    Project Information Brief May 2006

    Yogyakarta

    Ironsands- Pig IronProject

  • 7/22/2019 Proyek Pasir Besi

    2/18

    Project Information Brief May 2006

    Introduction Indo Mines Ltd emerged from the former company Australian Kimberley

    Diamonds ( AKD ). AKD has been listed on the Australian Stock Exchangesince December 1993 and has been involved in the exploration and

    development of mineral projects, in particular diamonds, sinceincorporation.

    AKD has a portfolio of high quality exploration prospects both in Australiaand Peru.

    In Australia, AKD's assets include the King George and Seppelt Rangediamond projects located in the North Kimberley of Western Australia, theBird in Hand gold project located in the South Australia and the Wonarahphosphate project located in the Northern Territory.

    In Peru, AKD has 100% of the Chinguela gold project and 30% of the Nangaligold project. It also retains a 0.5% NSR in the El Molino copper gold project.

    Following a change of direction towards the development of mineralresource projects in Indonesia, in particular the development of the

    Yogyakarta Ironsands / Pig Iron Project, AKD Ltd was renamed IndoMines Limited in March 2006.

  • 7/22/2019 Proyek Pasir Besi

    3/18

    Project Information Brief May 2006

    Project Brief Recently Indo Mines Ltd acquired the rights to earn a 70% interest in the

    Yogyakarta Ironsands - Pig Iron project in Indonesia, following the relevantapprovals and due diligence.

    The Ironsands deposit was initially drilled by PT Aneka Tambang in the 1970's

    and early 1980's. On the basis of this drilling and subsequent test-work,feasibility studies completed by Lurgi and Davy McKee in 1985 reported a largeironsand deposit containing titano-ferrous magnetite over a 22 km by 1.5 kmwide strip of coastal plain.

    The ironsands deposit at Yogyakarta will be used as the basis for theestablishment of a pig iron making facility at Yogyakarta to provide feedstockfor regional steel producers.

    The location of the beneficiation and pig iron plant at Kulon Progo will be inthe Yogyakarta Province. This location is nominated due to its strategicposition - close to raw material sources, the availability of infrastructure andother required utilities power, water, rail and harbour

    Proposed initial capacity is 300,000 Tonne / year of Pig Iron. During thefeasibility study options will be evaluated to increase pig iron production

    capacity produce and to produce additional ironsand concentrate for directexport sale.

    Apart from ironsand as its raw material, the project requires other supportingmaterials such as coal and limestone, all of which are available within closeproximity in Indonesia.

  • 7/22/2019 Proyek Pasir Besi

    4/18

    Project Information Brief May 2006

  • 7/22/2019 Proyek Pasir Besi

    5/18

  • 7/22/2019 Proyek Pasir Besi

    6/18

    Project Information Brief May 2006

  • 7/22/2019 Proyek Pasir Besi

    7/18

    Project Information Brief May 2006

    Historical and Potential Ironsand Deposit Data

    Deposit: Titaniferrous magnetite sand deposit over22km x 1.8km area; Historical data indicates an average

    10m depth from surface; grading up to13 % Fe

    Exploration Target: + 300 Mt ironsand based ongeological due diligence completed by McKay &

    Schnellman

    (a substantial non JORC Compliant resource was defined by Lurgi/ Davy

    McKee in 1985 based on +13,000 drill holes by Aneka Tambang in 1970s)

    Potential Mine Life:The potential size of the deposit isexpected to be well in excess of a 15 year mine lifeproducing 300,000 tpa pig iron

  • 7/22/2019 Proyek Pasir Besi

    8/18

    Project Information Brief May 2006

    Resource Definition Program

    CurrentlyCompleted geological due diligence

    Topogaphical Survey using Differential GPS being

    completed by Gajah Mada University

    Management of exploration program by expatriates

    Mackay & Schnellmann

    Drilling using 2 track mounted air core rigs is being

    completed by PT RB Drilling JakartaLaboratory XRF analysis underway with ALS in Perth

  • 7/22/2019 Proyek Pasir Besi

    9/18

    Project Information Brief May 2006

    Resource Definition Program ( cont )

    April to June 2006Resource definition drilling program

    Topographical SurveyUp to 16,000m of air core drilling

    Up to 1000 holes at 16 m average depth

    Initial drilling on a wide spaced 800m x 100m grid

    Infill drilling to follow in order to define deposit to a measured /indicated JORC standard

