DAILY REPORT P E K E R J A A N PEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN " JALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH NAMA PEMILIK : Mrs. TETI YANI HARTONO KONTRAKTOR : PT. ADHI KARYA (Persero) Tbk. NOMOR KONTRAK : 10/TENDER/TWUJIL/UNG/XII/2014 TANGGAL : 18 Desember 2014 SPMK : 11/TENDER/TWUJIL/UNG/XII/2014 TANGGAL : 19 Desember 2014 LAPORAN HARIAN MINGGU KE : 17 ( Tujuh Belas ) TANGGAL : 08 April 2015 s/d TANGGAL : 14 April 2015 MANAJEMEN KONSTRUKSI

Upload: kurniadi-saputra

Post on 25-Jan-2016

15 views

Category:

Documents


5 download

DESCRIPTION

a

TRANSCRIPT

Page 1: LH Periode 8 Apr - 14 Apr 2015

DAILY REPORT

P E K E R J A A N

PEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "JALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH

NAMA PEMILIK : Mrs. TETI YANI HARTONOKONTRAKTOR : PT. ADHI KARYA (Persero) Tbk.

NOMOR KONTRAK : 10/TENDER/TWUJIL/UNG/XII/2014

TANGGAL : 18 Desember 2014

SPMK : 11/TENDER/TWUJIL/UNG/XII/2014

TANGGAL : 19 Desember 2014

LAPORAN HARIAN

MINGGU KE : 17 ( Tujuh Belas )TANGGAL : 08 April 2015

s/d TANGGAL : 14 April 2015

MANAJEMEN KONSTRUKSI

Page 2: LH Periode 8 Apr - 14 Apr 2015

DAILY ACTIVITY REPORT

LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015

OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "

PT. INDAH SARI LESTARIJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH

Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE

Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE -

Waktu Pelaksanaan 210 Hari Kalender 8-Apr-2015 17 ( Tujuh Belas ) 111

U R A I A N

TENAGA KERJA JMLKEGIATAN

HARI INI

MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN

1 Project Manager 1 1 Uitzet dan Bouwplank 0.005 Ls

2 Project Engineer Manager 1 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls

3 Project Production Manager 1 3 Mobil Tadano (sewa) 0.005 Ls

4 Project Planning 1 4 Mob Demob material dan alat 0.011 Ls

5 Project Control 1 Beton Basement

6 Drafter 2 5 Kolom Praktis 12.857 M'

LAPANGAN Beton Lantai 1

7 Kepala Pelaksana 1 6 Kolom Praktis 107.143 M'

8 Pelaksana (P) 3 7 Beton ring balk dan latai 107.143 M'

9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2

10 Surveyor 5 Pemasangan Bata Ringan area toilet finish plesteran acian

Tukang Pekerja 9 Lantai 1 Elevasi 75.554 M2

11 Kayu 17 31 48 Pemasangan Bata Ringan area dinding biasa finish plesteran acian

12 Batu - 9 Lantai 1 Elevasi 225.883 M2

13 Besi 10 14 24 Plesteran Acian Beton mu 290

14 Las 2 5 7 11 Lantai Basement 153.944 M2

15 Listrik - Lantai 2

16 Plumbing 5 24 29 12 Pipa PVC AW dia.4" (air k 31.857 M

17 Aspal - 13 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M

18 Cat - 14 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M

19 Galian - Lantai 3

20 Pembersih - 15 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M

21 Waterproofing - 16 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M

22 Finishing - 17 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M

23 Pembantu - 5 5 Pekerjaan Drainase Hujan

24 Pengecoran 3 7 10 18 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M

25 Operator Alat Berat 3 19 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M

26 Operator/Driver Lainnya 2 20 Roofdrain (cast iron tipe meshroom) 12.000 Bh

T O T A L 147

CV. WASTU BUANA ADI CIPTA

PT. ADHI KARYA (Persero) Tbk.

Page 3: LH Periode 8 Apr - 14 Apr 2015

Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai

Excavator Pc - 200

Stamper

Mobile Crane 25 Ton

KEADAAN CUACA HARI INI JAM KERJA

Pagi Cerah Mulai

Siang Cerah Selesai

Sore Cerah

Malam Cerah

PERMASALAHAN :

PENYELESAIAN :

Menyetujui, Disusun Oleh,

Kontraktor Pelaksana Manajemen Konstruksi

PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA

Heri Prayono, ST. Hari Sugiarto, ST.

Project Production Manager Supervisi Struktur

Catatan :

TANGGAL REVISI HAL ……… / ……….

