PEMERINTAH KABUPATEN SIDENRENG RAPPANG DINAS PERMUKIMAN DAN PRASARANA DAERAH JL. JEND. SUDIRMAN NO. 370 PANGKAJENE - SIDRAP DOKUMEN PERENCANAAN : RENCANA KERJA DAN SYARAT - SYARAT PEKERJAAN : PEMBANGUNAN GEDUNG SIDRAP CENTER TAHUN ANGGARAN 2005 Tahap I (Pertama) : PEMBANGUNAN GEDUNG INDUK SIDRAP CENTER Lokasi : Jl. PERINTIS KEMERDEKAAN (KM 7) TALLO - MAKASSAR Konsultan Perencana

Upload: blackbird-nee

Post on 04-Aug-2015

75 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: Kor Training Centre

PEMERINTAH KABUPATEN SIDENRENG RAPPANGDINAS PERMUKIMAN DAN PRASARANA DAERAH

JL. JEND. SUDIRMAN NO. 370 PANGKAJENE - SIDRAP

DOKUMEN PERENCANAAN :

RENCANA KERJA DAN SYARAT - SYARAT

PEKERJAAN :PEMBANGUNAN GEDUNG SIDRAP CENTER

TAHUN ANGGARAN 2005

Tahap I (Pertama) : PEMBANGUNAN GEDUNG INDUK SIDRAP CENTER

Lokasi :Jl. PERINTIS KEMERDEKAAN (KM 7) TALLO - MAKASSAR

Konsultan Perencana

Page 2: Kor Training Centre

CV. BAJIRUPA KONSULTANArchitect Planner,Supervisi

Jl. Dg. Tata I Blok 2 No. 4A, Makassar. Tlp. 0411 - 8216234

Page 3: Kor Training Centre

REKAPITULASI TOTAL ANGGARAN BIAYAPEMBANGUNAN GEDUNG SIDRAP CENTER KABUPATEN SIDRAP

KOTA MAKASSARTAHAP I (PERTAMA) - TAHUN ANGGARAN 2005

UNIT PEKERJAAN : PEMBANGUNAN GEDUNG INDUK SIDRAP CENTER

NO URAIAN PEKERJAAN JML. HARGA

I PEKERJAAN PENDAHULUAN Rp 192,918,000.00

II PEKERJAAN TIMBUNAN DAN TALUD Rp 166,134,000.00

III PEKERJAAN GEDUNG INDUK SIDRAP CENTER Rp 1,997,630,000.00

JUMLAH TOTAL SIDRAP CENTER TAHAP I (PERTAMA) Rp 2,356,682,000.00 Dibulatkan Rp 2,356,682,000.00

Terbilang : Dua milyar dua ratus tiga puluh tujuh juta seratus tiga puluh dua ribu rupiah,-

Makassar, Desember 2005

Pemimpin Kegiatan Konsultan PerencanaCV. BAJIRUPA KONSULTAN

Ir. ABD. RAHMAN SAMAILA Ir. BADARUDDINNip. 110 047 950 Direktur

Mengetahui/MenyetujuiKADIS KIMPRASDA KAB. SIDRAP

Ir. H. ABDULLAH DALIENip. 110 019 916

Mengetahui/MenyetujuiBUPATI SIDRAP

H. ANDI RANGGONG

Page 4: Kor Training Centre

RENCANA ANGGARAN BIAYAPEMBANGUNAN GEDUNG SIDRAP CENTER KABUPATEN SIDRAP

KOTA MAKASSAR

PEKERJAAN : PEK. PENDAHULUAN

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

I PEKERJAAN PENDAHULUAN

1 Pek. Papan Nama Proyek 1.00 Bh 2,000,000.00 2,000,000.00

2 Pek. Survey Dan Pengukuran Lokasi 1.00 Ls 6,000,000.00 6,000,000.00

3 Pek. Pagar Sementara Dari Seng Setinggi 2 M 210.00 M' 170,475.84 35,799,926.40

4 Pek. Direksi Keet 24.00 M2 393,264.00 9,438,336.00

5 Pek. Pematangan Lahan Training Centre 47,400.00 M2 2,000.00 94,800,000.00

6 Izin Mendirikan Bangunan (IMB) 2,039.98 M2 22,000.00 44,879,560.00

REAL COST PEK. PENDAHULUAN Rp. 192,917,822.40

Dibulatkan Rp. 192,918,000.00

Terbilang : Seratus sembilan puluh dua juta sembilan ratus delapan belas ribu rupiah,-

Makassar, Desember 2005

Konsultan PerencanaCV. PRAPRIMADANI PRATAMA

SUMARNI, SH.Direktris

Page 5: Kor Training Centre

RENCANA ANGGARAN BIAYAPEMBANGUNAN GEDUNG SIDRAP CENTER KABUPATEN SIDRAP

KOTA MAKASSAR

PEKERJAAN : PEK. TIMBUNAN DAN TALUD/PONDASI PAGAR

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

I PEKERJAAN PEMATANGAN LAHAN1 Pek. Timbunan Tanah T : 85 cm 1,999.94 M3 65,557.92 131,111,906.52

131,111,906.52

II PEKERJAAN TALUD/PONDASI PAGAR1 Pek. Galian Tanah Biasa 76.26 M3 10,304.00 785,805.71

2 Pek. Urugan Tanah Bekas Galian 19.07 M3 4,939.20 94,168.56

3 Pek. Pasir Urug Alas Pondasi 14.60 M3 92,064.00 1,344,447.42

4 Pek. Pasangan Batu Kosong 29.21 M3 149,805.60 4,375,342.20

5 Pek. Pondasi Batu Gunung (1 pc : 5 psr) 93.71 M3 303,311.68 28,421,866.47

35,021,630.36

REAL COST PEK. TIMBUNAN DAN TALUD Rp. 166,133,536.88 Dibulatkan Rp. 166,134,000.00

Terbilang : Seratus enam puluh enam juta seratus tiga puluh empat ribu rupiah,-

Makassar, Desember 2005

Pemimpin Kegiatan Konsultan PerencanaCV. BAJIRUPA KONSULTAN

Ir. ABD. RAHMAN SAMAILA Ir. BADARUDDINNip. 110 047 950 Direktur

Page 6: Kor Training Centre

REKAPITULASI TOTAL ANGGARAN BIAYA

TRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

PROPINSI SULAWESI SELATAN

TAHUN ANGGARAN 2006

NO URAIAN PEKERJAAN JML. HARGA

I PEKERJAAN PENDAHULUAN Rp 192,918,000.00

II PEKERJAAN GEDUNG PENGELOLA Rp 1,997,630,000.00

III PEKERJAAN GEDUNG SERBAGUNA Rp 838,673,000.00

IV PEKERJAAN ASRAMA PUTRA Rp 1,062,273,000.00

V PEKERJAAN ASRAMA PUTRI Rp 1,062,273,000.00

VI PEKERJAAN SITE DEVELOPMENT Rp 4,810,051,000.00

JUMLAH TOTAL Rp 9,963,818,000.00 Dibulatkan Rp 9,963,800,000.00

Terbilang : SEMBILAN MILYAR SEMBILAN RATUS ENAM PULUH TIGA JUTA DELAPAN RATUS RIBU RUPIAH,-,-

Makassar, Desember 2005

Mengetahui/Menyetujui; Konsultan Perencana

KADIS TATA RUANG DAN PERMUKIMAN CV. PRAPRIMADANI PRATAMA

PROPINSI SULAWESI SELATAN

Ir. H. SYAFRUDDIN A. PATIWIRI, MSi. SUMARNI, SH.

Nip. 110 035 385 Direktris

Page 7: Kor Training Centre

RENCANA ANGGARAN BIAYATRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

TAHUN ANGGARAN 2006

PEKERJAAN : GEDUNG PENGELOLAUNIT : LANTAI I (DASAR)

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

I PEKERJAAN PERSIAPAN1 Pek. Pengukuran Dan Pas. Bouwplank 309.70 M' 2,856.00 884,503.20 2 Pek. Air kerja + P3K 1.00 Ls 500,000.00 500,000.00

1,384,503.20 II PEKERJAAN TANAH1 Pek. Galian Tanah Biasa 349.18 M3 10,304.00 3,597,924.96 2 Pek. Urugan Tanah Bekas Galian 87.29 M3 4,939.20 431,164.38 3 Pek. Urugan Tanah Bawah Lantai 169.12 M3 42,604.80 7,205,408.99

11,234,498.32 III PEKERJAAN PASIR1 Pek. Pasir Urug Alas Pondasi 26.53 M3 92,064.00 2,442,596.02 2 Pek. Pasir Urug Alas Lantai 92.48 M3 92,064.00 8,514,078.72

10,956,674.74 IV PEKERJAAN PONDASI BATU GUNUNG1 Pek. Pasangan Batu Kosong 47.82 M3 149,805.60 7,164,153.21 2 Pek. Pondasi Batu Gunung (1 pc : 5 psr) 132.14 M3 303,311.68 40,080,363.67

47,244,516.88 V PEKERJAAN PEMASANGAN BATU BATA LT I 1 Pek. Pas. Bt. Bata, tebal 1/2 bt (1pc : 3psr) 67.86 M2 53,713.24 3,645,050.29 2 Pek. Pas. Bt. Bata, tebal 1/2 bt (1pc : 5psr) 745.82 M2 50,323.56 37,532,478.55

41,177,528.85 VI PEKERJAAN PLESTERAN LT. I 1 Plesteran t : 15 mm (1pc : 3psr) 129.18 M2 18,220.44 2,353,789.32 2 Plesteran t : 15 mm (1pc : 5psr) 1,419.78 M2 16,717.68 23,735,499.60 3 Plesteran Beton t : 15 mm (1pc : 2psr) 153.18 M2 19,709.48 3,019,098.15 4 Pek. Acian (saus semen) 1,702.15 M2 9,045.20 15,396,278.61

44,504,665.68 VII PEKERJAAN BETON LT. I 1 Pek. Lantai Kerja t : 5 cm. 51.63 M2 44,703.23 2,307,804.35 2 Pek. Rabat Beton t : 7 cm (Alas Lantai) 462.40 M2 62,584.52 28,939,084.27 3 Pek. Pondasi Poer (75 x 75) 4.25 M3 2,413,937.72 10,259,235.33 4 Pek. Pondasi Poer (90 x 90) 11.59 M3 2,413,937.72 27,982,366.11 5 Pek. Stek Poer (40 x 40) 0.64 M3 2,752,081.86 1,761,332.39 6 Pek. Stek Poer (30 x 30) 3.78 M3 3,295,003.59 12,455,113.57 7 Pek. Stek Poer (25 x 25) 0.63 M3 3,427,680.59 2,142,300.37 8 Pek. Kolom Teras (40 x 40) 2.56 M3 2,752,081.86 7,045,329.57 9 Pek. Kolom Utama (30 x 30) 15.12 M3 3,295,250.22 49,824,183.37

10 Pek. Kolom Utama (25 x 25) 2.50 M3 3,427,680.59 8,569,201.48 11 Pek. Kolom Praktis (15 x 15) 6.12 M3 3,497,445.81 21,404,368.36 12 Pek. Sloef Praktis (20 x 25) 2.02 M3 2,242,255.96 4,529,357.04 13 Pek. Sloef Utama (25 x 40) 26.93 M3 2,229,290.28 60,034,787.24 14 Pek. Balok Latei 6.04 M3 2,213,883.28 13,373,626.13 15 Pek. Balok Gantung Entrance (25 x 40) 3.17 M3 2,582,857.53 8,187,658.38 16 Pek. Meja Beton 0.27 M3 4,459,330.72 1,182,614.51

259,998,362.47

Page 8: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

VIII PEKERJAAN KUSEN, PINTU DAN JENDELA LT. I 1 Pek. Kusen Kayu Kls. I 2.42 M3 6,685,280.00 16,173,029.38 2 Pek. Pintu Panel Kayu Kls. I 24.90 M2 378,000.00 9,410,310.00 3 Pek. Pintu PVC 5.00 Bh 240,000.00 1,200,000.00 4 Pek. Pintu Kaca Rangka Kayu Kls. I 14.22 M2 545,973.27 7,761,010.07 5 Pek. Daun Jendela Kaca 38.19 M2 545,973.27 20,849,627.34 6 Pek. Pas. Engsel Pintu 66.00 Bh 18,827.20 1,242,595.20 7 Pek. Pas. Engsel Jendela 88.00 Bh 7,828.80 688,934.40 8 Pek. Pas. Rel Pintu Sorong 6.00 Set 220,852.80 1,325,116.80 9 Pek. Pas. Kunci Pintu 11.00 Bh 110,180.00 1,211,980.00

10 Pek. Pas. Kunci Pintu Km/Wc 5.00 Bh 148,820.00 744,100.00 11 Pek. Pas. Kunci Pintu Dorong 6.00 Bh 108,122.00 648,732.00 12 Pek. Pas. Grendel Tanam Pintu 7.00 Bh 30,368.80 212,581.60 13 Pek. Pas. Grendel Jendela 44.00 Bh 25,216.80 1,109,539.20 14 Pek. Pas. Kait Angin 88.00 Bh 11,393.20 1,002,601.60 15 Pas. Kaca Buram 5 mm 6.24 M2 127,279.60 794,224.70

64,374,382.29 IX PEKERJAAN KERAMIK LANTAI DAN DINDING LT. I 1 Pek. Keramik Lantai 40 x 40 cm 340.55 M2 84,836.64 28,891,117.75 2 Pek. Keramik Lantai Km/Wc 20 x 20 cm 16.25 M2 76,436.64 1,242,095.40 3 Pek. Plint Lantai Keramik 10 x 40 cm 364.41 M' 13,016.58 4,743,347.34 4 Pek. Keramik Entrance 49.40 M2 84,836.64 4,190,930.02 5 Pek. Keramik Teras 28.68 M2 84,836.64 2,433,114.84 6 Pek. Keramik Dinding Km/Wc 20 x 25 cm 92.00 M2 81,942.56 7,538,715.52 7 Pek. Keramik Meja Dapur 6.62 M2 77,536.64 512,904.87

49,552,225.74 X PEKERJAAN PLAFOND LT. I 1 Pek. Rangka Plafond Kayu Kls. II 421.85 M2 37,016.00 15,615,199.60 2 Pek. Plafond Gibsum 421.85 M2 23,704.80 9,999,869.88 3 Pek. Pas. List Profil Gibsum 522.30 M' 31,830.40 16,625,017.92

42,240,087.40 XI PEKERJAAN PENGECATAN LT I 1 Pek. Pengecatan Dinding 1,702.15 M2 27,466.88 46,752,703.10 2 Pek. Pengecatan Plafond 421.85 M2 27,466.88 11,586,903.33 3 Pek. Pengecatan Kayu 121.73 M2 19,598.32 2,385,664.30 4 Pek. Residu Rangka Plafond 337.48 M2 4,470.20 1,508,603.10

62,233,873.82

XII PEKERJAAN SANITASI LT I 1 Pek. Pas. Kloset Duduk + Assesoris 5.00 Bh 1,282,948.80 6,414,744.00 2 Pek. Pas. Bak Air 5.00 Bh 150,000.00 750,000.00 3 Pek. Pas. Washtafel Lengkap 2.00 Bh 640,469.20 1,280,938.40 4 Pek. Pas. Kran Washtafel 2.00 Bh 37,765.00 75,530.00 5 Pek. Pas. Kran Air 7.00 Bh 37,765.00 264,355.00 6 Pek. Pas. Tempat Sabun 7.00 Bh 44,520.00 311,640.00 7 Pek. Pas. Floordrain 7.00 Bh 33,656.00 235,592.00 8 Pek. Pas. Urinoir 3.00 Bh 1,330,949.20 3,992,847.60 9 Pek. Pas. Pipa Air PVC (D) Dia. 3" 117.00 M' 49,686.56 5,813,327.52

10 Pek. Pas. Pipa Air PVC (AW) Dia. 3/4" 164.00 M' 13,860.00 2,273,040.00 11 Pek. Septictank 2.00 Bh 2,576,265.52 5,152,531.03 12 Pek. Sumur bor 1.00 Ls 2,000,000.00 2,000,000.00 13 Pek. Pemasukan Inst. Air PDAM 1.00 Ls 7,500,000.00 7,500,000.00 14 Alat Bantu Instalasi 1.00 Ls 1,500,000.00 1,500,000.00

37,564,545.55

Page 9: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

XIII PEKERJAAN INSTALASI LISTRIK LT I 1 Pek. Instalasi Penerangan 76.00 Ttk 219,436.00 16,677,136.00 2 Pek. Instalasi Titik Stop Kontak 21.00 Ttk 160,070.40 3,361,478.40 3 Pek. Instalasi Stop Kontak AC 13.00 Ttk 160,070.40 2,080,915.20 4 Pek. Instalasi Telepon PABX (17 Line) 1.00 Unit 4,061,300.00 4,061,300.00 5 Pek. Instalasi Televisi 21.00 Ttk 238,900.00 5,016,900.00 6 Pek. Pas. Stop Kontak 21.00 Bh 28,560.00 599,760.00 7 Pek. Pas. Stop Kontak AC 13.00 Bh 100,128.00 1,301,664.00 8 Pek. Pas. Saklar Tunggal 14.00 Bh 22,624.00 316,736.00 9 Pek. Pas. Saklar Ganda 20.00 Bh 27,328.00 546,560.00

10 Pek. Pas. Fitting Lampu 62.00 Bh 20,608.00 1,277,696.00 11 Pek. Pas. Lampu TL 2x20 Watt 14.00 Bh 108,192.00 1,514,688.00 12 Pek. Pas. Lampu SLE 20W E27 54.00 Bh 51,520.00 2,782,080.00 13 Pek. Pas. Lampu Pijar GLS Clear 25W 8.00 Bh 5,600.00 44,800.00 14 Pemasukan Daya Listrik PLN 66,000.00 VA 455.00 30,030,000.00 15 Pek. Panil Induk 1.00 Ls 7,500,000.00 7,500,000.00 16 Pek. Panil Pembagi 1.00 Ls 2,500,000.00 2,500,000.00 17 Pek. Penyambungan Telepon 1.00 Ls 825,000.00 825,000.00 18 Alat Bantu Instalasi 1.00 Ls 1,500,000.00 1,500,000.00

81,936,713.60 XIV PEKERJAAN TANGGA BETON 2.00 Unit1 Pek. Tangga Beton Utama

- Pek. Galian Tanah 12.71 M3 10,304.00 130,989.60 - Pek. Urugan Kembali 3.18 M3 4,939.20 15,697.40 - Pek. Pasir Urug Alas Pondasi 1.01 M3 92,064.00 93,214.80 - Pek. Pas. Bt. Kosong 2.03 M3 149,805.60 303,356.34 - Pek. Pondasi Poer Tangga 0.36 M3 2,413,937.72 875,052.43 - Pek. Pondasi Bt. Gunung 3.94 M3 303,311.68 1,194,289.74 - Pek. Struktur Beton Tangga (Plat + Balok) 6.82 M3 3,782,039.28 25,779,287.45 - Pek. Kolom Utama 25/25 0.88 M3 3,427,680.59 2,999,220.52 - Pek. Kolom Praktis 0.32 M3 3,497,445.81 1,101,695.43 - Pek. Sloef Beton Tangga 0.43 M3 2,242,255.96 958,564.42 - Pek. Balok Plat Atap Tangga 0.71 M3 2,646,995.11 1,885,984.02 - Pek. Plat Atap Tangga 1.86 M3 4,459,330.72 8,297,030.75 - Pek. Pasangan Dinding Bt. Bata 75.25 M2 50,323.56 3,786,847.89 - Pek. Plesteran Biasa 150.50 M2 16,717.68 2,516,010.84 - Pek. Plesteran Beton Plat Bawah Tangga 43.96 M2 19,709.48 866,330.19 - Pek. Acian (Saus Semen) 194.46 M2 9,045.20 1,758,885.14 - Pek. Reling Tangga Steinless 8.00 M1 700,000.00 5,600,000.00

Total (1) 58,162,456.96 2 Pek. Tangga Beton Belakang

- Pek. Galian Tanah 8.48 M3 10,304.00 87,400.59 - Pek. Urugan Kembali 2.12 M3 4,939.20 10,473.82 - Pek. Pasir Urug Alas Pondasi 1.14 M3 92,064.00 105,146.29 - Pek. Pas. Bt. Kosong 2.28 M3 149,805.60 342,185.95 - Pek. Pondasi Poer Tangga 0.25 M3 2,413,937.72 603,484.43 - Pek. Pondasi Bt. Gunung 4.44 M3 303,311.68 1,347,158.83 - Pek. Struktur Beton Tangga (Plat + Balok) 2.74 M3 3,782,039.28 10,370,351.72 - Pek. Sloef Beton Tangga 0.38 M3 2,242,255.96 853,626.84 - Pek. Kolom Praktis 0.30 M3 3,497,445.81 1,041,889.11 - Pek. Balok Plat Atap Tangga 0.91 M3 2,646,995.11 2,395,530.58 - Pek. Plat Atap Tangga 1.63 M3 4,459,330.72 7,254,885.16 - Pek. Pasangan Dinding Bt. Bata 84.01 M2 50,323.56 4,227,571.56

Page 10: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

- Pek. Plesteran Biasa 168.02 M2 16,717.68 2,808,831.04 - Pek. Plesteran Beton Plat Bawah Tangga 23.33 M2 19,709.48 459,822.17 - Pek. Acian (Saus Semen) 191.35 M2 9,045.20 1,730,759.99 - Pek. Reling Tangga Steinless 7.75 M1 700,000.00 5,425,000.00

Total (2) 39,064,118.07 Total Pek. Tangga Beton (1 + 2) 97,226,575.03

XV PEKERJAAN LAIN - LAIN1 Pek. Selasar Keliling Gedung 61.56 M2 62,584.52 3,852,703.35 2 Pek. Saluran Air Keliling Gedung 94.80 M' 24,019.04 2,277,005.11 3 Pek. Logo Dan Nama Gedung 1.00 Bh 25,000,000.00 25,000,000.00 4 Pek. Tower Air 1.00 Unit 8,750,000.00 8,750,000.00

39,879,708.45

Real cost Rp. 891,508,862.02

Page 11: Kor Training Centre

RENCANA ANGGARAN BIAYATRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

TAHUN ANGGARAN 2006

PEKERJAAN : GEDUNG PENGELOLAUNIT : LANTAI II (DUA)

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

I PEKERJAAN PEMASANGAN BATU BATA LT II1 Pek. Pas. Bt. Bata, tebal 1/2 bt (1pc : 5psr) 1,042.76 M2 50,323.56 52,475,420.59

52,475,420.59

II PEKERJAAN PLESTERAN LT. II1 Plesteran t : 15 mm (1pc : 5psr) 1,923.01 M2 16,717.68 32,148,265.82 2 Plesteran Beton t : 15 mm (1pc : 2psr) 311.82 M2 19,709.48 6,145,859.33 3 Pek. Acian (saus semen) 2,234.83 M2 9,045.20 20,214,515.87

58,508,641.01

III PEKERJAAN BETON LT. II1 Pek. Kolom Utama (25 x 25) 13.88 M3 3,427,680.59 47,559,068.21 2 Pek. Kolom Utama (20 x 20) 1.26 M3 3,713,110.80 4,678,519.61 3 Pek. Kolom Praktis (15 x 15) 9.00 M3 3,497,445.81 31,477,012.30 4 Pek. Balok Beton B1 (25 x 50) 19.86 M3 2,630,777.41 52,247,239.28 5 Pek. Balok Beton B2 (25 x 40) 9.24 M3 2,582,857.53 23,865,603.61 6 Pek. Balok Beton B3 (20 x 30) 5.33 M3 2,646,995.11 14,103,189.95 7 Pek. Balok Beton B2' + Lesplank Beton (25 x 40) 3.56 M3 2,582,857.53 9,191,873.39 8 Pek. Balok Beton B4 + Lesplank Beton (15 x 30) 6.68 M3 3,192,283.19 21,332,432.42 9 Pek. Balok Beton B5 (15 x 20) 1.78 M3 3,048,371.27 5,418,479.94

10 Pek. Balok Beton Konsol 1.20 M3 2,646,995.11 3,176,394.13 11 Pek. Plat Lantai t : 12 cm 42.77 M3 3,194,339.94 136,620,961.00 12 Pek. Plat Built in + Level t : 10 cm 4.55 M3 4,459,330.72 20,291,069.63 13 Pek. Balok Plat Built in 2.87 M3 2,646,995.11 7,591,581.98 14 Pek. Balok Latei 5.75 M3 2,213,883.28 12,725,401.10 15 Pek. Ringbalk RB 1 (20 x 25) 15.12 M3 1,938,510.56 29,310,279.67 16 Pek. Ringbalk RB 2 (15 x 20) 3.42 M3 2,213,883.28 7,561,518.35 17 Pek. Ringbalk RB 3 (15 x 15) 0.51 M3 2,782,469.33 1,427,406.76

428,578,031.32

IV PEKERJAAN KUSEN, PINTU DAN JENDELA LT. II1 Pek. Kusen Kayu Kls. I 3.02 M3 6,685,280.00 20,203,250.42 2 Pek. Pintu Panel Kayu Kls. I 35.35 M2 378,000.00 13,360,410.00 3 Pek. Pintu PVC 12.00 M2 240,000.00 2,880,000.00 4 Pek. Pintu Kaca Rangka Kayu Kls. I - M2 545,973.27 0.00 5 Pek. Daun Jendela Kaca Kls. I 35.84 M2 545,973.27 19,565,934.98 6 Pek. Pas. Engsel Pintu 54.00 Bh 18,827.20 1,016,668.80 7 Pek. Pas. Engsel Jendela 56.00 Bh 7,828.80 438,412.80 8 Pek. Pas. Rel Pintu Dorong 6.00 Set 220,852.80 1,325,116.80 9 Pek. Pas. Kunci Pintu 10.00 Bh 110,180.00 1,101,800.00

10 Pek. Pas. Kunci Pintu Km/Wc 12.00 Bh 148,820.00 1,785,840.00 11 Pek. Pas. Kunci Dorong 6.00 Bh 108,122.00 648,732.00 12 Pek. Pas. Grendel Tanam Pintu 5.00 Bh 30,368.80 151,844.00 13 Pek. Pas. Grendel Jendela 28.00 Bh 25,216.80 706,070.40 14 Pek. Pas. Kait Angin 56.00 Bh 11,393.20 638,019.20 15 Pas. Kaca Bening 5 mm 22.75 M2 98,943.60 2,251,243.94 16 Pas. Kaca Buram 5 mm 6.24 M2 127,279.60 794,224.70 17 Pek. Pas. Reling Koridor Dan Balkon 41.40 M' 797,500.00 33,016,500.00

99,884,068.05

Page 12: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

V PEKERJAAN KERAMIK LANTAI DAN DINDING LT. II1 Pek. Keramik Lantai 40 x 40 cm 398.68 M2 84,836.64 33,823,044.92 2 Pek. Keramik Lantai Km/Wc 20 x 20 cm 44.61 M2 76,436.64 3,409,930.23 3 Pek. Plint Lantai Keramik 10 x 40 cm 338.40 M' 13,016.58 4,404,812.03 4 Pek. Keramik Meja Beton 4.70 M2 77,536.64 364,654.82 5 Pek. Keramik Dinding Km/Wc 20 x 25 cm 162.42 M2 81,942.56 13,309,110.60

55,311,552.59

VI PEKERJAAN PLAFOND LT. II1 Pek. Rangka Plafond Kayu Kls. II 560.26 M2 37,016.00 20,738,491.62 2 Pek. Plafond Gibsum 560.26 M2 23,704.80 13,280,791.99 3 Pek. Pas. List Plafond 732.08 M' 31,830.40 23,302,240.08

57,321,523.69

VII PEKERJAAN PENGECATAN LT. II 1 Pek. Pengecatan Dinding 2,234.83 M2 27,466.88 61,383,876.10 2 Pek. Pengecatan Plafond 560.26 M2 27,466.88 15,388,525.52 3 Pek. Pengecatan Kayu 215.38 M2 19,598.32 4,221,086.16 4 Pek. Residu Rangka Plafond 448.21 M2 4,470.20 2,003,579.40 5 Pek. Waterproofing (Anti Bocor) Plat Built In 45.50 M2 139,203.12 6,334,089.97

89,331,157.15

VIII PEKERJAAN SANITASI LT. II1 Pek. Pas. Kloset Duduk + Assesoris 10.00 Bh 1,282,948.80 12,829,488.00 2 Pek. Pas. Bak Air 10.00 Bh 150,000.00 1,500,000.00 3 Pek. Pas. Washtafel Lengkap 4.00 Bh 640,469.20 2,561,876.80 4 Pek. Pas. Kran Washtafel 4.00 Bh 37,765.00 151,060.00 5 Pek. Pas. Kran Air 15.00 Bh 37,765.00 566,475.00 6 Pek. Pas. Tempat Sabun 12.00 Bh 44,520.00 534,240.00 7 Pek. Pas. Floordrain 15.00 Bh 33,656.00 504,840.00 8 Pek. Pas. Urinoir 3.00 Bh 1,330,949.20 3,992,847.60 9 Pek. Pas. Pipa Air PVC (D) Dia. 3" 76.00 M' 49,686.56 3,776,178.56

10 Pek. Pas. Pipa Air PVC (AW) Dia. 3/4" 136.00 M' 13,860.00 1,884,960.00 11 Alat Bantu Instalasi 1.00 Ls 1,500,000.00 1,500,000.00

29,801,965.96

IX PEKERJAAN INSTALASI LISTRIK LT. II 1 Pek. Instalasi Penerangan 89.00 Ttk 219,436.00 19,529,804.00 2 Pek. Instalasi Titik Stop Kontak 23.00 Ttk 160,070.40 3,681,619.20 3 Pek. Instalasi Stop Kontak AC 17.00 Ttk 160,070.40 2,721,196.80 4 Pek. Instalasi Televisi 10.00 Ttk 238,900.00 2,389,000.00 5 Pek. Pas. Stop Kontak 23.00 Bh 28,560.00 656,880.00 6 Pek. Pas. Stop Kontak AC 17.00 Bh 100,128.00 1,702,176.00 7 Pek. Pas. Saklar Tunggal 24.00 Bh 22,624.00 542,976.00 8 Pek. Pas. Saklar Ganda 24.00 Bh 27,328.00 655,872.00 9 Pek. Pas. Fitting Lampu 71.00 Bh 20,608.00 1,463,168.00

10 Pek. Pas. Lampu TL 2x20 Watt 18.00 Bh 108,192.00 1,947,456.00 11 Pek. Pas. Lampu SLE 20W E27 52.00 Bh 51,520.00 2,679,040.00 12 Pek. Pas. Lampu Pijar GLS Clear 25W 12.00 Bh 5,600.00 67,200.00 13 Alat Bantu Instalasi 1.00 Ls 1,500,000.00 1,500,000.00

39,536,388.00

Page 13: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

X PEKERJAAN ATAP 1 Pek. Kuda - Kuda Kayu Kls. I 8.35 M3 6,336,848.00 52,893,325.53 2 Pek. Gording Uk. 8/12 Kayu Kls. I 0.69 M3 6,294,848.00 4,350,998.94 3 Pek. Gording Uk. 6/12 Kayu Kls. I 6.72 M3 6,294,848.00 42,279,472.49 4 Pek. Kasau Dan Reng Kayu Kls. I 708.91 M2 69,944.00 49,583,826.18 5 Pek. Pas. Atap Genteng Beton 708.91 M2 46,625.60 33,053,237.53 6 Pek. Bubungan Atap 103.71 M' 25,177.60 2,611,168.90 7 Pek. Pas. Jurai Talang 37.54 M' 65,326.00 2,452,338.04 8 Pek. Pas. Lesplank 2 Susun Kayu Kls. I 130.02 M' 62,664.00 8,147,573.28

