lh periode 8 apr - 14 apr 2015
DESCRIPTION
aTRANSCRIPT
DAILY REPORT
P E K E R J A A N
PEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "JALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH
NAMA PEMILIK : Mrs. TETI YANI HARTONOKONTRAKTOR : PT. ADHI KARYA (Persero) Tbk.
NOMOR KONTRAK : 10/TENDER/TWUJIL/UNG/XII/2014
TANGGAL : 18 Desember 2014
SPMK : 11/TENDER/TWUJIL/UNG/XII/2014
TANGGAL : 19 Desember 2014
LAPORAN HARIAN
MINGGU KE : 17 ( Tujuh Belas )TANGGAL : 08 April 2015
s/d TANGGAL : 14 April 2015
MANAJEMEN KONSTRUKSI
DAILY ACTIVITY REPORT
LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015
OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "
PT. INDAH SARI LESTARIJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH
Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE
Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE -
Waktu Pelaksanaan 210 Hari Kalender 8-Apr-2015 17 ( Tujuh Belas ) 111
U R A I A N
TENAGA KERJA JMLKEGIATAN
HARI INI
MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN
1 Project Manager 1 1 Uitzet dan Bouwplank 0.005 Ls
2 Project Engineer Manager 1 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls
3 Project Production Manager 1 3 Mobil Tadano (sewa) 0.005 Ls
4 Project Planning 1 4 Mob Demob material dan alat 0.011 Ls
5 Project Control 1 Beton Basement
6 Drafter 2 5 Kolom Praktis 12.857 M'
LAPANGAN Beton Lantai 1
7 Kepala Pelaksana 1 6 Kolom Praktis 107.143 M'
8 Pelaksana (P) 3 7 Beton ring balk dan latai 107.143 M'
9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2
10 Surveyor 5 Pemasangan Bata Ringan area toilet finish plesteran acian
Tukang Pekerja 9 Lantai 1 Elevasi 75.554 M2
11 Kayu 17 31 48 Pemasangan Bata Ringan area dinding biasa finish plesteran acian
12 Batu - 9 Lantai 1 Elevasi 225.883 M2
13 Besi 10 14 24 Plesteran Acian Beton mu 290
14 Las 2 5 7 11 Lantai Basement 153.944 M2
15 Listrik - Lantai 2
16 Plumbing 5 24 29 12 Pipa PVC AW dia.4" (air k 31.857 M
17 Aspal - 13 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M
18 Cat - 14 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M
19 Galian - Lantai 3
20 Pembersih - 15 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M
21 Waterproofing - 16 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M
22 Finishing - 17 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M
23 Pembantu - 5 5 Pekerjaan Drainase Hujan
24 Pengecoran 3 7 10 18 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M
25 Operator Alat Berat 3 19 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M
26 Operator/Driver Lainnya 2 20 Roofdrain (cast iron tipe meshroom) 12.000 Bh
T O T A L 147
CV. WASTU BUANA ADI CIPTA
PT. ADHI KARYA (Persero) Tbk.
Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai
Excavator Pc - 200
Stamper
Mobile Crane 25 Ton
KEADAAN CUACA HARI INI JAM KERJA
Pagi Cerah Mulai
Siang Cerah Selesai
Sore Cerah
Malam Cerah
PERMASALAHAN :
PENYELESAIAN :
Menyetujui, Disusun Oleh,
Kontraktor Pelaksana Manajemen Konstruksi
PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA
Heri Prayono, ST. Hari Sugiarto, ST.
Project Production Manager Supervisi Struktur
Catatan :
TANGGAL REVISI HAL ……… / ……….
LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015
PEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "
JALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH
PERIODE
SISA HARI
99
U R A I A N
KEGIATAN
HARI INI
KET.
