REKAPITULASI PENGURANGAN PEKERJAAN PROYEK WARE HOUSE AMPLAS - MEDAN BLOK B & C (57 UNIT) NO URAIAN SATUAN VOLUME HARGA SATUAN (Rp) UPAH BAHAN 1 Galian tanah M3 1,625.82 35,000.00 2 Beton lantai kerja, tb = 50mm, mutu K-100 M3 54.19 65,000.00 525,000.00 3 Beton cor mutu K-225 M3 238.90 65,000.00 661,500.00 4 Bekisting / acuan M2 796.32 35,000.00 45,000.00 5 Pembesian: - D 13 mm Kg 30,075.68 1,500.00 8,500.00 JUMLAH TOTAL Medan, 25 Januari 2013 Diajukan Oleh, KONTRAKTOR SARIPUDDIN PROJECT MANAGER

Upload: judee-av

Post on 31-Dec-2015

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PEKERJAAN PENGURANGAN

REKAPITULASI PENGURANGAN PEKERJAANPROYEK WARE HOUSE AMPLAS - MEDAN

BLOK B & C (57 UNIT)

NO URAIAN SATUAN VOLUMEHARGA SATUAN (Rp) JLH. HARGA

KETERANGANUPAH BAHAN Rp.

1 Galian tanah M3 1,625.82 35,000.00 56,903,700.00 2 Beton lantai kerja, tb = 50mm, mutu K-100 M3 54.19 65,000.00 525,000.00 31,974,460.00 3 Beton cor mutu K-225 M3 238.90 65,000.00 661,500.00 173,557,944.00 4 Bekisting / acuan M2 796.32 35,000.00 45,000.00 63,705,600.00 5 Pembesian: -

- D 13 mm Kg 30,075.68 1,500.00 8,500.00 300,756,775.41

JUMLAH TOTAL ###

Medan, 25 Januari 2013Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

SARIPUDDIN RAHMAD S.PROJECT MANAGER PIMPRO

Page 2: PEKERJAAN PENGURANGAN

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) GALIAN TANAH PONDASI P1,P2,P3,P4,P5Tanggal: 25 Januari 2013

Sketsa:

NO.DIMENSI VOLUME JUMLAH PONDASI (UNIT) VOLUME/BLOK (m3)

Panjang (m') Lebar (m') Tinggi (m') BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)

P1 1.40 1.40 1.50 2.940 179.00 183.00 526.26 538.02P2 1.40 1.40 1.50 2.940 31.00 28.00 91.14 82.32P3 1.40 1.40 1.50 2.940 12.00 13.00 35.28 38.22P4 1.40 1.40 1.50 2.940 38.00 18.00 111.72 52.92P5 1.40 1.40 1.50 2.940 11.00 40.00 32.34 117.60

JUMLAH TOTAL

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

(m3)

Page 3: PEKERJAAN PENGURANGAN

BACK-UP DATA ADDENDUM I

GALIAN TANAH PONDASI P1,P2,P3,P4,P5Tanggal: 25 Januari 2013

TOTAL VOLUMEKETERANGAN

m3j= (h + i)

1064.280173.46073.500

164.640149.940

1625.820

Diperiksa Oleh,BURSA PROPERTY

THAMBOSSite Manager

Page 4: PEKERJAAN PENGURANGAN

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) BETON LANTAI KERJA K 100PONDASI P3 & P4Tanggal: 25 Januari 2013

Sketsa:

NO.DIMENSI VOLUME JUMLAH PONDASI (UNIT) VOLUME/BLOK (m3)

Panjang (m') Lebar (m') Tinggi (m') BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)

P1 1.40 1.40 0.05 0.098 179.00 183.00 17.54 17.93P2 1.40 1.40 0.05 0.098 31.00 28.00 3.04 2.74P3 1.40 1.40 0.05 0.098 12.00 13.00 1.18 1.27P4 1.40 1.40 0.05 0.098 38.00 18.00 3.72 1.76P5 1.40 1.40 0.05 0.098 11.00 40.00 1.08 3.92

JUMLAH TOTAL

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

(m3)

Page 5: PEKERJAAN PENGURANGAN

BACK-UP DATA ADDENDUM I

BETON LANTAI KERJA K 100PONDASI P3 & P4Tanggal: 25 Januari 2013

TOTAL VOLUMEKETERANGAN

m3j= (h + i)35.4765.7822.4505.4884.998

54.194

Diperiksa Oleh,BURSA PROPERTY

THAMBOSSite Manager

Page 6: PEKERJAAN PENGURANGAN

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) MAL/ BEKISTING PONDASI P3 & P4Tanggal: 25 Januari 2013

Sketsa:

NO.DIMENSI VOLUME JUMLAH PONDASI (UNIT) VOLUME/BLOK (m3)