195,371,940.89

Real cost Rp. 1,106,120,689.24

Page 14: Kor Training Centre

REKAPITULASI RENCANA ANGGARAN BIAYATRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

TAHUN ANGGARAN 2006

UNIT PEKERJAAN : GEDUNG PENGELOLA

NO URAIAN PEKERJAAN JML. HARGA

I LANTAI I (DASAR)I PEKERJAAN PERSIAPAN Rp 1,384,503.20 II PEKERJAAN TANAH Rp 11,234,498.32 III PEKERJAAN PASIR Rp 10,956,674.74 IV PEKERJAAN PONDASI BATU GUNUNG Rp 47,244,516.88 V PEKERJAAN PEMASANGAN BATU BATA LT I Rp 41,177,528.85 VI PEKERJAAN PLESTERAN LT. I Rp 44,504,665.68 VII PEKERJAAN BETON LT. I Rp 259,998,362.47 VIII PEKERJAAN KUSEN, PINTU DAN JENDELA LT. I Rp 64,374,382.29 IX PEKERJAAN KERAMIK LANTAI DAN DINDING LT. I Rp 49,552,225.74 X PEKERJAAN PLAFOND LT. I Rp 42,240,087.40 XI PEKERJAAN PENGECATAN LT I Rp 62,233,873.82 XII PEKERJAAN SANITASI LT I Rp 37,564,545.55 XIII PEKERJAAN INSTALASI LISTRIK LT I Rp 81,936,713.60 XIV PEKERJAAN TANGGA BETON Rp 97,226,575.03 XV PEKERJAAN LAIN - LAIN Rp 39,879,708.45

Lantai (I) Rp 891,508,862.02 II LANTAI II (DUA)I PEKERJAAN PEMASANGAN BATU BATA LT II Rp 52,475,420.59 II PEKERJAAN PLESTERAN LT. II Rp 58,508,641.01 III PEKERJAAN BETON LT. II Rp 428,578,031.32 IV PEKERJAAN KUSEN, PINTU DAN JENDELA LT. II Rp 99,884,068.05 V PEKERJAAN KERAMIK LANTAI DAN DINDING LT. II Rp 55,311,552.59 VI PEKERJAAN PLAFOND LT. II Rp 57,321,523.69 VII PEKERJAAN PENGECATAN LT. II Rp 89,331,157.15 VIII PEKERJAAN SANITASI LT. II Rp 29,801,965.96 IX PEKERJAAN INSTALASI LISTRIK LT. II Rp 39,536,388.00 X PEKERJAAN ATAP Rp 195,371,940.89

Lantai (II) Rp 1,106,120,689.24

A REAL COST GEDUNG GEDUNG PENGELOLA Rp 1,997,629,551.26 Dibulatkan Rp 1,997,630,000.00

Terbilang : Satu milyar sembilan ratus sembilan puluh tujuh juta enam ratus tiga puluh ribu rupiah,-

Makassar, Desember 2005

Pemimpin Kegiatan Konsultan PerencanaCV. PRAPRIMADANI PRATAMA

Ir. ABD. RAHMAN SAMAILA SUMARNI, SH.Nip. 110 047 950 Direktris

Page 15: Kor Training Centre

RENCANA ANGGARAN BIAYATRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

TAHUN ANGGARAN 2006

PEKERJAAN : GEDUNG SERBAGUNA

NO URAIAN PEKERJAAN JML. HARGA

I PEKERJAAN PERSIAPAN Rp 835,580.00 II PEKERJAAN TANAH Rp 8,125,038.13 III PEKERJAAN PASIR Rp 8,976,700.32 IV PEKERJAAN PONDASI BATU GUNUNG Rp 15,290,038.12 V PEKERJAAN PEMASANGAN BATU BATA Rp 23,166,679.31 VI PEKERJAAN PLESTERAN Rp 28,631,012.02 VII PEKERJAAN BETON Rp 207,535,883.56 VIII PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 60,851,862.78 IX PEKERJAAN KERAMIK LANTAI DAN DINDING Rp 129,470,473.32 X PEKERJAAN PLAFOND Rp 27,732,120.53 XI PEKERJAAN ATAP Rp 194,266,191.12 XII PEKERJAAN PENGECATAN Rp 66,137,411.07 XIII PEKERJAAN SANITASI Rp 23,331,573.60 XIV PEKERJAAN INSTALASI LISTRIK Rp 23,919,213.60 XV PEKERJAAN STAGE (PANGGUNG) Rp 14,391,988.75 XVI PEKERJAAN LAIN - LAIN Rp 6,011,288.43

A REAL COST GEDUNG SERBAGUNA SIDRAP CENTER Rp 838,673,054.67 Dibulatkan Rp 838,673,000.00

Terbilang : Delapan ratus tiga puluh delapan juta enam ratus tujuh puluh tiga ribu rupiah,-

Makassar, Desember 2005

Pemimpin Kegiatan Konsultan Perencana

CV. PRAPRIMADANI PRATAMA

Ir. ABD. RAHMAN SAMAILA SUMARNI, SH.Nip. 110 047 950 Direktris

Page 16: Kor Training Centre

RENCANA ANGGARAN BIAYATRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

TAHUN ANGGARAN 2006

PEKERJAAN : GEDUNG SERBAGUNA

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

I PEKERJAAN PERSIAPAN1 Pek. Pengukuran Dan Pas. Bouwplank 117.50 M' 2,856.00 335,580.00 2 Pek. Air kerja + P3K 1.00 Ls 500,000.00 500,000.00

835,580.00

II PEKERJAAN TANAH1 Pek. Galian Tanah Biasa 122.74 M3 10,304.00 1,264,687.20 2 Pek. Urugan Tanah Bekas Galian 32.18 M3 4,939.20 158,935.43 3 Pek. Urugan Tanah Bawah Lantai 157.29 M3 42,604.80 6,701,415.50

8,125,038.13

III PEKERJAAN PASIR1 Pek. Pasir Urug Alas Pondasi 9.40 M3 92,064.00 865,401.60 2 Pek. Pasir Urug Alas Lantai 88.11 M3 92,064.00 8,111,298.72

8,976,700.32

IV PEKERJAAN PONDASI BATU GUNUNG1 Pek. Pasangan Batu Kosong 18.80 M3 149,805.60 2,816,345.28 2 Pek. Pondasi Batu Gunung (1 pc : 5 psr) 41.13 M3 303,311.68 12,473,692.84

15,290,038.12

V PEKERJAAN PEMASANGAN BATU BATA 1 Pek. Pas. Bt. Bata, tebal 1/2 bt (1pc : 3psr) 31.17 M2 53,713.24 1,674,241.69 2 Pek. Pas. Bt. Bata, tebal 1/2 bt (1pc : 5psr) 427.09 M2 50,323.56 21,492,437.62

23,166,679.31

VI PEKERJAAN PLESTERAN 1 Plesteran t : 15 mm (1pc : 3psr) 52.19 M2 18,220.44 950,833.66 2 Plesteran t : 15 mm (1pc : 5psr) 796.63 M2 16,717.68 13,317,721.83 3 Plesteran Beton t : 15 mm (1pc : 2psr) 232.48 M2 19,709.48 4,581,996.84 4 Pek. Acian (saus semen) 1,081.29 M2 9,045.20 9,780,459.69

28,631,012.02

VII PEKERJAAN BETON 1 Pek. Lantai Kerja t : 5 cm. 25.43 M2 44,703.23 1,136,579.67 2 Pek. Rabat Beton t : 7 cm (Alas Lantai) 361.80 M2 62,584.52 22,643,081.07 3 Pek. Pondasi Poer 7.10 M3 2,413,937.72 17,129,603.84 4 Pek. Stek Poer (30 x 50) 3.63 M3 2,642,194.14 9,591,164.72 5 Pek. Stek Poer (40 x 40) 0.70 M3 2,752,081.86 1,937,465.63 6 Pek. Kolom Utama (30 x 50) 18.98 M3 2,642,194.14 50,135,633.75 7 Pek. Kolom Utama (40 x 40) 5.52 M3 2,752,081.86 15,191,491.89 8 Pek. Kolom Praktis (15 x 15) 1.86 M3 3,497,445.81 6,492,133.79 9 Pek. Sloef Praktis (15 x 20) 1.43 M3 2,589,868.25 3,690,562.26

10 Pek. Sloef Utama (25 x 40) 10.46 M3 2,229,290.28 23,318,376.33 11 Pek. Plat Atap Km/Wc t : 12 cm 3.23 M3 4,459,330.72 14,384,017.19 12 Pek. Balok Gantung Teras (15 x 40) 1.82 M3 2,229,290.28 4,052,849.73 13 Pek. Balok Latei (15 x 20) 2.22 M3 2,213,883.28 4,914,820.88 14 Pek. Talang Beton 4.22 M3 4,459,330.72 18,836,212.98 15 Pek. Ringbalk Praktis(15 x 25) 1.78 M3 2,213,883.28 3,943,479.59 16 Pek. Ringbalk Utama (20 x 25) 5.23 M3 1,938,510.56 10,138,410.23

207,535,883.56

Page 17: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

VIII PEKERJAAN KUSEN, PINTU DAN JENDELA 1 Pek. Kusen Kayu Kls I 2.72 M3 6,685,280.00 18,206,691.55 2 Pek. Pintu/Jendela Panel 3.17 M2 378,000.00 1,197,504.00 3 Pek. Pintu/Jendela Kaca 56.98 M2 545,973.27 31,107,482.38 4 Pek. Pintu PVC 8.00 Bh 240,000.00 1,920,000.00 5 Pek. Jalusi Papan Kls I 1.64 M2 467,824.00 768,260.57 6 Pek. Pas. Engsel Pintu 46.00 Bh 18,827.20 866,051.20 7 Pek. Pas. Engsel Jendela 92.00 Bh 7,828.80 720,249.60 8 Pek. Pas. Kunci Pintu 6.00 Bh 110,180.00 661,080.00 9 Pek. Pas. Kunci Pintu Km/Wc 8.00 Bh 148,820.00 1,190,560.00

10 Pek. Pas. Grendel Pintu 4.00 Bh 30,368.80 121,475.20 11 Pek. Pas. Grendel Jendela 46.00 Bh 25,216.80 1,159,972.80 12 Pek. Pas. Kait Angin 92.00 Bh 11,393.20 1,048,174.40 13 Pas. Kaca Bening 5 mm 19.04 M2 98,943.60 1,884,361.07

60,851,862.78

IX PEKERJAAN KERAMIK LANTAI DAN DINDING 1 Pek. Keramik Lantai 40 x 40 cm 185.64 M2 84,836.64 15,749,073.85 2 Pek. Keramik Lantai Km/Wc 20 x 20 cm 25.08 M2 76,436.64 1,916,648.75 3 Pek. Plint Lantai Keramik 10 x 40 cm 84.20 M' 13,016.58 1,095,996.37 4 Pek. Keramik Dinding Km/Wc 20 x 25 cm 67.70 M2 81,942.56 5,547,511.31 5 Pek. Lantai Parquet Jati 144.00 M2 685,104.00 98,654,976.00 6 Pek. Pas. Paving Block Entrance 47.97 M2 135,632.00 6,506,267.04

129,470,473.32

X PEKERJAAN PLAFOND 1 Pek. Rangka Plafond Kayu Kls II 142.46 M2 37,016.00 5,273,299.36 2 Pek. Plafond Gibsum 647.46 M2 23,704.80 15,347,909.81 3 Pek. Pas. List Profil Gibsum 223.40 M' 31,830.40 7,110,911.36

27,732,120.53

XI PEKERJAAN ATAP 1 Pek. Kuda - Kuda + Konsol Kayu Kls. I 8.07 M3 6,336,848.00 51,123,154.92 2 Pek. Gording Uk. 8/12 Kayu Kls. I 1.92 M3 6,294,848.00 12,086,108.16 3 Pek. Gording Uk. 6/12 Kayu Kls. I 5.96 M3 6,294,848.00 37,509,463.29 4 Pek. Kasau Dan Reng Kayu Kls. I 685.07 M2 69,944.00 47,916,675.97 5 Pek. Pas. Atap Genteng Beton 685.07 M2 46,625.60 31,941,893.04 6 Pek. Bubungan Atap 76.96 M' 25,177.60 1,937,668.10 7 Pek. Pas. Jurai Talang 24.66 M' 65,326.00 1,610,939.16 8 Pek. Pas. Lesplank 2 Susun Kayu Kls. I 161.82 M' 62,664.00 10,140,288.48

194,266,191.12

XII PEKERJAAN PENGECATAN1 Pek. Pengecatan Dinding 1,081.29 M2 27,466.88 29,699,574.78 2 Pek. Pengecatan Plafond 647.46 M2 27,466.88 17,783,706.12 3 Pek. Cat Kayu (Gording,Kuda-Kuda + Kusen) 734.88 M2 19,598.32 14,402,389.88 4 Pek. Residu Rangka Plafond 114.08 M2 4,470.20 509,960.42 5 Pek. Waterproofing (Anti Bocor) Plat Built In 26.88 M2 139,203.12 3,741,779.87

66,137,411.07

Page 18: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

XIII PEKERJAAN SANITASI1 Pek. Pas. Kloset Duduk + Assesoris 8.00 Bh 1,282,948.80 10,263,590.40 2 Pek. Pas. Bak Air 8.00 Bh 150,000.00 1,200,000.00 3 Pek. Pas. Washtafel Lengkap 2.00 Bh 640,469.20 1,280,938.40 4 Pek. Pas. Kran Washtafel 2.00 Bh 37,765.00 75,530.00 5 Pek. Pas. Kran Air 8.00 Bh 37,765.00 302,120.00 6 Pek. Pas. Tempat Sabun 8.00 Bh 44,520.00 356,160.00 7 Pek. Pas. Floordrain 10.00 Bh 33,656.00 336,560.00 8 Pek. Pas. Reservoir 1.5 Kbk 1.00 Bh 1,000,000.00 1,000,000.00 9 Pek. Pas. Pipa Air PVC (D) Dia. 3" 38.00 M' 49,686.56 1,888,089.28

10 Pek. Pas. Pipa Air PVC (AW) Dia. 3/4" 112.00 M' 13,860.00 1,552,320.00 11 Pek. Septictank 1.00 Bh 2,576,265.52 2,576,265.52 12 Pompa Air 1.00 Bh 1,000,000.00 1,000,000.00 13 Alat Bantu Instalasi 1.00 Ls 1,500,000.00 1,500,000.00

23,331,573.60

XIV PEKERJAAN INSTALASI LISTRIK 1 Pek. Instalasi Penerangan 71.00 Ttk 219,436.00 15,579,956.00 2 Pek. Instalasi Titik Stop Kontak 4.00 Ttk 160,070.40 640,281.60 3 Pek. Instalasi Televisi - Ttk 238,900.00 0.00 4 Pek. Pas. Stop Kontak 4.00 Bh 28,560.00 114,240.00 5 Pek. Pas. Saklar Tunggal 8.00 Bh 22,624.00 180,992.00 6 Pek. Pas. Saklar Ganda 16.00 Bh 27,328.00 437,248.00 7 Pek. Pas. Fitting Lampu 47.00 Bh 20,608.00 968,576.00 8 Pek. Pas. Lampu TL 2x40 Watt 24.00 Bh 109,480.00 2,627,520.00 9 Pek. Pas. Lampu SLE 20W E27 35.00 Bh 51,520.00 1,803,200.00

10 Pek. Pas. Lampu Pijar GLS Clear 25W 12.00 Bh 5,600.00 67,200.00 11 Alat Bantu Instalasi 1.00 Ls 1,500,000.00 1,500,000.00

23,919,213.60

XV PEKERJAAN STAGE (PANGGUNG)1 Pek. Galian Tanah 2.73 M3 10,304.00 28,099.01 2 Pek.Urugan Kembali 0.68 M3 4,939.20 3,367.30 3 Pek. Pasir Urug 11.09 M3 92,064.00 1,020,989.76 4 Pek. Pas. Pondasi Trasram 29.04 M2 111,989.92 3,252,187.28 5 Pek. Plesteran Trasram (1pc : 2ps) 58.08 M2 19,709.48 1,144,726.60 6 Pek. Tanah Urug 39.38 M3 42,604.80 1,677,564.00 7 Pek. Rabat Beton 55.45 M2 62,584.52 3,470,311.90 8 Pek. Keramik Lantai Dan Tangga Stage 44.73 M2 84,836.64 3,794,742.91

14,391,988.75

XVI PEKERJAAN LAIN - LAIN1 Pek. Pot Depan Entrance 2.99 M2 250,000.00 747,500.00 2 Pek. Selasar Keliling Gedung 54.05 M2 62,584.52 3,382,693.57 3 Pek. Saluran Air Keliling Gedung 57.50 M' 24,019.04 1,381,094.87 4 Pek. Pembersihan 1.00 Ls 500,000.00 500,000.00

6,011,288.43

Real cost Rp. 838,673,054.67

Page 19: Kor Training Centre

REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)TRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

TAHUN ANGGARAN 2006

PEKERJAAN : PEMBANGUNAN GEDUNG ASRAMA PUTRA ( BERLANTAI II )

NO J E N I S P E K E R J A A NJUMLAH HARGA

(TOTAL)

A PEKERJAAN PEMBANGUNAN LANTAI DASAR Rp. 428,474,625.85

I PEK. PERSIAPAN Rp. 2,466,670.40

II PEK. TANAH & PONDASI Rp. 28,867,072.53

III PEK. STRUKTUR BETON Rp. 91,330,372.02

IV PEK. PASANGAN & PLESTERAN Rp. 79,039,347.02

V PEK. PENGECATAN Rp. 47,355,167.95

VI PEKERJAAN LANTAI / KERAMIK Rp. 78,708,139.62

VII PEKERJAAN KOSEN PINTU DAN JENDELA Rp. 43,450,558.75

VIII PEK. PLAFOND Rp. 31,507,039.76

IX PEK. SANITASI Rp. 25,750,257.80

B PEKERJAAN PEMBANGUNAN LANTAI DUA Rp. 633,798,899.31

I PEK. STRUKTUR BETON Rp. 188,595,886.27

II PEK. PASANGAN & PLESTERAN Rp. 71,430,456.90

III PEK. PENGECATAN Rp. 46,828,544.10

IV PEKERJAAN LANTAI / KERAMIK Rp. 23,273,029.81

V PEKERJAAN TANGGA Rp. 5,000,000.00

VI PEK. KONSTRUKSI KAP DAN ATAP Rp. 107,392,528.32

VII PEK. KOSEN PINTU DAN JENDELA Rp. 35,386,061.60

VIII PEK. PLAFOND Rp. 43,118,683.72

IX PEK. SANITASI Rp. 9,139,698.60

X PEK. MEKANIKAL & ELEKTRIKAL LT 1 & 2 Rp. 101,134,010.00

XI PEK. LAIN-LAIN Rp. 2,500,000.00

C TOTAL COST ( I + II ) Rp. 1,062,273,525.16

D DIBULATKAN Rp. 1,062,273,000.00

Terbilang : Satu milyar enam puluh dua juta dua ratus tujuh puluh tiga ribu rupiah

Makassar, Desember 2005

Konsultan PerencanaCV. PRAPRIMADANI PRATAMA

SUMARNI, SH.Direktris

Page 20: Kor Training Centre

RENCANA ANGGARAN BIAYATRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

TAHUN ANGGARAN 2006

PEKERJAAN : PEMBANGUNAN GEDUNG ASRAMA PUTRA ( LANTAI DASAR )

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML HARGA

(Rp) ( Rp )

I PEK. PERSIAPAN1 Pengukuran + Bouplank 163.40 m' 2,856.00 466,670.40 2 Penyediaan P3K + Air Kerja 1.00 unit Ls 1,500,000.00 3 Penyediaan Alat Bantu 1.00 unit Ls 500,000.00

2,466,670.40 II PEK. TANAH & PONDASI1 Galian Tanah Pondasi 177.23 m3 10,304.00 1,826,177.92 2 Pek. Urugan Tanah Kembali 44.30 m3 4,939.20 218,806.56 3 Pasir Urug Alas Pondasi 14.00 m3 92,064.00 1,288,896.00 4 Pondasi Batu Gunung 60.30 m3 303,311.68 18,289,694.30 5 Pas. Batu Kosong 27.70 m3 149,805.60 4,149,615.12 6 Pas. Pondasi Trasram 57.60 m2 53,713.24 3,093,882.62

28,867,072.53 III PEK. STRUKTUR BETON1 Pek. Pondasi Sumuran Dia 60 cm 28.00 titik 760,000.00 21,280,000.00 2 Pek. Pondasi Poer 5.92 m3 1,511,029.37 8,945,293.87 3 Pek. Stek Poer 2.52 m3 2,642,194.14 6,658,329.23 4 Pek. Sloof Utama 9.11 m3 2,229,290.28 20,308,834.45 5 Pek. Sloof Praktis 0.81 m3 2,589,868.25 2,097,793.28 6 Pek. Kolom Utama 8.70 m3 2,752,081.86 23,943,112.22 7 Pek. Kolom Praktis 2.53 m3 3,497,445.81 8,848,537.90 8 Balok Latei 0.82 m3 2,229,290.28 1,828,018.03 9 Ring Balok + Kuda-kuda Beton 0.20 m3 2,213,883.28 442,776.66

10 Plat Leufel 2.82 m3 4,459,330.72 12,575,312.64 11 Tangga Beton 3.26 m3 758,173.50 2,471,645.61 12 Meja Beton 0.72 m3 4,459,330.72 3,210,718.12

91,330,372.02 IV PEK. PASANGAN & PLESTERAN1 Pas. Batu Trasram 52.58 m2 53,713.24 2,824,421.20 2 Pas. Batu Biasa 539.83 m2 50,323.56 27,166,335.14 3 Plesteran Trasram ( 1 : 2 ) 105.17 m2 18,220.44 1,916,182.94 4 Plesteran Biasa ( 1 : 5 ) 1,079.67 m2 16,717.68 18,049,521.84 5 Plestran Beton ( 1 : 3 ) 163.15 m2 19,709.48 3,215,601.66 6 Acian 1,347.98 m2 9,045.20 12,192,784.24 7 Pek. Lubang Ventilasi 59.00 bh 35,000.00 2,065,000.00 8 Pek. Profil Dibawah Jendela 22.00 m' 45,000.00 990,000.00 9 Pek. Profil Kolom 2.00 bh 150,000.00 300,000.00

10 Les Tembok ( Adumanis ) 127.70 m' 35,000.00 4,469,500.00 11 Realing Tangga 9.75 m' 600,000.00 5,850,000.00

79,039,347.02

Page 21: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML HARGA

(Rp) ( Rp )

V PEK. PENGECATAN1 Cat Tembok Luar (Mowilex) 269.60 m2 30,000.00 8,087,880.00 2 Cat Tembok (Ex, Metrolite) 1,078.38 m2 27,466.88 29,619,843.92 3 Cat Plafond 233.80 m2 27,466.88 6,421,756.54 4 Cat Kayu Kilap 145.00 m2 19,598.32 2,841,756.40 5 Cat Les Plafond 19.59 m2 19,598.32 383,931.09

47,355,167.95 VI PEKERJAAN LANTAI / KERAMIK1 Pek. Urugan Tanah lantai 280.00 m3 42,604.80 11,929,344.00 2 Pek. Penyemprotan Anti Rayap di Bawah Pond. & Lt. 253.05 m2 45,000.00 11,387,250.00 3 Pek. Urugan Pasir Lantai 48.00 m3 92,064.00 4,419,072.00 4 Lantai Keramik 40x40 cm 214.00 m2 84,836.64 18,155,040.96 5 Lantai Keramik 20x20 cm (Kasar) 27.00 m2 76,436.64 2,063,789.28 5 Dinding Keramik 20x25 cm 98.50 m2 81,942.56 8,071,342.16 6 Plant lantai Tegel Keramik 233.80 m' 13,016.58 3,043,277.34 7 Lantai Alas Keramik Beton Cor T. 7 cm 232.00 m2 62,584.52 14,519,609.75 8 Lantai Rabat Keliling Bangunan 81.80 m2 62,584.52 5,119,414.13

78,708,139.62 VII PEKERJAAN KOSEN PINTU DAN JENDELA1 Kosen Kayu Kelas I ( 5/14 ) 1.60 m3 6,685,280.00 10,696,448.00 2 Daun Pintu Panil Bayam 31.50 m2 378,000.00 11,907,000.00 3 Pintu / Jendela Kaca 25.10 m2 545,973.27 13,703,929.15 4 Rel Pintu Dorong 8.00 set 175,000.00 1,400,000.00 5 Kunci Pintu Dorong 8.00 bh 75,000.00 600,000.00 6 Engsel Pintu Biasa 75.00 bh 18,827.20 1,412,040.00 7 Engsel Jendela 52.00 bh 7,828.80 407,097.60 8 Hak Angin 52.00 bh 11,393.20 592,446.40 9 Kunci Pintu 2x Putar (Ex Yale) 6.00 bh 110,180.00 661,080.00

10 Kunci Bundar Kamar Mandi 8.00 bh 148,820.00 1,190,560.00 11 Grendel Jendela / Pintu 27.00 bh 30,368.80 819,957.60 12 Grendel Tanam 3.00 psg 20,000.00 60,000.00

43,450,558.75 VIII PEK. PLAFOND1 Plafond Metal Puring + Rangka 233.80 m2 106,250.00 24,841,250.00 2 Profil Gypsum Type SL (Kecil) 281.20 m' 23,704.80 6,665,789.76

31,507,039.76 IX PEK. SANITASI1 Pek. Pas. Kloset Duduk + Assesoris 8.00 bh 1,282,948.80 10,263,590.40 2 Ember Penapungan Air Sementara 8.00 bh 45,000.00 360,000.00 3 Kran Air 11.00 bh 37,765.00 415,415.00 4 Stop Kran 1.00 bh 50,000.00 50,000.00 5 Floor Drine 9.00 bh 33,656.00 302,904.00 6 Tempat Sabun Ex. TOTO (11x11 cm) 8.00 bh 44,520.00 356,160.00 7 Washtafel 2.00 bh 640,469.20 1,280,938.40 8 Cermin/Kaca 1.75 m2 95,000.00 166,250.00 9 Washbasin 1.00 bh 200,000.00 200,000.00

10 Saluran Terbuka 67.70 m' 125,000.00 8,462,500.00 11 Saluran Tertutup 7.50 m' 165,000.00 1,237,500.00 12 Urinoir 3.00 bh 885,000.00 2,655,000.00

25,750,257.80

Page 22: Kor Training Centre

RENCANA ANGGARAN BIAYATRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

TAHUN ANGGARAN 2006

PEKERJAAN : PEMBANGUNAN GEDUNG ASRAMA PUTRA ( LANTAI DUA )

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML HARGA

(Rp) ( Rp )

I PEK. STRUKTUR BETON1 Pek. Balok Lantai Induk 14.18 m3 2,582,857.53 36,624,919.82 2 Balok Lantai Anak 2.40 m3 2,646,995.11 6,352,788.27 3 Plat lantai T. 12 28.50 m3 3,194,339.94 91,038,688.33 4 Kolom Utama Lt. II 7.23 m3 3,427,680.59 24,782,130.68 5 kolom Praktis Lt. II 1.68 m3 3,497,445.81 5,875,708.96 6 Ring Balok 4.85 m3 1,938,510.56 9,401,776.22 7 Balok Level + Lesplank Beton 5.35 m3 2,213,883.28 11,844,275.56 8 Meja Beton 0.60 m3 4,459,330.72 2,675,598.43

188,595,886.27 II PEK. PASANGAN & PLESTERAN1 Pas. Batu Biasa 568.83 m2 50,323.56 28,625,718.38 2 Plesteran Biasa ( 1 : 4 ) 1,137.67 m2 16,717.68 19,019,147.28 3 Plestran Beton ( 1 : 3 ) 169.34 m2 18,220.44 3,085,449.31 4 Acian 1,307.01 m2 9,045.20 11,822,141.93 5 Les Tembok ( Adumanis ) 22.00 m' 35,000.00 770,000.00 6 Pek. Profil Dibawah Jendela 188.80 m' 35,000.00 6,608,000.00 7 Pek. Lubang Ventilasi 60.00 bh 25,000.00 1,500,000.00

71,430,456.90 III PEK. PENGECATAN1 Cat Tembok Luar (Mowileks) 326.75 m2 27,466.88 8,974,871.71 1 Cat Tembok (Ex, Metrolite) 980.26 m2 27,466.88 26,924,615.12 2 Cat Plafond 318.50 m2 27,466.88 8,748,201.28 3 Cat Les Plafond 18.69 m2 27,466.88 513,355.99 4 Waterproofing (Coating KM ) 23.00 m2 72,500.00 1,667,500.00

46,828,544.10 IV PEKERJAAN LANTAI / KERAMIK1 Lantai Keramik 40x40 cm 198.00 m2 84,836.64 16,797,654.72 2 Lantai Keramik 20x20 cm (Kasar) 19.00 m2 76,436.64 1,452,296.16 3 Dinding Keramik 20x25 cm 61.30 m2 81,942.56 5,023,078.93

23,273,029.81 V PEKERJAAN TANGGA

Tangga Besi + Pemasangan ( Lengkap ) 2.00 Ls 2,500,000.00 5,000,000.00 5,000,000.00

VI PEK. KONSTRUKSI KAP DAN ATAP1 Kuda-Kuda Kayu Kls-I 3.05 m3 6,336,848.00 19,327,386.40 2 Gording + Skor Angin Kayu Kls-I 4.88 m3 6,294,848.00 30,718,858.24 3 Pek. Reng dan Kaso Kls-I 413.80 m2 69,944.00 28,942,827.20 4 Pek. Lesplank Papan 128.50 m' 62,664.00 8,052,324.00 5 Pek. Nok Atap Genteng Beton 42.00 m' 25,177.60 1,057,459.20 6 Atap Genteng Beton 413.80 m2 46,625.60 19,293,673.28

107,392,528.32

Page 23: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML HARGA

(Rp) ( Rp )VII PEK. KOSEN PINTU DAN JENDELA1 Kosen Kayu Kelas I ( 5/14 ) 1.15 m3 6,685,280.00 7,688,072.00 2 Jalusi Papan Miring Kayu Kls I 3.24 m2 467,824.00 1,515,749.76 3 Daun Pintu Panil Bayam 28.40 m2 378,000.00 10,735,200.00 4 Jendela Kaca Kayu kls I 20.80 m2 378,000.00 7,862,400.00 5 Kaca Mati Rayband 5 mm 2.40 m2 98,943.60 237,464.64 6 Pintu PVC 4.00 bh 240,000.00 960,000.00 7 Expanyolet Tempel / Dor Closer 7.00 bh 65,000.00 455,000.00 8 Engsel Pintu Biasa 57.00 bh 18,827.20 1,073,150.40 9 Engsel Jendela 44.00 bh 7,828.80 344,467.20

