REKAPITULASI PEKERJAAN KEGIATAN : Pembangunan/Rehabilitasi Fasilitas Gedung Pendidikan Dasar Sembilan Tahun PEKERJAAN : BIAYA PERENCANAAN NILAI PEKERJAAN 1M - 2M (PAKET 17) LOKASI : SDN KETINTANG IV Surabaya NO. URAIAN PEKERJAAN JUMLAH HARGA (Rp.) A PEKERJAAN LANTAI 1 I PEKERJAAN PENDAHULUAN 31,389,467.14 II PEKERJAAN TANAH 130,750,170.20 III PEKERJAAN PONDASI & BETON 990,903,469.35 IV PEKERJAAN PASANGAN & PLESTERAN 175,879,401.02 V PEKERJAAN KERAMIK 162,052,439.52 VI PEKERJAAN PLAFOND 43,342,067.02 VII PEKERJAAN PINTU DAN JENDELA DAN PENGUNCI 85,114,781.84 VIII PEKERJAAN SUNSCREEN, RAILLING TANGGA & SELASAR 15,935,501.79 IX PEKERJAAN PENGECATAN 41,088,286.72 X PEKERJAAN INSTALASI LISTRIK 33,436,145.40 XI PEKERJAAN SANITAIR & INSTALASI AIR 20,525,752.65 JUMLAH A 1,730,417,482.66 B PEKERJAAN LANTAI 2 I PEKERJAAN BETON 21,937,657.24 II PEKERJAAN PENGECATAN 14,093,149.58 III PEKERJAAN INSTALASI LISTRIK 114,189.10 IV PEKERJAAN SANITAIR & INSTALASI AIR 3,667,378.44 V PEKERJAAN LAIN-LAIN 1,950,000.00 JUMLAH B 41,762,374.36 JUMLAH TOTAL (A+B) 1,772,179,857.02 JUMLAH TOTAL 1,772,179,857.02 PPN 10% 177,217,985.70 NILAI PEKERJAAN 1,949,397,842.72 DIBULATKAN 1,949,397,000.00 Terbilang SATU MILYAR SEMBILAN RATUS EMPAT PULUH SEMBILAN JUTA TIGA RATUS SEMBILAN PULUH TUJUH RIBU Surabaya , Dibuat oleh : CV. MAKARYA ENGINEERING SHOLEHUDDIN, ST Direktur

Upload: vicky-syahrul

Post on 31-Jan-2016

305 views

Category:

Documents


9 download

DESCRIPTION

rab pemkot

TRANSCRIPT

Page 1: Rab Sd Petemon 12

REKAPITULASI PEKERJAAN

KEGIATAN : Pembangunan/Rehabilitasi Fasilitas Gedung Pendidikan Dasar Sembilan TahunPEKERJAAN : BIAYA PERENCANAAN NILAI PEKERJAAN 1M - 2M (PAKET 17)LOKASI : SDN KETINTANG IV Surabaya

NO. URAIAN PEKERJAAN JUMLAH HARGA (Rp.)

A PEKERJAAN LANTAI 1I PEKERJAAN PENDAHULUAN 31,389,467.14 II PEKERJAAN TANAH 130,750,170.20 III PEKERJAAN PONDASI & BETON 990,903,469.35 IV PEKERJAAN PASANGAN & PLESTERAN 175,879,401.02 V PEKERJAAN KERAMIK 162,052,439.52

VI PEKERJAAN PLAFOND 43,342,067.02 VII PEKERJAAN PINTU DAN JENDELA DAN PENGUNCI 85,114,781.84 VIII PEKERJAAN SUNSCREEN, RAILLING TANGGA & SELASAR 15,935,501.79 IX PEKERJAAN PENGECATAN 41,088,286.72 X PEKERJAAN INSTALASI LISTRIK 33,436,145.40 XI PEKERJAAN SANITAIR & INSTALASI AIR 20,525,752.65

JUMLAH A 1,730,417,482.66

B PEKERJAAN LANTAI 2I PEKERJAAN BETON 21,937,657.24 II PEKERJAAN PENGECATAN 14,093,149.58 III PEKERJAAN INSTALASI LISTRIK 114,189.10 IV PEKERJAAN SANITAIR & INSTALASI AIR 3,667,378.44 V PEKERJAAN LAIN-LAIN 1,950,000.00

JUMLAH B 41,762,374.36

JUMLAH TOTAL (A+B) 1,772,179,857.02

JUMLAH TOTAL 1,772,179,857.02 PPN 10% 177,217,985.70 NILAI PEKERJAAN 1,949,397,842.72 DIBULATKAN 1,949,397,000.00

Terbilang :SATU MILYAR SEMBILAN RATUS EMPAT PULUH SEMBILAN JUTA TIGA RATUS SEMBILAN PULUH TUJUH RIBU

Surabaya , Dibuat oleh :CV. MAKARYA ENGINEERING

SHOLEHUDDIN, STDirektur

Page 2: Rab Sd Petemon 12

RINCIAN PEKERJAAN

KEGIATAN : Pembangunan/Rehabilitasi Fasilitas Gedung Pendidikan Dasar Sembilan TahunPEKERJAAN : BIAYA PERENCANAAN NILAI PEKERJAAN 1M - 2M (PAKET 17)LOKASI : SDN KETINTANG IV Surabaya

NO. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA

1 2 4 5 6

A PEKERJAAN LANTAI 1

I PEKERJAAN PENDAHULUAN1 Pembongkaran Ruang Kelas, R.Guru (10 ruang) 1.00 ls 9,750,000.00 9,750,000.00 2 Pembongkaran Ruang Aula (1 ruang) 1.00 ls 9,750,000.00 9,750,000.00 3 Uitzet dan Pemasangan bowplank 114.00 m1 104,293.57 11,889,467.14

JUMLAH I 31,389,467.14

II PEKERJAAN TANAH1 Galian Tanah Konstruksi 48.72 m3 69,250.00 3,373,860.00 2 Galian Pondasi Bor Pile Ø40cm - 12m (Alat) 792.00 m1 101,125.40 80,091,316.80 3 Urugan Sirtu Padat 228.70 m3 185,200.00 42,355,240.00 4 Urugan Pasir Padat Bawah Pondasi 4.87 m3 177,700.00 865,754.40 5 Urugan Pasir Padat Bawah Rabat Keliling bangunan 22.87 m3 177,700.00 4,063,999.00

JUMLAH II 130,750,170.20

III PEKERJAAN PONDASI & BETON1 Rabat Beton Tebal 5 cm Bawah Pondasi & Sloof K175 7.54 m3 879,675.42 6,636,711.24 2 Rabat Beton Tebal 5 cm Bawah Lantai K175 22.87 m3 879,675.42 20,118,176.95 3 K250 99.48 m3 2,012,813.43 200,225,018.81 4 Poer P1 K250 20.06 m3 3,057,970.87 61,355,127.62 5 Poer P2 K250 13.09 m3 2,783,327.19 36,428,186.22 6 Poer P3 K250 1.94 m3 3,229,730.09 6,252,757.45 7 Poer P4 K250 3.89 m3 2,624,520.48 10,204,135.61 8 Sloof S1 25/50 K250 10.19 m3 3,377,651.41 34,409,823.76 9 Sloof S2 20/40 K250 3.70 m3 3,960,536.58 14,638,143.18

10 Sloof S3 20/35 K250 4.20 m3 3,909,789.40 16,421,115.46 11 Sloof S4 15/25 K250 2.96 m3 4,604,259.07 13,622,851.53 12 Kolom K1 30/40 K250 16.80 m3 4,114,707.56 69,127,086.94 13 Kolom K2 20/20 K250 2.40 m3 6,953,003.70 16,687,208.88 14 Kolom Praktis KP 12/12 K250 1.37 m3 5,906,246.12 8,079,744.69 15 Balok B1 30/60 K250 13.23 m3 3,968,839.81 52,507,750.62 16 Balok B1A 30/60 K250 1.35 m3 4,560,890.24 6,157,201.82 17 Balok B1B 30/60 K250 6.57 m3 4,264,865.02 28,020,163.19 18 Balok B2 20/40 K250 6.23 m3 5,123,175.28 31,927,628.35 19 Balok B3 20/35 K250 6.49 m3 4,700,592.31 30,518,595.54 20 Balok B4 15/25 K250 1.92 m3 4,829,530.13 9,296,241.81 21 Balok BK 25/50 K250 3.00 m3 5,032,972.20 15,098,916.59 22 Balok Latei BL 12/20 K250 1.40 m3 6,708,443.83 9,418,655.13 23 Balok Level BLV 12/20 K250 1.58 m3 7,217,237.17 11,432,103.67 24 Plat Level tebal 8 cm K250 1.41 m3 5,081,251.09 7,146,271.53 25 Plat Lantai tebal 12 cm Type A K250 18.26 m3 4,933,151.39 90,069,478.07 26 Plat Lantai tebal 12 cm Type B K250 35.09 m3 4,637,126.17 162,714,160.63 27 Plat Tangga K250 3.41 m3 6,559,120.59 22,390,214.03

JUMLAH IV 990,903,469.35

V PEKERJAAN PASANGAN & PLESTERAN1 Pasangan Dinding biasa 1/2 bata (1pc : 5ps) 508.39 m2 109,980.60 55,912,861.27 2 Pasangan Dinding Trasram 1/2 bata (1pc : 3ps) 54.34 m2 115,890.40 6,297,484.34 3 Plesteran Halus biasa (1pc : 5ps) 1,016.78 m2 54,746.28 55,664,747.39 4 Plesteran Halus trasram (1pc : 3ps) 108.68 m2 57,976.92 6,300,931.67 5 Acian Dinding 1,016.78 m2 33,605.00 34,168,784.36 6 Benangan 992.00 m1 17,676.00 17,534,592.00

JUMLAH V 175,879,401.02

Bor Pile Ø40cm - 12m

Page 3: Rab Sd Petemon 12

NO. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA

1 2 4 5 6

VI PEKERJAAN KERAMIK1 Lantai keramik 40 x 40 cm 309.43 m2 221,555.00 68,556,871.42 2 Lantai keramik 40 x 40 cm Tekstur Kasar (Lantai Trap Teras & Tangga) 113.04 m2 226,859.00 25,644,141.36 3 Plint keramik 10 x 40 cm 220.18 m1 28,032.80 6,172,261.90 4 Lantai keramik 30 x 30 cm Tekstur Kasar (Lantai KM) 30.07 m2 215,327.00 6,474,882.89 5 Keramik Dinding 30 x 60 cm (Dinding KM) 168.20 m2 328,214.00 55,204,281.94

JUMLAH VI 162,052,439.52

VII PEKERJAAN PLAFOND1 Pasang Plafon Kalsiboard 4 mm rangka Hollow 341.63 m2 112,561.69 38,454,450.50 2 Pasang List Plafond Gypsum 245.72 m2 19,891.00 4,887,616.52

JUMLAH VII 43,342,067.02

VIII PEKERJAAN PINTU DAN JENDELA DAN PENGUNCI1 Pas. Kusen Type PJ1 6.00 unit 4,500,314.46 27,001,886.74 3 Pas. Kusen Type PBV 2.00 unit 2,447,217.64 4,894,435.28 4 Pas. Kusen Type J1 15.00 unit 2,545,677.03 38,185,155.48 6 Pas. Kusen Type J2 2.00 unit 1,072,571.47 2,145,142.94 7 Pas. Kusen Type P1 6.00 unit 1,979,759.20 11,878,555.17 8 Pas. Kusen Type BV 3.00 unit 336,535.41 1,009,606.23

JUMLAH VIII 85,114,781.84

IX PEKERJAAN SUNSCREEN, RAILLING TANGGA & SELASAR1 Pas. Sunscreen 27.03 m1 485,916.00 13,134,309.48 2 Railing Tangga Besi Hollow 8.28 m2 338,308.25 2,801,192.31

JUMLAH IX 15,935,501.79

X PEKERJAAN PENGECATAN1 Cat Dinding Tembok Interior (Enamel/spotless) 503.00 m2 25,481.44 12,817,285.42 2 Cat Dinding Tembok Exterior (Weathershield) 491.02 m2 29,567.50 14,518,340.29 3 Cat Plafond Interior (Enamel/spotless) 341.63 m2 25,481.44 8,705,223.53 4 Cat Plafond Exterior (Weathershield) 99.20 m2 29,567.50 2,933,096.00 5 Cat Besi Railing Tangga 8.28 m2 63,214.00 523,411.92 6 Waterproofing Plat Level 52.32 m2 30,410.00 1,590,929.56

JUMLAH X 41,088,286.72

XI PEKERJAAN INSTALASI LISTRIK1 Instalasi Titik Lampu + fitting lampu 35.00 bh 215,330.00 7,536,550.00 2 Instalasi Titik Stop Kontak + Stop Kontak 23.00 bh 114,189.10 2,626,349.30 3 Pemasangan Saklar Tunggal 7.00 bh 32,439.10 227,073.70 4 Pemasangan Saklar Ganda 9.00 bh 41,539.10 373,851.90 5 Pemasangan Lampu TL Waterproof 2x36W 35.00 bh 592,791.00 20,747,685.00 6 Pemasangan Lampu SL 11 Watt & Downligth 4" 10.00 bh 105,291.00 1,052,910.00 7 Pemasangan Panel Box MCB 9 Modul 1.00 unit 871,725.50 871,725.50

JUMLAH XI 33,436,145.40

XII PEKERJAAN SANITAIR & INSTALASI AIR1 Pemasangan Pipa Air Bersih PVC Type AW Ø 3/4" 43.70 m1 17,122.20 748,240.14 2 Pemasangan Pipa Air Bersih PVC Type AW Ø 1" 15.00 m1 18,682.20 280,233.00 3 Pemasangan Pipa Air Kotor PVC Type D Ø 3" 73.50 m1 33,502.20 2,462,411.70 4 Pemasangan Pipa Air Kloset PVC Type D Ø 4" 27.00 m1 45,502.20 1,228,559.40 5 Kloset Jongkok 6.00 bh 721,415.00 4,328,490.00 6 Pasang Kran Air 6.00 bh 49,725.00 298,350.00 7 Pasang Avour 8.00 bh 34,225.00 273,800.00 8 Wastafel + Kran + Cermin 4.00 bh 823,255.00 3,293,020.00 9 Septic Tank Beton Kap. 3 m3 eks Fabrikan 1.00 Unit 3,600,000.00 3,600,000.00

10 Sumur Resapan 1.00 bh 3,045,923.41 3,045,923.41 11 Pompa elektric (kapasitas hisap 30m,dorong 30m ) 1.00 Unit 966,725.00 966,725.00

JUMLAH XII 20,525,752.65

JUMLAH A 1,730,417,482.66

Page 4: Rab Sd Petemon 12

NO. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA

1 2 4 5 6

B PEKERJAAN LANTAI 2

I PEKERJAAN BETON1 Kolom K1 30/40 Stek K175 4.37 m3 4,039,775.73 17,645,740.39 2 Kolom K2 20/20 Stek K175 0.62 m3 6,878,071.88 4,291,916.85

JUMLAH I 21,937,657.24 II PEKERJAAN PENGECATAN1 Waterproofing Plat Atap 463.44 m2 30,410.00 14,093,149.58

JUMLAH II 14,093,149.58

III PEKERJAAN INSTALASI LISTRIK1 Instalasi Titik Stop Kontak + Stop Kontak 1.00 bh 114,189.10 114,189.10

JUMLAH III 114,189.10

IV PEKERJAAN SANITAIR & INSTALASI AIR1 Pemasangan Pipa Air Bersih PVC Type AW Ø 3/4" 11.00 m1 17,122.20 188,344.20 2 Pemasangan Pipa Air Kotor PVC Type D Ø 3" 2.40 m1 33,502.20 80,405.28 3 Pemasangan Pipa Air Kloset PVC Type D Ø 4" 1.80 m1 45,502.20 81,903.96 4 Roof Tank 1200lt (Stainless) 1.00 Unit 2,350,000.00 2,350,000.00 5 Pompa Booster 1.00 Unit 966,725.00 966,725.00

JUMLAH IV 3,667,378.44

V PEKERJAAN LAIN-LAIN1 Pembersihan Akhir 1.00 ls 975,000.00 975,000.00 2 Pekerjaan Penutup Tangga Lt. 2 (Sementara) 1.00 ls 975,000.00 975,000.00

JUMLAH V 1,950,000.00

JUMLAH B 41,762,374.36

JUMLAH TOTAL (A+B) 1,772,179,857.02

Page 5: Rab Sd Petemon 12

RINCIAN PEKERJAAN

KEGIATAN : Pembangunan/Rehabilitasi Fasilitas Gedung Pendidikan Dasar Sembilan TahunPEKERJAAN : BIAYA PERENCANAAN NILAI PEKERJAAN 1M - 2M (PAKET 59)LOKASI : SDN KETINTANG IV Surabaya

NO. URAIAN PEKERJAAN PANJANG LEBAR TINGGI JUMLAH LUAS

1 2 3 4 5 6 7

I PEKERJAAN PENDAHULUAN Uitzet dan Pemasangan bowplank 82.2 31.8

II PEKERJAAN TANAH Galian Tanah Konstruksipoer 1 2.2 1.2 0.5 19poer 2 2.2 1.2 0.5 8

1.45 1 0.5 8

poer 3 2.2 2.2 0.5 1poer 4 0.9 0.9 0.5 12

Galian Pondasi Bor Pile Ø40cm - 12m (Alat) 12 66 Urugan Sirtu Padat 32.5 9 0.5

17 9.7 0.5

Urugan Pasir Padat Bawah Pondasi poer 1 2.2 1.2 0.05 19poer 2 2.2 1.2 0.05 8

1.45 1 0.05 8

poer 3 2.2 2.2 0.05 1poer 4 0.9 0.9 0.05 12

Urugan Pasir Padat Bawah Rabat Keliling bangunan 32.5 9 0.0517 9.7 0.05

PEKERJAAN PONDASI & BETON Rabat Beton Tebal 5 cm Bawah Pondasi & Sloof

Poer, P1,P2,P3,P4S1 melintang 49 0.25 0.05S1 memanjang 32.5 0.25 0.05S2 melintang 34 0.2 0.05S2 memanjang 12.2 0.2 0.05S3 memanjang 60 0.2 0.05S4 memanjang 42.7 0.15 0.05S4 melintang 36.2 0.15 0.05

Rabat Beton Tebal 5 cm Bawah Lantai32.5 9 0.05

17 9.7 0.05

Page 6: Rab Sd Petemon 12

Bor Pile Ø40cm - 12m 12 66 0.1256 Poer P1 2.2 1.2 0.4 19 Poer P2 2.2 1.2 0.4 8

1.45 1 0.4 8

Poer P3 2.2 2.2 0.4 1 Poer P4 0.9 0.9 0.4 12

Sloof S1 25/50S1 melintang 49 0.25 0.5S1 memanjang 32.5 0.25 0.5

Sloof S2 20/40S2 melintang 34 0.2 0.4S2 memanjang 12.2 0.2 0.4

Sloof S3 20/35S3 memanjang 60 0.2 0.35

Sloof S4 15/25S4 memanjang 42.7 0.15 0.25S4 melintang 36.2 0.15 0.25

Kolom K1 30/40 0.4 0.3 5 28 Kolom K2 20/20 0.2 0.2 5 12 Kolom Praktis KP 12/12 0.12 0.12 3.8 25 Balok B1 30/60

B1 Melintang 56 0.3 0.6B1 Memanjang 17.5 0.3 0.6

Balok B1A 30/60B1A Memanjang 7.5 0.3 0.6

Balok B1B 30/60B1B Melintang 14 0.3 0.6B1B Memanjang 22.5 0.3 0.6

Balok B2 20/40B2 Memanjang 26.9 0.2 0.4B2 Melintang 51 0.2 0.4

Balok B3 20/35B3 Memanjang 85.75 0.2 0.35B3 Melintang 7 0.2 0.35

Balok B4 15/25B4 Memanjang 32.5 0.15 0.25B4 Melintang 18.83 0.15 0.25

Balok BK 25/50BK Memanjang 6 0.25 0.5BK Melintang 18 0.25 0.5

Balok Latei BL 12/20BL Memanjang 32.5 0.12 0.2BL Melintang 26 0.12 0.2

Balok Level BLV 12/20

Page 7: Rab Sd Petemon 12

BLV Memanjang 40 0.12 0.2BLV Melintang 26 0.12 0.2

Plat Level tebal 8 cmJ1 2.3 0.6 0.08 11J3 0.8 0.6 0.08 2BV 0.8 0.6 0.08 3

Plat Lantai tebal 12 cm Type A 17 9.5 0.12factor pengurang (voide) 4.25 2.2 0.12

Plat Lantai tebal 12 cm Type B 32.5 9 0.12factor pengurang (shap) 0.44 0.2 0.12

Plat Tangga 7.75 1 0.12Bordes 2.05 1.6 0.12Anak Tangga 1 22 0.095

PEKERJAAN PASANGAN & PLESTERAN Pasangan Dinding biasa 1/2 bata (1pc : 5ps)

As 1, 2 17 4.2 2As 6, 8, 10, 12 7 4.2 4As 3, 4, 5 7 2.7 3As Toilet 4.4 1 2As A, A' 7.5 4.2 2As D, G 32.5 2.7 2As F 9.7 2.7 1As Toilet 1.5 1 6

Factor PengurangPJ1 6 4.876PBV 1.72 0.56 2

0.98 0.6 2J1 15 3.4352J3 2 1.1856P1 0.78 0.6 8 3.744BV 0.8 0.5 3 1.2

Pasangan Dinding Trasram 1/2 bata (1pc : 3ps)As 3, 4, 5 7 1.5 3As D, G 5 1.5 2As Toilet 4.4 1 2As Toilet 1.5 1 6

Factor PengurangP1 0.78 1.5 6 7.02PBV 0.98 1.5 2 2.94

Plesteran Halus biasa (1pc : 5ps) Plesteran Halus trasram (1pc : 3ps) Acian Dinding Benangan As 1 4 42

As 2 4 40As 3 4 12

Page 8: Rab Sd Petemon 12

1.5 21As 4 1.5 6As 5 4 17

1.5 29As 6 4 17As 7 4 16As 8 4 17As 9 4 16As 10 4 17As 11 4 16As 12 4 17

PEKERJAAN KERAMIK Lantai keramik 40 x 40 cm

Ruang Kelas 7.35 6.85 3perpus 7.35 4.85 1R.Komputer & kelas 7.35 8.35 2

Lantai keramik 40 x 40 cm Tekstur Kasar (Lantai Trap Teras & Tangga)teras 32.5 2

17.1 2Bordes 2.05 1.6Anak Tangga 0.48 1 22

Plint keramik 10 x 40 cm 221.74factor pengurang 1.56

Lantai keramik 30 x 30 cm Tekstur Kasar (Lantai KM) 14.8215.25

Keramik Dinding 30 x 60 cm (Dinding KM)17.6 2.5

toilet 6.22 2.5 618.4 2.5

Factor pengurang 0.78 2.1 80.8 0.5 5

PEKERJAAN PLAFOND Pasang Plafon Kalsiboard 4 mm rangka Hollow

Ruang Kelas 7.35 6.85 3perpus 7.35 4.85 1R.Komputer & kelas 7.35 8.35 2Toilet 2.35 6.85 2

Pasang List Plafond GypsumRuang Kelas 14.7 13.7 3perpus 14.7 9.7 1R.Komputer & kelas 14.7 16.7 2Toilet 17.6 18.4 1

6.22 6

PEKERJAAN PINTU DAN JENDELA DAN PENGUNCI

Page 9: Rab Sd Petemon 12

Pas. Kusen Type PJ1Kusen 4" Horisontal 6.44Kusen 4" Vertical 8.4Kusen Slimar 6.4Pintu Wpc L=90cm T=210cm 1Kisi-Kisi 1.23Kaca Bening 5mm 1.26

Pas. Kusen Type PJ2Kusen 4" Horisontal 7.84Kusen 4" Vertical 8.9Kusen Slimar 6.4Pintu Wpc L=90cm T=210cm 2Kisi-Kisi 1.58Kaca Bening 5mm 1.26

Pas. Kusen Type PBVKusen 4" Horisontal 3.47Kusen 4" Vertical 5.94Pintu Wpc L=90cm T=210cm 1Kisi-Kisi 0.86

Pas. Kusen Type J1Kusen 4" Vertical 6.08Kusen 4" Horisontal 6.78Kusen Slimar 9.6Kisi-Kisi 1.13Kaca Bening 5mm 1.89

Pas. Kusen Type J2Kusen 4" Vertical 4.56Kusen 4" Horisontal 4.56Kusen Slimar 6.4Kisi-Kisi 0.76Kaca Bening 5mm 1.26

Pas. Kusen Type J2Kusen 4" Vertical 3.04Kusen 4" Horisontal 2.34Kusen Slimar 3.2Kisi-Kisi 0.39Kaca Bening 5mm 0.63

Pas. Kusen Type P1Kusen 4" Vertical 4.2Kusen 4" Horisontal 0.78Pintu WPC L=70cm T=210cm 1

Pas. Kusen Type BVKusen 4" Vertical 1Kusen 4" Horisontal 1.6Kaca Bening 5mm 0.4

Pas. Sunscreen 3.55 0.85 62.8 0.85 12.7 0.85 13.3 0.85 11.7 0.85 1

Railing Tangga Besi Hollow 9.2 0.9PEKERJAAN PENGECATAN

Page 10: Rab Sd Petemon 12

Cat Dinding Tembok Interior (Enamel/spotless)Ruang Kelas 7.35 6.85 3.4 3perpus 7.35 4.85 3.4 1R.Komputer & kelas 7.35 8.35 3.4 2Factor PengurangPJ1 6 4.876J1 15 3.4352J3 2 1.1856

Cat Dinding Tembok Exterior (Weathershield)79 4

51.2 4Kolom K2 1.2 4 12

Factor PengurangPJ1 6 4.876J1 15 3.4352J3 2 1.1856BV 0.8 0.5 3PBV 1.72 0.56 1

0.98 2.1 1

Cat Plafond Exterior (Weathershield)Plafond Interior 341.63Plafond Exterior

teras 32.5 217.1 2

Cat Besi Railing Tangga Waterproofing Plat Level

Area Toilet 7 5Canoipy J1 2.26 0.6 11Canoipy J3 0.8 0.6 2Canopy BV 0.8 0.6 3

PEKERJAAN INSTALASI LISTRIK Instalasi Titik Lampu + fitting lampu 35 Instalasi Titik Stop Kontak + Stop Kontak 23 Pemasangan Saklar Tunggal 7 Pemasangan Saklar Ganda 9 Pemasangan Lampu TL Waterproof 2x36W 35 Pemasangan Lampu SL 11 Watt & Downligth 4" 10 Pemasangan Panel Box MCB 9 Modul 1

PEKERJAAN SANITAIR & INSTALASI AIR Pemasangan Pipa Air Bersih PVC Type AW Ø 3/4"

Up 11.2Down 32.5

Pemasangan Pipa Air Bersih PVC Type AW Ø 1" 15 Pemasangan Pipa Air Kotor PVC Type D Ø 3" 49.5

24

Page 11: Rab Sd Petemon 12

Pemasangan Pipa Air Kloset PVC Type D Ø 4" 27 Kloset Jongkok Pasang Kran Air Pasang Avour Wastafel + Kran + Cermin Urinoir + Sekat Septic Tank Beton Kap. 3 m3 eks Fabrikan Sumur ResapanPompa elektric (kapasitas hisap 30m,dorong 30m )

PEKERJAAN LANTAI 2PEKERJAAN BETON Kolom K1 30/40 Stek 0.4 0.3 4 28 Kolom K2 20/20 Stek 0.2 0.2 5 12 Kolom Praktis KP 12/12 0.12 0.12 3.8 25

Kolom K2 20/20 Stek Kolom Praktis KP 12/12 Balok B2 20/40 Balok B3 20/35 Balok B4 15/25 Balok RB1 25/50 Balok BK 25/50 Balok Latei BL 12/20 Balok Level BLV 12/20 Plat Level tebal 8 cm Plat Lantai tebal 12 cm

