2
1 2 3 4 5 6 A BIAYA LANGSUNG PERSONIL I TENAGA AHLI 1 Team Leader 1 x 5 - 2 Quantity Engineer 1 x 5 - 3 Quality Engineer 1 x 5 - Jumlah I - II TENAGA PENDUKUNG 1 Inspector 2 x 5 - 2 Surveyor 1 x 5 - 3 Operator Komputer 1 x 5 - Jumlah II - JUMLAH TOTAL A (I + II) - 1 2 3 4 5 6 B BIAYA LANGSUNG NON PERSONIL I BIAYA MOBILISASI & DEMOBILISASI 1 Mobilisasi & Demobilisasi Personil Orang/Trip 3 x 1 - Jumlah I - II SEWA PERALATAN 1 Sewa Komputer + Printer unit/bulan 2 x 5 - 2 Sewa Kantor Kerja dan Furniture unit/bulan 1 x 5 - 3 Sewa Motor + BBM unit/bulan 5 x 5 - Jumlah II - III BUKU PELAPORAN 1 Laporan Harian/Mingguan set 5 x 20 - 2 Laporan Bulanan set 5 x 5 - 3 Laporan Akhir set 5 x 1 - Jumlah III - IV KOMUNIKASI 1 Telepon/Fax unit/bulan 1 x 5 - 2 Alat Kantor lot/bulan 1 x 5 - Jumlah IV - JUMLAH TOTAL B (I + II + III + IV) - RENCANA ANGGARAN BIAYA JASA KONSULTANSI PENGAWASAN LANJUTAN PEKERJAAN TANAH DI BANDARA MOROWALI NO URAIAN PEKERJAAN KLASIFIKASI VOLUME/ MAN MONTH HARGA SATUAN JUMLAH BIAYA NO URAIAN PEKERJAAN KLASIFIKASI VOLUME HARGA SATUAN JUMLAH BIAYA

Upload: lukman-sugiarto

Post on 06-Nov-2015

9 views

Category:

Documents


0 download

TRANSCRIPT

  • 1 2 3 4 5 6

    A BIAYA LANGSUNG PERSONIL

    I TENAGA AHLI

    1 Team Leader 1 x 5 -

    2 Quantity Engineer 1 x 5 -

    3 Quality Engineer 1 x 5 -

    Jumlah I -

    II TENAGA PENDUKUNG

    1 Inspector 2 x 5 -

    2 Surveyor 1 x 5 -

    3 Operator Komputer 1 x 5 -

    Jumlah II -

    JUMLAH TOTAL A (I + II) -

    1 2 3 4 5 6

    B BIAYA LANGSUNG NON PERSONIL

    I BIAYA MOBILISASI & DEMOBILISASI

    1 Mobilisasi & Demobilisasi Personil Orang/Trip 3 x 1 -

    Jumlah I -

    II SEWA PERALATAN

    1 Sewa Komputer + Printer unit/bulan 2 x 5 -

    2 Sewa Kantor Kerja dan Furniture unit/bulan 1 x 5 -

    3 Sewa Motor + BBM unit/bulan 5 x 5 -

    Jumlah II -

    III BUKU PELAPORAN

    1 Laporan Harian/Mingguan set 5 x 20 -

    2 Laporan Bulanan set 5 x 5 -

    3 Laporan Akhir set 5 x 1 -

    Jumlah III -

    IV KOMUNIKASI

    1 Telepon/Fax unit/bulan 1 x 5 -

    2 Alat Kantor lot/bulan 1 x 5 -

    Jumlah IV -

    JUMLAH TOTAL B (I + II + III + IV) -

    RENCANA ANGGARAN BIAYA

    JASA KONSULTANSI PENGAWASAN

    LANJUTAN PEKERJAAN TANAH

    DI BANDARA MOROWALI

    NO URAIAN PEKERJAAN KLASIFIKASIVOLUME/

    MAN MONTHHARGA SATUAN JUMLAH BIAYA

    NO URAIAN PEKERJAAN KLASIFIKASI VOLUME HARGA SATUAN JUMLAH BIAYA

  • REKAPITULASI :

    A BIAYA LANGSUNG PERSONIL

    I TENAGA AHLI -

    II TENAGA PENDUKUNG -

    JUMLAH A -

    B BIAYA LANGSUNG NON PERSONIL

    I BIAYA MOBILISASI & DEMOBILISASI -

    II SEWA PERALATAN -

    III BUKU PELAPORAN -

    IV KOMUNIKASI -

    JUMLAH B -

    JUMLAH (A+B) -

    PPN 10% -

    JUMLAH TOTAL -

    DIBULATKAN -

    Terbilang :

    RENCANA ANGGARAN BIAYA

    JASA KONSULTANSI PENGAWASAN

    LANJUTAN PEKERJAAN TANAH

    DI BANDARA MOROWALI