10 Hak Angin 44.00 bh 11,393.20 501,300.80 11 Kunci Pintu 2x Putar (Ex Yale) 5.00 bh 110,180.00 550,900.00 12 Kunci Bulat 4.00 bh 148,820.00 595,280.00 13 Grendel Jendela / Pintu 26.00 bh 25,216.80 655,636.80 14 Grendel Tanam 2.00 psg 25,000.00 50,000.00 15 Rel Pintu Dorong 8.00 set 160,000.00 1,280,000.00 16 Kunci Pintu Dorong 8.00 bh 110,180.00 881,440.00

35,386,061.60 VIII PEK. PLAFOND1 Plafond Metal Puring + Rangka 318.50 m2 106,250.00 33,840,625.00 2 Profil Gypsum Type SL (Kecil) 391.40 m' 23,704.80 9,278,058.72

43,118,683.72 IX PEK. SANITASI1 Kloset Duduk Ex.TOTO.KIA (duk blok) 4.00 bh 1,282,948.80 5,131,795.20 2 Ember Penapungan Air Sementara 4.00 bh 45,000.00 180,000.00 3 Kran Air 7.00 bh 37,765.00 264,355.00 4 Cermin/Kaca 1.75 m2 95,000.00 166,250.00 5 Floor Drine 5.00 bh 33,656.00 168,280.00 6 Urinoir + Pemisah 2.00 bh 885,000.00 1,770,000.00 7 Tempat Sabun Ex. TOTO (11x11 cm) 4.00 bh 44,520.00 178,080.00 8 Washtafel Ex KIA Lengkap 2.00 bh 640,469.20 1,280,938.40

9,139,698.60

X PEK. MEKANIKAL & ELEKTRIKAL LT 1 & 21 ELEKTRIKALA Panel Utama1 Panel Utama 1.00 unit ls 3,200,000.00 2 Panel AS. 1 1.00 unit ls 2,860,000.00 B ARMATURE1 Lampu Baret Bulat 22.00 bh 85,150.00 1,873,300.00 2 Lampu Baca, TL, 1 x 18 W 36.00 bh 66,400.00 2,390,400.00 3 Lampu TL 2 x 20 w Inbow 22.00 bh 95,100.00 2,092,200.00 4 Lampu Pijar 25 w 8.00 bh 2,960.00 23,680.00 C SAKLAR & STOP KONTAK1 Saklar Tunggal 66.00 bh 20,600.00 1,359,600.00 2 Saklar Ganda 6.00 bh 24,100.00 144,600.00 3 Stop Kontak Biasa 54.00 bh 25,000.00 1,350,000.00 4 Stop Kontak AC 4.00 bh 86,700.00 346,800.00

Page 24: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML HARGA

(Rp) ( Rp )

D INSTALASI1 Instalasi Penerangan 88.00 ttk 165,740.00 14,585,120.00 2 Instalasi Stop Kontak 54.00 ttk 175,560.00 9,480,240.00 3 Instalasi Stop kontak AC 4.00 ttk 195,200.00 780,800.00 4 Gronding System 1.00 lot 442,200.00 442,200.00 5 Kabel Feeder NYY 4 x 6 mm 4.00 m' 20,800.00 83,200.00

Dari P.U - P. AS Putri6 Kabel Feeder NYY 4 x 10 mm 46.00 m' 26,700.00 1,228,200.00

Dari P.U - P. AS Putra7 Kabel Feeder NYY 4 x 6 mm 68.00 m' 20,800.00 1,414,400.00

Dari P.U - P. Dokter8 Kabel 4 x 25 Dari Mob - PU Asrama Putra 68.00 m' 62,400.00 4,243,200.00 9 Instalasi Exaust Fan 12.00 titik 175,560.00 2,106,720.00

JUMLAH 1=A+B+C+D 50,004,660.00 2 AIR CONDITIONING

AC Split : Air ConditioningType : Wall Mounted

1 Kapasitas 9000 BTU/H Type G 4.00 bh 3,200,000.00 12,800,000.00 2 Exaust Fan 12.00 bh 330,000.00 3,960,000.00

Instalasi1 Pipa Refrigator c/w Isolation 24.00 m 54,000.00 1,296,000.00 2 Pipa Drain AC 16.00 m 8,600.00 137,600.00

JUMLAH 2 18,193,600.00 3 TELEPON1 Terminl Box Tlp 1.00 bh 176,000.00 176,000.00 2 Soket Outlet Telepon 1.00 bh 55,450.00 55,450.00 3 Instalasi Outlet Telepon ITC 2 x 2 x 0,6 mm 1.00 ttk 167,800.00 167,800.00 4 Kabel Tlp ITL 2x2x0,6 mmj + Konduit 79.35 m 12,625.00 1,001,793.00

( Dari Bag. Utama - As.1 )JUMLAH 3 1,401,043.00

4 MATV1 Instalasi MATV 2.00 ttk 186,000.00 372,000.00 2 Boster 1.00 bh 80,000.00 80,000.00 3 Spliter 1.00 bh 160,000.00 160,000.00 4 Soket Outlet TV 2.00 bh 85,200.00 170,400.00 5 Kabel TV, Coaxial + Conduit 97.00 m 13,437.00 1,303,389.00

( Dari Bag. Utama - As.1 )JUMLAH 4 2,085,789.00

5 PLAMBINGA Instalasi Air Bersih Dlm Gedung1 Pipa GIP dia 25 mm 12.00 m 35,190.00 422,280.00 2 Pipa GIP dia 20 mm 36.00 m 21,170.00 762,120.00 3 Pipa GIP dia 15 mm 60.00 m 17,835.00 1,070,100.00 4 Pipa GIP dia 50 mm 70.00 m 63,800.00 4,466,000.00 B Instalasi Air Kotor Dlm Gedung1 Pipa PVC dia 100 mm 24.00 m 87,246.00 2,093,904.00 2 Pipa PVC dia 80 mm 16.00 m 56,592.00 905,472.00 3 Gate Valve ø 25 mm 2.00 bh 80,000.00 160,000.00

Page 25: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML HARGA

(Rp) ( Rp )

C Instalasi Air Kotor Di Luar Gedung1 Pipa PVC dia 150 mm 43.00 m 153,270.00 6,590,610.00 2 Pipa PVC dia 100 mm 128.00 m 87,246.00 11,167,488.00 3 Pipa PVC dia 80 mm 32.00 m 56,592.00 1,810,944.00

JUMLAH 5=A+B+C 29,448,918.00 JML=1+2+3+4+5 101,134,010.00

XI PEK. LAIN-LAIN1 Pekerjaan Pembersihan Lantai Dasar dan Dua 1.00 unit 2,500,000.00 2,500,000.00

2,500,000.00

Page 26: Kor Training Centre

RENCANA ANGGARAN BIAYATRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

TAHUN ANGGARAN 2006

PEKERJAAN : POS JAGA

NO URAIAN PEKERJAAN JML. HARGA

I PEKERJAAN PENDAHULUAN Rp 279,988.00 II PEKERJAAN TANAH Rp 102,135.69 III PEKERJAAN PASIR Rp 181,736.18 IV PEKERJAAN PONDASI BATU KALI Rp 1,025,689.72 V PEKERJAAN PEMASANGAN BATU BATA Rp 1,685,706.29 VI PEKERJAAN PLESTERAN Rp 1,182,516.38 VII PEKERJAAN BETON Rp 3,857,063.06 VIII PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 1,198,233.41 IX PEKERJAAN KERAMIK LANTAI DAN DINDING Rp 1,384,328.95 X PEKERJAAN PLAFOND Rp 924,937.28 XI PEKERJAAN PENGECATAN Rp 1,531,790.90 XII PEKERJAAN SANITASI Rp 4,502,121.36 XIII PEKERJAAN INSTALASI LISTRIK Rp 1,271,086.40 XIV PEKERJAAN ATAP Rp 6,509,154.89

A REAL COST Rp 25,636,488.49 Dibulatkan Rp 25,636,000.00

Terbilang : Dua puluh lima juta enam ratus tiga puluh enam ribu rupiah,-

Makassar, Desember 2005

Konsultan PerencanaCV. PRAPRIMADANI PRATAMA

SUMARNI, SH.

Direktris

Page 27: Kor Training Centre

RENCANA ANGGARAN BIAYATRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

TAHUN ANGGARAN 2006

PEKERJAAN : POS JAGA

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

I PEKERJAAN PENDAHULUAN1 Pek. Pengukuran Dan Pas. Bouwplank 10.50 M' 2,856.00 29,988.00 2 Pek. Air kerja + P3K 1.00 Ls 250,000.00 250,000.00

279,988.00

II PEKERJAAN TANAH1 Pek. Galian Tanah Biasa 8.85 M3 10,304.00 91,205.86 2 Pek. Urugan Tanah Bekas Galian 2.21 M3 4,939.20 10,929.83

102,135.69

III PEKERJAAN PASIR1 Pek. Pasir Urug Alas Pondasi 0.81 M3 92,064.00 74,433.74 2 Pek. Pasir Urug Alas Sloef Utama - M3 92,064.00 0.00 3 Pek. Pasir Urug Alas Lantai 1.17 M3 92,064.00 107,302.43

181,736.18

IV PEKERJAAN PONDASI BATU KALI1 Pek. Pasangan Batu Kosong 1.62 M3 149,805.60 242,235.66 2 Pek. Pondasi Batu Kali (1 pc : 5 psr) 2.58 M3 303,311.68 783,454.07

1,025,689.72

V PEKERJAAN PEMASANGAN BATU BATA 1 Pek. Pas. Pondasi Bt. Bata Trasram (1pc : 3psr) 3.54 M2 111,989.92 396,668.30 2 Pek. Pas. Bt. Bata, tebal 1/2 bt (1pc : 5psr) 25.62 M2 50,323.56 1,289,037.99

1,685,706.29

VI PEKERJAAN PLESTERAN 1 Plesteran t : 15 mm (1pc : 3psr) - M2 18,220.44 0.00 2 Plesteran t : 15 mm (1pc : 5psr) 45.90 M2 16,717.68 767,341.51 3 Plesteran Beton t : 15 mm (1pc : 2psr) - M2 19,709.48 0.00 4 Pek. Acian (saus semen) 45.90 M2 9,045.20 415,174.86

1,182,516.38

VII PEKERJAAN BETON1 Pek. Rabat Beton t : 7 cm (Alas Lantai) 4.50 M2 62,584.52 281,630.36 2 Pek. Kolom Praktis (15 x 15) 0.42 M3 3,497,445.81 1,479,419.58 3 Pek. Sloef Praktis (15 x 20) 0.32 M3 2,589,868.25 815,808.50 4 Pek. Balok Gantung / Latei (15 x 25) 0.13 M3 3,192,283.19 409,809.35 5 Pek. Plat Meja Beton 0.04 M3 4,459,330.72 173,022.03 6 Pek. Ringbalk (15 x 20) 0.32 M3 2,213,883.28 697,373.23

3,857,063.06

VIII PEKERJAAN KUSEN, PINTU DAN JENDELA1 Pek. Kusen Kayu Kls I 0.06 M3 6,685,280.00 376,047.00 2 Pek. Pintu Panel Kayu Kls I 1.44 M2 378,000.00 544,320.00 3 Pek. Pas. Engsel Pintu 3.00 Bh 18,827.20 56,481.60 4 Pek. Pas. Kunci Pintu Km/Wc 1.00 Bh 148,820.00 148,820.00 5 Pek. Pas. Grendel Pintu 1.00 Bh 25,216.80 25,216.80 6 Pas. Kaca Buram 5 mm 0.37 M2 127,279.60 47,348.01

1,198,233.41

Page 28: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

IX PEKERJAAN KERAMIK LANTAI DAN DINDING1 Pek. Keramik Lantai 30 x 30 cm 3.00 M2 77,366.24 232,098.72 2 Pek. Keramik Lantai Km/Wc 20 x 20 cm 1.50 M2 76,436.64 114,654.96 3 Pek. Keramik Dinding Km/Wc 20 x 25 cm 5.40 M2 81,942.56 442,489.82 4 Pek. Keramik Meja Beton 20 x 20 cm 0.36 M2 77,536.64 27,913.19 5 Pek. Selasar Pos Jaga 9.06 M2 62,584.52 567,172.26

1,384,328.95

X PEKERJAAN PLAFOND 1 Pek. Rangka Plafond Kayu Kls II 10.43 M2 37,016.00 385,938.07 2 Pek. Plafond GRC 10.43 M2 22,182.40 231,279.21 3 Pek. Pas. List Profil Kayu 35.00 M' 8,792.00 307,720.00

924,937.28

XI PEKERJAAN PENGECATAN1 Pek. Pengecatan Dinding 45.90 M2 23,112.32 1,060,855.49 2 Pek. Pengecatan Plafond 10.43 M2 23,112.32 240,974.83 3 Pek. Cat Kayu 9.38 M2 19,598.32 183,734.25 4 Pek. Residu Rangka Plafond 10.34 M2 4,470.20 46,226.34

1,531,790.90

XII PEKERJAAN SANITASI1 Pek. Pas. Kloset Jongkok 1.00 Bh 256,710.80 256,710.80 2 Pek. Pas. Kran Air 2.00 Bh 37,765.00 75,530.00 3 Pek. Pas. Tempat Sabun 1.00 Bh 44,520.00 44,520.00 4 Pek. Pas. Floordrain 1.00 Bh 33,656.00 33,656.00 5 Pek. Pas. Pipa Air PVC (D) Dia. 3" 9.00 M' 49,686.56 447,179.04 6 Pek. Pas. Pipa Air PVC (AW) Dia. 3/4" 41.00 M' 13,860.00 568,260.00 7 Pek. Septictank 1.00 Bh 2,576,265.52 2,576,265.52 8 Alat Bantu Instalasi 1.00 Ls 500,000.00 500,000.00

4,502,121.36

XIII PEKERJAAN INSTALASI LISTRIK 1 Pek. Instalasi Penerangan 2.00 Ttk 219,436.00 438,872.00 2 Pek. Instalasi Titik Stop Kontak 1.00 Ttk 160,070.40 160,070.40 3 Pek. Pas. Stop Kontak 1.00 Bh 28,560.00 28,560.00 4 Pek. Pas. Saklar Tunggal 2.00 Bh 22,624.00 45,248.00 5 Pek. Pas. Fitting Lampu 2.00 Bh 20,608.00 41,216.00 6 Pek. Pas. Lampu SLE 20W E27 1.00 Bh 51,520.00 51,520.00 7 Pek. Pas. Lampu Pijar GLS Clear 25W 1.00 Bh 5,600.00 5,600.00 8 Alat Bantu Instalasi 1.00 Ls 500,000.00 500,000.00

1,271,086.40

XIV PEKERJAAN ATAP 1 Pek. Kuda - Kuda Kayu Kls. I 0.23 M3 6,336,848.00 1,433,040.15 2 Pek. Gording Kayu Kls. I 0.21 M3 6,294,848.00 1,323,428.84 3 Pek. Kasau + Reng Kayu Kls. I 20.58 M2 69,944.00 1,439,447.52 4 Pek. Lesplank Kayu Kls. I 16.60 M' 62,664.00 1,040,222.40 5 Pek. Atap Genteng Beton Glazur 20.58 M2 46,625.60 959,554.85 6 Pek. Nok Genteng Beton Glazur 12.45 M' 25,177.60 313,461.12

6,509,154.89

Real cost Rp. 25,636,488.49

Page 29: Kor Training Centre

RENCANA ANGGARAN BIAYATRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

TAHUN ANGGARAN 2006

PEKERJAAN : SITE DEVELOPMENT

NO URAIAN PEKERJAAN JML. HARGA

I PEK. PERSIAPAN Rp 5,000,000.00 II PEK. TROTOAR PAVING Rp 434,763,228.60 III PEK. PARKIR + JALAN KOMPLEKS Rp 2,415,310,268.80 IV PEK. SALURAN KOMPLEKS Rp 40,902,899.73 V PEK. SALURAN LUAR KOMPLEKS Rp 114,833,934.21 VI PEK. TIANG BENDERA Rp 5,585,693.39 VII PEK. CANSTEEN Rp 354,663,549.80 VIII PEK. TAMAN Rp 83,772,823.66 IX PEK. PENERANGAN KOMPLEKS Rp 412,500,000.00 X PEK. PAGAR Rp 935,219,000.00 XI PEKERJAAN LAIN - LAIN Rp 7,500,000.00

REAL COST SITE DEVELOPMENT Rp 4,810,051,398.19 Dibulatkan Rp 4,810,051,000.00

Terbilang : Dua ratus enam puluh sembilan juta empat ratus sembilan puluh empat ribu rupiah,-

Makassar, Desember 2005

Konsultan Perencana

CV. PRAPRIMADANI PRATAMA

SUMARNI, SH.Direktris

Page 30: Kor Training Centre

RENCANA ANGGARAN BIAYATRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

TAHUN ANGGARAN 2006

PEKERJAAN : SITE DEVELOPMENT

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

I PEK. PERSIAPAN1 Pengukuran Dan Pemasangan Bouwplank - M' 2,856.00 0.00 2 Air Kerja Dan P3K 1.00 Ls 5,000,000.00 5,000,000.00

5,000,000.00 II PEK. TROTOAR PAVING1 Pemadatan Tanah 457.65 M3 8,220.00 3,761,883.00 2 Pek. Timbunan Sirtu 610.20 M3 136,808.00 83,480,241.60 3 Pek. Paving Block 3,051.00 M2 113,904.00 347,521,104.00

434,763,228.60

III PEK. PARKIR + JALAN KOMPLEKS1 Pek. Timbunan Tanah - M3 0.00 0.00 2 Pek. Timbunan Sirtu Halaman 2,723.60 M3 136,808.00 372,610,268.80 3 Pek. Jalan Aspal 13,618.00 M2 150,000.00 2,042,700,000.00

2,415,310,268.80

IV PEK. SALURAN KOMPLEKS 1,026.00 M'1 Saluran Air Terbuka 906.00 M1 24,019.04 21,761,251.33 2 Saluran Air Tertutup 120.00 M1 53,347.07 6,401,648.40 3 Pemasangan Grill Saluran 36.40 M1 350,000.00 12,740,000.00

40,902,899.73 V PEK. SALURAN LUAR KOMPLEKS 400.00 M'1 Pek. Galian Tanah 208.00 M3 10,304.00 2,143,232.00 2 Pek. Urugan Pasir Alas Pondasi + Alas Rabat 32.00 M3 92,064.00 2,946,048.00 3 Pek. Pas. Bt. Kosong 64.00 M3 149,805.60 9,587,558.40 4 Pek. Pondasi Bt. Gunung (1 pc : 5 ps) 238.00 M3 303,311.68 72,188,179.84 5 Pek. Plesteran Pondasi (1 pc : 4 ps) 1,040.00 M2 17,264.80 17,955,392.00 6 Pek. Rabat Dasar Saluran 160.00 M2 62,584.52 10,013,523.97

114,833,934.21

VI PEK. TIANG BENDERA1 Pek. Galian Tanah 3.38 M3 10,304.00 34,776.00 2 Pek. Urugan Kembali 2.59 M3 4,939.20 12,802.41 3 Pek. Urugan Pasir Alas Pondasi 0.23 M3 92,064.00 20,714.40 4 Pek. Pas. Lantai Kerja 2.25 M2 62,584.52 140,815.18 5 Pek. Pondasi Poer 0.68 M3 2,413,937.72 1,651,133.40 6 Pek. Stek Poer 0.10 M3 3,295,003.59 326,205.36 7 Pek. Beton Tiang Bendera 0.37 M3 3,713,110.80 1,358,070.28 8 Pek. Acian Tiang Bendera 5.04 M2 9,045.20 45,587.83 9 Pek. Pengecatan 5.04 M2 67,122.72 338,298.51

10 Pek. Profil Kaki Dan Puncak Tiang Bendera 1.00 Ls 1,500,000.00 1,500,000.00 11 Pek. Paving Block Keliling Tiang Bendera 1.38 M2 113,904.00 157,290.03

5,585,693.39

Page 31: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

VII PEK. CANSTEEN 3,619.50 M'1 Pek. Beton Cansteen 542.93 M3 418,971.84 227,470,286.23 2 Pek. Pasir Urug Alas Cansteen 90.49 M3 92,064.00 8,330,641.20 3 Pek. Plesteran Beton Cansteen 2,171.70 M2 18,220.44 39,569,329.55 4 Pek. Acian 2,171.70 M2 9,045.20 19,643,469.53 5 Pek. Pengecatan 2,171.70 M2 27,466.88 59,649,823.30

354,663,549.80

VIII PEK. TAMAN1 Pek. Urugan Tanah Subur 27.01 M3 42,604.80 1,150,873.96 2 Pek. Tanam Rumput Gajah 122.79 M2 21,330.56 2,619,079.66 3 Pek. Tanaman Pohon Asoka 761.00 Btg 75,491.24 57,448,833.64 4 Pek. Tanaman Pohon Palm Raja 80.00 Btg 180,491.24 14,439,299.20 5 Pek. Tanaman Pohon Palm Botol 30.00 Btg 270,491.24 8,114,737.20

83,772,823.66

IX PEK. PENERANGAN KOMPLEKS1 Pek. Pas. Lampu Taman Kompleks + Inst. 30.00 Unit 7,000,000.00 210,000,000.00 2 Pek. Panel Induk Listrik Kompleks 1.00 Ls 45,000,000.00 45,000,000.00 3 Pek. Kabel Tanam (Kabel Tanah) 1,500.00 M1 105,000.00 157,500,000.00

412,500,000.00

X PEKERJAAN LAIN - LAIN1 Pekerjaan Pembersihan 1.00 Ls 7,500,000.00 7,500,000.00

7,500,000.00

Real Cost Rp. 3,874,832,398.19

Page 32: Kor Training Centre

RENCANA ANGGARAN BIAYATRAINING CENTER - KAWASAN OLAHRAGA SUDIANG

TAHUN ANGGARAN 2006

PEKERJAAN : PEMBANGUNAN PAGAR

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

I PEK. PERSIAPAN1 Penyediaan P3K + Air Kerja 1.00 Ls 500,000.00 500,000.00 2 Pengukuran + Bouwplank 210.00 M' 2,856.00 599,760.00

1,099,760.00 II PEKERJAAN PAGAR DEPAN 1 PEK. BETONa Sloof Praktis 10.50 M3 2,242,255.96 23,543,687.58 b Ringbalk Praktis (Dudukan Pagar Besi) 7.56 M3 2,213,883.28 16,736,957.61

40,280,645.19 2 PEK. PILAR PAGAR 35.00 Bha Kolom Beton 4.36 M3 3,295,250.22 14,361,171.53 b Pas. Batu Bata Biasa 1:5 181.93 M2 50,323.56 9,155,365.27 c Plesteran Tembok 209.09 M2 16,717.68 3,495,499.71 d Acian (Saus Semen) 209.09 M2 9,045.20 1,891,261.70 e Cat Tembok 209.09 M2 27,466.88 5,743,049.94

34,646,348.15 3 PEK. TEMBOK KAKI PAGAR 196.00 M'a Pas. Batu Bata Biasa 1:5 94.08 M2 50,323.56 4,734,440.52 b Plesteran Tembok (1:5) 188.16 M2 16,717.68 3,145,598.67 c Acian (Saus Semen) 188.16 M2 9,045.20 1,701,945.58 d Cat Tembok 188.16 M2 27,466.88 5,168,168.14

14,750,152.92

4 PEK. PAPAN NAMA (PAGAR DEPAN) 10.000 m'a Ringbalk Praktis 0.38 M3 2,213,883.28 830,206.23 b Pas. Batu Bata Biasa 1:5 3.00 M2 50,323.56 150,970.68 c Plesteran Tembok (1:5) 40.00 M2 16,717.68 668,707.20 d Acian (Saus Semen) 40.00 M2 9,045.20 361,808.16 e Cat Tembok 40.00 M2 27,466.88 1,098,675.20 f Pek. Nama Kompleks 1.00 Unit 5,000,000.00 5,000,000.00

8,110,367.47

5 Pek. Pagar Besi + Pintu Besi 196.00 M' 600,000.00 117,600,000.00

Total Pagar Depan 216,487,273.73

Page 33: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

III PEKERJAAN PAGAR SAMPING KANAN 371.00 1 PEK. BETONa Sloof Praktis 13.91 M3 2,242,255.96 31,195,386.04 b Ringbalk Praktis (Dudukan Pagar Besi) 13.91 M3 2,213,883.28 30,800,651.15

61,996,037.20 2 PEK. PILAR PAGAR 124.00 Bha Kolom Beton 12.40 M3 3,295,250.22 40,860,004.35 b Pas. Batu Bata Biasa 1:5 - M2 50,323.56 0.00 c Plesteran Tembok 223.19 M2 16,717.68 3,731,285.87 d Acian (Saus Semen) 223.19 M2 9,045.20 2,018,835.26 e Cat Tembok 223.19 M2 27,466.88 6,130,442.81

52,740,568.30 3 PEK. TEMBOK a Pas. Batu Bata Biasa 1:5 103.86 M2 50,323.56 5,226,615.01 b Plesteran Tembok (1:5) 1,384.80 M2 16,717.68 23,150,687.84 c Acian (Saus Semen) 1,384.80 M2 9,045.20 12,525,822.62 d Cat Tembok 1,384.80 M2 27,466.88 38,036,208.67

78,939,334.14

4 Pek. Pagar Besi + Pintu Besi - M' 725,000.00 0.00

Total Pagar S. Kanan 193,675,939.63

IV PEKERJAAN PAGAR SAMPING KIRI 210.00 M'1 PEK. BETONa Sloof Praktis 7.88 M3 2,242,255.96 17,657,765.69 b Ringbalk Praktis 7.88 M3 1,938,510.56 15,265,770.66 c Kolom 7.00 M3 3,713,110.80 25,991,775.60

58,915,311.95

2 PEK. TEMBOKa Pas. Batu Bata Biasa 1:5 12.60 M2 50,323.56 634,076.86 b Plesteran Tembok (1:5) 168.00 M2 16,717.68 2,808,570.24 c Acian (Saus Semen) 168.00 M2 9,045.20 1,519,594.27 d Cat Tembok 168.00 M2 27,466.88 4,614,435.84

9,576,677.21

3 Pek. Pintu Besi - Bh 750,000.00 0.00

Total Pagar S. Kiri 68,491,989.15

Page 34: Kor Training Centre

NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT. JML. HARGA

V PEKERJAAN PAGAR BELAKANG 235.00 1 PEK. BETONa Sloof Praktis 8.81 M3 2,242,255.96 19,759,880.65 b Ringbalk Praktis 8.81 M3 1,938,510.56 17,083,124.31 c Balok Latei - M3 2,213,883.28 0.00 d Kolom 7.83 M3 3,713,110.80 29,086,034.60

65,929,039.56 2 PEK. TEMBOK PAGARa Pas. Batu Bata Biasa 1:5 70.50 M2 50,323.56 3,547,810.98 b Plesteran Tembok (1:5) 940.00 M2 16,717.68 15,714,619.20 c Acian (Saus Semen) 940.00 M2 9,045.20 8,502,491.76 d Cat Tembok 940.00 M2 27,466.88 25,818,867.20

53,583,789.14 Total Pagar Belakang 119,512,828.70

VI PEK. DECKER + talud 24.00 M'1 Galian Tanah Pondasi 656.64 M3 10,304.00 6,766,018.56 2 Pasir Urug Alas Pondasi 82.08 M3 92,064.00 7,556,613.12 3 Pas. Batu Kosong 164.16 M3 149,805.60 24,592,087.30 4 Pondasi Bt.Gunung 718.20 M3 303,311.68 217,838,448.58 5 Plester Pondasi 2,872.80 M2 17,264.80 49,598,317.44 6 Plat Beton Decker 8.64 M3 3,194,339.94 27,599,097.09 7 Tembok Leaning 19.20 M2 104,181.84 2,000,291.33

335,950,873.41

Real Cost Rp. 935,218,664.63

Page 35: Kor Training Centre

PEMERINTAH PROPINSI SULAWESI SELATANDINAS TATA RUANG DAN PERMUKIMAN

Jalan Andi Pangerang Pettarani No. 90 Tlp. 0411-458489 Makassar

Dokumen Usulan Biaya :

RENCANA ANGGARAN BIAYA

Pekerjaan :

TRAINING CENTREKAWASAN OLAHRAGA SUDIANG

CV. PRAPRIMADANI PRATAMA PERENCANAAN ~ PENGAWASAN ~ STUDI-STUDI ~ PENGUKURAN ~ PEMETAAN

Jalan Baji Rupa No. 16, Tlp (0411) 857226, Fax (0411) 830684

E-mail : [email protected] ~ Makassar 90224

Page 36: Kor Training Centre

DAFTAR HARGA BAHAN MATERIAL DAN UPAH KERJAPEMBANGUNAN GEDUNG SIDRAP CENTER DI MAKASSAR

TAHUN ANGGARAN 2005

No NAMA MATERIAL HARGA & SATUAN

1 Batu Gunung/Batu Belah Rp 77,280.00 /m32 Pasir Urug Rp 70,840.00 /m33 Tanah Timbunan Rp 29,624.00 /m34 Sirtu Rp 108,640.00 /m35 Pasir Pasangan Rp 83,720.00 /m36 Pasir Beton Rp 122,080.00 /m37 Koral Beton/split (Batu pecah 2-3 cm) Rp 149,408.00 /m38 Semen Portland @ 50 kg Rp 812.00 /Kg9 Semen Putih Rp 6,440.00 /Kg

10 Bata merah 5 x 11 x 22 cm Rp 380.80 /Bh11 Paving Block T : 8 cm Rp 1,624.00 /Bh12 Besi Beton Polos / Ulir Rp 7,728.00 /Kg13 Sekop Rp 19,320.00 /Bh14 Pacul Rp 20,608.00 /Bh15 Kawat Beton Rp 10,864.00 /Kg16 Paku biasa 1/2" - 1" Rp 8,960.00 /Kg17 Paku biasa 2" - 5" Rp 8,960.00 /Kg18 Paku Skrup 3,5" Rp 9,632.00 /Kg19 Bubungan Genteng Beton Glazur Rp 3,080.00 /Bh20 Genteng Beton Glazur Rp 2,968.00 /Bh21 Karet Pelapis Genteng Rp 8,400.00 /M224 Tegel Keramik 20x25 Untuk Dinding Rp 1,456.00 /Bh25 Tegel Keramik 30x30 (Bermotif) Rp 3,360.00 /Bh26 Tegel Keramik 40x40 Rp 7,168.00 /Bh28 Tegel Keramik 20x20 ( Warna ) Rp 1,500.00 /Bh30 Tegel Keramik 20x20 (Kasar) Rp 1,456.00 /Bh31 Plin Keramik 10 x 40 Rp 2,800.00 /Bh34 Multipleks 6 mm Rp 60,410.56 /M235 Multipleks 9 mm Rp 103,131.84 /M236 Gypsum Board 9 mm Rp 18,032.00 /M236 Gypsum Board 12 mm Rp 32,200.00 /M237 Profil Gypsum Type CA (Besar) Rp 36,708.00 /M138 Profil Gypsum Type CE (Sedang) Rp 25,760.00 /M139 Profil Gypsum Type SL (Kecil) Rp 22,540.00 /M141 GRC 4 mm Rp 16,648.00 /M242 Kaca Buram 5mm Rp 109,424.00 /m243 Kaca Rayband 5mm Rp 96,544.00 /m244 Kaca Bening 5mm Rp 83,664.00 /m245 Kaca 10 mm Rp 167,440.00 /m249 Kayu Kls I (Balok Somil) Rp 5,152,000.00 /m350 Kayu Kls I (Papan Somil) Rp 6,118,000.00 /m351 Kayu Kls I (Balok Senso) Rp 3,542,000.00 /m352 Kayu Kls II (Balok) Rp 1,610,000.00 /m353 Kayu Kls II (Papan) Rp 1,932,000.00 /m354 Kayu Kls III (Balok) Rp 1,242,920.00 /m352 Kayu Kls III (Papan) Rp 1,242,920.00 /m354 Kayu Dolken Rp 8,960.00 /Btg56 Formtie/penjaga jarak bekisting/spacer Rp 6,440.00 /Bh