Jumlah
1
2
2
JAM KERJA
8:00
17:00
PERMASALAHAN :
PENYELESAIAN :
Disusun Oleh,
Manajemen Konstruksi
CV. WASTU BUANA ADI CIPTA
Hari Sugiarto, ST.
Supervisi Struktur
DAILY ACTIVITY REPORT
LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015
OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "
PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH
Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE
Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE - SISA HARI
Waktu Pelaksanaan 210 Hari Kalender 9-Apr-2015 17 ( Tujuh Belas ) 112 98
U R A I A N
TENAGA KERJA JMLKEGIATAN
HARI INI
MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN KET.
1 Project Manager 1 1 Uitzet dan Bouwplank 0.005 Ls
2 Project Engineer Manager 1 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls
3 Project Production Manager 1 3 Mobil Tadano (sewa) 0.005 Ls
4 Project Planning 1 4 Mob Demob material dan alat 0.011 Ls
5 Project Control 1 Beton Basement
6 Drafter 2 5 Kolom Praktis 12.857 M'
LAPANGAN Beton Lantai 1
7 Kepala Pelaksana 1 6 Kolom Praktis 107.143 M'
8 Pelaksana (P) 3 7 Beton ring balk dan latai 107.143 M'
9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2
10 Surveyor 5 Pemasangan Bata Ringan area toilet finish plesteran acian
Tukang Pekerja Jumlah 9 Lantai 1 Elevasi 75.554 M2
11 Kayu 13 30 43 Pemasangan Bata Ringan area dinding biasa finish plesteran acian
12 Batu - 10 Lantai 1 Elevasi 225.883 M2
13 Besi 11 15 26 Plesteran Acian Beton mu 290
14 Las 2 5 7 11 Lantai Basement 153.944 M2
15 Listrik - Lantai 2
16 Plumbing 6 22 28 12 Pipa PVC AW dia.4" (air kotor) merk WAVIN 31.857 M
17 Aspal - 13 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M
18 Cat - 14 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M
19 Galian - Lantai 3
20 Pembersih - 15 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M
21 Waterproofing - 16 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M
22 Finishing - 17 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M
23 Pembantu - 5 5 Pekerjaan Drainase Hujan
24 Pengecoran 3 7 10 18 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M
25 Operator Alat Berat 4 19 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M
26 Operator/Driver Lainnya 2 20 Roofdrain (cast iron tipe meshroom) 12.000 Bh
T O T A L 144
PT. ADHI KARYA (Persero) Tbk.
Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai Jumlah
Excavator Pc - 200 1
Stamper 2
Mobile Crane 25 Ton 2
KEADAAN CUACA HARI INI JAM KERJA
Pagi Cerah Mulai 8:00
Siang Cerah Selesai 17:00
Sore Cerah
Malam Cerah
PERMASALAHAN :
PENYELESAIAN :
Menyetujui, Disusun Oleh,
Kontraktor Pelaksana Manajemen Konstruksi
PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA
Heri Prayono, ST. Hari Sugiarto, ST.
Project Production Manager Supervisi Struktur
Catatan :
TANGGAL REVISI HAL ……… / ……….
DAILY ACTIVITY REPORT
LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015
OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "
PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH
Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE
Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE - SISA HARI
Waktu Pelaksanaan 210 Hari Kalender 10-Apr-2015 17 ( Tujuh Belas ) 113 97
U R A I A N
TENAGA KERJA JMLKEGIATAN
HARI INI
MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN KET.