Page 12: Rab Sd Petemon 12

RINCIAN PEKERJAAN

TOTAL VOLUME

8 9

114 114

25.08 25.08

10.565.8

16.36 16.36

2.42 2.42

4.86 4.86

48.72

792 792 38

146.25 24

82.45 4

228.7 228.7 66

2.508 2.508

1.0560.58

1.636 1.636

0.242 0.242

0.486 0.486

4.872

14.6258.24522.87 22.87

4.8720.6125

0.406250.34

0.1220.6

0.320250.2715

7.5445

14.6258.24522.87 22.87

Page 13: Rab Sd Petemon 12

99.4752 99.4752

20.064 20.064

8.4484.64

13.088 13.088

1.936 1.936

3.888 3.888

6.1254.0625

10.1875 10.1875

2.720.9763.696 3.696

4.2 4.2

1.601251.3575

2.95875 2.95875

16.8 16.8

2.4 2.4

1.368 1.368

10.083.15

13.23 13.23

1.35 1.35

2.524.056.57 6.57

2.1524.08

6.232 6.232

6.00250.49

6.4925 6.4925

1.218750.7061251.924875 1.924875

0.752.25

3 3

0.780.6241.404 1.404

Page 14: Rab Sd Petemon 12

0.960.6241.584 1.584

1.21440.07680.11521.4064 1.4064

19.38 161.5

1.122 9.35

18.258 18.258 0 -18.25835.1 292.5

0.01056 0.088

35.08944 35.08944 463.438

0.930.3936

2.093.4136 3.4136

142.8117.6

56.78.863

175.526.19

9599.59

29.2561.92641.176

51.5282.37123.744

1.291.2016

508.3884

31.515

8.89

64.3

7.022.949.96

54.34

1016.7768 1016.7768

108.68 108.68

1016.7768 1016.7768

168160

48

Page 15: Rab Sd Petemon 12

31.59

6843.5

68646864686468

992 992

151.042535.6475122.745Err:522 Err:522

6534.23.28

10.56113.04 113.04

220.18 220.18

30.07 30.07

4493.3

46183.3

13.1042

15.104

168.196

151.042535.6475122.74532.195

341.63 341.63

85.224.462.8

3637.32

245.72 245.72

Page 16: Rab Sd Petemon 12

18.1052.38

2.2952.8051.44527.03 27.03

8.28 8.28

Page 17: Rab Sd Petemon 12

289.6882.96

213.52586.16

29.25651.5282.3712

83.1552

503.0048

316204.8

57.6578.4

29.25651.5282.3712

1.20.96322.058

87.3764

491.0236

341.63 341.63

6534.299.2 99.2

8.28 8.28

3514.916

0.961.44

52.316 52.316

11.232.543.7 43.7

15 15

49.524

Page 18: Rab Sd Petemon 12

73.5 73.5

27 27

6 6

6 6

8 8

4 4

0

1 1

1 1

1 1

13.44 13.44

2.4 2.4

1.368 1.368

Page 19: Rab Sd Petemon 12

RINCIAN PEKERJAAN

KEGIATAN : Pembangunan/Rehabilitasi Fasilitas Gedung Pendidikan Dasar Sembilan TahunPEKERJAAN : BIAYA PERENCANAAN NILAI PEKERJAAN 1M - 2M (PAKET 59)LOKASI : SDN KETINTANG IV Surabaya

NO. URAIAN PEKERJAAN PANJANG LEBAR TINGGI JUMLAH LUAS

1 2 3 4 5 6 7

PEKERJAAN LANTAI 2PEKERJAAN BETON

Kolom K1 30/40 0.4 0.3 1.3 28 Kolom K2 20/20 0.2 0.2 1.3 12 Kolom Praktis KP 12/12 0.12 0.12 3.8 25 Balok B1 30/60

B1 Melintang 56 0.3 0.6B1 Memanjang 17.5 0.3 0.6

Balok B1A 30/60B1A Memanjang 7.5 0.3 0.6

Balok B1B 30/60B1B Melintang 14 0.3 0.6B1B Memanjang 22.5 0.3 0.6

Balok B2 20/40B2 Memanjang 26.9 0.2 0.4B2 Melintang 51 0.2 0.4

Balok B3 20/35B3 Memanjang 85.75 0.2 0.35B3 Melintang 7 0.2 0.35

Balok B4 15/25B4 Memanjang 32.5 0.15 0.25B4 Melintang 18.83 0.15 0.25

Balok BK 25/50BK Memanjang 6 0.25 0.5BK Melintang 18 0.25 0.5

Balok Latei BL 12/20BL Memanjang 32.5 0.12 0.2BL Melintang 26 0.12 0.2

Balok Level BLV 12/20BLV Memanjang 40 0.12 0.2BLV Melintang 26 0.12 0.2

Plat Level tebal 8 cmJ1 2.3 0.6 0.08 11J3 0.8 0.6 0.08 2BV 0.8 0.6 0.08 3

Page 20: Rab Sd Petemon 12

Plat Lantai tebal 12 cm Type A 17 9.5 0.12factor pengurang (voide) 4.25 2.2 0.12

Plat Lantai tebal 12 cm Type B 32.5 9 0.12factor pengurang (shap) 0.44 0.2 0.12

Plat Tangga 7.75 1 0.12Bordes 2.05 1.6 0.12Anak Tangga 1 22 0.095

PEKERJAAN PASANGAN & PLESTERAN Pasangan Dinding biasa 1/2 bata (1pc : 5ps)

As 1, 2 17 4.2 2As 6, 8, 10, 12 7 4.2 4As 3, 4, 5 7 2.7 3As Toilet 4.4 1 2As A, A' 7.5 4.2 2As D, G 32.5 2.7 2As F 9.7 2.7 1As Toilet 1.5 1 6

Factor PengurangPJ1 6 4.876PBV 1.72 0.56 2

0.98 0.6 2J1 15 3.4352J3 2 1.1856P1 0.78 0.6 8 3.744BV 0.8 0.5 3 1.2

Pasangan Dinding Trasram 1/2 bata (1pc : 3ps)As 3, 4, 5 7 1.5 3As D, G 5 1.5 2As Toilet 4.4 1 2As Toilet 1.5 1 6

Factor PengurangP1 0.78 1.5 6 7.02PBV 0.98 1.5 2 2.94

Plesteran Halus biasa (1pc : 5ps) Plesteran Halus trasram (1pc : 3ps) Acian Dinding Benangan As 1 4 42

As 2 4 40As 3 4 12

1.5 21As 4 1.5 6As 5 4 17

1.5 29As 6 4 17As 7 4 16As 8 4 17

Page 21: Rab Sd Petemon 12

As 9 4 16As 10 4 17As 11 4 16As 12 4 17

PEKERJAAN KERAMIK Lantai keramik 40 x 40 cm

Ruang Kelas 7.35 6.85 3perpus 7.35 4.85 1R.Komputer & kelas 7.35 8.35 2

Lantai keramik 40 x 40 cm Tekstur Kasar (Lantai Trap Teras & Tangga)teras 32.5 2

17.1 2Bordes 2.05 1.6Anak Tangga 0.48 1 22

Plint keramik 10 x 40 cm 221.74factor pengurang 1.56

Lantai keramik 30 x 30 cm Tekstur Kasar (Lantai KM) 14.8215.25

Keramik Dinding 30 x 60 cm (Dinding KM)17.6 2.5

toilet 6.22 2.5 618.4 2.5

Factor pengurang 0.78 2.1 80.8 0.5 5

PEKERJAAN PLAFOND Pasang Plafon Kalsiboard 4 mm rangka Hollow

Ruang Kelas 7.35 6.85 3perpus 7.35 4.85 1R.Komputer & kelas 7.35 8.35 2Toilet 2.35 6.85 2

Pasang List Plafond GypsumRuang Kelas 14.7 13.7 3perpus 14.7 9.7 1R.Komputer & kelas 14.7 16.7 2Toilet 17.6 18.4 1

6.22 6

PEKERJAAN PINTU DAN JENDELA DAN PENGUNCIPas. Kusen Type PJ1

Kusen 4" Horisontal 6.44Kusen 4" Vertical 8.4Kusen Slimar 6.4Pintu Wpc L=90cm T=210cm 1Kisi-Kisi 1.23Kaca Bening 5mm 1.26

Page 22: Rab Sd Petemon 12

Pas. Kusen Type PJ2Kusen 4" Horisontal 7.84Kusen 4" Vertical 8.9Kusen Slimar 6.4Pintu Wpc L=90cm T=210cm 2Kisi-Kisi 1.58Kaca Bening 5mm 1.26

Pas. Kusen Type PBVKusen 4" Horisontal 3.47Kusen 4" Vertical 5.94Pintu Wpc L=90cm T=210cm 1Kisi-Kisi 0.86

Pas. Kusen Type J1Kusen 4" Vertical 6.08Kusen 4" Horisontal 6.78Kusen Slimar 9.6Kisi-Kisi 1.13Kaca Bening 5mm 1.89

Pas. Kusen Type J2Kusen 4" Vertical 4.56Kusen 4" Horisontal 4.56Kusen Slimar 6.4Kisi-Kisi 0.76Kaca Bening 5mm 1.26

Pas. Kusen Type J2Kusen 4" Vertical 3.04Kusen 4" Horisontal 2.34Kusen Slimar 3.2Kisi-Kisi 0.39Kaca Bening 5mm 0.63

Pas. Kusen Type P1Kusen 4" Vertical 4.2Kusen 4" Horisontal 0.78Pintu WPC L=70cm T=210cm 1

Pas. Kusen Type BVKusen 4" Vertical 1Kusen 4" Horisontal 1.6Kaca Bening 5mm 0.4

Pas. Sunscreen 3.55 0.85 62.8 0.85 12.7 0.85 13.3 0.85 11.7 0.85 1

Railing Tangga Besi Hollow 9.2 0.9PEKERJAAN PENGECATANCat Dinding Tembok Interior (Enamel/spotless)

Ruang Kelas 7.35 6.85 3.4 3perpus 7.35 4.85 3.4 1R.Komputer & kelas 7.35 8.35 3.4 2Factor PengurangPJ1 6 4.876J1 15 3.4352

Page 23: Rab Sd Petemon 12

J3 2 1.1856

Cat Dinding Tembok Exterior (Weathershield)79 4

51.2 4Kolom K2 1.2 4 12

Factor PengurangPJ1 6 4.876J1 15 3.4352J3 2 1.1856BV 0.8 0.5 3PBV 1.72 0.56 1

0.98 2.1 1

Cat Plafond Exterior (Weathershield)Plafond Interior 0Plafond Exterior

teras 32.5 217.1 2

Cat Besi Railing Tangga Waterproofing Plat Level

Area Toilet 7 5Canoipy J1 2.26 0.6 11Canoipy J3 0.8 0.6 2Canopy BV 0.8 0.6 3

PEKERJAAN INSTALASI LISTRIK Instalasi Titik Lampu + fitting lampu 35 Instalasi Titik Stop Kontak + Stop Kontak 19 Pemasangan Saklar Tunggal 7 Pemasangan Saklar Ganda 9 Pemasangan Lampu TL Waterproof 2x36W 35 Pemasangan Lampu SL 11 Watt & Downligth 4" 10 Pemasangan Panel Box MCB 9 Modul 1

PEKERJAAN SANITAIR & INSTALASI AIR Pemasangan Pipa Air Bersih PVC Type AW Ø 3/4"

Up 5.5Down 5.5

Pemasangan Pipa Air Bersih PVC Type AW Ø 1" 15 Pemasangan Pipa Air Kotor PVC Type D Ø 3" 2.4

Pemasangan Pipa Air Kloset PVC Type D Ø 4" 1.8 Kloset Jongkok Pasang Kran Air Pasang Avour Wastafel + Kran + Cermin Urinoir + Sekat

Page 24: Rab Sd Petemon 12

Septic Tank Beton Kap. 3 m3 eks Fabrikan Sumur ResapanRoof Tank 1200lt (Stainless)Pompa Booster

00

Page 25: Rab Sd Petemon 12

RINCIAN PEKERJAAN

TOTAL VOLUME

8 9

4.368 4.368

0.624 0.624

1.368

10.083.15

13.23

1.35

2.524.056.57

2.1524.08

6.232

6.00250.49

6.4925

1.218750.7061251.924875

0.752.25

3

0.780.6241.404

0.960.6241.584

1.21440.07680.1152

Page 26: Rab Sd Petemon 12

1.406419.381.122

18.258 -18.25835.1

0.0105635.08944

0.930.3936

2.093.4136

142.8117.6

56.78.863

175.526.19

9599.59

29.2561.92641.176

51.5282.37123.744

1.291.2016

31.515

8.89

64.3

7.022.949.96

000

168160

4831.5

968

43.5686468

Page 27: Rab Sd Petemon 12

64686468

992

151.042535.6475122.745Err:522

6534.23.28

10.56113.04

220.18

30.07

4493.3

46183.3

13.1042

15.104

151.042535.6475122.74532.195

341.63

85.224.462.8

3637.32

245.72

Page 28: Rab Sd Petemon 12

18.1052.38

2.2952.8051.44527.03

8.28

289.6882.96

213.52586.16

29.25651.528

Page 29: Rab Sd Petemon 12

2.371283.1552

316204.8

57.6578.4

29.25651.5282.3712

1.20.96322.058

87.3764

0

6534.299.28.28

3514.916

0.961.44

52.316

1

5.55.511 11

152.4

02.4 2.4

1.8 1.8

6684

Page 30: Rab Sd Petemon 12

111 1

1

Page 31: Rab Sd Petemon 12

DAFTAR STANDAR HARGA SATUAN DASAR(SHSD)

No Namadan Spesifikasi Satuan Harga(Rp) Keterangan

1 2 3 4 5

I MATERIAL.

1 Air (Biaya air tawar) ltr Rp 30.00 2 Aluminium 4" (silver) M1 Rp 90,000.00 YKK3 Aluminium 4" (dark brown) M1 Rp 90,000.00 YKK4 Aluminium 4" (brown) M1 Rp 90,000.00 YKK5 Aluminium 4" (powder coating) M2 Rp 100,000.00 YKK6 Aluminium 3" (silver) M1 Rp 90,000.00 YKK7 Aluminium 3" (dark brown) M1 Rp 90,000.00 YKK8 Aluminium 3" (brown) M1 Rp 90,000.00 YKK9 Aluminium 3" (powder coating) M2 Rp 100,000.00 YKK10 Aluminium Composite Panel 1,22x2,44 (0.21PVDV) lembar Rp 192,000.00 goldstar11 Aluminium Composite Panel 1,22x2,44 (0.21PVDV) lembar Rp 192,000.00 alumebond12 Aluminium Composite Panel 1,22x2,44 (0.21 PE) lembar Rp 204,000.00 Alustar13 Aluminium Composite Panel 1,22x2,44 (0.3 PVDV) lembar Rp 264,000.00 Alustar14 Aluminium Composite Panel 1,22x2,44 (0.21 PE) lembar Rp 204,000.00 seven15 Aluminium Composite Panel 1,22x2,44 (0.3 PVDV) lembar Rp 264,000.00 seven16 Aluminium Composite Panel 1,22x2,44 (0.5 PVDV) lembar Rp 324,000.00 seven17 Aluminium Composite Panel 1,22x2,44 (0.21 PE) lembar Rp 264,000.00 New Alucopan18 Aluminium Composite Panel 1,22x2,44 (0.21PVDV) lembar Rp 312,000.00 New Alucopan19 Aluminium Composite Panel 1,22x2,44 (0.5 PVDV) lembar Rp 384,000.00 Alcopla20 Aluminium Composite Panel 1,22x2,44 (0.3 PVDV) lembar Rp 570,000.00 Alucobond21 Aluminium Composite Panel 1,22x2,44 (0.5 PVDV) lembar Rp 636,000.00 Alucobond22 Aluminium Composite Panel 1,22x2,44 (0.21PVDV) lembar Rp 192,000.00 marks23 Kisi-kisi Aluminium Profil Z m1 Rp 13,500.00 24 Asbes datar Tb. 4 mm (1x1m) Lembar Rp 16,000.00 Djabesment25 Asbes gelombang besar M2 Rp 35,000.00 Djabesment26 Asbes gelombang kecil (150x108x0,5 cm) M2 Rp 35,371.43 Djabesment27 Asbes gelombang kecil (180x108x0,5 cm) M2 Rp 36,352.94 Djabesment28 Asbes gelombang kecil (210x108x0,5 cm) M2 Rp 33,375.00 Djabesment29 Asbes gelombang kecil (150x108x0,4 cm) M2 Rp 27,714.29 Djabesment30 Asbes gelombang kecil (180x108x0,4 cm) M2 Rp 27,364.71 Djabesment31 Asbes gelombang kecil (210x108x0,4 cm) M2 Rp 27,000.00 Djabesment32 Aqua Proof kg Rp 45,500.00 No drop33 Angkur dia 12mm kg Rp 14,000.00 Hi Steel34 Avour bh Rp 17,500.00 axel35 Wuwung asbes gelombang besar m1 Rp 55,000.00 Djabesment36 Wuwung asbes gelombang kecil m1 Rp 29,500.00 Djabesment37 Batu ampyang m2 Rp 29,300.00 Rockindo38 Batu alam m2 Rp 32,100.00 Rockindo39 Batu bobos uk10x20x1,5cm m2 Rp 123,500.00 Rockindo40 Batu Gilang ex jember uk.20x20cm m2 Rp 76,500.00 Rockindo41 Batu Gilang ex jember m2 Rp 72,000.00 Rockindo42 Batu Gilang ex Cirebon uk. 20x20 m2 Rp 103,600.00 Rockindo43 Batu Gilang ex Cirebon m2 Rp 60,700.00 Rockindo44 Batu hias m2 Rp 80,300.00 Rockindo45 Batu kali pecah15/20 m3 Rp 140,200.00 Ex. UD. Hartono46 Batu pecah mesin 1/2 m3 Rp 250,000.00 Ex. UD. Hartono47 Batu pecah mesin 2/3 m3 Rp 150,000.00 Ex. UD. Hartono48 Batu Kali Pecah 5/7 M3 Rp 215,000.00 Ex. UD. Hartono49 Batu Kerikil M3 Rp 150,000.00 Ex. UD. Hartono50 Bataco t =10 cm Bh Rp 4,600.00 Ex. UD. Hartono51 Bata merah (kelas 1) Bh Rp 730.00 MRH52 Bata Berongga Expose Bh Rp 4,200.00 Ex. UD. Hartono53 Bata ringan m3 Rp 830,000.00 citicon54 Batu Klinker Bh Rp 28,700.00 Ex. UD. Hartono

G43
adzra: perkantoran pacific megah block d-4 jl. Dupak 17
G44
adzra: perkantoran pacific megah block d-4 jl. Dupak 17
G45
adzra: perkantoran pacific megah block d-4 jl. Dupak 17
G46
adzra: perkantoran pacific megah block d-4 jl. Dupak 17
G47
adzra: perkantoran pacific megah block d-4 jl. Dupak 17
G48
adzra: perkantoran pacific megah block d-4 jl. Dupak 17
G49
adzra: perkantoran pacific megah block d-4 jl. Dupak 17
G50
adzra: perkantoran pacific megah block d-4 jl. Dupak 17
Page 32: Rab Sd Petemon 12

55 Baut HTB 16 mm bh Rp 3,000.00 56 Angkur dia 19mm bh Rp 30,000.00 57 Besi beton polos/ulir Kg Rp 9,200.00 Setia Agung Jaya58 Besi Wiremesh Kg Rp 18,714.04 CV. Sembilan perkasa59 Besi plat strip + baut mur Kg Rp 16,309.70 Abadi metal utama60 Besi plat strip Kg Rp 13,059.70 Abadi metal utama61 Besi plat tebal 1cm Kg Rp 26,000.00 Abadi metal utama62 Besi profil (baja konstruksi) Kg Rp 18,200.00 Abadi metal utama63 Besi profil siku 50x50x6 Kg Rp 7,300.00 Abadi metal utama64 Batu gilang ex cirebon(110x20x1,5) Kg Rp 5,200.00 Rockindo65 Bambu Bongkotan d 8-12 cm pj 3m btg Rp 22,000.00 66 Bambu Bongkotan d 8-12 cm pj 4m btg Rp 27,000.00 67 Bambu Ori 10-12Cm P j 3.00 Mt btg Rp 31,000.00 68 Besi Profil C100-150mm Kg Rp 12,500.00 69 Besi Profil WF Kg Rp 12,500.00 Abadi metal utama70 Besi Profil (Baja Konstruksi) Kg Rp 12,500.00 Abadi metal utama71 Besi Plat Bordes 4\"x8\"Tebal 3 mm kg Rp 12,500.00 Abadi metal utama72 Besi Plat Bordes 4\"x8\"Tebal 2 mm kg Rp 12,500.00 Abadi metal utama73 Besi Plat landas tb12mm kg Rp 12,500.00 Abadi metal utama74 Besi Plat Strip Pj6,00m3x30mm kg Rp 12,500.00 Abadi metal utama75 Blank Flanged 100 kg Rp 84,200.00 Global Exporter76 Box Bak Kontrol m3 Rp 1,801,200.00 Ex. UD. Hartono77 Bondek 1mmx1000mm m2 Rp 150,000.00 Bluescope78 Buis beton bulat uk. 100x50 cm bh Rp 70,000.00 Ex. UD. Hartono79 Cat Alkali Resisting Primer kg Rp 25,000.00 Jotun, dulux80 Cat Emco kg Rp 45,700.00 Emco81 Cat Genteng kg Rp 58,400.00 Avian Paint82 Cat tembok luar (5kg) Kaleng Rp 300,000.00 jotashiled, dulux weatershield83 Cat tembok dalam (5kg) Kaleng Rp 215,000.00 jotun majestic, dulux pentalite84 Cat tembok dalam spotless (2,5 ltr) kebutuhan 3,74 ltr Kaleng Rp 221,408.00 Nipo Paint85 Cat dasar (dempul tembok) Kg Rp 15,000.00 gm286 Cat dasar/primer (2,5 ltr)_kebutuhan 3,74 ltr (5kg) Kg Rp 24,600.00 dulux87 Cat Meni Besi Kg Rp 32,000.00 emco88 Cat Meni Kayu Kg Rp 46,000.00 emco89 Cat Kayu Kg Rp 43,000.00 emco90 Cat Penutup Kayu Kg Rp 20,950.00 emco91 Cerlak kg Rp 11,500.00 multi jaya92 Clear doof kg Rp 46,000.00 Suzuka93 Closed Jongkok Porselain bh Rp 300,000.00 Toto CE694 Closed Duduk Porselain bh Rp 2,000,000.00 Toto CW661jt195 Closed Duduk Porselain tanpa reservoir bh Rp 700,000.00 Toto C5096 Coating kg Rp 5,000.00 kyoto97 Coumpond kg Rp 19,000.00 Blinken98 Daun pintu PVC bh Rp 195,000.00 varian99 Daun Pintu WPC + Kaca + Finishing Politur (92x210) bh Rp 1,350,000.00 100 Daun Pintu WPC + Finishing Politur (82x210) bh Rp 1,200,000.00 101 Daun Pintu WPC + Finishing Politur (72x210) bh Rp 1,130,000.00 102 Engsel Kuningan ARCH u Pintu Stel Rp 26,000.00 Solid103 Engsel H Stel Rp 10,000.00 Solid104 Engsel Kuningan ARCH u Jendela Stel Rp 13,500.00 Solid105 Engsel Casement u Jendela Stel Rp 40,000.00 106 Elektroda las Kg Rp 29,200.00 Badak Steel107 Elektroda baja(20%) Kg Rp 30,000.00 Badak Steel108 Elektroda baja Kg Rp 49,325.00 Badak Steel109 FBBT 100 Bh Rp 412,000.00 Maspion110 Friction Stay 16" Bh Rp 68,000.00 111 Friction Stay 12" Bh Rp 52,000.00 112 Fitting Plafond Bh Rp 42,500.00 Broco113 Fiber Glass m2 Rp 33,500.00 Sunloid114 Fitrase m2 Rp 325,600.00 Bekron

G64
adzra: Kebraon Selatan E11 0317668419
G65
adzra: Sukomanunggal jaya A-5 0317317975
G66
adzra: Sukomanunggal jaya A-5 0317317975
G67
adzra: Sukomanunggal jaya A-5 0317317975
G68
adzra: Sukomanunggal jaya A-5 0317317975
G69
adzra: Sukomanunggal jaya A-5 0317317975
G70
adzra: perkantoran pacific megah block d-4 jl. Dupak 17
G75
adzra: Sukomanunggal jaya A-5 0317317975
G76
adzra: Sukomanunggal jaya A-5 0317317975
G77
adzra: Sukomanunggal jaya A-5 0317317975
G78
adzra: Sukomanunggal jaya A-5 0317317975
G79
adzra: Sukomanunggal jaya A-5 0317317975
G80
adzra: Sukomanunggal jaya A-5 0317317975
Page 33: Rab Sd Petemon 12

115 Foam Lapisan Karet m2 Rp 49,200.00 Utama Berdikari116 Gedeg Guling m2 Rp 38,750.00 117 Glangsing 25 kg (isi 150 kg sedimen) Lembar Rp 1,500.00 welttech118 Genteng flam pres jawa Bh Rp 1,750.00 PG. Genteng Press119 Genteng Kaca Bh Rp 22,000.00 M Class120 Genteng karang Pilang / Wisma Bh Rp 4,000.00 Karang Pilang121 Genteng Keramik Bh Rp 8,500.00 M class122 Genteng Galvalume lbr Rp 49,200.00 Profile Asia123 Genteng Wuwung Jawa bh Rp 4,000.00 PG. Genteng Press124 Genteng wuwung karang Pilang / Wisma Bh Rp 12,300.00 Karang Pilang125 Genteng wuwung Keramik Bh Rp 83,600.00 M class126 Genteng Wuwung Asbes Gelombang Kecil bh Rp 29,000.00 Djabesment127 GentengWuwung Galvalume bh Rp 67,525.00 Profile Asia128 Glass Blok bh Rp 16,500.00 Mulia129 Gorden Ekksklusif bh Rp 42,000.00 Famili Gorden130 Grendel Panjang bh Rp 20,000.00 Solid131 Grendel Biasa Kecil bh Rp 12,500.00 Solid132 Grendel Biasa Besar bh Rp 17,000.00 Solid133 Grendel Tanam bh Rp 102,000.00 Solid134 Grendel Ekspanyolet bh Rp 69,300.00 Solid135 Gym Floor m2 Rp 270,000.00 Connor Sport.136 Gypsumt =9mm lbr Rp 53,500.00 Jayaboard137 Gypsumt =12 mm lbr Rp 72,500.00 Jayaboard138 Kalsiboard EG Uk. 240 x 120 x 9mm Lembar Rp 146,500.00 Kalsiboard139 Kalsiboard EG Uk. 240 x 120 x 4mm Lembar Rp 72,890.00 Kalsiboard140 Kalsiboard EG Uk. 240 x 120 x 6mm Lembar Rp 106,750.00 Kalsiboard141 Kalsiplank polos Uk. 30 x 300 x 8mm Lembar Rp 52,000.00 142 Kalsiplank polos Uk. 20 x 300 x 8mm Lembar Rp 34,000.00 143 Hakangin sikutan (biasa) bh Rp 9,500.00 solid144 Hakangin sikutan (kuningan) Stel Rp 11,200.00 solid145 Hakangin Lurus bh Rp 27,200.00 solid146 Hakangin Lurus kuningan bisa disetel maju/mundur bh Rp 16,500.00 solid147 Handle + Kunci Tanam besar 2x putar kuningan bh Rp 125,000.00 148 Head Penangkal Petir bh Rp 4,720,000.00 kurn 150149 Isolator Bh Rp 30,200.00 Vickers150 Ijuk Kg Rp 10,250.00 UD lestari151 Wuwung Genteng karangPilang/Wisma Bh Rp 8,200.00 Karang Pilang152 Kaca Cermin t=5mm m2 Rp 182,000.00 Assahimass153 Kanstin BDCM 21,5 m m Rp 65,700.00 Kanstin154 KanstinTrap. Uk.15.25.40 m Rp 55,650.00 Kanstin155 Kapur pasang m3 Rp 60,000.00 156 Kapur Gamping m3 Rp 67,200.00 157 Karpet Wold Cels m2 Rp 292,500.00 158 Kawat Bendrat Kg Rp 14,500.00 Hi Steel159 Kawat Baja Hitam 10mm Kg Rp 14,000.00 Hi Steel160 Kawat Duri Pagar Kg Rp 61,000.00 Hi Steel161 Kawat Harmonika lebar 90cm m2 Rp 16,100.00 Hi Steel162 Kawat Nyamuk kasa Plastik Lebar 90 cm m2 Rp 19,000.00 Hi Steel163 Kawat Nyamuk kasa Aluminium Lebar 90 cm m2 Rp 29,500.00 Hi Steel164 Kawat Ikat m2 Rp 12,300.00 Hi Steel165 Kawat Beton Diameter 30 cm Kg Rp 14,500.00 Hi Steel166 Kayu jati reng m3 Rp 4,820,000.00 167 Dolken Kayu Gelam Ø 8-10cm p=4m btg Rp 6,800.00 168 Kayu Jati papan klas II m3 Rp 14,900,000.00 169 Kayu Jati Balok (8/12) m3 Rp 14,584,000.00 170 Kayu Jati Balok (6/15) m3 Rp 4,822,000.00 171 Kayu Jati usuk (5/7) m3 Rp 14,584,000.00 172 Kayu Kamper Balok (6/15) m3 Rp 9,027,777.78 173 Kayu Kamper balok 8/12 m3 Rp 6,500,000.00 174 Kayu Kamper 2/20 cm m3 Rp 4,875,000.00