Page 37: Kor Training Centre

No NAMA MATERIAL HARGA & SATUAN

57 Minyak Bekisting Rp 12,208.00 /Ltr58 List Plafond (Kayu Profil 3x4) Rp 4,816.00 /m167 Cat Tembok (Metrolite / Catilac) Rp 55,328.00 /Kg68 Cat Tembok (Dulux/Mowilex) Rp 105,280.00 /Kg69 Cat Kayu Ex. Glotex Rp 30,912.00 /Kg70 Cat Dasar Rp 32,200.00 /Kg71 Cat Meni Kayu/Besi Merek Gloteks Rp 29,624.00 /Kg72 Cat Residu / Alcater Rp 5,796.00 /Ltr73 Cat Waterproofing Rp 86,940.00 /Kg74 Cat Arcilic Anti Lumut Rp 97,216.00 /Kg75 Lem Kayu Rp 7,500.00 /Ltr76 Plamur Rp 25,760.00 /Kg77 Minyak Cat Rp 10,948.00 /Lt79 Kran Air Stainless Stell Rp 32,200.00 /Bh80 Stop Kran Rp 19,320.00 /Bh81 Washtafel Ex. KIA Lengkap Rp 483,000.00 /Bh82 Kloset Jongkok Rp 150,000.00 /Bh83 Kloset Duduk Ex. TOTO/KIA (dud Blok) Rp 1,094,800.00 /Set84 Floor Drine Rp 28,896.00 /Bh86 Urinoir Ex. KIA/TOTO (Lengkap) Rp 966,000.00 /Set87 Tempat Sabun Ex. Toto (11x11 cm) Rp 39,760.00 /Bh91 PVC Dia 4" (D) Rp 32,816.00 /M'92 PVC Dia 3" (D) Rp 26,992.00 /M'93 PVC Dia 1" Rp 11,760.00 /M'94 PVC Dia 3/4" Rp 5,040.00 /M'95 PVC Dia 2" Rp 16,240.00 /M'96 PVC Dia 5/8" Rp 2,800.00 /Btg97 Bak Air Fiberglass (Tangki) 1 M3 Rp 702,000.00 /Bh98 Bak Air Fiberglass (Tangki) 3 M3 Rp 910,000.00 /Bh99 Baut-Baut Rp 3,864.00 /Bh100 Besi Strip Rp 2,800.00 /M'101 Engsel Pintu Biasa Rp 23,828.00 /Psg102 Engsel Jendela Rp 6,440.00 /Psg103 Engsel Pintu KW1 Rp 32,200.00 /Psg104 Engsel Jendela KW1 Rp 27,048.00 /Psg

105 Engsel Tanam (Atas Bawah) Otomatis Rp 38,640.00 /Psg106 Expanyolet Tempel / Dor Closer Rp 59,248.00 /Set107 Grendel Jendela / Pintu Kodok Rp 20,608.00 /Bh108 Grendel Tanam Rp 25,760.00 /Psg109 Rel Pintu Dorong Rp 193,200.00 /Bh110 Kunci Pintu 2x Putar (Ex Yale) Rp 90,160.00 /Bh109 Kunci Bulat KW1 Rp 128,800.00 /Bh110 Kunci Pintu Dorong Rp 96,600.00 /Bh111 Hak Angin Rp 4,480.00 /Psg113 Lampu SLE 20 W E27 Rp 51,520.00 /Bh114 Lampu TL 2 x 20 Watt Rp 108,192.00 /Bh115 Lampu TL 2 x 36 Watt Rp 109,480.00 /Set117 Lampu Pijar GLS Clear 25W Rp 5,600.00 /Bh118 Stop Kontak Rp 28,560.00 /Bh119 Stop Kontak AC Rp 100,128.00 /Bh

Page 38: Kor Training Centre

No NAMA MATERIAL HARGA & SATUAN

120 Saklar Tunggal Rp 22,624.00 /Bh121 Saklar Ganda Rp 27,328.00 /Bh122 Fitting Lampu Rp 20,608.00 /Bh123 Kabel NYM (2x2,5) mm Rp 8,120.00 /M1124 Kabel NYM (3x2,5) mm Rp 9,184.00 /M1125 Klem Kabel No. 10 Rp 280.00 /Bh126 Klem Kabel No. 12 Rp 280.00 /Bh127 Inbow Dos Rp 3,360.00 /Bh

128 Las Dop Rp 280.00 /Bh

129 Isolasi Rp 1,680.00 /Roll

130 T - Dos 5/8" Rp 224.00 /Bh

131 Kabel Telpon Rp 1,680.00 /M1132 Stop Kontak Telpon KW1 Rp 151,200.00 /Bh133 Kotak Sambungan Rp 7,800.00 /Bh155 Lantai Parquet Jati Rp 610,400.00 /M2156 Lem Vinyl Rp 16,800.00 /Kg157 Pupuk Kandang Rp 3,220.00 /Kg

155 Pupuk Anorganik Rp 5,796.00 /Kg

No NAMA TENAGA KERJA UPAH & SATUAN

1 Tukang Instalasi Rp 39,200.00 Org/Hr2 Tukang Taman Rp 39,200.00 Org/Hr3 Tukang cat Rp 33,600.00 Org/Hr4 Tukang besi Rp 33,600.00 Org/Hr5 Tukang Gali Rp 33,600.00 Org/Hr6 Tukang batu Rp 39,200.00 Org/Hr7 Tukang kayu Rp 39,200.00 Org/Hr8 Kepala tukang Rp 44,800.00 Org/Hr9 Pekerja Rp 22,400.00 Org/Hr

10 Pekerja Taman Rp 22,400.00 Org/Hr11 Mandor Rp 33,600.00 Org/Hr

Makassar, Desember 2005

Pemimpin Kegiatan Konsultan Perencana

CV. BAJIRUPA KONSULTAN

Ir. ABD. RAHMAN SAMAILA Ir. BADARUDDINNip. 110 047 950 Direktur

Page 39: Kor Training Centre
Page 40: Kor Training Centre

1.12

125,000.00 141,666.67 141,666.67

790.00 1,242.50

275.00

6.25 6,320.00

1,700.00

Page 41: Kor Training Centre

900,000.00

Page 42: Kor Training Centre

1350006000

Page 43: Kor Training Centre

DAFTAR ANALISA HARGA SATUANPEMBANGUNAN GEDUNG SIDRAP CENTER DI MAKASSAR

TAHUN ANGGARAN 2005

PEKERJAAN PERSIAPAN1 1 M2 PEMBERSIHAN

0.100 Oh Pekerja @ Rp 22,400.00 Rp 2,240.00

0.050 Oh Mandor @ Rp 33,600.00 Rp 1,680.00

Rp 3,920.00

2 1 M' PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 M

1.250 Btg Kayu Dolken @ Rp 8,960.00 Rp 11,200.00

1.200 Lbr Seng Gelombang BJLS 28 (80x180 c@ Rp 42,400.00 Rp 50,880.00

0.072 M3 Kayu 5/7 ( Kls III ) @ Rp 1,242,920.00 Rp 89,490.24

0.060 Kg Paku Biasa 2' - 5' @ Rp 8,960.00 Rp 537.60

0.200 Oh Tukang Kayu @ Rp 39,200.00 Rp 7,840.00

0.400 Oh Pekerja @ Rp 22,400.00 Rp 8,960.00

0.020 Oh Kepala Tukang @ Rp 44,800.00 Rp 896.00

0.020 Oh Mandor @ Rp 33,600.00 Rp 672.00

Rp 170,475.84

3 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK

0.012 M3 Kayu 5/7 @ Rp 1,242,920.00 Rp 14,915.04

0.02 Kg Paku Biasa 2'-5" @ Rp 8,960.00 Rp 179.20

0.007 M3 Kayu Papan 3/20 @ Rp 1,932,000.00 Rp 13,524.00

0.100 Oh Tukang Kayu @ Rp 39,200.00 Rp 3,920.00

0.100 Oh Pekerja @ Rp 22,400.00 Rp 2,240.00

0.010 Oh Kepala Tukang @ Rp 44,800.00 Rp 448.00

0.005 Oh Mandor @ Rp 33,600.00 Rp 168.00

Rp 2,856.00

4 1 M2 PEKERJAAN KANTOR DIREKSI

0.100 M3 Kayu Kls II @ Rp 1,610,000.00 Rp 161,000.00

0.250 Kg Paku @ Rp 8,960.00 Rp 2,240.00

1.100 Lbr Seng Gelombang BJLS 28 (80x180 c@ Rp 42,400.00 Rp 46,640.00

1.440 Lbr Triplks 3 mm @ Rp 79,200.00 Rp 114,048.00

5.000 Kg PC @ Rp 812.00 Rp 4,060.00

0.250 M3 Pasir Pasang @ Rp 83,720.00 Rp 20,930.00

70.000 Bh Bata Merah @ Rp 380.80 Rp 26,656.00

0.020 Ls Peralatan @ Rp 97000 Rp 1,940.00

0.150 Ls Ongkos Pasang @ Rp 105000 Rp 15,750.00

Rp 393,264.00

PEKERJAAN TANAH1 1 M3 GALIAN TANAH BIASA

0.400 Oh Pekerja @ Rp 22,400.00 Rp 8,960.00

0.040 Oh Mandor @ Rp 33,600.00 Rp 1,344.00

Rp 10,304.00

untuk 1M' Rp 1,030.40

2 1 M3 URUGAN KEMBALI

0.192 Oh Pekerja @ Rp 22,400.00 Rp 4,300.80

0.019 Oh Mandor @ Rp 33,600.00 Rp 638.40

Rp 4,939.20

Page 44: Kor Training Centre

3 1 M3 PEMADATAN TANAH

1.000 Jam Stamper @ Rp 5,000.00 Rp 5,000.00

0.125 Oh Pekerja @ Rp 22,400.00 Rp 2,800.00

0.0125 Oh Mandor @ Rp 33,600.00 Rp 420.00

Rp 8,220.00

4 1 M3 URUGAN PASIR

1.200 M3 Pasir Urug @ Rp 70,840.00 Rp 85,008.00

0.300 Oh Pekerja @ Rp 22,400.00 Rp 6,720.00

0.010 Oh Mandor @ Rp 33,600.00 Rp 336.00

Rp 92,064.00

5 1 M3 TIMBUNAN TANAH

1.200 M3 Tanah Timbunan @ Rp 29,624.00 Rp 35,548.80

0.300 Oh Pekerja @ Rp 22,400.00 Rp 6,720.00

0.010 Oh Mandor @ Rp 33,600.00 Rp 336.00

Rp 42,604.80

6 1 M3 URUGAN SIRTU

1.200 M3 Sirtu @ Rp 108,640.00 Rp 130,368.00

0.250 Oh Pekerja @ Rp 22,400.00 Rp 5,600.00

0.025 Oh Mandor @ Rp 33,600.00 Rp 840.00

Rp 136,808.00 PEKERJAAN PONDASI

1 1 M3 PASANG PONDASI BATU KALI, 1 Pc : 3 Ps

1.100 M3 Batu belah 15/20 cm @ Rp 77,280.00 Rp 85,008.00

202.000 Kg Semen portland @ Rp 812.00 Rp 164,024.00

0.485 M3 Pasir pasangan @ Rp 83,720.00 Rp 40,604.20

1.500 Oh Pekerja @ Rp 22,400.00 Rp 33,600.00

0.600 Oh Tukang batu @ Rp 39,200.00 Rp 23,520.00

0.060 Oh Kepala tukang @ Rp 44,800.00 Rp 2,688.00

0.075 Oh Mandor @ Rp 33,600.00 Rp 2,520.00

Rp 351,964.20

2 1 M3 PASANG PONDASI BATU GUNUNG, 1 Pc : 5 Ps

1.100 M3 Batu Gunung / Bt. Kali belah @ Rp 77,280.00 Rp 85,008.00

136.000 Kg Semen portland @ Rp 812.00 Rp 110,432.00

0.544 M3 Pasir pasangan @ Rp 83,720.00 Rp 45,543.68

1.500 Oh Pekerja @ Rp 22,400.00 Rp 33,600.00

0.600 Oh Tukang batu @ Rp 39,200.00 Rp 23,520.00

0.060 Oh Kepala tukang @ Rp 44,800.00 Rp 2,688.00

0.075 Oh Mandor @ Rp 33,600.00 Rp 2,520.00

Rp 303,311.68

3 1 M3 PASANG PONDASI BATU KOSONG

1.200 M3 Batu Kali belah @ Rp 77,280.00 Rp 92,736.00

0.300 M3 Pasir urug @ Rp 70,840.00 Rp 21,252.00

0.780 Oh Pekerja @ Rp 22,400.00 Rp 17,472.00

0.390 Oh Tukang batu @ Rp 39,200.00 Rp 15,288.00

0.039 Oh Kepala tukang @ Rp 44,800.00 Rp 1,747.20

0.039 Oh Mandor @ Rp 33,600.00 Rp 1,310.40

Rp 149,805.60

PEKERJAAN DINDING

Page 45: Kor Training Centre

1 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc : 2 Ps

140.000 Bh Bata merah 5 x 11 x 22 cm @ Rp 380.80 Rp 53,312.00

43.500 Kg Semen portland @ Rp 812.00 Rp 35,322.00

0.080 M3 Pasir pasangan @ Rp 83,720.00 Rp 6,697.60

0.650 Oh Pekerja @ Rp 22,400.00 Rp 14,560.00

0.200 Oh Tukang batu @ Rp 39,200.00 Rp 7,840.00

0.020 Oh Kepala tukang @ Rp 44,800.00 Rp 896.00

0.030 Oh Mandor @ Rp 33,600.00 Rp 1,008.00

Rp 119,635.60

2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc : 3 Ps

140.000 Bh Bata merah 5 x 11 x 22 cm @ Rp 380.80 Rp 53,312.00

32.950 Kg Semen portland @ Rp 812.00 Rp 26,755.40

0.091 M3 Pasir pasangan @ Rp 83,720.00 Rp 7,618.52

0.650 Oh Pekerja @ Rp 22,400.00 Rp 14,560.00

0.200 Oh Tukang batu @ Rp 39,200.00 Rp 7,840.00

0.020 Oh Kepala tukang @ Rp 44,800.00 Rp 896.00

0.030 Oh Mandor @ Rp 33,600.00 Rp 1,008.00

Rp 111,989.92

3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 Pc : 5 Ps

140.000 Bh Bata merah 5 x 11 x 22 cm @ Rp 380.80 Rp 53,312.00

22.200 Kg Semen portland @ Rp 812.00 Rp 18,026.40

0.102 M3 Pasir pasangan @ Rp 83,720.00 Rp 8,539.44

0.650 Oh Pekerja @ Rp 22,400.00 Rp 14,560.00

0.200 Oh Tukang batu @ Rp 39,200.00 Rp 7,840.00

0.020 Oh Kepala tukang @ Rp 44,800.00 Rp 896.00

0.030 Oh Mandor @ Rp 33,600.00 Rp 1,008.00

Rp 104,181.84

4 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Pc : 3 Ps

70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp 380.80 Rp 26,656.00

14.370 Kg Semen portland @ Rp 812.00 Rp 11,668.44

0.040 M3 Pasir pasangan @ Rp 83,720.00 Rp 3,348.80

0.320 Oh Pekerja @ Rp 22,400.00 Rp 7,168.00

0.100 Oh Tukang batu @ Rp 39,200.00 Rp 3,920.00

0.010 Oh Kepala tukang @ Rp 44,800.00 Rp 448.00

0.015 Oh Mandor @ Rp 33,600.00 Rp 504.00

Rp 53,713.24

5 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Pc : 4 Ps

70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp 380.80 Rp 26,656.00

11.500 Kg Semen portland @ Rp 812.00 Rp 9,338.00

0.043 M3 Pasir pasangan @ Rp 83,720.00 Rp 3,599.96

0.320 Oh Pekerja @ Rp 22,400.00 Rp 7,168.00

0.100 Oh Tukang batu @ Rp 39,200.00 Rp 3,920.00

0.010 Oh Kepala tukang @ Rp 44,800.00 Rp 448.00

0.015 Oh Mandor @ Rp 33,600.00 Rp 504.00

Rp 51,633.96

6 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Pc : 5 Ps

70.000 Bh Bata merah 5 x 11 x 22 cm @ Rp 380.80 Rp 26,656.00

9.680 Kg Semen portland @ Rp 812.00 Rp 7,860.16

0.045 M3 Pasir pasangan @ Rp 83,720.00 Rp 3,767.40

0.320 Oh Pekerja @ Rp 22,400.00 Rp 7,168.00

0.100 Oh Tukang batu @ Rp 39,200.00 Rp 3,920.00

0.010 Oh Kepala tukang @ Rp 44,800.00 Rp 448.00

0.015 Oh Mandor @ Rp 33,600.00 Rp 504.00

Rp 50,323.56

PEKERJAAN PLESTERAN

Page 46: Kor Training Centre

1 1 M3 PLESTERAN 1 Pc : 2 Ps, Tebal 15 mm.

8.520 Kg Semen portland @ Rp 812.00 Rp 6,918.24

0.017 M3 Pasir pasangan @ Rp 83,720.00 Rp 1,423.24

0.200 Oh Pekerja @ Rp 22,400.00 Rp 4,480.00

0.150 Oh Tukang batu @ Rp 39,200.00 Rp 5,880.00

0.015 Oh Kepala tukang @ Rp 44,800.00 Rp 672.00

0.010 Oh Mandor @ Rp 33,600.00 Rp 336.00

Rp 19,709.48

2 1 M2 PLESTERAN 1 Pc : 4 Ps, Tebal 15 mm.

5.200 Kg Semen portland @ Rp 812.00 Rp 4,222.40

0.020 M3 Pasir pasangan @ Rp 83,720.00 Rp 1,674.40

0.200 Oh Pekerja @ Rp 22,400.00 Rp 4,480.00

0.150 Oh Tukang batu @ Rp 39,200.00 Rp 5,880.00

0.015 Oh Kepala tukang @ Rp 44,800.00 Rp 672.00

0.010 Oh Mandor @ Rp 33,600.00 Rp 336.00

Rp 17,264.80

3 1 M2 PLESTERAN 1 Pc : 5 Ps, Tebal 15 mm.

4.320 Kg Semen portland @ Rp 812.00 Rp 3,507.84

0.022 M3 Pasir pasangan @ Rp 83,720.00 Rp 1,841.84

0.200 Oh Pekerja @ Rp 22,400.00 Rp 4,480.00

0.150 Oh Tukang batu @ Rp 39,200.00 Rp 5,880.00

0.015 Oh Kepala tukang @ Rp 44,800.00 Rp 672.00

0.010 Oh Mandor @ Rp 33,600.00 Rp 336.00

Rp 16,717.68

4 1 M2 PLESTERAN 1 Pc : 3 Ps, Tebal 15 mm.

6.480 Kg Semen portland @ Rp 812.00 Rp 5,261.76

0.019 M3 Pasir pasangan @ Rp 83,720.00 Rp 1,590.68

0.200 Oh Pekerja @ Rp 22,400.00 Rp 4,480.00

0.150 Oh Tukang batu @ Rp 39,200.00 Rp 5,880.00

0.015 Oh Kepala tukang @ Rp 44,800.00 Rp 672.00

0.010 Oh Mandor @ Rp 33,600.00 Rp 336.00

Rp 18,220.44

6 10 M2 ACIAN SEMEN (SAUS SEMEN)

