 75,000.00 75,000.00

75 Keramik 20 x 25 cm Dos 75,000.00 75,000.00

76 Keramik Anti Slip 20 x 25 cm Dos 80,000.00 80,000.00

77 Keramik 60 x 60 cm Dos 125,000.00 125,000.00

78 Keramik 40 x 40 cm Dos 85,000.00 85,000.00

79 Kran air Ø1/2" Bh 25,000.00 25,000.00

80 Kuas biasa 4" Bh 15,000.00 15,000.00

81 Kuas biasa 3 " Bh 12,000.00 12,000.00

82 Kuas Roll Bh 25,000.00 25,000.00

83 Kunci Tanam 2x putar Type I Bh 215,000.00 215,000.00

84 Kunci Tanam 2x putar Type II Bh 145,000.00 145,000.00

85 Klem Kabel 9mm Bh 500.00 500.00

86 Kabel dak 30mm M' 17,000.00 17,000.00

87 Kabel dak 50mm M' 20,000.00 20,000.00

Self Drilling Screw Ø 6-20mm (Truss Srew)

Self Drilling Screw Ø 4-16mm(Roof Batten Srew)

Page 6: RAB Gudang Bahan Pangan

Halaman : 6

No Bahan/Material Satuan

Harga Jarak Ongkos

Di Angkut Angkut Total Harga Quary Rata - Rata per satuan

Rp Rp

88 Lampu Pijar 25 watt ( Philips ) Bh 35,000.00 35,000.00

89 Lampu TL 40 Watt (Komplit) Bh 85,000.00 85,000.00

90 Lampu Spiral Philips 10 Watt+ Fiting Tempel Bh 35,000.00 35,000.00

91 Lampu Spiral Philips 18 Watt+ Fiting Tempel Bh 60,000.00 60,000.00

92 Lampu Spiral Philips 24 Watt+ Fiting Tempel Bh 75,000.00 75,000.00

Page 7: RAB Gudang Bahan Pangan

Halaman : 7

No Bahan/Material Satuan

Harga Jarak Ongkos

Di Angkut Angkut Total Harga Quary Rata - Rata per satuan

Rp Rp

93 Lampu TL 20 Watt (komplit) Bh 80,000.00 80,000.00

94 Lem Aica Aibon Kg 50,000.00 50,000.00

95 Lem Kayu (Weber/Raja Wali) Kg 35,000.00 35,000.00

96 List Plafon Tripleks 9 mm lbr 5 cm M1 3,500.00 3,500.00

97 List Plafon Gypsum M1 20,000.00 20,000.00

98 List Kaca Kayu Profil M1 3,000.00 3,000.00

99 List Plafond Papan Profil 2/5cm. M1 15,000.00 15,000.00

100 Meteran 1.350 Watt+Pentanahan ( arde) Pkt 8,500,000.00 8,500,000.00

101 Minyak Cat / Thiner A Kg 30,000.00 30,000.00

102 Acecories / Tombak Untuk Pagar Besi Bh 3,500.00 3,500.00

103 Pengelasan Titik 3,000.00 3,000.00

104 Pintu Framelles Bening 15 mm + Asesoris Unit 20,000,000.00 20,000,000.00

105 Paku Biasa Kg 20,000.00 20,000.00

106 Paku seng Biji 250.00 250.00

107 Paku Triplex/Halus Kg 25,000.00 25,000.00

108 Paving Block Segi 6 Natural (t.8cm) Bh 2,500.00 2,500.00

109 Pipa Instalasi Listrik 3/8" M1 6,500.00 6,500.00

110 Pipa GIP 1/2" Btg 220,000.00 220,000.00

111 Pipa GIP 3/4 Diem M' 46,875.00 46,875.00

112 Pipa GIP 2 Diem M' 125,583.33 125,583.33

113 Pipa GIP 1 Diem M' 62,500.00 62,500.00

114 Pipa GIP 1.25 Diem M' 103,650.00 103,650.00

115 Pipa GIP 1.5 Diem M' 109,500.00 109,500.00

116 Pipa Paralon 3/4 Btg 173,800.00 173,800.00

117 Pipa PVC 1/2" Btg 45,000.00 45,000.00

118 Pipa PVC 2" Btg 99,800.00 99,800.00

119 Pipa PVC 3" Btg 166,500.00 166,500.00

120 Pipa PVC 4" Btg 199,650.00 199,650.00

121 Plat Strip 5mm Kg 25,000.00 25,000.00

122 Plamir Kayu Kg 19,250.00 19,250.00

123 Plamir Tembok Kg 19,250.00 19,250.00

124 Pembersih Krum / Autosol Tube 15,000.00 15,000.00

125 Saklar Ganda Bh 35,000.00 35,000.00

126 Saklar Tunggal Bh 25,000.00 25,000.00

127 Saklar Triple Bh 40,000.00 40,000.00

128 ACB 9 Ampere Bh 100,000.00 100,000.00

129 Box ACB Bh 80,000.00 80,000.00

130 Sekring Cast 3 Fase(10 Grund) Bh 125,000.00 125,000.00

131 Selotip Pipa Bh 5,000.00 5,000.00

132 Lbr 48,000.00 48,000.00

133 M1 35,000.00 35,000.00

134 Soket 1/2" Bh 9,900.00 9,900.00

135 Stop Kontak Tanam Bh 15,000.00 15,000.00

136 Terminal 4 Lubang Bh 27,500.00 27,500.00

137 Steker Saklar Bh 17,000.00 17,000.00

138 Stop Kran 1/2 dim Bh 25,000.00 25,000.00

139 Unit 750,000.00 750,000.00

140 Teac Oil Kg 35,000.00 35,000.00

141 Teac Wood Lbr 110,000.00 110,000.00

Seng Gelombang BJLS 0,20

Seng Plat bubungan 0.20 lebar 50 cm

Tiang Bendera Ø 2" (T.8,5m)

Page 8: RAB Gudang Bahan Pangan

Halaman : 8

No Bahan/Material Satuan

Harga Jarak Ongkos

Di Angkut Angkut Total Harga Quary Rata - Rata per satuan

Rp Rp

142 Tripleks 3 mm Lbr 82,000.00 82,000.00

143 Tripleks 6 mm Lbr 95,000.00 95,000.00

144 Tripleks 9 mm Lbr 139,500.00 139,500.00

145 Kalsiboard 6 mm Lbr 180,000.00 180,000.00

146 Kalsiplank 9 mm M' 45,000.00 45,000.00

Page 9: RAB Gudang Bahan Pangan

Halaman : 9

No Bahan/Material Satuan

Harga Jarak Ongkos

Di Angkut Angkut Total Harga Quary Rata - Rata per satuan

Rp Rp

147 Wastavel Bh 280,000.00 280,000.00

148 Tripleks Lapis Aluminium Lbr 100,000.00 100,000.00

149 Vernis/Politur Kg 38,500.00 38,500.00

JENIS POHON PELINDUNG/PENGHIJAUAN

1 Pengadaan Rumput Mutiara /Jepang Rmp 550.00 550.00

2 Pengadaan Pohon Cemara (T.2m) Phn 115,000.00 115,000.00

3 Penngadaan Pohon Kelapa Gading (T.1,5m) Phn 175,000.00 175,000.00

4 Penngadaan Pohon Every Green (T.2m) Phn 185,000.00 185,000.00

BAHAN BAKAR

1 Minyak Tanah Ltr 3,800.00 3,800.00

2 Bensin Ltr 4,500.00 4,500.00

3 Solar Ltr 4,500.00 4,500.00

4 Oli Ltr 30,000.00 30,000.00

Waikabubak,....................2014

Engineering Consultan Engineering Consultan

stance construction consultant stance construction consultant

Perwakilan Sumba Barat

Claudius Herry, ST Kristianus Behar, ST

Inspector Engineer

Page 10: RAB Gudang Bahan Pangan

stanceconstruction.blogspot.com

REKAPITULASI

PEKERJAAN : PEMBANGUNAN GUDANGL O K A S I : WEERAMETAHUN ANGGARAN : 2014

URAIAN PEKERJAANJUMLAH

NO. HARGA(Rp.)

I PEKEKERJAAN PERSIAPAN 3,000,000.00 II PEKERJAAN TANAH DAN URUGAN 54,627,348.65 III PEKERJAAN PASANGAN DAN PLESTERAN 153,068,129.41 IV PEKERJAAN BETON 384,055,184.14 V PEKERJAAN LANTAI KERAMIK 39,304,225.27 VI PEKERJAAN KAYU DAN KACA 10,158,983.47 VII PEK. KUDA-KUDA, GORDING & LISTPLANK 53,669,650.73 VIII PEKERJAAN ATAP DAN PLAFOND 17,952,844.99 IX PEK. ALAT-ALAT PENGGANTUNG 3,003,125.00 X PEKERJAAN INSTALASI LISTRIK 6,330,347.00 XI PEKERJAAN SANITAIR 12,052,868.72 XII PEKERJAAN CAT 26,679,018.36 XIII PEKERJAAN LAIN - LAIN 500,000.00

JUMLAH HARGA LANGSUNG 764,401,725.74 PAJAK PPN 10%

JUMLAH 764,401,725.74

DI BULATKAN 764,402,000.00

TERBILANG :

Waikabubak,....................2014Diperiksa Direncanakan Oleh :

Engineering Consultan Engineering Consultan

stance construction consultant stance construction consultant

Claudius Herry, ST Kristianus Behar, ST Inspector Engineer

Disetujui

Bp. Marthen Bili LendePemilik

TUJUH RATUS ENAM PULUH EMPAT JUTA EMPAT RATUS SERIBU TUJUH RATUS DUA RIBU RUPIAH

Page 11: RAB Gudang Bahan Pangan

stanceconstruction.blogspot.com

DAFTAR KUANTITAS DAN HARGAPEKERJAAN : PEMBANGUNAN GUDANGL O K A S I : WEERAMETAHUN ANGGARAN : 2014

URAIAN PEKERJAANHARGA JUMLAH

NO. SAT. VOL. SATUAN HARGA(Rp.) (Rp.)

I PEKEKERJAAN PERSIAPAN 1 Pembersihan lokasi Ls 1.00 500,000.00 500,000.00 2 Pasang bouwplank dan pengukuran Ls 1.00 500,000.00 500,000.00 3 Penyediaan air kerja Ls 1.00 2,000,000.00 2,000,000.00

J u m l a h I 3,000,000.00 II PEKERJAAN TANAH DAN URUGAN1 Galian Pondasi Footplate M³ 82.32 31,280.00 2,574,969.60 2 Galian Pondasi Menerus M³ 68.16 31,280.00 2,132,044.80 3 Galian Septic Tank M³ 6.37 31,280.00 199,253.60 4 Urugan Tanah Leveling Lantai M³ 65.69 122,117.17 8,021,867.01 5 Urugan Pasir Bawah Pondasi M³ 12.64 187,981.36 2,375,332.45 6 Aanstamping (Urugan Batu Kosong) M³ 25.27 276,614.05 6,990,590.27 7 Pasangan Pondasi Batu Karang M³ 42.17 766,664.08 32,333,290.92

J u m l a h II 54,627,348.65 III PEKERJAAN PASANGAN DAN PLESTERAN1 Pasangan Dinding Batu Potong M³ 98.29 824,129.30 81,006,552.94 2 Plesteran Dinding M² 1,310.58 39,538.75 51,818,699.97 3 Acian Dinding M² 1,310.58 15,445.74 20,242,876.50

J u m l a h III 153,068,129.41 IV PEKERJAAN BETON1 Pondasi Footplate 1pc : 2ps : 3kp set 21.00 1,963,022.38 41,223,470.06 2 Sloof S1 20/30 M³ 5.11 5,929,973.65 30,314,025.31 2 Kolom K1 30/30 M³ 14.58 5,953,557.87 86,802,873.69 3 Kolom Praktis KP 15/15 M³ 1.35 5,174,826.46 6,986,015.72 4 Balok B1 20/30 M³ 8.74 6,581,659.00 57,544,761.00 5 Balok B2 20/40 M³ 7.22 6,581,659.00 47,503,782.03 6 Balok Anak B3 15/25 M³ 2.50 5,797,931.71 14,506,425.14 7 Plat Beton tebal 12 cm M³ 16.53 5,604,378.76 92,650,334.32 8 Plat Tangga tebal 12 M³ 1.16 5,604,378.76 6,523,496.88

J u m l a h IV 384,055,184.14 V PEKERJAAN LANTAI KERAMIK1 Lantai tegel keramik 40x40 cm2 M² 245.76 151,972.34 37,349,452.70 2 Lantai tegel wafel keramik 20x20 cm2 KM/WC M² 2.53 139,117.34 352,140.78 3 Pasang keramik dinding 20x25 cm2 KM/WC M² 11.52 139,117.34 1,602,631.80

J u m l a h V 39,304,225.27

Page 12: RAB Gudang Bahan Pangan

stanceconstruction.blogspot.com

PEKERJAAN : PEMBANGUNAN GUDANGL O K A S I : WEERAMETAHUN ANGGARAN : 2014

URAIAN PEKERJAANHARGA JUMLAH

NO. SAT. VOL. SATUAN HARGA(Rp.) (Rp.)

