NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
A. Pekerjaan Struktur BawahA.1. Pekerjaan Tanah
1 Galian Tanah Pondasi m3
45,57 48.969,93Rp 2.231.363,92Rp
2 Bowplank m' 52,00 63.395,32Rp 3.296.556,81Rp
A.2. Pekerjaan Pondasi, Sloof & Lantai
1 Pekerjaan Pondasi Batu Kali m3
10,43 596.748,64Rp 6.221.104,62Rp
2 Pekerjaan Tie Beam / Sloof
- Beton (K-175) m3
1,99 957.677,13Rp 1.903.383,29Rp
- Besi Tulangan
- Besi f 8 mm kg 73,16 9.401,00Rp 687.814,68Rp- Besi f 12 mm kg 231,78 9.447,20Rp 2.189.638,68Rp
- Bekisting 15/20 m2
38,09 82.111,27Rp 3.127.413,02Rp
3 Pekerjaan Lantai Dasar tebal = 5 cm
- Beton m3
2,60 1.088.269,46Rp 2.829.500,61Rp
B. Pekerjaan Struktur LT.Dasar
B1. Pekerjaan Kolom, Balok, list beton dan Dinding
1 Pekerjaan struktur Kolom 15/35
- Beton (K-175) m3
0,79 957.677,13Rp 754.170,74Rp
- Besi Tulangan
- Besi f 8 mm kg 62,97 9.401,00Rp 592.027,36Rp
- Besi D13 mm (4bh) + D10 mm ( 4bh) kg 182,33 9.401,00Rp 1.714.099,48Rp
- Bekisting 15/35 m2
23,63 63.395,32Rp 1.497.714,51Rp
2 Pekerjaan struktur Kolom 15/15
- Beton (K-175) m3
1,47 957.677,13Rp 1.407.785,38Rp
- Besi Tulangan
- Besi f 8 mm kg 62,97 9.401,00Rp 592.027,36Rp
- Besi f 12 mm kg 122,01 9.401,00Rp 1.146.981,06Rp
- Bekisting 15/15 m2
15,13 82.111,27Rp 1.241.932,97Rp
3 Pekerjaan struktur Balok
- Beton (K-175) m3
3,21 957.677,13Rp 3.074.143,58Rp
- Besi Tulangan
- Besi f 8 mm kg 119,64 9.401,00Rp 1.124.765,43Rp
- Besi f 12 mm kg 376,30 9.401,00Rp 3.537.636,37Rp
- Bekisting 15/20 m2
27,34 82.111,27Rp 2.244.511,58Rp
4 Pekerjaan Pasangan Dinding Bata merah m2
176,94 86.208,53Rp 15.253.306,47Rp
B.2. Pekerjaan Plat beton kanopi depan dan belakang
- plat tebal 10 cm di talang belakang
- Beton (K-175) m3
3,99 957.677,13Rp 3.817.684,10Rp
RENCANA ANGGARAN BIAYA (R.A.B)
ANALISA HARGA RUMAH TIPE 65
-
8/17/2019 RAB TIPE 65 (b)
2/4
-
8/17/2019 RAB TIPE 65 (b)
3/4
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
RENCANA ANGGARAN BIAYA (R.A.B)
ANALISA HARGA RUMAH TIPE 65
- J3 bh 2,00 748.000,00Rp 1.496.000,00Rp
- J4 bh 1,00 1.320.000,00Rp 1.320.000,00Rp- BV bh 1,00 396.000,00Rp 396.000,00Rp
B3. Pekerjaan Pengecetan
- Cat Exterior dinding depan dan belakang,acrylic kualitas Weathershield m2
5,34 39.600,00Rp 211.582,80Rp
- Cat Interior dinding dalam, jenis Emulsi Acrylic kualitas I m2
241,94 24.200,00Rp 5.854.827,00Rp
- Cat water proofing liquit ex sika didak atap dan semua atas kanopi m2
16,84 48.400,00Rp 815.056,00Rp
B4. Pekerjaan Atap + plafond
1 Rangka Kuda - Kuda profil baja ringan T=0.85mm m3
46,80 114.400,00Rp 5.353.920,00Rp
2 Luas Bidang Penutup Atap Ex.Kanmuri m2
46,80 182.160,00Rp 8.525.088,00Rp3 Listplank dari woodplank m' 12,00 35.640,00Rp 427.680,00Rp
4 plafond gypsum dalam m2
