    NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

    A. Pekerjaan Struktur BawahA.1. Pekerjaan Tanah

    1 Galian Tanah Pondasi m3

    45,57 48.969,93Rp 2.231.363,92Rp

    2 Bowplank m' 52,00 63.395,32Rp 3.296.556,81Rp

    A.2. Pekerjaan Pondasi, Sloof & Lantai

    1 Pekerjaan Pondasi Batu Kali m3

    10,43 596.748,64Rp 6.221.104,62Rp

    2 Pekerjaan Tie Beam / Sloof

    - Beton (K-175) m3

    1,99 957.677,13Rp 1.903.383,29Rp

    - Besi Tulangan

    - Besi f 8 mm kg 73,16 9.401,00Rp 687.814,68Rp- Besi f 12 mm kg 231,78 9.447,20Rp 2.189.638,68Rp

    - Bekisting 15/20 m2

    38,09 82.111,27Rp 3.127.413,02Rp

    3 Pekerjaan Lantai Dasar tebal = 5 cm

    - Beton m3

    2,60 1.088.269,46Rp 2.829.500,61Rp

    B. Pekerjaan Struktur LT.Dasar

    B1. Pekerjaan Kolom, Balok, list beton dan Dinding

    1 Pekerjaan struktur Kolom 15/35

    - Beton (K-175) m3

    0,79 957.677,13Rp 754.170,74Rp

    - Besi Tulangan

    - Besi f 8 mm kg 62,97 9.401,00Rp 592.027,36Rp

    - Besi D13 mm (4bh) + D10 mm ( 4bh) kg 182,33 9.401,00Rp 1.714.099,48Rp

    - Bekisting 15/35 m2

    23,63 63.395,32Rp 1.497.714,51Rp

    2 Pekerjaan struktur Kolom 15/15

    - Beton (K-175) m3

    1,47 957.677,13Rp 1.407.785,38Rp

    - Besi Tulangan

    - Besi f 8 mm kg 62,97 9.401,00Rp 592.027,36Rp

    - Besi f 12 mm kg 122,01 9.401,00Rp 1.146.981,06Rp

    - Bekisting 15/15 m2

    15,13 82.111,27Rp 1.241.932,97Rp

    3 Pekerjaan struktur Balok

    - Beton (K-175) m3

    3,21 957.677,13Rp 3.074.143,58Rp

    - Besi Tulangan

    - Besi f 8 mm kg 119,64 9.401,00Rp 1.124.765,43Rp

    - Besi f 12 mm kg 376,30 9.401,00Rp 3.537.636,37Rp

    - Bekisting 15/20 m2

    27,34 82.111,27Rp 2.244.511,58Rp

    4 Pekerjaan Pasangan Dinding Bata merah m2

    176,94 86.208,53Rp 15.253.306,47Rp

    B.2. Pekerjaan Plat beton kanopi depan dan belakang

    - plat tebal 10 cm di talang belakang

    - Beton (K-175) m3

    3,99 957.677,13Rp 3.817.684,10Rp

    RENCANA ANGGARAN BIAYA (R.A.B)

    ANALISA HARGA RUMAH TIPE 65

  • 8/17/2019 RAB TIPE 65 (b)

    2/4

  • 8/17/2019 RAB TIPE 65 (b)

    3/4

    NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

    RENCANA ANGGARAN BIAYA (R.A.B)

    ANALISA HARGA RUMAH TIPE 65

    - J3 bh 2,00 748.000,00Rp 1.496.000,00Rp

    - J4 bh 1,00 1.320.000,00Rp 1.320.000,00Rp- BV bh 1,00 396.000,00Rp 396.000,00Rp

    B3. Pekerjaan Pengecetan

    - Cat Exterior dinding depan dan belakang,acrylic kualitas Weathershield m2

    5,34 39.600,00Rp 211.582,80Rp

    - Cat Interior dinding dalam, jenis Emulsi Acrylic kualitas I m2

    241,94 24.200,00Rp 5.854.827,00Rp

    - Cat water proofing liquit ex sika didak atap dan semua atas kanopi m2

    16,84 48.400,00Rp 815.056,00Rp

    B4. Pekerjaan Atap + plafond

    1 Rangka Kuda - Kuda profil baja ringan T=0.85mm m3

    46,80 114.400,00Rp 5.353.920,00Rp

    2 Luas Bidang Penutup Atap Ex.Kanmuri m2

    46,80 182.160,00Rp 8.525.088,00Rp3 Listplank dari woodplank m' 12,00 35.640,00Rp 427.680,00Rp