Page 34: Rab Sd Petemon 12

175 Kayu Kamper 3/30 cm m3 Rp 8,190,277.78 176 Kayu Kamper 1/3cm m3 Rp 6,250,000.00 177 Kayu Kamper 1/5cm m3 Rp 4,300,000.00 178 Kayu kamper (slimar) m3 Rp 5,150,000.00 179 Kayu Kamper Usuk m3 Rp 3,300,000.00 180 Kayu Kamper reng (balok 3/5) m3 Rp 4,816,666.67 181 Kayu Meranti 3/5 m3 Rp 4,816,666.67 182 Kayu Meranti Balok 8/12 m3 Rp 5,333,333.33 183 Kayu Meranti Usuk 4/6 m3 Rp 4,166,666.67 184 Kayu Meranti Usuk balok 5/7 m3 Rp 4,160,714.29 185 Kayu Meranti (Papan 2/20) m3 Rp 5,000,000.00 186 Kayu Meranti Bekisting m3 Rp 3,500,000.00 187 Kayu Meranti papan 3/30 m3 Rp 6,162,500.00 188 Kayu usuk meranti (SKUR) m3 Rp 3,854,166.67 189 Keramik 20x20cm (motif/warna) m2 Rp 47,000.00 Asia / Roman190 Keramik 30x 30putihpolos m2 Rp 47,500.00 Asia / Roman191 Keramik 30x 30cm (motif/warna) m2 Rp 70,000.00 Asia / Roman192 Keramik 40x 40cm putih polos m2 Rp 70,000.00 Platinum / Roman193 Keramik 40x 40cm (motif/warna) m2 Rp 80,000.00 Platinum / Roman194 Keramik 40x40cm Tekstur Kasar m2 Rp 85,000.00 195 Keramik 50x 50cm putih polos m2 Rp 82,500.00 Platinum / Roman196 Keramik 50x 50cm (motif/warna) m2 Rp 86,000.00 Platinum / Roman197 Keramik 60x 60cm (motif/warna) m2 Rp 140,000.00 Platinum / Roman198 Keramik 20x 33cm putih polos m2 Rp 80,000.00 Platinum / Roman199 Keramik 20x 33cm (motif/warna) m2 Rp 65,000.00 Platinum / Roman200 Keramik 20x 50cm putih polos m2 Rp 90,000.00 Platinum / Roman201 Keramik 20x 50cm (motif/warna) m2 Rp 85,000.00 Platinum / Roman202 Keramik 30x 60cm (motif/warna) m2 Rp 152,500.00 Platinum / Roman203 Keramik tegel plint warna/motif 7,5x20 bh Rp 7,200.00 Platinum / Roman204 Keramik tegel plint warna/motif 7,5x21 bh Rp 7,200.00 Platinum / Roman205 Keramik Tegel Porselain11x11 m2 Rp 89,700.00 Mulia206 Keramik step nosing 8x30 cm bh Rp 11,000.00 Platinum / Roman207 Keramik lantai marmer m2 Rp 427,000.00 ex. Tulung Agung208 Kuku Macan bh Rp 1,000.00 Mulia209 Granite Tile 30x30 m2 Rp 245,000.00 Roman210 Granite Tile 15x60 m2 Rp 270,000.00 Roman211 Granite Tile 20x60 m2 Rp 270,000.00 Roman212 Granite Tile 30x60 m2 Rp 295,000.00 Roman213 Granite Tile 60x60 m2 Rp 270,000.00 Roman214 Granite Tile 15x90 m2 Rp 420,000.00 Roman215 Granite Tile 30x90 m2 Rp 420,000.00 Roman216 Keramik tegel trotoar m2 Rp 47,000.00 Asia tile217 Kertas gosok No. 150 Lbr Rp 8,750.00 Taiyo218 Kertas gosok No. 280 Lbr Rp 10,250.00 Taiyo219 Kran air1/2\"sun'i Bh Rp 57,000.00 sun'i220 Kran air Ex Import Bh Rp 22,300.00 Onda221 Krepyak Nako bh Rp 9,750.00 Esia222 Kuas Bh Rp 8,500.00 Eterna223 Kunci Tanam besar 2x putar kuningan Bh Rp 97,000.00 solid224 Kunci Tanam Kecil Bh Rp 75,000.00 solid225 Kaca Polost =5mm m2 Rp 90,000.00 Assahimass226 Kaca Polost =3mm m2 Rp 55,000.00 Assahimass227 Kaca Reyben t = 5 mm m2 Rp 97,200.00 Assahimass228 Kaca Gravier m2 Rp 273,000.00 Assahimass229 Kaca Stainglass m2 Rp 296,000.00 Assahimass230 Kabel NYA 1x1,5 m Rp 1,450.00 Eterna231 Kabel NYA 1x2.5 m Rp 2,300.00 Eterna232 Kabel NYA 1x4 m Rp 3,600.00 Eterna233 Kabel NYA 1x6 m Rp 5,300.00 Eterna234 Kabel NYA 1x10 m Rp 8,770.00 Eterna

Page 35: Rab Sd Petemon 12

235 Kabel NYA 500 volt 2 x 2,5 mm2 m Rp 6,500.00 Eterna236 Kabel NYM 3X1,5 m Rp 5,860.00 Eterna237 Kabel NYM 3X2,5 m Rp 8,340.00 Eterna238 Kabel NYM 2X1,5 m Rp 4,580.00 Eterna239 Kabel NYM 2X2,5 m Rp 6,560.00 Eterna240 Kabel NYM 3X4 m Rp 13,740.00 Eterna241 Kabel NYM 4X2,5 m Rp 10,700.00 Eterna242 Kabel NYM 4X4 m Rp 17,700.00 Eterna243 Kabel NYM 4X6 m Rp 24,900.00 Eterna244 Kabel NYM 4X10 m Rp 40,540.00 Eterna245 Kabel NYY 2X1,5 m Rp 6,440.00 Eterna246 Kabel NYY 2X2,5 m Rp 8,680.00 Eterna247 Kabel NYY 3X1,5 m Rp 7,960.00 Eterna248 Kabel NYY 3X2,5 m Rp 10,700.00 Eterna249 Kabel NYY 3X4 m Rp 16,600.00 Eterna250 Kabel NYY 3X6 m Rp 22,000.00 Eterna251 Kabel NYY 4X2,5 m Rp 12,960.00 Eterna252 Kabel NYY 4X4 m Rp 20,200.00 Eterna253 Kabel NYY 4X6 m Rp 26,200.00 Eterna254 Kabel NYY 4X10 m Rp 44,400.00 Eterna255 Kabel NYY 4 x 16 mm2 m1 Rp 95,000.00 256 Kabel BC 50 mm m1 Rp 40,000.00 257 Las Doof bh Rp 750.00 Shukaku258 Lampu TL 18 Watt bh Rp 9,500.00 Phillips259 Lampu SL 5 Watt bh Rp 21,000.00 Phillips260 Lampu SL 8 Watt bh Rp 21,000.00 Phillips261 Lampu SL 11 Watt bh Rp 26,000.00 Phillips262 Lampu SL 14 Watt bh Rp 27,000.00 Phillips263 Lampu SL 18 Watt bh Rp 29,000.00 Phillips264 Lampu SL 23 Watt bh Rp 35,000.00 Phillips265 Lampu SL 35 Watt bh Rp 87,000.00 Phillips266 Lampu SL 50 Watt bh Rp 120,000.00 Phillips267 Lampu SL 70 Watt bh Rp 140,000.00 Phillips268 Lampu LED 5 Watt bh Rp 65,000.00 Phillips269 Lampu LED 10 Watt bh Rp 80,000.00 Phillips270 Lampu TL waterproof 2x36watt bh Rp 590,000.00 Phillips271 Lampu Tempel hias SL 18 Watt bh Rp 96,000.00 Phillips272 Downligth 4" bh Rp 22,500.00 Vacolux273 Lapis triplek 0,4cm lbr Rp 58,250.00 Cooltech274 Lem kayu kg Rp 7,800.00 rajawali275 Lem PVC bh Rp 7,200.00 masplast276 Lem Wall Paper kg Rp 43,200.00 wallpac277 Lem Epoxi kg Rp 133,000.00 avian278 Lem Gypsum kg Rp 14,000.00 279 List plafond Gypsum bh Rp 9,300.00 jayaboard280 List Kayu 1/4 m1 Rp 10,000.00 281 L PVC 100x90 bh Rp 256,325.00 Maspion282 L PVC 100x45 bh Rp 256,325.00 Maspion283 Eternit gresik lbr Rp 31,200.00 jayaboard284 Minyak Cat (Afdunner) Ltr Rp 6,300.00 Asoka285 Minyak Bekisting Ltr Rp 8,500.00 Robinair286 Minyak pelumas Ltr Rp 22,900.00 Mesran287 Metal stud m3 Rp 3,750,000.00 Kalsi288 MCB bh Rp 40,250.00 schneider289 Panel Box MCB bh Rp 675,000.00 290 Paku kayu Kg Rp 13,850.00 Hi Steel291 Paku reng Kg Rp 12,750.00 Hi Steel292 Paku usuk Kg Rp 13,850.00 Hi Steel293 Panel lantai m3 Rp 2,350,000.00 citicon294 skrup Bh Rp 150.00 Hi Steel

Page 36: Rab Sd Petemon 12

295 Paku Seng Payung kg Rp 19,000.00 Hi Steel296 Paku triplek Kg Rp 12,500.00 Hi Steel297 Paku triplek/eternit Kg Rp 16,000.00 Hi Steel298 Paku Asbes Kg Rp 37,500.00 Hi Steel299 Pasir Cor m3 Rp 187,500.00 300 Paku Klem (No.4) kg Rp 13,850.00 Hi Steel301 Paku Klem (No.4) doz Rp 20,000.00 Hi Steel302 Paku Biasa 2"-5" kg Rp 12,750.00 Hi Steel303 Paras m3 Rp 90,000.00 304 Pasir Pasang m3 Rp 150,000.00 305 Pasir Urug m3 Rp 125,000.00 306 Pipa paralon 5/8\" m Rp 5,000.00 maspion307 Profil hollow 2x4 m Rp 19,000.00 Hi Steel308 Pewarna sct Rp 700.00 merak309 Kran Pelampung Set Rp 19,750.00 onda310 Pagar BRC/pmg A (uk. 1,2x2,4) unit Rp 297,500.00 Hi Steel311 Pagar BRC/pmg unit Rp 297,500.00 Hi Steel312 Pintu swing ganda BRC / PMG uk. 1,2x3m unit Rp 398,750.00 Hi Steel313 Pintu dorong ganda BRC / PMG uk. 1,2x3m unit Rp 398,750.00 Hi Steel314 Pintu pagar besi komplit dengan asesoris m2 Rp 625,000.00 Hi Steel315 Penambahan daya listrik ls Rp 2,200,000.00 316 Pipa Pipa Galvanis medium 1/2" m1 Rp 19,600.00 Hi Steel317 Pipa Pipa Galvanis medium 3/4" m1 Rp 24,166.67 Hi Steel318 Pipa Pipa Galvanis medium 1" m1 Rp 36,083.33 Hi Steel319 Pipa Pipa Galvanis medium 2" m1 Rp 71,125.00 Hi Steel320 Pipa Pipa Galvanis medium 2 1/2" m1 Rp 90,250.00 Hi Steel321 Pipa Pipa Galvanis medium 3" m1 Rp 115,416.67 Hi Steel322 Pipa Pipa Galvanis medium 4" m1 Rp 167,166.67 Hi Steel323 Pipa Pipa Galvanis medium 5" m1 Rp 169,666.67 Hi Steel324 Pipa Pipa Galvanis medium 1 1/4" m1 Rp 46,416.67 Hi Steel325 Pipa Pipa Galvanis medium 8" m1 Rp 131,250.00 Hi Steel326 Pipa Pipa Galvanis medium 6" m1 Rp 1,701,666.67 Hi Steel327 Pipa Galvanis Ø 1,5" m1 Rp 39,916.67 Hi Steel328 Pipa Galvanis Ø 2" m1 Rp 53,416.67 Hi Steel329 Pipa Galvanis Ø 2,5" m1 Rp 70,583.33 Hi Steel330 Pipa Galvanis Ø 3" m1 Rp 82,833.33 Hi Steel331 Pipa PVC Ø1/2\ "Type AW batang Rp 20,000.00 Wavin332 Pipa PVC Ø3/4\ "Type AW batang Rp 25,400.00 Wavin333 Pipa PVC Ø1\ "Type AW batang Rp 30,600.00 Wavin334 Pipa PVC Ø11/2\ "Type AW batang Rp 46,500.00 Wavin335 Pipa PVC Ø3\ "AW panjang 4 mtr ljr Rp 127,500.00 Wavin336 Pipa PVC Ø3\ "AW panjang 6 mtr ljr Rp 707,500.00 Wavin337 Pipa PVC Ø4\ "AW panjang 4 mtr ljr Rp 227,500.00 Wavin338 Pipa PVC Ø4\ "AW panjang 6 mtr ljr Rp 335,200.00 Wavin339 Pipa PVC Ø5\ "AW panjang 4 mtr ljr Rp 352,500.00 Wavin340 Pipa PVC Ø11/2\"C ljr Rp 14,200.00 maspion341 Pipa PVC Ø2\"C m Rp 33,500.00 maspion342 Pipa PVC Ø4\"C batang Rp 63,450.00 maspion343 Pipa PVC Ø3\"C batang Rp 49,300.00 maspion344 Pipa PVC Ø5\"C batang Rp 96,200.00 maspion345 Pipa PVC Ø6\"C ljr Rp 125,200.00 maspion346 Pipa PVC D Ø5 (@4 meter) batang Rp 160,000.00 maspion347 Pipa PVC D Ø4 (@4 meter) batang Rp 120,000.00 maspion348 Pipa PVC D Ø3 (@4 meter) batang Rp 80,000.00 maspion349 Pipa PVC 110 m Rp 20,100.00 maspion350 Pipa PVC 160 m Rp 73,750.00 maspion351 Pipa Cooker 150 m Rp 156,900.00 maspion352 Pipa baja (Hitam) Ø2\"medium m Rp 11,000.00 Wavin353 Pipa baja (Hitam) Ø3\"medium m Rp 13,000.00 Wavin354 Pipa baja (Hitam) Ø4\"medium m Rp 15,000.00 Wavin

F304
adzra: diambil panjang 10 cm
Page 37: Rab Sd Petemon 12

355 Pipa baja (Hitam) Ø5\"medium m Rp 17,200.00 Wavin356 Pipa pe 12 mm m Rp 23,750.00 Wavin357 Pipa stainless steel SCH 40 welded 1" m Rp 96,725.00 Wavin358 Pipa stainless steel SCH 40 welded 2" m Rp 97,200.00 Wavin359 Plamur Tembok kg Rp 46,000.00 Big lion360 Plamur Kayu kg Rp 23,000.00 Emco361 Profil tank 650 litter kg Rp 719,200.00 Cipta Proma perkasa362 Profil tank 800 litter kg Rp 818,400.00 Cipta Proma perkasa363 Profil tank 1100 litter kg Rp 1,054,000.00 Cipta Proma perkasa364 Profil tank 550 litter steinless kg Rp 1,229,000.00 Cipta Proma perkasa365 Profil tank 700 litter steinless kg Rp 1,521,000.00 Cipta Proma perkasa366 Profil tank 1100 litter steinless kg Rp 2,383,000.00 Cipta Proma perkasa367 Klem PVC Bh Rp 1,925.00 maspion368 Plywood Tegofilm tebal 9mm lbr Rp 300,000.00 369 Plywood tebal 9mm lbr Rp 82,600.00 Parindo370 Profil Alumunium putih uk. 4x10, profil 4" m1 Rp 33,200.00 Hi Steel371 Precast Pagar Panil/Pabrikasi m1 Rp 40,000.00 Lisa372 Saklar Tunggal Bh Rp 8,500.00 Broco373 Saklar Ganda Bh Rp 17,600.00 Broco374 Shanding kg Rp 50,500.00 Peacock375 Ramset / dynabolt buah Rp 2,500.00 Ramset TM376 Rol (Tba) Roll Rp 3,000.00 Fukuda377 Rangka Galvalume uk 0.8 mm m2 Rp 237,600.00 Hi Steel378 Rangka Galvalume uk 0.5 mm m2 Rp 186,500.00 Hi Steel379 Rangka Galvalume Campuran m2 Rp 205,200.00 Hi Steel380 Usuk Galvalum 5/7cm tebal 0,55mm m1 Rp 25,000.00 381 Reng Galvalum tebal 0,45mm m1 Rp 18,500.00 382 Skrup + Plat Galvalum kg Rp 20,000.00 383 Roof Drain bh Rp 45,000.00 384 Metal furing 2/4 cm ex. Sakura trust, bluscoopsteel m1 Rp 13,500.00

385 Semen Pc 50kg Zak Rp 71,000.00 Gresik / Holcim386 Semen Pc 40kg Zak Rp 57,000.00 Gresik / Holcim387 Semen Grouting 25kg Zak Rp 160,000.00 sikagrout388 Semen berwarna yiyitan kg Rp 11,200.00 MU389 Seng Gelombang BJLS 30uk(08x1.5) m2 Rp 56,200.00 Hi Steel390 Seng Gelombang BJLS 40uk(08x1.5) m2 Rp 49,700.00 Hi Steel391 Seng Gelombang BJLS 30uk(08x1.5)L=60cm m2 Rp 23,000.00 Hi Steel392 Seng Gelombang BJLS 30uk(80x180 cm) lembar Rp 55,650.00 Hi Steel393 Seng Gelombang BJLS 30uk(80x150 cm) lembar Rp 51,200.00 Hi Steel394 Seng BJLS 30L=90cm ml Rp 27,940.00 Hi Steel395 Seng BJLS 30L=60cm ml Rp 23,500.00 Hi Steel396 Seng BJLS 40L=60cm ml Rp 22,250.00 Hi Steel397 Seng BJLS 40L=90cm ml Rp 42,500.00 Hi Steel398 Seng datar BJLS 40 ml Rp 39,200.00 Hi Steel399 Serat fiber m2 Rp 4,500.00 serat mat400 Sifon Wasser m2 Rp 12,000.00 onda401 Sirap Asbes 4mm lbr Rp 17,250.00 Djabesment402 Sirtu m3 Rp 115,000.00 403 Slang spiral Set Rp 23,200.00 Raja Selang404 Slimar Alumunium3/8" m1 Rp 62,375.00 YKK405 Sealent tube Rp 26,800.00 Shirikon406 Solar ltr Rp 5,500.00 Pertamina407 Spritus Ltr Rp 12,500.00 Naga408 Stop Kontak Broco Bh Rp 18,500.00 Broco409 Stopper uskup tbl.6cm Bh Rp 7,200.00 conblock410 Sun Screen m2 Rp 96,750.00 Alexindo411 Tanah katel m3 Rp 109,200.00 412 Tempat sabun bh Rp 18,500.00 Krisbow413 T doos PVC Bh Rp 1,750.00 Maspion414 Teak wood t= 4mm Lbr Rp 61,000.00 Parindo

Page 38: Rab Sd Petemon 12

415 Teak wood uk. 122x244 t=3mm Lbr Rp 65,300.00 Parindo416 Tee 150x150 bh Rp 563,200.00 Hi Steel417 Tee 100x100 bh Rp 295,600.00 Hi Steel418 Triplek uk. 110x244 t=3 mm meranti Lbr Rp 43,000.00 Parindo419 Triplek uk. 110x244 t=4mm meranti Lbr Rp 53,000.00 Parindo420 Triplek uk. 110x244 t=8 mm meranti Lbr Rp 86,000.00 Parindo421 Triplek uk. 110x244 t=9 mm meranti Lbr Rp 93,500.00 Parindo422 Triplek uk. 110x244 t=12 mm meranti Lbr Rp 150,000.00 Parindo423 Triplek uk. 110x244 t=15 mm meranti Lbr Rp 180,000.00 Parindo424 Triplek uk. 110x244 t=18 mm meranti Lbr Rp 225,000.00 Parindo425 Triplek uk. 110x244 t=3 mm meranti Lbr Rp 66,500.00 Parindo426 Triplek uk. 110x244 t=3 mm meranti Lbr Rp 66,500.00 Parindo427 Triplek uk. 110x244 t=12 mm film satu muka Lbr Rp 110,000.00 Parindo428 Triplek uk. 110x244 t=15 mm film satu muka Lbr Rp 225,000.00 Parindo429 Triplek uk. 110x244 t=12 mm film dua muka Lbr Rp 205,000.00 Parindo430 Triplek uk. 110x244 t=15 mm film dua muka Lbr Rp 245,000.00 Parindo431 Triplek uk. 110x244 t=18 mm film dua muka Lbr Rp 275,000.00 Parindo432 Lbr Rp 210,000.00 433 Teer Kg Rp 5,750.00 Teer434 Tanah Urug m3 Rp 115,000.00 435 Thinner A ltr Rp 24,000.00 Thinner436 Tiang Pancang 20/20 m Rp 137,500.00 metro pile437 Tiang Pancang 25/25 m Rp 189,200.00 metro pile438 Tiang Pancang 30/30 m Rp 223,000.00 metro pile439 U Gutter U1000/1000-2400 (K 350 Besi 130 kg) (Fabrikasi) bh Rp 2,426,500.00 440 Urinoir bh Rp 450,000.00 441 Cover 1000x1000x2400 (K 350; besi 160 kg ) (Fabrikasi) bh Rp 2,426,500.00 442 Vertical Blind m2 Rp 182,100.00 Ellite443 Valve 100 bh Rp 1,019,300.00 maspion444 Valve 150 bh Rp 2,096,500.00 maspion445 Wall Paper m2 Rp 96,000.00 Ellite446 Wastafel Besar Warna bh Rp 327,000.00 Toto L38V1447 Waterproofing kg Rp 38,750.00 No drop448 Wood filler kg Rp 27,500.00 Emco449 Wood plank + pemasangan m1 Rp 62,000.00 Elephant450 Walter Moer bh Rp 15,200.00 onda451 Besi Hollow 4/4 m1 Rp 21,000.00 Hi Steel452 Besi Hollow 4/4 m1 Rp 21,000.00 Hi Steel453 Besi Hollow 5/5 m1 Rp 45,000.00 Hi Steel454 Besi Hollow 2/4 m1 Rp 19,500.00 Hi Steel455 Got talang R25 (Segmen) bh Rp 26,750.00 Ex. UD. Hartono456 Got talang R15 (Segmen) bh Rp 18,700.00 Ex. UD. Hartono457 Got talang R10 (Segmen) bh Rp 17,000.00 Ex. UD. Hartono458 Got talang R25 (1/2 lingkaran) bh Rp 24,000.00 Ex. UD. Hartono459 Got talang R15 (1/2 lingkaran) bh Rp 16,000.00 Ex. UD. Hartono460 Got talang R10 (1/2 lingkaran) bh Rp 25,000.00 Ex. UD. Hartono461 Paving abu-abu tbl. 6 cm (4 persegi pj ) bh Rp 1,500.00 conblock462 Paving abu-abu tbl. 8 cm (4 persegi pj ) bh Rp 1,800.00 conblock463 Paving stone merah tbl. 8 cm (4 persegi pj ) bh Rp 2,500.00 conblock464 Paving stone full warna tbl. 6 cm (4 persegi pj ) bh Rp 1,800.00 conblock465 Paving stone motif warna abu abu tbl. 6 cm (4 persegi pj ) bh Rp 1,800.00 conblock466 Paving Cassada abu-abu T=8mm m2 Rp 90,000.00 Alexis467 Paving Cassada warna T=8mm m2 Rp 120,000.00 Alexis468 GRC Board 4 mm Lembar Rp 54,000.00 grc469 cross runner 50x25 m' Rp 27,000.00 Kalsi470 main runner 38x13 m' Rp 22,500.00 Kalsi471 root hanger 8mm m' Rp 11,000.00 Kalsi472 Beton ready mix k-175 m' Rp 879,675.42 jaya mix473 Beton ready mix k-250 m' Rp 954,607.25 jaya mix474 Beton ready mix k-300 m' Rp 685,000.00 jaya mix

Triplek Phenolic 1 sisi  12 mm  uk. 122 x 244 cm

Page 39: Rab Sd Petemon 12

475 Beton ready mix k-350 m' Rp 735,000.00 jaya mix476 Perlengkapan Penangkal Petir

477 Pasang Head splitz petir CU 3/4" dengan pipa GIP D 1" Bh Rp 250,000.00 478 Kabel BC dia 50 mm2 m1 Rp 40,000.00 479 Isolator pipa PVC AW D 3/4" + klem plat m1 Rp 27,000.00 480 Pentanahan grounding Kabel BC 50 mm2 Unit Rp 350,000.00 481 Bak kontrol grounding Unit Rp 45,000.00 482 Box test line Set Rp 250,000.00 483 Kabel Schoon Set Rp 7,500.00 484 Connector Set Rp 8,500.00 485 Peralatan Bantu Jam Rp 1,000.00 486 Testing dan Commissioning termasuk ijin-ijin penangkal petir Ls Rp 500,000.00 487 Tandon Air Beton Kap. 4 m3 eks Fabrikan + pasang bh Rp 5,400,000.00 488 Septic tank Kap 3 m3 eks fabrikan + pasang bh Rp 3,600,000.00 489 Profil tank kapasitas 1,1 m3 (stenlessteel) Unit Rp 2,350,000.00 490 Pompa elektric (kapasitas hisap 30m,dorong 30m ) unit Rp 950,000.00 491 Plastik m2 Rp 2,000.00

II TENAGA

1 Mandor hr Rp 97,000.00 1 Surveyor Geodesi hr Rp 97,000.00 2 Kepala Tukang Batu hr Rp 95,000.00 3 Kepala Tukang Besi hr Rp 95,000.00 4 Kepala Tukang Cat hr Rp 95,000.00 5 Kepala Tukang Kayu hr Rp 95,000.00 6 Kepala Tukang Listrik hr Rp 95,000.00 7 Kepala Tukang Pipa hr Rp 95,000.00 8 Tukang Batu hr Rp 92,500.00 9 Tukang Besi hr Rp 92,500.00 10 Tukang Cat hr Rp 92,500.00 11 Tukang Kayu hr Rp 92,500.00 12 Tukang Las hr Rp 92,500.00 13 Tukang Listrik hr Rp 92,500.00 14 Tukang Pipa hr Rp 92,500.00 15 Pekerja Terampil hr Rp 89,100.00 16 Pekerja / Buruh Tak Terampil hr Rp 89,100.00 17 Petugas Survey hr Rp 97,000.00