Page 4: LH Periode 8 Apr - 14 Apr 2015

LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015

PEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "

JALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH

PERIODE

SISA HARI

99

U R A I A N

KEGIATAN

HARI INI

KET.

Page 5: LH Periode 8 Apr - 14 Apr 2015

Jumlah

1

2

2

JAM KERJA

8:00

17:00

PERMASALAHAN :

PENYELESAIAN :

Disusun Oleh,

Manajemen Konstruksi

CV. WASTU BUANA ADI CIPTA

Hari Sugiarto, ST.

Supervisi Struktur

Page 6: LH Periode 8 Apr - 14 Apr 2015

DAILY ACTIVITY REPORT

LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015

OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "

PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH

Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE

Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE - SISA HARI

Waktu Pelaksanaan 210 Hari Kalender 9-Apr-2015 17 ( Tujuh Belas ) 112 98

U R A I A N

TENAGA KERJA JMLKEGIATAN

HARI INI

MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN KET.

1 Project Manager 1 1 Uitzet dan Bouwplank 0.005 Ls

2 Project Engineer Manager 1 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls

3 Project Production Manager 1 3 Mobil Tadano (sewa) 0.005 Ls

4 Project Planning 1 4 Mob Demob material dan alat 0.011 Ls

5 Project Control 1 Beton Basement

6 Drafter 2 5 Kolom Praktis 12.857 M'

LAPANGAN Beton Lantai 1

7 Kepala Pelaksana 1 6 Kolom Praktis 107.143 M'

8 Pelaksana (P) 3 7 Beton ring balk dan latai 107.143 M'

9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2

10 Surveyor 5 Pemasangan Bata Ringan area toilet finish plesteran acian

Tukang Pekerja Jumlah 9 Lantai 1 Elevasi 75.554 M2

11 Kayu 13 30 43 Pemasangan Bata Ringan area dinding biasa finish plesteran acian

12 Batu - 10 Lantai 1 Elevasi 225.883 M2

13 Besi 11 15 26 Plesteran Acian Beton mu 290

14 Las 2 5 7 11 Lantai Basement 153.944 M2

15 Listrik - Lantai 2

16 Plumbing 6 22 28 12 Pipa PVC AW dia.4" (air kotor) merk WAVIN 31.857 M

17 Aspal - 13 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M

18 Cat - 14 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M

19 Galian - Lantai 3

20 Pembersih - 15 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M

21 Waterproofing - 16 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M

22 Finishing - 17 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M

23 Pembantu - 5 5 Pekerjaan Drainase Hujan

24 Pengecoran 3 7 10 18 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M

25 Operator Alat Berat 4 19 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M

26 Operator/Driver Lainnya 2 20 Roofdrain (cast iron tipe meshroom) 12.000 Bh

T O T A L 144

PT. ADHI KARYA (Persero) Tbk.

Page 7: LH Periode 8 Apr - 14 Apr 2015

Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai Jumlah

Excavator Pc - 200 1

Stamper 2

Mobile Crane 25 Ton 2

KEADAAN CUACA HARI INI JAM KERJA

Pagi Cerah Mulai 8:00

Siang Cerah Selesai 17:00

Sore Cerah

Malam Cerah

PERMASALAHAN :

PENYELESAIAN :

Menyetujui, Disusun Oleh,

Kontraktor Pelaksana Manajemen Konstruksi

PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA

Heri Prayono, ST. Hari Sugiarto, ST.

Project Production Manager Supervisi Struktur

Catatan :

TANGGAL REVISI HAL ……… / ……….

Page 8: LH Periode 8 Apr - 14 Apr 2015

DAILY ACTIVITY REPORT

LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015

OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "

PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH

Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE

Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE - SISA HARI

Waktu Pelaksanaan 210 Hari Kalender 10-Apr-2015 17 ( Tujuh Belas ) 113 97

U R A I A N

TENAGA KERJA JMLKEGIATAN

HARI INI

MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN KET.