59.270 Kg Semen @ Rp 812.00 Rp 48,127.24

0.850 Oh Pekerja @ Rp 22,400.00 Rp 19,040.00

0.500 Oh Tukang batu @ Rp 39,200.00 Rp 19,600.00

0.050 Oh Kepala tukang @ Rp 44,800.00 Rp 2,240.00

0.043 Oh Mandor @ Rp 33,600.00 Rp 1,444.80

Rp 90,452.04

Maka 1 M2 Mengaci = 1/10 Rp 9,045.20

PEKERJAAN KAYU1 1 M3 PASANG KUSEN PINTU DAN JENDELA KAYU KELAS - I

1.100 M3 Kayu Kls I (Balok Somil) @ Rp 5,152,000.00 Rp 5,667,200.00

6.000 Oh Pekerja @ Rp 22,400.00 Rp 134,400.00

20.000 Oh Tukang kayu @ Rp 39,200.00 Rp 784,000.00

2.000 Oh Kepala tukang @ Rp 44,800.00 Rp 89,600.00

0.300 Oh Mandor @ Rp 33,600.00 Rp 10,080.00

Rp 6,685,280.00

2 1 M3 PASANG KUSEN PINTU DAN JENDELA KAYU KELAS - II

1.200 M3 Kayu Kls II (Balok) @ Rp 1,610,000.00 Rp 1,932,000.00

6.000 Oh Pekerja @ Rp 22,400.00 Rp 134,400.00

Page 47: Kor Training Centre

18.000 Oh Tukang kayu @ Rp 44,800.00 Rp 806,400.00

2.000 Oh Kepala tukang @ Rp 44,800.00 Rp 89,600.00

0.300 Oh Mandor @ Rp 33,600.00 Rp 10,080.00

2,972,480.00

3 1 M3 PASANG PINTU PANEL KAYU KELAS I

0.040 M3 Kayu Kls I (Papan Somil) @ Rp 6,118,000.00 Rp 244,720.00

1.000 Oh Pekerja @ Rp 22,400.00 Rp 22,400.00

2.500 Oh Tukang kayu @ Rp 39,200.00 Rp 98,000.00

0.250 Oh Kepala tukang @ Rp 44,800.00 Rp 11,200.00

0.050 Oh Mandor @ Rp 33,600.00 Rp 1,680.00

378,000.00

7 1 M2 MENGERJAKAN PINTU/JENDELA KACA

0.017 M3 Kayu Kls I (Papan Somil) @ Rp 6,118,000.00 Rp 101,781.27

0.800 M2 Kaca 10 MM @ Rp 167,440.00 Rp 133,952.00

6.000 Oh Tukang kayu @ Rp 39,200.00 Rp 235,200.00

0.600 Oh Kepala tukang @ Rp 44,800.00 Rp 26,880.00

2.000 Oh Pekerja @ Rp 22,400.00 Rp 44,800.00

0.100 Oh Mandor @ Rp 33,600.00 Rp 3,360.00

Rp 545,973.27

9 1 M2 PASANG JALUSI MATI KUSEN KAYU KELAS - I

0.0600 M3 Kayu Kls I (Papan Somil) @ Rp 6,118,000.00 Rp 367,080.00

0.150 Kg Paku biasa 1/2" - 1" @ Rp 8,960.00 Rp 1,344.00

0.500 Oh Pekerja @ Rp 22,400.00 Rp 11,200.00

2.000 Oh Tukang kayu @ Rp 39,200.00 Rp 78,400.00

0.200 Oh Kepala tukang @ Rp 44,800.00 Rp 8,960.00

0.025 Oh Mandor @ Rp 33,600.00 Rp 840.00

Rp 467,824.00

10 1 M3 PASANG KONSTRUKSI KUDA-KUDA KAYU KELAS - I

1.1000 M3 Kayu Kls I (Balok Somil) @ Rp 5,152,000.00 Rp 5,667,200.00

15.000 Kg Besi strip @ Rp 2,800.00 Rp 42,000.00

0.800 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 7,168.00

4.000 Oh Pekerja @ Rp 22,400.00 Rp 89,600.00

12.000 Oh Tukang kayu @ Rp 39,200.00 Rp 470,400.00

1.200 Oh Kepala tukang @ Rp 44,800.00 Rp 53,760.00

0.200 Oh Mandor @ Rp 33,600.00 Rp 6,720.00

Rp 6,336,848.00

11 1 M3 PASANG GORDING KAYU KELAS - I

1.1000 M3 Kayu Kls I (Balok Somil) @ Rp 5,152,000.00 Rp 5,667,200.00

0.800 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 7,168.00

4.000 Oh Pekerja @ Rp 22,400.00 Rp 89,600.00

12.000 Oh Tukang kayu @ Rp 39,200.00 Rp 470,400.00

1.200 Oh Kepala tukang @ Rp 44,800.00 Rp 53,760.00

0.200 Oh Mandor @ Rp 33,600.00 Rp 6,720.00

Rp 6,294,848.00

12 1 M2 PASANG KASO + RENG GENTENG BETON KAYU KELAS - I

0.012 M3 Kayu Kelas I (Balok) @ Rp 5,152,000.00 Rp 61,824.00

0.150 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 1,344.00

0.100 Oh Pekerja @ Rp 22,400.00 Rp 2,240.00

Page 48: Kor Training Centre

0.100 Oh Tukang kayu @ Rp 39,200.00 Rp 3,920.00

0.010 Oh Kepala tukang @ Rp 44,800.00 Rp 448.00

0.005 Oh Mandor @ Rp 33,600.00 Rp 168.00

Rp 69,944.00

14 1 M2 PASANG RANGKA LANGIT-LANGIT (1.00 X 1.00) M, KAYU KELAS - II

0.012 M3 Kayu Kelas II (Balok) @ Rp 1,610,000.00 Rp 19,320.00

0.100 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 896.00

0.150 Oh Pekerja @ Rp 22,400.00 Rp 3,360.00

0.250 Oh Tukang kayu @ Rp 39,200.00 Rp 9,800.00

0.025 Oh Kepala tukang @ Rp 44,800.00 Rp 1,120.00

0.075 Oh Mandor @ Rp 33,600.00 Rp 2,520.00

Rp 37,016.00

16 1 M' PASANG LISPLANG UKURAN 2x (2 x 20) CM, KAYU BAYAM

0.0088 M3 Kayu Kls I (Papan Somil) @ Rp 6,118,000.00 Rp 53,838.40

0.060 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 537.60

0.100 Oh Pekerja @ Rp 22,400.00 Rp 2,240.00

0.100 Oh Tukang kayu @ Rp 39,200.00 Rp 3,920.00

0.010 Oh Kepala tukang @ Rp 44,800.00 Rp 448.00

0.050 Oh Mandor @ Rp 33,600.00 Rp 1,680.00

Rp 62,664.00

PEKERJAAN BETON3 1 M2 MEMBUAT LANTAI KERJA BETON TUMBUK, 1 Pc : 3 Ps : 5 Kr TEBAL 5 Cm

10.000 Kg Semen portland @ Rp 812.00 Rp 8,120.00

0.026 M3 Pasir beton @ Rp 122,080.00 Rp 3,174.08

0.044 M3 Koral Beton @ Rp 149,408.00 Rp 6,573.95

1.150 Oh Pekerja @ Rp 22,400.00 Rp 25,760.00

0.020 Oh Tukang batu @ Rp 39,200.00 Rp 784.00

0.002 Oh Kepala tukang @ Rp 44,800.00 Rp 89.60

0.006 Oh Mandor @ Rp 33,600.00 Rp 201.60

Rp 44,703.23

4 1 M2 MEMBUAT LANTAI KERJA BETON TUMBUK, 1 Pc : 3 Ps : 5 Kr TEBAL 7 Cm

14.000 Kg Semen portland @ Rp 812.00 Rp 11,368.00

0.036 M3 Pasir beton @ Rp 122,080.00 Rp 4,443.71

0.062 M3 Koral Beton @ Rp 149,408.00 Rp 9,203.53

1.610 Oh Pekerja @ Rp 22,400.00 Rp 36,064.00

0.028 Oh Tukang batu @ Rp 39,200.00 Rp 1,097.60

0.003 Oh Kepala tukang @ Rp 44,800.00 Rp 125.44

0.008 Oh Mandor @ Rp 33,600.00 Rp 282.24

Rp 62,584.52

5 1 M3 MEMBUAT BETON 1 Pc : 2 Ps : 3 Kr

232.000 Kg Semen portland @ Rp 812.00 Rp 188,384.00

0.520 M3 Pasir beton @ Rp 122,080.00 Rp 63,481.60

0.780 M3 Koral Beton @ Rp 149,408.00 Rp 116,538.24

1.650 Oh Pekerja @ Rp 22,400.00 Rp 36,960.00

0.250 Oh Tukang batu @ Rp 39,200.00 Rp 9,800.00

0.025 Oh Kepala tukang @ Rp 44,800.00 Rp 1,120.00

0.080 Oh Mandor @ Rp 33,600.00 Rp 2,688.00

Rp 418,971.84

6 1 M2 PASANG BEKISTING UNTUK PONDASI

0.040 M3 Kayu Kls III (Papan) @ Rp 1,242,920.00 Rp 49,716.80

0.300 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 2,688.00

0.100 Lt Minyak bekisting @ Rp 12,208.00 Rp 1,220.80

Page 49: Kor Training Centre

0.300 Oh Pekerja @ Rp 22,400.00 Rp 6,720.00

0.260 Oh Tukang batu @ Rp 39,200.00 Rp 10,192.00

0.026 Oh Kepala tukang @ Rp 44,800.00 Rp 1,164.80

0.005 Oh Mandor @ Rp 33,600.00 Rp 168.00

Rp 71,870.40

7 1 M2 PASANG BEKISTING UNTUK SLOOF

0.045 M3 Kayu Kls III (Papan) @ Rp 1,242,920.00 Rp 55,931.40

0.300 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 2,688.00

0.100 Lt Minyak bekisting @ Rp 12,208.00 Rp 1,220.80

0.300 Oh Pekerja @ Rp 22,400.00 Rp 6,720.00

0.260 Oh Tukang batu @ Rp 39,200.00 Rp 10,192.00

0.026 Oh Kepala tukang @ Rp 44,800.00 Rp 1,164.80

0.005 Oh Mandor @ Rp 33,600.00 Rp 168.00

Rp 78,085.00

8 1 M2 PASANG BEKISTING UNTUK KOLOM

0.040 M3 Kayu Kls II (Balok) @ Rp 1,610,000.00 Rp 64,400.00

0.400 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 3,584.00

0.200 Lt Minyak bekisting @ Rp 12,208.00 Rp 2,441.60

0.015 M3 Kayu Kls III (Balok) @ Rp 1,242,920.00 Rp 18,643.80

0.350 Lbr Multipleks 9 mm @ Rp 103,131.84 Rp 36,096.14

2.000 Btg Kayu Dolken @ Rp 8,960.00 Rp 17,920.00

0.300 Oh Pekerja @ Rp 22,400.00 Rp 6,720.00

0.330 Oh Tukang batu @ Rp 39,200.00 Rp 12,936.00

0.033 Oh Kepala tukang @ Rp 44,800.00 Rp 1,478.40

0.006 Oh Mandor @ Rp 33,600.00 Rp 201.60

Rp 164,421.54

9 1 M2 PASANG BEKISTING UNTUK BALOK

0.040 M3 Kayu Kls II (Balok) @ Rp 1,610,000.00 Rp 64,400.00

0.400 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 3,584.00

0.200 Lt Minyak bekisting @ Rp 12,208.00 Rp 2,441.60

0.015 M3 Kayu Kls III (Balok) @ Rp 1,242,920.00 Rp 18,643.80

0.350 Lbr Multipleks 9 mm @ Rp 103,131.84 Rp 36,096.14

2.000 Btg Kayu Dolken 8,960.00 Rp 17,920.00

0.320 Oh Pekerja @ Rp 22,400.00 Rp 7,168.00

0.330 Oh Tukang batu @ Rp 39,200.00 Rp 12,936.00

0.033 Oh Kepala tukang @ Rp 44,800.00 Rp 1,478.40

0.006 Oh Mandor @ Rp 33,600.00 Rp 201.60

Rp 164,869.54

10 1 M' PASANG BEKISTING UNTUK RING BALOK

0.003 M3 Kayu Kls III (Papan) @ Rp 1,242,920.00 Rp 3,728.76

0.020 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 179.20

0.050 Lt Minyak bekisting @ Rp 12,208.00 Rp 610.40

0.100 Oh Pekerja @ Rp 22,400.00 Rp 2,240.00

0.033 Oh Tukang kayu @ Rp 39,200.00 Rp 1,293.60

0.010 Oh Kepala tukang @ Rp 44,800.00 Rp 448.00

0.005 Oh Mandor @ Rp 33,600.00 Rp 168.00

Rp 8,667.96

11 1 M2 PASANG BEKISTING UNTUK DINDING

0.030 M3 Kayu Kls II (Balok) @ Rp 1,610,000.00 Rp 48,300.00

0.400 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 3,584.00

0.200 Lt Minyak bekisting @ Rp 12,208.00 Rp 2,441.60

0.020 M3 Kayu Kls III (Balok) @ Rp 1,242,920.00 Rp 24,858.40

Page 50: Kor Training Centre

0.350 Lbr Multipleks 9 mm @ Rp 103,131.84 Rp 36,096.14

3.000 Btg Kayu Dolken @ Rp 8,960.00 Rp 26,880.00

4.000 Bh Formtie/penjaga jarak bekisting/spac @ Rp 6,440.00 Rp 25,760.00

0.320 Oh Pekerja @ Rp 22,400.00 Rp 7,168.00

0.330 Oh Tukang batu @ Rp 39,200.00 Rp 12,936.00

0.033 Oh Kepala tukang @ Rp 44,800.00 Rp 1,478.40

0.006 Oh Mandor @ Rp 33,600.00 Rp 201.60

Rp 189,704.14

12 1 M2 PASANG BEKISTING UNTUK LANTAI

0.040 M3 Kayu Kls II (Balok) @ Rp 1,610,000.00 Rp 64,400.00

0.400 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 3,584.00

0.200 Lt Minyak bekisting @ Rp 12,208.00 Rp 2,441.60

0.015 M3 Kayu Kls III (Balok) @ Rp 1,242,920.00 Rp 18,643.80

0.350 Lbr Multipleks 9 mm @ Rp 103,131.84 Rp 36,096.14

6.000 Btg Kayu Dolken @ Rp 8,960.00 Rp 53,760.00

0.320 Oh Pekerja @ Rp 22,400.00 Rp 7,168.00

0.330 Oh Tukang batu @ Rp 39,200.00 Rp 12,936.00

0.033 Oh Kepala tukang @ Rp 44,800.00 Rp 1,478.40

0.006 Oh Mandor @ Rp 33,600.00 Rp 201.60

Rp 200,709.54

13 1 M2 PASANG BEKISTING UNTUK TANGGA

0.030 M3 Kayu Kls II (Balok) @ Rp 1,610,000.00 Rp 48,300.00

0.400 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 3,584.00

0.150 Lt Minyak bekisting @ Rp 12,208.00 Rp 1,831.20

0.015 M3 Kayu Kls III (Balok) @ Rp 1,242,920.00 Rp 18,643.80

0.350 Lbr Multipleks 9 mm @ Rp 103,131.84 Rp 36,096.14

2.000 Btg Kayu Dolken @ Rp 8,960.00 Rp 17,920.00

0.320 Oh Pekerja @ Rp 22,400.00 Rp 7,168.00

0.330 Oh Tukang batu @ Rp 39,200.00 Rp 12,936.00

0.033 Oh Kepala tukang @ Rp 44,800.00 Rp 1,478.40

0.006 Oh Mandor @ Rp 33,600.00 Rp 201.60

Rp 148,159.14

14 1 M3 MEMBUAT BETON DENGAN MUTU K 225

388.000 Kg Semen portland @ Rp 812.00 Rp 315,056.00

0.650 M3 Pasir beton @ Rp 122,080.00 Rp 79,352.00

0.650 M3 Kerikil beton @ Rp 149,408.00 Rp 97,115.20

6.000 Oh Pekerja @ Rp 22,400.00 Rp 134,400.00

1.000 Oh Tukang batu @ Rp 39,200.00 Rp 39,200.00

0.100 Oh Kepala tukang @ Rp 44,800.00 Rp 4,480.00

0.300 Oh Mandor @ Rp 33,600.00 Rp 10,080.00

Rp 679,683.20

15 1 M3 MEMBUAT BETON DENGAN MUTU K 175

340.000 Kg Semen portland @ Rp 812.00 Rp 276,080.00

0.540 M3 Pasir beton @ Rp 122,080.00 Rp 65,923.20

0.830 M3 Kerikil beton @ Rp 149,408.00 Rp 124,008.64

6.000 Oh Pekerja @ Rp 22,400.00 Rp 134,400.00

1.000 Oh Tukang batu @ Rp 39,200.00 Rp 39,200.00

0.100 Oh Kepala tukang @ Rp 44,800.00 Rp 4,480.00

Page 51: Kor Training Centre

0.300 Oh Mandor @ Rp 33,600.00 Rp 10,080.00

Rp 654,171.84

16 1 Kg PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR

1.050 Kg Besi Beton ( Polos / Ulir ) @ Rp 7,728.00 Rp 8,114.40

0.015 Kg Kawat Beton @ Rp 10,864.00 Rp 162.96

0.007 Oh Pekerja @ Rp 22,400.00 Rp 156.80

0.0070 Oh Tukang Besi @ Rp 33,600.00 Rp 235.20

0.00007 Oh Kepala tukang @ Rp 44,800.00 Rp 3.14

0.00030 Oh Mandor @ Rp 33,600.00 Rp 10.08

Rp 8,682.58

1 Pek. Pondasi Poer

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 172 Kg ) Rp 1,493,403.07

Bekisting ( 2,4 m2 x Analisa )------( 2 x Pakai ) 50% Rp 240,851.45

Rp 2,413,937.72

2 Pek. Stek Poer 40/40

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 144 Kg ) Rp 1,250,290.94

Bekisting ( 10 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 822,107.72

Rp 2,752,081.86

3 Pek. Stek Poer 30/50

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 125 Kg ) Rp 1,085,322.00

Bekisting ( 10,67 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 877,188.94

Rp 2,642,194.14

Pek. Stek Poer 30/30

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 175 Kg ) Rp 1,519,450.80

Bekisting ( 13.333 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 1,095,869.59

Rp 3,295,003.59

Pek. Stek Poer 25/25

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 165 Kg ) Rp 1,432,625.04

Bekisting ( 16 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 1,315,372.35

Rp 3,427,680.59

4 Pek. Kolom Beton 40/40

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 144 Kg ) Rp 1,250,290.94

Bekisting ( 10 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 822,107.72

Rp 2,752,081.86

5 Pek. Kolom Beton 30/50

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 125 Kg ) Rp 1,085,322.00

Bekisting ( 10,67 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 877,188.94

Rp 2,642,194.14

Pek. Kolom Beton 30/30

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 175 Kg ) Rp 1,519,450.80

Bekisting ( 13.333 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 1,096,116.22

Rp 3,295,250.22

Pek. Kolom Beton 25/25

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 165 Kg ) Rp 1,432,625.04

Page 52: Kor Training Centre

Bekisting ( 16 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 1,315,372.35

Rp 3,427,680.59

Pek. Kolom Beton 20/20

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 160 Kg ) Rp 1,389,212.16

Bekisting ( 20 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 1,644,215.44

Rp 3,713,110.80

6 Pek. Kolom Praktis

Beton K. 175 Rp 654,171.84

Besi Beton ( 1 kg x 204 Kg ) Rp 1,771,245.50

Bekisting ( 13,04 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 1,072,028.47

Rp 3,497,445.81

7 Pek. Sloef Beton 25/40

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 142.5 Kg ) Rp 1,237,267.08

Bekisting ( 8 m2 x Analisa )-------( 2 x Pakai ) 50 % Rp 312,340.00

Rp 2,229,290.28

8 Pek. Sloef Beton 20/25

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 135 Kg ) Rp 1,172,147.76

Bekisting ( 10 m2 x Analisa )-------( 2 x Pakai ) 50 % Rp 390,425.00

Rp 2,242,255.96

9 Pek. Sloef Beton 15/20

Beton K. 175 Rp 654,171.84

Besi Beton ( 1 kg x 163 Kg ) Rp 1,415,259.89

Bekisting ( 13,33 m2 x Analisa )-------( 2 x Pakai ) 50 % Rp 520,436.53

Rp 2,589,868.25

10 Pek. Balok Latei 15/20

Beton K. 175 Rp 654,171.84

Besi Beton ( 1 kg x 163 Kg ) Rp 1,415,259.89

Bekisting ( 33,33 m' x Analisa )-------( 2 x Pakai ) 50 % Rp 144,451.55

Rp 2,213,883.28

11 Pek. Balok Latei 10/20

Beton K. 175 Rp 654,171.84

Besi Beton ( 1 kg x 234 Kg ) Rp 2,031,722.78

Bekisting ( 50 m' x Analisa )-------( 2 x Pakai ) 50 % Rp 216,699.00

Rp 2,902,593.62

12 Pek. Tangga Beton

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 115 Kg ) Rp 998,496.24

Bekisting ( 14,2 m2 x Analisa ) Rp 2,103,859.84

Rp 3,782,039.28

13 Pek. Balok 25/50

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 148 Kg ) Rp 1,285,021.25

Bekisting ( 8,08 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 666,072.96

Rp 2,630,777.41

15 Pek. Balok 20/30

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 138 Kg ) Rp 1,198,195.49

Bekisting ( 9.33 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 769,116.42

Page 53: Kor Training Centre

Rp 2,646,995.11

19 Pek. Balok 25/40

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 142.5 Kg ) Rp 1,237,267.08

Bekisting ( 8.10 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 665,907.25

Rp 2,582,857.53

Pek. Balok 15/30

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 140 Kg ) Rp 1,215,560.64

Bekisting ( 15.777 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 1,297,039.35

Rp 3,192,283.19

Pek. Balok 15/20

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 175 Kg ) Rp 1,519,450.80

Bekisting ( 10,33 m2 x Analisa )-------( 2 x Pakai ) 50% Rp 849,237.27

Rp 3,048,371.27

21 Pek. Ringbalk 15/15

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 220 Kg ) Rp 1,910,166.72

Bekisting ( 44.44 m' x Analisa )-------( 2 x Pakai ) 50% Rp 192,619.41

Rp 2,782,469.33

22 Pek. Ringbalk 20/25

Beton K. 225 Rp 679,683.20

Besi Beton ( 1 kg x 135 Kg ) Rp 1,172,147.76

Bekisting ( 20 m' x Analisa )-------( 2 x Pakai ) 50 % Rp 86,679.60

Rp 1,938,510.56

23 Pek. Ring Balok 15/20

Beton K. 175 Rp 654,171.84

Besi Beton ( 1 kg x 163 Kg ) Rp 1,415,259.89

Bekisting ( 33,33 m' x Analisa )--------( 2 x Pakai ) 50% Rp 144,451.55

Rp 2,213,883.28

24 Pek. Plat Lantai

Beton K. 175 Rp 654,171.84

Besi Beton ( 1 kg x 100 Kg ) Rp 868,257.60

Bekisting ( 8,33 m2 x Analisa ) Rp 1,671,910.50

Rp 3,194,339.94

25 Pek. Plat Leufel

Beton K. 175 Rp 654,171.84

Besi Beton ( 1 kg x 110 Kg ) Rp 955,083.36

Bekisting ( 14,2 m2 x Analisa ) Rp 2,850,075.52

Rp 4,459,330.72

PEKERJAAN PENUTUP ATAP

1 1 M' PASANG NOK GENTENG

4.000 bh Bubungan Genteng Beton Glazur @ Rp 3,080.00 Rp 12,320.00

0.030 Kg Paku biasa 1/2" - 1" @ Rp 8,960.00 Rp 268.80

0.250 Oh Pekerja @ Rp 22,400.00 Rp 5,600.00

0.150 Oh Tukang kayu @ Rp 39,200.00 Rp 5,880.00

0.015 Oh Kepala tukang @ Rp 44,800.00 Rp 672.00

0.013 Oh Mandor @ Rp 33,600.00 Rp 436.80

Page 54: Kor Training Centre

Rp 25,177.60

2 1 M2 PASANG ATAP GENTENG

9.000 Bh Genteng Beton Glazur @ Rp 2,968.00 Rp 26,712.00

1.100 M2 Karet Pelapis Genteng @ Rp 8,400.00 Rp 9,240.00

0.200 Kg Paku biasa 2" - 5" @ Rp 8,960.00 Rp 1,792.00

0.200 Oh Pekerja @ Rp 22,400.00 Rp 4,480.00

0.100 Oh Tukang kayu @ Rp 39,200.00 Rp 3,920.00

0.010 Oh Kepala tukang @ Rp 44,800.00 Rp 448.00

0.001 Oh Mandor @ Rp 33,600.00 Rp 33.60

1 M2 Menutup Atap Dengan Genteng Beton Rp 46,625.60

1 M2 Menutup Atap Dengan Genteng Beton (Tidak Pakai Karet Pelapis) Rp 37,385.60

PEKERJAAN BESI DAN ALMINIUM

1 1 M' PASANG TALANG

0.300 Lbr Seng Plat 3' x 6' bjls 28 @ Rp 40,000.00 Rp 12,000.00

0.100 Kg Paku biasa 1/2" - 1" @ Rp 8,960.00 Rp 896.00

0.019 M3 Kayu Kls II Papan @ Rp 1,932,000.00 Rp 36,708.00

0.500 Kg Besi Strip @ Rp 2,800.00 Rp 1,400.00

0.150 Oh Pekerja @ Rp 22,400.00 Rp 3,360.00

0.250 Oh Tukang kayu @ Rp 39,200.00 Rp 9,800.00

0.025 Oh Kepala tukang @ Rp 44,800.00 Rp 1,120.00

0.00125 Oh Mandor @ Rp 33,600.00 Rp 42.00

Rp 65,326.00

PEKERJAAN PENGECATAN

1 1 M2 PENGECATAN TEMBOK BARU ( 1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup

