tugas 4 metode konstruksi

13
SI3151 MANAJEMEN KONSTRUKSI TUGAS 4 Amira Maryana 15012025 PROGRAM STUDI TEKNIK SIPIL FAKULTAS TEKNIK SIPIL DAN LINGKUNGAN INSTITUT TEKNOLOGI BANDUNG

Upload: amira-maryana

Post on 08-Dec-2015

15 views

Category:

Documents


3 download

DESCRIPTION

Tugas 4 Metode Kosntruksi ITB 2012

TRANSCRIPT

Page 1: Tugas 4 Metode Konstruksi

SI3151

MANAJEMEN KONSTRUKSI

TUGAS 4

Amira Maryana

15012025

PROGRAM STUDI TEKNIK SIPIL

FAKULTAS TEKNIK SIPIL DAN LINGKUNGAN

INSTITUT TEKNOLOGI BANDUNG

2014

LATIHAN 1

Page 2: Tugas 4 Metode Konstruksi

Kegiatan Durasi (D) Predecessor Successor

A 10 - B

B 2 A C

C 10 B,E -

D 5 - F,E

E 9 D C

F 9 D I

G 4 - H

H 12 G I

I 7 H,F -

Berdasarkan tabel tersebut, buatlah suatu diagram CPM dan tentukanlah nilai ES,EF, LS,

LF, Total Float, Free Float untuk masing-masing kegiatan.

Buat pula Barchart berdasarakan Early Event dan Late Event

Jawaban:

Tabel Perhitungan CPM

KegiatanDurasi (D) Early Event Late Event Float

Nama i - j ES EF LS LF TF FFA 1 -- 2 10 0 10 2 12 2 0B 2 -- 5 2 10 12 12 14 2 2C 5 -- 7 10 14 24 14 24 0 0D 1 -- 3 5 0 5 0 5 0 0E 3 -- 5 9 5 14 5 14 0 0F 3 -- 6 9 5 14 8 17 3 2G 1 -- 4 4 0 4 1 5 1 0H 4 -- 6 12 4 16 5 17 1 0I 6 -- 7 7 16 23 17 24 1 1

Pada diagram CPM, terdapat jalur yang berwarna merah. Jalur yang berwarna merah

merupakan jalur kritis. Jalur kritis adalah jalur yang memiliki nilai TF = 0, yang berarti kegiatan

yang dilakukan pada jalur tersebut tidak boleh terlambat karena jika dilakukan terlambat,

proyek keseluruhan juga akan terlambat.

Page 3: Tugas 4 Metode Konstruksi

Diagram CPM

Page 4: Tugas 4 Metode Konstruksi

Barchart berdasarkan Early Event dan Late Event

Kegiatan Durasi 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

A 10

B 2

C 10

D 5

E 9

F 9

G 4

H 12

I 7

Early Event 3 3 3 3 3 4 4 4 4 4 4 4 3 3 2 2 2 2 2 2 2 2 2 1Akumulasi 3 6 9 12 15 19 23 27 31 35 39 43 46 49 51 53 55 57 59 61 63 65 67 68Late Event 1 2 3 3 3 3 3 3 4 4 4 4 4 4 3 3 3 2 2 2 2 2 2 2Akumulasi 1 3 6 9 12 15 18 21 25 29 33 37 41 45 48 51 54 56 58 60 62 64 66 68

-12

-2

8

18

28

38

48

58

68

Early Event

Late Event

Page 5: Tugas 4 Metode Konstruksi

LATIHAN 2

No Nama Kegiatan Durasi (D) Konstrain

1 Project Start 0 -

10 A 3 FS (1-10) = 0

20 B 4 FS (1-20) = 0

30 C 2 FS (10-30) = 1

40 D 2 FS (20-40) = 0

FF (30-40) = 3

50 E 4 FS (20-50) = 0

60 F 6 SS (50-60) = 2

70 G 3 FS (60-70) = 0

80 H 6 FS (40-80) = 0

FS (50-80) = 0

SF (70-80) = 1

90 I 2 FS (80-90) = 0

100 Project Complete 0 FS (90-100) = 0

FS (70-100) = 0

Buatlah diagram PDM dan hitunglah ES, EF, LS, dan LF.

Dan buat juga barchart untuk early dan late eventnya.

Jawaban:

Tabel Perhitungan PDM

Page 6: Tugas 4 Metode Konstruksi

No Nama Kegiatan Durasi (D) Konstrain

Early Event Late EventES EF LS LF

1 Project Start 0 - 0 0 0 010 A 3 FS (1-10) = 0 0 3 0 320 B 4 FS (1-20) = 0 0 4 1 530 C 2 FS (10-30) = 1 4 6 4 6

40 D 2FS (20-40) = 0

7 9 7 9FF (30-40) = 3

50 E 4 FS (20-50) = 0 4 8 5 960 F 6 SS (50-60) = 2 6 12 8 1470 G 3 FS (60-70) = 0 12 15 14 17

80 H 6FS (40-80) = 0

9 15 9 15FS (50-80) = 0SF (70-80) = 1

90 I 2 FS (80-90) = 0 15 17 15 17

100 Project Finish 0FS (90-100) = 0

17 17 17 17FS (70-100) = 0

Page 7: Tugas 4 Metode Konstruksi

Diagram PDM

Page 8: Tugas 4 Metode Konstruksi

Barchart berdasarkan Early Event dan Late Event

Kegiatan Durasi 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Project Start 0

A 3

B 4

C 2

D 2

E 4

F 6

G 3

H 6

I 2

Project Finish 0

Early Event 2 2 2 1 2 2 2 3 2 2 2 2 2 2 2 1 1Akumulasi 2 4 6 7 9 11 13 16 18 20 22 24 26 28 30 31 32Late Event 1 2 2 1 2 2 1 2 3 2 2 2 2 2 2 2 2Akumulasi 1 3 5 6 8 10 11 13 16 18 20 22 24 26 28 30 32

0

4

8

12

16

20

24

28

32

Early EventLate Event