VI PEKERJAAN KAYU DAN KACA1 Daun pintu panil papan P1 M² 6.40 558,815.87 3,576,421.57 2 Daun pintu teakwood lapis aluminium P2 M² 1.20 545,465.26 654,558.31 3 Daun Jendela kaca J1 5 mm M² 4.95 570,765.33 2,825,288.37 4 Kusen P1 M³ 0.1590 6,549,128.71 1,041,154.29 5 Kusen P2 M³ 0.0383 6,549,128.71 250,857.83 6 Kusen J1 M³ 0.2765 6,549,128.71 1,810,703.11

J u m l a h VI 10,158,983.47 VII PEK. KUDA-KUDA, GORDING & LISTPLANK1 Kuda-kuda kayu M³ 4.16 6,917,352.71 28,806,180.92 2 Gording M³ 3.06 6,917,352.71 21,167,099.30 3 Nok M³ 0.20 6,917,352.71 1,361,335.01 4 Lisplank Papan Kayu M² 18.52 126,109.07 2,335,035.50

J u m l a h VII 53,669,650.73 VIII PEKERJAAN ATAP DAN PLAFOND1 Atap Seng Gelombang BJLS 0.2 M² 265.08 63,317.50 16,783,943.74 2 Pas. Bubungan Genteng Metalroof 0,30 mm M¹ 21.50 54,367.50 1,168,901.25

J u m l a h VIII 17,952,844.99 IX PEK. ALAT-ALAT PENGGANTUNG1 Pas. Engsel Pintu Bh 15.00 31,250.00 468,750.00 2 Pas. Engsel Jendela Bh 20.00 21,875.00 437,500.00 3 Pas. Kait angin Bh 10.00 25,000.00 250,000.00 4 Pas. Gerendel Pintu & Jendela Bh 15.00 21,875.00 328,125.00 5 Gagang Pintu Bh 5.00 303,750.00 1,518,750.00

J u m l a h IX 3,003,125.00 X PEKERJAAN INSTALASI LISTRIK1 Pas. Box Sekring/MCB Ls 1.00 212,400.00 212,400.00 2 Pek Titik Instalasi Listrik Titik 19.00 213,738.00 4,061,022.00 3 Pas. Stop Kontak Bh 8.00 17,975.00 143,800.00 4 Pas Saklar Ganda Bh 5.00 36,750.00 183,750.00 5 Pas Saklar tunggal Bh 3.00 26,250.00 78,750.00 6 Pas. Lampu XL 18 watt Unit 19.00 86,875.00 1,650,625.00

J u m l a h X 6,330,347.00

Page 13: RAB Gudang Bahan Pangan

stanceconstruction.blogspot.com

PEKERJAAN : PEMBANGUNAN GUDANGL O K A S I : WEERAMETAHUN ANGGARAN : 2014

URAIAN PEKERJAANHARGA JUMLAH

NO. SAT. VOL. SATUAN HARGA(Rp.) (Rp.)

XI PEKERJAAN SANITAIR1 Pekerjaan Septic tank Unit 1.00 8,604,243.28 8,604,243.28 2 Kloset jongkok Unit 1.00 296,404.66 296,404.66 3 Floor Drain Unit 1.00 26,851.00 26,851.00 4 Instalasi air bersih (Pipa GIP) dlm tembok / lantai Ls 1.00 2,500,000.00 2,500,000.00 5 Bak air lps keramik 50x50x75 cm Unit 1.00 593,518.77 593,518.77 6 Kran air 1/2" Bh 1.00 31,851.00 31,851.00

J u m l a h XI 12,052,868.72 XII PEKERJAAN CAT1 Cat Dinding M² 1,310.58 20,356.65 26,679,018.36

J u m l a h XII 26,679,018.36 XIII PEKERJAAN LAIN - LAIN1 Pembersihan Akhir Ls 1.00 500,000.00 500,000.00

J u m l a h XIII 500,000.00

Page 14: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 14

ANALISA HARGA SATUANPROGRAM :

KEGIATAN :

PEKERJAAN :

LOKASI :

SUMBER DANA :

TAHUN ANGGARAN :

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

I PEKERJAAN PERSIAPAN1 Pek. 1M2 PENGUKURAN DAN BOW PLANK UNTUK BANGUNAN BERTINGKAT

kayu Usuk 5/7 0.0120 M3 4,578,976.27 54,947.72

Paku Biasa 0.0200 Kg 20,000.00 400.00

Papan bekisting 0.0070 M3 1,478,976.27 10,352.83

Benang Nilon 0.0400 Roll 10,000.00 400.00

Tukang 0.1000 Org 61,600.00 6,160.00

Kep.Tukang 0.0100 Org 74,600.00 746.00

Pekerja 0.1000 Org 37,100.00 3,710.00

Mandor 0.0050 Org 69,100.00 345.50

Jumlah 77,062.05

2 Pek. 1M' PENGUKURAN DAN BOW PLANK

kayu Usuk 5/7 0.0060 M3 4,578,976.27 27,473.86

Paku Biasa 0.0100 Kg 20,000.00 200.00

Papan bekisting 0.0035 M3 1,478,976.27 5,176.42

Benang Nilon 0.0200 Roll 10,000.00 200.00

Tukang 0.0500 Org 61,600.00 3,080.00

Kep.Tukang 0.0050 Org 74,600.00 373.00

Pekerja 0.0500 Org 37,100.00 1,855.00

Mandor 0.0025 Org 69,100.00 172.75

Jumlah 38,531.02

3 MEMBUAT 1 M' PAGAR SEMENTARA DARI GEDEK ISI TINGGI 2.METER

Kayu Dolken 0.5000 Btg 10,000.00 5,000.00 Gedek Isi 2 x 2 0.5000 lbr 30,000.00 15,000.00 Paku Biasa 2" - 5" 0.0600 kg 20,000.00 1,200.00 Pekerja 0.4000 OH 37,100.00 14,840.00 Tukang Kayu 0.2000 OH 61,600.00 12,320.00 Kepala Tukang 0.0200 OH 74,600.00 1,492.00 Mandor 0.0200 OH 69,100.00 1,382.00

Jumlah 51,234.00

I PEKERJAAN GALIAN DAN TIMBUNAN1 1 M3 PEK. GALIAN TANAH

Pekerja 0.7500 Org 37,100.00 27,825.00

Mandor 0.0500 Org 69,100.00 3,455.00

Jumlah 31,280.00

2 1 M3 PEK. GALIAN TANAH CADAS

Pekerja 2.0000 Org 37,100.00 74,200.00

Mandor 0.0660 Org 69,100.00 4,560.60

Jumlah 78,760.60

3 1 M3 PEK. URUGAN TANAH BEKAS GALIAN

Pekerja 0.1875 Org 37,100.00 6,956.25

Mandor 0.0060 Org 69,100.00 414.60

Alat bantu 0.3000 Set 50,000.00 15,000.00

Jumlah 22,370.85

4 1 M3 PEK. URUGAN TANAH BIASA

Pekerja 0.1875 Org 37,100.00 6,956.25

Mandor 0.0066 Org 69,100.00 456.06

Tanah Urug Biasa 1.2000 M3 95,587.38 114,704.86

Jumlah 122,117.17

5 1 M3 PEK. URUGAN SIRTU

Sirtu 1.2000 M3 154,115.47 184,938.56

Pekerja 0.0500 Org 37,100.00 1,855.00

Mandor 0.0500 Org 69,100.00 3,455.00

Jumlah 190,248.56

Page 15: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 15

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

6 1 M3 PEK. URUGAN PASIR

Pasir urug 1.2000 M3 146,800.30 176,160.36

Pekerja 0.3000 Org 37,100.00 11,130.00

Mandor 0.0100 Org 69,100.00 691.00

Jumlah 187,981.36

7 1 M3 PEK. URUGAN KERIKIL

Kerikil 1.1500 M3 529,069.20 608,429.58

Pekerja 0.3000 Org 37,100.00 11,130.00

Mandor 0.0100 Org 69,100.00 691.00

Jumlah 620,250.58

8 1m³ PEK. URUGAN TANAH HUMUS

Tanah Humus 1.1000 m³ 95,587.38 105,146.12

Pekerja 0.2000 Org/hr 37,100.00 7,420.00

Mandor 0.0200 Org/hr 69,100.00 1,382.00

Jumlah 113,948.12

II PEK. PASANGAN, PONDASI & PLESTERAN1 1 M3 PEK.PASANGAN BATU KOSONGAN

Batu Karang 1.1500 M3 187,936.57 216,127.05

Pekerja 1.5000 Org 37,100.00 55,650.00

Mandor 0.0700 Org 69,100.00 4,837.00

Jumlah 276,614.05

2 1 M3 PEK.PAS.PONDASI BATU KARANG CAMP 1Pc:4 Psr

Batu Karang 1.1500 M3 187,936.57 216,127.05

Semen 3.3400 Zak 76,330.49 254,943.82

Pasir Pasang 0.3600 M3 316,800.30 114,048.11

Tukang Batu 1.2000 Org 61,600.00 73,920.00

Kep.Tukang 0.1200 Org 74,600.00 8,952.00

Pekerja 3.6000 Org 37,100.00 133,560.00

Mandor 0.1800 Org 69,100.00 12,438.00

Jumlah 813,988.98

3 1 M3 PEK.PAS.PONDASI BATU KARANG CAMP 1Pc:5 Psr

Batu Karang 1.1500 M3 187,936.57 216,127.05

Semen 2.7200 Zak 76,330.49 207,618.92

Pasir Pasang 0.3600 M3 316,800.30 114,048.11

Tukang Batu 1.2000 Org 61,600.00 73,920.00

Kep.Tukang 0.1200 Org 74,600.00 8,952.00

Pekerja 3.6000 Org 37,100.00 133,560.00

Mandor 0.1800 Org 69,100.00 12,438.00

Jumlah 766,664.08

4 1 M3 PEK. BETON BERTULANG MUTU K-175

a. Beton 1 : 2 : 3

Semen 50 Kg 6.5000 Zak 76,330.49 496,148.16

Pasir Pasang 0.5400 M3 316,800.30 171,072.16

Kerikil pecah 0.8200 M3 529,069.20 433,836.75

Tukang Batu 1.0000 Org 61,600.00 61,600.00

Kep.Tukang 0.1000 Org 74,600.00 7,460.00

Pekerja 6.0000 Org 37,100.00 222,600.00

Mandor 0.3000 Org 69,100.00 20,730.00

Jumlah 1,413,447.07

5 1 M3 PEK. BETON BERTULANG MUTU K-250 (UNTUK PEK. STRUKTUR)

b. Beton 1 : 1,5 : 2,5

Semen 50 Kg 8.5000 Zak 76,330.49 648,809.13

Pasir Pasang 0.5400 M3 316,800.30 171,072.16

Kerikil Pecah 0.8200 M3 529,069.20 433,836.75

Tukang Batu 1.0000 Org 61,600.00 61,600.00

Kep.Tukang 0.1000 Org 74,600.00 7,460.00

Pekerja 6.0000 Org 37,100.00 222,600.00

Mandor 0.3000 Org 69,100.00 20,730.00

Jumlah 1,566,108.04

Page 16: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 16

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

6 1 M2 PEK. BEKISTING

a. 1M2 Bekisting Papan

Papan Bekisting 0.0120 M3 1,478,976.27 17,747.72

Paku 0.4000 Kg 20,000.00 8,000.00

Tukang 0.3300 Org 61,600.00 20,328.00

Kep.Tukang 0.0330 Org 74,600.00 2,461.80

Pekerja 0.6600 Org 37,100.00 24,486.00

Mandor 0.0330 Org 69,100.00 2,280.30

Jumlah 75,303.82

b. 1M2 Bekisting Multiplex 9mm

Multipleks 9 mm 0.1653 Lbr 139,500.00 23,056.56

Paku > 5 cm 0.4000 Kg 20,000.00 8,000.00

Usuk 5/7 0.0200 m³ 4,578,976.27 91,579.53

Tukang kayu 0.3300 Org/hr 61,600.00 20,328.00

Kepala tukang 0.0330 Org/hr 74,600.00 2,461.80

Pekerja 0.6600 Org/hr 37,100.00 24,486.00

Pekerja bongkar bagisting 0.0660 Org/hr 37,100.00 2,448.60

Mandor 0.0330 Org/hr 69,100.00 2,280.30

Jumlah 174,640.79

7 110 Kg. PEK. PEMBESIAN BESI POLOS dan BESI ULIR

c. Pembesian 110 Kg

Besi Beton Polos 110.0000 Kg 14,000.00 1,540,000.00

Besi Beton Ulir 110.0000 Kg 17,000.00 1,870,000.00

Kawat Ikat 2.5000 Kg 25,000.00 62,500.00

Tukang besi 3.0000 Org 61,600.00 184,800.00

Kep.Tukang 0.5000 Org 74,600.00 37,300.00

Pekerja 2.0000 Org 37,100.00 74,200.00

1,898,800.00

Jumlah Besi Beton Polos / 1.kg = (A/100) : 18,988.00

2,228,800.00

Jumlah Besi Beton Ulir / 1.kg = (B/100) : 22,288.00

8Semen 3.2000 zak 76,330.49 244,257.56

Pasir Pasang 0.5200 316,800.30 164,736.16

Kerikil 0.8700 529,069.20 460,290.21

Pekerja 1.6500 org 37,100.00 61,215.00

Mandor 0.0800 org 69,100.00 5,528.00

Tukang batu 0.2500 org 61,600.00 15,400.00

Kepala tukang batu 0.0250 org 74,600.00 1,865.00

Jumlah 953,291.92

a Pek. Beton Bertulang untuk Kolom Praktis & RingBalk 15/15 ( /m3 )

Beton Mutu K.175) 1Pc : 2Psr : 3Krl 1.0000 M³ 1,413,447.07 1,413,447.07

Besi Beton Polos 145.2144 Kg 18,988.00 2,757,331.03

Papan Bekisting 13.3333 M² 75,303.82 1,004,048.36

Jumlah 5,174,826.46

b Pek. Beton Bertulang untuk Sloof, Kolom & Ring Balk 15/20 ( /m3 )

Beton Mutu K.175) 1Pc : 2Psr : 3Krl 1.0000 M³ 1,413,447.07 1,413,447.07

Besi Beton Polos 113.8927 Kg 18,988.00 2,162,594.59

Papan Bekisting 13.3333 M² 75,303.82 1,004,048.36

Jumlah 4,580,090.02

c Pek. Beton Bertulang untuk Kolom 15/50 ( /m3 )

Beton Mutu K.175) 1Pc : 2Psr : 3Krl 1.0000 M³ 1,413,447.07 1,413,447.07

Besi Beton Polos 113.8927 Kg 18,988.00 2,162,594.59

Papan Bekisting 17.3333 M² 75,303.82 1,305,263.62

Jumlah 4,881,305.28

d Pek. Beton Bertulang untuk Sloof, & Ring Balk 20/25 ( /m3 )

Beton Mutu K.175) 1Pc : 2Psr : 3Krl 1.0000 M³ 1,413,447.07 1,413,447.07

Besi Beton Polos 124.0451 Kg 18,988.00 2,355,368.36

Papan Bekisting 10.0000 M² 75,303.82 753,038.15

Jumlah 4,521,853.58

e Pek. Beton Bertulang untuk & Ring Balk Gantung 15/20 ( /m3 )