Sisi (m') Jumlah Segi Tinggi (m') (m2) BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)

P1 1.20 4.00 0.30 1.440 179.00 183.00 257.760 263.520P2 1.20 4.00 0.30 1.440 31.00 28.00 44.640 40.320P3 1.20 4.00 0.30 1.440 12.00 13.00 17.280 18.720P4 1.20 4.00 0.30 1.440 38.00 18.00 54.720 25.920P5 1.20 4.00 0.30 1.440 11.00 40.00 15.840 57.600

JUMLAH TOTAL

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

Page 7: PEKERJAAN PENGURANGAN

BACK-UP DATA ADDENDUM I

MAL/ BEKISTING PONDASI P3 & P4Tanggal: 25 Januari 2013

TOTAL VOLUMEKETERANGAN

m2j= (h + i)521.28084.96036.00080.64073.440

796.320

Diperiksa Oleh,BURSA PROPERTY

THAMBOSSite Manager

Page 8: PEKERJAAN PENGURANGAN

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) BETON COR MUTU K 225 PONDASI P3 & P4Tanggal: 25 Januari 2013

Sketsa:

NO.DIMENSI VOLUME JUMLAH PONDASI (UNIT) VOLUME/BLOK (m3)

Panjang (m') Lebar (m') Tinggi (m') BLOK B BLOK C BLOK B BLOK Ca b c d e= (b x c x d) f g h=(f x e) i= (g x e)

P1 1.20 1.20 0.30 0.432 179.00 183.00 77.328 79.056P2 1.20 1.20 0.30 0.432 31.00 28.00 13.392 12.096P3 1.20 1.20 0.30 0.432 12.00 13.00 5.184 5.616P4 1.20 1.20 0.30 0.432 38.00 18.00 16.416 7.776P5 1.20 1.20 0.30 0.432 11.00 40.00 4.752 17.280

JUMLAH TOTAL

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

(m3)

Page 9: PEKERJAAN PENGURANGAN

BACK-UP DATA ADDENDUM I

BETON COR MUTU K 225 PONDASI P3 & P4Tanggal: 25 Januari 2013

TOTAL VOLUMEKETERANGAN

m3j= (h + i)156.38425.48810.80024.19222.032

238.896

Diperiksa Oleh,BURSA PROPERTY

THAMBOSSite Manager

Page 10: PEKERJAAN PENGURANGAN

PROYEK WARE HOUSE AMPLAS - MEDAN BACK-UP DATA ADDENDUM I

TOTAL LUAS 25.277,70 M2 (57 UNIT) PEMBESIAN D 13 mm PONDASI P3 & P4Tanggal: 25 Januari 2013

Sketsa:

TipeJLH. Panjang Jlh. Batang Volume Berat Besi JUMLAH PONDASI (UNIT) VOLUME/BLOK (m3) TOTAL VOLUME

KETERANGANPANJANG (m') (m') (Btg.) (m') (Kg) BLOK B BLOK C BLOK B BLOK C Kg

a b c d= (a+b+c) e f=(d x e) g h i j=(h x g) k= (i x g) l =(j +k)Tipe 1

P1 0.100 0.12 1.120 1.340 18.00 24.120 25.130 179.00 183.00 4,498.32 4,598.84 9,097.16 P2 0.100 0.12 1.120 1.340 18.00 24.120 25.130 31.00 28.00 779.04 703.65 1,482.69 P3 0.100 0.12 1.120 1.340 18.00 24.120 25.130 12.00 13.00 301.56 326.69 628.26 P4 0.100 0.12 1.120 1.340 18.00 24.120 25.130 38.00 18.00 954.95 452.34 1,407.29 P5 0.100 0.12 1.120 1.340 18.00 24.120 25.130 11.00 40.00 276.43 1,005.21 1,281.64

Tipe 2P1 0.220 1.12 0.220 1.560 18.00 28.080 29.256 179.00 183.00 5,236.85 5,353.87 10,590.72 P2 0.220 1.12 0.220 1.560 18.00 28.080 29.256 31.00 28.00 906.94 819.17 1,726.11 P3 0.220 1.12 0.220 1.560 18.00 28.080 29.256 12.00 13.00 351.07 380.33 731.40 P4 0.220 1.12 0.220 1.560 18.00 28.080 29.256 38.00 18.00 1,111.73 526.61 1,638.34 P5 0.220 1.12 0.220 1.560 18.00 28.080 29.256 11.00 40.00 321.82 1,170.25 1,492.06

TOTAL 30,075.68

Diajukan Oleh, Diperiksa Oleh,KONTRAKTOR BURSA PROPERTY

HENDRA SAFRIZA THAMBOSSite Manager Site Manager

Besi D 10 mm - 15 cm

a

Tipe 1 = 18 Btg

ab b

c

a b

c

Tipe 2 = 18 Btg