    4 plafond gypsum dalam m2

    65,00 74.800,00Rp 4.862.000,00Rp

    5 Plafond grc board luar m2

    8,01 92.400,00Rp 739.754,40Rp

    6 list plafond dalam 7 cm m' 57,50 11.000,00Rp 632.500,00Rp

    B5. Pekerjaan Railing

    1 Pasang Railing tangga hollow fin.cat duko H 20.40 medium 2.1 m2

    4,20 1.056.000,00Rp 4.435.200,00Rp

    2 Pasang Railing balkon hollow fin.cat duko H 20.40 medium 2.1 m2

    5,40 1.056.000,00Rp 5.702.400,00Rp

    3 Pasang Railing balkon belakang hollow fin.cat duko H 20.40 medium 2.1 m2

    1,80 1.056.000,00Rp 1.900.800,00Rp

    C. Pekerjaan Mekanikal

    1 Shower tanam didinding + kran tanam setara san-ei bh 2,00 198.966,69Rp 397.933,38Rp

    2 Kloset Duduk ex.toto CW421J/SW420JP bh 2,00 2.200.000,00Rp 4.400.000,00Rp

    3 Floordrain setara san-ei bh 3,00 31.256,82Rp 93.770,45Rp

    4 Wastavel bh 1,00 572.000,00Rp 572.000,00Rp

    C1. Instalasi Air Bersih

    Sumur Dalam unit 1,00 1.056.000,00Rp 1.056.000,00Rp

    pipa pvc 1/2" ex.wavin lt 4,00 79.200,00Rp 316.800,00Rp

    pipa galvanise 1" lt 8,00 220.000,00Rp 1.760.000,00Rp

    knee 1/2" bh 16,00 13.200,00Rp 211.200,00Rp

    sambungan 1" bh 4,00 17.600,00Rp 70.400,00Rp

    sambunagn 1 1/2' bh 4,00 22.000,00Rp 88.000,00Rp

    kran bh 4,00 22.153,23Rp 88.612,91Rp

    lem bh 8,00 13.200,00Rp 105.600,00Rp

    solatip bh 4,00 8.800,00Rp 35.200,00Rp

    C2. Instalasi Air Kotor

    Buis Beton f 1 m - 0.5 m bh 4,00 440.000,00Rp 1.760.000,00Rp

    Buis Beton f 1 m - 1.0 m bh 4,00 440.000,00Rp 1.760.000,00Rp

    Plat Beton Bertulang f 1 m, t = 8 cm unit 4,00 704.000,00Rp 2.816.000,00Rp

    Lantai Beton Tumbuk t = 10 cm unit 4,00 957.677,13Rp 3.830.708,51Rp

    Bak Kontrol unit 4,00 440.000,00Rp 1.760.000,00Rp

    pipa pvc 4" ex.wavin lt 32,00 241.689,68Rp 7.734.069,73Rp

  • 8/17/2019 RAB TIPE 65 (b)

    4/4

    NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

    RENCANA ANGGARAN BIAYA (R.A.B)

    ANALISA HARGA RUMAH TIPE 65

    pipa pvc 3" ex.wavin lt 24,00 158.529,68Rp 3.804.712,29Rp

    sambungan T 4" lt 16,00 26.400,00Rp 422.400,00Rpsambungan T 3" lt 16,00 22.000,00Rp 352.000,00Rp

    sambungan knee 4" lt 32,00 7.700,00Rp 246.400,00Rp

    sambungan knee 3" lt 16,00 10.311,35Rp 164.981,58Rp

    sambungan lurus 4" lt 16,00 12.145,82Rp 194.333,15Rp

    sambungan lurus 3" lt 24,00 2.779,88Rp 66.717,19Rp

    Lem pvc bh 8,00 13.200,00Rp 105.600,00Rp

    isolatif bh 8,00 8.800,00Rp 70.400,00Rp

    D. Pekerjaan Elektrikal

    Titik Lampu led philip 12 watt downlight bh 12,00 65.319,04Rp 783.828,50RpStop kontak ex.philips bh 8,00 50.579,04Rp 404.632,33Rp

    Saklar Tunggal ex.philips bh 4,00 41.669,04Rp 166.676,17Rp

    Saklar Ganda ex.philips bh 6,00 46.421,04Rp 278.526,25Rp

    Kabel m 200,00 13.200,00Rp 2.640.000,00Rp

    Panel Kontrol Box Sekring/kwh meter unit 1,00 440.000,00Rp 440.000,00Rp

    E Pekerjaan Taman

    Tanam rumput gajah d halaman depan dan belakang m2

    18,60 30.800,00Rp 572.880,00Rp

    228.101.731,78GRAND TOTAL HARGA