Beton Mutu K.175) 1Pc : 2Psr : 3Krl 1.0000 M³ 1,413,447.07 1,413,447.07

Besi Beton Polos 171.8894 Kg 18,988.00 3,263,835.93

Papan Bekisting 18.3333 M² 75,303.82 1,380,567.44

Kayu Dolken / Perancah 52.3809 Btg 10,000.00 523,808.57

Jumlah 6,581,659.00

(A) Jumlah Besi Beton Polos :

(B) Jumlah Besi Beton Ulir :

1 M3 COR BETON LANTAI KERJA camp. 1 pc : 3 psr : 5 krl (tbl 7cm)

m3

m3

D126
Mc: Bekisting 3x Pakai (dibagi 2,5)
D134
Mc: Bekisting 3x Pakai (dibagi 2,5)
Page 17: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 17

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

f 1 m3 Pek. Beton Bertulang Untuk Kolom Bebas (20/20)

Beton Mutu (K.175) 1Pc : 2Psr : 3Krl 1.0000 M³ 1,413,447.07 1,413,447.07

Besi Beton Polos 158.4049 Kg 18,988.00 3,007,792.24

Papan Bekisting 35.5556 M² 75,303.82 2,677,472.33

Jumlah 7,098,711.64

g Pek. Beton Bertulang untuk Kolom 25/25 ( /m3 )

Beton Mutu K.175) 1Pc : 2Psr : 3Krl 1.0000 M³ 1,413,447.07 1,413,447.07

Besi Beton Polos 136.0851 Kg 18,988.00 2,583,983.88

Papan Bekisting 8.0000 M² 75,303.82 602,430.52

Jumlah 4,599,861.47

h Pek. Beton Bertulang untuk Kolom 12/20 ( /m3 )

Beton Mutu K.175) 1Pc : 2Psr : 3Krl 1.0000 M³ 1,413,447.07 1,413,447.07

Besi Beton Polos 136.0851 Kg 18,988.00 2,583,983.88

Papan Bekisting 13.3333 M² 75,303.82 1,004,048.36

Kayu Dolken / Perancah 38.0951 Btg 10,000.00 380,951.43

Jumlah 5,382,430.74

i Pek. Beton Bertulang untuk Balok 15/25 ( /m3 )

Beton Mutu K.175) 1Pc : 2Psr : 3Krl 1.0000 M³ 1,413,447.07 1,413,447.07

Besi Beton Polos 136.0851 Kg 18,988.00 2,583,983.88

Papan Bekisting 17.3333 M² 75,303.82 1,305,263.62

Kayu Dolken / Perancah 49.5237 Btg 10,000.00 495,237.14

Jumlah 5,797,931.71

j Pek. Beton Bertulang untuk List Plank Beton 5/40 ( /m3 )

Beton Mutu K.175) 1Pc : 2Psr : 3Krl 1.0000 M³ 1,413,447.07 1,413,447.07

Besi Beton Polos 136.0851 Kg 18,988.00 2,583,983.88

Papan Bekisting 42.5000 M² 75,303.82 3,200,412.15

Kayu Dolken / Perancah 121.4286 Btg 10,000.00 1,214,285.71

Jumlah 8,412,128.81

9 1 UNIT Bangku Duduk Beton Bertulang Tebal 8cm

Lantai Kerja Camp. 1;3;5 Tebal 5cm 0.0225 M3 953,291.92 21,449.07

Pasangan Batu Potong 0.0630 M3 824,129.30 51,920.15

Beton Sandaran Camp. 1:2:3 0.4200 M3 1,413,447.07 593,647.77

Beton Dudukan Camp. 1:2:3 0.5000 M3 1,413,447.07 706,723.53

Besi Polos 108.2191 Kg 18,988.00 2,054,864.27

Begisting Triplex 9mm 13.1600 M² 174,640.79 2,298,272.74

Kayu Dolken / Perancah 10.9667 Btg 10,000.00 109,666.67

Plesteran Biasa (1pc : 5psr) 10.1200 M2 39,538.75 400,132.19

Acian 10.1200 M2 15,445.74 156,310.88

Cat Permukaan Pasangan 10.1200 M2 24,593.80 248,889.26

Pas. Keramik 40 x 40 Kwalitas "A" 5.6000 M2 151,972.34 851,045.13

Jumlah 7,492,921.64

A 1 Unit Beton Foot Plat (ukuran 0,80x0,80x0,20) K.250

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 0.1280 M³ 1,566,108.04 200,461.83

Besi Beton Polos 17.7182 Kg 18,988.00 336,433.18

Jumlah 536,895.01

B 1 Unit Beton Foot Plat (ukuran 1,20x1,20x0,20) K.250

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 0.4680 M³ 1,566,108.04 732,938.56

Besi Beton Polos 64.7822 Kg 18,988.00 1,230,083.82

Jumlah 1,963,022.38

C 1 Unit Pekerjaan Pelat Duiker (12,48x1,60x 0,20) K.250

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 3.9900 M³ 1,566,108.04 6,248,771.09

Besi Beton Polos 650.3055 Kg 18,988.00 12,348,000.83

Begisting Papan 48.1280 M2 75,303.82 3,624,222.02

Kayu Dolken / Perancah 34.3771 Btg 10,000.00 343,771.43

Jumlah 22,564,765.37

D 1 m3 Pek. Beton Bertulang Sloof 15 / 25

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 1.0000 M³ 1,566,108.04 1,566,108.04

Besi Beton Polos 95.1086 Kg 18,988.00 1,805,922.10

Begisting Triplex 9mm 13.3333 M² 174,640.79 2,328,537.98

Jumlah 5,700,568.12

E 1 m3 Pek. Beton Bertulang Sloof 20 / 25

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 1.0000 M³ 1,566,108.04 1,566,108.04

Besi Beton Polos 174.3002 Kg 18,988.00 3,309,612.20

Begisting Papan 14.0000 M² 75,303.82 1,054,253.41

Jumlah 5,929,973.65

Page 18: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 18

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

F 1 m3 Pek. Beton Bertulang Kolom Struktur 15/15

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 1.0000 M³ 1,566,108.04 1,566,108.04

Besi Beton Polos 145.2144 Kg 18,988.00 2,757,331.03

Begisting Triplex 9mm 26.6667 M² 174,640.79 4,657,093.43

Jumlah 8,980,532.50

G 1 m3 Pek. Beton Bertulang Kolom 30 / 30

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 1.0000 M³ 1,566,108.04 1,566,108.04

Besi Beton Polos 178.1863 Kg 18,988.00 3,383,401.46

Begisting Papan 13.3333 M² 75,303.82 1,004,048.36

Jumlah 5,953,557.87

H 1 m3 Pek. Beton Bertulang Untuk Kolom Bebas (20/20)

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 1.0000 M³ 1,566,108.04 1,566,108.04

Besi Beton Polos 158.4049 Kg 18,988.00 3,007,792.24

Begisting Triplex 9mm 35.5556 M² 174,640.79 6,209,457.91

Jumlah 10,783,358.19

I 1 m3 Pek. Beton Bertulang Balok 15 / 30

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 1.0000 M³ 1,566,108.04 1,566,108.04

Besi Beton Polos 266.2673 Kg 18,988.00 5,055,883.49

Begisting Triplex 9mm 16.6667 M² 174,640.79 2,910,685.58

Jumlah 9,532,677.11

J 1 m3 Pek. Beton Bertulang Balok 20 / 35

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 1.0000 M³ 1,566,108.04 1,566,108.04

Besi Beton Polos 211.8866 Kg 18,988.00 4,023,302.76

Begisting Triplex 9mm 13.7143 M² 174,640.79 2,395,076.12

Jumlah 7,984,486.93

K 1 m3 Pek. Beton Bertulang Kolom Struktur 15 / 20

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 1.0000 M³ 1,566,108.04 1,566,108.04

Besi Beton Polos 113.8927 Kg 18,988.00 2,162,594.59

Begisting Triplex 9mm 13.3333 M² 174,640.79 2,328,537.98

Jumlah 6,057,240.61

L 1 m3 Pek. Beton Plat Dek Tebal 10 cm

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 1.0000 M³ 1,566,108.04 1,566,108.04

Besi Beton Polos 246.6000 Kg 18,988.00 4,682,440.80

Begisting Triplex 9mm 10.0000 M² 174,640.79 1,746,407.85

Kayu Dolken / Perancah 60.0000 Btg 10,000.00 600,000.00

Jumlah 8,594,956.70

M 1 m3 Pek. Beton Plat Dek Tebal 8 cm

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 1.0000 M³ 1,566,108.04 1,566,108.04

Besi Beton Polos 123.3000 Kg 18,988.00 2,341,220.40

Begisting Triplex 9mm 10.0000 M² 174,640.79 1,746,407.85

Kayu Dolken / Perancah 30.0000 Btg 10,000.00 300,000.00

Jumlah 5,953,736.30

N 1 m3 Pek. Beton Plat Dek Tebal 12 cm

Beton Mutu (K.250) 1Pc : 1,5Psr : 2,5Krl 1.0000 M³ 1,566,108.04 1,566,108.04

Besi Beton Polos 96.8663 Kg 18,988.00 1,839,297.30

Begisting Triplex 9mm 10.5733 M² 174,640.79 1,846,529.42

Kayu Dolken / Perancah 35.2444 Btg 10,000.00 352,444.00

Jumlah 5,604,378.76

6 1M3 PEK. PAS. TEMBOK BATU POTONG CAMP 1Pc : 5 Psr

Batu Potong 14x15x24 Cm 200.0000 Bh 2,048.43 409,685.40

Semen 1.4700 Zak 76,330.49 112,205.81

Pasir Pasang 0.2630 M3 316,800.30 83,318.48

Tukang Batu 1.2000 Org 61,600.00 73,920.00

Kep.Tukang 0.1200 Hok 74,600.00 8,952.00

Pekerja 3.6000 Hok 37,100.00 133,560.00

Mandor 0.0360 Hok 69,100.00 2,487.60

Jumlah 824,129.30

7 1M3 PEK. PAS. TEMBOK TRANSRAM CAMP 1Pc : 3 Psr

Batu Potong 14x14x24 Cm 200.0000 Bh 2,048.43 409,685.40

Semen 2.3670 Zak 76,330.49 180,674.26

Pasir Pasang 0.2630 M3 316,800.30 83,318.48

Tukang Batu 1.5000 Org 61,600.00 92,400.00

Kep.Tukang 0.1500 Hok 74,600.00 11,190.00

Pekerja 4.5000 Hok 37,100.00 166,950.00

Mandor 0.2250 Hok 69,100.00 15,547.50

Jumlah 959,765.64

Page 19: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 19

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

8 1 M2 PLESTERAN TRASRAAM 1Pc : 3pSR

Semen 0.2550 M3 76,330.49 19,464.27

Pasir ayak 0.0228 M3 316,800.30 7,223.05

Tukang 0.1550 Org 61,600.00 9,548.00

Kep.Tukang 0.0750 Org 74,600.00 5,595.00

Pekerja 0.0950 Org 37,100.00 3,524.50

Mandor 0.0100 Org 69,100.00 691.00

Jumlah 46,045.82

9 1 M2 PLESTERAN BIASA 1Pc: 5 Psr

Semen 0.2200 M3 76,330.49 16,792.71

Pasir ayak 0.0228 M3 316,800.30 7,223.05

Tukang 0.1200 Org 61,600.00 7,392.00

Kep.Tukang 0.0500 Org 74,600.00 3,730.00

Pekerja 0.1000 Org 37,100.00 3,710.00

Mandor 0.0100 Org 69,100.00 691.00

Jumlah 39,538.75

10 1 M2 PEK. ACIAN

Semen 0.0800 Zak 76,330.49 6,106.44

Tukang 0.1000 Org 61,600.00 6,160.00

Kep.Tukang 0.0100 Org 74,600.00 746.00

Pekerja 0.0600 Org 37,100.00 2,226.00

Mandor 0.0030 Org 69,100.00 207.30

Jumlah 15,445.74

11 1 M2 PEK. BENANGAN + ACIAN

Semen 0.0800 Zak 76,330.49 6,106.44

Pasir Pasang 0.0050 M3 316,800.30 1,584.00

Tukang 0.5500 Org 61,600.00 33,880.00

Kep.Tukang 0.0550 Org 74,600.00 4,103.00

Pekerja 0.3000 Org 37,100.00 11,130.00

Mandor 0.0150 Org 69,100.00 1,036.50

Jumlah 57,839.94

12 1 M1 PEK. SALURAN KELILING BANGUNAN TIPE 0.20 CM x 0.30

Galian Tanah Biasa 0.1500 M3 31,280.00 4,692.00

Urugan Pasir 0.0250 M3 187,981.36 4,699.53

Pasangan Batu Karang 0.1000 M3 813,988.98 81,398.90

Plesteran Biasa 1.0900 M2 46,045.82 50,189.94

Acian Permukaan 1.0900 M2 15,445.74 16,835.86

Jumlah 157,816.23

13 1 M1 PEK. SALURAN KELILING BANGUNAN TIPE 0.50 CM x 0.25

Galian Tanah Biasa 0.3300 M3 31,280.00 10,322.40

Urugan Pasir 0.0275 M3 187,981.36 5,169.49

Pas. Batu Potong Transram 0.1500 M3 959,765.64 143,964.85

Pasangan Batu Karang 0.1100 M3 813,988.98 89,538.79

Plesteran Biasa 1.5500 M2 46,045.82 71,371.02

Jumlah 320,366.54

III PEKERJAAN KAYU, KUSEN PINTU JENDELA KACA DAN ATAP1 1M3 PEK.KUSEN PINTU/JENDELA KAYU KLAS II

Kayu Balok Kls II Non Lokal 1.1500 M3 4,178,976.27 4,805,822.71

Paku 0.8000 Kg 20,000.00 16,000.00

Tukang 20.0000 Org 61,600.00 1,232,000.00

Kep.Tukang 3.6000 Org 74,600.00 268,560.00

Pekerja 6.0000 Org 37,100.00 222,600.00

Mandor 0.0600 Org 69,100.00 4,146.00

Jumlah 6,549,128.71

2 /M1 PEK. KUSEN ALUMINIUM PINTU DAN JENDELA

a. Bahan :