    July to August 2006

    Complete JORC compliant Resource for minimumproject life ( + 15 years )Ore Resource calculation

    Geostatiscal analysis

    Mine Plan and Costing

  • 7/22/2019 Proyek Pasir Besi

    10/18

    Project Information Brief May 2006

    Current as of May 20 5,000 m drilled

  • 7/22/2019 Proyek Pasir Besi

    11/18

    Project Information Brief May 2006

    Anticipated Product Grades

    Ore % Concentrate % Pig Iron %

    Fe up to13 58 to 60 C 1.5 to 2.5

    TiO2 7 to 9 Si 0.5 max

    V2O5 0.5 to 0.6 P 0.1 maxSiO2 1.2 to 1.4 S 0.05 max

    Al2O3 3.3 to 3.5 Ti 0.05 max

    S 0.03 to 0.05 V 0.02 max

    P2O5 0.24 to 0.26 Fe 94 min

  • 7/22/2019 Proyek Pasir Besi

    12/18

    Project Information Brief May 2006

    Proposed Schedule* 2006 *

    March Commence resource definition drilling program including Topographical

    Survey and up to 16,000 m of air core drilling Initial drilling on a wide spaced 800m x 100m grid with Infill drilling to follow

    to define deposit to a measured/indicated JORC standard

    Approx. 10,000 samples for analysis

    July

    Complete JORC compliant Resource for minimum project life (+ 15 years )including Ore Resource Calculation and Geostatistical Analysis

    Mine Plan and Costing

    Concentration, reduction and smelting testwork based on representativedrilling sample by Outokumpu

    August Commence Bankable Feasibility

    September Finalisation of Offtake arrangements

  • 7/22/2019 Proyek Pasir Besi

    13/18

    Project Information Brief May 2006

    Proposed Schedule ( cont ) 2007

    January

    Continue Bankable Feasibility Study

    Commence project finance arrangements Performance Guarantee Testwork

    June

    Completion Bankable Feasibility Study

    If BFS is positive the following schedule is anticipated for project execution

    July

    Commence Project Design

    2008

    August Commence Concentrate Production

    2009 December

    Commence Pig Iron Production

  • 7/22/2019 Proyek Pasir Besi

    14/18

    Project Information Brief May 2006

    Proposed Study Development Schedule

    1 2 3 4 5 6 7 8 9 10 11 12

    Technical Study

    Exploration Program

    Testwork

    Drilling

    Resource Estimate

    Mine Plan

    Design

    Estimation

    Infrastructure

    Report

    Design

    Performance

    Month

    XRF Analysis

  • 7/22/2019 Proyek Pasir Besi

    15/18

    Project Information Brief May 2006

    Feasibility Study - Managed by Outokumpu

    Technical Study Resource Definition

    Mining Development

    Testwork

    Process Plant including Beneficiation / Multiple Hearth Furnace / KilnReduction and Ti & V slag removal

    Local infrastructure / fabrication / construction

    Environmental

    Commercial Project Capital and Operating Costs

    Develop financial model and project debt / equity arrangement

    Offtake Arrangements Negotiate product offtake with Indonesian Steel Producers and Others

  • 7/22/2019 Proyek Pasir Besi

    16/18

    Project Information Brief May 2006

    Project Development Alternatives Subject to

    Study

    Current base project 300,000 tpa pig iron

    Alternatives

    Increase total pig iron production up to 0.5 to 1 Mtpa

    Increase Concentrator Size ~ 1.5 Mtpa plus 300 to 500,000 tpa pig

    iron for pig iron and concentrate sale

    Downstream expansion to Specialty Steels from liquid pig iron

  • 7/22/2019 Proyek Pasir Besi

    17/18

  • 7/22/2019 Proyek Pasir Besi

    18/18

    Project Information Brief May 2006

    Anticipated Process Flowsheet

    Mining

    5.5 Mtpa

    Beneficiation0.7 Mtpa

    MHF / SLRNReduction0.51 Mtpa

    Ironmaking

    0.3 Mtpa

    0.33 Mtpa of Coal

    131 GwH

    Power

    The technology proposed is

    similar to that successfullyemployed for 20 + years on an

    ironsands to steel operation in

    New Zealand

    ~3.0 Mtpa