III. PERALATAN

1 Sewa Compresor Jam Rp 33,250.00 2 Sewa Concreate Mixer m3 (min 3jam) Jam Rp 61,750.00 3 Sewa Concreate Pump (min 3 jam ) Jam Rp 61,750.00 4 Sewa Concreate vibrator Jam Rp 14,250.00 5 Sewa Crane 30ton-min8jam (termasuk mob/demob.6 Opertor, BBM) Jam Rp 130,625.00 7 Sewa Hammer tiang pancang-min8jam Hidrolis (termasuk8 mob/demob,operator, BBM) Jam Rp 175,750.00 9 Sewa Bucket dan crane/draglin scraper Jam Rp 76,000.00 10 Sewa Motor Grader125-140Pk (min5jam) Jam Rp 261,250.00 11 Sewa PhenumaticTire Roller (min5jam) Jam Rp 209,000.00 12 SewaTruck Tangki Air (min 5 jam) Jam Rp 470,250.00 13 Sewa Truk Kelas 3 Dalam kota Jam Rp 727,500.00 13 Sewa Vibrator Roller (min 5 jam) Jam Rp 128,250.00 14 Sewa Excavator 6m Jam Rp 123,500.00 15 SewaTheodolit set Rp 329,175.00 16 Sewa Welding Set (min 5 jam) hari Rp 28,500.00 17 Sewa Alat Bantu (1 set@3alat ) jam Rp 950.00 18 Sewa Dump truck 6T min(5jam) jam Rp 65,000.00 19 Sewa Dump truck 5T min(5jam) jam Rp 61,750.00 17 Sewa Dump truck 3,5T min(5jam) jam Rp 61,750.00

Page 40: Rab Sd Petemon 12

18 Sewa alat bantu boor pile jam Rp 275,000.00 19 Sewa Stampper jam Rp 150,000.00

Page 41: Rab Sd Petemon 12

DAFTAR HARGA SATUAN POKOK KEGIATAN BANGUNAN GEDUNG Pekerjaan Persiapan & TanahPembuatan Bouwplank (UITZET) m1Upah:Kepala Tukang Kayu 0.0100 O.H 95,000.00 950.00 Tukang Kayu 0.1000 O.H 92,500.00 9,250.00 Pekerja 0.1000 O.H 89,100.00 8,910.00

Jumlah: 19,110.00 Bahan/Material:Kayu Meranti (Papan 2/20) 0.0070 m3 5,000,000.00 35,000.00 Kayu Meranti (Usuk 5/7) 0.0120 m3 4,160,714.29 49,928.57 Paku biasa 2" - 5" 0.0200 Kg 12,750.00 255.00

Jumlah: 85,183.57 Nilai HSPK : 104,293.57 Pengangkutan Tanah keluar Proyek m3Upah:Pekerja 0.2500 O.H 89,100.00 22,275.00

Jumlah: 22,275.00 Sewa Peralatan:Sewa Dump Truck 5 T (min 5 jam) 0.2500 Jam 61,750.00 15,437.50

Jumlah: 15,437.50 Nilai HSPK : 37,712.50

Penggalian Tanah untuk Konstruksi m3Upah:Mandor 0.0250 O.H 97,000.00 2,425.00 Pekerja 0.7500 O.H 89,100.00 66,825.00

Jumlah: 69,250.00 Nilai HSPK : 69,250.00

Pengurugan Tanah Kembali untuk Konstruksi m3Upah:Mandor 0.0083 O.H 97,000.00 808.33 Pekerja 0.2500 O.H 89,100.00 22,275.00

Jumlah: 23,083.33 Nilai HSPK : 23,083.33

Pengurugan Pasir (PADAT) m3Upah:Mandor 0.0100 O.H 97,000.00 970.00 Pekerja 0.3000 O.H 89,100.00 26,730.00

Jumlah: 27,700.00 Bahan:Pasir Urug 1.2000 m3 125,000.00 150,000.00

Jumlah: 150,000.00 Nilai HSPK : 177,700.00

Pengurugan Sirtu (PADAT) m3Upah:Mandor 0.0250 O.H 97,000.00 2,425.00 Pekerja 0.2500 O.H 89,100.00 22,275.00

Jumlah: 24,700.00 Bahan:Tasirtu/ Sirtu 1.2000 m3 115,000.00 138,000.00 Sewa Stampper 0.1500 jam 150,000.00 22,500.00

Jumlah: 160,500.00 Nilai HSPK : 185,200.00

m3Upah:Mandor 0.0390 O.H 97,000.00 3,783.00 Kepala Tukang Batu 0.0390 O.H 95,000.00 3,705.00 Tukang Batu 0.3900 O.H 92,500.00 36,075.00 Pekerja 0.7800 O.H 89,100.00 69,498.00

Jumlah: 113,061.00 Bahan:Batu Kali Belah 15/20 cm 1.2000 m3 140,200.00 168,240.00 Pasir Urug 0.4320 m3 125,000.00 54,000.00

Jumlah: 222,240.00 Nilai HSPK : 335,301.00

Pekerjaan Pemasangan Batu Kali Belah 15/20 cm (1 Pc : 4 Ps) m3

Upah:Mandor 0.0750 O.H 97,000.00 7,275.00 Kepala Tukang Batu 0.0750 O.H 95,000.00 7,125.00 Tukang Batu 0.7500 O.H 92,500.00 69,375.00 Pekerja 1.5000 O.H 89,100.00 133,650.00

Jumlah: 217,425.00 Bahan:Semen portland (50kg) 3.2600 Zak 71,000.00 231,460.00 Pasir Pasang 0.5200 m3 150,000.00 78,000.00 Batu Kali Belah 15/20 cm 1.2000 m3 140,200.00 168,240.00

Jumlah: 477,700.00 Nilai HSPK : 695,125.00

Pemasangan Batu Kali Belah Kosongan (aanstamping)

B14
Asmar: Paku Reng
B17
harun: asumsi perjalanan PP 10 km 1 jam, waktu angkut 1 jam waktu nurunkan 1/2 jam
Page 42: Rab Sd Petemon 12

Pemasangan Dinding Batu Merah 1 Pc : 3 Pp tebal 1/2 bata m2

Upah:Mandor 0.0150 O.H 97,000.00 1,455.00 Kepala Tukang Batu 0.0100 O.H 95,000.00 950.00 Tukang Batu 0.1000 O.H 92,500.00 9,250.00 Pekerja 0.3000 O.H 89,100.00 26,730.00

Jumlah: 38,385.00 Bahan:Semen PC (Portland Cement) 50 kg 0.2874 Zak 71,000.00 20,405.40 Pasir Pasang 0.0400 m3 150,000.00 6,000.00 Batu Bata Merah uk 22 x 11 x 4.5 cm 70.0000 Buah 730.00 51,100.00

Jumlah: 77,505.40 Nilai HSPK : 115,890.40

Pemasangan Dinding Batu Merah 1 Pc : 5 Pp tebal 1/2 bata m2

Upah:Mandor 0.0150 O.H 97,000.00 1,455.00 Kepala Tukang Batu 0.0100 O.H 95,000.00 950.00 Tukang Batu 0.1000 O.H 92,500.00 9,250.00 Pekerja 0.3000 O.H 89,100.00 26,730.00

Jumlah: 38,385.00 Bahan:Semen PC (Portland Cement) 50 kg 0.1936 Zak 71,000.00 13,745.60 Pasir Pasang 0.0450 m3 150,000.00 6,750.00 Batu Bata Merah uk 22 x 11 x 4.5 cm 70.0000 Buah 730.00 51,100.00

Jumlah: 71,595.60 Nilai HSPK : 109,980.60

Plesteran Halus 1 Pc : 3 Ps tebal 1.5 cm m2Upah:Mandor 0.0150 O.H 97,000.00 1,455.00 Kepala Tukang Batu 0.0150 O.H 95,000.00 1,425.00 Tukang Batu 0.1500 O.H 92,500.00 13,875.00 Pekerja 0.3000 O.H 89,100.00 26,730.00

Jumlah: 43,485.00 Bahan:Semen PC (Portland Cement) 50 kg 0.1555 Zak 71,000.00 11,041.92 Pasir Pasang 0.0230 m3 150,000.00 3,450.00

Jumlah: 14,491.92 Nilai HSPK : 57,976.92

Plesteran Halus 1 Pc : 5 Ps tebal 1.5 cm m2Upah:Mandor 0.0150 O.H 97,000.00 1,455.00 Kepala Tukang Batu 0.0150 O.H 95,000.00 1,425.00 Tukang Batu 0.1500 O.H 92,500.00 13,875.00 Pekerja 0.3000 O.H 89,100.00 26,730.00

Jumlah: 43,485.00 Bahan:Semen PC (Portland Cement) 50 kg 0.1037 Zak 71,000.00 7,361.28 Pasir Pasang 0.0260 m3 150,000.00 3,900.00

Jumlah: 11,261.28 Nilai HSPK : 54,746.28

Pasang Benangan 1 Pc: 2Ps mUpah:Mandor 0.0040 O.H 97,000.00 388.00 Kepala Tukang Batu 0.0400 O.H 95,000.00 3,800.00 Tukang Batu 0.0400 O.H 92,500.00 3,700.00 Pekerja 0.0800 O.H 89,100.00 7,128.00

Jumlah: 15,016.00 Bahan:Semen PC (Portland Cement) 50 kg 0.0100 Zak 71,000.00 710.00 Pasir Pasang 0.0130 m3 150,000.00 1,950.00

Jumlah: 2,660.00 Nilai HSPK : 17,676.00

Pekerjaan Acian m2Upah:Mandor 0.0100 O.H 97,000.00 970.00 Kepala Tukang Batu 0.0100 O.H 95,000.00 950.00 Tukang Batu 0.1000 O.H 92,500.00 9,250.00 Pekerja 0.2000 O.H 89,100.00 17,820.00

Jumlah: 28,990.00 Bahan:Semen portland (50 kg) 0.0650 Zak 71,000.00 4,615.00

Jumlah: 4,615.00 Nilai HSPK : 33,605.00

Plamur Tembok m2Upah:Mandor 0.0010 O.H 97,000.00 97.00 Kepala Tukang Cat 0.0030 O.H 95,000.00 285.00 Tukang Cat 0.0300 O.H 92,500.00 2,775.00 Pekerja 0.0200 O.H 89,100.00 1,782.00

Jumlah: 4,939.00

Page 43: Rab Sd Petemon 12

Bahan:Plamur Tembok 0.1000 Kg 46,000.00 4,600.00 Kertas Gosok no 150 0.5000 Lembar 8,750.00 4,375.00

Jumlah: 8,975.00 Nilai HSPK : 13,914.00

Pemasangan Tegel Keramik 30x30 cm tekstur kasar m2Upah:Mandor 0.0350 O.H 97,000.00 3,395.00 Kepala Tukang Batu 0.0350 O.H 95,000.00 3,325.00 Tukang Batu 0.3500 O.H 92,500.00 32,375.00 Pekerja 0.7000 O.H 89,100.00 62,370.00

Jumlah: 101,465.00 Bahan:Semen PC (Portland Cement) 50 kg 0.2080 Zak 71,000.00 14,768.00 Semen Berwarna Yiyitan 1.6200 Kg 11,200.00 18,144.00 Pasir Pasang 0.0450 m3 150,000.00 6,750.00 Tegel Keramik 30 x 30 Cm tekstur kasar 1.0600 m2 70,000.00 74,200.00

Jumlah: 113,862.00 Nilai HSPK : 215,327.00

Pemasangan Tegel Keramik 40x40 cm m2

Upah:Mandor 0.0350 O.H 97,000.00 3,395.00 Kepala Tukang Batu 0.0350 O.H 95,000.00 3,325.00 Tukang Batu 0.3500 O.H 92,500.00 32,375.00 Pekerja 0.7000 O.H 89,100.00 62,370.00

Jumlah: 101,465.00 Bahan:Semen PC (Portland Cement) 50 kg 0.1960 Zak 71,000.00 13,916.00 Semen Berwarna Yiyitan 1.3000 Kg 11,200.00 14,560.00 Pasir Pasang 0.0450 m3 150,000.00 6,750.00 Tegel Keramik 40x40 1.0608 m2 80,000.00 84,864.00

Jumlah: 120,090.00 Nilai HSPK : 221,555.00

Pemasangan Tegel Keramik 40x40 cm Tekstur Kasar m2 Upah:Mandor 0.0350 O.H 97,000.00 3,395.00 Kepala Tukang Batu 0.0350 O.H 95,000.00 3,325.00 Tukang Batu 0.3500 O.H 92,500.00 32,375.00 Pekerja 0.7000 O.H 89,100.00 62,370.00

Jumlah: 101,465.00 Bahan:Semen PC (Portland Cement) 50 kg 0.1960 Zak 71,000.00 13,916.00 Semen Berwarna Yiyitan 1.3000 Kg 11,200.00 14,560.00 Pasir Pasang 0.0450 m3 150,000.00 6,750.00 Tegel Keramik 40x40 tekstur kasar 1.0608 m2 85,000.00 90,168.00

Jumlah: 125,394.00 Nilai HSPK : 226,859.00

Pemasangan Plint keramik 10x40 cm m1 Upah:Mandor 0.0050 O.H 97,000.00 485.00 Kepala Tukang Batu 0.0090 O.H 95,000.00 855.00 Tukang Batu 0.0900 O.H 92,500.00 8,325.00 Pekerja 0.0900 O.H 89,100.00 8,019.00

Jumlah: 17,684.00 Bahan:Semen PC (Portland Cement) 50 kg 0.0228 Zak 71,000.00 1,618.80 Semen Berwarna Yiyitan 0.0250 Kg 11,200.00 280.00 Pasir Pasang 0.0030 m3 150,000.00 450.00 Tegel Keramik 10x40 0.1000 m2 80,000.00 8,000.00

Jumlah: 10,348.80 Nilai HSPK : 28,032.80

Pemasangan Tegel Keramik 30x60 cm (Dinding) m2

Upah:Mandor 0.045 O.H 97,000.00 4,365.00 Kepala Tukang Batu 0.045 O.H 95,000.00 4,275.00 Tukang Batu 0.45 O.H 92,500.00 41,625.00 Pekerja 0.9 O.H 89,100.00 80,190.00

Jumlah: 130,455.00 Bahan:Semen PC (Portland Cement) 50 kg 0.1860 Zak 71,000.00 13,206.00 Semen Berwarna Yiyitan 1.9400 Kg 11,200.00 21,728.00 Pasir Pasang 0.0180 m3 150,000.00 2,700.00 Tegel Keramik 30 x 60 Cm (dinding) 1.0500 m2 152,500.00 160,125.00

Jumlah: 197,759.00 Nilai HSPK : 328,214.00

Page 44: Rab Sd Petemon 12

Pemasangan Tegel Step Nosing m'Upah:Mandor 0.0050 O.H 97,000.00 485.00 Kepala Tukang Batu 0.0090 O.H 95,000.00 855.00 Tukang Batu 0.0900 O.H 92,500.00 8,325.00 Pekerja 0.0900 O.H 89,100.00 8,019.00

Jumlah: 17,684.00 Bahan:Semen PC (Portland Cement) 50 kg 0.0228 Zak 71,000.00 1,618.80 Semen Berwarna Yiyitan 0.0250 Kg 11,200.00 280.00 Pasir Pasang 0.0030 m3 150,000.00 450.00 Stop Nosing 5.3000 Buah 11,000.00 58,300.00

Jumlah: 60,648.80 Nilai HSPK : 78,332.80

Pemasangan Paving Stone persegi panjang t. 6cm m'Upah:Mandor 0.0250 O.H 97,000.00 2,425.00 Kepala Tukang Batu 0.0250 O.H 95,000.00 2,375.00 Tukang Batu 0.0500 O.H 92,500.00 4,625.00 Pekerja 0.0500 O.H 89,100.00 4,455.00

Jumlah: 13,880.00 Bahan:Paving Stone persegi panjang t. 6cm 44.0000 bh 1,500.00 66,000.00

Jumlah: 66,000.00 Nilai HSPK : 79,880.00

Pemasangan Kaca Polos tebal 5 mm m2Upah:Mandor 0.00075 O.H 97,000.00 72.75 Kepala Tukang Kayu 0.0150 O.H 95,000.00 1,425.00 Tukang Kayu 0.1500 O.H 92,500.00 13,875.00 Pekerja 0.0150 O.H 89,100.00 1,336.50

Jumlah: 16,709.25 Bahan:Kaca Polos Tebal 5 mm 1.1000 m2 90,000.00 99,000.00 Karet sealent 0.2700 tube 26,800.00 7,236.00

Jumlah: 106,236.00 Nilai HSPK : 122,945.25

Pemasangan Kunci Tanam Besar 2x Putar kuningan BuahUpah:Mandor 0.0050 O.H 97,000.00 485.00 Kepala Tukang Kayu 0.0100 O.H 95,000.00 950.00 Tukang Kayu 0.5000 O.H 92,500.00 46,250.00 Pekerja 0.0100 O.H 89,100.00 891.00

Jumlah: 48,576.00 Bahan:Kunci Tanam Besar 2x Putar (kuningan) 1.0000 Buah 97,000.00 97,000.00

Jumlah: 97,000.00 Nilai HSPK : 145,576.00

Pemasangan Engsel Casement Untuk Jendela StelUpah:Mandor 0.0005 O.H 97,000.00 48.50 Kepala Tukang Kayu 0.0100 O.H 95,000.00 950.00 Tukang Kayu 0.1000 O.H 92,500.00 9,250.00 Pekerja 0.0100 O.H 89,100.00 891.00

Jumlah: 11,139.50 Bahan:Engsel Casement 1.0000 stel 40,000.00 40,000.00

Jumlah: 40,000.00 Nilai HSPK : 51,139.50

Pemasangan Engsel Kuningan Untuk Pintu StelUpah:Mandor 0.00075 O.H 97,000.00 72.75 Kepala Tukang Kayu 0.0150 O.H 95,000.00 1,425.00 Tukang Kayu 0.1500 O.H 92,500.00 13,875.00 Pekerja 0.0150 O.H 89,100.00 1,336.50

Jumlah: 16,709.25 Bahan:Engsel Kuningan (untuk Pintu) 1.0000 stel 26,000.00 26,000.00

Jumlah: 26,000.00 Nilai HSPK : 42,709.25

Pemasangan Grendel Jendela BuahUpah:Tukang Kayu 0.1200 O.H 92,500.00 11,100.00 Pekerja 0.0600 O.H 89,100.00 5,346.00

Jumlah: 16,446.00

Bahan:Grendel biasa 1.0000 Buah 12,500.00 12,500.00

Jumlah: 12,500.00 Nilai HSPK : 28,946.00

Page 45: Rab Sd Petemon 12

Pemasangan Kusen Alumunium Profil 4" m1Upah:Mandor 0.0021 O.H 97,000.00 203.70 Kepala Tukang Kayu 0.0043 O.H 95,000.00 408.50 Tukang Kayu 0.0430 O.H 92,500.00 3,977.50 Pekerja 0.0430 O.H 89,100.00 3,831.30

Jumlah: 8,421.00 Bahan:Aluminium Profil 4" Dark brown 1.1000 m1 90,000.00 99,000.00 Skrup/Ripet 2.0000 Buah 150.00 300.00 Sealent 0.0600 tube 26,800.00 1,608.00

Jumlah: 100,908.00 Nilai HSPK : 109,329.00

Pemasangan Slimar Alumunium Daun Jendela Profil 3/8 m1Upah:Mandor 0.0022 O.H 97,000.00 214.37 Kepala Tukang Kayu 0.0043 O.H 95,000.00 408.50 Tukang Kayu 0.0430 O.H 92,500.00 3,977.50 Pekerja 0.0430 O.H 89,100.00 3,831.30

Jumlah: 8,431.67 Bahan:Slimar Alumunium 3/8 1.1000 m1 62,375.00 68,612.50 Sealent 0.0600 tube 26,800.00 1,608.00 Skrup/Ripet 2.0000 Buah 150.00 300.00

Jumlah: 70,520.50 Nilai HSPK : 78,952.17

m2Upah:Mandor 0.0500 O.H 97,000.00 4,850.00 Kepala Tukang Kayu 0.3000 O.H 95,000.00 28,500.00 Tukang Kayu 3.0000 O.H 92,500.00 277,500.00 Pekerja 1.0000 O.H 89,100.00 89,100.00

Jumlah: 399,950.00 Bahan:Kayu Kamper 0.0200 m3 4,875,000.00 97,500.00 Plywood 12 mm 0.6000 m2 82,600.00 49,560.00 Teakwood 4mm 0.6000 m2 61,000.00 36,600.00 Skrup 10.0000 Buah 150.00 1,500.00

Jumlah: 185,160.00 Nilai HSPK : 585,110.00

Pasang Daun Pintu WPC finish politur unitUkuran 92 x 210 cmUpah:Kepala Tukang Kayu 0.0800 O.H 95,000.00 7,600.00 Pekerja 0.0800 O.H 89,100.00 7,128.00

Jumlah: 14,728.00 Bahan:Daun Pintu WPC finish politur (92x210) 1.0000 unit 1,350,000.00 1,350,000.00

Jumlah: 1,350,000.00 Nilai HSPK : 1,364,728.00

Pasang Daun Pintu WPC finish politur unitUkuran 82 x 210 cmUpah:Kepala Tukang Kayu 0.0800 O.H 95,000.00 7,600.00 Pekerja 0.0800 O.H 89,100.00 7,128.00

Jumlah: 14,728.00 Bahan:Daun Pintu WPC + kaca + finish politur (82x210) 1.0000 unit 1,200,000.00 1,200,000.00

Jumlah: 1,200,000.00 Nilai HSPK : 1,214,728.00

Pasang Daun Pintu WPC finish politur unitUkuran 72 x 210 cmUpah:Kepala Tukang Kayu 0.0800 O.H 95,000.00 7,600.00 Pekerja 0.0800 O.H 89,100.00 7,128.00

Jumlah: 14,728.00 Bahan:Daun Pintu WPC finish politur (72x210) 1.0000 unit 1,130,000.00 1,130,000.00

Jumlah: 1,130,000.00 Nilai HSPK : 1,144,728.00

Daun Pintu Slimar Kayu Kamper isian Plywood 12 mm dilapis teakwood 4mm Bagian dalam dilapis formika

Page 46: Rab Sd Petemon 12

Pemasangan pintu type PJPemasangan Kusen Alumunium Profil 4" 15.14 m1 109,329.00 1,655,241.06 Pemasangan Daun Pintu WPC + Finish ukuran 92 x 210 cm 1.00 unit 1,364,728.00 1,364,728.00 Pemasangan Selimar Aluminium Daun Jendela 8.32 m1 78,952.17 656,882.05 Pemasangan Kaca Bening 2.35 m2 122,945.25 288,404.97 Pemasangan Engsl Pintu 1.50 bh 42,709.25 64,063.88 Pemasangan casement 3.00 bh 51,139.50 153,418.50 Pemasangan Handle + Kunci pintu 1.00 bh 145,576.00 145,576.00 Friction Stay 16" 1.00 bh 68,000.00 68,000.00 Friction Stay 12" 2.00 bh 52,000.00 104,000.00

4,500,314.46

Pekerjaan Kusen Pintu Type P2Pemasangan Kusen Alumunium Profil 4" 5.08 m1 109,329.00 555,391.32 Pemasangan Daun Pintu WPC + Finish ukuran 82 x 210 cm 1.00 unit 1,214,728.00 1,214,728.00 Pemasangan Engsl Pintu 1.50 bh 42,709.25 64,063.88 Pemasangan Handle + Kunci 1.00 bh 145,576.00 145,576.00

1,979,759.20

Pekerjaan Kusen Pintu Type P3Pemasangan Kusen Alumunium Profil 4" 4.98 m1 109,329.00 544,458.42 Pemasangan Daun Pintu WPC + Finish ukuran 72 x 210 cm 1.00 unit 1,144,728.00 1,144,728.00 Pemasangan Engsl Pintu 1.50 bh 42,709.25 64,063.88 Pemasangan Handle + Kunci 1.00 bh 145,576.00 145,576.00

1,898,826.30

Pekerjaan Kusen Pintu Type P3Pemasangan Kusen Alumunium Profil 4" 5.18 m1 109,329.00 566,324.22 Pemasangan Daun Pintu WPC + Finish ukuran 92 x 210 cm 1.00 unit 1,364,728.00 1,364,728.00 Pemasangan Engsl Pintu 1.50 bh 42,709.25 64,063.88 Pemasangan Handle + Kunci 1.00 bh 145,576.00 145,576.00

2,140,692.10

Pekerjaan Kusen Jendela Type J1Pemasangan Kusen Alumunium Profil 4" 13.00 m1 109,329.00 1,421,277.00 Pemasangan Selimar Aluminium Daun Jendela 4.80 m1 78,952.17 378,970.42 Pemasangan Kaca Bening 2.45 m2 122,945.25 300,871.62 Pemasangan casement 4.00 bh 51,139.50 204,558.00 Friction Stay 16" 2.00 bh 68,000.00 136,000.00 Friction Stay 12" 2.00 bh 52,000.00 104,000.00

2,545,677.03

Pekerjaan Kusen Jendela Type J2Pemasangan Kusen Alumunium Profil 4" 5.38 m1 109,329.00 588,190.02 Pemasangan Selimar Aluminium Daun Jendela 3.20 m1 78,952.17 252,646.94 Pemasangan Kaca Bening 0.63 m2 122,945.25 77,455.51 Pemasangan Engsl Jendela casement 2.00 bh 51,139.50 102,279.00 Pemasangan Grendel Jendela 1.00 bh 52,000.00 52,000.00

1,072,571.47

Pas. Kusen Type BVPemasangan Kusen Alumunium Profil 4" 2.56 m1 109,329.00 279,882.24 Pemasangan Kaca Bening 0.46 m2 122,945.25 56,653.17

336,535.41

Pekerjaan Kusen Jendela Type BV1Pemasangan Kusen Alumunium Profil 4" 2.50 m1 109,329.00 273,322.50 Pemasangan Kaca Bening 0.38 m2 122,945.25 46,719.20

320,041.70

Pekerjaan Pagar Selasar m1Ongkos Pemasangan Pipa Galvanis termasuk Elektrode 1.2000 m 9,283.25 11,139.90Pipa Galvanis Med Diameter 2,5" 1.0000 m 90,250.00 90,250.00Pipa Galvanis Med Diameter 2" 0.2000 m 71,125.00 14,225.00

Jumlah: 115,614.90Nilai HSPK : 115,614.00

Pemasangan Sunscreen Rangka Aluminium 4" Isian Aluminium Profil Z m1Upah:Mandor 0.0021 O.H 97,000.00 203.70 Kepala Tukang Kayu 0.0043 O.H 95,000.00 408.50 Tukang Kayu 0.0430 O.H 92,500.00 3,977.50 Pekerja 0.0430 O.H 89,100.00 3,831.30

Jumlah: 8,421.00 Bahan:Aluminium Coklat , Profil 4" 3.3000 m1 90,000.00 297,000.00 Kisi-kisi Aluminium profil Z 12.8700 m1 13,500.00 173,745.00 Skrup/Ripet 45.0000 Buah 150.00 6,750.00

Jumlah: 477,495.00 Nilai HSPK : 485,916.00

Page 47: Rab Sd Petemon 12

Pemasangan Pipa Galvanis Termasuk Elektrode m1Upah:Mandor 0.0020 O.H 97,000.00 194.00 Tukang Besi 0.0600 O.H 95,000.00 5,700.00 Pekerja 0.0280 O.H 89,100.00 2,494.80