Kosen Aluminium 1.1000 M' 185,000.00 203,500.00

b. Upah :

Tukang Besi 0.2000 Org/hr 61,600.00 12,320.00

Kepala Tukang 0.0200 Org/hr 74,600.00 1,492.00

Pekerja 0.1000 Org/hr 37,100.00 3,710.00

Mandor 0.0100 Org/hr 69,100.00 691.00

Jumlah 221,713.00

Page 20: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 20

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

3 1M3 PEK. DAUN PINTU PANIL KACA 5 mm

Kaca polos 5 mm 1.0000 M2 200,000.00 200,000.00

Papan Klas II Non Lokal 0.0084 M3 4,278,976.27 35,943.40

Paku halus 0.0050 Kg 25,000.00 125.00

Plamir 0.0060 Kg 19,250.00 115.50

Lem Kayu 0.1500 Kg 35,000.00 5,250.00

Amplas 0.8000 Lbr 4,500.00 3,600.00

Tukang 2.1500 Org 61,600.00 132,440.00

Kep.Tukang 0.2150 Org 74,600.00 16,039.00

Pekerja 0.8150 Org 37,100.00 30,236.50

Mandor 0.0401 Org 69,100.00 2,769.18

Jumlah 426,518.58

4

Papan Klas II Non Lokal 0.0392 M3 4,278,976.27 167,735.87

Dumpul 0.1000 kg 30,000.00 3,000.00

Lem Kayu 0.5000 Kg 35,000.00 17,500.00

Amplas 0.7500 Lmbr 4,500.00 3,375.00

Tukang Kayu 5.0000 org 61,600.00 308,000.00

Kepala Tukang kayu 0.2500 org 74,600.00 18,650.00

Pekerja 1.0000 org 37,100.00 37,100.00

Mandor 0.0500 org 69,100.00 3,455.00

Jumlah 558,815.87

5 1M2 PEK. DAUN JENDELA PANIL KACA 5 mm

Kaca Bening polos 5 mm 1.1000 M2 200,000.00 220,000.00

Kaca Reyben 5 mm 1.1000 M2 250,000.00 275,000.00

Papan Klas II Non Lokal 0.0360 M3 4,278,976.27 154,043.15

Lem Kayu 0.2500 Kg 35,000.00 8,750.00

Plamir 0.1500 Kg 19,250.00 2,887.50

Amplas 0.8000 Lbr 4,500.00 3,600.00

Tukang Kayu 2.1500 org 61,600.00 132,440.00

Kepala Tukang kayu 0.2150 org 74,600.00 16,039.00

Pekerja 0.8150 org 37,100.00 30,236.50 Mandor 0.0401 org 69,100.00 2,769.18

Kaca Reyben 5mm : 625,765.33

Kaca Bening Polos 5mm : 570,765.33

6

Kaca Bening polos 5 mm 1.1000 M2 200,000.00 220,000.00

Kaca Reyben 5 mm 1.1000 250,000.00 275,000.00

Plamur/Dempul kayu 0.0470 kg 19,250.00 904.75

List kaca 4.0000 m' 3,000.00 12,000.00

Paku halus 0.0050 kg 25,000.00 125.00

Tukang Kayu 0.1500 org 61,600.00 9,240.00

Kepala Tukang kayu 0.0008 org 74,600.00 1,119.00

Pekerja 0.0150 org 37,100.00 556.50

Mandor 0.0150 org 69,100.00 1,036.50

Kaca Reyben 5mm : 299,981.75

Kaca Bening Polos 5mm : 244,981.75

7

Kaca polos 5 mm 1.2000 200,000.00 240,000.00

Kaca Reyben 5 mm 1.1000 250,000.00 275,000.00

Plamur/Dempul kayu 0.0470 kg 19,250.00 904.75

List kaca 4.0000 m' 3,000.00 12,000.00

Paku halus 0.0050 kg 25,000.00 125.00

Tukang Kayu 0.0150 org 61,600.00 924.00

Kepala Tukang kayu 0.0008 org 74,600.00 55.95

Pekerja 0.1500 org 37,100.00 5,565.00

Mandor 0.0150 org 69,100.00 1,036.50

Kaca Reyben 5mm : 295,611.20

Kaca Bening Polos 5mm : 260,611.20

1 M2 PEKERJAAN DAUN PINTU PANIL PAPAN

1 M2 PASANGAN JENDELA KACA MATI 5mm

m2

1 M2 PASANGAN KACA ZIG-ZAG

m2

m2

Page 21: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 21

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

8 1M3 PEK. KUDA - KUDA/ GORDING/BALOK ANGIN

Kayu Balok Kls II Non Lokal 1.1500 M3 4,178,976.27 4,805,822.71

Plat Strip 5mm 15.0000 Kg 25,000.00 375,000.00

Paku 12 cm 5.6000 Kg 20,000.00 112,000.00

Tukang 20.0000 Org 61,600.00 1,232,000.00

Kep.Tukang 2.0000 Org 74,600.00 149,200.00

Pekerja 6.0000 Org 37,100.00 222,600.00

Mandor 0.3000 Org 69,100.00 20,730.00

Jumlah 6,917,352.71

9 1M2 PEK. KUDA - KUDA BAJA RINGAN

2.1800 M' 22,000.00 47,960.00

3.1600 M' 17,000.00 53,720.00

15.0000 Bh 500.00 7,500.00

25.0000 Bh 400.00 10,000.00

Dynabolt ǿ 12 x 120mm 4.0000 bh 7,000.00 28,000.00

Tukang 0.2470 Org/Hr 61,600.00 15,215.20

Kepala Tukang 0.1170 Org/Hr 74,600.00 8,728.20

Pekerja 0.1170 Org/Hr 37,100.00 4,340.70

Alat Bantu (Bor Listrik)/Genset 1.0000 Ls 5,000.00 5,000.00

Jumlah 180,464.10

10 1M2 PEK. PENUTUP ATAP SENG GELOMBANG BJLS. 0,20 (PADA RANGKA BAJA RINGAN)

Seng Gelombang (BJLS. 0,20) 0.9000 M2 48,000.00 43,200.00

12.0000 Bh 1,000.00 12,000.00

Tukang 0.4500 Org/Hr 61,600.00 27,720.00

Kepala Tukang 0.0450 Org/Hr 74,600.00 3,357.00

Pekerja 0.3500 Org/Hr 37,100.00 12,985.00

Mandor 0.0350 Org/Hr 69,100.00 2,418.50

Jumlah 101,680.50

11 1m1 PEK. BUBUNGAN ATAP SENG PLAT/TALANG DAN JURAI

Seng Plat Bubungan/Talang/Jurai 1.1000 M' 35,000.00 38,500.00

12.0000 Bh 1,000.00 12,000.00

Tukang 0.1500 Org/Hr 61,600.00 9,240.00

Kepala Tukang 0.0150 Org/Hr 74,600.00 1,119.00

Pekerja 0.1000 Org/Hr 37,100.00 3,710.00

Mandor 0.0100 Org/Hr 69,100.00 691.00

Jumlah 65,260.00

12 1M2 PEK. PENUTUP ATAP GENTENG METAL

Atap Genteng Metal 0,30 1.1600 M2 105,000.00 121,800.00

12.0000 Bh 1,000.00 12,000.00

Tukang 0.4500 Org/Hr 61,600.00 27,720.00

Kepala Tukang 0.0450 Org/Hr 74,600.00 3,357.00

Pekerja 0.3500 Org/Hr 37,100.00 12,985.00

Mandor 0.0350 Org/Hr 69,100.00 2,418.50

Jumlah 180,280.50

13 1m1 PEK. JURAI / BUBUNGAN ATAP GENTENG METAL

Jurai / Bubungan Genteng Metal 1.1000 M' 35,000.00 38,500.00

12.0000 Bh 1,000.00 12,000.00

Tukang 0.1750 Org/Hr 61,600.00 10,780.00

Kepala Tukang 0.0175 Org/Hr 74,600.00 1,305.50

Pekerja 0.1000 Org/Hr 37,100.00 3,710.00

Mandor 0.0100 Org/Hr 69,100.00 691.00

Jumlah 66,986.50

1 1M2 PEK. LISPLANK (Kalsi Plank 9mm/300mm)

Kalsi Plank 9mm/300mm 1.1000 M' 45,000.00 49,500.00

15.0000 Bh 500.00 7,500.00

Tukang 0.2000 Org 61,600.00 12,320.00

Kep.Tukang 0.0100 Org 74,600.00 746.00

Pekerja 0.1000 Org 37,100.00 3,710.00

Mandor 0.0050 Org 69,100.00 345.50

Jumlah 74,121.50

Main Truss C.75.- 0,8mm

Roof Batten/Reng 41.35.0.45

Self Drilling Screw Ø 6-20mm(Truss Screw)

Self Drilling Screw Ø 4-16mm(R.B. Screw)

Paku Sekrup Ø 4mm - 50mm

Paku Sekrup Ø 4mm - 50mm

Paku Sekrup Ø 4mm - 50mm

Paku Sekrup Ø 4mm - 50mm

Self Drilling Screw Ø 6-20mm (Screw)

Page 22: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 22

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

14 1M2 PEK. LISPLANK (PAPAN 2/20)

Papan Kls II/mahoni 0.0140 M3 4,178,976.27 58,505.67

Paku 5cm - 7 cm 0.0500 Kg 20,000.00 1,000.00

Tukang 0.8000 Org 61,600.00 49,280.00

Kep.Tukang 0.0800 Org 74,600.00 5,968.00

Pekerja 0.2800 Org 37,100.00 10,388.00

Mandor 0.0140 Org 69,100.00 967.40

Jumlah 126,109.07

15 1 M' PEK. TALANG JURAI

Seng Datar BJLS 0,30 1.0000 M' 35,000.00 35,000.00

Papan Kayu Klas II 0.0180 M3 4,178,976.27 75,221.57

Paku < 5 Cm 0.1100 Kg 20,000.00 2,200.00

Tukang 0.1750 Org 61,600.00 10,780.00

Kep. Tukang 0.0600 Org 74,600.00 4,476.00

Pekerja 0.6000 Org 37,100.00 22,260.00

Mandor 0.3500 Org 69,100.00 24,185.00

Jumlah 174,122.57

16 1 M2 PEK. ATAP SENG GELOMBANG BJS 0.20 (PADA RANGKA KAYU)

Seng Bjls 0.20 0.9000 Lbr 48,000.00 43,200.00

Paku Seng 9.0000 Biji 250.00 2,250.00

Tukang 0.2000 Org 61,600.00 12,320.00

Kep.Tukang 0.0200 Org 74,600.00 1,492.00

Pekerja 0.1000 Org 37,100.00 3,710.00

Mandor 0.0050 Org 69,100.00 345.50

Jumlah 63,317.50

17 1M' PEK.BUBUNGAN SENG PLAT BJLS 0.20 (PADA RANGKA KAYU)

Seng Plat Bjls 0.20 lbr 50cm 1.0000 M' 35,000.00 35,000.00

Paku Seng 6.0000 biji 250.00 1,500.00

Tukang 0.2000 Org 61,600.00 12,320.00

Kep.Tukang 0.0200 Org 74,600.00 1,492.00

Pekerja 0.1000 Org 37,100.00 3,710.00

Mandor 0.0050 Org 69,100.00 345.50

Jumlah 54,367.50

18 1 M2 DAUN PINTU DOUBLE TEAK WOOD

Papan3 cm Kls II/Non lokal 0.0250 M3 4,178,976.27 104,474.41

Teakwood (110 x 210) 0.8600 lbr 110,000.00 94,600.00

Paku halus 0.0300 Kg 25,000.00 750.00

Lem aica aibon 0.5000 Kg 50,000.00 25,000.00

Tukang 2.0000 Org 61,600.00 123,200.00

Kep.Tukang 0.2000 Org 74,600.00 14,920.00

Pekerja 0.6000 Org 37,100.00 22,260.00

Mandor 0.0300 Org 69,100.00 2,073.00

Jumlah 387,277.41

19 1M2 PEK. PINTU TRIPLEX LAPIS ALUMINIUM

Papan 3 Cm Kls II/Non lokal 0.0270 M3 4,178,976.27 112,832.36

Trikplex Lapis Aluminium 0.3360 lbr 100,000.00 33,595.00

Trikplex 3mm 0.3360 lbr 82,000.00 27,547.90

Paku halus 0.0900 Kg 25,000.00 2,250.00

Lem aica aibon 0.3000 Kg 50,000.00 15,000.00

Tukang 3.6000 Org 61,600.00 221,760.00

Kep.Tukang 0.3600 Org 74,600.00 26,856.00

Pekerja 2.4000 Org 37,100.00 89,040.00

Mandor 0.2400 Hok 69,100.00 16,584.00

Jumlah 545,465.26

20 1 M2 BOVEN KACA MATI POLOS 5mm ZIG - ZAG

Kaca Polos 5 mm 1.0000 M2 200,000.00 200,000.00

List Papan 3 cm Kls II/ Non lokal 0.0040 m3 4,178,976.27 16,715.91

Tukang 1.0000 Org 61,600.00 61,600.00

Kep.Tukang 0.2500 Org 74,600.00 18,650.00

Pekerja 0.7500 Org 37,100.00 27,825.00

Mandor 0.1000 Org 69,100.00 6,910.00

Jumlah 331,700.91

Page 23: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 23

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

21 PEK. PARTISI PEMBAGI RUANGAN

a. KUSEN ALUMINIUM TIPE P3 TERPASANG 146.5000 M' 221,713.00 32,480,954.50

b. PAS. DAUN PINTU ALUMINIUM TIPE P3

Kaca Rayban 5 mm 8.4810 M2 250,000.00 2,120,250.00

Rangka Aluminium 45.0000 M' 60,000.00 2,700,000.00

List Kaca dari Karet 450.0000 M' 3,000.00 1,350,000.00

Tukang Besi 10.0000 Org/Hr 61,600.00 616,000.00

Kepala Tukang 1.0000 Org/Hr 74,600.00 74,600.00

Pekerja 5.0000 Org/Hr 37,100.00 185,500.00

Mandor 0.5000 Org/Hr 69,100.00 34,550.00

c. PENUTUP PARTISI CASIBORD 59.1075 M2 85,000.00 5,024,137.50

Sekrup 177.3225 Bh 400.00 70,929.00

Pekerja 5.9000 Org/Hari 37,100.00 218,890.00

Tukang 14.7500 Org/Hari 61,600.00 908,600.00

Kepala Tukang 2.9500 Org/Hari 74,600.00 220,070.00

Mandor 0.0295 Org/Hari 69,100.00 2,038.45

Jumlah 46,006,519.45

IV PEK. LANTAI, PLAFOND TEXTUR TEMBOK DAN CAT1 1 M3 PEK. BETON TUMBUK/NEUT KUSEN 1Pc:3Psr:5Krl dipleter 1:3 Tebal 1 cm dan diaci