1 Project Manager 1 1 Uitzet dan Bouwplank 0.005 Ls
2 Project Engineer Manager 1 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls
3 Project Production Manager 1 3 Mobil Tadano (sewa) 0.005 Ls
4 Project Planning 1 4 Mob Demob material dan alat 0.011 Ls
5 Project Control 1 Beton Basement
6 Drafter 2 5 Kolom Praktis 12.857 M'
LAPANGAN Beton Lantai 1
7 Kepala Pelaksana 1 6 Kolom Praktis 107.143 M'
8 Pelaksana (P) 3 7 Beton ring balk dan latai 107.143 M'
9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2
10 Surveyor 5 Beton Lantai 2
Tukang Pekerja 9 Kolom K2 3.159 M3
11 Kayu 7 33 40 10 Kolom K6 2.592 M3
12 Batu - 11 Kolom K10 2.800 M3
13 Besi 8 21 29 Beton Lantai 3
14 Las 2 5 7 12 Kolom K2 5.832 M3
15 Listrik - 13 Kolom K10 2.100 M3
16 Plumbing 5 17 22 Pemasangan Bata Ringan area toilet finish plesteran acian
17 Aspal - 14 Lantai 1 Elevasi 75.554 M2
18 Cat - Pemasangan Bata Ringan area dinding biasa finish plesteran acian
19 Galian - 15 Lantai 1 Elevasi 225.883 M2
20 Pembersih - Plesteran Acian Beton mu 290
21 Waterproofing - 16 Lantai Basement 153.944 M2
22 Finishing - Lantai 2
23 Pembantu - 5 5 17 Pipa PVC AW dia.4" (air kotor) merk WAVIN 31.857 M
24 Pengecoran 3 7 10 18 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M
25 Operator Alat Berat 3 19 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M
26 Operator/Driver Lainnya 2 Lantai 3
20 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M
21 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M
T O T A L 137 22 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M
Pekerjaan Drainase Hujan
23 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M
24 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M
25 Roofdrain (cast iron tipe meshroom) 14.000 Bh
PT. ADHI KARYA (Persero) Tbk.
Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai Jumlah
Beton K-300 16.5 M3 Excavator Pc - 200 1
Pasir 10 M3 Stamper 2
Sirtu 15 M3 Mobile Crane 25 Ton 2
KEADAAN CUACA HARI INI JAM KERJA
Pagi Cerah Mulai 8:00
Siang Cerah Selesai 17:00
Sore Cerah
Malam Hujan
PERMASALAHAN :
PENYELESAIAN :
Menyetujui, Disusun Oleh,
Kontraktor Pelaksana Manajemen Konstruksi
PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA
Heri Prayono, ST. Hari Sugiarto, ST.
Project Production Manager Supervisi Struktur
Catatan :
TANGGAL REVISI HAL ……… / ……….
DAILY ACTIVITY REPORT
LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015
OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "
PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH
Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE
Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE - SISA HARI
Waktu Pelaksanaan 210 Hari Kalender 11-Apr-2015 17 ( Tujuh Belas ) 114 96
U R A I A N
TENAGA KERJA JMLKEGIATAN
HARI INI
MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN KET.
1 Project Manager 1 1 Uitzet dan Bouwplank 0.005 Ls
2 Project Engineer Manager 1 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls
3 Project Production Manager 1 3 Mobil Tadano (sewa) 0.005 Ls
4 Project Planning 1 4 Mob Demob material dan alat 0.011 Ls
5 Project Control 1 Beton Basement
6 Drafter 2 5 Kolom Praktis 12.857 M'
LAPANGAN Beton Lantai 1
7 Kepala Pelaksana 1 6 Kolom Praktis 107.143 M'
8 Pelaksana (P) 3 7 Beton ring balk dan latai 107.143 M'
9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2
10 Surveyor 5 Beton Lantai 2
Tukang Pekerja 9 Kolom K2 3.159 M3
11 Kayu 7 27 34 10 Kolom K3 3.024 M3
12 Batu - 11 Kolom K4 0.648 M3
13 Besi 6 18 24 Beton Lantai 3
14 Las 2 5 7 12 Kolom K4 1.944 M3
15 Listrik - 13 Kolom K6 5.184 M3
16 Plumbing 6 19 25 Pemasangan Bata Ringan area toilet finish plesteran acian
17 Aspal - 14 Lantai 1 Elevasi 75.554 M2
18 Cat - Pemasangan Bata Ringan area dinding biasa finish plesteran acian
19 Galian - 15 Lantai 1 Elevasi 225.883 M2
20 Pembersih - Plesteran Acian Beton mu 290
21 Waterproofing - 16 Lantai Basement 153.944 M2
22 Finishing - Lantai 2
23 Pembantu 5 5 17 Pipa PVC AW dia.4" (air kotor) merk WAVIN 31.857 M
24 Pengecoran 3 7 10 18 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M
25 Operator Alat Berat 3 19 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M
26 Operator/Driver Lainnya 2 Lantai 3
20 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M
21 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M
T O T A L 129 22 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M
Pekerjaan Drainase Hujan
23 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M
24 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M
PT. ADHI KARYA (Persero) Tbk.
Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai Jumlah
Betom K-300 14 M3 Excavator Pc - 200 1
Tanah 10 M3 Stamper 2
Bata Ringan 60 M3 Mobile Crane 25 Ton 2
KEADAAN CUACA HARI INI JAM KERJA
Pagi Cerah Mulai 8:00
Siang Hujan Selesai 17:00
Sore Cerah
Malam Gerimis
PERMASALAHAN :
PENYELESAIAN :
Menyetujui, Disusun Oleh,
Kontraktor Pelaksana Manajemen Konstruksi
PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA
Heri Prayono, ST. Hari Sugiarto, ST.
Project Production Manager Supervisi Struktur
Catatan :
TANGGAL REVISI HAL ……… / ……….
DAILY ACTIVITY REPORT
LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015
OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "
PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH
Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE
Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE - SISA HARI
Waktu Pelaksanaan 210 Hari Kalender 12-Apr-2015 17 ( Tujuh Belas ) 115 95
U R A I A N
TENAGA KERJA JMLKEGIATAN
HARI INI
MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN KET.
1 Project Manager 1 Uitzet dan Bouwplank 0.005 Ls
2 Project Engineer Manager 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls
3 Project Production Manager 3 Mobil Tadano (sewa) 0.005 Ls
4 Project Planning 4 Mob Demob material dan alat 0.011 Ls
5 Project Control Beton Basement
6 Drafter 5 Kolom Praktis 12.857 M'
LAPANGAN Beton Lantai 1
7 Kepala Pelaksana 6 Kolom Praktis 107.143 M'
8 Pelaksana (P) 2 7 Beton ring balk dan latai 107.143 M'
9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2
10 Surveyor 2 Beton Lantai 2
Tukang Pekerja 9 Beton Balok B1 2.974 M3
11 Kayu 4 9 13 10 Beton Balok B2 0.294 M3
12 Batu - 11 Beton Balok B3 1.952 M3
13 Besi 4 9 13 12 Beton Balok B4 2.225 M3
14 Las - 13 Beton Balok B5 2.362 M3
15 Listrik - 14 Beton Balok B6 0.934 M3
16 Plumbing 8 17 25 15 Beton Balok B7 1.492 M3
17 Aspal - 16 Beton Balok B7a 0.093 M3
18 Cat - 17 Beton Balok B8 0.574 M3
19 Galian - 18 Beton Balok B9 0.058 M3
20 Pembersih - 19 Beton Balok B10 0.578 M3
21 Waterproofing - 20 Beton Balok B11 1.149 M3
22 Finishing - 21 Plat Lantai 7.214 M3
23 Pembantu 5 5 Pemasangan Bata Ringan area toilet finish plesteran acian
24 Pengecoran 3 7 10 22 Lantai 1 Elevasi 75.554 M2
25 Operator Alat Berat 3 Pemasangan Bata Ringan area dinding biasa finish plesteran acian
26 Operator/Driver Lainnya 2 23 Lantai 1 Elevasi 225.883 M2
Plesteran Acian Beton mu 290
24 Lantai Basement 153.944 M2
T O T A L 78 Lantai 2
25 Pipa PVC AW dia.4" (air kotor) merk WAVIN 31.857 M
26 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M
27 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M
Lantai 3
28 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M
29 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M
30 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M
Pekerjaan Drainase Hujan
31 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M
32 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M
PT. ADHI KARYA (Persero) Tbk.
Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai Jumlah
Beton K-300 22 M3 Excavator Pc - 200 1
Concrete Pump 1 unit Stamper 2
Air compresor 1 unit Mobile Crane 25 Ton 2
Concrete Pump 1
Air Compresor 1
KEADAAN CUACA HARI INI JAM KERJA
Pagi Cerah Mulai 8:00
Siang Cerah Selesai 17:00
Sore Cerah
Malam Hujan
PERMASALAHAN :
PENYELESAIAN :
Menyetujui, Disusun Oleh,
Kontraktor Pelaksana Manajemen Konstruksi
PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA
Heri Prayono, ST. Hari Sugiarto, ST.
Project Production Manager Supervisi Struktur
Catatan :
TANGGAL REVISI HAL ……… / ……….
DAILY ACTIVITY REPORT
LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015
OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "
PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH
Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE
Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE - SISA HARI
Waktu Pelaksanaan 210 Hari Kalender 13-Apr-2015 17 ( Tujuh Belas ) 116 94
U R A I A N
TENAGA KERJA JMLKEGIATAN
HARI INI
MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN KET.
1 Project Manager 1 1 Uitzet dan Bouwplank 0.005 Ls
2 Project Engineer Manager 1 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls
3 Project Production Manager 1 3 Mobil Tadano (sewa) 0.005 Ls
4 Project Planning 1 4 Mob Demob material dan alat 0.011 Ls
5 Project Control 1 Beton Basement
6 Drafter 2 5 Kolom Praktis 12.857 M'
LAPANGAN Beton Lantai 1
7 Kepala Pelaksana 1 6 Kolom Praktis 107.143 M'
8 Pelaksana (P) 3 7 Beton ring balk dan latai 107.143 M'
9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2
10 Surveyor 5 Pemasangan Bata Ringan area toilet finish plesteran acian
Tukang Pekerja 9 Lantai 1 Elevasi 75.554 M2
11 Kayu 13 31 44 Pemasangan Bata Ringan area dinding biasa finish plesteran acian
12 Batu - 10 Lantai 1 Elevasi 225.883 M2
13 Besi 8 21 29 Plesteran Acian Beton mu 290
14 Las 2 5 7 11 Lantai Basement 153.944 M2
15 Listrik - Lantai 2
16 Plumbing 6 19 25 12 Pipa PVC AW dia.4" (air kotor) merk WAVIN 31.857 M
17 Aspal - 13 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M
18 Cat - 14 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M
19 Galian - Lantai 3
20 Pembersih - 15 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M
21 Waterproofing - 16 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M
22 Finishing - 17 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M
23 Pembantu 5 5 Pekerjaan Drainase Hujan
24 Pengecoran 3 7 10 18 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M
25 Operator Alat Berat 3 19 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M
26 Operator/Driver Lainnya 2
T O T A L 144
PT. ADHI KARYA (Persero) Tbk.
Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai Jumlah
Bata Ringan 60 M3 Excavator Pc - 200 1
Tanah 5 M3 Stamper 2
Mobile Crane 25 Ton 2
KEADAAN CUACA HARI INI JAM KERJA
Pagi Cerah Mulai 8:00
Siang Cerah Selesai 17:00
Sore Cerah
Malam Cerah
PERMASALAHAN :
PENYELESAIAN :
Menyetujui, Disusun Oleh,
Kontraktor Pelaksana Manajemen Konstruksi
PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA
Heri Prayono, ST. Hari Sugiarto, ST.
Project Production Manager Supervisi Struktur
Catatan :
TANGGAL REVISI HAL ……… / ……….
