Basement : Pekerjaan Acian Dinding Bata Ringan (Mortar MM-300)
Luas dinding = 1315,9 m2
Luas Acian = 2 sisi x 1315,9 m2 = 2.631,9 m2
Bobot = Harga pekerjaan acian : Harga total keseluruhan pekerjaan
= Rp 96.590.358 : Rp 10.901.966.271
= 0,00886
Minggu 1
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = 197,4 m2 (Rp 7.244.276)
Progres Pekerjaan = (197,4 : 2.631,9 ) x 100 = 7,5 %
Bobot Pekerjaan = Rp 7.244.276 : Rp 10.901.966.271 = 0,0007
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
0% - 7,5 % 0,0007 7,5 % 0,0007
Minggu 2
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = 65,8 m2 (Rp 2.414.759) Progres Pekerjaan = (65,8 : 2.631,9 ) x 100 = 2,5 %
Bobot Pekerjaan = Rp 2.414.759 : Rp 10.901.966.271 = 0,0002
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
7,5% 0,0007 2,5 % 0,0002 10 % 0,0009
Minggu 3
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = 131,6 m2 (Rp 4.829.518) Progres Pekerjaan = (131,6 : 2.631,9 ) x 100 = 5 %
Bobot Pekerjaan = Rp 4.829.518 : Rp 10.901.966.271 = 0,0004
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
10% 0,0009 5 % 0,0004 15 % 0,0013
Minggu 4
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = 394,8 m2 (Rp 14.488.553) Progres Pekerjaan = (394,8 : 2.631,9 ) x 100 = 15 %
Bobot Pekerjaan = Rp 14.488.553 : Rp 10.901.966.271 = 0,0013
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
15% 0,0013 15 % 0,0013 30 % 0,0026
Minggu 5
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = -
Progres Pekerjaan = -
Bobot Pekerjaan = -
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I BOBOT PRESTASI
%BOBOT PRESTASI
%BOBOT
%30% 0,0026 0 % - 30 % 0,0026
Minggu 6
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = 684,3 m2 (Rp 25.113.493) Progres Pekerjaan = (684,3 : 2.631,9 ) x 100 = 26 %
Bobot Pekerjaan = Rp 25.113.493 : Rp 10.901.966.271 = 0,0023
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
30% 0,0026 26 % 0,0023 56 % 0,0049
Minggu 7
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = 52,6 m2 (Rp 1.931.807) Progres Pekerjaan = (52,6 : 2.631,9 ) x 100 = 2%
Bobot Pekerjaan = Rp 1.931.807 : Rp 10.901.966.271 = 0,0002
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
56% 0,0049 2 % 0,0002 58% 0,0051
Minggu 8
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = -
Progres Pekerjaan = -
Bobot Pekerjaan = -
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUAL
PRESTASI
%BOBOT PRESTASI
% BOBOT PRESTASI % BOBOT
58% 0,0051 0 % - 58% 0,0051
Minggu 9
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = -
Progres Pekerjaan = -
Bobot Pekerjaan = -
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
58% 0,0051 0 % - 58% 0,0051
Minggu 10
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = -
Progres Pekerjaan = -
Bobot Pekerjaan = -
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
58% 0,0051 0 % - 58% 0,0051
Minggu 11
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = 131,6 m2 (Rp 4.829.518) Progres Pekerjaan = (131,6 : 2.631,9 ) x 100 = 5%
Bobot Pekerjaan = Rp 4.829.518 : Rp 10.901.966.271 = 0,0004
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
56% 0,0049 5 % 0,0004 61% 0,0054
Minggu 12
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = 148,5 m2 (Rp 5.450.983)
Progres Pekerjaan = (148,5 : 2.631,9 ) x 100 = 5,6%
Bobot Pekerjaan = Rp 4.829.518 : Rp 10.901.966.271 = 0,0005
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
61% 0,0054 5,6 % 0,0005 66% 0,0063
Minggu 13
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = -
Progres Pekerjaan = -
Bobot Pekerjaan = -
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
66% 0,0063 0 % - 66% 0,0063
Minggu 14
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = 103,9 m2 (Rp 3.815.688) Progres Pekerjaan = (103,9 : 2.631,9 ) x 100 = 4%
Bobot Pekerjaan = Rp 3.815.688 : Rp 10.901.966.271 = 0,0004
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
66% 0,0063 4 % 0,0005 70% 0,0068
Minggu 15
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = 130,7 m2 (Rp 4.796.865) Progres Pekerjaan = (130,7 : 2.631,9 ) x 100 = 5%
Bobot Pekerjaan = Rp 4.796.865 : Rp 10.901.966.271 = 0,00044
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
70% 0,0068 5 % 0,00044 75% 0,00724
Minggu 15
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = 116,9 m2 (Rp 4.251.767)
Progres Pekerjaan = (116,9 : 2.631,9 ) x 100 = 5%
Bobot Pekerjaan = Rp 4.251.767 : Rp 10.901.966.271 = 0,0004
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
75% 0,00724 5 % 0,0004 80% 0,008
Minggu 16
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = 131,6 m2 (Rp 4.829.518) Progres Pekerjaan = (131,6 : 2.631,9 ) x 100 = 5%
Bobot Pekerjaan = Rp 4.829.518 : Rp 10.901.966.271 = 0,0004
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
80% 0,008 5% 0,0004 95% 0,0084
Minggu 16
Volume total acian = 2.631,9 m2 (Rp 96.590.358)
Volume acian yg dikerjakan = 128,8 m2 (Rp 4.578.826) Progres Pekerjaan = (128,8 : 2.631,9 ) x 100 = 5%
Bobot Pekerjaan = Rp 4.578.826 : Rp 10.901.966.271 = 0,0004
SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI
AKTUALPRESTAS
I %
BOBOT PRESTASI % BOBOT PRESTASI
% BOBOT
95% 0,0084 5% 0,0004 100% 0,0088