A 0.260 Kg Cat Penutup 2 x ( Metrolite / Catilac ) @ Rp 55,328.00 Rp 14,385.28

B 0.178 Kg Cat Penutup 2 x ( Mowilex ) @ Rp 105,280.00 Rp 18,739.84

0.100 Kg Plamir @ Rp 25,760.00 Rp 2,576.00

0.100 Kg Cat Dasar @ Rp 32,200.00 Rp 3,220.00

0.020 Oh Pekerja @ Rp 22,400.00 Rp 448.00

0.063 Oh Tukang Cat @ Rp 33,600.00 Rp 2,116.80

0.006 Oh Kepala tukang @ Rp 44,800.00 Rp 282.24

0.003 Oh Mandor @ Rp 33,600.00 Rp 84.00

JUML. A Rp 23,112.32

JUML. B Rp 27,466.88

2 1 M2 MENGECAT ANTI BOCOR LANTAI 3 X

0.500 Ltr Cat Lapisan Anti Bocor @ Rp 86,940.00 Rp 43,470.00

0.200 Ltr Cat Arcilic Anti Lumut @ Rp 97,216.00 Rp 19,443.20

Upah mengacat Rp 2,931.04

Anti Bocor Rp 46,401.04

Arcilic Rp 22,374.24

Untuk 1 M2 Mengecat Anti Bocor 3 Kali 3 x 46,401.04 Rp 139,203.12

Untuk 1 M2 Mengecat Arcilic 2 Kali 3 x 22,374.24 Rp 67,122.72

3 1 M2 PELABURAN BIDANG KAYU DGN CAT RESIDU DAN TER

Page 55: Kor Training Centre

0.350 Ltr Residu atau Ter @ Rp 5,796.00 Rp 2,028.60

0.100 Oh Pekerja @ Rp 22,400.00 Rp 2,240.00

0.006 Oh Mandor @ Rp 33,600.00 Rp 201.60

Rp 4,470.20

4 1 M2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup

0.200 Kg Cat Meni @ Rp 29,624.00 5,924.80

0.150 Kg Plamir @ Rp 25,760.00 Rp 3,864.00

0.170 Kg Cat Dasar @ Rp 32,200.00 Rp 5,474.00

0.260 Kg Cat Penutup 2 x ( Glotex ) @ Rp 30,912.00 Rp 8,037.12

0.070 Oh Pekerja @ Rp 22,400.00 Rp 1,568.00

0.009 Oh Tukang Cat @ Rp 33,600.00 Rp 302.40

0.006 Oh Kepala tukang @ Rp 44,800.00 Rp 268.80

0.0025 Oh Mandor @ Rp 33,600.00 Rp 84.00

Rp 19,598.32 PEKERJAAN LANTAI DAN DINDING

1 1 M2 PASANG LANTAI KERAMIK

A 6.250 Bh Lantai Keramik 40x40 @ Rp 7,168.00 Rp 44,800.00

B 11.110 Bh Lantai Keramik 30x30 @ Rp 3,360.00 Rp 37,329.60

C 25.000 Bh Lantai Keramik 20x20 ( Kasar ) @ Rp 1,456.00 Rp 36,400.00

D 25.000 Bh Lantai Keramik 20x20 ( Warna ) @ Rp 1,500.00 Rp 37,500.00

11.300 Kg Semen Portland @ Rp 812.00 Rp 9,175.60

0.042 M3 Pasir Pasang @ Rp 83,720.00 Rp 3,516.24

1.500 Kg Semen Warna @ Rp 6,440.00 Rp 9,660.00

0.062 Oh Pekerja @ Rp 22,400.00 Rp 1,388.80

0.350 Oh Tukang Batu @ Rp 39,200.00 Rp 13,720.00

0.035 Oh Kepala tukang @ Rp 44,800.00 Rp 1,568.00

0.030 Oh Mandor @ Rp 33,600.00 Rp 1,008.00

Jum : A Rp 84,836.64

Jum : B Rp 77,366.24

Jum : C Rp 76,436.64

Jum : D Rp 77,536.64

2 1 M2 PASANG DINDING KERAMIK 20 X 25

20.000 Bh Keramik 20 X 25 cm @ Rp 1,456.00 Rp 29,120.00

9.300 Kg Semen Porland @ Rp 812.00 Rp 7,551.60

0.018 M3 Pasir Pasang @ Rp 83,720.00 Rp 1,506.96

1.500 Kg Semen Warna @ Rp 6,440.00 9,660.00

0.600 Oh Pekerja @ Rp 22,400.00 Rp 13,440.00

0.450 Oh Tukang Batu @ Rp 39,200.00 Rp 17,640.00

0.045 Oh Kepala tukang @ Rp 44,800.00 Rp 2,016.00

0.030 Oh Mandor @ Rp 33,600.00 Rp 1,008.00

Rp 81,942.56

3 1 M' PASANG PLINT KERAIMIK 10 X 40

1.667 Bh Plint Keramik 10 X 40 cm @ Rp 2,800.00 Rp 4,666.48

1.650 Kg Semen Portland @ Rp 812.00 Rp 1,339.80

0.0032 M3 Pasir Pasang @ Rp 83,720.00 Rp 267.90

0.100 Kg Semen Warna @ Rp 6,440.00 Rp 644.00

0.090 Oh Pekerja @ Rp 22,400.00 Rp 2,016.00

0.090 Oh Tukang Batu @ Rp 39,200.00 Rp 3,528.00

0.009 Oh Kepala tukang @ Rp 44,800.00 Rp 403.20

0.0045 Oh Mandor @ Rp 33,600.00 Rp 151.20

Rp 13,016.58

Page 56: Kor Training Centre

PEKERJAAN KUNCI DAN KACA

1 1 M2 PASANG KACA TEBAL, 5 MM

A 1.1000 M2 Kaca Rybend t=5mm @ Rp 96,544.00 Rp 106,198.40

B 1.1000 M2 Kaca Buram t=5mm @ Rp 109,424.00 Rp 120,366.40

C 1.1000 M2 Kaca Bening t=5mm @ Rp 83,664.00 Rp 92,030.40

D 1.1000 M2 Kaca Cermin t=5mm @ Rp 85,000.00 Rp 93,500.00

0.0150 Oh Pekerja @ Rp 22,400.00 Rp 336.00

0.1500 Oh Tukang Kayu @ Rp 39,200.00 Rp 5,880.00

0.0150 Oh Kepala tukang @ Rp 44,800.00 Rp 672.00

0.00075 Oh Mandor @ Rp 33,600.00 Rp 25.20

Jum : A Rp 113,111.60

Jum : B Rp 127,279.60

Jum : C Rp 98,943.60

Jum : D Rp 100,413.20

2 1 BH PASANG REL PINTU DORONG

1.0000 Bh Rel Pintu Dorong @ Rp 193,200.00 Rp 193,200.00

0.0600 Oh Pekerja @ Rp 22,400.00 Rp 1,344.00

0.6000 Oh Tukang Kayu @ Rp 39,200.00 Rp 23,520.00

0.0600 Oh Kepala tukang @ Rp 44,800.00 Rp 2,688.00

0.00300 Oh Mandor @ Rp 33,600.00 Rp 100.80

Rp 220,852.80

3 1 BH PASANG KUNCI PINTU DORONG

1.0000 Bh Kunci Pintu Dorong @ Rp 96,600.00 Rp 96,600.00

0.0250 Oh Pekerja @ Rp 22,400.00 Rp 560.00

0.2500 Oh Tukang Kayu @ Rp 39,200.00 Rp 9,800.00

0.0250 Oh Kepala tukang @ Rp 44,800.00 Rp 1,120.00

0.00125 Oh Mandor @ Rp 33,600.00 Rp 42.00

Rp 108,122.00

4 1 BH PASANG KUNCI PINTU

A 1.000 Bh Kunci Pintu 2x Putar (Ex Yale) @ Rp 90,160.00 Rp 90,160.00

B 1.000 Bh Kunci Bundar Kamar Mandi @ Rp 128,800.00 Rp 128,800.00

0.0050 Oh Pekerja @ Rp 22,400.00 Rp 112.00

0.5000 Oh Tukang Kayu @ Rp 39,200.00 Rp 19,600.00

0.0050 Oh Kepala tukang @ Rp 44,800.00 Rp 224.00

0.00250 Oh Mandor @ Rp 33,600.00 Rp 84.00

Jum : A Rp 110,180.00

Jum : B Rp 148,820.00

5 1 BH PASANG KAIT ANGIN

1.000 Bh Kait Angin @ Rp 4,480.00 Rp 4,480.00

0.0150 Oh Pekerja @ Rp 22,400.00 Rp 336.00

0.1500 Oh Tukang Kayu @ Rp 39,200.00 Rp 5,880.00

0.0150 Oh Kepala tukang @ Rp 44,800.00 Rp 672.00

0.00075 Oh Mandor @ Rp 33,600.00 Rp 25.20

Rp 11,393.20

6 1 BH PASANG ENGSEL JENDELA

1.000 Bh Engsel Jendela @ Rp 3,220.00 Rp 3,220.00

0.0100 Oh Pekerja @ Rp 22,400.00 Rp 224.00

0.1000 Oh Tukang Kayu @ Rp 39,200.00 Rp 3,920.00

0.0100 Oh Kepala tukang @ Rp 44,800.00 Rp 448.00

Page 57: Kor Training Centre

0.00050 Oh Mandor @ Rp 33,600.00 Rp 16.80

Rp 7,828.80

7 1 BH PASANG ENGSEL PINTU

1.000 Bh Engsel Pintu @ Rp 11,914.00 Rp 11,914.00

0.0150 Oh Pekerja @ Rp 22,400.00 Rp 336.00

0.1500 Oh Tukang Kayu @ Rp 39,200.00 Rp 5,880.00

0.0150 Oh Kepala tukang @ Rp 44,800.00 Rp 672.00

0.00075 Oh Mandor @ Rp 33,600.00 Rp 25.20

Rp 18,827.20

8 1 BH PASANG EXPANYOLET TEMPEL/DOOR CLOSER

1.000 Bh Expanyolet Tempel/Door Closer @ Rp 59,248.00 Rp 59,248.00

0.0500 Oh Pekerja @ Rp 22,400.00 Rp 1,120.00

0.5000 Oh Tukang Kayu @ Rp 39,200.00 Rp 19,600.00

0.0500 Oh Kepala tukang @ Rp 44,800.00 Rp 2,240.00

0.00250 Oh Mandor @ Rp 33,600.00 Rp 84.00

Rp 82,292.00

9 1 BH PASANG GRENDEL

A 1.000 Bh Gerendel Jendela @ Rp 20,608.00 Rp 20,608.00

B 1.000 Psg Gerendel Tanam @ Rp 25,760.00 Rp 25,760.00

0.0100 Oh Pekerja @ Rp 22,400.00 Rp 224.00

0.1000 Oh Tukang Kayu @ Rp 39,200.00 Rp 3,920.00

0.0100 Oh Kepala tukang @ Rp 44,800.00 Rp 448.00

0.00050 Oh Mandor @ Rp 33,600.00 Rp 16.80

Jum : A Rp 25,216.80

Jum : B Rp 30,368.80 PEKERJAAN PELAFOND

1 1 M2 PEKERJAAN PLAFOND

A 1.100 M2 Plafond Tripleks 6 mm @ Rp 20,975.89 Rp 23,073.48

B 1.1000 Lbr GRC t=4 cm @ Rp 16,648.00 Rp 18,312.80

C 1.1000 M2 Gypsum 9 mm @ Rp 18,032.00 Rp 19,835.20

0.0100 Kg Paku @ Rp 8,960.00 Rp 89.60

0.0300 Oh Pekerja @ Rp 22,400.00 Rp 672.00

0.0700 Oh Tukang Kayu @ Rp 39,200.00 Rp 2,744.00

0.0070 Oh Kepala tukang @ Rp 44,800.00 Rp 313.60

0.00150 Oh Mandor @ Rp 33,600.00 Rp 50.40

Jum : A Rp 26,943.08

Jum : B Rp 22,182.40

Jum : C Rp 23,704.80

3 1 M' PEKERJAAN LIST PLAFOND KAYU PROFIL

A 1.100 M' List Plafond (kayu profil 3x4) @ Rp 4,816.00 Rp 5,297.60

B 1.100 M' Profil Gypsum Type CE (Sedang) @ Rp 25,760.00 Rp 28,336.00

C 1.100 M' Profil Gypsum Type SL (Kecil) @ Rp 22,540.00 Rp 24,794.00

0.0100 Kg Paku @ Rp 8,960.00 Rp 89.60

0.0500 Oh Pekerja @ Rp 22,400.00 Rp 1,120.00

0.0500 Oh Tukang Kayu @ Rp 39,200.00 Rp 1,960.00

0.0050 Oh Kepala tukang @ Rp 44,800.00 Rp 224.00

0.00300 Oh Mandor @ Rp 33,600.00 Rp 100.80

JUML. A Rp 8,792.00

JUML. B Rp 31,830.40

JUML. C Rp 28,288.40 PEKERJAAN SANITASI

Page 58: Kor Training Centre

1 1 BH MEMASANG KLOSET DUDUK

1.000 Bh Kloset Duduk Ex. TOTO / KIA @ Rp 1,094,800.00 Rp 1,094,800.00

0.0600 Perlengkapan @ Rp 1,094,800.00 Rp 65,688.00

3.3000 Oh Pekerja @ Rp 22,400.00 Rp 73,920.00

1.1000 Oh Tukang Batu @ Rp 39,200.00 Rp 43,120.00

0.0010 Oh Kepala tukang @ Rp 44,800.00 Rp 44.80

0.16000 Oh Mandor @ Rp 33,600.00 Rp 5,376.00

Rp 1,282,948.80

2 1 BH MEMASANG KLOSET JONGKOK

1.000 Bh Kloset Jongkok @ Rp 150,000.00 Rp 150,000.00

7.0000 Bh Bata Merah @ Rp 380.80 Rp 2,665.60

6.0000 Kg Semen Portland @ Rp 812.00 Rp 4,872.00

0.0100 M3 Pasir Pasang @ Rp 83,720.00 Rp 837.20

1.0000 Oh Pekerja @ Rp 22,400.00 Rp 22,400.00

1.5000 Oh Tukang Batu @ Rp 39,200.00 Rp 58,800.00

0.3000 Oh Kepala tukang @ Rp 44,800.00 Rp 13,440.00

0.11000 Oh Mandor @ Rp 33,600.00 Rp 3,696.00

Rp 256,710.80

3 1 BH MEMASANG URINOIR

1.000 Bh Urinoir @ Rp 966,000.00 Rp 966,000.00

0.3000 Perlengkapan @ Rp 966,000.00 Rp 289,800.00

6.0000 Kg Semen Portland @ Rp 812.00 Rp 4,872.00

0.0100 M3 Pasir Pasang @ Rp 83,720.00 Rp 837.20

1.0000 Oh Pekerja @ Rp 22,400.00 Rp 22,400.00

1.0000 Oh Tukang Batu @ Rp 39,200.00 Rp 39,200.00

0.1000 Oh Kepala tukang @ Rp 44,800.00 Rp 4,480.00

0.10000 Oh Mandor @ Rp 33,600.00 Rp 3,360.00

Rp 1,330,949.20

4 1 BH MEMASANG WASTAFEL

1.000 Bh Wastafel @ Rp 483,000.00 Rp 483,000.00

0.1200 Perlengkapan @ Rp 483,000.00 Rp 57,960.00

6.0000 Kg Semen Porland @ Rp 812.00 Rp 4,872.00

0.0100 M3 Pasir Pasang @ Rp 83,720.00 Rp 837.20

1.2000 Oh Pekerja @ Rp 22,400.00 Rp 26,880.00

1.4500 Oh Tukang Batu @ Rp 39,200.00 Rp 56,840.00

0.1500 Oh Kepala tukang @ Rp 44,800.00 Rp 6,720.00

0.10000 Oh Mandor @ Rp 33,600.00 Rp 3,360.00

Rp 640,469.20

5 1 BH MEMASANG BAK KONTROL PAS. BATU ( 45X45 ) T = 50 cm

0.250 M3 Batu Bata @ Rp 380.80 Rp 95.20

77.0000 Kg Semen Portland @ Rp 812.00 Rp 62,524.00

0.1300 M3 Pasir Pasang @ Rp 83,720.00 Rp 10,883.60

0.0200 M3 Batu Krikil @ Rp 149,408.00 Rp 2,988.16

2.6000 Kg Besi Beton @ Rp 7,728.00 Rp 20,092.80

0.0900 M3 Pasir Beton @ Rp 122,080.00 Rp 10,987.20

1.4200 Oh Pekerja @ Rp 22,400.00 Rp 31,808.00

0.4730 Oh Tukang Batu @ Rp 39,200.00 Rp 18,541.60

0.4700 Oh Kepala tukang @ Rp 44,800.00 Rp 21,056.00

0.07100 Oh Mandor @ Rp 33,600.00 Rp 2,385.60

Rp 181,362.16

6 1 BH MEMASANG PIPA PVC AIR BERSIH

A 1.200 M' Pipa PVC Dia 3/4" @ Rp 5,040.00 Rp 6,048.00

0.3500 Perlengkapan @ Rp 5,040.00 Rp 1,764.00

Page 59: Kor Training Centre

B 1.200 M' Pipa PVC Dia 1" @ Rp 11,760.00 Rp 14,112.00

0.3500 Perlengkapan @ Rp 11,760.00 Rp 4,116.00

0.0540 Oh Pekerja @ Rp 22,400.00 Rp 1,209.60

0.0900 Oh Tukang Batu @ Rp 39,200.00 Rp 3,528.00

0.0090 Oh Kepala tukang @ Rp 44,800.00 Rp 403.20

0.02700 Oh Mandor @ Rp 33,600.00 Rp 907.20

Jum : A Rp 13,860.00

Jum : B Rp 24,276.00

7 1 BH MEMASANG PIPA PVC AIR KOTOR

A 1.200 M' Pipa Pvc Dia. 2 " ( D ) @ Rp 16,240.00 Rp 19,488.00

0.3500 Perlengkapan @ Rp 16,240.00 Rp 5,684.00

B 1.200 M' Pipa Pvc Dia. 3 " ( D ) @ Rp 26,992.00 Rp 32,390.40

0.3500 Perlengkapan @ Rp 26,992.00 Rp 9,447.20

C 1.200 M' Pipa Pvc Dia. 4 " ( D ) @ Rp 32,816.00 Rp 39,379.20

0.3500 Perlengkapan @ Rp 32,816.00 Rp 11,485.60

0.0810 Oh Pekerja @ Rp 22,400.00 Rp 1,814.40

0.1350 Oh Tukang Batu @ Rp 39,200.00 Rp 5,292.00

0.0135 Oh Kepala tukang @ Rp 44,800.00 Rp 604.80

0.00410 Oh Mandor @ Rp 33,600.00 Rp 137.76

Jum : A Rp 33,020.96

Jum : B Rp 49,686.56

Jum : C Rp 58,713.76

8 1 BH MEMASANG WASHBASIN

1.000 Bh Washbasin @ Rp 200,000.00 Rp 200,000.00

1.0000 Set Water Drain + Asesories @ Rp 28,896.00 Rp 28,896.00

0.0360 Oh Pekerja @ Rp 22,400.00 Rp 806.40

0.0600 Oh Tukang Batu @ Rp 39,200.00 Rp 2,352.00

0.0060 Oh Kepala tukang @ Rp 44,800.00 Rp 268.80

0.00180 Oh Mandor @ Rp 33,600.00 Rp 60.48

Rp 232,383.68

9 1 BH MEMASANG KRAN AIR

A 1.000 Bh Kran Air @ Rp 32,200.00 Rp 32,200.00

0.0250 Set Seal Tape @ Rp 32,200.00 Rp 805.00

B 1.0000 Bh Stop Kran @ Rp 19,320.00 Rp 19,320.00

0.0250 Set Seal Tape @ Rp 19,320.00 Rp 483.00

0.0100 Oh Pekerja @ Rp 22,400.00 Rp 224.00

0.1000 Oh Tukang Batu @ Rp 39,200.00 Rp 3,920.00

0.0100 Oh Kepala tukang @ Rp 44,800.00 Rp 448.00

0.00500 Oh Mandor @ Rp 33,600.00 Rp 168.00

Jum : A Rp 37,765.00

Jum : B Rp 25,368.00

10 1 BH MEMASANG FLOOR DRAIN

1.000 Bh Floor Drain @ Rp 28,896.00 Rp 28,896.00

0.0100 Oh Pekerja @ Rp 22,400.00 Rp 224.00

0.1000 Oh Tukang Batu @ Rp 39,200.00 Rp 3,920.00

0.0100 Oh Kepala tukang @ Rp 44,800.00 Rp 448.00

Page 60: Kor Training Centre

0.00500 Oh Mandor @ Rp 33,600.00 Rp 168.00

Rp 33,656.00

11 1 BH MEMASANG TEMPAT SABUN

1.000 Bh Tempat Sabun @ Rp 39,760.00 Rp 39,760.00

0.0100 Oh Pekerja @ Rp 22,400.00 Rp 224.00

0.1000 Oh Tukang Batu @ Rp 39,200.00 Rp 3,920.00

0.0100 Oh Kepala tukang @ Rp 44,800.00 Rp 448.00

0.00500 Oh Mandor @ Rp 33,600.00 Rp 168.00

Rp 44,520.00

12 1 M' MENGERJAKAN SALURAN AIR HUJAN

0.070 M3 Beton Penutup Saluran @ Rp 418,971.84 Rp 29,328.03

0.263 M3 Galian Tanah @ Rp 10,304.00 Rp 2,704.80

0.090 M3 Pas. Trasram @ Rp 53,713.24 Rp 4,834.19

0.065 M3 Pasir Urug @ Rp 92,064.00 Rp 5,984.16

0.050 M3 Urugan Kembali @ Rp 4,939.20 Rp 246.96

0.520 M2 Plester Trasram @ Rp 19,709.48 Rp 10,248.93

1 M1 Mengerjakan saluran Air Hujan (Terbuka) Rp 24,019.04

1 M1 Mengerjakan saluran Air Hujan (Tertutup) Rp 53,347.07

13 1 UNIT SEPTICKTANK DAN PERESAPAN

10.000 M3 Galian Tanah @ Rp 10,304.00 Rp 103,040.00

1.663 M3 Pas. Trasram @ Rp 53,713.24 Rp 89,309.00

1.600 M3 Pasir Urug @ Rp 92,064.00 Rp 147,302.40

3.599 M3 Urugan Kembali @ Rp 4,939.20 Rp 17,774.95

46.216 M2 Plester Trasram @ Rp 19,709.48 Rp 910,893.33

1.350 M2 Ijuk @ Rp 68,664.00 Rp 92,696.40

0.406 M3 Plat Beton @ Rp 418,971.84 Rp 170,052.29

46.216 M2 Acian Semen Licin @ Rp 9,045.20 Rp 418,033.15

0.600 M1 Pipa Penghawaan @ Rp Ls Rp 50,000.00

0.870 M3 Krikil @ Rp 149,408.00 Rp 129,984.96

9.000 M' PVC Dia 4" (D) + By Pasang + Samb @ Rp 49,686.56 Rp 447,179.04

Rp 2,576,265.52

PEKERJAAN INSTALASI LISTRIK

1 MENGERJAKAN INSTALASI PENERANGAN

1.000 Ttk PEMASANGAN TITIK LAMPU

20.000 Meter Kabel NYM (2x2,5) mm @ Rp 8,120.00 Rp 162,400.00

40.000 Bh Klem Kabel No. 10 @ Rp 280.00 Rp 11,200.00

1.000 Btg Pipa Pvc 5/8" @ Rp 2,800.00 Rp 2,800.00

1.000 Bh Inbow Dos @ Rp 3,360.00 Rp 3,360.00

4.000 Bh Las Dop @ Rp 280.00 Rp 1,120.00

4.000 Roll Isolasi @ Rp 1,680.00 Rp 6,720.00

1.000 Bh T - Dos 5/8" @ Rp 224.00 Rp 224.00

0.100 Set Alat Bantu @ Rp 8,120.00 Rp 812.00

0.500 Tukang Instalatur @ Rp 39,200.00 Rp 19,600.00

0.500 Pekerja @ Rp 22,400.00 Rp 11,200.00

Rp 219,436.00

Page 61: Kor Training Centre

2 Ttk PEMASANGAN STOP KONTAK

12.000 Meter Kabel NYM (3x2,5) mm @ Rp 9,184.00 Rp 110,208.00

20.000 Bh Klem Kabel No. 12 @ Rp 280.00 Rp 5,600.00

2.000 Btg Pipa Pvc 5/8" @ Rp 2,800.00 Rp 5,600.00

1.000 Bh Inbow Dos @ Rp 3,360.00 Rp 3,360.00

6.000 Bh Las Dop @ Rp 280.00 Rp 1,680.00

1.000 Roll Isolasi @ Rp 1,680.00 Rp 1,680.00

1.000 Bh T - Dos 5/8" @ Rp 224.00 Rp 224.00

0.100 Set Alat Bantu @ Rp 9,184.00 Rp 918.40

0.500 Oh Tukang Instalatur @ Rp 39,200.00 Rp 19,600.00

0.500 Oh Pekerja @ Rp 22,400.00 Rp 11,200.00

Rp 160,070.40

1 TITIK MENGERJAKAN INSTALASI KABEL TELPON

20.000 Meter Kabel Telpon @ Rp 1,680.00 Rp 33,600.00

40.000 Bh Klem Kabel @ Rp 280.00 Rp 11,200.00

1.000 Btg Pipa Pvc 5/8" @ Rp 2,800.00 Rp 2,800.00

1.000 Bh Stop Kontak Telpon KW1 @ Rp 151,200.00 Rp 151,200.00

1.000 Bh Kotak Sambungan @ Rp 7,800.00 Rp 7,800.00

1.000 Ls Alat Bantu @ Rp 1,500.00 Rp 1,500.00

0.500 Tukang Instalatur @ Rp 39,200.00 Rp 19,600.00

0.500 Pembantu Tukang @ Rp 22,400.00 Rp 11,200.00

Rp 238,900.00

1 M2 PASANG LANTAI PARQUET JATI

1.050 M2 Parquet Jati @ Rp 610,400.00 Rp 640,920.00

0.600 Kg Lem Vinyl @ Rp 16,800.00 Rp 10,080.00

0.600 Oh Pekerja @ Rp 22,400.00 Rp 13,440.00

0.450 Oh Tukang Batu @ Rp 39,200.00 Rp 17,640.00

0.045 Oh Kepala tukang @ Rp 44,800.00 Rp 2,016.00

0.030 Oh Mandor @ Rp 33,600.00 Rp 1,008.00

Rp 685,104.00

1 M2 PASANGAN PAVING BLOCK (BETON CETAK)

50.000 Bh Paving Block Tebal 8 cm K225 @ Rp 1,624.00 Rp 81,200.00

0.100 M3 Pasir Urug @ Rp 70,840.00 Rp 7,084.00

0.200 M3 Pasir Sirtu @ Rp 108,640.00 Rp 21,728.00

0.311 Oh Tukang @ Rp 39,200.00 Rp 12,191.20

Page 62: Kor Training Centre

0.031 Oh Kepala tukang @ Rp 44,800.00 Rp 1,388.80

0.500 Oh Pekerja @ Rp 22,400.00 Rp 11,200.00

0.025 Oh Mandor @ Rp 33,600.00 Rp 840.00

Tebal 8 cm Rp 113,904.00

Tebal 8 cm + Sirtu Rp 135,632.00

ANALISA LANSEKAP

1 PEKERJAAN POHON TANAM PADI

0.500 Kg Pupuk Kandang @ Rp. 3,220.00 Rp. 1,610.00

0.750 Kg Pupuk Anorganik @ Rp. 5,796.00 Rp. 4,347.00

0.250 Pekerja @ Rp. 22,400.00 Rp. 5,600.00

0.125 Tukang Taman @ Rp. 39,200.00 Rp. 4,900.00

0.025 Mandor @ Rp. 33,600.00 Rp. 840.00

0.080 Sekop @ Rp. 19,320.00 Rp. 1,545.60

0.080 Pacul @ Rp. 20,608.00 Rp. 1,648.64

Rp. 20,491.24 2 PEKERJAAN 1 PERDU SEMAK TANAM PADI

0.004 Kg Pupuk Kandang @ Rp. 3,220.00 Rp. 13.42

0.083 Kg Pupuk Anorganik @ Rp. 5,796.00 Rp. 483.00

0.008 Pekerja @ Rp. 22,400.00 Rp. 186.67

0.004 Tukang Taman @ Rp. 39,200.00 Rp. 163.33

0.001 Mandor @ Rp. 33,600.00 Rp. 28.00

0.013 Sekop @ Rp. 19,320.00 Rp. 257.60

0.013 Pacul @ Rp. 20,608.00 Rp. 274.77

Rp. 1,406.79 3 PEKERJAAN 1 M2 PENANAMAN RUMPUT

0.019 Kg Pupuk Kandang @ Rp. 3,220.00 Rp. 60.38

0.375 Kg Pupuk Anorganik @ Rp. 5,796.00 Rp. 2,173.50

0.038 Pekerja @ Rp. 22,400.00 Rp. 840.00

0.019 Tukang Taman @ Rp. 39,200.00 Rp. 735.00

0.004 Mandor @ Rp. 33,600.00 Rp. 126.00

0.060 Sekop @ Rp. 19,320.00 Rp. 1,159.20

0.060 Pacul @ Rp. 20,608.00 Rp. 1,236.48

Rp. 6,330.56

4 L PALEM RAJA

1.000 Btg Pohon Palem Raja @ Rp. 160,000.00 Rp. 160,000.00

Pekerjaan Penanaman 1 Pohon @ Rp. 20,491.24 Rp. 20,491.24

Rp. 180,491.24 5 M PALEM Botol

1.000 Btg Pohon Palem Botol @ Rp. 250,000.00 Rp. 250,000.00

Pekerjaan Penanaman 1 Pohon @ Rp. 20,491.24 Rp. 20,491.24

Rp. 270,491.24

6 N AKASIA

1.000 Btg Pohon Akasia @ Rp. 140,000.00 Rp. 140,000.00

Pekerjaan Penanaman 1 Pohon @ Rp. 20,491.24 Rp. 20,491.24

Rp. 160,491.24 7 I ASOKA

1.000 Btg Azoka Bangkok @ Rp. 55,000.00 Rp. 55,000.00

Azoka Rambat @ Rp. 60,000.00 Rp. 60,000.00

Pekerjaan Penanaman 1 Bunga @ Rp. 20,491.24 Rp. 20,491.24

Aoka Bangkok Rp. 75,491.24

Aoka Rambat Rp. 80,491.24

Page 63: Kor Training Centre

8 J RUMPUT

1.000 M2 Rumput Veking @ Rp. 17,500.00 Rp. 17,500.00

1.000 M2 Rumput Gajah Pendek @ Rp. 15,000.00 Rp. 15,000.00

Pekerjaan Penanaman 1 M2 Rumput @ Rp. 6,330.56 Rp. 6,330.56

Veking Rp. 23,830.56

Gajah Rp. 21,330.56

Page 64: Kor Training Centre

PEMERINTAH KABUPATEN SIDENRENG RAPPANGDINAS PERMUKIMAN DAN PRASARANA DAERAH

JL. JEND. SUDIRMAN NO. 370 PANGKAJENE - SIDRAP

DAFTAR ANALISA HARGA SATUAN PEKERJAAN

TAHUN ANGGARAN 2005

Konsultan PerencanaCV. BAJIRUPA KONSULTAN

Architect Planner,Supervisi

Jl. Dg. Tata I Blok 2 No. 4A, Makassar. Tlp. 0411 - 8216234

Page 65: Kor Training Centre

PEMERINTAH DAERAH KABUPATEN SIDRAP

RENCANA KERJA DAN SYARAT - SYARAT(RKS)

Konsultan PerencanaCV. BAJIRUPA KONSULTAN

Architect Planner,Supervisi

Jl. Dg. Tata I Blok 2 No. 4A, Makassar. Tlp. 0411 - 8216234

Page 66: Kor Training Centre

PEMERINTAH KABUPATEN SIDENRENG RAPPANGDINAS PERMUKIMAN DAN PRASARANA DAERAH

JL. JEND. SUDIRMAN NO. 370 PANGKAJENE - SIDRAP

DOKUMEN PERENCANAAN :

RENCANA KERJA DAN SYARAT - SYARAT

PEKERJAAN :PEMBANGUNAN GEDUNG SIDRAP CENTER

TAHUN ANGGARAN 2005

Lokasi :Jl. PERINTIS KEMERDEKAAN (KM 7) TALLO - MAKASSAR

Konsultan PerencanaCV. BAJIRUPA KONSULTAN

Architect Planner,Supervisi

Jl. Dg. Tata I Blok 2 No. 4A, Makassar. Tlp. 0411 - 8216234

Page 67: Kor Training Centre

DAFTAR HARGA BAHAN & UPAH KERJA

No NAMA MATERIAL HARGA & SATUAN

1 Batu Gunung Rp 48,000.00 /m3

2 Batu Kali Rp 67,800.00 /m3

3 Batu Belah 10-15 cm Rp 70,800.00 /m3

4 Pasir Timbunan Rp 38,500.00 /m3

5 Tanah Timbunan Rp 25,000.00 /m3

6 Tanah Timbunan Pilihan Rp 32,000.00 /m3

7 Pasir Pasangan Rp 49,700.00 /m3

8 Pasir Beton Rp 49,700.00 /m3

9 Sirtu Tidak Diayak Rp 53,500.00 /m3

10 Batu Pecah 7-10 cm Rp 65,000.00 /m3

11 Batu Pecah 5-7 cm Rp 119,500.00 /m3

12 Batu Pecah 3-5 cm Rp 123,500.00 /m3

13 Batu Pecah 2-3 cm Rp 130,000.00 /m3

14 Batu Pecah 1-2 cm Rp 135,500.00 /m3

15 Batu Pecah 0,5-1cm Rp 138,000.00 /m3

16 Kerikil Galian Rp 76,750.00 /m3

17 Kerikil Sungai Rp 54,400.00 /m3

18 Kapur Rp 48,000.00 /m3

19 Kapur Bakar Rp 247,200.00 /Krg

20 Semen (Tonasa) Rp 26,250.00 /Zak

21 Semen (Bosowa) Rp 24,375.00 /Zak

22 Semen Putih Rp 68,250.00 /Zak

23 Bata Merah Rp 295.00 /Bh

24 Baja Tralis Rp 11,300.00 /Kg

25 Baja Konstruksi Rp 12,350.00 /Kg

26 Baja Tulangan Beton Rp 3,836.00 /Kg

27 Kawat Bronjong Rp 9,150.00 /Kg

28 Aspal Bitumen Rp 3,550.00 /Kg

29 Kayu Bakar Rp 105,360.00 /M3

30 Kawat Ikat Beton Rp 6,000.00 /Kg

31 Minyak Diesel / Solar Rp 700.00 /Ltr

32 Bensin Premium Rp 1,265.00 /Ltr

33 Minyak Pelumas Rp 14,900.00 /Ltr

34 Minyak Tanah Rp 600.00 /Ltr

35 Baut Baja Rp 9,450.00 /Kg

36 Paku Biasa 5-10 cm Rp 4,800.00 /Kg

37 Paku Biasa 4 cm Rp 6,000.00 /Kg

38 Paku Sirap 2-3 cm Rp 9,000.00 /Kg

39 Paku Beton 2;3 cm Putih Rp 12,250.00 /Kg

40 Paku Beton 4 cm Putih Rp 11,400.00 /Kg

41 Paku Beton 5;7 cm Putih Rp 8,400.00 /Kg

42 Paku Beton 10 cm Putih Rp 8,400.00 /Kg

43 Paku Panjang Rp 8,650.00 /Kg

44 Paku Asbes/Seng Rp 21,600.00 /Kg

No NAMA MATERIAL HARGA & SATUAN

45 Genteng Beton Warna Rp 3,250.00 /Bh

Page 68: Kor Training Centre

46 Bubungan Genteng Beton Rp 3,250.00 /Bh

47 Atap Prima Roof Rp 25,000.00 /Lbr

48 Nok Bulat Prima Roof Rp 20,000.00 /Bh

49 Karet Genteng 55 CM Rp 5,050.00 /M1

50 Karet Genteng 90 CM Rp 7,350.00 /M1

51 Karet Genteng 110 CM Rp 11,050.00 /M1

52 Seng Plat BWG 0,28 Rp 32,500.00 /M2

53 Seng Gelombang BJLS 0,20 Rp 2,325.00 /M2

54 Asbes Gelombang 11 Glb Rp 3,600.00 /KK

55 Nok Asbes Rp 15,000.00 /Bh

56 Genteng Asbes Rp 18,750.00 /Lbr

57 Genteng Nok Asbes Rp 18,750.00 /Lbr

58 Tegel Porselin 11x11 Rp 27,500.00 /M2

59 Tegel Keramik 30x30 Rp 22,000.00 /M2

60 Tegel Plint 15x20 cm Rp 30,000.00 /M2

61 Tegel Keramik 20x25 cm Rp 30,000.00 /M2

62 Tegel 30x30 (Ex. Platinium) Rp 40,000.00 /M2

63 Tegel Keramik 20x20 cm Rp 31,250.00 /M2

64 Tegel Ezensa 60x60 cm Rp 200,000.00 /M2

65 Tegel Ezensa 40x40 cm Rp 165,000.00 /M2

66 Tegel Ezensa 30x30 cm Rp 135,000.00 /M2

67 Tegel PC, 30x30 cm Lokal Rp 13,750.00 /M2

68 Tegel PC, 20x20 cm Lokal Rp 600.00 /Biji

69 Tegel Wafel, 20x20 cm Lokal Rp 960.00 /Biji

70 Tegel Wafel warna, 20x20 cm Lokal Rp 1,000.00 /Biji

71 Paving Block Rp 700.00 /Biji

72 Tripleks 3mm Rp 14,750.00 /M2

73 Tripleks 4mm Rp 30,000.00 /Lbr

74 Tripleks 6mm Rp 35,000.00 /M2

75 Tripleks 9mm Rp 24,500.00 /M2

76 Tripleks Tipis Palopo Rp 26,100.00 /Lbr

77 Tripleks Tebal Benteng Rp 29,000.00 /Lbr

78 Gypsum Board Rp 12,000.00 /M2

79 Eternit 1 x 1 M Rp 6,000.00 /M2

80 Hardpleks 1 x 1 M Rp 11,550.00 /M2

81 Kaca Buram 5 mm Rp 66,000.00 /m2

82 Kaca Rayband 3mm Rp 35,000.00 /m2

83 Kaca Rayband 5mm Rp 51,000.00 /m2

84 Kaca Bening 3 mm Rp 34,800.00 /m2

85 Kaca Bening 5 mm Rp 46,500.00 /m2

86 Kaca / Cermin Rp 57,000.00 /m2

87 Kawat Raam Rp 13,200.00 /m2

88 Kawat Duri Rp 6,000.00 /Kg

89 Kayu Kls I (Papan) Rp 2,160,000.00 /m3

90 Kayu Kls I (Balok) Rp 1,751,400.00 /m3

91 Kayu Kelas II (Balok) Rp 1,040,000.00 /m3

92 Kayu Kelas II (Papan) Rp 1,488,000.00 /m3

No NAMA MATERIAL HARGA & SATUAN

93 Kayu Kelas III (Balok) Rp 675,000.00 /m3

94 Kayu Kelas III (Papan) Rp 700,000.00 /m3

95 List Kayu Profil 2x3 cm Rp 3,000.00 /m1

Page 69: Kor Training Centre

96 List Kayu Profil Rp 3,000.00 /m1

97 Lambiserin Kls II 1x9x400 Rp 2,800.00 /m1

98 Teakwood Pintu Rp 60,000.00 /Lbr

99 Teakwood Lebar Rp 60,000.00 /Lbr

100 Cat Tembok Kls B (Ex Metrolite) Rp 6,400.00 /Kg

101 Cat Tembok Kls (Ex Vinotex) Rp 4,200.00 /Kg

102 Cat Tembok Kls (Ex Wintex) Rp 10,800.00 /Kg

103 Cat Kayu Gloteks Rp 22,200.00 /Kg

104 Cat Dasar Rp 6,000.00 /Kg

105 Cat Teak Oil/Politur Rp 18,750.00 /Kg

106 Politur Cap Kayu Rp 18,000.00 /Lt

107 Vernis Cap Jangkar Rp 9,000.00 /Lt

108 Dempul Kayu Cap Kucing Rp 12,000.00 /Kg

109 Dempul Kayu Cap Ayam Rp 7,200.00 /Kg

110 Amplas Gosok Rp 1,800.00 /Lbr

111 Minyak Cat Rp 3,600.00 /Lt

112 Minyak Cat Tenner A Rp 9,360.00 /Lt

113 Kloset Jongkok Rp 64,800.00 /Bh

114 Roster Beton Rp 4,200.00 /Bh

115 Loster Lokal Rp 3,000.00 /Biji

116 Kran Air Rp 60,000.00 /Bh

117 Washtafel EX.Lokal Warna Rp 300,000.00 /Bh

118 Kloset Duduk Rp 550,000.00 /Bh

119 Kloset Duduk KIA Warna (dud Blok) Rp 1,100,000.00 /Bh

120 Floor Drine Rp 25,000.00 /Bh

121 Washbasin Rp 220,000.00 /Bh

122 Urinoir Rp 495,000.00 /Bh

123 Tempat Sabun Rp 23,000.00 /Bh

124 Hand Shower Ex. San Ei Rp 175,000.00 /Bh

125 Pipa GIV 1/2" Medium B Rp 15,000.00 /M1

126 Pipa GIV 1 1/4" Medium B Rp 10,666.67 /M1

127 Pipa GIV 3/4" Medium B Rp 19,000.00 /M1

128 Pipa GIV 2" Medium B Rp 7,000.00 /M1

129 Pipa PVC 1/2" Maspion Rp 3,000.00 /M1

130 Pipa PVC 3/4" Maspion Rp 4,500.00 /M1

131 Pipa PVC 1" Maspion Rp 5,000.00 /M1

132 Pipa PVC 1 1/2" Maspion Rp 6,000.00 /M1

133 Pipa PVC 2" Maspion Rp 6,900.00 /M1

134 Pipa PVC 2 1/2" Maspion Rp 9,750.00 /M1

135 Pipa PVC 3" Maspion Rp 13,500.00 /M1

136 Pipa PVC 4" Maspion Rp 19,200.00 /M1

137 Pipa PVC 6" Maspion Rp 42,250.00 /M1

No NAMA MATERIAL HARGA & SATUAN

138 Pipa PVC 3" Maspion AW Rp 24,000.00 /M1

139 Pipa PVC 4" Maspion AW Rp 19,200.00 /M1

140 Samb. Pipa Bentuk T 1/2" Rp 900.00 /Bh

141 Samb. Pipa Bentuk - 1/2" Rp 600.00 /Bh

142 Samb. Pipa Bentuk L 1/2" Rp 900.00 /Bh

143 Samb. Pipa Bentuk T 1" Rp 1,800.00 /Bh

144 Samb. Pipa Bentuk - 1" Rp 1,200.00 /Bh

Page 70: Kor Training Centre

145 Samb. Pipa Bentuk L 1" Rp 1,800.00 /Bh

146 Kuas Tangan 1" Asli Rp 2,500.00 /Bh

147 Kuas Tangan 1 1/2" Asli Rp 3,600.00 /Bh

148 Kuas Tangan 2" Asli Rp 4,800.00 /Bh

149 Kuas Tangan 2 1/2" Asli Rp 6,000.00 /Bh

150 Kuas Tangan 3" Asli Rp 7,200.00 /Bh

151 Kuas Tangan 4" Asli Rp 9,600.00 /Bh

152 Kuas Tangan 5" Asli Rp 12,000.00 /Bh

153 Kuas Rol Imunteks Rp 12,000.00 /Bh

154 Kabel NYY 2x2,5 mm Rp 4,500.00 /M1

155 Kabel NYY GBY 2x1,5 mm Rp 4,000.00 /M1

156 Kabel NYY 4 mm Rp 7,000.00 /M1

157 Penangkal Petir Rp 1,750,000.00 /Set

158 Sekering Kas Rp 175,000.00 /Set

159 Isolasi Dari Plastik Rp 1,500.00 /Bh

160 Baut-Baut Rp 3,750.00 /Bh

161 Engsel Pintu Rp 5,760.00 /Psg

162 Engsel Jendela Rp 3,000.00 /Psg

163 Expanyolet Tempel / Dor Closer Rp 259,000.00 /Psg

164 Grendel Jendela / Pintu Rp 2,400.00 /Bh

165 Kunci Pintu 2 x Putar Rp 60,000.00 /Bh

166 Kunci Pintu Merek Top Rp 24,480.00 /Bh

167 Kunci Pintu Merek Napoli Rp 20,160.00 /Bh

168 Kunci Pintu Merek VNS Rp 54,000.00 /Bh

169 Kunci Pintu Merek Bruno Rp 21,600.00 /Bh

170 Hak Angin Rp 3,000.00 /Psg

171 Nako L. 60 Kaca 5 mm KPL Rp 10,200.00 /Daun

172 Nako L. 60 Kaca 3 mm KPL Rp 9,000.00 /Daun

173 Stang Nako Trali Besi 70 cm Rp 11,850.00 /Daun

174 Lampu SL-25 Waat Rp 62,500.00 /Bh

175 Lampu Sanex SL-14 Rp 32,000.00 /Bh

176 Lampu TL 2 x 20 Watt Rp 53,500.00 /Bh

177 Mercury 20 Watt Rp 125,000.00 /Bh

178 Lampu TL 1 x 20 Watt Rp 38,500.00 /Bh

179 Lampu TL 2 x 36 Watt Rp 125,000.00 /Bh

180 Lampu Downlight Besar Rp 132,000.00 /Bh

181 Lampu Pijar 40 Watt Rp 5,000.00 /Bh

182 Lampu Pijar 15 Watt Rp 3,000.00 /Bh

Page 71: Kor Training Centre

No NAMA MATERIAL HARGA & SATUAN

183 Stop Kontak Biasa Broco Rp 14,400.00 /Bh

184 Saklar Tunggal Ex. Broco Rp 14,400.00 /Bh

185 Saklar Seri Ex. Broco Rp 18,000.00 /Bh

186 Saklar Engkel Ex. Broco Rp 14,400.00 /Bh

187 Fitting Duduk Rp 2,400.00 /Bh

188 Fitting Gantung Rp 1,800.00 /Bh

189 Balon Neon 10 Watt Lengkap Rp 24,000.00 /Bh

190 Balon Neon 20 Watt Lengkap Rp 30,000.00 /Bh

191 Balon Pijar 40 Watt Rp 2,400.00 /Bh

192 Balon Pijar 60 Watt Rp 3,000.00 /Bh

193 Balon Pijar 100 Watt Rp 3,600.00 /Bh

No NAMA TENAGA KERJA UPAH & SATUAN

1 Tukang Rp 32,500.00 Org/Hr

2 Kepala tukang Rp 35,000.00 Org/Hr

3 Pekerja Rp 17,500.00 Org/Hr

4 Pekerja Semi Terampil Rp 20,000.00 Org/Hr

5 Pekerja Terampil Rp 22,500.00 Org/Hr

6 Mandor Rp 30,000.00 Org/Hr

7 Mekanik Terampil Rp 35,000.00 Org/Hr

8 Mekanik Semi Terampil Rp 30,000.00 Org/Hr

9 Operator Terampil Rp 35,000.00 Org/Hr

10 Operator Semi Terampil Rp 30,000.00 Org/Hr

11 Pembantu Operator Rp 25,000.00 Org/Hr

12 Sopir Terampil Rp 32,500.00 Org/Hr

13 Sopir Semi Terampil Rp 27,500.00 Org/Hr

14 Pembantu Sopir Rp 20,000.00 Org/Hr

Page 72: Kor Training Centre

57,500.00 56,500.00 59,000.00 50,000.00 25,000.00 32,000.00 57,000.00 57,000.00 53,500.00 65,000.00