Semen 50 Kg 4.3600 Zak 76,330.49 332,800.92

Pasir 0.5200 M3 316,800.30 164,736.16

Kerikil 0.8700 M3 529,069.20 460,290.21

Tukang 0.2500 Org 61,600.00 15,400.00

Kep.Tukang 0.0250 Org 74,600.00 1,865.00

Pekerja 1.6500 Org 37,100.00 61,215.00

Mandor 0.0800 Org 69,100.00 5,528.00

Jumlah 1,041,835.28

2 1 M2 PEK.LANTAI RABAT BETON (1PC:3Psr:5Krl) dipleter 1:3 tbl 1cm + diaci dengan Saus Semen

Semen 50 Kg 4.6000 Zak 76,330.49 351,120.24

Pasir 0.6300 M3 316,800.30 199,584.19

Kerikil 0.7600 M3 529,069.20 402,092.59

Tukang 0.2000 Org 61,600.00 12,320.00

Kep.Tukang 0.0200 Org 74,600.00 1,492.00

Pekerja 1.2000 Org 37,100.00 44,520.00

Mandor 0.0600 Org 69,100.00 4,146.00

Jumlah A 1,015,275.02 1 M2 Pek. Lantai Rabat Tebal 5cm : ( 5 / 100 x A ) 50,763.75 1 M2 Pek. Lantai Rabat Tebal 7cm : ( 7 / 100 x A ) 71,069.25

3 1M2 PEK LANTAI KERAMIK

Keramik 40 x 40 cm Kwalitas "A" 1.1000 M2 85,000.00 93,500.00

Semen 0.2700 Zak 76,330.49 20,609.23

Pasir 0.0420 M3 316,800.30 13,305.61

Tukang 0.2500 Org 61,600.00 15,400.00

Kep.Tukang 0.0250 Org 74,600.00 1,865.00

Pekerja 0.1500 Org 37,100.00 5,565.00

Mandor 0.0250 Org 69,100.00 1,727.50

Jumlah 151,972.34

4 1M2 PEK DINDING KERAMIK

Keramik 20 x 25 cm 1.1000 M2 75,000.00 82,500.00

Semen 0.2700 Zak 76,330.49 20,609.23

Pasir 0.0420 M3 316,800.30 13,305.61

Tukang 0.2500 Org 61,600.00 15,400.00

Kep.Tukang 0.0250 Org 74,600.00 1,865.00

Pekerja 0.1000 Org 37,100.00 3,710.00

Mandor 0.0250 Org 69,100.00 1,727.50

Jumlah 139,117.34

5 1M2 PEK TEXTUR TEMBOK BATU ALAM

Batu Alam Bertekstur (10 x 20) 1.1000 M2 115,000.00 126,500.00

Semen 0.2700 Zak 76,330.49 20,609.23

Pasir 0.0420 M3 316,800.30 13,305.61

Tukang 0.2500 Org 61,600.00 15,400.00

Kep.Tukang 0.0250 Org 74,600.00 1,865.00

Pekerja 0.1000 Org 37,100.00 3,710.00

Mandor 0.0250 Org 69,100.00 1,727.50

Jumlah 183,117.34

Page 24: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 24

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

6 1M2 PEK LANTAI KERAMIK

Keramik 20 x 20 cm 1.1000 M2 75,000.00 82,500.00

Semen 0.2700 Zak 76,330.49 20,609.23

Pasir 0.0420 M3 316,800.30 13,305.61

Tukang 0.2500 Org 61,600.00 15,400.00

Kep.Tukang 0.0250 Org 74,600.00 1,865.00

Pekerja 0.1000 Org 37,100.00 3,710.00

Mandor 0.0250 Org 69,100.00 1,727.50

Jumlah 139,117.34

7 1M2 PEK KERAMIK ANTI SLIP

Keramik 20 x 25 cm 1.1000 M2 80,000.00 88,000.00

Semen 0.2700 Zak 76,330.49 20,609.23

Pasir 0.0420 M3 316,800.30 13,305.61

Tukang 0.2500 Org 61,600.00 15,400.00

Kep.Tukang 0.0250 Org 74,600.00 1,865.00

Pekerja 0.1000 Org 37,100.00 3,710.00

Mandor 0.0250 Org 69,100.00 1,727.50

Jumlah 144,617.34

8 1 M2 PEK PLAFOND TRIKPLEKS + RANGKA

Kayu usuk 5/7 cm Klas II 0.0140 M3 4,578,976.27 64,105.67

Paku biasa 0.1000 Kg 20,000.00 2,000.00

Triplex 3mm 0.3359 Lbr 82,000.00 27,543.80

Triplex 6mm 0.3359 Lbr 95,000.00 31,910.50

kalsiboard 6mm 0.3359 Lbr 180,000.00 60,462.00

Paku Triplex 0.0500 Kg 25,000.00 1,250.00

Tukang 0.2500 Org 61,600.00 15,400.00

Kep.Tukang 0.0400 Org 74,600.00 2,984.00

Pekerja 0.2800 Org 37,100.00 10,388.00

Mandor 0.0140 Org 69,100.00 967.40

Plafond Triplex 3mm : 124,638.87

Plafond Triplex 6mm : 129,005.57

Plafond Kalsiboard 6mm : 157,557.07

9 1 M' PEK LIST PLAFOND

List Plafond Papan Profil Lbr 2/55cm 1.0000 M' 15,000.00 15,000.00

List Plafond Triplex 9mm Lbr. 5cm 1.0000 M' 3,500.00 3,500.00

6.0000 Bh 1,000.00 6,000.00

Pekerja 0.1000 Org 37,100.00 3,710.00

Mandor 0.0140 Org 69,100.00 967.40

List Plafond Papan Profil 2/5cm (lbr.5cm) : 25,677.40

List Plafond Triplex 9mm (lbr.5cm) : 14,177.40

10 1M2 PEK. PLAFOND TRIPLEX 6mm dan KALSIBOARD 6mm. - RANGKA METAL HOLLOW

Tripleks 6 mm 0.6500 Lbr 95,000.00 61,750.00

Kalsiboard 6 mm 0.6500 Lbr 180,000.00 117,000.00

Rangka Metal 3.7000 M' 17,000.00 62,900.00

Sekrup 0.0096 Kg 35,000.00 336.00

Tukang 0.0850 Org/Hr 61,600.00 5,236.00

Kepala Tukang 0.0075 Org/Hr 74,600.00 559.50

Pekerja 0.0450 Org/Hr 37,100.00 1,669.50

Mandor 0.0080 Org/Hr 69,100.00 552.80

Plafond Triplex 6mm : 133,003.80

Plafond Kalsiboard 6mm : 188,253.80

11 1M1 PEK. LIST PLAFOND GIPSUM

List Plafon Gypsum 1.1000 M' 20,000.00 22,000.00

Tukang 0.0230 Org/Hr 61,600.00 1,416.80

Pekerja 0.0150 Org/Hr 37,100.00 556.50

Jumlah 23,973.30

12 1 M2 PEK CAT TEMBOK

Cat Kualitas "A" 0.3400 Kg 35,000.00 11,900.00

Plamir 0.1200 Kg 19,250.00 2,310.00

Amplas 0.2000 Lbr 4,500.00 900.00

Kuas Biasa 4" 0.0050 Bh 15,000.00 75.00

Kuas Roll 0.0050 Bh 25,000.00 125.00

Tukang 0.1200 Org 61,600.00 7,392.00

Kep.Tukang 0.0120 Hok 74,600.00 895.20

Pekerja 0.0250 Hok 37,100.00 927.50

Mandor 0.0010 Hok 69,100.00 69.10

Jumlah 24,593.80

Paku Sekrup Ø 4mm - 50mm

Page 25: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 25

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

13 1 M2 PEK CAT PLAFOND

Cat Kualitas "A" 0.3400 Kg 35,000.00 11,900.00

Kuas Roll 0.0050 Bh 19,250.00 96.25

Kuas Biasa 4" 0.0050 Bh 15,000.00 75.00

Tukang 0.1200 Hok 61,600.00 7,392.00

Kep.Tukang 0.0120 Hok 74,600.00 895.20

Pekerja 0.0250 Hok 37,100.00 927.50

Mandor 0.0010 Hok 69,100.00 69.10

Jumlah 21,355.05

14 10 M2 PEK. CAT MENIE KAYU

Cat Menie 1.2000 Kg 30,000.00 36,000.00

Minyak Cat 0.3000 Kg 30,000.00 9,000.00

Kuas 0.0050 bh 15,000.00 75.00

Tukang 2.5000 Org 61,600.00 154,000.00

Mandor 0.0650 Org 69,100.00 4,491.50

Jumlah 203,566.50

Tiap M2 memerlukan 20,356.65

15 10 M2 PEK CAT WARNA 1 X DASAR; 2X KILAP

Cat Dasar 1.4200 Kg 30,000.00 42,600.00

Cat Kilat /Warna 2.8000 Kg 50,000.00 140,000.00

Minyak cat 1.2000 Kg 30,000.00 36,000.00

Dumpul 0.5000 Kg 30,000.00 15,000.00

Kwas Biasa 4" 0.0500 Bh 15,000.00 750.00

Tukang 1.5000 Org 61,600.00 92,400.00

Kep.Tukang 0.1500 Org 74,600.00 11,190.00

Pekerja 0.4500 Org 37,100.00 16,695.00

Mandor 0.0225 Org 69,100.00 1,554.75

Jumlah Cat Warna /10 m2 : 356,189.75

Tiap M2 memerlukan : 35,618.98 16 1M2 PEK. POLITUR / TAEK OIL

Politur 0.2300 Ltr 38,500.00 8,855.00

Amplas 0.2500 Lbr 4,500.00 1,125.00

Kuas biasa 0.1000 bh 15,000.00 1,500.00

Tukang 0.3400 Org 61,600.00 20,944.00

Kep.Tukang 0.0340 Org 74,600.00 2,536.40

Pekerja 0.1000 Org 37,100.00 3,710.00

Mandor 0.0100 Org 69,100.00 691.00

Jumlah 39,361.40

17 1M2 PEK. CAT PERMUKAAN BAJA DENGAN CAT BESI/WARNA

Cat Besi/Warna 0.1000 Kg 50,000.00 5,000.00

Kuas biasa 0.0100 Bh 15,000.00 150.00

Tukang 0.2000 Org 61,600.00 12,320.00

Kep.Tukang 0.0200 Org 74,600.00 1,492.00

Pekerja 0.0200 Org 37,100.00 742.00

Mandor 0.0100 Org 69,100.00 691.00

Jumlah 20,395.00

V PEKERJAAN SANITAIR PENGUNCI DAN PENGGANTUNG1 PAS KUNCI TANAM DOBLE SLAAG

1.0000 set 215,000.00 215,000.00

Upah + Alat Bantu = 25% x Hrg Bahan 0.2500 Org 215,000.00 53,750.00

Jumlah 268,750.00

2 PAS HANDLE/GAGANG PINTU

Handle/Gagang Pintu 1.0000 Bh 250,000.00 250,000.00

Upah + Alat Bantu = 25% x Hrg Bahan 0.2500 Org 215,000.00 53,750.00

Jumlah 303,750.00

3 PAS. ENGSEL KUNIG PINTU

Ensel kuning pintu 1.0000 set 25,000.00 25,000.00

Upah + Alat Bantu = 25% x Hrg Bahan 0.2500 Org 6,250.00

Jumlah 31,250.00

4 PAS. ENGSEL KUNING JENDELA

Ensel kuning jendela 1.0000 set 17,500.00 17,500.00

Upah + Alat Bantu = 25% x Hrg Bahan 0.2500 Org 4,375.00

Jumlah 21,875.00

Kunci tanam 2 slaag Tipe I

Page 26: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 26

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

5 PAS. GRENDEL PINTU

Grendel pintu 1.0000 set 17,500.00 17,500.00

Upah + Alat Bantu = 25% x Hrg Bahan 0.2500 Org 4,375.00

Jumlah 21,875.00

6 PAS. GRENDEL JENDELA

Grendel jendela 1.0000 set 15,000.00 15,000.00

Upah + Alat Bantu = 25% x Hrg Bahan 0.2500 Org 3,750.00

Jumlah 18,750.00

7 PAS.KAIT ANGIN JENDELA

Kait angin jendela Type "a" 1.0000 set 20,000.00 20,000.00

Kait angin jendela Type "c" 1.0000 set 7,500.00 7,500.00

Upah + Alat Bantu = 25% x Hrg Bahan 0.2500 Org 5,000.00

Type "a" 25,000.00

Type "c" 12,500.00

8 1 UNIT BAK KM/WC PAS. KERAMIK 0,50 x 0,50 x 0,75 m

Pasangan Batu Potong 0.1800 M3 824,129.30 148,343.27

Pasangan Keramik 3.2000 M2 139,117.34 445,175.50

Jumlah 593,518.77

9 1BH BAK MANDI FIBER GLASS VOL 0,30 m³

Bak Fibreglass (Kotak) 120 ltr. 1.0000 bh 260,000.00 260,000.00 Perlengkapan (18% x Harga Bahan) 0.1800 Set 260,000.00 46,800.00 Pekerja 1.8000 OH 37,100.00 66,780.00 Tukang Batu 2.7000 OH 61,600.00 166,320.00 Kepala Tukang 0.5400 OH 74,600.00 40,284.00 Mandor 0.1100 OH 69,100.00 7,601.00