DAILY ACTIVITY REPORT
LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015
OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "
PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH
Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE
Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE - SISA HARI
Waktu Pelaksanaan 210 Hari Kalender 14-Apr-2015 17 ( Tujuh Belas ) 117 93
U R A I A N
TENAGA KERJA JMLKEGIATAN
HARI INI
MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN KET.
1 Project Manager 1 1 Uitzet dan Bouwplank 0.005 Ls
2 Project Engineer Manager 1 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls
3 Project Production Manager 1 3 Mobil Tadano (sewa) 0.005 Ls
4 Project Planning 1 4 Mob Demob material dan alat 0.011 Ls
5 Project Control 1 Beton Basement
6 Drafter 2 5 Kolom Praktis 12.857 M'
LAPANGAN Beton Lantai 1
7 Kepala Pelaksana 1 6 Kolom Praktis 107.143 M'
8 Pelaksana (P) 3 7 Beton ring balk dan latai 107.143 M'
9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2
10 Surveyor 5 Beton Lantai 3
Tukang Pekerja 9 Beton Balok B1 4.973 M3
11 Kayu 11 29 40 10 Beton Balok B2 0.637 M3
12 Batu - 11 Beton Balok B3 4.230 M3
13 Besi 12 19 31 12 Beton Balok B4 4.814 M3
14 Las 2 5 7 13 Beton Balok B5 3.931 M3
15 Listrik - 14 Beton Balok B6 5.006 M3
16 Plumbing 6 19 25 15 Beton Balok B7 4.846 M3
17 Aspal - 16 Beton Balok B8 1.539 M3
18 Cat - 17 Beton Balok B11 4.445 M3
19 Galian - 18 Plat Lantai 25.988 M3
20 Pembersih - Pemasangan Bata Ringan area toilet finish plesteran acian
21 Waterproofing - 19 Lantai 1 Elevasi 75.554 M2
22 Finishing - Pemasangan Bata Ringan area dinding biasa finish plesteran acian
23 Pembantu - 5 5 20 Lantai 1 Elevasi 225.883 M2
24 Pengecoran 3 7 10 Plesteran Acian Beton mu 290
25 Operator Alat Berat 4 21 Lantai Basement 153.944 M2
26 Operator/Driver Lainnya 2 Lantai 2
22 Pipa PVC AW dia.4" (air kotor) merk WAVIN 31.857 M
23 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M
T O T A L 143 24 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M
Lantai 3
25 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M
26 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M
27 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M
Pekerjaan Drainase Hujan
28 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M
29 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M
PT. ADHI KARYA (Persero) Tbk.
Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai Jumlah
Beton K-300 60.5 M3 Excavator Pc - 200 1
Concrete pump 1 unit Stamper 2
Air compresor 1 unit Mobile Crane 25 Ton 2
Material Bekisting (Plywood) 100 lembar Concrete Pump 1
Air Compresor 1
KEADAAN CUACA HARI INI JAM KERJA
Pagi Cerah Mulai 8:00
Siang Cerah Selesai 17:00
Sore Cerah
Malam Cerah
PERMASALAHAN :
PENYELESAIAN :
Menyetujui, Disusun Oleh,
Kontraktor Pelaksana Manajemen Konstruksi
PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA
Heri Prayono, ST. Hari Sugiarto, ST.
Project Production Manager Supervisi Struktur
Catatan :
TANGGAL REVISI HAL ……… / ……….