Bahan:Elektroda Baja 0.0060 kg 49,325.00 295.95

Sewa Peralatan:Sewa Welding Set (min 5 jam) 0.0210 Hari 28,500.00 598.50

Jumlah: 9,283.25 Nilai HSPK : 9,283.25

Pekerjaan Pagar Selasar m1

Ongkos Pemasangan Pipa Galvanis termasuk Elektrode 1.2000 m 9,283.25 11,139.90 Pipa Galvanis Med Diameter 2,5" 1.0000 m 90,250.00 90,250.00 Pipa Galvanis Med Diameter 2" 0.2000 m 71,125.00 14,225.00

Jumlah: 115,614.90

Nilai HSPK : 115,614.90

Pemasangan Gril Penutup Saluran m1

Ongkos Pemasangan termasuk Elektrode 1.2000 m 9,283.25 11,139.90 Besi siku 50.50.5 36.9000 kg 7,300.00 269,370.00

Jumlah: 280,509.90

Nilai HSPK : 280,509.90

Pemasangan Plafond Rangka Hollow Galvalum m2Upah:Mandor 0.0750 O.H 97,000.00 7,275.00 Kepala Tukang Besi 0.0250 O.H 95,000.00 2,375.00 Pekerja 0.2500 O.H 89,100.00 22,275.00 Tukang Besi 0.1500 O.H 92,500.00 13,875.00

Jumlah: 45,800.00 Bahan:Metal furing 2/4 cm ex. Sakura trust, bluscoopsteel 2.7500 m' 13,500.00 37,125.00 Kalsiboard Uk.240 x 120 x 4 mm 0.3819 Lembar 72,890.00 27,836.69 Pku Skrup 12.0000 Buah 150.00 1,800.00

Jumlah: 66,761.69 Nilai HSPK : 112,561.69

Pemasangan List Plafond Gypsum m1Upah:Mandor 0.0030 O.H 97,000.00 291.00 Kepala Tukang Kayu 0.0050 O.H 95,000.00 475.00 Tukang Kayu 0.0500 O.H 92,500.00 4,625.00 Pekerja 0.0500 O.H 89,100.00 4,455.00

Jumlah: 9,846.00 Bahan:List Gypsum 1.0500 m1 9,300.00 9,765.00 Lem 0.0200 Buah 14,000.00 280.00

Jumlah: 10,045.00 Nilai HSPK : 19,891.00

Pemasangan List Plafond Kayu 1/4 m1Upah:Mandor 0.0030 O.H 97,000.00 291.00 Kepala Tukang Kayu 0.0050 O.H 95,000.00 475.00 Tukang Kayu 0.0500 O.H 92,500.00 4,625.00 Pekerja 0.0500 O.H 89,100.00 4,455.00

Jumlah: 9,846.00 Bahan:List kayu 1/4 1.0500 m1 10,000.00 10,500.00 Paku 0.0324 kg 12,500.00 405.00

Jumlah: 10,905.00 Nilai HSPK : 20,751.00

Plamur Tembok m2Upah:Mandor 0.0010 O.H 97,000.00 97.00 Kepala Tukang Cat 0.0030 O.H 95,000.00 285.00 Tukang Cat 0.0300 O.H 92,500.00 2,775.00 Pekerja 0.0200 O.H 89,100.00 1,782.00

Jumlah: 4,939.00 Bahan:Plamur Tembok 0.1000 Kg 46,000.00 4,600.00 Kertas Gosok no 150 0.5000 Lembar 8,750.00 4,375.00

Jumlah: 8,975.00 Nilai HSPK : 13,914.00

B521
andrik-cakep: INI UNTUK KETEBALAN PIPA BERAPA JENIS ELEKTRODANYA APA
B544
andrik-cakep: INI UNTUK KETEBALAN PIPA BERAPA JENIS ELEKTRODANYA APA
Page 48: Rab Sd Petemon 12

Pengecatan Dinding Interior (Enamel/Spotless) m2Upah:Mandor 0.0025 O.H 97,000.00 242.50 Kepala Tukang Cat 0.0042 O.H 95,000.00 399.00 Tukang Cat 0.0420 O.H 92,500.00 3,885.00 Pekerja 0.0280 O.H 89,100.00 2,494.80

Jumlah: 7,021.30 Bahan:Cat Dinding Enamel/Spotless 0.0360 kaleng 44,281.60 1,594.14 Cat Dasar 0.1200 kg 24,600.00 2,952.00 Plamur Tembok 1.0000 m2 13,914.00 13,914.00

Jumlah: 18,460.14 Nilai HSPK : 25,481.44

Pengecatan Dinding Exterior (Weathershield) m2Upah:Mandor 0.0025 O.H 97,000.00 242.50 Kepala Tukang Cat 0.0075 O.H 95,000.00 712.50 Tukang Cat 0.0750 O.H 92,500.00 6,937.50 Pekerja 0.0500 O.H 89,100.00 4,455.00

Jumlah: 12,347.50 Bahan:Cat Alkali 0.0840 kg 25,000.00 2,100.00 Cat Weathershield 0.2520 kg 60,000.00 15,120.00

Jumlah: 17,220.00 Nilai HSPK : 29,567.50

Pengecatan Besi m2Upah:Mandor 0.0200 O.H 97,000.00 1,940.00 Kepala Tukang Cat 0.0400 O.H 95,000.00 3,800.00 Tukang Cat 0.4000 O.H 92,500.00 37,000.00 Pekerja 0.0400 O.H 89,100.00 3,564.00

Jumlah: 46,304.00 Bahan:Cat Meni (besi) 0.1000 Kg 32,000.00 3,200.00 Cat Besi doff 0.3000 Kg 45,700.00 13,710.00

Jumlah: 16,910.00 Nilai HSPK : 63,214.00

Pengecatan Menie Besi m2Upah:Mandor 0.0050 O.H 97,000.00 485.00 Kepala Tukang Cat 0.0100 O.H 95,000.00 950.00 Tukang Cat 0.1000 O.H 92,500.00 9,250.00 Pekerja 0.0100 O.H 89,100.00 891.00

Jumlah: 11,576.00 Bahan:Cat Meni (besi) 0.1000 Kg 32,000.00 3,200.00

Jumlah: 3,200.00 Nilai HSPK : 14,776.00

Pelapisan Waterproofing m2Upah:Mandor 0.0025 O.H 97,000.00 242.50 Kepala Tukang Cat 0.0075 O.H 95,000.00 712.50 Tukang Cat 0.0750 O.H 92,500.00 6,937.50 Pekerja 0.0500 O.H 89,100.00 4,455.00

Jumlah: 12,347.50 Bahan:Waterproofing 0.3500 Kg 38,750.00 13,562.50 Serat Fiber 1.0000 m2 4,500.00 4,500.00

Jumlah: 18,062.50 Nilai HSPK : 30,410.00

Pemasangan Titik Stop Kontak Gedung TitikUpah:Kepala Tukang Listrik 0.0500 O.H 97,000.00 4,850.00 Tukang Listrik 0.2000 O.H 95,000.00 19,000.00 Pekerja 0.0010 O.H 89,100.00 89.10

Jumlah: 23,939.10 BahanStop Kontak 1.0000 Buah 18,500.00 18,500.00 Kabel NYA 500 Volt 2 x 2,5 mm2 10.0000 m1 6,500.00 65,000.00 Pipa Pralon 5/8 1.0000 Lonjor 5,000.00 5,000.00 T Doos Pvc 1.0000 Buah 1,750.00 1,750.00

Jumlah: 90,250.00 Nilai HSPK : 114,189.10

Page 49: Rab Sd Petemon 12

Pemasangan Titik Lampu Gedung TitikUpah:Kepala Tukang Listrik 0.0500 O.H 97,000.00 4,850.00 Tukang Listrik 0.5000 O.H 95,000.00 47,500.00 Pekerja 0.3000 O.H 89,100.00 26,730.00

Jumlah: 79,080.00 BahanIsolator 4.0000 Buah 5,500.00 22,000.00 Kabel NYA 500 Volt 2 x 2,5 mm2 10.0000 m1 6,500.00 65,000.00 Pipa Pralon 5/8 1.0000 Lonjor 5,000.00 5,000.00 T Doos Pvc 1.0000 Buah 1,750.00 1,750.00 Fiting Plafon 1.0000 Buah 42,500.00 42,500.00

Jumlah: 136,250.00 Nilai HSPK : 215,330.00

Pemasangan Saklar Tunggal TitikUpah:Kepala Tukang Listrik 0.0500 O.H 97,000.00 4,850.00 Tukang Listrik 0.2000 O.H 95,000.00 19,000.00 Pekerja 0.0010 O.H 89,100.00 89.10

Jumlah: 23,939.10 BahanSaklar Tunggal 1.0000 Buah 8,500.00 8,500.00

Jumlah: 8,500.00 Nilai HSPK : 32,439.10

Pemasangan Saklar Ganda Titik 32,439.10 Upah:Kepala Tukang Listrik 0.0500 O.H 97,000.00 4,850.00 Tukang Listrik 0.2000 O.H 95,000.00 19,000.00 Pekerja 0.0010 O.H 89,100.00 89.10

Jumlah: 23,939.10 BahanSaklar Ganda 1.0000 Buah 17,600.00 17,600.00

Jumlah: 17,600.00 Nilai HSPK : 41,539.10

Pemasangan Lampu TL Waterproof 2x36WUpah :Tukang Listrik 0.0200 O.H 95,000.00 1,900.00 Pekerja Terampil 0.0100 O.H 89,100.00 891.00

Jumlah: 2,791.00 Bahan :lampu TL waterproof 2x36watt 1.0000 Buah 590,000.00 590,000.00

Jumlah: 590,000.00 Nilai HSPK : 592,791.00

Pemasangan Lampu LED 5 Watt TitikUpah:Tukang Listrik 0.0200 O.H 95,000.00 1,900.00 Pekerja 0.0100 O.H 89,100.00 891.00

Jumlah: 2,791.00 BahanLampu LED 5 Watt 1.0000 Buah 65,000.00 65,000.00

Jumlah: 65,000.00 Nilai HSPK : 67,791.00

Pemasangan Lampu LED 10 Watt TitikUpah:Tukang Listrik 0.0200 O.H 95,000.00 1,900.00 Pekerja 0.0100 O.H 89,100.00 891.00

Jumlah: 2,791.00 BahanDownligth 4" 1.0000 Buah 22,500.00 22,500.00 Lampu LED 10 Watt 1.0000 Buah 80,000.00 80,000.00

Jumlah: 102,500.00 Nilai HSPK : 105,291.00

Pemasangan Panel Box MCB 9 Modul UnitUpah:Mandor 0.0800 O.H 97,000.00 7,760.00 Kepala Tukang Listrik 0.0800 O.H 95,000.00 7,600.00 Tukang Listrik 0.8000 O.H 92,500.00 74,000.00 Pekerja 1.2050 O.H 89,100.00 107,365.50

Jumlah: 196,725.50 BahanPanel Box 9 Modul + Lamp 1.0000 Buah 675,000.00 675,000.00

Jumlah: 675,000.00 Nilai HSPK : 871,725.50

Page 50: Rab Sd Petemon 12

Pemasangan Kabel NYY 4 x 16 mm2 mUpah:Mandor 0.0060 O.H 97,000.00 582.00 Tukang Listrik 0.0640 O.H 92,500.00 5,920.00

Jumlah: 6,502.00 BahanKabel NYY 4 x 16 mm2 1.0000 m 95,000.00 95,000.00

Jumlah: 95,000.00 Nilai HSPK : 101,502.00

Pemasangan Kabel NYA 10 mm2 mUpah:Mandor 0.0060 O.H 97,000.00 582.00 Tukang Listrik 0.0640 O.H 92,500.00 5,920.00

Jumlah: 6,502.00 BahanKabel NYA 10 mm2 1.0000 Buah 8,770.00 8,770.00

Jumlah: 8,770.00 Nilai HSPK : 15,272.00

Pemasangan MCCB 20 A buahUpah:Mandor 0.0300 O.H 97,000.00 2,910.00 Tukang Listrik 0.3400 O.H 92,500.00 31,450.00

Jumlah: 34,360.00 BahanMCCB 20 A 1.0000 Buah 40,250.00 40,250.00

Jumlah: 40,250.00 Nilai HSPK : 74,610.00

Kloset Duduk Porselen BuahUpah:Mandor 0.1600 O.H 97,000.00 15,520.00 Kepala Tukang Batu 0.0010 O.H 95,000.00 95.00 Tukang Batu 1.1000 O.H 92,500.00 101,750.00 Pekerja 3.3000 O.H 89,100.00 294,030.00

Jumlah: 411,395.00 Bahan:Closet Duduk Porselen 1.0000 Buah 2,000,000.00 2,000,000.00 Perlengkapan 6% harga closet 0.0600 Buah 2,000,000.00 120,000.00

Jumlah: 2,120,000.00 Nilai HSPK : 2,531,395.00

Kloset Duduk Porselen tanpa reservoir BuahUpah:Mandor 0.1600 O.H 97,000.00 15,520.00 Kepala Tukang Batu 0.0010 O.H 95,000.00 95.00 Tukang Batu 1.1000 O.H 92,500.00 101,750.00 Pekerja 3.3000 O.H 89,100.00 294,030.00

Jumlah: 411,395.00 Bahan:Closet Duduk Porselen tanpa reservoir 1.0000 Buah 700,000.00 700,000.00 Perlengkapan 6% harga closet 0.0600 Buah 700,000.00 42,000.00

Jumlah: 742,000.00 Nilai HSPK : 1,153,395.00

Kloset Jongkok BuahUpah:Mandor 0.1600 O.H 97,000.00 15,520.00 Kepala Tukang Batu 0.0010 O.H 95,000.00 95.00 Tukang Batu 1.1000 O.H 92,500.00 101,750.00 Pekerja 3.3000 O.H 89,100.00 294,030.00

Jumlah: 411,395.00 Bahan:Closet jongkok 1.0000 Buah 300,000.00 300,000.00 Semen PC (50kg) 0.1200 zak 71,000.00 8,520.00 Pasir Pasang 0.0100 m3 150,000.00 1,500.00

Jumlah: 310,020.00 Nilai HSPK : 721,415.00

Pemasangan Wastafel BuahUpah:Mandor 0.1000 O.H 97,000.00 9,700.00 Kepala Tukang Batu 0.1500 O.H 95,000.00 14,250.00 Tukang Batu 1.4500 O.H 92,500.00 134,125.00 Pekerja 1.2000 O.H 89,100.00 106,920.00

Jumlah: 264,995.00 Bahan:Wastafel 1.0000 Buah 327,000.00 327,000.00 Perlengkapan 12 % harga wastafel 0.1200 Buah 327,000.00 39,240.00 Cermin 50x70 cm 1.0000 Buah 182,000.00 182,000.00 Semen portland (50kg) 0.1200 Zak 71,000.00 8,520.00 Pasir Pasang 0.0100 m3 150,000.00 1,500.00

Jumlah: 558,260.00 Nilai HSPK : 823,255.00

Page 51: Rab Sd Petemon 12

Pemasangan Urinoir BuahUpah:Mandor 0.1000 O.H 97,000.00 9,700.00 Kepala Tukang Batu 0.1500 O.H 95,000.00 14,250.00 Tukang Batu 1.4500 O.H 92,500.00 134,125.00 Pekerja 1.2000 O.H 89,100.00 106,920.00

Jumlah: 264,995.00 Bahan:Urinoir 1.0000 Buah 450,000.00 450,000.00 Perlengkapan 12 % harga wastafel 0.1200 Buah 450,000.00 54,000.00 Semen portland (50kg) 0.1200 Zak 71,000.00 8,520.00 Pasir Pasang 0.0100 m3 150,000.00 1,500.00

Jumlah: 514,020.00 Nilai HSPK : 779,015.00

Pemasangan Avour BuahUpah:Kepala Tukang Pipa 0.0300 O.H 95,000.00 2,850.00 Tukang Pipa 0.1500 O.H 92,500.00 13,875.00

Jumlah: 16,725.00 Bahan:Avour 1.0000 Buah 17,500.00 17,500.00

Jumlah: 17,500.00 Nilai HSPK : 34,225.00

Pemasangan Kran Air BuahUpah:Kepala Tukang Pipa 0.0300 O.H 95,000.00 2,850.00 Tukang Pipa 0.1500 O.H 92,500.00 13,875.00

Jumlah: 16,725.00 Bahan:Kran Air 1.0000 Buah 30,000.00 30,000.00 Rol TBA 1.0000 Buah 3,000.00 3,000.00

Jumlah: 33,000.00 Nilai HSPK : 49,725.00

Pasang Pipa PVC D 4" m1Upah:Mandor 0.0018 O.H 97,000.00 174.60Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Pipa 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0360 O.H 89,100.00 3,207.60

Jumlah: 9,502.20Bahan:Pipa PVC 4'' type D Panjang 4 m 0.3000 btg 120,000.00 36,000.00

Jumlah: 36,000.00Nilai HSPK : 45,502.20

Pasang Pipa PVC D 3" m1Upah:Mandor 0.0018 O.H 97,000.00 174.60Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Pipa 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0360 O.H 89,100.00 3,207.60

Jumlah: 9,502.20

Bahan:Pipa PVC 3'' type D Panjang 4 m 0.3000 btg 80,000.00 24,000.00

Jumlah: 24,000.00Nilai HSPK : 33,502.20

Pasang Pipa PVC AW 1" m1Upah:Mandor 0.0018 O.H 97,000.00 174.60Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Pipa 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0360 O.H 89,100.00 3,207.60

Jumlah: 9,502.20

Bahan:Pipa PVC 1'' type AW Panjang 4 m 0.3000 btg 30,600.00 9,180.00

Jumlah: 9,180.00Nilai HSPK : 18,682.20

Pasang Pipa PVC AW 3/4" m1Upah:Mandor 0.0018 O.H 97,000.00 174.60Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Pipa 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0360 O.H 89,100.00 3,207.60

Jumlah: 9,502.20

Bahan:Pipa PVC 3/4'' type AW Panjang 4 m 0.3000 btg 25,400.00 7,620.00

Jumlah: 7,620.00Nilai HSPK : 17,122.20

Page 52: Rab Sd Petemon 12

Pekerjaan Sumur Resapan unit

Galian tanah 5.34114 m3 69,250.00 369,873.95Urug pasir 0.50868 m3 177,700.00 90,392.44Pasangan batu bata 1 PC : 5 PS 0.62172 m3 916,138.40 569,581.56Pasangan bata trasram 0.67824 m3 965,367.03 654,750.54Plesteran 1 PC : 3 PS 1.256 m2 57,976.92 72,819.01Tutup Plat beton t. 10 cm 0.11304 m3 5,352,184.34 605,010.92Pipa ventilasi galvanis O 2 " 1 unit 25,000.00 25,000.00Lapisan ijuk 11.304 kg 15,000.00 169,560.00Lapisan kerikil 0.471 m3 105,000.00 49,455.00Pasangan bata tanpa spesi 1.0362 m3 400,000.00 414,480.00

Jumlah: 3,020,923.41Nilai HSPK : 3,045,923.41

unitUpah:Kepala Tukang Pipa 0.0300 O.H 95,000.00 2,850.00 Tukang Pipa 0.1500 O.H 92,500.00 13,875.00

Jumlah: 16,725.00 Bahan:Pompa elektric (kapasitas hisap 30m,dorong 30m ) 1.0000 unit 950,000.00 950,000.00Rol TBA 1.0000 Buah 3,000.00 3,000.00

Jumlah: 950,000.00Nilai HSPK : 966,725.00

Pemasangan Pipa Pagar HollowUpah:Mandor 0.002 O.H 97,000.00 194.00 Tukang Besi 0.06 O.H 92,500.00 5,550.00 Pekerja 0.028 O.H 89,100.00 2,494.80

Jumlah: 8,238.80Bahan:Elektroda Baja 0.006 kg 49,325.00 295.95 Hollow 20x40 7.65 m' 19,500.00 149,175.00 Hollow 50x50 4 m' 45,000.00 180,000.00

Jumlah: 329,470.95Sewa Peralatan:Sewa Welding Set (min 5 jam) 0.021 Hari 28,500.00 598.50

Jumlah: 598.50 - 338,308.25

Page 53: Rab Sd Petemon 12

PEKERJAAN BETONLantai Kerja K-175 m3 SNI 7394:2008 (6.4)Upah:Mandor 0.08 O.H 97,000.00 8,051.00 Kepala Tukang Batu 0.03 O.H 95,000.00 2,660.00 Tukang batu 0.28 O.H 92,500.00 25,437.50 Pekerja 1.65 O.H 89,100.00 147,015.00

Jumlah: 183,163.50 Bahan:Semen portland (40kg) 8.15 Zak 57,000.00 464,550.00 Pasir Beton 0.48 m3 187,500.00 90,117.19 Batu Pecah Mesin 1/2 cm 0.54 m3 250,000.00 135,394.74 Air (biaya air tawar) 215.00 Liter 30.00 6,450.00

Jumlah: 696,511.92 Nilai HSPK : 879,675.42

Pekerjaan Beton K-250 m3 SNI 7394:2008 (6.7)Upah:Mandor 0.08 O.H 97,000.00 8,051.00 Kepala Tukang Batu 0.03 O.H 95,000.00 2,660.00 Tukang batu 0.28 O.H 92,500.00 25,437.50 Pekerja 1.65 O.H 89,100.00 147,015.00

Jumlah: 183,163.50 Bahan:Semen portland (40kg) 9.60 Zak 57,000.00 547,200.00 Pasir Beton 0.43 m3 187,500.00 81,093.75 Batu Pecah Mesin 1/2 cm 0.55 m3 250,000.00 136,700.00 Air (biaya air tawar) 215.00 Liter 30.00 6,450.00

Jumlah: 771,443.75 Nilai HSPK : 954,607.25

Pekerjaan Lubang Bored Pile Ø 40 cm m SNI 7394:2008 (6.7)Upah:Mandor 0.06 O.H 97,000.00 5,645.40 Pekerja 0.30 O.H 89,100.00 26,730.00

Jumlah: 32,375.40 Bahan:Sewa Alat Bantu Bor Strouss (Alat) 0.25 jam 275,000.00 68,750.00

- Jumlah: 68,750.00

Nilai HSPK : 101,125.40

Pekerjaan Beton Lunak m3 SNI 7394:2008 (6.7)Upah:Mandor 0.03 O.H 97,000.00 2,910.00 Kepala Tukang Batu 0.01 O.H 95,000.00 950.00 Tukang batu 0.10 O.H 92,500.00 9,250.00 Pekerja 0.40 O.H 89,100.00 35,640.00

Jumlah: 48,750.00 Bahan:Semen portland (40kg) 1.00 Zak 57,000.00 57,000.00 Pasir Beton 0.90 m3 187,500.00 168,750.00 Air (biaya air tawar) 215.00 Liter 30.00 6,450.00

Jumlah: 232,200.00 Nilai HSPK : 280,950.00

kg SNI 7394:2008 (6.17)Upah:Mandor 0.00 O.H 97,000.00 38.80 Kepala Tukang Besi 0.00 O.H 95,000.00 66.50 Tukang Besi 0.01 O.H 92,500.00 647.50 Pekerja 0.01 O.H 89,100.00 623.70

Jumlah: 1,376.50 Bahan:Besi Beton (polos) 1.05 Kg 9,200.00 9,660.00 Kawat Beton 0.02 Kg 14,500.00 217.50

Jumlah: 9,877.50 Nilai HSPK : 11,254.00

Pekerjaan Bekisting Sloof m2 SNI 7394:2008 (6.21)Upah:Mandor 0.03 O.H 97,000.00 2,522.00 Kepala Tukang kayu 0.03 O.H 95,000.00 2,470.00 Tukang Kayu 0.26 O.H 92,500.00 24,050.00 Pekerja 0.52 O.H 89,100.00 46,332.00

Jumlah: 75,374.00 Bahan:Kayu meranti bekisting 0.05 m3 3,500,000.00 157,500.00 Paku Usuk 0.30 Kg 13,850.00 4,155.00 Minyak Bekisting 0.10 ltr 8,500.00 850.00

Jumlah: 162,505.00 Asumsi Pemakaian Bahan 2 x PakaiTenaga 1.50 x 75,374.00 113,061.00 Bahan 1.00 x 162,505.00 162,505.00

275,566.00 Nilai HSPK : 275,566.00

Pekerjaan Pembesian dengan besi beton (polos/ulir)

Page 54: Rab Sd Petemon 12

Pekerjaan Bekisting Kolom m2 SNI 7394:2008 (6.22)Upah:Mandor 0.03 O.H 97,000.00 3,201.00 Kepala Tukang kayu 0.03 O.H 95,000.00 3,135.00 Tukang Kayu 0.33 O.H 92,500.00 30,525.00 Pekerja 0.66 O.H 89,100.00 58,806.00

Jumlah: 95,667.00 Bahan:Kayu meranti bekisting 0.04 m3 3,500,000.00 140,000.00 Paku Usuk 0.40 Kg 13,850.00 5,540.00 Minyak Bekisting 0.20 ltr 8,500.00 1,700.00 Kayu Meranti balok 3/5 0.02 m3 4,816,666.67 72,250.00 Triplek Phenolic 1 sisi 12 mm uk. 122 x 244 cm 0.35 lembar 210,000.00 73,500.00 Dolken kayu gelam dia 8-10 cm, panjang 4m 2.00 btg 6,800.00 13,600.00

Jumlah: 306,590.00 Asumsi Pemakaian Bahan 2 x PakaiTenaga 1.50 x 95,667.00 143,500.50 Bahan 1.00 x 306,590.00 306,590.00

450,090.50 Nilai HSPK : 450,090.50

Pekerjaan Bekisting Balok m2 SNI 7394:2008 (6.23)Upah:Mandor 0.03 O.H 97,000.00 3,201.00 Kepala Tukang kayu 0.03 O.H 95,000.00 3,135.00 Tukang Kayu 0.33 O.H 92,500.00 30,525.00 Pekerja 0.66 O.H 89,100.00 58,806.00

Jumlah: 95,667.00 Bahan:Kayu meranti bekisting 0.04 m3 3,500,000.00 140,000.00 Paku Usuk 0.40 Kg 13,850.00 5,540.00 Minyak Bekisting 0.20 ltr 8,500.00 1,700.00 Kayu Meranti balok 3/5 0.02 m3 4,816,666.67 86,700.00 Triplek Phenolic 1 sisi 12 mm uk. 122 x 244 cm 0.35 lembar 210,000.00 73,500.00 Dolken kayu gelam dia 8-10 cm, panjang 4m 2.00 btg 6,800.00 13,600.00

Jumlah: 321,040.00

Asumsi Pemakaian Bahan 2 x PakaiTenaga 1.50 x 95,667.00 143,500.50 Bahan 1.00 x 321,040.00 321,040.00

464,540.50 Nilai HSPK : 464,540.50

Pekerjaan Bekisting Lantai m2 SNI 7394:2008 (6.24)Upah:Mandor 0.03 O.H 97,000.00 3,201.00 Kepala Tukang kayu 0.03 O.H 95,000.00 3,135.00 Tukang Kayu 0.33 O.H 92,500.00 30,525.00 Pekerja 0.66 O.H 89,100.00 58,806.00

Jumlah: 95,667.00 Bahan:Kayu meranti bekisting 0.04 m3 3,500,000.00 140,000.00 Paku Usuk 0.40 Kg 13,850.00 5,540.00 Minyak Bekisting 0.20 ltr 8,500.00 1,700.00 Kayu Meranti balok 3/5 0.02 m3 4,816,666.67 72,250.00 Triplek Phenolic 1 sisi 12 mm uk. 122 x 244 cm 0.35 lembar 210,000.00 73,500.00 Dolken kayu gelam dia 8-10 cm, panjang 4m 6.00 btg 6,800.00 40,800.00