119,500.00 123,500.00 130,000.00 135,500.00 138,000.00

63,957.00 1.60 62,177.00 37.60 40,000.00 0.05

206,000.00 Krg21,000.00 20.83 19,500.00 56,865.00 12.00

300.00 9,410.00

10,260.00 0.00 3,300.00 7,610.00 0.00 2,940.00

87,800.00 5,000.00

700.00 1,265.00

14,900.00 600.00

9,410.00 4,000.00 5,000.00 7,500.00

10,200.00 9,500.00 7,000.00 7,000.00 7,200.00

18,000.00

Page 73: Kor Training Centre

4,200.00 6,120.00 0.00 9,180.00 0.00

32,500.00 Lbr2,325.00 KK3,600.00 KK

15,000.00 15,600.00 15,600.00 27,500.00 M226,700.00 27,000.00 33,000.00

600.00 960.00

1,000.00 550.00

30,000.00 Lbr35,000.00 Lbr

26,100.00 29,000.00

5,500.00 9,600.00

13,200.00 M26,000.00

2,200,000.00 1,600,000.00 1,040,000.00 1,240,000.00

700,000.00 725,000.00

1,500.00

Page 74: Kor Training Centre

2,250.00

50,000.00

3,500.00 Kg9,000.00 Kg

18,500.00 Kg5,000.00

15,600.00 15,000.00 Ltr7,500.00 Ltr

10,000.00 Kg6,000.00 Kg1,500.00 Lbr3,000.00 Ltr7,800.00 Ltr

54,000.00 Bh3,500.00 Bh2,500.00

250,000.00 Bh

Page 75: Kor Training Centre

4,800.00 2,500.00 Bj

2,000.00 Bj30,000.00 Psg20,400.00 Psg16,800.00 Psg45,000.00 Psg18,000.00 Psg2,500.00 Bh8,500.00 Daun7,500.00 Daun9,850.00

Page 76: Kor Training Centre

17,250.00 20,750.00 10,350.00 12,500.00 15,750.00 17,250.00 20,750.00 17,250.00 20,750.00 17,250.00 15,750.00 15,750.00 13,750.00 11,000.00

Page 77: Kor Training Centre

D A F T A R A N A L I S A

1 A. 1. 1 M3 PEKERJAAN GALIAN/MENGURUG TANAH PADAT

0.750 Pekerja @ Rp 38,500.00 Rp 28,875.00

0.025 Mandor @ Rp 70,800.00 Rp 1,770.00

Rp 30,645.00

2 A. 9. 1 M3 MENGURUG TANAH

1.200 M3 Tanah Timbunan @ Rp 25,000.00 Rp 30,000.00

0.300 Pekerja @ Rp 38,500.00 Rp 11,550.00

0.010 Mandor @ Rp 70,800.00 Rp 708.00

1 M3 Mengurug Tanah Rp 42,258.00

3 A. 18. 1 M3 PEKERJAAN TIMBUNAN PASIR DIBAWAH LANTAI

1.200 M3 Pasir Timbunan @ Rp 38,500.00 Rp 46,200.00

0.300 Pekerja @ Rp 38,500.00 Rp 11,550.00

0.010 Mandor @ Rp 70,800.00 Rp 708.00

Rp 58,458.00

4 G. 1. 1 M3 PASANGAN BATU KOSONG

1.200 M3 Batu Gunung @ Rp 48,000.00 Rp 57,600.00

5.000 Pekerja @ Rp 38,500.00 Rp 192,500.00

0.250 Mandor @ Rp 70,800.00 Rp 17,700.00

Rp 267,800.00

5 G.32F. 1 M3 PAS. PONDASI BATU GUNUNG (1Pc : 1/2Kp : 5Ps)

1.200 M3 Batu Gunung @ Rp 48,000.00 Rp 57,600.00

2.557 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 98,436.80

0.509 M3 Pasir Pasangan @ Rp 70,800.00 Rp 36,037.20

0.051 M3 Kapur @ Rp 70,800.00 Rp 3,610.80

1.200 Tukang @ Rp 18,000.00 Rp 21,600.00

0.120 Kepala tukang @ Rp 70,800.00 Rp 8,496.00

0.180 Mandor @ Rp 70,800.00 Rp 12,744.00

3.600 Pekerja @ Rp 38,500.00 Rp 138,600.00

Rp 377,124.80

6 G.32H. 1 M3 PASANGAN PONDASI (1pc : 4 ps)

1.200 M3 Batu Gunung @ Rp 48,000.00 Rp 57,600.00

3.257 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 125,402.20

0.522 M3 Pasir Pasangan @ Rp 70,800.00 Rp 36,957.60

Upah Kerja G.32 F Rp 181,440.00

Rp 401,399.80

7 G.32M. 1 M3 PASANGAN PONDASI (1pc : 3 ps)

1.200 M3 Batu Gunung @ Rp 48,000.00 Rp 57,600.00

4.049 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 155,901.90

0.486 M3 Pasir Pasangan @ Rp 70,800.00 Rp 34,408.80

Upah Kerja G.32 F Rp 181,440.00

Rp 429,350.70

8 SPL.V. 1 M3 BETON BERTULANG Camp. 1Pc : 2Ps : 3Kr

A. Pekerjaan Beton

1. Bahan Beton K. 225

7.650 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 294,525.00

0.480 m3 Pasir Beton @ Rp 70,800.00 Rp 33,984.00

0.800 m3 Batu Pecah 2-3 cm @ Rp 70,800.00 Rp 56,640.00

Rp 385,149.00

Page 78: Kor Training Centre

2. Bahan Beton K. 175

6.800 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 261,800.00

0.540 m3 Pasir Beton @ Rp 70,800.00 Rp 38,232.00

0.820 m3 Batu Pecah 2-3 cm @ Rp 70,800.00 Rp 58,056.00

Rp 358,088.00

3. Upah Kerja Cor

1.000 Tukang @ Rp 18,000.00 Rp 18,000.00

0.100 Kepala tukang @ Rp 70,800.00 Rp 7,080.00

6.000 Pekerja @ Rp 38,500.00 Rp 231,000.00

0.300 Mandor @ Rp 70,800.00 Rp 21,240.00

Rp 277,320.00

B. Pekerjaan Besi Penulangan

1. Upah Kerja + Kawat Beton

2.000 Kg Kawat Ikat Beton @ Rp 70,800.00 Rp 141,600.00

9.000 Tukang @ Rp 18,000.00 Rp 162,000.00

3.000 Kepala tukang @ Rp 70,800.00 Rp 212,400.00

9.000 Pekerja @ Rp 38,500.00 Rp 346,500.00

Rp 720,900.00

2. Pond. Poer Plat

100.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 383,600.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 1,104,500.00

3. Pek. Stek Poer

240.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 920,640.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 1,641,540.00

4. Sloof Utama

120.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 460,320.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 1,181,220.00

5. Sloof Praktis

105.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 402,780.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 1,123,680.00

6. Kolom Utama

200.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 767,200.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 1,488,100.00

7. P l a t

75.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 287,700.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 1,008,600.00

8. Kuda-kuda Beton

95.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 364,420.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 1,085,320.00

9. Kolom Praktis

165.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 632,940.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 1,353,840.00

10. Listplank

95.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 364,420.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 1,085,320.00

Page 79: Kor Training Centre

11. Balok Lantai

160.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 613,760.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 1,334,660.00

12. Ringbalk

125.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 479,500.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 1,200,400.00

13. Beton Sirip

60.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 230,160.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 951,060.00

14. Plat Built in

95.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 364,420.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 1,085,320.00

15. Beton Tangga

110.000 Kg Baja Tulangan Beton @ Rp 3,836.00 Rp 421,960.00

Upah Kerja + Kawat Beton Dihitung Rp 720,900.00

Rp 1,142,860.00

C. Cetakan beton Multipleks dan kayu KLs. II

( Membuat, membongkar dan menyiram )