1 Project Manager 1 1 Uitzet dan Bouwplank 0.005 Ls

2 Project Engineer Manager 1 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls

3 Project Production Manager 1 3 Mobil Tadano (sewa) 0.005 Ls

4 Project Planning 1 4 Mob Demob material dan alat 0.011 Ls

5 Project Control 1 Beton Basement

6 Drafter 2 5 Kolom Praktis 12.857 M'

LAPANGAN Beton Lantai 1

7 Kepala Pelaksana 1 6 Kolom Praktis 107.143 M'

8 Pelaksana (P) 3 7 Beton ring balk dan latai 107.143 M'

9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2

10 Surveyor 5 Beton Lantai 2

Tukang Pekerja 9 Kolom K2 3.159 M3

11 Kayu 7 33 40 10 Kolom K6 2.592 M3

12 Batu - 11 Kolom K10 2.800 M3

13 Besi 8 21 29 Beton Lantai 3

14 Las 2 5 7 12 Kolom K2 5.832 M3

15 Listrik - 13 Kolom K10 2.100 M3

16 Plumbing 5 17 22 Pemasangan Bata Ringan area toilet finish plesteran acian

17 Aspal - 14 Lantai 1 Elevasi 75.554 M2

18 Cat - Pemasangan Bata Ringan area dinding biasa finish plesteran acian

19 Galian - 15 Lantai 1 Elevasi 225.883 M2

20 Pembersih - Plesteran Acian Beton mu 290

21 Waterproofing - 16 Lantai Basement 153.944 M2

22 Finishing - Lantai 2

23 Pembantu - 5 5 17 Pipa PVC AW dia.4" (air kotor) merk WAVIN 31.857 M

24 Pengecoran 3 7 10 18 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M

25 Operator Alat Berat 3 19 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M

26 Operator/Driver Lainnya 2 Lantai 3

20 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M

21 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M

T O T A L 137 22 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M

Pekerjaan Drainase Hujan

23 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M

24 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M

25 Roofdrain (cast iron tipe meshroom) 14.000 Bh

PT. ADHI KARYA (Persero) Tbk.

Page 9: LH Periode 8 Apr - 14 Apr 2015

Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai Jumlah

Beton K-300 16.5 M3 Excavator Pc - 200 1

Pasir 10 M3 Stamper 2

Sirtu 15 M3 Mobile Crane 25 Ton 2

KEADAAN CUACA HARI INI JAM KERJA

Pagi Cerah Mulai 8:00

Siang Cerah Selesai 17:00

Sore Cerah

Malam Hujan

PERMASALAHAN :

PENYELESAIAN :

Menyetujui, Disusun Oleh,

Kontraktor Pelaksana Manajemen Konstruksi

PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA

Heri Prayono, ST. Hari Sugiarto, ST.

Project Production Manager Supervisi Struktur

Catatan :

TANGGAL REVISI HAL ……… / ……….

Page 10: LH Periode 8 Apr - 14 Apr 2015

DAILY ACTIVITY REPORT

LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015

OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "

PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH

Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE

Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE - SISA HARI

Waktu Pelaksanaan 210 Hari Kalender 11-Apr-2015 17 ( Tujuh Belas ) 114 96

U R A I A N

TENAGA KERJA JMLKEGIATAN

HARI INI

MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN KET.

1 Project Manager 1 1 Uitzet dan Bouwplank 0.005 Ls

2 Project Engineer Manager 1 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls

3 Project Production Manager 1 3 Mobil Tadano (sewa) 0.005 Ls

4 Project Planning 1 4 Mob Demob material dan alat 0.011 Ls

5 Project Control 1 Beton Basement

6 Drafter 2 5 Kolom Praktis 12.857 M'

LAPANGAN Beton Lantai 1

7 Kepala Pelaksana 1 6 Kolom Praktis 107.143 M'

8 Pelaksana (P) 3 7 Beton ring balk dan latai 107.143 M'

9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2

10 Surveyor 5 Beton Lantai 2

Tukang Pekerja 9 Kolom K2 3.159 M3

11 Kayu 7 27 34 10 Kolom K3 3.024 M3

12 Batu - 11 Kolom K4 0.648 M3

13 Besi 6 18 24 Beton Lantai 3

14 Las 2 5 7 12 Kolom K4 1.944 M3

15 Listrik - 13 Kolom K6 5.184 M3

16 Plumbing 6 19 25 Pemasangan Bata Ringan area toilet finish plesteran acian

17 Aspal - 14 Lantai 1 Elevasi 75.554 M2

18 Cat - Pemasangan Bata Ringan area dinding biasa finish plesteran acian

19 Galian - 15 Lantai 1 Elevasi 225.883 M2

20 Pembersih - Plesteran Acian Beton mu 290

21 Waterproofing - 16 Lantai Basement 153.944 M2

22 Finishing - Lantai 2

23 Pembantu 5 5 17 Pipa PVC AW dia.4" (air kotor) merk WAVIN 31.857 M

24 Pengecoran 3 7 10 18 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M

25 Operator Alat Berat 3 19 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M

26 Operator/Driver Lainnya 2 Lantai 3

20 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M

21 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M

T O T A L 129 22 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M

Pekerjaan Drainase Hujan

23 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M

24 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M

PT. ADHI KARYA (Persero) Tbk.