Jumlah: 333,790.00 Asumsi Pemakaian Bahan 2 x PakaiTenaga 1.50 x 95,667.00 143,500.50 Bahan 1.00 x 333,790.00 333,790.00

477,290.50 Nilai HSPK : 477,290.50

Pekerjaan Bekisting Tangga m2 SNI 7394:2008 (6.26)Upah:Mandor 0.03 O.H 97,000.00 3,201.00 Kepala Tukang kayu 0.03 O.H 95,000.00 3,135.00 Tukang Kayu 0.33 O.H 92,500.00 30,525.00 Pekerja 0.66 O.H 89,100.00 58,806.00

Jumlah: 95,667.00 Bahan:Kayu meranti bekisting 0.03 m3 3,500,000.00 105,000.00 Paku Usuk 0.40 Kg 13,850.00 5,540.00 Minyak Bekisting 0.15 ltr 8,500.00 1,275.00 Kayu Meranti balok 3/5 0.02 m3 4,816,666.67 72,250.00 Triplek Phenolic 1 sisi 12 mm uk. 122 x 244 cm 0.35 lembar 210,000.00 73,500.00 Dolken kayu gelam dia 8-10 cm, panjang 4m 2.00 btg 6,800.00 13,600.00

Jumlah: 271,165.00 Asumsi Pemakaian Bahan 2 x PakaiTenaga 1.50 x 95,667.00 143,500.50 Bahan 1.00 x 271,165.00 271,165.00

414,665.50 Nilai HSPK : 414,665.50

Pembongkaran Cetakan m2 Upah:Mandor 0.03 O.H 97,000.00 2,425.00 Pekerja 0.05 O.H 89,100.00 4,455.00

Jumlah: 6,880.00 Nilai HSPK : 6,880.00

Page 55: Rab Sd Petemon 12

Pemancangan Tiang Pancang m1 (≥ 200m) m1Upah:Mandor 0.13 O.H 97,000.00 12,125.00

Jumlah: 12,125.00 Bahan:Tiang Pancang 2525 cm 1.00 m 189,200.00 189,200.00

Jumlah: 189,200.00 Sewa Peralatan:

0.22 Jam 130,625.00 28,476.25

0.22 Jam 175,750.00 38,313.50

Jumlah: 66,789.75 Nilai HSPK : 268,114.75

m3Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 35.96 Kg 11,254.00 404,721.98 Pembesian dengan besi Ulir 58.07 Kg 11,254.00 653,484.21

Jumlah: 2,012,813.43 Nilai HSPK : 2,012,813.43

Pekerjaan Sloof S1 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 31.56 Kg 11,254.00 355,230.26 Pembesian dengan besi Ulir 83.35 Kg 11,254.00 938,029.90 Bekisting Sloof 4.00 m2 275,566.00 1,102,264.00 Pembongkaran Cetakan 4.00 m2 6,880.00 27,520.00

Jumlah: 3,377,651.41 Nilai HSPK : 3,377,651.41

Pekerjaan Sloof S2 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 52.31 Kg 11,254.00 588,667.29 Pembesian dengan besi Ulir 89.30 Kg 11,254.00 1,005,032.04 Bekisting Sloof 5.00 m2 275,566.00 1,377,830.00 Pembongkaran Cetakan 5.00 m2 6,880.00 34,400.00

Jumlah: 3,960,536.58 Nilai HSPK : 3,960,536.58

Pekerjaan Sloof S3 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 47.80 Kg 11,254.00 537,920.11 Pembesian dengan besi Ulir 89.30 Kg 11,254.00 1,005,032.04 Bekisting Sloof 5.00 m2 275,566.00 1,377,830.00 Pembongkaran Cetakan 5.00 m2 6,880.00 34,400.00

Jumlah: 3,909,789.40 Nilai HSPK : 3,909,789.40

Pekerjaan Sloof S4 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 156.98 Kg 11,254.00 1,766,678.49 Bekisting Sloof 6.67 m2 275,566.00 1,837,106.67 Pembongkaran Cetakan 6.67 m2 6,880.00 45,866.67

Jumlah: 4,604,259.07 Nilai HSPK : 4,604,259.07

Pekerjaan Poer P1 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian dengan besi Ulir 156.18 Kg 11,254.00 1,757,649.72 Bekisting Poer 1.22 m2 275,566.00 337,292.78 Pembongkaran Cetakan 1.22 m2 6,880.00 8,421.12

Jumlah: 3,057,970.87 Nilai HSPK : 3,057,970.87

Pekerjaan Poer P2 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian dengan besi Ulir 106.11 Kg 11,254.00 1,194,192.63 Bekisting Poer 2.25 m2 275,566.00 619,071.08 Pembongkaran Cetakan 2.25 m2 6,880.00 15,456.22

Jumlah: 2,783,327.19 Nilai HSPK : 2,783,327.19

Pekerjaan Poer P3 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian dengan besi Ulir 179.35 Kg 11,254.00 2,018,353.75 Bekisting Poer 0.91 m2 275,566.00 250,514.55 Pembongkaran Cetakan 0.91 m2 6,880.00 6,254.55

Jumlah: 3,229,730.09 Nilai HSPK : 3,229,730.09

Pekerjaan Poer P4 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian dengan besi Ulir 92.61 Kg 11,254.00 1,042,255.45 Bekisting Poer 2.22 m2 275,566.00 612,368.89 Pembongkaran Cetakan 2.22 m2 6,880.00 15,288.89

Jumlah: 2,624,520.48 Nilai HSPK : 2,624,520.48

Pekerjaan Kolom K1 30/40 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 53.43 Kg 11,254.00 601,301.22 Pembesian dengan besi Ulir 69.46 Kg 11,254.00 781,691.59 Bekisting Kolom 3.89 m2 450,090.50 1,750,351.94 Pembongkaran Cetakan 3.89 m2 6,880.00 26,755.56

Jumlah: 4,114,707.56 Nilai HSPK : 4,114,707.56

Sewa Crane 30 ton - min. 8 jam (termasuk mob/demob, operator, BBM)

Sewa Hammer tiang pancang - min. 8 jam(termasuk mob/demob, operator, BBM)

Pekerrjaan Bor Pile Ø 40cm

Page 56: Rab Sd Petemon 12

Pekerjaan Kolom K1 30/40 (Stek Lt.2) m3 Pekerjaan Beton Berstruktur K-175 1.00 m3 879,675.42 879,675.42 Pembesian Besi Beton Polos 53.43 Kg 11,254.00 601,301.22 Pembesian dengan besi Ulir 69.46 Kg 11,254.00 781,691.59 Bekisting Kolom 3.89 m2 450,090.50 1,750,351.94 Pembongkaran Cetakan 3.89 m2 6,880.00 26,755.56

Jumlah: 4,039,775.73 Nilai HSPK : 4,039,775.73

Pekerjaan Kolom K2 20/20 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 53.92 Kg 11,254.00 606,851.69 Pembesian Besi Beton Ulir 208.38 Kg 11,254.00 2,345,074.76 Bekisting Kolom 6.67 m2 450,090.50 3,000,603.33 Pembongkaran Cetakan 6.67 m2 6,880.00 45,866.67

Jumlah: 6,953,003.70 Nilai HSPK : 6,953,003.70

Pekerjaan Kolom K2 20/20 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 879,675.42 879,675.42 Pembesian Besi Beton Polos 53.92 Kg 11,254.00 606,851.69 Pembesian Besi Beton Ulir 208.38 Kg 11,254.00 2,345,074.76 Bekisting Kolom 6.67 m2 450,090.50 3,000,603.33 Pembongkaran Cetakan 6.67 m2 6,880.00 45,866.67

Jumlah: 6,878,071.88 Nilai HSPK : 6,878,071.88

Pekerjaan Kolom KP 12/12 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 214.41 Kg 11,254.00 2,412,913.87 Bekisting Kolom (3 x pakai) 5.56 m2 450,090.50 2,500,502.78 Pembongkaran Cetakan 5.56 m2 6,880.00 38,222.22

Jumlah: 5,906,246.12 Nilai HSPK : 5,906,246.12

Pekerjaan Kolom KP2 12/25 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 156.95 Kg 11,254.00 1,766,277.79 Bekisting Kolom (3 x pakai) 2.67 m2 450,090.50 1,200,241.33 Pembongkaran Cetakan 2.67 m2 6,880.00 18,346.67

Jumlah: 3,939,473.04 Nilai HSPK : 3,939,473.04

Pekerjaan Stekan Kolom K1 40/40 + Beton Lunak m3 Pekerjaan Beton Lunak 1.00 m3 280,950.00 280,950.00 Pembesian dengan besi Ulir 69.46 Kg 11,254.00 781,691.59 Bekisting Kolom 1.94 m2 450,090.50 875,175.97 Pembongkaran Cetakan 1.94 m2 6,880.00 13,377.78

Jumlah: 1,951,195.34 Nilai HSPK : 1,951,195.34

Pekerjaan Stekan Kolom K2 30/30 + Beton Lunak m3 Pekerjaan Beton Lunak 1.00 m3 280,950.00 280,950.00 Pembesian dengan besi Ulir 208.38 Kg 11,254.00 2,345,074.76 Bekisting Kolom 5.00 m2 450,090.50 2,250,452.50 Pembongkaran Cetakan 5.00 m2 6,880.00 34,400.00

Jumlah: 4,910,877.26 Nilai HSPK : 4,910,877.26

Pekerjaan Stekan Kolom KP ttk Pembesian Besi Beton Polos 2.47 Kg 11,254.00 27,774.87

Jumlah: 27,774.87 Nilai HSPK : 27,774.87

Pekerjaan Balok B1 30/60 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 33.27 Kg 11,254.00 374,436.66 Pembesian dengan besi Ulir 78.91 Kg 11,254.00 888,075.65 Bekisting Balok 3.83 m2 450,090.50 1,725,346.92 Pembongkaran Cetakan 3.83 m2 6,880.00 26,373.33

Jumlah: 3,968,839.81 Nilai HSPK : 3,968,839.81

Balok B1A 30/60 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 33.27 Kg 11,254.00 374,436.66 Pembesian dengan besi Ulir 131.52 Kg 11,254.00 1,480,126.08 Bekisting Balok 3.83 m2 450,090.50 1,725,346.92 Pembongkaran Cetakan 3.83 m2 6,880.00 26,373.33

Jumlah: 4,560,890.24 Nilai HSPK : 4,560,890.24

Balok B1B 30/60 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 33.27 Kg 11,254.00 374,436.66 Pembesian dengan besi Ulir 105.22 Kg 11,254.00 1,184,100.86 Bekisting Balok 3.83 m2 450,090.50 1,725,346.92 Pembongkaran Cetakan 3.83 m2 6,880.00 26,373.33

Page 57: Rab Sd Petemon 12

Jumlah: 4,264,865.02 Nilai HSPK : 4,264,865.02

Balok B2 20/40 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 48.44 Kg 11,254.00 545,135.72 Pembesian dengan besi Ulir 98.64 Kg 11,254.00 1,110,094.56 Bekisting Balok 5.50 m2 450,090.50 2,475,497.75 Pembongkaran Cetakan 5.50 m2 6,880.00 37,840.00

Jumlah: 5,123,175.28

Balok B3 20/35 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 32.21 Kg 11,254.00 362,479.86 Pembesian dengan besi Ulir 74.42 Kg 11,254.00 837,526.70 Bekisting Balok 5.57 m2 450,090.50 2,507,647.07 Pembongkaran Cetakan 5.57 m2 6,880.00 38,331.43

Jumlah: 4,700,592.31 Nilai HSPK : 4,700,592.31

Balok B4 15/25 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 42.09 Kg 11,254.00 473,640.35 Pembesian Besi Beton Polos 110.93 Kg 11,254.00 1,248,443.73 Bekisting Balok 4.71 m2 450,090.50 2,120,426.36 Pembongkaran Cetakan 4.71 m2 6,880.00 32,412.44

Jumlah: 4,829,530.13 Nilai HSPK : 4,829,530.13

Balok BK 25/50 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 45.14 Kg 11,254.00 508,037.71 Pembesian dengan besi Ulir 133.71 Kg 11,254.00 1,504,820.57 Bekisting Balok 4.52 m2 450,090.50 2,034,409.06 Pembongkaran Cetakan 4.52 m2 6,880.00 31,097.60

Jumlah: 5,032,972.20 Nilai HSPK : 5,032,972.20

Pekerjaan BALOK LATEI 12/20 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 172.89 Kg 11,254.00 1,945,749.08 Bekisting Balok (2xpakai) 8.33 m2 450,090.50 3,750,754.17 Pembongkaran Cetakan 8.33 m2 6,880.00 57,333.33

Jumlah: 6,708,443.83 Nilai HSPK : 6,708,443.83

Pekerjaan BALOK LEVEL BLV 12/20 m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 218.10 Kg 11,254.00 2,454,542.42 Bekisting Balok 8.33 m2 450,090.50 3,750,754.17 Pembongkaran Cetakan 8.33 m2 6,880.00 57,333.33

Jumlah: 7,217,237.17 Nilai HSPK : 7,217,237.17

Pekerjaan PLAT LEVEL TEBAL 8CM m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 138.13 Kg 11,254.00 1,554,488.06 Bekisting Plat 5.31 m2 477,290.50 2,535,605.78 Pembongkaran Cetakan 5.31 m2 6,880.00 36,550.00

Jumlah: 5,081,251.09 Nilai HSPK : 5,081,251.09

Pekerjaan Plat Lantai Tebal 12 cm Type A m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 174.26 Kg 11,254.00 1,961,167.06 Bekisting Plat 4.17 m2 477,290.50 1,988,710.42 Pembongkaran Cetakan 4.17 m2 6,880.00 28,666.67

Jumlah: 4,933,151.39 Nilai HSPK : 4,933,151.39

Pekerjaan Plat Lantai Tebal 12 cm Type B m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 147.96 Kg 11,254.00 1,665,141.84 Bekisting Plat 4.17 m2 477,290.50 1,988,710.42 Pembongkaran Cetakan 4.17 m2 6,880.00 28,666.67

Jumlah: 4,637,126.17 Nilai HSPK : 4,637,126.17

Pekerjaan Plat Tangga m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton 216.02 Kg 11,254.00 2,431,107.09 Bekisting Tangga 6.94 m2 450,090.50 3,125,628.47 Pembongkaran Cetakan 6.94 m2 6,880.00 47,777.78

Jumlah: 6,559,120.59 Nilai HSPK : 6,559,120.59

Pekerjaan Stekan Plat Tangga unit

Pembesian Besi Beton 18.72 Kg 11,254.00 210,674.88 Jumlah: 210,674.88

Nilai HSPK : 210,674.88

Pekerjaan Tutup Plat Beton Tebal 10 cm m3 Pekerjaan Beton Berstruktur K-250 1.00 m3 954,607.25 954,607.25 Pembesian Besi Beton Polos 175.65 Kg 11,254.00 1,976,724.59 Bekisting Plat 5.00 m2 477,290.50 2,386,452.50 Pembongkaran Cetakan 5.00 m2 6,880.00 34,400.00

Jumlah: 5,352,184.34 Nilai HSPK : 5,352,184.34

Page 58: Rab Sd Petemon 12

PEKERJAAN BETON / M3

BOR PILE Ø 40 cmTULANGAN Jarak PJG SATUAN JML BERAT/M JML BERAT (KG)

LUAS = 0.1256

BESI D13 7.9617834395 7 1.0419 58.0668

PJG= 12

Panjang/m3 7.961783 BESI Ø10 0.15 1.099 53.078556263 0.6165 35.9625

94.0293

POER P1

TULANGAN PJG SATUAN JML BERAT/M JML BERAT (KG)

PJG = 1.2

LBR = 1.2 BESI D16 3 7 1.58 33.1430

TGGI= 0.4 -

BESI D16 3 12 1.58 56.8166

volume 0.576 m3

bekisting per poer 1.92 m2 Jumlah Berat tulangan per poer 89.9597

bekisting per m3 1.728 m2

Jumlah Berat tulangan per m3 156.1800

POER P2TULANGAN PJG SATUAN JML BERAT/M JML BERAT (KG)

PJG = 2.2LBR = 1.2 BESI D16 5 7 1.58 55.2384 TGGI= 0.4 -

BESI D16 3 12 1.58 56.8166 volume 1.056 m3

bekisting per poer 2.72 m2 Jumlah Berat tulangan per poer 112.0550 bekisting per m3 2.448 m2

Jumlah Berat tulangan per m3 106.1127

POER P3TULANGAN PJG SATUAN JML BERAT/M JML BERAT (KG)

PJG = 2.2LBR = 1.2 BESI D16 5.2 8 1.58 65.6548 TGGI= 0.5 -

BESI D16 3.2 15 1.58 75.7555 PJG = 1.7LBR = 1 BESI D16 4.2 7 1.58 46.4003 TGGI= 0.5 -

BESI D16 2.8 10 1.58 44.1907

volume 1.736 m3

bekisting per poer 7.8 m2 Jumlah Berat tulangan per poer 232.0013 bekisting per m3 4.493087558 m2

Jumlah Berat tulangan per m3 133.6413

POER P3TULANGAN PJG SATUAN JML BERAT/M JML BERAT (KG)

PJG = 2.2LBR = 2.2 BESI D16 5 22 1.58 173.6064 TGGI= 0.4 -

BESI D16 5 22 1.58 173.6064 volume 1.936 m3

bekisting per poer 3.52 m2 Jumlah Berat tulangan per poer 347.2128 bekisting per m3 1.818181818 m2

Jumlah Berat tulangan per m3 179.3455

POER P4TULANGAN PJG SATUAN JML BERAT/M JML BERAT (KG)

PJG = 0.9LBR = 0.9 BESI D13 2.4 6 1.04 15.0031 TGGI= 0.4 -

BESI D13 2.4 6 1.04 15.0031 volume 0.324 m3

bekisting per poer 1.44 m2 Jumlah Berat tulangan per poer 30.0063 bekisting per m3 4.444444444 m2

Jumlah Berat tulangan per m3 92.6120

SLOOF S1 25/50TULANGAN JML PANJANG/M3 BERAT/M JML BERAT (KG)

PJG = 0.25LBR = 0.5 BESI D13 6 8 1.04 50.0105 Panjang/m3 8 BESI D13 4 8 1.04 33.3403

83.3508 BKSTG= 8 m2

BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø10 0.15 1.5 53.333333333 0.3946 31.5648

31.5648

SLOOF S2 20/35

Page 59: Rab Sd Petemon 12

TULANGAN JML PANJANG/M3 BERAT/M JML BERAT (KG) PJG = 0.2LBR = 0.35 BESI D13 6 14.285714286 1.04 89.3044 Panjang/m3 14.28571

BKSTG= 10 m2BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø8 0.125 1.16 114.28571429 0.3946 52.3074

SLOOF S3 20/35TULANGAN JML PANJANG/M3 BERAT/M JML BERAT (KG)

PJG = 0.2LBR = 0.35 BESI D13 6 14.285714286 1.04 89.3044 Panjang/m3 14.28571

BKSTG= 10 m2BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø8 0.125 1.06 114.28571429 0.3946 47.7981

SLOOF S4 15/25TULANGAN JML PANJANG/M3 BERAT/M JML BERAT (KG)

PJG = 0.15LBR = 0.25 BESI Ø 12 4 26.666666667 0.89 94.6944 Panjang/m3 26.66667

BKSTG= 13.33333 m2BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø8 0.125 0.74 213.33333333 0.3946 62.2879

KOLOM K1 30/40TULANGAN JML PANJANG/M3 BERAT/M JML BERAT (KG)

PJG = 0.3LBR = 0.4Panjang/m3 8.333333 8 8.3333333333 1.04 69.4590

BKSTG= 11.66667 m2BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø10 0.125 1.3 66.666666667 0.6165 53.4300

KOLOM K2 20/20TULANGAN JML PANJANG/M3 BERAT/M JML BERAT (KG)

PJG = 0.2LBR = 0.2Panjang/m3 25 8 25 1.04 208.3770

BKSTG= 20 m2BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø8 0.15 0.82 166.66666667 0.3946 53.9232

KOLOM KP 12/12TULANGAN JML TINGGI/M3 BERAT/M JML BERAT (KG)

PJG = 0.12LBR = 0.12Panjang/m3 69.44444 BESI Ø10 4 69.444444444 0.62 171.2500

BKSTG= 16.66667 m2BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø6 0.15 0.42 462.96296296 0.2219 43.1550

BALOK B1 30/60TULANGAN JML TINGGI/M3 BERAT/M JML BERAT (KG)

PJG = 0.6LBR = 0.3 BESI D16 6 5.5555555556 1.58 52.6080 TGGI= 5.555556 BESI D16 3 5.5555555556 1.58 26.3040

78.9120 BKSTG= 7.666667 m2

BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø10 0.175 1.7 31.746031746 0.62 33.2714

Balok B1A 30/60TULANGAN JML TINGGI/M3 BERAT/M JML BERAT (KG)

PJG = 0.6

BESI D16

BESI D13

Page 60: Rab Sd Petemon 12

LBR = 0.3 BESI D16 10 5.5555555556 1.58 87.6800 TGGI= 5.555556 BESI D16 5 5.5555555556 1.58 43.8400

131.5200 BKSTG= 7.666667 m2

BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø10 0.175 1.7 31.746031746 0.62 33.2714

Balok B1B 30/60TULANGAN JML TINGGI/M3 BERAT/M JML BERAT (KG)

PJG = 0.6LBR = 0.3 BESI D16 8 5.5555555556 1.58 70.1440 TGGI= 5.555556 BESI D16 4 5.5555555556 1.58 35.0720

105.2160 BKSTG= 7.666667 m2

BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø10 0.175 1.7 31.746031746 0.62 33.2714

Page 61: Rab Sd Petemon 12

Balok B2 20/40TULANGAN JML TINGGI/M3 BERAT/M JML BERAT (KG)

PJG = 0.4LBR = 0.2 BESI D16 3 12.5 1.58 59.1840 TGGI= 12.5 BESI D16 2 12.5 1.58 39.4560

98.6400 BKSTG= 11 m2

BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø10 0.175 1.1 71.428571429 0.62 48.4393

Balok B3 20/35TULANGAN JML TINGGI/M3 BERAT/M JML BERAT (KG)

PJG = 0.35LBR = 0.2 BESI D13 3 14.285714286 1.04 44.6522 TGGI= 14.28571 BESI D13 2 14.285714286 1.04 29.7681

74.4204 BKSTG= 11.14286 m2

BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø8 0.175 1 81.632653061 0.39 32.2090

Balok B4 15/25TULANGAN JML TINGGI/M3 BERAT/M JML BERAT (KG)

PJG = 0.25LBR = 0.15 BESI Ø12 2 26.666666667 1.04 55.4667 TGGI= 26.66667 BESI Ø12 2 26.666666667 1.04 55.4667

110.9333 BKSTG= 14.13333 m2

BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø8 0.175 0.7 152.38095238 0.3946 42.0864

Balok BK 25/50TULANGAN JML TINGGI/M3 BERAT/M JML BERAT (KG)

PJG = 0.5LBR = 0.25 BESI D16 4 8 1.58 50.5037 TGGI= 8 BESI D16 2 8 1.58 25.2518

75.7555 BKSTG= 9.04 m2

BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø10 0.175 1.4 45.714285714 0.62 39.4560

BALOK BK 20/40 - 20/30TULANGAN JML TINGGI/M3 BERAT/M JML BERAT (KG)

PJG = 0.2LBR = 0.35 BESI D13 9 14.285714286 1.04 133.7143 TGGI= 14.28571

BKSTG= 9 m2BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø8 0.125 1 114.28571429 0.3950 45.1429

BALOK BLP 15/20TULANGAN JML TINGGI/M3 BERAT/M JML BERAT (KG)

PJG = 0.2LBR = 0.15 BESI Ø12 4 33.333333333 0.888 118.4000 TGGI= 33.33333

BKSTG= 6.666667 m2BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø8 0.15 0.64 222.22222222 0.3950 56.1778

BALOK Latei BL 12/20TULANGAN JML TINGGI/M3 BERAT/M JML BERAT (KG)

PJG = 0.12LBR = 0.2 BESI Ø10 4 41.666666667 0.62 102.7500 TGGI= 41.66667

BKSTG= 16.66667 m2BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø8 0.15 0.64 277.77777778 0.3946 70.1440

BALOK LEVEL 12/20 TULANGAN JML TINGGI/M3 BERAT/M JML BERAT (KG)

PJG = 0.12LBR = 0.2 BESI Ø12 4 41.666666667 0.89 147.9600 TGGI= 41.66667

BKSTG= 16.66667 m2BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

Page 62: Rab Sd Petemon 12

BESI Ø8 0.15 0.64 277.77777778 0.3946 70.1440

BALOK JENDELA JD 30/35 TULANGAN JML TINGGI/M3 BERAT/M JML BERAT (KG)

PJG = 0.3LBR = 0.35 BESI Ø110 8 9.5238095238 0.62 46.9714 TGGI= 9.52381

BKSTG= 9.047619 m2BEGEL JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø6 0.15 1.24 63.492063492 0.2220 17.4781

PLAT LEVEL TEBAL 8CMTULANGAN JML PJG/M3 BERAT/M JML BERAT (KG)

PJG = 0.8TBL = 0.08 BESI Ø10 4 15.625 0.62 38.5313 PJG= 15.625 BESI Ø10 3 15.625 0.62 28.8984

67.4297 BKSTG= 10.625 m2

TULANGAN JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø10 0.15 1.1 104.16666667 0.617 70.6979

PLAT LISPLANK TEBAL 5CMTULANGAN JML PJG/M3 BERAT/M JML BERAT (KG)

TGG = 0.3TBL = 0.05 BESI Ø10 3 66.666666667 0.617 123.4000 PJG= 66.66667

BKSTG= 36.66667 m2TULANGAN JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

BESI Ø10 0.15 0.5 444.44444444 0.617 137.1111

PLAT LANTAI TYPE A TEBAL 12CMasumsi: TULANGAN JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

LBR = 1PJG = 1 ARAH PJG

BESI Ø10 0.25 1 4 0.62 2.4660 VOLUME 0.12 M3 0.25 1 4 0.62 2.4660

BESI Ø8 0.15 1 7 0.39 2.7619 0.15 1 7 0.39 2.7619

ARAH LBRBESI Ø10 0.25 1 4 0.62 2.4660

0.25 1 4 0.62 2.4660 BESI Ø8 0.15 1 7 0.39 2.7619

0.15 1 7 0.39 2.7619

JUMLAH 20.9117

JUMLAH DALAM M3 174.2640

BKSTG= 8.333333 m2

PLAT LANTAI TYPE B TEBAL 12CMasumsi: TULANGAN JRK PJG SATUAN JML BERAT/M JML BERAT (KG)

LBR = 1PJG = 1 ARAH PJG

BESI Ø10 0.3 1 4 0.62 2.4660 VOLUME 0.12 M3 0.3 1 4 0.62 2.4660

BESI Ø8 0.2 1 5 0.39 1.9728 0.2 1 5 0.39 1.9728

ARAH LBRBESI Ø10 0.3 1 4 0.62 2.4660

0.3 1 4 0.62 2.4660 BESI Ø8 0.2 1 5 0.39 1.9728

0.2 1 5 0.39 1.9728

JUMLAH 17.7552

JUMLAH DALAM M3 147.9600

BKSTG= 8.333333 m2

Page 63: Rab Sd Petemon 12

DAFTAR HARGA SATUAN POKOK KEGIATAN

C PEKERJAAN BESI DAN BAJAPemasangan Besi Profil (Baja Konstruksi) kgUpah:Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Las 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0600 O.H 89,100.00 5,346.00

Jumlah: 11,466.00

Bahan:Besi Profil WF 1.1500 kg 12,500.00 14,375.00Elektroda Baja 0.0200 kg 29,200.00 584.00Sewa Welding Set 0.0140 Hari 28,500.00 399.00

