Basement : Pekerjaan Acian Dinding Bata Ringan (Mortar MM-300) Luas dinding = 1315,9 m 2 Luas Acian = 2 sisi x 1315,9 m 2 = 2.631,9 m2 Bobot = Harga pekerjaan acian : Harga total keseluruhan pekerjaan = Rp 96.590.358 : Rp 10.901.966.271 = 0,00886 Minggu 1 Volume total acian = 2.631,9 m2 (Rp 96.590.358) Volume acian yg dikerjakan = 197,4 m2 (Rp 7.244.276) Progres Pekerjaan = (197,4 : 2.631,9 ) x 100 = 7,5 % Bobot Pekerjaan = Rp 7.244.276 : Rp 10.901.966.271 = 0,0007 SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI AKTUAL PRESTASI % BOBOT PRESTASI % BOBOT PRESTASI % BOBOT 0% - 7,5 % 0,000 7 7,5 % 0,0007 Minggu 2 Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Upload: dendi-krisyandana

Post on 20-Feb-2016

8 views

Category:

Documents


0 download

DESCRIPTION

basement

TRANSCRIPT

Page 1: Basement

Basement : Pekerjaan Acian Dinding Bata Ringan (Mortar MM-300)

Luas dinding = 1315,9 m2

Luas Acian = 2 sisi x 1315,9 m2 = 2.631,9 m2

Bobot = Harga pekerjaan acian : Harga total keseluruhan pekerjaan

= Rp 96.590.358 : Rp 10.901.966.271

= 0,00886

Minggu 1

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = 197,4 m2 (Rp 7.244.276)

Progres Pekerjaan = (197,4 : 2.631,9 ) x 100 = 7,5 %

Bobot Pekerjaan = Rp 7.244.276 : Rp 10.901.966.271 = 0,0007

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

0% - 7,5 % 0,0007 7,5 % 0,0007

Minggu 2

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = 65,8 m2 (Rp 2.414.759) Progres Pekerjaan = (65,8 : 2.631,9 ) x 100 = 2,5 %

Bobot Pekerjaan = Rp 2.414.759 : Rp 10.901.966.271 = 0,0002

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

7,5% 0,0007 2,5 % 0,0002 10 % 0,0009

Page 2: Basement

Minggu 3

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = 131,6 m2 (Rp 4.829.518) Progres Pekerjaan = (131,6 : 2.631,9 ) x 100 = 5 %

Bobot Pekerjaan = Rp 4.829.518 : Rp 10.901.966.271 = 0,0004

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

10% 0,0009 5 % 0,0004 15 % 0,0013

Minggu 4

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = 394,8 m2 (Rp 14.488.553) Progres Pekerjaan = (394,8 : 2.631,9 ) x 100 = 15 %

Bobot Pekerjaan = Rp 14.488.553 : Rp 10.901.966.271 = 0,0013

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

15% 0,0013 15 % 0,0013 30 % 0,0026

Minggu 5

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = -

Progres Pekerjaan = -

Bobot Pekerjaan = -

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I BOBOT PRESTASI

%BOBOT PRESTASI

%BOBOT

Page 3: Basement

%30% 0,0026 0 % - 30 % 0,0026

Minggu 6

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = 684,3 m2 (Rp 25.113.493) Progres Pekerjaan = (684,3 : 2.631,9 ) x 100 = 26 %

Bobot Pekerjaan = Rp 25.113.493 : Rp 10.901.966.271 = 0,0023

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

30% 0,0026 26 % 0,0023 56 % 0,0049

Minggu 7

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = 52,6 m2 (Rp 1.931.807) Progres Pekerjaan = (52,6 : 2.631,9 ) x 100 = 2%

Bobot Pekerjaan = Rp 1.931.807 : Rp 10.901.966.271 = 0,0002

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

56% 0,0049 2 % 0,0002 58% 0,0051

Minggu 8

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = -

Progres Pekerjaan = -

Bobot Pekerjaan = -

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUAL

Page 4: Basement

PRESTASI

%BOBOT PRESTASI

% BOBOT PRESTASI % BOBOT

58% 0,0051 0 % - 58% 0,0051

Minggu 9

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = -

Progres Pekerjaan = -

Bobot Pekerjaan = -

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

58% 0,0051 0 % - 58% 0,0051

Minggu 10

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = -

Progres Pekerjaan = -

Bobot Pekerjaan = -

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

58% 0,0051 0 % - 58% 0,0051

Minggu 11

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = 131,6 m2 (Rp 4.829.518) Progres Pekerjaan = (131,6 : 2.631,9 ) x 100 = 5%

Bobot Pekerjaan = Rp 4.829.518 : Rp 10.901.966.271 = 0,0004

Page 5: Basement

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

56% 0,0049 5 % 0,0004 61% 0,0054

Minggu 12

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = 148,5 m2 (Rp 5.450.983)

Progres Pekerjaan = (148,5 : 2.631,9 ) x 100 = 5,6%

Bobot Pekerjaan = Rp 4.829.518 : Rp 10.901.966.271 = 0,0005

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

61% 0,0054 5,6 % 0,0005 66% 0,0063

Minggu 13

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = -

Progres Pekerjaan = -

Bobot Pekerjaan = -

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

66% 0,0063 0 % - 66% 0,0063

Minggu 14

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = 103,9 m2 (Rp 3.815.688) Progres Pekerjaan = (103,9 : 2.631,9 ) x 100 = 4%

Bobot Pekerjaan = Rp 3.815.688 : Rp 10.901.966.271 = 0,0004

Page 6: Basement

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

66% 0,0063 4 % 0,0005 70% 0,0068

Minggu 15

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = 130,7 m2 (Rp 4.796.865) Progres Pekerjaan = (130,7 : 2.631,9 ) x 100 = 5%

Bobot Pekerjaan = Rp 4.796.865 : Rp 10.901.966.271 = 0,00044

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

70% 0,0068 5 % 0,00044 75% 0,00724

Minggu 15

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = 116,9 m2 (Rp 4.251.767)

Progres Pekerjaan = (116,9 : 2.631,9 ) x 100 = 5%

Bobot Pekerjaan = Rp 4.251.767 : Rp 10.901.966.271 = 0,0004

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

75% 0,00724 5 % 0,0004 80% 0,008

Minggu 16

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = 131,6 m2 (Rp 4.829.518) Progres Pekerjaan = (131,6 : 2.631,9 ) x 100 = 5%

Page 7: Basement

Bobot Pekerjaan = Rp 4.829.518 : Rp 10.901.966.271 = 0,0004

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

80% 0,008 5% 0,0004 95% 0,0084

Minggu 16

Volume total acian = 2.631,9 m2 (Rp 96.590.358)

Volume acian yg dikerjakan = 128,8 m2 (Rp 4.578.826) Progres Pekerjaan = (128,8 : 2.631,9 ) x 100 = 5%

Bobot Pekerjaan = Rp 4.578.826 : Rp 10.901.966.271 = 0,0004

SAMPAI DENGAN MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

AKTUALPRESTAS

I %

BOBOT PRESTASI % BOBOT PRESTASI

% BOBOT

95% 0,0084 5% 0,0004 100% 0,0088