Jumlah 587,785.00

10 1 BH. PAS. CLOSED DUDUK

Klosed Duduk + Acecories 1.0000 Bh 600,000.00 600,000.00

Pekerja 0.3300 Org/hr 37,100.00 12,243.00

Tukang 1.1000 Org/hr 61,600.00 67,760.00

Kepala Tukang 0.0010 Org/hr 74,600.00 74.60

Mandor 0.0160 Org/hr 69,100.00 1,105.60

Jumlah 681,183.20

11 1 BH. PAS. CLOSED JONGKOK

Klosed Jongkok 1.0000 Bh 200,000.00 200,000.00

Semen PC 50kg. 0.1200 Zak 76,330.49 9,159.66

Pasir Pasang 0.0100 M3 316,800.30 3,168.00

Pekerja 0.2000 Org/hr 37,100.00 7,420.00

Tukang 1.1000 Org/hr 61,600.00 67,760.00

Kepala Tukang 0.1100 Org/hr 74,600.00 8,206.00

Mandor 0.0100 Org/hr 69,100.00 691.00

Jumlah 296,404.66

12 1 BH. PEK FLOOR DRAIN

Floor Drain 1.0000 Bh 20,000.00 20,000.00

Tukang 0.1000 Org 61,600.00 6,160.00

Mandor 0.0100 Org 69,100.00 691.00

Jumlah 26,851.00

13 1 BH. PEK WASTAVEL

Wastavel 1.0000 Bh 280,000.00 280,000.00

Tukang 0.3000 Org 61,600.00 18,480.00

Mandor 0.0100 Org 69,100.00 691.00

Jumlah 299,171.00

14 1 M' PEK. INTALASI PIPA GALVANIS AIR BERSIH 1/2"

Pipa 1/2" 0.2500 M' 220,000.00 55,000.00 Soket 3.0000 Bh 9,900.00 29,700.00 Selotip Pipa 0.4500 Bh 5,000.00 2,250.00 Elbow/ T. 1/2 " 0.2500 Bh 6,000.00 1,500.00 Kepala Tukang 0.1500 Org 74,600.00 11,190.00 Tukang Pipa 0.0750 Hok 61,600.00 4,620.00 Pekerja 0.0250 Hok 37,100.00 927.50 Mandor 0.0025 Hok 69,100.00 172.75

Jumlah 105,360.25 15 1 Bh BAK CUCI STEINLESS STEEL

Bak Cuci Stainless 1.0000 Bh 425,000.00 425,000.00

Upah + Alat Bantu = 25% x Hrg Bahan 0.2500 Org 425,000.00 106,250.00

Jumlah 531,250.00

Page 27: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 27

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

16

Stop Kran 1/2" 1.0000 Bh 25,000.00 25,000.00

Tukang 0.1000 Org 61,600.00 6,160.00

Mandor 0.0100 Org 69,100.00 691.00

Jumlah 31,851.00

17 Pas. 1 m' Pipa PVC tipe AW Ø 1/2 "Pipa PVC Ø 1/2" 1.1000 m' 11,250.00 12,375.00

Perlengakapan (35% harga Pipa) 0.3500 Set 11,250.00 3,937.50

Pekerja 0.0360 Org/hr 37,100.00 1,335.60

Tukang 0.0600 Org/hr 61,600.00 3,696.00

Kepala Tukang 0.0060 Org/hr 74,600.00 447.60

Mandor 0.0018 Org/hr 69,100.00 124.38

Jumlah 21,916.08

18 Pas. 1 m' Pipa PVC tipe AW Ø 2 "Pipa PVC Ø 2" 1.1000 m' 24,950.00 27,445.00

Perlengakapan (35% harga Pipa) 0.3500 Set 24,950.00 8,732.50

Pekerja 0.0360 Org/hr 37,100.00 1,335.60

Tukang 0.0600 Org/hr 61,600.00 3,696.00

Kepala Tukang 0.0060 Org/hr 74,600.00 447.60

Mandor 0.0018 Org/hr 69,100.00 124.38

Jumlah 41,781.08

19 Pas. 1 m' Pipa PVC tipe AW Ø 3 "Pipa PVC Ø 3" 1.1000 m' 166,500.00 183,150.00

Perlengakapan (35% harga Pipa) 0.3500 Set 166,500.00 58,275.00

Pekerja 0.0360 Org/hr 37,100.00 1,335.60

Tukang 0.0600 Org/hr 61,600.00 3,696.00

Kepala Tukang 0.0060 Org/hr 74,600.00 447.60

Mandor 0.0018 Org/hr 69,100.00 124.38

Jumlah 247,028.58

20 Pas. 1 m' Pipa PVC tipe AW Ø 4 "Pipa PVC Ø 4" 1.1000 m' 199,650.00 219,615.00

Perlengakapan (35% harga Pipa) 0.3500 Set 199,650.00 69,877.50

Pekerja 0.0360 Org/hr 37,100.00 1,335.60

Tukang 0.0600 Org/hr 61,600.00 3,696.00

Kepala Tukang 0.0060 Org/hr 74,600.00 447.60

Mandor 0.0018 Org/hr 69,100.00 124.38

Jumlah 295,096.08

21 1 UNIT PEK.SEPTICTANK

Galian Tanah Biasa 3.5000 M3 31,280.00 109,480.00

Urugan Tanah Bekas Galian 1.1667 M3 22,370.85 26,099.40

Urugan Pasir 0.1500 M3 187,981.36 28,197.20

Pasangan Batu Kosongan 0.4875 M3 276,614.05 134,849.35

Beton rabat 2.6500 M2 1,015,275.02 2,690,478.80

Pasangan Batu Karang 2.5500 M3 813,988.98 2,075,671.90

Beton Bertulang 1:2:3 0.4500 M3 5,174,826.46 2,328,671.91

Plesteran transram 15.0000 M2 46,045.82 690,687.31

Acian 15.0000 M2 15,445.74 231,686.08

Pipa PVC 3" 1.8000 btg 99,800.00 179,640.00

BAK PERESAPAN

Bak Peresapan 0.1250 Bh 250,000.00 31,250.00

Urugan Kerikil 0.1250 620,250.58 77,531.32

Jumlah 8,604,243.28

VI PEKERJAAN INSTALASI MEKANIKAL ELEKTRIKAL1 1 TITIK PASANG TITIK SAMBUNGAN INSTALASI

Kabel ETERNA 2x2,5 mm 8.0000 M' 17,500.00 140,000.00

Pipa Paralon 3/8" 2.5000 M' 6,500.00 16,250.00

T dos 1.0000 Bh 5,000.00 5,000.00

Isolasi 0.3000 Bh 10,000.00 3,000.00

Benang Isolasi 0.8000 M' 10,000.00 8,000.00

Isolator Cap 5.0000 Bh 3,500.00 17,500.00

Isolator Kecil 4.0000 Bh 2,000.00 8,000.00

Tukang Listrik 0.2000 Org 61,600.00 12,320.00

Pekerja 0.0800 Org 37,100.00 2,968.00

Senior Instalator 0.0100 Org 70,000.00 700.00

Jumlah 213,738.00

1 BH. PEK KRAN AIR Ø 1/2 "

M3

Page 28: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 28

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

2 1 M' INSTALASI KABEL

Kabel ETERNA 2x1,5 mm 1.0500 M' 15,000.00 15,750.00

Isolasi 0.3000 Bh 10,000.00 3,000.00

Klem Kabel 9mm 4.0000 Bh 500.00 2,000.00

Tukang Listrik 0.2000 Org 61,600.00 12,320.00

Pekerja 0.0800 Org 37,100.00 2,968.00

Senior Instalator 0.0100 Org 70,000.00 700.00

Jumlah 36,738.00

3 1 M' INSTALASI KABEL DAK

Kabel Dak 30mm 1.0500 M' 17,000.00 17,850.00

Kabel Dak 50mm 1.0500 M' 20,000.00 21,000.00

Harga Bahan/Material : 38,850.00

Tukang Listrik 0.2000 Org 61,600.00 12,320.00

Pekerja 0.0800 Org 37,100.00 2,968.00

Senior Instalator 0.0100 Org 70,000.00 700.00

Peralatan (18% x harga Bahan/Material) 0.1800 Set 38,850.00 6,993.00

Instalasi Kabel Dak 30mm : 40,831.00

Instalasi Kabel Dak 50mm : 43,981.00

4 PAS. SEKRING CAST

Sekring Cast 3 Fase 1.0000 Bh 100,000.00 100,000.00

Ongkos kerja 5% x Hrg Bahan 0.0500 Org 5,000.00

Jumlah 105,000.00

5 PAS. STOP KONTAK

Stop Kontak Tanam 1.0000 Bh 15,000.00 15,000.00

Terminal 4 Lubang 1.0000 Bh 27,500.00 27,500.00

Steker Saklar 1.0000 Bh 17,000.00 17,000.00

Upahj kerja 5% x Hrg Bahan 0.0500 Org 59,500.00 2,975.00

Stop Kontak Tanam 17,975.00

Terminal 4 Lubang 30,475.00

Steker Saklar 19,975.00

6 PAS. SAKLAR TUNGGAL

Saklar Tunggal 1.0000 Bh 25,000.00 25,000.00

Ongkos kerja 5% x Hrg Bahan 0.0500 Org 25,000.00 1,250.00

Jumlah 26,250.00

7 PAS. SAKLAR GANDA

Saklar Ganda 1.0000 Bh 35,000.00 35,000.00

Ongkos kerja 5% x Hrg Bahan 0.0500 Org 1,750.00

Jumlah 36,750.00

8 PAS. SAKLAR TRIPLE

Saklar Triple 1.0000 Bh 40,000.00 40,000.00

Ongkos kerja 5% x Hrg Bahan 0.0500 Org 40,000.00 2,000.00

Jumlah 42,000.00

9 PAS. TITIK LAMPU

Lampu Spiral 24 Watt Philips 1.0000 Bh 75,000.00 75,000.00

Lampu Spiral 18 Watt Philips 1.0000 Bh 60,000.00 60,000.00

Lampu Spiral 10 Watt Philips 1.0000 Bh 35,000.00 35,000.00

Fitting Tempel 1.0000 Bh 17,500.00 17,500.00

Upah + Perlengkapan 5% x Hrg Bahan 0.0500 Org 187,500.00 9,375.00

Jumlah lampu 24 watt 101,875.00

Jumlah lampu 18 watt 86,875.00

Jumlah lampu 10 watt 61,875.00

10 PAS. TITIK LAMPU PIJAR

Lampu Pijar Tanam 50 Watt + asesories 1.0000 Bh 80,000.00 80,000.00

Upah + Perlengkapan 18% x Hrg Bahan 0.1800 Org 80,000.00 14,400.00

Jumlah 94,400.00

11 PAS. LAMPU TANAM TL 40 Watt (double)

Lampu TL 40 Watt 1.0000 Bh 85,000.00 85,000.00

Upah + Perlengkapan 18% x Hrg Bahan 0.1800 Org 85,000.00 15,300.00

Jumlah 100,300.00

12 1 UNIT. PAS. ACB + BOX

ACB 9 Apere 1.0000 Bh 100,000.00 100,000.00

Box Sekring MCB 1.0000 Bh 80,000.00 80,000.00

Upah + Perlengkapan 18% x Hrg Bahan 0.1800 Org 180,000.00 32,400.00

Jumlah 212,400.00

Page 29: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 29

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

13 1 UNIT. BOX SEKRING ACB

Box Sekring MCB 1.0000 Bh 80,000.00 80,000.00

Upah + Perlengkapan 18% x Hrg Bahan 0.1800 Org 80,000.00 14,400.00

Jumlah 94,400.00

VII PEKERJAAN PAVING, KANSTEEN, LEANING BETON DAN TERALIS1 1M2 PEK. PAS. PAVING STONE/PAVING BLOCK SEGI 6 NATURAL TEBAL 8CM.

Paving Block Segi 6 Natural 50.0000 Bh 2,500.00 125,000.00

Pasir Urug Dipadatkan 0.1000 M3 146,800.30 14,680.03

Pekerja 0.2500 Hok 37,100.00 9,275.00

Tukang 0.5000 Hok 61,600.00 30,800.00

Kepala Tukang 0.0500 Hok 74,600.00 3,730.00

Mandor 0.0250 Hok 69,100.00 1,727.50

Jumlah 185,212.53

2 1M3 PEK. BETON TUMBUK PRACETAK dan LENING PILAR BETON 1Pc:3Psr:5Krl.

a. Beton Tumbuk

Semen Portland (50 kg) 4.3600 Zak 76,330.49 332,800.92

Pasir Beton 0.5200 M3 316,800.30 164,736.16

Kerikil Pecah/Koral Beton 2/3 0.8700 Hok 679,069.20 590,790.21

Tukang 0.2500 Org 61,600.00 15,400.00

Kep.Tukang 0.0250 Org 74,600.00 1,865.00

Pekerja 1.6500 Org 37,100.00 61,215.00

Mandor 0.0800 Org 69,100.00 5,528.00

Jumlah 1,172,335.28

b. Bekisting Cetakan Beton

Begisting Triplex 9mm 1.0000 M2 174,640.79 174,640.79

Paku 0.5500 Kg 20,000.00 11,000.00

Kep.Tukang 0.2500 Org 74,600.00 18,650.00

Tukang 2.0000 Org 61,600.00 123,200.00

Mandor 0.3000 Org 69,100.00 20,730.00

Pekerja pembongkaran begesting 2.0000 Org 37,100.00 74,200.00

Jumlah 422,420.79

Jumlah a+b 1,594,756.07

3 1M2 PEKERJAAN PEMBERSIHAN PAGAR KRUM

Bahan Pembersih/Autosol 0.5000 Tube 15,000.00 7,500.00

Pekerja 0.1000 Org 37,100.00 3,710.00

Mandor 0.0500 Org 69,100.00 3,455.00

Alat bantu 0.3000 Set 50,000.00 15,000.00

Jumlah 29,665.00

4 1.TITIK PEKERJAAN PEPENGELASAN

Pengelasan 1.0500 titik 3,000.00 3,150.00

Tukang Las 0.0060 Org 61,600.00 369.60

Alat bantu 0.0600 Set 50,000.00 3,000.00

Jumlah 6,519.60

5

Pipa GIP 1,5diem 1.1000 M' 109,500.00 120,450.00

Pipa GIP 1diem 4.1000 M' 62,500.00 256,250.00

Besi Beton 12mm 12.3000 M' 10,500.00 129,150.00

Besi Beton 6mm 4.4200 M' 3,200.00 14,144.00

Cat Warna 1.0000 M2 20,395.00 20,395.00

Pengelasan 65.0000 titik 3,000.00 195,000.00

Acecories/Tombak 9.0000 Bh 3,500.00 31,500.00

Baut/Sekrup/Acecories 4.5000 Bj 1,000.00 4,500.00

Tukang 0.0625 Org 61,600.00 3,850.00

Kep. Tukang 0.0060 Org 74,600.00 447.60

Pekerja 0.0060 Org 37,100.00 222.60

Mandor 0.0003 Org 69,100.00 20.73

Jumlah 775,929.93

1M2 PEK. TERALIS BESI BETON Ø12mm KEMBANG Ø6mm RANGKA PIPA GIP.