DAILY ACTIVITY REPORT
REKAPITULASI LAPORAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015
OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "
PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH
Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE
Surat Penyerahan Lapangan 18-Dec-2014 Tanggal MINGGU KE - Awal 8-Apr-2015 SISA HARI
Waktu Pelaksanaan 210 Hr. Kalender 14-Apr-2015 17 ( Tujuh Belas ) Akhir 14-Apr-2015 93
U R A I A N
HARI Rabu Kamis Jumat Sabtu Minggu Senin Selasa
HARI KE - 111 112 113 114 115 116 117
JAM KERJA EFEKTIF ( Jam ) 12 12 12 12 17 12 17
JUMLAH JAM KERJA ( Jam ) 94
TENAGA KERJA JUMLAH TENAGAJUMLAH
RATA-RATA/HARI
MANAJEMEN
1 Project Manager 1 1 1 1 - 1 1 1
2 Project Engineer Manager 1 1 1 1 - 1 1 1
3 Project Production Manager 1 1 1 1 - 1 1 1
4 Project Planning 1 1 1 1 - 1 1 1
5 Project Control 1 1 1 1 - 1 1 1
6 Drafter 2 2 2 2 - 2 2 2
LAPANGAN -
7 Kepala Pelaksana 1 1 1 1 - 1 1 1
8 Pelaksana (P) 3 3 3 3 2 3 3 3
9 Mandor (M) 3 3 3 3 3 3 3 3
10 Surveyor 5 5 5 5 2 5 5 4
-
11 Kayu 48 43 40 34 13 44 40 36
12 Batu - - - - - 0 0 -
13 Besi 24 26 29 24 13 29 31 23
14 Las 7 7 7 7 - 7 7 6
15 Listrik - - - - - - -
16 Plumbing 29 28 22 25 25 25 25 26
17 Aspal - - - - - - - -
18 Cat - - - - - - - -
19 Galian - - - - - - - -
20 Pembersih - - - - - - - -
21 Waterproofing - - - - - - - -
22 Finishing - - - 5 - - - 1
23 Pembantu 5 5 5 10 5 5 5 6
24 Pengecoran 10 10 10 3 10 10 10 9
25 Operator Alat Berat 3 4 3 2 3 3 4 3
26 Operator Lainnya 2 2 2 - 2 2 2 2
T O T A L 147 144 137 129 78 144 143 922
CATATAN : Jumlah Tenaga s/d Minggu Lalu 8,756
Jumlah Tenaga Minggu Ini 922
Jumlah Tenaga s/d Minggu Ini 9,678
Menyetujui, Disusun Oleh,
Kontraktor Pelaksana Manajemen Konstruksi
PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA
Heri Prayono, ST. Hari Sugiarto, ST.
Project Production Manager Supervisi Struktur
TANGGAL REVISI HAL ……… / ……….
PT. ADHI KARYA (Persero) Tbk.
WEEKLY ACTIVITY REPORT
REKAPITULASI PEKERJAAN
OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "
PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH
Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE
Surat Penyerahan Lapangan 18-Dec-2014 Tanggal MINGGU KE - Awal SISA HARI
Waktu Pelaksanaan 210 Hr. Kalender Akhir
U R A I A N
NO. ITEM PEKERJAAN VOLUME SATUAN KET.
