    Volume : 6.00 km

    Lokasi : Malinau, Kaltara

    A. PERSIAPAN, MOBILISASI, DEMOBILISASI)

    Volume Pekerjaan = 6 km

    Kapasitas/Tim/Hari = 1 km

    Jumlah Tim = 4 Orang

    Waktu Pelaksanaan = 15 hari

    a. Mobilisasi Personil dan Peralatan

    1 Tiket Pesawata Surabaya - Tarakan = 4 Orang x 2 pp x Rp. 2,000,000 = Rp. 16,000,000

    Speed Boat (Tarakan - Malinau) = 4 Orang x 2 pp x Rp. 400,000 = Rp. 3,200,000

    2 Penginapan Base Camp = 2 Unit 20 Hari x Rp. 200,000 = Rp. 8,000,000

    3 Konsumsi = 15 hari x 4 org x Rp. 25,000 = Rp. 1,500,000

    Jumlah (A) = Rp. 28,700,000

    B. PEMBUATAN/ PEMASANGAN TUGU BM (Bench Mark) dan CP (Control Point)

    Volume Pekerjaan = 4 tugu

    Kapasitas/Tim/Hari = 2 tugu/hari

    Jumlah Tim = 1 tim/lokasi

    Waktu Pelaksanaan = 2 hari

    1. Gaji

    a. Surveyor = 1 Orang x 2 Hari x Rp. 250,000 = Rp. 500,000

    c. Buruh Lokal = 4 Orang x 2 Hari x Rp. 100,000 = Rp. 800,000

    2. Uang Makan

    a. Surveyor = 1 Orang x 2 hari x Rp. 100,000 = Rp. 200,000

    3. Biaya Material

    a. Tugu BM = 4 Tugu x Rp. 200,000 = Rp. 800,000

    b. Patok CP (Paralon) = 4 Tugu x Rp. 100,000 = Rp. 400,000

    4. Tranportasi

    a. Sewa kendaraan Roda 4 + BBM = 1 Unit x 2 hari x Rp. 250,000 = Rp. 500,000

    Jumlah (B) = Rp 3,200,000

    C. SURVEY TOPOGRAFI

    Volume = 20 Ha

    Jumlah Tim = 1 Tim

    Kapasitas Tim/hari = 4 km

    Waktu Pelaksanaan = 5 hari

    1. Gaji

    a. Surveyor = 1 Orang x 5 Hari x Rp. 250,000 = Rp. 1,250,000b. Ass. Surveyor = 2 Orang x 5 Hari x Rp. 150,000 = Rp. 1,500,000

    c. Tenaga Lokal = 3 Orang x 5 Hari x Rp. 100,000 = Rp. 1,500,000

    2. Uang makan

    a. Surveyor = 1 Orang x 5 hari x Rp. 50,000 = Rp. 250,000

    b. Ass. Surveyor = 4 Orang x 5 hari x Rp. 50,000 = Rp. 1,000,000

    3. Biaya alat

    a. Theodolite Total Station (TS) = 1 Unit x 5 hari x Rp. 250,000 = Rp. 1,250,000

    b. Waterpass/ Leveling = 1 Unit x 5 hari x Rp. 75,000 = Rp. 375,000

    c. GPS RTK / Trimbel DGPS = 1 Unit x 5 hari x Rp. 1,500,000 = Rp. 7,500,000

    d. Radio Komunikasi/ Handy Talky = 5 Buah x 5 hari x Rp. 25,000 = Rp. 625,000

    e. ATK Ls = Rp. 100,000

    4 Sewa Kendaraan

    a. Sewa kendaraan Roda 4 + BBM = 1 Unit x 5 hari x Rp. 400,000 = Rp. 2,000,000

    Jumlah (C) = Rp. 17,350,000

    D. SURVEY ARUS

    Volume = 2 Titik

    Jumlah Tim = 1 Tim

    Kapasitas Tim/hari = 2 Titik

    Waktu Pelaksanaan = 2 hari

    1. Gaji

    a. Surveyor = 1 Orang x 2 Hari x Rp. 300,000 = Rp. 600,000

    b. Ass. Surveyor = 2 Orang x 2 Hari x Rp. 200,000 = Rp. 800,000

    c. Tenaga Lokal = 1 Orang x 2 Hari x Rp. 100,000 = Rp. 200,000

    2. Uang makan

    a. Surveyor = 1 Orang x 2 hari x Rp. 50,000 = Rp. 100,000

    b. Ass. Surveyor = 1 Orang x 2 hari x Rp. 50,000 = Rp. 100,000

    3. Biaya alat

    a. Current Meter = 1 Unit x 2 hari x Rp. 250,000 = Rp. 500,000

    c. GPS Garmin = 1 Unit x 2 hari x Rp. 30,000 = Rp. 60,000

    4 Sewa Kendaraan

    a. Sewa Perahu = 1 Unit x 2 hari x Rp. 1,000,000 = Rp. 2,000,000

    Jumlah (D) = Rp. 4,360,000

    RENCANA ANGGARAN BIAYASURVEY TOPOGRAFI DAN BATHYMETRI

    Malinau, Kalimantan Utara

  • 8/10/2019 Lampiran Bathimetri,Ecoshounding,Hidro

    2/2

    E SURVEY BATHYMETRI, HIDRO-OCEANOGRAFI

    Volume = 6 Km

    Jumlah Tim = 1 Tim

    Kapasitas Tim/hari = 2 KmWaktu Pelaksanaan = 3 hari

    1. Gaji

    a. Surveyor = 1 Orang x 3 Hari x Rp. 300,000 = Rp. 900,000

    b. Ass. Surveyor = 3 Orang x 3 Hari x Rp. 150,000 = Rp. 1,350,000

    c. Tenaga Lokal = 4 Orang x 15 Hari x Rp. 100,000 = Rp. 6,000,000

    2. Uang makan

    a. Surveyor = 1 Orang x 3 hari x Rp. 50,000 = Rp. 150,000

    b. Ass. Surveyor = 2 Orang x 3 hari x Rp. 50,000 = Rp. 300,000

    3. Biaya alat

    a. Echosounder + Trimbel DGPS = 1 Unit x 3 hari x Rp. 1,500,000 = Rp. 4,500,000

    b. Laptop = 1 Unit x 3 hari x Rp. 150,000 = Rp. 450,000

    e. Pasang Surut = 1 Unit x 15 hari x Rp. 100,000 = Rp. 1,500,000f. Radio Komunikasi/ Handy Talky = 1 Buah x 3 hari x Rp. 50,000 = Rp. 150,000

    g. Sewa Perahu = 1 Buah x 3 hari x Rp. 1,000,000 = Rp. 3,000,000

    h. Kayu, Tali Ls = Rp. 300,000

    Jumlah (E) = Rp. 18,600,000

    F PENGOLAHAN DATA ,PENGGAMBARAN DAN PELAPORAN

    Waktu pelaksanaan = 15 hari

    1. Gaji

    a. Juru Gambar/ Operator CAD = 1 Orang x 15 hari x Rp. 250,000 = Rp. 3,750,000

    2. Reproduksi/ Pencetakan Peta Ls = Rp. 1,000,000

    Jumlah (F) = Rp. 4,750,000

    Total (A+B+C+D+E+F) = Rp. 76,960,000

    NB ;

    - DP 50% di bayar di muka

    - Sisa Pembayaran 50% dibayar setelah laporan akhir diterima

    - Waktu pelaksanaan pekerjaan 30 hari

    - dimulai dari titik awal pengukuran