8.500 M2 Tripleks 6mm @ Rp 35,000.00 Rp 297,500.00

0.035 M3 Kayu Kelas II (Balok) @ Rp 70,800.00 Rp 2,478.00

0.040 m3 Kayu Kelas II (Papan) @ Rp 70,800.00 Rp 2,832.00

0.400 kg Paku Biasa 5-10 cm @ Rp 70,800.00 Rp 28,320.00

4.000 Tukang @ Rp 18,000.00 Rp 72,000.00

0.500 Kepala tukang @ Rp 70,800.00 Rp 35,400.00

1.600 Pekerja @ Rp 38,500.00 Rp 61,600.00

0.100 Mandor @ Rp 70,800.00 Rp 7,080.00

4.000 Bongkar/Siram @ Rp 3,000.00 Rp 12,000.00

Rp 519,210.00

Multipleks 6 mm Rp 516,378.00

Papan Rp 221,710.00

D. Alat-alat Bantu

Pompa Air Rp 1,500.00

Molen Rp 5,000.00

Vibrator Rp 2,250.00

Lift Beton / Tangga Rp 3,000.00

E. 1 M3 Steiger Work

1.100 Bt Bambu @ Rp 3,500.00 Rp 3,850.00

0.040 M3 Kayu Kelas II (Papan) @ Rp 70,800.00 Rp 2,832.00

0.400 kg Paku Biasa 5-10 cm @ Rp 70,800.00 Rp 28,320.00

0.200 Pekerja @ Rp 38,500.00 Rp 7,700.00

0.070 Mandor @ Rp 70,800.00 Rp 4,956.00

0.300 Tukang @ Rp 18,000.00 Rp 5,400.00

0.030 Kepala tukang @ Rp 70,800.00 Rp 2,124.00

Rp 55,182.00

Page 80: Kor Training Centre

F. Harga Beton/m3

Pond. Poer Plat A1+A3+B2+C2+D1,2 Rp 1,995,179.00

Pek. Stek Poer A1+A3+B3+C2+D2 Rp 2,530,719.00

Sloof Utama A2+A3+B4+C2+D2 Rp 2,043,338.00

Sloof Praktis A2+A3+B5+C2+D2 Rp 1,985,798.00

Kolom A1+A3+B6+C1+D2+E Rp 2,727,129.00

P l a t A2+A3+B7+C1+D2,3+E Rp 2,222,818.00

Kuda-kuda Beton A1+A3+B8+C2+D2+E Rp 2,029,681.00

Kolom Praktis A2+A3+B9+C2 Rp 2,210,958.00

Listplank A2+A3+B10+C1+D2 Rp 2,242,106.00

Balok Lantai A1+A3+B11+C1+D2,3+E Rp 2,575,939.00

Ringbalk A2+A3+B12+C1+D2+E Rp 2,412,368.00

Beton Sirip A2+A3+B13+C1+D2 Rp 2,107,846.00

Plat Built in A2+A3+B14+C1+D2 Rp 2,242,106.00

Beton Tangga A2+A3+B15+C1+D2+E Rp 2,354,828.00

9 G.33F. 1 M3 PAS. TEMBOK 1/2 BATA Camp. 1pc : 1/2Kp : 5Ps

550.000 Bh Bata Merah @ Rp #N/A Rp #N/A

1.972 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 75,922.00

0.396 M3 Pasir Pasangan @ Rp 70,800.00 Rp 28,036.80

0.040 M3 Kapur @ Rp 70,800.00 Rp 2,832.00

1.500 Tukang @ Rp 18,000.00 Rp 27,000.00

0.150 Kepala tukang @ Rp 70,800.00 Rp 10,620.00

4.500 Pekerja @ Rp 38,500.00 Rp 173,250.00

0.225 Mandor @ Rp 70,800.00 Rp 15,930.00

Rp #N/A

10 G.33M. 1 M3 PAS. TEMBOK Camp. 1Pc : 2 Ps

550.000 Bh Bata Merah @ Rp #N/A Rp #N/A

4.117 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 158,519.90

0.333 Pasir Pasangan @ Rp 70,800.00 Rp 23,576.40

Upah Kerja (G.33F) Rp 226,800.00

Rp #N/A

11 G.55b. 1 M2 PAS. BATU-BATA LANTAI 1 LAPIS

30.000 Bh Bata Merah @ Rp #N/A Rp #N/A

0.035 Pasir Pasangan @ Rp 70,800.00 Rp 2,478.00

0.060 Tukang @ Rp 18,000.00 Rp 1,080.00

0.200 Pekerja @ Rp 38,500.00 Rp 7,700.00

Rp #N/A

12 G. 50P. 1 M2 PLESTERAN Camp. 1Pc : 1/2Kp : 5Ps

0.068 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 2,618.00

0.014 M3 Pasir Pasangan @ Rp 70,800.00 Rp 962.88

0.002 M3 Kapur @ Rp 70,800.00 Rp 141.60

0.150 Tukang @ Rp 18,000.00 Rp 2,700.00

0.015 Kepala tukang @ Rp 70,800.00 Rp 1,062.00

0.400 Pekerja @ Rp 38,500.00 Rp 15,400.00

0.020 Mandor @ Rp 70,800.00 Rp 1,416.00

Rp 24,300.48

13 G.50H. 1 M2 PLESTERAN TEMBOK Camp. 1Pc : 2Ps

0.143 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 5,497.80

0.011 M3 Pasir Pasangan @ Rp 70,800.00 Rp 807.12

Upah Kerja (G.50P) Dihitung Rp 20,578.00

Rp 26,882.92

Page 81: Kor Training Centre

14 G.50K. 1 M2 PLESTERAN Camp. 1Pc : 3 Ps

0.108 Zak Semen (Bosowa) @ Rp 38,500.00 Rp 4,149.53

0.013 M3 Pasir Pasangan @ Rp 70,800.00 Rp 920.40

Upah Kerja (G.50P) Dihitung G.50P Rp 20,578.00

Rp 25,647.93

Untuk Plester Beton Bundar 1,8 x 25,647.93 Rp 46,166.27

15 G. 43. 1 M2 RABAT BETON Camp. 1Pc : 3Kr : 5Ps

0.100 M3 Kerikil Sungai @ Rp 70,800.00 Rp 7,080.00

0.060 M3 Pasir Beton @ Rp 70,800.00 Rp 4,248.00

0.364 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 14,006.30

0.600 Tukang @ Rp 18,000.00 Rp 10,800.00

0.030 Kepala tukang @ Rp 70,800.00 Rp 2,124.00

0.100 Pekerja @ Rp 38,500.00 Rp 3,850.00

0.010 Mandor @ Rp 70,800.00 Rp 708.00

Rp 42,816.30

16 G. 67 1 M3 RABAT BETON Camp. 1Pc:3Kr:6Ps

0.070 M3 Kerikil Sungai @ Rp 70,800.00 Rp 4,956.00

0.044 M3 Pasir Beton @ Rp 70,800.00 Rp 3,115.20

0.364 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 14,006.30

0.135 Tukang @ Rp 18,000.00 Rp 2,430.00

0.014 Kepala tukang @ Rp 70,800.00 Rp 955.80

0.720 Pekerja @ Rp 38,500.00 Rp 27,720.00

0.036 Mandor @ Rp 70,800.00 Rp 2,548.80

Rp 55,732.10

17 G. 69. Upah Lantai Tegel

0.500 Tukang @ Rp 18,000.00 Rp 9,000.00

0.050 Kepala tukang @ Rp 70,800.00 Rp 3,540.00

1.000 Pekerja @ Rp 38,500.00 Rp 38,500.00

0.500 Mandor @ Rp 70,800.00 Rp 35,400.00

Rp 86,440.00

18 G. 14. 1 M3 PEREKAT SEMEN Camp. 1Pc : 2Ps

11.750 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 452,390.40

0.950 M3 Pasir Pasangan @ Rp 70,800.00 Rp 67,260.00

Rp 519,650.40

19 SPL.IV. 1 M2 MEMASANG LANTAI TEGEL

A 1.000 M3 Analisa G. 69 @ Rp 86,440.00 Rp 86,440.00

B 0.010 M3 Analisa G. 14 @ Rp 519,650.40 Rp 5,196.50

C 1.000 M2 Tegel Keramik 40x40 @ Rp 52,000.00 Rp 52,000.00

D 1.000 M2 Tegel Keramik 20x20 cm @ Rp 18,750.00 Rp 18,750.00

E 1.000 M2 Tegel Keramik 30x30 @ Rp 18,750.00 Rp 18,750.00

F 1.000 M2 Batu Alam @ Rp 25,000.00 Rp 25,000.00

Maka 1 M2 Pekerjaan Tegel

1 Tegel Keramik 40x40 A+B+C Rp 143,636.50

2 Tegel Keramik 30x30 cm A+B+E Rp 110,386.50

3 Tegel Mozaik 20x20 cm A+B+D Rp 110,386.50

4 Pas. Batu Alam A+B+F Rp 116,636.50

Page 82: Kor Training Centre

20 SPL. IV. 1 M2 PAS. DINDING PORSELIN 20 X 25 cm / MARMO

1.100 M2 Tegel Keramik 20x25 cm @ Rp 18,750.00 Rp 20,625.00

0.010 Analisa G. 14 @ Rp 519,650.40 Rp 5,196.50

1.000 Upah Kerja G. 69 @ Rp 86,440.00 Rp 86,440.00

Untuk 1 m2 Pekerjaan tegel porselin Rp 112,261.50

21 G. 69B. UPAH KERJA PLINT

0.500 Tukang @ Rp 18,000.00 Rp 9,000.00

0.050 Kepala tukang @ Rp 70,800.00 Rp 3,540.00

1.000 Pekerja @ Rp 38,500.00 Rp 38,500.00

0.050 Mandor @ Rp 70,800.00 Rp 3,540.00

Rp 54,580.00

22 G. 68A. 1 M' PASANGAN TEGEL PLINT

0.025 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 962.50

0.002 M3 Pasir Pasangan @ Rp 70,800.00 Rp 1,039.30

0.200 Upah Kerja G. 69B. 54,580.00 Rp 10,916.00

1.100 M2 Tegel Porselin 11x11 27,500.00 Rp 30,250.00

Rp 43,167.80

23 SPL.IV a. 1 M2 MEMASANG TEGEL KERAMIK 60/60 (Ezensa)/GRANIT

1.100 M2 Marmer Bosowa @ Rp 200,000.00 Rp 220,000.00

1.100 M2 Tegel Ezensa 60x60 cm @ Rp 18,750.00 Rp 20,625.00

0.300 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 11,550.00

0.032 M3 Pasir Pasangan @ Rp 70,800.00 Rp 2,265.60

0.003 M3 Kapur @ Rp 70,800.00 Rp 212.40

0.750 Tukang @ Rp 18,000.00 Rp 13,500.00

0.100 Kepala tukang @ Rp 70,800.00 Rp 7,080.00

1.500 Pekerja @ Rp 38,500.00 Rp 57,750.00

0.100 Mandor @ Rp 70,800.00 Rp 7,080.00

1 M2 Memasang tegel Keramik Ezensa 30x30 cm Rp 319,438.00

1 M2 Memasang tegel Keramik Ezensa 60x60 cm 120,063.00

24 K. 23 1 M2 Upah Mengecat Tembok 1 x Olah

0.075 Tukang @ Rp 18,000.00 Rp 1,350.00

0.0075 Kepala tukang @ Rp 70,800.00 Rp 531.00

0.050 Pekerja @ Rp 38,500.00 Rp 1,925.00

0.0025 Mandor @ Rp 70,800.00 Rp 177.00

Rp 3,983.00

25 Spl.VIII + K.23 1 M2 PEKERJAAN CAT DINDING 1 x PLAMUR DAN 3 x MENGECAT

0.425 Kg Cat Tembok Kls B (Ex Metrolite) @ Rp 70,800.00 Rp 30,090.00

1.000 M2 Pekerja Plamur @ Rp 1,000.00 Rp 1,000.00

1.000 M2 Mengaci Dengan Plamur Tembok @ Rp 1,500.00 Rp 1,500.00

Upah mengacat 3 x @ Rp 3,983.00 Rp 11,949.00

Rp 44,539.00

26 Spl.VIIIa. 1 M2 MENGERJAKAN PENGECATAN TEKSTUR + CAT DASAR

0.142 Kg Cat Dasar @ Rp 70,800.00 Rp 10,053.60

Upah Kerja Cat K.23 @ Rp 3,983.00 Rp 3,983.00

1.200 Kg Cat Tembok Kls B (Ex Metrolite) @ Rp 70,800.00 Rp 84,960.00

0.012 Kg Lem Perekat @ Rp 5,500.00 Rp 250.00

0.025 Alat Semprot @ Rp 55,000.00 Rp 1,375.00

Alat Bantu Rp 750.00

0.200 Tukang Tekstur @ Rp 17,250.00 Rp 3,450.00

0.120 Pembantu Tukang @ Rp 10,350.00 Rp 1,242.00

Kelas B Rp 106,063.60

Page 83: Kor Training Centre

27 G.53.A 1 M2 MENGECAT TEMBOK 2 KALI

0.320 Kg Cat Tembok Kls B (Ex Metrolite) @ Rp 70,800.00 Rp 22,656.00

0.150 Tukang @ Rp 18,000.00 Rp 2,700.00

0.015 Kepala tukang @ Rp 70,800.00 Rp 1,062.00

0.100 Pekerja @ Rp 38,500.00 Rp 3,850.00

0.005 Mandor @ Rp 70,800.00 Rp 354.00

1 M2 Mengecat tembok 2 Kali Rp 30,622.00

28 G.53.X 1 M2 MENGECAT TEMBOK KEDAP AIR 2 X

0.500 Ltr Cat Aqua Seal @ Rp 25,000.00 Rp 12,500.00

0.320 Ltr Cat Dulux @ Rp 24,200.00 Rp 7,744.00

Upah mengacat K. 23 Rp 3,983.00

Rp 24,227.00

Untuk 1 M2 Mengecat Aqua Seal 2 Kali 2 x 24,227.00 Rp 48,454.00

Untuk 1 M2 Mengecat Anti Lumut 2 Kali 2 x 11,727.00 Rp 23,454.00

29 Supl. IX 10 M2 MENGECAT KAYU (1X DASAR, PLAMUR DAN 2X CAT WARNA)

1.420 Kg Cat Dasar @ Rp 70,800.00 Rp 100,536.00

2.840 Kg Cat Kayu Gloteks @ Rp 70,800.00 Rp 201,072.00

2.250 Tukang @ Rp 18,000.00 Rp 40,500.00

0.225 Kepala tukang @ Rp 70,800.00 Rp 15,930.00

1.500 Pekerja @ Rp 38,500.00 Rp 57,750.00

0.075 Mandor @ Rp 70,800.00 Rp 5,310.00

Rp 421,098.00

1 M2 Mengecat, Memplamur, Menggosok Rp 42,109.80

30 Supl. IX.a 1 M2 MENGECAT ATAP SENG

0.2400 Kg Cat Atap Seng @ Rp 22,200.00 Rp 5,328.00

0.0285 Ltr Minyak Cat @ Rp 70,800.00 Rp 2,017.80

0.200 Tukang @ Rp 18,000.00 Rp 3,600.00

0.020 Kepala tukang @ Rp 70,800.00 Rp 1,416.00

0.135 Pekerja @ Rp 38,500.00 Rp 5,197.50

0.0067 Mandor @ Rp 70,800.00 Rp 474.36

Rp 18,033.66

31 K. 6. 1 M2 RESIDU RANGKA PLAFOND

0.150 Kg Cat Residu @ Rp 2,000.00 Rp 300.00

0.150 Tukang @ Rp 18,000.00 Rp 2,700.00

0.015 Kepala tukang @ Rp 70,800.00 Rp 1,062.00

0.100 Pekerja @ Rp 38,500.00 Rp 3,850.00

0.005 Mandor @ Rp 70,800.00 Rp 354.00

Rp 8,266.00

32 K. 5. 1 M2 MENGECAT TEAK OIL/POLITUR

0.320 Kg Cat Teak Oil/Politur @ Rp 70,800.00 Rp 22,656.00

0.150 Tukang @ Rp 18,000.00 Rp 2,700.00

0.015 Kepala tukang @ Rp 70,800.00 Rp 1,062.00

0.100 Pekerja @ Rp 38,500.00 Rp 3,850.00

0.005 Mandor @ Rp 70,800.00 Rp 354.00

Rp 30,622.00

33 G. 53. 100 M2 MENGAPUR TEMBOK 3 X

0.110 M3 Kapur Ayak @ Rp 49,700.00 Rp 5,467.00

1.100 Tukang @ Rp 18,000.00 Rp 19,800.00

0.011 Kepala tukang @ Rp 70,800.00 Rp 778.80

6.600 Pekerja @ Rp 38,500.00 Rp 254,100.00

Rp 280,145.80

Maka 1 M2 Mengapur = 1/100 x Rp 280,145.80 Rp 2,801.46

Page 84: Kor Training Centre

34 G. 54. 10 M2 ACIAN TEMBOK

0.030 Zak Semen (Tonasa) @ Rp 38,500.00 Rp 1,155.00

0.053 M3 Kapur @ Rp 70,800.00 Rp 3,752.40

0.500 Tukang @ Rp 18,000.00 Rp 9,000.00

0.050 Kepala tukang @ Rp 70,800.00 Rp 3,540.00

0.850 Pekerja @ Rp 38,500.00 Rp 32,725.00

0.043 Mandor @ Rp 70,800.00 Rp 3,044.40

Rp 53,216.80

Maka 1 M2 Mengaci = 1/10 x Rp 53,216.80 Rp 5,321.68

35 F. 21. 1 M2 MENGERJAKAN PAPAN LISTPLANK

0.100 Kg Paku Biasa 4 cm @ Rp 70,800.00 Rp 7,080.00

0.033 M3 Kayu Kls I (Papan) @ Rp 70,800.00 Rp 2,336.40

0.800 Tukang @ Rp 18,000.00 Rp 14,400.00

0.080 Kepala tukang @ Rp 70,800.00 Rp 5,664.00

0.280 Pekerja @ Rp 38,500.00 Rp 10,780.00

0.014 Mandor @ Rp 70,800.00 Rp 991.20

1 M2 Papan Listplank Kls. I Rp 41,251.60

36 F. 22. 1 M3 MENGERJAKAN KUDA-KUDA KAYU

1.100 M3 Kayu Kls I (Balok) @ Rp 70,800.00 Rp 77,880.00

1.100 M3 Kayu Kelas II (Balok) @ Rp 70,800.00 Rp 77,880.00

24.000 Tukang @ Rp 18,000.00 Rp 432,000.00

2.400 Kepala tukang @ Rp 70,800.00 Rp 169,920.00

8.000 Pekerja @ Rp 38,500.00 Rp 308,000.00

0.400 Mandor @ Rp 70,800.00 Rp 28,320.00

Kuda-kuda Kayu Kls.II Rp 1,016,120.00

Kuda-kuda Kayu Kls.I Senso Rp 1,016,120.00

37 F. 24 1 M3 MENGERJAKAN GORDING, RENG DAN KASO

1.100 M3 Kayu Kls I (Balok) @ Rp 70,800.00 Rp 77,880.00

1.100 M3 Kayu Kelas II (Balok) @ Rp 70,800.00 Rp 77,880.00

14.000 Tukang @ Rp 18,000.00 Rp 252,000.00

1.400 Kepala tukang @ Rp 70,800.00 Rp 99,120.00

6.000 Pekerja @ Rp 38,500.00 Rp 231,000.00

0.300 Mandor @ Rp 70,800.00 Rp 21,240.00

KAP Kayu Kls.II Rp 681,240.00

KAP Kayu Kls.I Senso Rp 681,240.00

38 F. 26. 1 M3 MENGERJAKAN KOSEN

1.100 M3 Kayu Kls I (Balok Somil) @ Rp 2,160,000.00 Rp 2,376,000.00

30.000 Tukang @ Rp 18,000.00 Rp 540,000.00

3.000 Kepala tukang @ Rp 70,800.00 Rp 212,400.00

10.000 Pekerja @ Rp 38,500.00 Rp 385,000.00

0.500 Mandor @ Rp 70,800.00 Rp 35,400.00

Rp 3,548,800.00

39 F.33A. 1 M2 MENGERJAKAN PINTU PANIL

0.033 M3 Kayu Kls I (Papan) @ Rp 70,800.00 Rp 2,336.40

7.500 Tukang @ Rp 18,000.00 Rp 135,000.00

0.750 Kepala tukang @ Rp 70,800.00 Rp 53,100.00

2.500 Pekerja @ Rp 38,500.00 Rp 96,250.00

0.125 Mandor @ Rp 70,800.00 Rp 8,850.00

Rp 295,536.40

Page 85: Kor Training Centre

40 F.33B. 1 M2 MENGERJAKAN PINTU TEAKWOOD 2X

0.015 M3 Kayu Kelas II (Papan) @ Rp 70,800.00 Rp 1,062.00

0.015 M3 Kayu Kls I (Papan) @ Rp 70,800.00 Rp 1,062.00

0.040 Kg Paku Sirap 2-3 cm @ Rp 70,800.00 Rp 2,832.00

2.600 Tukang @ Rp 18,000.00 Rp 46,800.00

0.260 Kepala tukang @ Rp 70,800.00 Rp 18,408.00

0.850 Pekerja @ Rp 38,500.00 Rp 32,725.00

0.043 Mandor @ Rp 70,800.00 Rp 3,009.00

2.100 M2 Tripleks 6mm @ Rp 35,000.00 Rp 73,500.00

Dengan Rangka Kls II Rp 178,336.00

Dengan Rangka Kls I Rp 178,336.00

41 F. 35. 1 M2 MENGERJAKAN JALUSI PAPAN

0.055 M3 Kayu Kls I (Papan) @ Rp 70,800.00 Rp 3,894.00

0.020 Kg Paku Sirap 2-3 cm @ Rp 70,800.00 Rp 1,416.00

6.000 Tukang @ Rp 18,000.00 Rp 108,000.00

0.600 Kepala tukang @ Rp 70,800.00 Rp 42,480.00

2.000 Pekerja @ Rp 38,500.00 Rp 77,000.00

0.100 Mandor @ Rp 70,800.00 Rp 7,080.00

Rp 239,870.00

42 F. 36. 1 M2 MENGERJAKAN PINTU/JENDELA KACA

0.017 M3 Kayu Kls I (Papan) @ Rp 70,800.00 Rp 1,177.85

0.800 M2 Kaca Rayband 5mm @ Rp 70,800.00 Rp 56,640.00

6.000 Tukang @ Rp 18,000.00 Rp 108,000.00

0.600 Kepala tukang @ Rp 70,800.00 Rp 42,480.00

2.000 Pekerja @ Rp 38,500.00 Rp 77,000.00

0.100 Mandor @ Rp 70,800.00 Rp 7,080.00

Rp 292,377.85

43 F. 36. 1 M2 MEMASANG KACA MATI 5 MM

1.000 M2 Kaca Bening 5 mm @ Rp 70,800.00 Rp 70,800.00

1.000 M2 Kaca Rayband 5mm @ Rp 70,800.00 Rp 70,800.00

0.030 KG Paku Sirap 2-3 cm @ Rp 70,800.00 Rp 2,124.00

3.800 M' List Kayu Profil @ Rp 70,800.00 Rp 269,040.00

0.500 Tukang @ Rp 18,000.00 Rp 9,000.00

0.025 Kepala tukang @ Rp 70,800.00 Rp 1,770.00

1 M2 Memasang Kaca Mati 5 MM Rp 352,734.00

1 M2 Memasang Kaca Mati Bening 5 MM Rp 352,734.00

44 H.18A. 1 M2 MENUTUP ATAP DENGAN GENTENG + PELAPIS

9.000 Bh Genteng Beton Warna @ Rp 70,800.00 Rp 637,200.00

1.100 M2 Karet Genteng 90 CM @ Rp 70,800.00 Rp 77,880.00

0.200 Tukang @ Rp 18,000.00 Rp 3,600.00

0.020 Kepala tukang @ Rp 70,800.00 Rp 1,416.00

0.100 Pekerja @ Rp 38,500.00 Rp 3,850.00

0.005 Mandor @ Rp 70,800.00 Rp 354.00

1 M2 Menutup Atap Dengan Genteng Beton Warna Rp 724,300.00

Page 86: Kor Training Centre

45 H.10. 1 M' MENGERJAKAN BUBUNGAN ATAP

3.300 Bh Bubungan Genteng Beton @ Rp 70,800.00 Rp 233,640.00

1.100 Lbr Bubungan Asbes Gelombang @ Rp 15,000.00 Rp 16,500.00

0.330 Kg Paku Biasa 4 cm @ Rp 70,800.00 Rp 23,364.00

0.250 Tukang @ Rp 18,000.00 Rp 4,500.00

0.025 Kepala tukang @ Rp 70,800.00 Rp 1,770.00

0.250 Pekerja @ Rp 38,500.00 Rp 9,625.00

0.013 Mandor @ Rp 70,800.00 Rp 885.00

Perekat @ Rp 2,000.00 Rp 2,000.00

Untuk 1 M1 Bubungan Genteng Beton Rp 275,784.00

Untuk 1 M1 Bubungan Atap Asbes Rp 58,644.00

46 H.8 1 M2 MENUTUP ATAP SENG GELOMBANG

1.100 M2 Seng Gelombang BJLS 0,20 @ Rp 38,500.00 Rp 42,350.00

0.040 Kg Paku Asbes/Seng @ Rp 70,800.00 Rp 2,832.00

0.200 Tukang @ Rp 18,000.00 Rp 3,600.00

0.020 Kepala tukang @ Rp 70,800.00 Rp 1,416.00

0.100 Pekerja @ Rp 38,500.00 Rp 3,850.00

0.005 Mandor @ Rp 70,800.00 Rp 354.00

1 M2 Menutup Atap Seng Rp 54,402.00

H.9 1 M1 MENGERJAKAN NOK SENG LICIN

0.200 Lbr Seng Plat BWG 0,28 @ Rp 38,500.00 Rp 7,700.00

0.006 M3 Kayu Kelas II (Papan) @ Rp 70,800.00 Rp 424.80

0.080 Kg Paku Asbes/Seng @ Rp 70,800.00 Rp 5,664.00

0.020 Tukang @ Rp 18,000.00 Rp 360.00

0.010 Kepala tukang @ Rp 70,800.00 Rp 708.00

0.030 Pekerja @ Rp 38,500.00 Rp 1,155.00

0.010 Mandor @ Rp 70,800.00 Rp 708.00

1 M' Mengerjakan Nok Seng Licin Rp 16,719.80

47 H.8x 1 M2 MENUTUP ATAP GENTENG PRIMA ROOF

2.700 Lbr Atap Prima Roof @ Rp #N/A Rp #N/A

0.025 Kg Paku @ Rp 17,500.00 Rp 437.50

0.100 Tukang @ Rp 18,000.00 Rp 1,800.00

0.010 Kepala tukang @ Rp 70,800.00 Rp 708.00

0.500 Pekerja @ Rp 38,500.00 Rp 19,250.00

0.005 Mandor @ Rp 70,800.00 Rp 354.00

Rp #N/A

48 H.8y 1 M1 NOK GENTENG PRIMA ROOF

3.100 Bh Nok Bulat Prima Roof @ Rp 70,800.00 Rp 219,480.00

0.025 Kg Paku @ Rp 17,500.00 Rp 437.50

0.080 Tukang @ Rp 18,000.00 Rp 1,440.00

0.008 Kepala tukang @ Rp 70,800.00 Rp 566.40

0.001 Pekerja @ Rp 38,500.00 Rp 38.50

0.0025 Mandor @ Rp 70,800.00 Rp 177.00

Rp 222,139.40

49 F. 1. 1 M3 PEKERJAAN RANGKA PLAFOND

1.100 M3 Kayu Kelas II (Balok) @ Rp 70,800.00 Rp 77,880.00

2.000 Kg Paku Biasa 5-10 cm @ Rp 70,800.00 Rp 141,600.00

15.000 Tukang @ Rp 18,000.00 Rp 270,000.00

1.500 Kepala tukang @ Rp 70,800.00 Rp 106,200.00

5.000 Pekerja @ Rp 38,500.00 Rp 192,500.00

0.250 Mandor @ Rp 70,800.00 Rp 17,700.00

Rp 805,880.00

Page 87: Kor Training Centre

50 Supl. VII 1 M2 PEKERJAAN PLAFOND

13.000 M1 Lambiserin Kls II 1x9x400 @ Rp 70,800.00 Rp 920,400.00

1.100 M2 Tripleks 4mm @ Rp 30,000.00 Rp 33,000.00

1.100 M2 Gypsum Board @ Rp 70,800.00 Rp 77,880.00

1.100 M2 Eternit 1 x 1 M @ Rp 70,800.00 Rp 77,880.00

0.040 Kg Paku Gypsum @ Rp 30,000.00 Rp 1,200.00

0.040 Kg Paku Sirap 2-3 cm @ Rp 70,800.00 Rp 2,832.00

0.500 Pekerja @ Rp 38,500.00 Rp 19,250.00

0.025 Mandor @ Rp 70,800.00 Rp 1,770.00

1 M2 Mengerjakan Plafond Tripleks Rp 56,852.00

1 M2 Mengerjakan Plafond Lambiserin Rp 944,252.00

1 M2 Mengerjakan Plafond Gypsum Rp 100,100.00

1 M2 Mengerjakan Plafond Eternit Rp 101,732.00

51 10 M' MENGERJAKAN KOSEN ALUMINIUM

10.500 M1 Aluminium 3" @ Rp 37,800.00 Rp 396,900.00

5.500 Tukang @ Rp 18,000.00 Rp 99,000.00

0.550 Kepala tukang @ Rp 70,800.00 Rp 38,940.00

1.800 Pekerja @ Rp 38,500.00 Rp 69,300.00

0.180 Mandor @ Rp 70,800.00 Rp 12,744.00

Alat-alat bantu Rp 1,500.00

Rp 618,384.00

Untuk 1 M' Rp 61,838.40

52 1 M2 MENGERJAKAN JENDELA ALUMINIUM

4.000 M1 Aluminium 2" @ Rp 36,450.00 Rp 145,800.00

0.800 M2 Kaca Rayband 5mm @ Rp 70,800.00 Rp 56,640.00

0.550 Tukang @ Rp 18,000.00 Rp 9,900.00

0.055 Kepala tukang @ Rp 70,800.00 Rp 3,894.00

0.180 Pekerja @ Rp 38,500.00 Rp 6,930.00

0.018 Mandor @ Rp 70,800.00 Rp 1,274.40

Alat-alat bantu Rp 2,000.00

Rp 226,438.40

53 SPL.VIa. 1 UNIT SEPTICKTANK DAN PERESAPAN

11.381 M3 Galian Tanah @ Rp 30,645.00 Rp 348,770.75

2.087 M3 Pas. Trasram @ Rp #N/A Rp #N/A

0.200 M3 Pasir Urug @ Rp 58,458.00 Rp 11,691.60

1.950 M3 Urugan Kembali @ Rp 30,645.00 Rp 59,757.75

14.930 M2 Plester Trasram @ Rp 25,647.93 Rp 382,923.59

6.000 M2 Ijuk @ Rp 1,800.00 Rp 10,800.00

0.221 M3 Plat Beton @ Rp 2,222,818.00 Rp 490,131.37

14.930 M2 Acian Semen Licin @ Rp 5,321.68 Rp 79,452.68

0.850 M1 Pipa Penghawaan @ Rp Ls Rp 10,000.00

0.900 M3 Pasir Pasangan @ Rp 70,800.00 Rp 63,720.00

5.000 Mtr Pipa PVC 4" Maspion @ Rp 38,500.00 Rp 192,500.00

Rp #N/A

54 SPL.VI. 1 M' MENGERJAKAN SALURAN AIR HUJAN

0.070 M3 Beton Penutup Saluran @ Rp 2,210,958.00 Rp 154,767.06

0.289 M3 Galian Tanah @ Rp 30,645.00 Rp 8,848.74

0.099 M3 Pas. Trasram @ Rp #N/A Rp #N/A

0.072 M3 Pasir Urug @ Rp 58,458.00 Rp 4,179.75

0.055 M3 Urugan Kembali @ Rp 30,645.00 Rp 1,685.48

0.572 M2 Plester Trasram @ Rp 25,647.93 Rp 14,670.62

1 M1 Mengerjakan saluran Air Hujan (Terbuka) Rp #N/A

1 M1 Mengerjakan saluran Air Hujan (Tertutup) Rp #N/A

Page 88: Kor Training Centre

55 G. 14. 1 M3 PASANGAN BETON COR 1pc : 2ps : 3kr

0.820 M3 Kerikil Sungai @ Rp 70,800.00 Rp 58,056.00

0.540 M3 Pasir Beton @ Rp 70,800.00 Rp 38,232.00

6.800 M3 Semen (Tonasa) @ Rp 38,500.00 Rp 261,800.00

1.000 Tukang @ Rp 18,000.00 Rp 18,000.00

0.100 Kepala tukang @ Rp 70,800.00 Rp 7,080.00

6.000 Pekerja @ Rp 38,500.00 Rp 231,000.00

0.300 Mandor @ Rp 70,800.00 Rp 21,240.00

Rp 635,408.00

56 1 TITIK MENGERJAKAN INSTALASI PENERANGAN

I Pemasangan Titik Lampu

18.000 Meter Kabel NYM 2 x 2,5 mm2 @ Rp 3,250.00 Rp 58,500.00

36.000 Bh Klem Kabel No. 10 @ Rp 100.00 Rp -

1.000 Btg Pipa Pvc 5/8" @ Rp 1,600.00 Rp 1,600.00

1.000 Bh Inbow Dos @ Rp 3,000.00 Rp 3,000.00

4.000 Bh Las Dop @ Rp 50.00 Rp 200.00

0.250 Roll Isolasi Dari Plastik @ Rp 70,800.00 Rp 17,700.00

1.000 Bh T - Dos 5/8" @ Rp 125.00 Rp 125.00

1.000 Ls Alat Bantu @ Rp 150.00 Rp 150.00

0.500 Tukang Instalatur @ Rp 32,500.00 Rp 16,250.00

0.500 Pembantu Tukang @ Rp 17,500.00 Rp 8,750.00

Rp 106,275.00

II Pemasangan Stop Kontak

10.000 Meter Kabel NYM 3 x 2,5 mm2 @ Rp 3,750.00 Rp 37,500.00

16.667 Bh Klem Kabel No. 12 @ Rp 100.00 Rp -

2.000 Btg Pipa Pvc 5/8" @ Rp 1,600.00 Rp 3,200.00

1.000 Bh Stop Kontak Biasa Broco @ Rp 38,500.00 Rp 38,500.00

1.000 Bh Inbow Dos @ Rp 3,000.00 Rp 3,000.00

6.000 Bh Las Dop @ Rp 50.00 Rp 300.00

0.025 Roll Isolasi Dari Plastik @ Rp 70,800.00 Rp 1,770.00

1.000 Bh T - Dos 5/8" @ Rp 125.00 Rp 125.00

1.000 Ls Alat Bantu @ Rp 150.00 Rp 150.00

0.500 Tukang Instalatur @ Rp 32,500.00 Rp 16,250.00

0.500 Pembantu Tukang @ Rp 17,500.00 Rp 8,750.00

Rp 109,545.00

57 Supl. III. 1 M2 PASANGAN PAVING BLOCK (BETON CETAK)

50.000 Bh Paving Block @ Rp 38,500.00 Rp 1,925,000.00

0.150 M3 Pasir Timbunan @ Rp 38,500.00 Rp 5,775.00

0.311 Tukang @ Rp 18,000.00 Rp 5,598.00

0.031 Kepala tukang @ Rp 70,800.00 Rp 2,194.80

0.500 Pekerja @ Rp 38,500.00 Rp 19,250.00

0.025 Mandor @ Rp 70,800.00 Rp 1,770.00

Tebal 6 cm Rp 1,959,587.80

58 F. 30b. 1 M2 PEKERJAAN DINDING TRIPLEKS 2 X + RANGKA

2.200 M2 Tripleks 6mm @ Rp 35,000.00 Rp 77,000.00

0.040 Kg Paku Biasa 5-10 cm @ Rp 70,800.00 Rp 2,832.00

0.074 M3 Kayu Kelas II (Balok) @ Rp 70,800.00 Rp 5,265.75

2.600 Tukang @ Rp 18,000.00 Rp 46,800.00

0.260 Kepala tukang @ Rp 70,800.00 Rp 18,408.00

0.850 Pekerja @ Rp 38,500.00 Rp 32,725.00

0.043 Mandor @ Rp 70,800.00 Rp 3,009.00

1 M2 Mengerjakan Dinding Doble Tripleks Rangka Kls. II Rp 186,039.75

Page 89: Kor Training Centre

ANALISA HARGA SATUANPENIMBUNAN TANAH KODE( Menggunakan Alat ) K. 230

PROPINSI KODE KOTA K O D E DISIAPKAN OLEH TanggalSULAWESI SELATAN ( 73 ) MAKASSAR PT/CV ……….2006

URAIAN ASUMSI :1. Material dikirim ke lokasi pekerjaan 1. Menggunakan alat berat (120 m3/hari)

2. Penghamparan dengan bulduzer 2. Dipakai material pilihan termurah untuk timbunan dikirim ke lokasi

3. Pemadatan dengan mesin gilas 3 roda dan pekerjaan sejauh 10 km oleh pemasok

penyelesaian akhir dengan mesin gilas bergetar

PEKERJAJUMLAH

HARI KODE JUMLAHUPAH BIAYA SUB JUMLAH

ORANG Rp.Hr.Org. RUPIAH RUPIAH

Mandor 1.00 1.00 L.061 1.00 33,600.00 33,600.00 Oprator Terampil 3.00 1.00 L.081 3.00 39,200.00 117,600.00 Pembantu Operator 3.00 1.00 L.083 3.00 30,800.00 92,400.00 Supir Terampil 1.00 1.00 L.091 1.00 36,400.00 36,400.00 Buruh Tak Terampil 1.00 1.00 L.101 1.00 22,400.00 22,400.00 Buruh Tak Terampil 6.00 1.00 L.101 6.00 22,400.00 134,400.00

PEKERJA Rp. 436,800.00 MATERIAL

SAT. KODETOT. HARGA BIAYA SUB JUMLAHVOL SAT.Rp. RUPIAH RUPIAH

Alat Bantu ( set @ 3 alat ) set M.170 0.24 100,000.00 24,000.00 Timbunan pilihan m3 M.050 144.00 29,624.00 4,265,856.00

MATERIAL Rp. 4,289,856.00 PERALATAN JUMLAH HARI KODE JAM UPAH BIAYA SUB JUMLAH

ALAT KERJA KERJA Rp./Jam RUPIAH RUPIAH

Buldozer 110 HP 1.00 1.00 E.001 4.00 272,408.80 1,089,635.20 Mesin Gilas Tiga Roda 6-8 ton 1.00 1.00 E.080 5.00 93,472.02 467,360.10 Mesin Gilas Bergetar 6-7 ton 1.00 1.00 E.082 5.00 96,521.78 482,608.90 Truck Tangki Air 115 HP 1.00 1.00 E.182 5.00 220,138.06 1,100,690.30

PERALATAN Rp. 3,140,294.50 TOTAL Rp. 7,866,950.50

VOLUME 120 m³ Harga Satuan Per m³ Rp. 65,557.92

Page 90: Kor Training Centre

Disiapkan CV. SYAFITRI Eng.Tanggal Juli 2005

DIREKTORAT JENDERAL BINA MARGA BIAYA ALAT UNTUK PERHITUNGANDIREKTORAT BINA PROGRAM JALAN ANALISA BIAYA PERALATAN KODE

SUB.DIT.PERENCANAAN JALAN E.001LOKAL DAN KABUPATEN BULLDOZER 100 HP

PROPINSI KODE KOTA KODE DISIAPKAN OLEH TanggalSULAWESI SELATAN 73 MAKASSAR CV. SYAFITRI Eng. Juli 2005

JENIS ALAT Bulldozer TENAGA 110.00 HP HARGA Rp. 175,000,000.00 UMUR KERJA 8 Tahun = 9,600 Jam Faktor CRF 0.20483

1 Tahun = 1,200 Jam kerja pada 12,5 %1 hari = 5 Jam kerja

A. BIAYA PEMILIKAN : (Rp./Jam)1. Depresiasi : 90 % Harga Alat =

90 % x 175,000,000.00 x 0.20483 = Rp. 26,883.94 1,200

2. Lain-lain : Asuransi 3 % / Tahun

3 % x 175,000,000.00 = Rp. 4,375.00 1,200

Sub. Total = Rp. 31,258.94 B. BIAYA OPERASI

Kebutuhan Bahan Bakar dan Pelumas tiap HP

Diesel = 0.158 liter/HP/JamBensin = 0.167 liter/HP/JamPelumas = 0.006 liter/HP/Jam

Harga : Diesel = 2,100.00 per literBensin = 2,400.00 per literPelumas = 17,000.00 per liter

Bahan Bakar 0.158 x 2,100.00 x ### = Rp. 36,498.00 Pelumas 0.006 x 17,000.00 x ### = Rp. 11,220.00 Perbaikan/Spare parts 0.600 x 26,883.94 = Rp. 16,130.36

Sub. Total = Rp. 63,848.36

Total Biaya Pemilikan dan Operasi Alat : A + B = Rp. 95,107.30 per jam

DIREKTORAT JENDERAL BINA MARGA BIAYA ALAT UNTUK PERHITUNGAN

Page 91: Kor Training Centre

DIREKTORAT BINA PROGRAM JALAN ANALISA BIAYA PERALATAN KODESUB.DIT.PERENCANAAN JALAN E.010

LOKAL DAN KABUPATEN MOTOR GRADER 110 HP

PROPINSI KODE KOTA KODE DISIAPKAN OLEH TanggalSULAWESI SELATAN 73 MAKASSAR CV. SYAFITRI Eng. Juli 2005

JENIS ALAT Motor Grader TENAGA 110.00 HP HARGA Rp. 125,000,000.00 UMUR KERJA 8 Tahun = 12,000 Jam Faktor CRF 0.20483

1 Tahun = 1,500 Jam kerja pada 12,5 %1 hari = 5 Jam kerja

A. BIAYA PEMILIKAN : (Rp./Jam)1. Depresiasi : 90 % Harga Alat =

90 % x 125,000,000.00 x 0.20483 = Rp. 15,362.25 1,500

2. Lain-lain : Asuransi 3 % / Tahun

3 % x 125,000,000.00 = Rp. 2,500.00 1,500

Sub. Total = Rp. 17,862.25 B. BIAYA OPERASI

Kebutuhan Bahan Bakar dan Pelumas tiap HP

Diesel = 0.158 liter/HP/JamBensin = 0.167 liter/HP/JamPelumas = 0.006 liter/HP/Jam

Harga : Diesel = 2,100.00 per literBensin = 2,400.00 per literPelumas = 17,000.00 per liter

Bahan Bakar 0.158 x 2,100.00 x ### = Rp. 36,498.00 Pelumas 0.006 x 17,000.00 x ### = Rp. 11,220.00 Perbaikan/Spare parts 0.600 x 15,362.25 = Rp. 9,217.35

Sub. Total = Rp. 56,935.35

Total Biaya Pemilikan dan Operasi Alat : A + B = Rp. 74,797.60 per jam

DIREKTORAT JENDERAL BINA MARGA BIAYA ALAT UNTUK PERHITUNGANDIREKTORAT BINA PROGRAM JALAN ANALISA BIAYA PERALATAN KODE

SUB.DIT.PERENCANAAN JALAN E.052LOKAL DAN KABUPATEN LOADER WHEELED

Page 92: Kor Training Centre

PROPINSI KODE KOTA KODE DISIAPKAN OLEH TanggalSULAWESI SELATAN 73 MAKASSAR CV. SYAFITRI Eng. Juli 2005

JENIS ALAT Loader Wheeled TENAGA 115.00 HP HARGA Rp. 87,000,000.00 UMUR KERJA 8 Tahun = 12,000 Jam Faktor CRF 0.20483

1 Tahun = 1,500 Jam kerja pada 12,5 %1 hari = 5 Jam kerja

A. BIAYA PEMILIKAN : (Rp./Jam)1. Depresiasi : 90 % Harga Alat =

90 % x 87,000,000.00 x 0.20483 = Rp. 10,692.13 1,500

2. Lain-lain : Asuransi 3 % / Tahun

3 % x 87,000,000.00 = Rp. 1,740.00 1,500

Sub. Total = Rp. 12,432.13 B. BIAYA OPERASI

Kebutuhan Bahan Bakar dan Pelumas tiap HP

Diesel = 0.158 liter/HP/JamBensin = 0.167 liter/HP/JamPelumas = 0.006 liter/HP/Jam

Harga : Diesel = 2,100.00 per literBensin = 2,400.00 per literPelumas = 17,000.00 per liter

Bahan Bakar 0.158 x 2,100.00 x ### = Rp. 38,157.00 Pelumas 0.006 x 17,000.00 x ### = Rp. 11,730.00 Perbaikan/Spare parts 0.600 x 10,692.13 = Rp. 6,415.28

Sub. Total = Rp. 56,302.28

Total Biaya Pemilikan dan Operasi Alat : A + B = Rp. 68,734.41 per jam

DIREKTORAT JENDERAL BINA MARGA BIAYA ALAT UNTUK PERHITUNGANDIREKTORAT BINA PROGRAM JALAN ANALISA BIAYA PERALATAN KODE

SUB.DIT.PERENCANAAN JALAN E.182LOKAL DAN KABUPATEN WATER TANK TRUK

PROPINSI KODE KOTA KODE DISIAPKAN OLEH TanggalSULAWESI SELATAN 73 MAKASSAR CV. SYAFITRI Eng. Juli 2005

JENIS ALAT Water tank truk

Page 93: Kor Training Centre

TENAGA 115.00 HP HARGA Rp. 35,000,000.00 UMUR KERJA 8 Tahun = 5,600 Jam Faktor CRF 0.20483

1 Tahun = 700 Jam kerja pada 12,5 %1 hari = Jam kerja

A. BIAYA PEMILIKAN : (Rp./Jam)1. Depresiasi : 90 % Harga Alat =

90 % x 35,000,000.00 x 0.20483 = Rp. 9,217.35 700

2. Lain-lain : Asuransi 3 % / Tahun

3 % x 35,000,000.00 = Rp. 1,500.00 700

Sub. Total = Rp. 10,717.35 B. BIAYA OPERASI

Kebutuhan Bahan Bakar dan Pelumas tiap HP

Diesel = 0.158 liter/HP/JamBensin = 0.167 liter/HP/JamPelumas = 0.006 liter/HP/Jam

Harga : Diesel = 2,100.00 per literBensin = 2,400.00 per literPelumas = 17,000.00 per liter

Bahan Bakar 0.158 x 2,100.00 x ### = Rp. 38,157.00 Pelumas 0.006 x 17,000.00 x ### = Rp. 11,730.00 Perbaikan/Spare parts 0.600 x 9,217.35 = Rp. 5,530.41

Sub. Total = Rp. 55,417.41

Total Biaya Pemilikan dan Operasi Alat : A + B = Rp. 66,134.76 per jam

DIREKTORAT JENDERAL BINA MARGA BIAYA ALAT UNTUK PERHITUNGANDIREKTORAT BINA PROGRAM JALAN ANALISA BIAYA PERALATAN KODE

SUB.DIT.PERENCANAAN JALAN E.212LOKAL DAN KABUPATEN DUMPTRUCK 5 TON

PROPINSI KODE KOTA KODE DISIAPKAN OLEH TanggalSULAWESI SELATAN 73 MAKASSAR CV. SYAFITRI Eng. Juli 2005

JENIS ALAT Dumptruck TENAGA 145.00 HP HARGA Rp. 22,000,000.00 UMUR KERJA 6 Tahun = 7800 Jam Faktor CRF 0.24668

1 Tahun = 1,300 Jam kerja pada 12,5 %

Page 94: Kor Training Centre

1 hari = Jam kerja

A. BIAYA PEMILIKAN : (Rp./Jam)1. Depresiasi : 90 % Harga Alat =

90 % x 22,000,000.00 x 0.24668 = Rp. 3,757.13 1,300

2. Lain-lain : Asuransi 3 % / Tahun

3 % x 22,000,000.00 = Rp. 507.69 1,300

Sub. Total = Rp. 4,264.82 B. BIAYA OPERASI

Kebutuhan Bahan Bakar dan Pelumas tiap HP

Diesel = 0.158 liter/HP/JamBensin = 0.167 liter/HP/JamPelumas = 0.006 liter/HP/Jam

Harga : Diesel = 2,100.00 per literBensin = 2,400.00 per literPelumas = 17,000.00 per liter

Bahan Bakar 0.158 x 2,100.00 x ### = Rp. 48,111.00 Pelumas 0.006 x 17,000.00 x ### = Rp. 14,790.00 Perbaikan/Spare parts 0.600 x 3,757.13 = Rp. 2,254.28

Sub. Total = Rp. 65,155.28

Total Biaya Pemilikan dan Operasi Alat : A + B = Rp. 69,420.10 per jam

DIREKTORAT JENDERAL BINA MARGA BIAYA ALAT UNTUK PERHITUNGANDIREKTORAT BINA PROGRAM JALAN ANALISA BIAYA PERALATAN KODE

SUB.DIT.PERENCANAAN JALAN E.341LOKAL DAN KABUPATEN WATERPUMP DIA.5 MM

PROPINSI KODE KOTA KODE DISIAPKAN OLEH TanggalSULAWESI SELATAN 73 MAKASSAR CV. SYAFITRI Eng. Juli 2005

JENIS ALAT Water Pump TENAGA 8.00 HP HARGA Rp. 3,000,000.00 UMUR KERJA 4 Tahun = 3,000 Jam Faktor CRF 0.33721

1 Tahun = 750 Jam kerja pada 12,5 %1 hari = Jam kerja

A. BIAYA PEMILIKAN : (Rp./Jam)1. Depresiasi : 90 % Harga Alat =

Page 95: Kor Training Centre

90 % x 3,000,000.00 x 0.33721 = Rp. 1,213.96 750

2. Lain-lain : Asuransi 3 % / Tahun

3 % x 3,000,000.00 = Rp. 120.00 750

Sub. Total = Rp. 1,333.96 B. BIAYA OPERASI

Kebutuhan Bahan Bakar dan Pelumas tiap HP

Diesel = 0.158 liter/HP/JamBensin = 0.167 liter/HP/JamPelumas = 0.006 liter/HP/Jam

Harga : Diesel = 2,100.00 per literBensin = 2,400.00 per literPelumas = 17,000.00 per liter

Bahan Bakar 0.158 x 2,100.00 x 8.00 = Rp. 2,654.40 Pelumas 0.006 x 17,000.00 x 8.00 = Rp. 816.00 Perbaikan/Spare parts 0.600 x 1,213.96 = Rp. 728.38

Sub. Total = Rp. 4,198.78

Total Biaya Pemilikan dan Operasi Alat : A + B = Rp. 5,532.74 per jam

DIREKTORAT JENDERAL BINA MARGA BIAYA ALAT UNTUK PERHITUNGANDIREKTORAT BINA PROGRAM JALAN ANALISA BIAYA PERALATAN KODE

SUB.DIT.PERENCANAAN JALAN E.082LOKAL DAN KABUPATEN VIBRATOR ROLLER

PROPINSI KODE KOTA KODE DISIAPKAN OLEH TanggalSULAWESI SELATAN 73 MAKASSAR CV. SYAFITRI Eng. Juli 2005

JENIS ALAT VIBRATOR ROLLER TENAGA 70.00 HP HARGA Rp. 125,000,000.00 UMUR KERJA 8 Tahun = 12,000 Jam Faktor CRF 0.20483

1 Tahun = 1,500 Jam kerja pada 12,5 %1 hari = Jam kerja

A. BIAYA PEMILIKAN : (Rp./Jam)1. Depresiasi : 90 % Harga Alat =

90 % x 125,000,000.00 x 0.20483 = Rp. 15,362.25 1,500

2. Lain-lain :

Page 96: Kor Training Centre

Asuransi 3 % / Tahun3 % x 125,000,000.00 = Rp. 2,500.00

1,500 Sub. Total = Rp. 17,862.25

B. BIAYA OPERASI

Kebutuhan Bahan Bakar dan Pelumas tiap HP

Diesel = 0.158 liter/HP/JamBensin = 0.167 liter/HP/JamPelumas = 0.006 liter/HP/Jam

Harga : Diesel = 2,100.00 per literBensin = 2,400.00 per literPelumas = 17,000.00 per liter

Bahan Bakar 0.158 x 2,100.00 x 70.00 = Rp. 23,226.00 Pelumas 0.006 x 17,000.00 x 70.00 = Rp. 7,140.00 Perbaikan/Spare parts 0.600 x 15,362.25 = Rp. 9,217.35

Sub. Total = Rp. 39,583.35

Total Biaya Pemilikan dan Operasi Alat : A + B = Rp. 57,445.60 per jam

Page 97: Kor Training Centre
Page 98: Kor Training Centre
Page 99: Kor Training Centre
Page 100: Kor Training Centre
Page 101: Kor Training Centre
Page 102: Kor Training Centre
Page 103: Kor Training Centre

DAFTAR HARGA SATUAN PEMBANGUNAN GEDUNG SIDRAP CENTER DI MAKASSAR

TAHUN ANGGARAN 2005

A. PERALATAN

No NAMA ALAT KODE BIAYA SATUAN

1 BULLDOZER 110 HP E 001 Rp 272,408.80 /jam

2 MESIN GILAS 3 RODA (6 - 8 Ton) E 080 Rp 93,472.02 /jam

3 MESIN GILAS BERGETAR (6 - 7 Ton) E 082 Rp 96,521.78 /jam

4 TRUCK TANGKI AIR (115 HP) E 182 Rp 220,138.06 /jam

B. B A H A N

No NAMA BAHAN/MATERIAL KODE HARGA SATUAN

1 TIMBUNAN PILIHAN M 050 Rp 29,624.00 /M3

2 ALAT BANTU M 170 Rp 100,000.00 Set

C. U P A H

No URAIAN KODE HARGA SATUAN

1 MANDOR L 061 Rp 33,600.00 /Hari

2 OPERATOR TERAMPIL L 081 Rp 39,200.00 /Hari

3 PEMBANTU OPERATOR L 083 Rp 30,800.00 /Hari

4 SOPIR TERAMPIL L 091 Rp 36,400.00 /Hari

5 PEMBANTU SOPIR L 099 Rp 28,000.00 /Hari

6 BURUH TAK TERAMPIL L 101 Rp 22,400.00 /Hari