Page 11: LH Periode 8 Apr - 14 Apr 2015

Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai Jumlah

Betom K-300 14 M3 Excavator Pc - 200 1

Tanah 10 M3 Stamper 2

Bata Ringan 60 M3 Mobile Crane 25 Ton 2

KEADAAN CUACA HARI INI JAM KERJA

Pagi Cerah Mulai 8:00

Siang Hujan Selesai 17:00

Sore Cerah

Malam Gerimis

PERMASALAHAN :

PENYELESAIAN :

Menyetujui, Disusun Oleh,

Kontraktor Pelaksana Manajemen Konstruksi

PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA

Heri Prayono, ST. Hari Sugiarto, ST.

Project Production Manager Supervisi Struktur

Catatan :

TANGGAL REVISI HAL ……… / ……….

Page 12: LH Periode 8 Apr - 14 Apr 2015

DAILY ACTIVITY REPORT

LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015

OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "

PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH

Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE

Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE - SISA HARI

Waktu Pelaksanaan 210 Hari Kalender 12-Apr-2015 17 ( Tujuh Belas ) 115 95

U R A I A N

TENAGA KERJA JMLKEGIATAN

HARI INI

MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN KET.

1 Project Manager 1 Uitzet dan Bouwplank 0.005 Ls

2 Project Engineer Manager 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls

3 Project Production Manager 3 Mobil Tadano (sewa) 0.005 Ls

4 Project Planning 4 Mob Demob material dan alat 0.011 Ls

5 Project Control Beton Basement

6 Drafter 5 Kolom Praktis 12.857 M'

LAPANGAN Beton Lantai 1

7 Kepala Pelaksana 6 Kolom Praktis 107.143 M'

8 Pelaksana (P) 2 7 Beton ring balk dan latai 107.143 M'

9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2

10 Surveyor 2 Beton Lantai 2

Tukang Pekerja 9 Beton Balok B1 2.974 M3

11 Kayu 4 9 13 10 Beton Balok B2 0.294 M3

12 Batu - 11 Beton Balok B3 1.952 M3

13 Besi 4 9 13 12 Beton Balok B4 2.225 M3

14 Las - 13 Beton Balok B5 2.362 M3

15 Listrik - 14 Beton Balok B6 0.934 M3

16 Plumbing 8 17 25 15 Beton Balok B7 1.492 M3

17 Aspal - 16 Beton Balok B7a 0.093 M3

18 Cat - 17 Beton Balok B8 0.574 M3

19 Galian - 18 Beton Balok B9 0.058 M3

20 Pembersih - 19 Beton Balok B10 0.578 M3

21 Waterproofing - 20 Beton Balok B11 1.149 M3

22 Finishing - 21 Plat Lantai 7.214 M3

23 Pembantu 5 5 Pemasangan Bata Ringan area toilet finish plesteran acian

24 Pengecoran 3 7 10 22 Lantai 1 Elevasi 75.554 M2

25 Operator Alat Berat 3 Pemasangan Bata Ringan area dinding biasa finish plesteran acian

26 Operator/Driver Lainnya 2 23 Lantai 1 Elevasi 225.883 M2

Plesteran Acian Beton mu 290

24 Lantai Basement 153.944 M2

T O T A L 78 Lantai 2

25 Pipa PVC AW dia.4" (air kotor) merk WAVIN 31.857 M

26 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M

27 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M

Lantai 3

28 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M

29 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M

30 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M

Pekerjaan Drainase Hujan

31 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M

32 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M

PT. ADHI KARYA (Persero) Tbk.

Page 13: LH Periode 8 Apr - 14 Apr 2015

Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai Jumlah

Beton K-300 22 M3 Excavator Pc - 200 1

Concrete Pump 1 unit Stamper 2

Air compresor 1 unit Mobile Crane 25 Ton 2

Concrete Pump 1

Air Compresor 1

KEADAAN CUACA HARI INI JAM KERJA

Pagi Cerah Mulai 8:00

Siang Cerah Selesai 17:00

Sore Cerah

Malam Hujan

PERMASALAHAN :

PENYELESAIAN :

Menyetujui, Disusun Oleh,

Kontraktor Pelaksana Manajemen Konstruksi

PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA

Heri Prayono, ST. Hari Sugiarto, ST.

Project Production Manager Supervisi Struktur

Catatan :

TANGGAL REVISI HAL ……… / ……….

Page 14: LH Periode 8 Apr - 14 Apr 2015

DAILY ACTIVITY REPORT

LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015

OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "

PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH

Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE

Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE - SISA HARI

Waktu Pelaksanaan 210 Hari Kalender 13-Apr-2015 17 ( Tujuh Belas ) 116 94

U R A I A N

TENAGA KERJA JMLKEGIATAN

HARI INI

MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN KET.