65,00 74.800,00Rp 4.862.000,00Rp
5 Plafond grc board luar m2
8,01 92.400,00Rp 739.754,40Rp
6 list plafond dalam 7 cm m' 57,50 11.000,00Rp 632.500,00Rp
B5. Pekerjaan Railing
1 Pasang Railing tangga hollow fin.cat duko H 20.40 medium 2.1 m2
4,20 1.056.000,00Rp 4.435.200,00Rp
2 Pasang Railing balkon hollow fin.cat duko H 20.40 medium 2.1 m2
5,40 1.056.000,00Rp 5.702.400,00Rp
3 Pasang Railing balkon belakang hollow fin.cat duko H 20.40 medium 2.1 m2
1,80 1.056.000,00Rp 1.900.800,00Rp
C. Pekerjaan Mekanikal
1 Shower tanam didinding + kran tanam setara san-ei bh 2,00 198.966,69Rp 397.933,38Rp
2 Kloset Duduk ex.toto CW421J/SW420JP bh 2,00 2.200.000,00Rp 4.400.000,00Rp
3 Floordrain setara san-ei bh 3,00 31.256,82Rp 93.770,45Rp
4 Wastavel bh 1,00 572.000,00Rp 572.000,00Rp
C1. Instalasi Air Bersih
Sumur Dalam unit 1,00 1.056.000,00Rp 1.056.000,00Rp
pipa pvc 1/2" ex.wavin lt 4,00 79.200,00Rp 316.800,00Rp
pipa galvanise 1" lt 8,00 220.000,00Rp 1.760.000,00Rp
knee 1/2" bh 16,00 13.200,00Rp 211.200,00Rp
sambungan 1" bh 4,00 17.600,00Rp 70.400,00Rp
sambunagn 1 1/2' bh 4,00 22.000,00Rp 88.000,00Rp
kran bh 4,00 22.153,23Rp 88.612,91Rp
lem bh 8,00 13.200,00Rp 105.600,00Rp
solatip bh 4,00 8.800,00Rp 35.200,00Rp
C2. Instalasi Air Kotor
Buis Beton f 1 m - 0.5 m bh 4,00 440.000,00Rp 1.760.000,00Rp
Buis Beton f 1 m - 1.0 m bh 4,00 440.000,00Rp 1.760.000,00Rp
Plat Beton Bertulang f 1 m, t = 8 cm unit 4,00 704.000,00Rp 2.816.000,00Rp
Lantai Beton Tumbuk t = 10 cm unit 4,00 957.677,13Rp 3.830.708,51Rp
Bak Kontrol unit 4,00 440.000,00Rp 1.760.000,00Rp
pipa pvc 4" ex.wavin lt 32,00 241.689,68Rp 7.734.069,73Rp
-
8/17/2019 RAB TIPE 65 (b)
4/4
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
RENCANA ANGGARAN BIAYA (R.A.B)
ANALISA HARGA RUMAH TIPE 65
pipa pvc 3" ex.wavin lt 24,00 158.529,68Rp 3.804.712,29Rp
sambungan T 4" lt 16,00 26.400,00Rp 422.400,00Rpsambungan T 3" lt 16,00 22.000,00Rp 352.000,00Rp
sambungan knee 4" lt 32,00 7.700,00Rp 246.400,00Rp
sambungan knee 3" lt 16,00 10.311,35Rp 164.981,58Rp
sambungan lurus 4" lt 16,00 12.145,82Rp 194.333,15Rp
sambungan lurus 3" lt 24,00 2.779,88Rp 66.717,19Rp
Lem pvc bh 8,00 13.200,00Rp 105.600,00Rp
isolatif bh 8,00 8.800,00Rp 70.400,00Rp
D. Pekerjaan Elektrikal
Titik Lampu led philip 12 watt downlight bh 12,00 65.319,04Rp 783.828,50RpStop kontak ex.philips bh 8,00 50.579,04Rp 404.632,33Rp
Saklar Tunggal ex.philips bh 4,00 41.669,04Rp 166.676,17Rp
Saklar Ganda ex.philips bh 6,00 46.421,04Rp 278.526,25Rp
Kabel m 200,00 13.200,00Rp 2.640.000,00Rp
Panel Kontrol Box Sekring/kwh meter unit 1,00 440.000,00Rp 440.000,00Rp
E Pekerjaan Taman
Tanam rumput gajah d halaman depan dan belakang m2
18,60 30.800,00Rp 572.880,00Rp
228.101.731,78GRAND TOTAL HARGA