Page 30: RAB Gudang Bahan Pangan

Analisa Harga Satuan STANDAR (SNI) Halaman : 30

No URAIAN JENIS PEKERJAAN VOLUMEHARGA SATUAN JUMLAH HARGA

(Rp) (Rp)

6 1M2 PEK. TERALIS BESI PENUTUP SALURAN

Besi siku L.7mm 5.0000 M' 35,000.00 175,000.00

Besi siku L.5mm 9.0000 M' 25,000.00 225,000.00

Cat Warna 1.0000 M2 20,395.00 20,395.00

Pengelasan 108.0000 titik 3,000.00 324,000.00

Tukang 0.0625 Org 61,600.00 3,850.00

Kep. Tukang 0.0060 Org 74,600.00 447.60

Pekerja 0.0060 Org 37,100.00 222.60

Mandor 0.0003 Org 69,100.00 20.73

Jumlah 748,935.93

Waikabubak,....................2014Disetujui, Dibuat

Engineering Consultan Engineering Consultan stance construction consultant stance construction consultant

Claudius Herry, ST Kristianus Behar, ST Inspector Engineer

Page 31: RAB Gudang Bahan Pangan

URAIAN ANALISA HARGA SATUAN

BIAYA Rp 187,936.57

TAHUN ANGGARAN 2014

No. U R A I A N KODE KOEFISIEN KETERANGAN

BATU KARANG

A ASUMSI :1 Batu Karang diangkut dari Quary2 Jarak angkut rata-rata L 12.00 KM3 Harga Dasar Batu Karang BK 129,000.00 Rp/M34 Harga Satuan Dumptruck DT 148,107.14 Rp/Jam

B PERHITUNGAN :1 Dump Truck2 Kapasitas bak Kb 3.00 M33 Eisiensi Alat Ea 0.90 Muatan sedang4 Kecepatan Rata-rata bermuatan V1 30.00 Km/jam5 Kecepatan Rata-rata Kosong V2 40.00 Km/jam6 Waktu siklus/Cycle time (Ts = T1 + T2 + T3 + T4) Ts 64.00 menit7 - Waktu tempuh bermuatan = (L/V1)x60 T1 24.00 menit

- Waktu tempuh kosong = (L/V2)x60 T2 18.00 menit- Waktu Muat T3 20.00 menit- Lain-lain T4 2.00 menitKapasitas Produksi per jam = (KbxEax60)/TS Q1 2.53 M3Biaya Dump Truck = (1/Q1)xDT Rp. 1 58,511.46 Rp/M3

C Tenaga manusia untuk bongkar muat- Harga dasar upah Pekerja 1hr = 8 jam Pk 4,637.50 Rp/jam- Menggunakan tenaga pekerja jpk 4.00 orang

- Biaya Tenaga Kerja = (T3 + T4)/60 x (Jpk/Pk) Rp2 425.10 Rp/M3

TOTAL BIAYA ANGKUT = Rp1 + Rp2 R 58,936.57 Rp/M3

D HARGA SATUAN BATU KARANG = Se + Rp.1 + Rp.2 187,936.57 Rp/M3

Page 32: RAB Gudang Bahan Pangan

URAIAN ANALISA HARGA SATUAN

BIAYA Rp 146,800.30 TAHUN ANGGARAN 2014

No. U R A I A N KODE KOEFISIEN KETERANGAN

PASIR URUG

A ASUMSI :1 Pasir Urug diangkut dari Quary2 Jarak angkut rata-rata L 25.00 KM3 Harga Dasar Pasir urug PU 50,000.00 Rp/M34 Harga Satuan Dumptruck DT 148,107.14 Rp/Jam

B PERHITUNGAN :1 Dump Truck2 Kapasitas bak Kb 3.00 M33 Eisiensi Alat Ea 0.90 Muatan sedang4 Kecepatan Rata-rata bermuatan V1 30.00 Km/jam5 Kecepatan Rata-rata Kosong V2 40.00 Km/jam6 Waktu siklus/Cycle time (Ts = T1 + T2 + T3 + T4) Ts 105.50 menit7 - Waktu tempuh bermuatan = (L/V1)x60 T1 50.00 menit

- Waktu tempuh kosong = (L/V2)x60 T2 37.50 menit- Waktu Muat T3 15.00 menit- Lain-lain T4 3.00 menitKapasitas Produksi per jam = (KbxEax60)/TS Q1 1.54 M3Biaya Dump Truck = (1/Q1)xDT Rp. 1 96,452.49 Rp/M3

C Tenaga manusia untuk bongkar muat- Harga dasar upah Pekerja 1hr = 8 jam Pk 4,637.50 Rp/jam- Menggunakan tenaga pekerja jpk 4.00 orang

- Biaya Tenaga Kerja = (T3 + T4)/60 x (Jpk/Pk) Rp2 347.81 Rp/M3

TOTAL BIAYA ANGKUT = Rp1 + Rp2 R 96,800.30 Rp/M3

D HARGA SATUAN PASIR URUG = Se + Rp.1 + Rp.2 146,800.30 Rp/M3

Page 33: RAB Gudang Bahan Pangan

URAIAN ANALISA HARGA SATUAN

BIAYA Rp 316,800.30 TAHUN ANGGARAN 2014

No. U R A I A N KODE KOEFISIEN KETERANGAN

PASIR PASANG

A ASUMSI :1 Pasir Pasang diangkut dari Quary2 Jarak angkut rata-rata L 25.00 KM3 Harga Dasar Pasir Pasang PP 220,000.00 Rp/M34 Harga Satuan Dumptruck DT 148,107.14 Rp/Jam

B PERHITUNGAN :1 Dump Truck2 Kapasitas bak Kb 3.00 M33 Eisiensi Alat Ea 0.90 Muatan sedang4 Kecepatan Rata-rata bermuatan V1 30.00 Km/jam5 Kecepatan Rata-rata Kosong V2 40.00 Km/jam6 Waktu siklus/Cycle time (Ts = T1 + T2 + T3 + T4) Ts 105.50 menit7 - Waktu tempuh bermuatan = (L/V1)x60 T1 50.00 menit

- Waktu tempuh kosong = (L/V2)x60 T2 37.50 menit- Waktu Muat T3 15.00 menit- Lain-lain T4 3.00 menitKapasitas Produksi per jam = (KbxEax60)/TS Q1 1.54 M3Biaya Dump Truck = (1/Q1)xDT Rp. 1 96,452.49 Rp/M3

C Tenaga manusia untuk bongkar muat- Harga dasar upah Pekerja 1hr = 8 jam Pk 4,637.50 Rp/jam- Menggunakan tenaga pekerja jpk 4.00 orang

- Biaya Tenaga Kerja = (T3 + T4)/60 x (Jpk/Pk) Rp2 347.81 Rp/Kg

TOTAL BIAYA ANGKUT = Rp1 + Rp2 R 96,800.30 Rp/M3

D HARGA SATUAN PASIR PASANG = Se + Rp.1 + Rp.2 316,800.30 Rp/M3

Page 34: RAB Gudang Bahan Pangan

URAIAN ANALISA HARGA SATUAN

BIAYA Rp 154,115.47 TAHUN ANGGARAN 2014

No. U R A I A N KODE KOEFISIEN KETERANGAN

SIRTU

A ASUMSI :1 Sirtu Kali diangkut dari Quary2 Jarak angkut rata-rata L 12.00 KM3 Harga Dasar Sirtu SRT 110,000.00 Rp/M34 Harga Satuan Dumptruck DT 148,107.14 Rp/Jam

B PERHITUNGAN :1 Dump Truck2 Kapasitas bak Kb 3.00 M33 Eisiensi Alat Ea 0.90 Muatan sedang4 Kecepatan Rata-rata bermuatan V1 30.00 Km/jam5 Kecepatan Rata-rata Kosong V2 40.00 Km/jam6 Waktu siklus/Cycle time (Ts = T1 + T2 + T3 + T4) Ts 48.00 menit7 - Waktu tempuh bermuatan = (L/V1)x60 T1 24.00 menit

- Waktu tempuh kosong = (L/V2)x60 T2 18.00 menit- Waktu Muat T3 4.00 menit- Lain-lain T4 2.00 menitKapasitas Produksi per jam = (KbxEax60)/TS Q1 3.38 M3Biaya Dump Truck = (1/Q1)xDT Rp. 1 43,883.60 Rp/M3

C Tenaga manusia untuk bongkar muat- Harga dasar upah Pekerja 1hr = 8 jam Pk 4,637.50 Rp/jam- Menggunakan tenaga pekerja jpk 2.00 orang

- Biaya Tenaga Kerja = (T3 + T4)/60 x (Jpk/Pk) Rp2 231.88 Rp/m3

TOTAL BIAYA ANGKUT = Rp1 + Rp2 R 44,115.47 Rp/M3

D HARGA SATUAN SIRTU = Se + Rp.1 + Rp.2 154,115.47 Rp/M3

Page 35: RAB Gudang Bahan Pangan

URAIAN ANALISA HARGA SATUAN

BIAYA Rp 2,048.43 TAHUN ANGGARAN 2014

No. U R A I A N KODE KOEFISIEN KETERANGAN

BATU POTONG

A ASUMSI :1 Batu Potong diangkut dari Quary2 Jarak angkut rata-rata L 4.00 KM3 Harga Dasar Batu Potong BP 1,800.00 Rp/buah4 Harga Satuan Dumptruck DT 148,107.14 Rp/Jam

B PERHITUNGAN :1 Dump Truck2 Kapasitas bak Kb 500.00 Buah3 Eisiensi Alat Ea 0.90 Muatan sedang4 Kecepatan Rata-rata bermuatan V1 40.00 Km/jam5 Kecepatan Rata-rata Kosong V2 50.00 Km/jam6 Waktu siklus/Cycle time (Ts = T1 + T2 + T3 + T4) Ts 21.10 menit7 - Waktu tempuh bermuatan = (L/V1)x60 T1 6.00 menit

- Waktu tempuh kosong = (L/V2)x60 T2 4.80 menit- Waktu Muat T3 8.30 menit- Lain-lain T4 2.00 menitKapasitas Produksi per jam = (KbxEax60)/TS Q1 1,279.62 BuahBiaya Dump Truck = (1/Q1)xDT Rp. 1 115.74 Rp/buah

C Tenaga manusia untuk bongkar muat- Harga dasar upah Pekerja 1hr = 8 jam Pk 4,637.50 Rp/jam- Menggunakan tenaga pekerja jpk 6.00 orang

- Biaya Tenaga Kerja = (T3 + T4)/60 x (Jpk/Pk) Rp2 132.68 Rp/buah

TOTAL BIAYA ANGKUT = Rp1 + Rp2 R 248.43 Rp/BH

D HARGA SATUAN BATU POTONG = Se + Rp.1 + Rp.2 2,048.43 Rp/M3

Page 36: RAB Gudang Bahan Pangan

URAIAN ANALISA HARGA SATUAN

BIAYA Rp 95,587.38 TAHUN ANGGARAN 2014

No. U R A I A N KODE KOEFISIEN KETERANGAN

URUGAN TANAH BIASA

A ASUMSI :1 Batu Potng diangkut dari Quary2 Jarak angkut rata-rata L 1.00 KM3 Harga Dasar UTB 80,000.00 Rp/M34 Harga Satuan Dumptruck DT 148,107.14 Rp/Jam

B PERHITUNGAN :1 Dump Truck2 Kapasitas bak Kb 3.00 m33 Eisiensi Alat Ea 0.90 Muatan sedang4 Kecepatan Rata-rata bermuatan V1 30.00 Km/jam5 Kecepatan Rata-rata Kosong V2 40.00 Km/jam6 Waktu siklus/Cycle time (Ts = T1 + T2 + T3 + T4) Ts 16.50 menit7 - Waktu tempuh bermuatan = (L/V1)x60 T1 2.00 menit

- Waktu tempuh kosong = (L/V2)x60 T2 1.50 menit- Waktu Muat T3 10.00 menit- Lain-lain T4 3.00 menitKapasitas Produksi per jam = (KbxEax60)/TS Q1 9.82 M3Biaya Dump Truck = (1/Q1)xDT Rp. 1 15,084.99 Rp/M3

TENAGA :C Tenaga manusia untuk bongkar muat

- Harga dasar upah Pekerja 1hr = 8 jam Pk 4,637.50 Rp/jam- Menggunakan tenaga pekerja jpk 2.00 orang

- Biaya Tenaga Kerja = (T3 + T4)/60 x (Jpk/Pk) Rp2 502.40 Rp/M3

TOTAL BIAYA ANGKUT = Rp1 + Rp2 R 15,587.38 Rp/M3

D HARGA SATUAN TANAH BIASA = Se + Rp.1 + Rp.2 95,587.38 Rp/M3

Page 37: RAB Gudang Bahan Pangan

URAIAN ANALISA HARGA SATUAN

BIAYA Rp 96,420.40

TAHUN ANGGARAN 2014

No. U R A I A N KODE KOEFISIEN KETERANGAN

URUGAN TANAH HUMUS

A ASUMSI :1 Batu Potng diangkut dari Quary2 Jarak angkut rata-rata L 15.00 KM3 Harga Dasar UTH 50,000.00 Rp/M34 Harga Satuan Dumptruck DT 148,107.14 Rp/Jam