Jumlah: 15,358.00Nilai HSPK : 26,824.00 ok

Pemasangan Besi Profil C 100 mm s/d 150 mm kg

Upah:Mandor 0.0030 O.H 97,000.00 291.00Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Las 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0600 O.H 89,100.00 5,346.00

Jumlah: 11,757.00

Bahan:Besi Profil C 1.1500 kg 12,500.00 14,375.00Elektroda Baja 0.0200 kg 29,200.00 584.00Sewa Welding Set 0.0140 Hari 28,500.00 399.00

Jumlah: 15,358.00Nilai HSPK : 27,115.00 ok

m2

Upah:Mandor 0.0050 O.H 97,000.00 485.00Kepala Tukang 0.0100 O.H 95,000.00 950.00Tukang Las 0.1000 O.H 92,500.00 9,250.00Pekerja 0.4000 O.H 89,100.00 35,640.00

Jumlah: 46,325.00

Bahan:Usuk galvalum 5/7 cm tebal 0,55 mm 1.5625 m 25,000.00 39,062.50Reng galvalum tebal 0,45 mm 4.0000 m 18,500.00 74,000.00Skrup + plat 0.2500 kg 20,000.00 5,000.00

Jumlah: 118,062.50Nilai HSPK : 164,387.50 ok

Pemasangan Besi Plat Rib kgUpah:Mandor 0.0030 O.H 97,000.00 291.00Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Las 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0600 O.H 89,100.00 5,346.00

Jumlah: 11,757.00

Bahan:Besi Plat tebal 8mm 1.1500 kg 12,500.00 14,375.00Elektroda Baja 0.0200 kg 29,200.00 584.00Sewa Welding Set 0.0140 Hari 28,500.00 399.00

Jumlah: 15,358.00Nilai HSPK : 27,115.00

Pemasangan Besi Siku kgUpah:Mandor 0.0030 O.H 97,000.00 291.00Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Las 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0600 O.H 89,100.00 5,346.00

Jumlah: 11,757.00

Pemasangan Rangka Atap Galvalume (Reng + Usuk)

Page 64: Rab Sd Petemon 12

Bahan:Besi Profil siku 1.1500 kg 7,300.00 8,395.00Elektroda Baja 0.0200 kg 29,200.00 584.00Sewa Welding Set 0.0140 Hari 28,500.00 399.00

Jumlah: 9,378.00Nilai HSPK : 21,135.00

Pemasangan Besi Plat Flenders kgUpah:Mandor 0.0030 O.H 97,000.00 291.00Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Las 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0600 O.H 89,100.00 5,346.00

Jumlah: 11,757.00

Bahan:Besi Plat tebal 12mm 1.1500 kg 12,500.00 14,375.00

Elektroda Baja 0.0200 kg 29,200.00 584.00Sewa Welding Set 0.0140 Hari 28,500.00 399.00

Jumlah: 15,358.00Nilai HSPK : 27,115.00

Pemasangan Besi Plat Simpul kgUpah:Mandor 0.0030 O.H 97,000.00 291.00Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Las 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0600 O.H 89,100.00 5,346.00

Jumlah: 11,757.00

Bahan:Besi Plat tebal 12mm 1.1500 kg 12,500.00 14,375.00

Elektroda Baja 0.0200 kg 29,200.00 584.00Sewa Welding Set 0.0140 Hari 28,500.00 399.00

Jumlah: 15,358.00Nilai HSPK : 27,115.00

kg

Upah:Mandor 0.0030 O.H 97,000.00 291.00Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Las 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0600 O.H 89,100.00 5,346.00

Jumlah: 11,757.00

Bahan:Besi Polos dia 8mm 1.1500 kg 9,200.00 10,580.00

Jumlah: 10,580.00Nilai HSPK : 22,337.00

Pemasangan Besi Ikatan Angin dia 12 mm kgUpah:Mandor 0.0030 O.H 97,000.00 291.00Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Las 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0600 O.H 89,100.00 5,346.00

Jumlah: 11,757.00

Bahan:Besi Polos dia 12mm 1.1500 kg 9,200.00 10,580.00

Jumlah: 10,580.00Nilai HSPK : 22,337.00

Pemasangan Besi Track Stank dia 16 mm kgUpah:Mandor 0.0030 O.H 97,000.00 291.00Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Las 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0600 O.H 89,100.00 5,346.00

Jumlah: 11,757.00

Bahan:Besi Polos dia 16mm 1.1500 kg 9,200.00 10,580.00

Jumlah: 10,580.00Nilai HSPK : 22,337.00

Pemasangan Ankur Bolt dia 19 mm buahUpah:Mandor 0.0030 O.H 97,000.00 291.00Kepala Tukang 0.0060 O.H 95,000.00 570.00Pekerja 0.0600 O.H 89,100.00 5,346.00

Jumlah: 6,207.00

Bahan:Ankur Bolt dia 19 mm 1.0000 buah 30,000.00 30,000.00

Jumlah: 30,000.00Nilai HSPK : 36,207.00

Pemasangan Besi Penggantung Gording dia 8mm

Page 65: Rab Sd Petemon 12

Pemasangan Mur Baut HTB 16 mm buahUpah:Mandor 0.0030 O.H 97,000.00 291.00Kepala Tukang 0.0060 O.H 95,000.00 570.00Pekerja 0.0060 O.H 89,100.00 534.60

Jumlah: 1,395.60

Bahan:Mur Baut HTB 16 mm 1.0000 buah 3,000.00 3,000.00

Jumlah: 3,000.00Nilai HSPK : 4,395.60

Pemasangan Penutup Atap Genteng m2Upah:Mandor 0.0080 O.H 97,000.00 776.00Kepala Tukang 0.0080 O.H 95,000.00 760.00Tukang Kayu 0.0750 O.H 92,500.00 6,937.50Pekerja 0.1500 O.H 97,000.00 14,550.00

Jumlah: 23,023.50

Bahan:Genteng Karang Pilang / Wisma 25.0000 buah 4,000.00 100,000.00

Jumlah: 100,000.00Nilai HSPK : 123,023.50

Pemasangan Wuwung Genteng m1Upah:Mandor 0.0020 O.H 97,000.00 194.00Kepala Tukang 0.0200 O.H 95,000.00 1,900.00Tukang Kayu 0.2000 O.H 92,500.00 18,500.00Pekerja 0.4000 O.H 97,000.00 38,800.00

Jumlah: 59,394.00

Bahan:Wuwung Genteng Karang Pilang / Wisma 5.0000 buah 12,300.00 61,500.00Semen PC @50kg 0.1600 zak 71,000.00 11,360.00Pasir Pasang 0.0323 m3 150,000.00 4,845.00

Jumlah: 77,705.00Nilai HSPK : 137,099.00

m1

Upah:Mandor 0.0050 O.H 97,000.00 485.00Kepala Tukang 0.0200 O.H 95,000.00 1,900.00Tukang Kayu 0.2000 O.H 92,500.00 18,500.00Pekerja 0.1000 O.H 97,000.00 9,700.00

Jumlah: 30,585.00

Bahan:Metal furing 2/4 cm ex. Sakura trust, bluscoopsteel 3.0000 m1 13,500.00 40,500.00Listplank Fiber/Kalsiplank 2x30 6mm 0.0099 Lembar 34,000.00 336.60Sekrup 12.0000 Bh 150.00 1,800.00

Jumlah: 42,636.60Nilai HSPK : 73,221.60

m1

Upah:Mandor 0.0050 O.H 97,000.00 485.00Kepala Tukang 0.0200 O.H 95,000.00 1,900.00Tukang Kayu 0.2000 O.H 92,500.00 18,500.00Pekerja 0.1000 O.H 97,000.00 9,700.00

Jumlah: 30,585.00

Bahan:Fiber/Kalsiplank 15 cm 0.0033 Lembar 34,000.00 112.20Sekrup 4.0000 Bh 150.00 600.00

Jumlah: 712.20Nilai HSPK : 31,297.20

Pemasangan Penangkal Petir Konvensional unitUpah:Mandor 0.0250 O.H 97,000.00 2,425.00Kepala Tukang Listrik 0.0250 O.H 95,000.00 2,375.00Tukang Listrik 0.0090 O.H 92,500.00 832.50Pekerja 0.0750 O.H 97,000.00 7,275.00

Jumlah: 12,907.50 x Panjang kabel 765,801.98

Bahan:Runcingan Penangkal Petir/Sliter 1" 4.0000 Bh 27,000.00 108,000.00Kabel BC dia 50 mm2 59.3300 m1 350,000.00 20,765,500.00Isolator pipa PVC AW D 3/4" + klem plat 59.3300 m1 45,000.00 2,669,850.00Pentanahan grounding Kabel BC 50 mm2 1.0000 Unit 250,000.00 250,000.00Bak Kontrol 1.0000 Unit 7,500.00 7,500.00Box test line 1.0000 Set 8,500.00 8,500.00Kabel Schoon 1.0000 Set 1,000.00 1,000.00Connector 10.0000 Set 500,000.00 5,000,000.00Peralatan Bantu 3.0000 Jam - 0.00

1.0000 Ls -

0.00

Jumlah: 28,810,350.00Nilai HSPK : 29,576,151.98

Pasang Talang Pembuluh Pipa PVC 3" m1

Pemasangan Listplank Fiber/Kalsiplank 2x30 6mm

Pemasangan Papan Kompres Fiber/Kalsiplank 15 cm

Testing dan Commissioning termasuk ijin-ijin penangkal petir

Page 66: Rab Sd Petemon 12

Upah:Mandor 0.0018 O.H 97,000.00 174.60Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Pipa 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0360 O.H 97,000.00 3,492.00

Jumlah: 9,786.60

Bahan:Pipa PVC 3'' type D Panjang 4 m 0.3000 btg 80,000.00 24,000.00Perlengkapan 35% harga pipa 0.3500 bh 24,000.00 8,400.00

Jumlah: 32,400.00Nilai HSPK : 42,186.60

Pasang Roof Drain bhUpah:Mandor 0.0018 O.H 97,000.00 174.60Kepala Tukang 0.0060 O.H 95,000.00 570.00Tukang Pipa 0.0600 O.H 92,500.00 5,550.00Pekerja 0.0360 O.H 97,000.00 3,492.00

Jumlah: 9,786.60

Bahan:Roof Drain 1.0000 bh 45,000.00 45,000.00

Jumlah: 45,000.00Nilai HSPK : 54,786.60

Page 67: Rab Sd Petemon 12

^

T A B E L T E R B I L A N G

OWNER ESTIMATE

1,949,397,000 0

0 0 NOL RATUS

0 0 NOL PULUH

0 0 NOL SE BELAS TRILYUN

0 0 NOL RATUS SATU SATU

0 0 NOL PULUH SEBELAS SATU MILYAR

1 1 SATU SE BELAS SEBELAS MILYAR

19 9 SEMBILAN RATUS SEMBILAN RATUS SEMBILAN RATUS SEMBILAN RATUS EMPAT PULUH SEMBILAN RATUS EMPAT PULUH SEMBILAN

194 4 EMPAT PULUH EMPAT PULUH SEMBILAN RATUS SEMBILAN B SEMBILAN RATUS EMPAT PULUH SEMBILAN JUTA

1949 9 SEMBILAN SE BELAS SEMBILAN BELAS JUTA

19493 3 TIGA RATUS TIGA RATUS TIGA RATUS TIGA RATUS SEMBILAN PULUH TIGA RATUS SEMBILAN PULUH TUJUH

194939 9 SEMBILAN PULUH SEMBILAN PULUH TIGA RATUS TUJUH BELAS TIGA RATUS SEMBILAN PULUH TUJUH RIBU

1949397 7 TUJUH SE BELAS TUJUH BELAS RIBU

19493970 0 NOL RATUS

1.95E+08 0 NOL PULUH

1.95E+09 0 NOL SE BELAS

SATU MILYAR SEMBILAN RATUS EMPAT PULUH SEMBILAN JUTA TIGA RATUS SEMBILAN PULUH TUJUH RIBU

RUPIAH

Satu Milyar Sembilan Ratus Empat Puluh Sembilan Juta Tiga Ratus Sembilan Puluh Tujuh Ribu Rupiah

96.00

48.00

51.00

Satu Milyar Sembilan Ratus Empat Puluh Sembilan Jut

Satu Milyar Sembilan Ratus Empat Puluh Sembilan Juta Tiga Ratus Sembilan Puluh Tujuh Ribu Rupiah (Termasuk Ppn 10 %)

Asus:MASUKKAN NILAI TOTAL

A5
Asus: MASUKKAN NILAI TOTAL
Page 68: Rab Sd Petemon 12

^

Satu Milyar Sembilan Ratus Empat Puluh Sembilan Juta Tiga Ratus Sembilan Puluh Tujuh Ribu Rupiah

Page 69: Rab Sd Petemon 12

^

T A B E L T E R B I L A N G

PENAWARAN

175,000,000 0

0 0 NOL RATUS

0 0 NOL PULUH

0 0 NOL SE BELAS TRILYUN

0 0 NOL RATUS

0 0 NOL PULUH

0 0 NOL SE BELAS MILYAR

1 1 SATU RATUS SERATUS SERATUS SERATUS TUJUH PULUH LIMA SERATUS TUJUH PULUH LIMA

17 7 TUJUH PULUH TUJUH PULUH SERATUS LIMA BELAS SERATUS TUJUH PULUH LIMA JUTA

175 5 LIMA SE BELAS LIMA BELAS JUTA

1750 0 NOL RATUS

17500 0 NOL PULUH

175000 0 NOL SE BELAS RIBU

1750000 0 NOL RATUS

17500000 0 NOL PULUH

1.75E+08 0 NOL SE BELAS

SERATUS TUJUH PULUH LIMA JUTA

RUPIAH

Seratus Tujuh Puluh Lima Juta Rupiah

36.00

18.00

51.00

Seratus Tujuh Puluh Lima Juta Rupiah

Seratus Tujuh Puluh Lima Juta Rupiah (Termasuk Ppn 10 %)

Page 70: Rab Sd Petemon 12

^

Seratus Tujuh Puluh Lima Juta Rupiah

Page 71: Rab Sd Petemon 12

^

T A B E L T E R B I L A N G

NEGOSIASI

987,757,000.00 0

0 0 NOL RATUS

0 0 NOL PULUH

0 0 NOL SE BELAS TRILYUN

0 0 NOL RATUS

0 0 NOL PULUH

0 0 NOL SE BELAS MILYAR

9 9 SEMBILAN RATUS SEMBILAN RATUS SEMBILAN RATUS SEMBILAN RATUS DELAPAN PUL SEMBILAN RATUS DELAPAN PULUH TUJUH

98 8 DELAPAN PULUH DELAPAN PULUH SEMBILAN RATUS TUJUH BELAS SEMBILAN RATUS DELAPAN PULUH TUJUH JUTA

987 7 TUJUH SE BELAS TUJUH BELAS JUTA

9877 7 TUJUH RATUS TUJUH RATUS TUJUH RATUS TUJUH RATUS LIMA PULUH TUJU TUJUH RATUS LIMA PULUH TUJUH

98775 5 LIMA PULUH LIMA PULUH TUJUH RATUS TUJUH BELAS TUJUH RATUS LIMA PULUH TUJUH RIBU

987757 7 TUJUH SE BELAS TUJUH BELAS RIBU

9877570 0 NOL RATUS

98775700 0 NOL PULUH

9.88E+08 0 NOL SE BELAS

SEMBILAN RATUS DELAPAN PULUH TUJUH JUTA TUJUH RATUS LIMA PULUH TUJUH RIBU

RUPIAH

Sembilan Ratus Delapan Puluh Tujuh Juta Tujuh Ratus Lima Puluh Tujuh Ribu Rupiah

80.00

40.00

51.00

Sembilan Ratus Delapan Puluh Tujuh Juta Tujuh Ratus

Sembilan Ratus Delapan Puluh Tujuh Juta Tujuh Ratus Lima Puluh Tujuh Ribu Rupiah (Termasuk Ppn 10 %)

Page 72: Rab Sd Petemon 12

^

Sembilan Ratus Delapan Puluh Tujuh Juta Tujuh Ratus Lima Puluh Tujuh Ribu Rupiah

Page 73: Rab Sd Petemon 12

KOLOM K1 40/40

TULANGAN JML

PJG = 0.4

LBR = 0.4

Panjang/m3 6.25 12

BKSTG= 10 m2

BEGEL JRK

Bekisting 3x pakai 3.3333333

Tonase besi 156.9305 BESI Ø10 0.15

BESI D16

Page 74: Rab Sd Petemon 12

PANJANG/M3 BERAT/M JML BERAT (KG) BESI

Diameter

6 0.006165

6.25 1.58 118.3680 8 0.006165

9 0.006165

10 0.006165

PJG SATUAN JML BERAT/M JML BERAT (KG) 12 0.006165

13 0.006165

1.5 41.66666667 0.617 38.5625 14 0.006165

16 0.006165

19 0.006165

22 0.006165

23 0.006165

25 0.006165

28 0.006165

31 0.006165

32 0.006165

Page 75: Rab Sd Petemon 12

12 M 1 M

2.66 0.22

4.73 0.39

6.0 0.50

7.4 0.62

10.7 0.89

12.5 1.04

14.5 1.21

19 1.58

26.7 2.23

35.8 2.98

39.1 3.26

46.2 3.85

58.0 4.83

71.1 5.92

75.8 6.31

Page 76: Rab Sd Petemon 12

HITUNGAN VOLUME

I. PEKERJAAN PERSIAPAN1. Pengukuran dan Bowplank

= 44.00 + 11.00 x 2.00 = 110.00 m1

2. Pekerjaan pembongkaran Bangunan eksistingkelas depan = 7.15 x 27.35 x 1.00 = 195.55 m2rumah penjaga = 7.00 x 15.00 x 1.00 = 105.00 m2km/wc = 4.50 x 6.00 x 1.00 = 27.00 m2km/wc = 3.65 x 6.00 x 1.00 = 21.90 m2ruang guru = 3.00 x 15.00 x 1.00 = 45.00 m2

394.45 m2

II. PEKERJAAN GALIAN TANAH DAN URUGAN1. Galian Tanah :

Pek Galian tanah bor pile Ø 40 cmpc 1 = 0.13 x 10.00 x 4.00 = 5.03 m3pc 2 = 0.13 x 20.00 x 20.00 = 50.28 m3pc 3 = 0.13 x 30.00 x 4.00 = 15.08 m3p4 4 = 0.13 x 40.00 x 8.00 = 40.22 m3

110.62 m3Galian tanah u. Poer

pc 1 = 1.44 x 0.45 x 4.00 = 2.59 m3pc 2 = 2.64 x 0.55 x 20.00 = 29.04 m3pc 3 = 4.84 x 0.65 x 4.00 = 12.58 m3p4 4 = 4.84 x 0.65 x 8.00 = 25.17 m3

69.38 m3Galian Pondasi u. tangga m3

= 1.20 x 1.30 x 1.70 = 2.65 m3

2. Pengurugan :Urugan pasir bawah poer, t=10 cm m3

pc 1 = 1.44 x 0.10 x 4.00 = 0.58 m3pc 2 = 2.64 x 0.10 x 20.00 = 5.28 m3pc 3 = 4.84 x 0.10 x 4.00 = 1.94 m3p4 4 = 4.84 x 0.10 x 8.00 = 3.87 m3

11.66 m3Urugan pasir bawah sloof, t=5cm m3

s2 = 0.01 x 43.00 x 3.00 = 1.61 m3= 0.01 x 4.00 x 5.00 = 0.25 m3= 0.01 x 2.50 x 3.00 = 0.09 m3

s1 = 0.02 x 7.00 x 8.00 = 0.84 m32.80 m3

Urugan pasir pondasi tangga, t=5cm m3= 1.20 x 0.05 x 1.70 = 0.10 m3

Urugan pasir bawah lantai t = 5 cm m3= 15.00 x 9.50 x 0.05 = 7.13 m3= 11.00 x 28.00 x 0.05 = 15.40 m3

22.53 m3

Urugan sirtu bawah lantai t = 45 cm m3

Page 77: Rab Sd Petemon 12

= 15.00 x 9.50 x 1.35 = 192.38 m3= 11.00 x 28.00 x 1.35 = 415.80 m3

608.18 m3Urugan tanah kembali m3

pondasi poer & tangga = 69.38 + 2.65 x 0.30 = 21.61 m3

III. PEKERJAAN STRUKTURA LANTAI 11. Beton bor pile Ø 40 cm = 110.62 m3

2. Beton lantai kerja t = 5 cm (1pc : 3ps : 6kr) m3pc 1 = 1.44 x 0.05 x 4.00 = 0.29 m3pc 2 = 2.64 x 0.05 x 20.00 = 2.64 m3pc 3 = 4.84 x 0.05 x 4.00 = 0.97 m3p4 4 = 4.84 x 0.05 x 8.00 = 1.94 m3

5.83 m33. Beton Rabat Bawah Lantai t = 5 cm (1pc : 3ps : m3

= 15.00 x 9.50 x 0.05 = 7.13 m3= 11.00 x 28.00 x 0.05 = 15.40 m3

22.53 m34. Beton Poer

PC1 120x120x40 K-250 = 1.44 x 0.40 x 4.00 = 2.30 m3

PC2 120x220x40 K-250 = 2.64 x 0.40 x 20.00 = 21.12 m3

PC3 220x220x50 K-250 = 2.14 x 0.50 x 20.00 = 21.40 m3

PC4 220x220x50 K-250 = 2.64 x 0.50 x 20.00 = 26.40 m3

5. Beton SloofBeton Sloof S1 25/50 K-250 m3

= 0.13 x 7.00 x 8.00 = 7.00 m3

Beton Sloof S2 20/35 K-250 m3= 0.06 x 43.00 x 3.00 = 7.74 m3= 0.06 x 4.00 x 5.00 = 1.20 m3= 0.06 x 2.50 x 3.00 = 0.45 m3

9.39 m3

Beton Sloof S3 20/30 K-250= 0.06 x 3.50 x 6.00 = 1.26 m3= 0.06 x 3.50 x 11.00 = 2.31 m3

3.57 m3

Beton Sloof Sp 15/20 K-250 = 0.03 x 11.00 x 8.00 = 2.64 m3= 0.03 x 9.50 x 4.00 = 1.14 m3= 0.03 x 43.00 x 3.00 = 3.87 m3= 0.03 x 7.00 x 4.00 = 0.84 m3= 0.03 x 3.00 x 1.00 = 0.09 m3

= 8.58 m3

6. Beton KolomK1 40/40 K-250

= 0.16 x 5.50 x 32.00 = 28.16 m3

Page 78: Rab Sd Petemon 12

K2 20/20 K-250= 0.04 x 5.50 x 4.00 = 0.88 m3

KP 12/12= 0.01 x 5.10 x 24.00 = 1.76 m3

7. Beton plat lantai 10 cm, tul. Wiremesh M4= 15.00 x 9.50 x 0.10 = 14.25 m3= 11.00 x 28.00 x 0.10 = 30.80 m3

45.05 m3

8. Beton Balok Latai 15/20 = 0.03 x 24.00 x 1.00 = 0.72 m3= 0.03 x 15.00 x 1.00 = 0.45 m3= 0.03 x 16.00 x 1.00 = 0.48 m3= 0.03 x 8.00 x 1.00 = 0.24 m3= 0.03 x 8.45 x 1.00 = 0.25 m3= 0.03 x 6.80 x 1.00 = 0.20 m3

2.35 m3

9. Balok kanopi beton 20/30 = 0.06 x 3.60 x 9.00 = 1.94 m3= 0.06 x 3.20 x 2.00 = 0.38 m3

2.33 m3

10. Plat kanopi beton, t = 8 cm = 2.16 x 0.08 x 9.00 = 1.56 m3= 1.92 x 0.08 x 2.00 = 0.31 m3= 2.16 x 0.08 x 8.00 = 1.38 m3= 0.84 x 0.08 x 2.00 = 0.13 m3

3.38 m3

11. Beton pondasi tangga = 0.30 x 1.70 x 1.00 = 0.51 m3= 0.26 x 1.30 x 1.00 = 0.33 m3

0.84 m312. Beton tangga lantai 1

Beton plat tangga t = 15 cm = 0.20 x 7.40 x 1.00 = 1.51 m3Anak tangga = 0.03 x 1.70 x 22.00 = 1.12 m3Bordes = 3.50 x 3.50 x 0.12 = 1.47 m3Balok bordes = 0.50 x 3.40 x 1.00 = 1.70 m3

B LANTAI 21. Beton Kolom

K1 40/40 K-250 = 0.16 x 0.50 x 32.00 = 2.56 m3K2 20/20 K-250 = 0.04 x 0.50 x 4.00 = 0.08 m3

2. Beton BalokB1 25/50 K-250 = 0.13 x 6.60 x 12.00 = 9.90 m3

B2 20/35 K-250 = 0.07 x 3.60 x 36.00 = 9.07 m3= 0.07 x 3.60 x 8.00 = 2.02 m3= 0.07 x 2.15 x 4.00 = 0.60 m3= 0.07 x 3.25 x 12.00 = 2.73 m3

14.42 m3

B3 20/30 K-250 = 0.06 x 4.96 x 1.00 = 0.30 m3

3. Beton plat deck lantai 2, t = 12 cm K-250= 12.21 x 0.12 x 16.00 = 23.44 m3= 14.44 x 0.12 x 7.00 = 12.13 m3

Page 79: Rab Sd Petemon 12

= 7.33 x 0.12 x 2.00 = 1.76 m3= 21.45 x 0.12 x 4.00 = 10.30 m3= 8.74 x 0.12 x 2.00 = 2.10 m3= 3.80 x 0.12 x 1.00 = 0.46 m3

50.18 m3

IV. PEKERJAAN ARSITEKTUR1. LANTAI 1A PEKERJAAN PASANGAN PLESTERAN1. Pasangan batu bata merah trasram 1Pc : 2Ps m2

bata Bawah sloof = 1.80 x 0.80 x 27.00 = 38.88 m2= 1.50 x 0.80 x 6.00 = 7.20 m2= 6.60 x 0.80 x 14.00 = 73.92 m2= 3.60 x 0.80 x 8.00 = 23.04 m2= 2.15 x 0.80 x 4.00 = 6.88 m2

149.92 m2

km/wc = 19.80 + 6.60 + 5.55 = 31.95 m1= 3.50 + 6.08 + 3.60 = 13.18 m1= 2.97 + 3.10 + 1.40 = 7.47 m1

= 52.60 m1= 52.60 x 2.00 x 1.00 = 105.20 m2

kusen = 0.78 x 2.14 x 5.00 = 8.35 m2= 0.98 x 2.14 x 2.00 = 4.19 m2= 0.78 x 1.28 x 1.00 = 1.00 m2

13.54 m2= 105.20 - 13.54 = 91.66 m2

jumlah = 149.92 + 91.66 = 241.58 m2

2. Pasangan batu merah biasa 1Pc : 4Ps m2sisi belakang = 3.60 x 3.60 x 7.00 = 90.72 m2lubang kusen = 1.48 x 2.36 x 6.00 = 20.96 m2

= 0.58 x 0.78 x 2.00 = 0.90 m2= 21.86 m2

= 90.72 - 21.86 = 68.86 m2

sisi depan = 3.60 x 3.60 x 6.00 = 77.76 m2lubang kusen = 1.48 x 2.36 x 3.00 = 10.48 m2

= 0.98 x 2.74 x 3.00 = 8.06 m2= 1.48 x 1.58 x 3.00 = 7.02 m2

= 25.55 m2= 77.76 - 25.55 = 52.21 m2

samping = 6.60 x 3.60 x 4.00 = 95.04 m2km/wc = 52.60 x 1.60 x 1.00 = 84.16 m2

jumlah = 68.86 + 52.21 + 95.04 + 84.16= 300.27 m2

3. Pasangan batu merah (pot dan trap) 1Pc : 2Ps m2pot = 9.10 x 0.60 x 2.00 = 10.92 m2

= 4.10 x 0.60 x 2.00 = 4.92 m2= 8.00 x 0.60 x 2.00 = 9.60 m2= 19.40 x 0.60 x 2.00 = 23.28 m2= 11.40 x 0.60 x 2.00 = 13.68 m2