1 Pekerjaan Struktur
2 Pekerjaan Persiapan 0.179 LS
3 Pekerjaan Beton
4 Beton Basement
5 Kolom Praktis 90.000 M'
6 Beton Lantai 1
7 Kolom Praktis 750.000 M'
8 Beton ring balk dan latai 750.000 M'
9 Kuda-kuda baja ringan galvanish GigaSteel 91.000 M2
10 Beton Lantai 2
11 Kolom K2, K3, K4, K6, K10 15.382 M3
12 Beton Balok B1, B2, B3, B4, B5, B6, B7, B7a, B8, B9, B10, B11, Plat Lantai 21.899 M3
13 Beton Lantai 3
14 Kolom K2, K4, K6, K10 15.060 M3
15 Beton Balok B1, B2, B3, B4, B5, B6, B7, B8, B11, Plat Lantai 60.409 M3
16 Pekerjaan Arsitektur
17 Pekerjaan Pasangan
18 Pemasangan Bata Ringan area toilet finish plesteran acian
19 Lantai 1 Elevasi 528.770 M2
20 Pemasangan Bata Ringan area dinding biasa finish plesteran acian
21 Lantai 1 Elevasi 1581.180 M2
22 Plesteran Acian Beton mu 290
23 Lantai Basement 1077.610 M2
24 Pekerjaan Sistem Air Limbah
25 Lantai 2
26 Pipa PVC AW dia.4" (air kotor) merk WAVIN 223.000 M
27 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 284.000 M
28 Pipa PV AW dia.1" (Vent) merk WAVIN 537.000 M
29 Lantai 3
30 Pipa PVC AW dia.4" (air kotor) merk WAVIN 234.000 M
31 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 434.000 M
32 Pipa PV AW dia.1" (Vent) merk WAVIN 618.000 M
33 Pekerjaan Drainase Hujan
34 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 95.000 M
35 Pipa drainase air hujan horizontal ,PVC AW dia.4" 292.500 M
36 Roofdrain (cast iron tipe meshroom) 38.000 Bh
NO. PERMASALAHAN
1
2
PT. ADHI KARYA (Persero) Tbk.
NO. SOLUSI PERMASALAHAN
1
2
CATATAN :
Menyetujui, Disusun Oleh,
Kontraktor Pelaksana Manajemen Konstruksi
PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA
Yan Arianto, ST. Ir. Edward Siahaan
Project Manager Team Leader
TANGGAL REVISI HAL ……… / ……….
LAPORAN KEGIATAN HARIAN
No. 001/LKH/PRYK-WUJIL/XII/2014
PROYEK : Pembangunan Komplek "THE WUJIL HOTEL UNGARAN"
LOKASI : JL. SOEKARNO HATTA KM 25.5 UNGARAN
KONTRAKTOR : PT. ADHI KARYA (Persero) Tbk. Tanggal : 18-Dec-14
URAIAN
TENAGA KERJA JMLKEGIATAN
HARI INI
MANAJEMEN NO. ITEM PEKERJAAN VOLUME SATUAN KETERANGAN
1 Project Manager 1
2 Project Engineer Manager 1 1 Uitzet dan Bouwplank ls
3 Project Production Manager 1 2 Pembersihan pohon eksisting ls
4 Project Planning 1
5 Project Control 1
6 Administrasi 1
LAPANGAN
7 Kepala Pelaksana 1
8 Pelaksana (P) 2
9 Mandor (M) 1
10 Tukang (T) 1
P M T
Kayu
Batu
Besi
Las
Listrik
Plumbing
Aspal
Cat
Galian
Pembersih 10
Waterproofing
Finishing
Pembantu 8
…………. CUACA
Jumlah GERIMIS HUJAN LEBAT
11 Operator Jam 12.00 s/d jam 14.00 Jam 14.00 s/d jam 16.00
12 Surveyor 1 Jam 17.00 s/d jam 18.00 Jam s/d jam
TOTAL Jam s/d jam Jam s/d jam
Bahan/Alat yang masuk Jumlah Bahan/Alat yang dipakai Jumlah
Masalah yang timbul Penyelesaian Menyetujui Diajukan
Catatan : Laporan harian ini diserahkan 1 (satu) hari berikutnya jam 09.00 dan dibuat dalam rangkap 2
TANGGAL REVISI HAL ……… / ……….
PT. ADHI KARYA (Persero) Tbk.DIVISI KONSTRUKSI VII
Jawa Tengah & DI YogyakartaJl. Pemuda No. 82 Semarang 50133, Telp: 024-354 7455 Fax.
024-355 1911
MENYETUJUI KONSUTAN MKPT. Wastu Buana Adi Cipta
Ir. Edward Siahaan Team Leader
DIAJUKAN OLEH KONTRAKTOR,PT. Adhi Karya (Persero) Tbk.
Yoga Adi Prasetyo, AmdProject Engineer Manager