B PERHITUNGAN :1 Dump Truck2 Kapasitas bak Kb 3.00 m33 Eisiensi Alat Ea 0.90 Muatan sedang4 Kecepatan Rata-rata bermuatan V1 40.00 Km/jam5 Kecepatan Rata-rata Kosong V2 60.00 Km/jam6 Waktu siklus/Cycle time (Ts = T1 + T2 + T3 + T4) Ts 50.50 menit7 - Waktu tempuh bermuatan = (L/V1)x60 T1 22.50 menit

- Waktu tempuh kosong = (L/V2)x60 T2 15.00 menit- Waktu Muat T3 10.00 menit- Lain-lain T4 3.00 menitKapasitas Produksi per jam = (KbxEax60)/TS Q1 3.21 M3Biaya Dump Truck = (1/Q1)xDT Rp. 1 46,169.20 Rp/M3

TENAGA :C Tenaga manusia untuk bongkar muat

- Harga dasar upah Pekerja 1hr = 8 jam Pk 4,637.50 Rp/jam- Menggunakan tenaga pekerja jpk 4.00 orang- Biaya Tenaga Kerja = (T3 + T4)/60 x (Jpk/Pk) Rp2 251.20 Rp/M3

TOTAL BIAYA ANGKUT = Rp1 + Rp2 R 46,420.40 Rp/M3

D HARGA SATUAN TANAH BIASA = Se + Rp.1 + Rp.2 96,420.40 Rp/M3

Page 38: RAB Gudang Bahan Pangan

URAIAN ANALISA HARGA SATUAN

BIAYA Rp 4,178,976.27 TAHUN ANGGARAN 2014

No. U R A I A N KODE KOEFISIEN KETERANGAN

KAYU BALOK

A ASUMSI :1 Bahan diangkut dari Quary2 Jarak angkut rata-rata L 10.00 KM3 Harga Dasar KB 4,100,000.00 Rp/m34 Harga Satuan Dumptruck DT 148,107.14 Rp/Jam

B PERHITUNGAN :1 Dump Truck2 Kapasitas bak Kb 5.00 m33 Eisiensi Alat Ea 0.90 Muatan sedang4 Kecepatan Rata-rata bermuatan V1 30.00 Km/jam5 Kecepatan Rata-rata Kosong V2 40.00 Km/jam6 Waktu siklus/Cycle time (Ts = T1 + T2 + T3 + T4) Ts 70.00 menit7 - Waktu tempuh bermuatan = (L/V1)x60 T1 20.00 menit

- Waktu tempuh kosong = (L/V2)x60 T2 15.00 menit- Waktu Muat T3 30.00 menit- Lain-lain T4 5.00 menitKapasitas Produksi per jam = (KbxEax60)/TS Q1 3.86 M3Biaya Dump Truck = (1/Q1)xDT Rp. 1 38,398.15 Rp/M3

C Tenaga manusia untuk bongkar muat - Harga dasar upah Pekerja 1hr = 8 jam Pk 4,637.50 Rp/jam- Menggunakan tenaga pekerja jpk 4.00 orang

- Biaya Tenaga Kerja = (T3 + T4)/60 x (Jpk/Pk) Rp2 40,578.13 Rp/M3

TOTAL BIAYA ANGKUT = Rp1 + Rp2 R 78,976.27 Rp/m3

D HARGA SATUAN KAYU BALOK = Se + Rp.1 + Rp.2 4,178,976.27 Rp/M3

Page 39: RAB Gudang Bahan Pangan

URAIAN ANALISA HARGA SATUAN

BIAYA Rp 679,069.20 TAHUN ANGGARAN 2014

No. U R A I A N KODE KOEFISIEN KETERANGAN

KERIKIL PECAH 2/3

A ASUMSI :1 Kerikil diangkut dari Quary2 Jarak angkut rata-rata L 18.00 KM3 Harga Dasar Kerikil KRL 600,000.00 Rp/Bh4 Harga Satuan Dumptruck DT 148,107.14 Rp/Jam

B PERHITUNGAN :1 Dump Truck2 Kapasitas bak Kb 3.00 M33 Eisiensi Alat Ea 0.90 Muatan sedang4 Kecepatan Rata-rata bermuatan V1 30.00 Km/jam5 Kecepatan Rata-rata Kosong V2 40.00 Km/jam6 Waktu siklus/Cycle time (Ts = T1 + T2 + T3 + T4) Ts 86.00 menit7 - Waktu tempuh bermuatan = (L/V1)x60 T1 36.00 menit

- Waktu tempuh kosong = (L/V2)x60 T2 27.00 menit- Waktu Muat T3 20.00 menit- Lain-lain T4 3.00 menitKapasitas Produksi per jam = (KbxEax60)/TS Q1 1.88 M3Biaya Dump Truck = (1/Q1)xDT Rp. 1 78,624.78 Rp/M3

C Tenaga manusia untuk bongkar muat- Harga dasar upah Pekerja 1hr = 8 jam Pk 4,637.50 Rp/jam- Menggunakan tenaga pekerja jpk 4.00 orang

- Biaya Tenaga Kerja = (T3 + T4)/60 x (Jpk/Pk) Rp2 444.43 Rp/Kg

TOTAL BIAYA ANGKUT = Rp1 + Rp2 R 79,069.20 Rp/Bh

D HARGA SATUAN KERIKIL KALI = Se + Rp.1 + Rp.2 679,069.20 Rp/M3

Page 40: RAB Gudang Bahan Pangan

URAIAN ANALISA HARGA SATUAN

BIAYA Rp 76,330.49 TAHUN ANGGARAN 2014

No. U R A I A N KODE KOEFISIEN KETERANGAN

SEMEN

A ASUMSI :1 Bahan diangkut dari Quary2 Jarak angkut rata-rata L 4.00 KM3 Harga Dasar PC 75,000.00 Rp/Zak4 Harga Satuan Dumptruck DT 148,107.14 Rp/Jam

B PERHITUNGAN :1 Dump Truck2 Kapasitas bak Kb 125.00 Zak3 Eisiensi Alat Ea 0.90 Muatan sedang4 Kecepatan Rata-rata bermuatan V1 40.00 Km/jam5 Kecepatan Rata-rata Kosong V2 50.00 Km/jam6 Waktu siklus/Cycle time (Ts = T1 + T2 + T3 + T4) Ts 37.30 menit7 - Waktu tempuh bermuatan = (L/V1)x60 T1 6.00 menit

- Waktu tempuh kosong = (L/V2)x60 T2 4.80 menit- Waktu Muat T3 25.00 menit- Lain-lain T4 1.50 menitKapasitas Produksi per jam = (KbxEax60)/TS Q1 180.97 ZakBiaya Dump Truck = (1/Q1)xDT Rp. 1 818.43 Rp/zak

TENAGA :C Tenaga manusia untuk bongkar muat

- Harga dasar upah Pekerja 1hr = 8 jam Pk 4,637.50 Rp/jam- Menggunakan tenaga pekerja jpk 4.00 orang

- Biaya Tenaga Kerja = (T3 + T4)/60 x (Jpk/Pk) Rp2 512.06 Rp/zak

TOTAL BIAYA ANGKUT = Rp1 + Rp2 R 1,330.49 Rp/Zak

D HARGA SATUAN SEMEN = Se + Rp.1 + Rp.2 76,330.49 Rp/Zak

Page 41: RAB Gudang Bahan Pangan

ANALISA BIAYA SEWA PERALATAN PER JAM KERJA

TENAGA KAPASITAS UMUR JAM HARGA NILAI FAKTOR BIAYA PASTI PER JAM BIAYA OPERASI PER JAM KERJAALAT ALAT ALAT OPERASI SETEMPAT SISA PENGEM- BIAYA ASURANSI TOTAL BAHAN BAKAR & PELUMAS WORKSHOP SPAREPART

1 TAHUN ALAT BALIAN PENGEM- DAN BIAYA BAHAN MINYAKMODAL BALIAN LAIN-LAIN PASTI / JAM BAKAR PELUMAS BIAYA KOEF. BIAYA KOEF.

MODAL(HP) - (Thn) (Jam) (Rp.) (Rp.) - (Rp.) (Rp.) (Rp.) Lt/HP/JamLtr/HP/Jam (Rp.) - (Rp.) -

No. JENIS PERALATAN KODE f1 x HP xALAT i(1+i)^A (B - C) x D 0.20 x C 0.125 0.0035 Harga BBM 0.0625 (g1 x B) 0.125

(10% X B) ------ ------- ----- (e1 + e2) s / d s / d + s / d ----- s / d(1+i)^A-1 W W 0.175 0.0060 f2 x HP x 0.0875 W 0.175

Harga OlieHP Cp A W B C D e1 e2 E f1 f2 F g1 G h1

1 2a 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

1. CONCRETE MIXER 0.3-0.6 M3 E06 15.0 500.0 Liter 5.0 1,800.0 10,000,000 1,000,000 0.33438 3,150.42 480.74 3,631.16 0.15 0.00475 12,652.50 0.075 416.67 0.150

2. CRANE 10-15 TON E07 150.0 15.0 Ton 5.0 1,800.0 500,000,000 50,000,000 0.33438 98,227.70 9,213.75 107,441.45 0.15 0.00475 126,525.00 0.075 20,833.33 0.150

3. DUMP TRUCK 3-3,5 M3 E08 100.0 6.0 Ton 10.0 1,200.0 100,000,000 10,000,000 0.23852 24,250.22 3,256.92 27,507.14 0.15 0.00475 84,350.00 0.075 6,250.00 0.150

4. DUMP TRUCK E09 120.0 8.0 Ton 5.0 1,800.0 175,000,000 17,500,000 0.33438 39,314.24 4,458.45 43,772.69 0.15 0.00475 101,220.00 0.075 7,291.67 0.150

5. EXCAVATOR 80-140 HP E10 80.0 0.9 M3 5.0 1,800.0 750,000,000 75,000,000 0.33438 146,668.85 13,652.45 160,321.29 0.15 0.00475 67,480.00 0.075 31,250.00 0.150

6. STAMPER E24 5.0 0.2 Ton 5.0 1,800.0 20,000,000 2,000,000 0.33438 4,860.82 601.48 5,462.30 0.15 0.00475 4,217.50 0.075 833.33 0.150

KETERANGAN :1. Tingkat Suku Bunga = 20.00 % per-tahun2. Upah Operator / Sopir / Mekanik = Rp 10,000.00 per-orang/jam3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik = Rp 7,500.00 per-orang/jam4. Harga Bahan Bakar Bensin = Rp 6,500.00 per-liter5. Harga Bahan Bakar Solar = Rp 4,800.00 per-liter6. Minyak Pelumas = Rp 26,000.00 per-liter7. Pajak Pertambahan Nilai (PPN) = 10 %

Page 42: RAB Gudang Bahan Pangan

ANALISA BIAYA SEWA PERALATAN PER JAM KERJA

BIAYA OPERASI PER JAM KERJA TOTALSPAREPART UPAH TOTAL BIAYA

OPERATOR PEMBANTU BIAYA SEWA ALATBIAYA / SOPIR OPERATOR OPERASI PER

/ SOPIR / JAM JAM KERJA(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)

(h1 x B) 1 Orang 1 Orang----- Per Per F+G+H+I+J E + KW Jam Kerja Jam Kerja

H I J K L19 20 21 22 23

833.33 10,000.00 7,500.00 31,402.50 35,033.66

41,666.67 10,000.00 7,500.00 206,525.00 313,966.45

12,500.00 10,000.00 7,500.00 120,600.00 148,107.14

14,583.33 10,000.00 7,500.00 140,595.00 184,367.69

62,500.00 10,000.00 7,500.00 178,730.00 339,051.29

1,666.67 10,000.00 7,500.00 24,217.50 29,679.80

Page 43: RAB Gudang Bahan Pangan

KEMENTERIAN KEHUTANANDIREKTORAT JENDERAL PERLINDUNGAN HUTAN DAN KONSERVASI ALAM

BALAI TAMAN NASIONAL MANUPEU TANAH DARUJln. Adyaksa Km.03 PO.Box 103 (0387) 22286 Fax. 22163 Waikabubak 87212 - Sumba Barat, Nusa Tenggara Timur

RENCANA ANGGARAN BIAYA(RAB)

PROGRAMPROGRAM KONSERVASI KEANEKARAGAMAN HAYATI DAN PERLINDUNGAN HUTAN

KEGIATAN

PENGADAAN SARANA PERKANTORAN BALAI

PEKERJAAN

PEMBANGUNAN LANJUTAN KANTOR STPN 2

LOKASI

DESA LEWA PAKU - KEC. LEWA - KABUPATEN SUMBA TIMUR

TAHUN ANGGARAN

2014

BALAI TAMAN NASIONAL MANUPEU TANAH DARU

Page 44: RAB Gudang Bahan Pangan
Page 45: RAB Gudang Bahan Pangan

INVOICE08/VII/IN-STC/014

Dengan Hormat,Dengan ini kami menyampaikan jumlah biaya untuk perancangan bangunangudang Fajar Baru di Weerame dengan rincian sebagai berikut :

Paket Perencanaan GudangGambar Kerja

Gambar ArsitekturalGambar StrukturalGambar Detil Bangunan

Rencana Anggaran dan BiayaRekapitulasi TotalDaftar Kuantitas & HargaDaftar Harga Satuan Upah, Bahan dan Sewa AlatPerhitungan Analisa Harga SatuanPerhitungan Analisa Sewa Alat per Jam

Biaya Perancangan : Rp 40,000.00 (Disepakati)

Luas Bangunan : 144.00 (Disepakati)

245.76 m² (Luasan Real)

Total Biaya Perancangan : Rp 5,760,000.00

Telah Diterima : Rp 500,000.00

Total Invoice : Rp 5,260,000.00

Note :

Total Rencana Anggaran Biaya : Rp 764,402,000.00 Prosentase Perancangan : 0.75 %