62.40 m2

Page 80: Rab Sd Petemon 12

trap = 3.70 + 1.65 + 7.25 = 12.60 m1= 12.60 x 0.35 x 1.00 = 4.41 m2= 12.60 x 0.50 x 2.00 = 12.60 m2

17.01 m2= 62.40 + 17.01 = 79.41 m2

4. Plesteran dinding 1Pc : 2Ps (trasram) tebal 1,5cm m2= 3.10 + 1.70 + 3.10 = 7.90 m1= 6.60 + 3.10 + 3.10 = 12.80 m1= 6.60 + 0.00 + 0.00 = 6.60 m1

27.30 m1= 27.30 x 3.47 x 1.00 = 94.73 m2

5. Plesteran dinding 1Pc : 4Ps tebal 1,5cm m2sisi belakang = 3.60 x 3.60 x 7.00 = 90.72 m2bingkai kusen = 7.68 x 0.15 x 7.00 = 8.06 m2

= 98.78 x 2.00 = 197.57 m2

lubang kusen = 1.48 x 2.36 x 6.00 = 20.96 m2= 0.58 x 0.78 x 2.00 = 0.90 m2

= 21.86 m2= 197.57 - 21.86 = 175.71 m2

sisi depan = 3.60 x 3.60 x 6.00 = 77.76 m2bingkai kusen = 7.68 x 0.15 x 3.00 = 3.46 m2

= 7.44 x 0.15 x 3.00 = 3.35 m2= 6.12 x 0.15 x 3.00 = 2.75 m2

87.32 m2= 87.32 x 2.00 = 174.64 m2

lubang kusen = 1.48 x 2.36 x 3.00 = 10.48 m2= 0.98 x 2.74 x 3.00 = 8.06 m2= 1.48 x 1.58 x 3.00 = 7.02 m2

= 25.55 m2= 174.64 - 25.55 = 149.09 m2

samping = 6.60 x 3.60 x 8.00 = 190.08 m2km/wc = 17.01 x 1.60 x 2.00 = 54.43 m2

jumlah = 175.71 + 149.09 + 190.08 + 54.43= 569.31 m2

6. Plesteran Beton Kolom 1Pc : 2Ps tebal 1,5cm m2kolom 40x40 = 1.60 x 4 x 12.00 = 76.80 m2

= 1.30 x 4 x 20.00 = 104.00 m2kolom 30x30 = 1.20 x 4 x 4.00 = 19.20 m2

200.00 m2

7. Acian dinding 569.31 m28. Benangan m1

kolom 40x40 = 4.00 x 12 x 1.00 = 48.00 m1= 4.00 x 20 x 1.00 = 80.00 m1

kolom 30x30 = 4.00 x 4 x 1.00 = 16.00 m1144.00 m2

kusen belakang = 7.68 x 2.00 x 7.00 = 107.52 m1kusen depan = 7.68 x 2.00 x 3.00 = 46.08 m1

= 7.40 x 2.00 x 3.00 = 44.40 m1= 6.12 x 2.00 x 3.00 = 36.72 m1

Page 81: Rab Sd Petemon 12

234.72 m1pot = 9.10 x 2 = 18.20 m1

= 4.10 x 2 = 8.20 m1= 8.00 x 2 = 16.00 m1= 19.40 x 2 = 38.80 m1= 11.40 x 2 = 22.80 m1

104.00 m1

jumlah = 144.00 + 234.72 + 104.00 = 482.72 m1

9. Kolkolan lantai = 15.00 + 14.00 + 7.00 = 36.00 m1x3 = 108.00 m1

= 8.00 + 14.00 + 7.00 = 29.00 m1137.00 m1

B PEKERJAAN LANTAI1. Keramik lantai ruang & selasar Uk. 40 x 40 cm m2

= 6.88 x 7.88 x 3.00 = 162.64 m2= 2.52 x 43.00 x 1.00 = 108.36 m2= 6.88 x 3.88 x 1.00 = 26.69 m2

297.70 m22. Keramik lantai t.parkir Uk. 40 x 40 cm motif kasar

= 11.00 x 8.00 x 1.00 = 88.00 m33. Keramik lantai KM/WC Uk. 40 x 40 cm Motif/warna

pria = 1.30 x 3.30 x 1.00 = 4.29 m2= 1.40 x 4.00 x 1.00 = 5.60 m2= 1.60 x 3.30 x 1.00 = 5.28 m2= 1.80 x 1.80 x 1.00 = 3.24 m2= 1.70 x 1.80 x 1.00 = 3.06 m2

meja = 1.60 x 0.80 x 1.00 = 1.28 m2= 0.15 x 2.00 x 1.00 = 0.30 m2

23.05 m2

wanita = 4.60 x 1.40 x 1.00 = 6.44 m2= 1.70 x 1.90 x 1.00 = 3.23 m2= 1.60 x 1.80 x 2.00 = 5.76 m2= 1.60 x 0.80 x 1.00 = 1.28 m2

guru = 1.60 x 1.60 x 1.00 = 2.56 m219.27 m2

total = 23.05 + 19.27 + 0.00 = 42.32 m2

4. Keramik dinding KM/WC Uk. 25 x 40 cm Motif/ m2pria = 3.30 + 5.90 + 3.30 = 12.50 m1

L = 1.60 + 2.00 + 1.35 = 4.95 m1L = 0.90 + 2.00 + 1.30 = 4.20 m1D = 1.80 + 1.80 + 2.60 = 6.20 m1D = 3.60 + 1.70 + 1.00 = 6.30 m2

34.15

= 34.15 X 2.70 X 1.00 = 92.21 m2atas pintu = 4.40 x 0.70 x 1.00 3.08 m2

95.29 m2

wanita = 4.60 + 1.40 + 1.00 = 7.00 m1L = 2.00 + 1.70 + 2.50 = 6.20 m1D = 3.60 + 1.60 + 0.80 = 6.00 m1

Page 82: Rab Sd Petemon 12

D = 3.60 + 1.60 + 0.80 = 6.00 m1= 4.80 + 0.80 + 0.00 = 5.60 m2

30.80

= 30.80 X 2.70 X 1.00 = 83.16 m2atas pintu = 5.20 x 0.70 x 1.00 3.64 m2

86.80 m2

total = 95.29 + 86.80 + 0.00 = 182.09 m2

5. Keramik stepnozing tangga 10x40 cm = 1.70 x 22.00 x 1.00 = 37.40 m1

C PEKERJAAN PLAFOND1. Plafond Kalsiboard+rangka hollow (area toilet) m2

= 7.00 x 7.00 - 0.93 = 48.07 m2

2. Acian plafond ekspose m2

3. List Gypsumkm pria = 1.50 + 3.50 + 7.00 = 12.00 m1

= 3.50 + 1.70 + 2.00 = 7.20 m1= 3.80 + 2.00 + 4.00 = 9.80 m1= 3.80 + 4.00 + 3.80 = 11.60 m1

40.60 m1

km wanita guru = 4.70 + 3.50 + 1.90 = 10.10 m1= 2.00 + 2.80 + 1.50 = 6.30 m1= 4.00 + 3.40 + 4.00 = 11.40 m1= 3.40 + 3.40 + 3.40 = 10.20 m1

38.00 m1

total = 40.60 + 38.00 = 78.60 m1

D PEKERJAAN KUSEN PINTU DAN JENDELA DLL1. Pemasangan pintu type PJ = 3.00 unit

Kusen Aluminium 4" = 2.74 + 2.74 + 1.48 = 6.96 m1= 1.48 + 2.56 + 2.56 = 6.60 m1= 1.58 + 0.00 + 0.00 = 1.58 m1

= 15.14 m1

Slimar jendela = 0.90 + 0.90 + 0.70 = 2.50 m1= 0.70 + 0.50 + 0.50 = 1.70 m1= 0.50 + 0.50 + 0.86 = 1.86 m1= 0.86 + 0.70 + 0.70 = 2.26 m1

= 8.32 m1

Kaca 5 mm = 0.20 x 1.00 x 1.00 = 0.20 m2= 0.78 x 0.38 x 1.00 = 0.30 m2= 0.82 x 0.52 x 1.00 = 0.43 m2= 0.58 x 0.38 x 1.00 = 0.22 m2= 0.74 x 0.65 x 1.00 = 0.48 m2= 0.82 x 0.88 x 1.00 = 0.72 m2

= 2.35 m2

Pas. Daun Pintu Wood Plastic Composite = 0.90 x 2.10 x 1.00 = 1.89 m2Kunci Tanam 2x putar = 1.00 set

engsel pintu = 1.50 stel

Page 83: Rab Sd Petemon 12

Friction Stay 16" = 1.00 setFriction Stay 12" = 2.00 set

Handle Cassement = 3.00 bh

2. Pemasangan pintu type P2 = 2.00 unitKusen Aluminium 4" = 2.14 + 0.80 + 2.14 = 5.08 m1

Pas. Daun Pintu Wood Plastic Composite = 0.80 x 2.10 x 1.00 = 1.68 m2Kunci Tanam 2x putar = 1.00 set

engsel pintu = 1.50 stel

3. Pemasangan pintu type P3 = 3.00 unitKusen Aluminium 4" = 2.14 + 0.70 + 2.14 = 4.98 m1

Pas. Daun Pintu Wood Plastic Composite = 0.70 x 2.10 x 1.00 = 1.47 m2Kunci Tanam 2x putar = 1.00 set

engsel pintu = 1.50 stel

4. Pemasangan pintu type P4 = 2.00 unitKusen Aluminium 4" = 2.14 + 0.90 + 2.14 = 5.18 m1

Pas. Daun Pintu Wood Plastic Composite = 0.90 x 2.10 x 1.00 = 1.89 m2Kunci Tanam 2x putar = 1.00 set

engsel pintu = 1.50 stel

5. Pemasangan jendela type J = 9.00 unitKusen Aluminium 4" = 1.48 + 1.48 + 1.48 = 4.44 m1

= 1.48 + 2.36 + 2.36 = 6.20 m1= 2.36 + 0.00 + 0.00 = 2.36 m1

= 13.00 m1

Slimar jendela = 0.70 + 0.50 + 0.70 = 1.90 m1= 0.50 + 0.70 + 0.50 = 1.70 m1= 0.70 + 0.50 + 0.00 = 1.20 m1

= 4.80 m1

Kaca 5 mm = 0.58 x 0.38 x 1.00 = 0.22 m2= 0.74 x 0.58 x 1.00 = 0.43 m2= 0.82 x 0.52 x 1.00 = 0.43 m2= 0.82 x 0.88 x 1.00 = 0.72 m2= 0.58 x 0.38 x 1.00 = 0.22 m2= 0.58 x 0.74 x 1.00 = 0.43 m2

= 2.45 m2Friction Stay 16" = 2.00 setFriction Stay 12" = 2.00 set

Handle Cassement = 4.00 bh

6. Pemasangan jendela type BV = 2.00 unitKusen Aluminium 4" = 0.58 + 0.70 x 2.00 = 2.56 m1

Kaca Es 5 mm = 0.72 x 0.32 x 2.00 = 0.46 m2

7. Pemasangan handrailing tangga = 4.20 + 3.20 + 0.20 = 7.60 m1= 7.60 x 0.80 = 6.08 m2

E PEKERJAAN PENGECATAN1. Pengecatan Dinding bag. Dalam m2

= 8.37 x 4.00 x 6.00 = 200.88 m2= 7.11 x 4.00 x 8.00 = 227.52 m2= 4.11 x 4.00 x 1.00 = 16.44 m2

= 444.84 m2

Page 84: Rab Sd Petemon 12

lubang kusen bekalang = 1.48 x 2.36 x 6.00 = 20.96 m2= 0.58 x 0.78 x 2.00 = 0.90 m2

= 21.86 m2lubang kusen = 1.48 x 2.36 x 3.00 = 10.48 m2

= 0.98 x 2.74 x 3.00 = 8.06 m2= 1.48 x 1.58 x 3.00 = 7.02 m2

= 25.55 m2= 21.86 + 25.55 = 47.41 m2= 444.84 - 47.41 = 397.43 m2

2. Pengecatan Dinding bag. Luar= 8.52 x 4.00 x 6.00 = 204.48 m2= 7.26 x 4.00 x 2.00 = 58.08 m2= 4.26 x 4.00 x 1.00 = 17.04 m2= 7.26 x 4.00 x 1.00 = 29.04 m2

kolom 40x40 = 1.60 x 12 x 1.00 = 19.20 m2= 1.60 x 20 x 1.00 = 32.00 m2

kolom 30x30 = 1.20 x 4 x 1.00 = 4.80 m2balok = 0.40 x 63 x 1.00 = 25.20 m2

389.84 m2= 389.84 - 25.55 = 364.29 m2

3. Pengecatan Plafond m2= 11.00 x 28.00 x 1.00 = 308.00 m2= 9.00 x 15.00 x 1.00 = 135.00 m2

balok = 6.60 x 0.50 x 18.00 = 59.40 m2= 2.15 x 0.23 x 7.00 = 3.46 m2= 2.15 x 0.23 x 15.00 = 7.42 m2= 24.00 x 0.23 x 2.00 = 11.04 m2= 43.00 x 0.23 x 1.00 = 9.89 m2

534.21 m24. Pengecatan Melamin / Duco daun pintu m25. Pengecatan Kolkolan = 137.00 x 0.10 = 13.70 m2

2. LANTAI 2A PEKERJAAN PASANGAN PLESTERAN1. Pasangan batu bata merah trasram 1Pc : 2Ps

= 43.00 + 11.00 + 43.00 = 97.00 m1= 11.00 + 12.00 + 4.00 = 27.00 m1

124.00 m1124.00 x 0.20 = 24.80 m2

2. Pelapisan waterproofing deck = 11.00 x 24.00 x 1.00 = 264.00 m2= 5.00 x 4.00 x 1.00 = 20.00 m2= 9.50 x 15.00 x 1.00 = 142.50 m2

426.50 m2

V. PEKERJAAN INSTALASI LISTRIK1. LANTAI 11. Penarikan jalur = 1.000 Ls2. Pas. Box MCB + panel = 1.000 unit3. Pasang titik Lampu = 38.000 titik4. Pasang titik stop kontak = 7.000 titik5. Pasang saklar ganda = 7.000 buah

Page 85: Rab Sd Petemon 12

6. Pasang saklar tunggal = 4.000 buah7. Pasang lampu led 5 Watt = 27.000 buah8. Pasang lampu led 10 Watt = 16.000 buah

VI. PEKERJAAN INSTALASI AIR BERSIH, AIR BEKAS DAN AIR KOTOR1. LANTAI 11. Tandon Air Kapasitas 1100 ltr+Asessorie = 1.000 unit2. Tandon air beton bawah kapasitas 4 m3 = 1.000 unit3. Mesin Pompa air = 1.000 unit4. Kloset jongkok porselin = 2.000 buah5. Kloset duduk porselin komplit = 3.000 buah6. Wastafel tanam komplit = 2.000 unit7. Urinoir komplit = 3.000 unit8. Floor drain stainlees = 8.000 buah9. Kran air 1/2" = 7.000 buah

10. Pas Floor Clean Out Ø 3" = 2.000 buah11. Pas Floor Clean Out Ø 4" = 2.000 buah12. Pas. pipa PVC type AW 1/2" = m113. Pas. pipa PVC type AW 3/4" = m114. Pas. pipa PVC type AW 1" outlet = m115. Pas. pipa PVC type AW 1" intlet = m116. Pas. pipa air kotor PVC type D 3" = m117. Pas. pipa air kotor PVC type D 4" = m118. Septiktank kapasitas 6 m3 = 1.000 unit19. Sumur Resapan = 1.000 unit

VII. PEKERJAAN LAIN - LAIN1. Pengadaan Air kerja = 1.000 Ls2. Pembersihan akhir = 1.000 Ls

Page 86: Rab Sd Petemon 12

RENCANA ANGGARAN BIAYA

NAMA KEGIATAN : PEMBANGUNAN / REHABILITASI FASILITAS GEDUNG PENDIDIKANNAMA PEKERJAAN LOKASI

NO. URAIAN PEKERJAAN VOL SAT HARGA SAT

(Rp) 1 2 3 4 5

I. PEKERJAAN PERSIAPAN1. Pengukuran dan Bowplank 110.00 m1 104,293.57 2. Pekerjaan pembongkaran Bangunan eksisting 394.45 m2

Sub. TotalII. PEKERJAAN GALIAN TANAH DAN URUGAN1. Galian Tanah :

Pek Galian tanah bor pile Ø 40 cmGalian tanah u. Poer 69.38 m3 69,250.00 Galian Pondasi u. tangga 2.65 m3 69,250.00

2. Pengurugan :Urugan pasir bawah poer, t=10 cm 11.66 m3 177,700.00 Urugan pasir bawah sloof, t=5cm 2.80 m3 177,700.00 Urugan pasir pondasi tangga, t=5cm 0.10 m3 177,700.00 Urugan pasir bawah lantai t = 5 cm 22.53 m3 177,700.00 Urugan sirtu bawah lantai t = 45 cm 608.18 m3 185,200.00 Urugan tanah kembali 21.61 m3 23,083.33

Sub. TotalIII. PEKERJAAN STRUKTURA LANTAI 11. Beton bor pile Ø 40 cm 110.62 m3 2,012,813.43 2. Beton lantai kerja t = 5 cm (1pc : 3ps : 6kr) 5.83 m3 879,675.42 3. Beton Rabat Bawah Lantai t = 5 cm (1pc : 3ps : 6kr) 22.53 m3 879,675.42 4. Beton Poer

PC1 120x120x40 K-250 2.30 m3 3,057,970.87 PC2 120x220x40 K-250 21.12 m3 2,783,327.19 PC3 220x220x50 K-250 21.40 m3PC4 220x220x50 K-250 26.40 m3

5. Beton SloofBeton Sloof S1 25/50 K-250 7.00 m3 3,377,651.41 Beton Sloof S2 20/35 K-250 9.39 m3Beton Sloof S3 20/30 K-250 3.57 m3Beton Sloof Sp 15/20 K-250 8.58 m3

6. Beton KolomK1 40/40 K-250 28.16 m3K2 20/20 K-250 0.88 m3KP 12/12 1.76 m3

7. Beton plat lantai 10 cm, tul. Wiremesh M4 45.05 m38. Beton Balok Latai 15/20 2.35 m39. Balok kanopi beton 20/30 2.33 m3

10. Plat kanopi beton, t = 8 cm 3.38 m311. Beton pondasi tangga 0.84 m312. Beton tangga lantai 1

Beton plat tangga t = 15 cm 1.51 m3Anak tangga 1.12 m3Bordes 1.47 m3Balok bordes 1.70 m3

Page 87: Rab Sd Petemon 12

Sub. TotalB LANTAI 21. Beton Kolom

K1 40/40 K-250 2.56 m3K2 20/20 K-250 0.08 m3

2. Beton BalokB1 25/50 K-250 9.90 m3B2 20/35 K-250 14.42 m3B3 20/30 K-250 0.30 m3

3. Beton plat deck lantai 2, t = 12 cm K-250 50.18 m3 Sub. Total

IV. PEKERJAAN ARSITEKTUR1. LANTAI 1A PEKERJAAN PASANGAN PLESTERAN1. Pasangan batu bata merah trasram 1Pc : 2Ps 241.58 m2 115,890.40 2. Pasangan batu merah biasa 1Pc : 4Ps 300.27 m2 109,980.60 3. Pasangan batu merah (pot dan trap) 1Pc : 2Ps 79.41 m2 115,890.40 4. Plesteran dinding 1Pc : 2Ps (trasram) tebal 1,5cm 94.73 m2 57,976.92 5. Plesteran dinding 1Pc : 4Ps tebal 1,5cm 569.31 m2 54,746.28 6. Plesteran Beton Kolom 1Pc : 2Ps tebal 1,5cm 200.00 m27. Acian dinding 569.31 m2 33,605.00 8. Benangan 482.72 m1 17,676.00 9. Kolkolan lantai 137.00 m1 28,032.80

Sub. TotalB PEKERJAAN LANTAI1. Keramik lantai ruang & selasar Uk. 40 x 40 cm 297.70 m2 221,555.00 2. Keramik lantai t.parkir Uk. 40 x 40 cm motif kasar 88.00 m3 226,859.00 3. Keramik lantai KM/WC Uk. 40 x 40 cm Motif/warna 42.32 m2 226,859.00 4. Keramik dinding KM/WC Uk. 25 x 40 cm Motif/warna 182.09 m25. Keramik stepnozing tangga 10x40 cm 37.40 m1 28,032.80

Sub. TotalC PEKERJAAN PLAFOND1. Plafond Kalsiboard+rangka hollow (area toilet) 48.07 m2 112,561.69 2. Acian plafond ekspose 0.00 m23. List Gypsum 78.60 m1 19,891.00

Sub. TotalD PEKERJAAN KUSEN PINTU DAN JENDELA DLL1. Pemasangan pintu type PJ 3.00 unit 4,500,314.46 2. Pemasangan pintu type P2 2.00 unit 1,979,759.20 3. Pemasangan pintu type P3 3.00 unit 1,898,826.30 4. Pemasangan pintu type P4 2.00 unit 1,898,826.30 5. Pemasangan jendela type J 9.00 unit 2,545,677.03 6. Pemasangan jendela type BV 2.00 unit 336,535.41 7. Pemasangan handrailing tangga 6.08 m2

Sub. TotalE PEKERJAAN PENGECATAN1. Pengecatan Dinding bag. Dalam 397.43 m2 25,481.44 2. Pengecatan Dinding bag. Luar 364.29 m2 29,567.50 3. Pengecatan Plafond 534.21 m2 25,481.44 4. Pengecatan Melamin / Duco daun pintu 0.00 m25. Pengecatan Kolkolan 13.70 m2

Sub. Total2. LANTAI 2A PEKERJAAN PASANGAN PLESTERAN1. Pasangan batu bata merah trasram 1Pc : 2Ps 24.80 m2 115,890.40 2. Pelapisan waterproofing deck 426.50 m2 30,410.00

Sub. Total

Page 88: Rab Sd Petemon 12

V. PEKERJAAN INSTALASI LISTRIK1. Penarikan jalur 1.00 Ls 2,500,000.00 2. Pas. Box MCB + panel 1.00 unit 871,725.50 3. Pasang titik Lampu 38.00 titik 215,330.00 4. Pasang titik stop kontak 7.00 titik 114,189.10 5. Pasang saklar ganda 7.00 buah 41,539.10 6. Pasang saklar tunggal 4.00 buah 32,439.10 7. Pasang lampu led 5 Watt 27.00 buah 67,791.00 8. Pasang lampu led 10 Watt 16.00 buah 105,291.00

Sub. TotalVI. PEKERJAAN INSTALASI AIR BERSIH, AIR BEKAS DAN AIR KOTOR1. Tandon Air Kapasitas 1100 ltr+Asessories Stenlees 1.00 unit 2,383,000.00 2. Tandon air beton bawah kapasitas 4 m3 1.00 unit 5,400,000.00 3. Mesin Pompa air 1.00 unit 950,000.00 4. Kloset jongkok porselin 2.00 buah 721,415.00 5. Kloset duduk porselin komplit 3.00 buah 2,531,395.00 6. Wastafel tanam komplit 2.00 unit 823,255.00 7. Urinoir komplit 3.00 unit 779,015.00 8. Floor drain stainlees 8.00 buah 34,225.00 9. Kran air 1/2" 7.00 buah 49,725.00

10. Pas Floor Clean Out Ø 3" 2.00 buah11. Pas Floor Clean Out Ø 4" 2.00 buah12. Pas. pipa PVC type AW 1/2" 0.00 m113. Pas. pipa PVC type AW 3/4" 0.00 m1 17,122.20 14. Pas. pipa PVC type AW 1" outlet 0.00 m1 18,682.20 15. Pas. pipa PVC type AW 1" intlet 0.00 m1 18,682.20 16. Pas. pipa air kotor PVC type D 3" 0.00 m1 33,502.20 17. Pas. pipa air kotor PVC type D 4" 0.00 m1 45,502.20 18. Septiktank kapasitas 6 m3 1.00 unit 3,600,000.00 19. Sumur Resapan 1.00 unit 3,045,923.41

Sub. TotalVII. PEKERJAAN LAIN - LAIN1. Pengadaan Air kerja 1.00 Ls 1,000,000.00 2. Pembersihan akhir 1.00 Ls 1,500,000.00

Sub. Total

SUB TOTALPPN 10%TOTALDIBULATKAN

Page 89: Rab Sd Petemon 12

RENCANA ANGGARAN BIAYA

JML HARGA(Rp)

6

11,472,292.86 - 11,472,292.86

4,804,565.00 183,512.50

2,071,982.00 497,560.00 17,770.00 4,003,581.00 112,634,936.00 498,830.83 124,712,737.33

222,649,370.71 5,128,507.72 19,819,087.31

7,033,333.01 58,783,870.19 -

23,643,559.89 - - -

- - -

-

-

- - - -

Page 90: Rab Sd Petemon 12

114,408,358.12

- -

- - - - -

27,996,802.83 33,023,874.76 9,202,856.66 5,492,153.63 31,167,604.67 - 19,131,662.55 8,532,558.72 3,840,493.60 138,388,007.43

65,956,923.50 19,963,592.00 9,600,672.88 - 1,048,426.72 96,569,615.10

5,410,840.49 - 1,563,432.60 6,974,273.09

13,500,943.37 3,959,518.39 5,696,478.89 3,797,652.59 22,911,093.29 673,070.82 - 50,538,757.34

10,127,087.75 10,771,144.58 13,612,438.78 - - 34,510,671.10

2,874,081.92 12,969,865.00 12,969,865.00

Page 91: Rab Sd Petemon 12

2,500,000.00 871,725.50 8,182,540.00 799,323.70 290,773.70 129,756.40 1,830,357.00 1,684,656.00 16,289,132.30

2,383,000.00 5,400,000.00 950,000.00 1,442,830.00 7,594,185.00 1,646,510.00 2,337,045.00 273,800.00 348,075.00 - - - - - - - - 3,600,000.00 3,045,923.41 29,021,368.41

1,000,000.00 1,500,000.00 2,500,000.00

751,116,804.39 75,111,680.44 826,228,484.83 826,228,000.00

Page 92: Rab Sd Petemon 12

REKAPITULASI

NAMA KEGIAT: PEMBANGUNAN / REHABILITASI FASILITAS GEDUNG PENDIDIKANNAMA PEKERJ 0LOKASI 0

PAGU ANGGARAN Rp 895,155,000.00

NO. URAIAN PEKERJAAN JUMLAH HARGA

I. PEKERJAAN PERSIAPAN Rp 11,472,292.86 II. PEKERJAAN GALIAN TANAH DAN URUGAN Rp 124,712,737.33 III. PEKERJAAN STRUKTUR

A LANTAI 1 Rp 114,408,358.12 B LANTAI 2 Rp -

IV. PEKERJAAN ARSITEKTUR1 LANTAI 1A PEKERJAAN PASANGAN PLESTERAN Rp 138,388,007.43 B PEKERJAAN LANTAI Rp 96,569,615.10 C PEKERJAAN PLAFOND Rp 6,974,273.09 D PEKERJAAN KUSEN PINTU DAN JENDELA DLL Rp 50,538,757.34 E PEKERJAAN PENGECATAN Rp 34,510,671.10 2 LANTAI 2A PEKERJAAN PASANGAN PLESTERAN Rp 12,969,865.00

V. PEKERJAAN INSTALASI LISTRIK Rp 16,289,132.30 VI. PEKERJAAN INSTALASI AIR BERSIH, AIR BEKAS DAN AIR Rp 29,021,368.41 VII. PEKERJAAN LAIN - LAIN Rp 2,500,000.00

SUB TOTAL Rp 638,355,078.08 PPN 10% Rp 63,835,507.81

TOTAL Rp 702,190,585.88 DIBULATKAN Rp 702,190,000.00

Terbilang :

Surabaya, 2015.........................

..................Direktur