1 Project Manager 1 1 Uitzet dan Bouwplank 0.005 Ls

2 Project Engineer Manager 1 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls

3 Project Production Manager 1 3 Mobil Tadano (sewa) 0.005 Ls

4 Project Planning 1 4 Mob Demob material dan alat 0.011 Ls

5 Project Control 1 Beton Basement

6 Drafter 2 5 Kolom Praktis 12.857 M'

LAPANGAN Beton Lantai 1

7 Kepala Pelaksana 1 6 Kolom Praktis 107.143 M'

8 Pelaksana (P) 3 7 Beton ring balk dan latai 107.143 M'

9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2

10 Surveyor 5 Pemasangan Bata Ringan area toilet finish plesteran acian

Tukang Pekerja 9 Lantai 1 Elevasi 75.554 M2

11 Kayu 13 31 44 Pemasangan Bata Ringan area dinding biasa finish plesteran acian

12 Batu - 10 Lantai 1 Elevasi 225.883 M2

13 Besi 8 21 29 Plesteran Acian Beton mu 290

14 Las 2 5 7 11 Lantai Basement 153.944 M2

15 Listrik - Lantai 2

16 Plumbing 6 19 25 12 Pipa PVC AW dia.4" (air kotor) merk WAVIN 31.857 M

17 Aspal - 13 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M

18 Cat - 14 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M

19 Galian - Lantai 3

20 Pembersih - 15 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M

21 Waterproofing - 16 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M

22 Finishing - 17 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M

23 Pembantu 5 5 Pekerjaan Drainase Hujan

24 Pengecoran 3 7 10 18 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M

25 Operator Alat Berat 3 19 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M

26 Operator/Driver Lainnya 2

T O T A L 144

PT. ADHI KARYA (Persero) Tbk.

Page 15: LH Periode 8 Apr - 14 Apr 2015

Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai Jumlah

Bata Ringan 60 M3 Excavator Pc - 200 1

Tanah 5 M3 Stamper 2

Mobile Crane 25 Ton 2

KEADAAN CUACA HARI INI JAM KERJA

Pagi Cerah Mulai 8:00

Siang Cerah Selesai 17:00

Sore Cerah

Malam Cerah

PERMASALAHAN :

PENYELESAIAN :

Menyetujui, Disusun Oleh,

Kontraktor Pelaksana Manajemen Konstruksi

PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA

Heri Prayono, ST. Hari Sugiarto, ST.

Project Production Manager Supervisi Struktur

Catatan :

TANGGAL REVISI HAL ……… / ……….

Page 16: LH Periode 8 Apr - 14 Apr 2015

DAILY ACTIVITY REPORT

LAPORAN KEGIATAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015

OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "

PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH

Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE

Surat Penyerahan Lapangan 18-Dec-2014 TANGGAL MINGGU KE - HARI KE - SISA HARI

Waktu Pelaksanaan 210 Hari Kalender 14-Apr-2015 17 ( Tujuh Belas ) 117 93

U R A I A N

TENAGA KERJA JMLKEGIATAN

HARI INI

MANAJEMEN NO. PEKERJAAN YANG DILAKSANAKAN VOLUME SATUAN KET.

1 Project Manager 1 1 Uitzet dan Bouwplank 0.005 Ls

2 Project Engineer Manager 1 2 Sewa kantor direksi/kantor proyek/workshop/gudang 0.005 Ls

3 Project Production Manager 1 3 Mobil Tadano (sewa) 0.005 Ls

4 Project Planning 1 4 Mob Demob material dan alat 0.011 Ls

5 Project Control 1 Beton Basement

6 Drafter 2 5 Kolom Praktis 12.857 M'

LAPANGAN Beton Lantai 1

7 Kepala Pelaksana 1 6 Kolom Praktis 107.143 M'

8 Pelaksana (P) 3 7 Beton ring balk dan latai 107.143 M'

9 Mandor (M) 3 8 Kuda-kuda baja ringan galvanish Giga Steel 13.000 M2

10 Surveyor 5 Beton Lantai 3

Tukang Pekerja 9 Beton Balok B1 4.973 M3

11 Kayu 11 29 40 10 Beton Balok B2 0.637 M3

12 Batu - 11 Beton Balok B3 4.230 M3

13 Besi 12 19 31 12 Beton Balok B4 4.814 M3

14 Las 2 5 7 13 Beton Balok B5 3.931 M3

15 Listrik - 14 Beton Balok B6 5.006 M3

16 Plumbing 6 19 25 15 Beton Balok B7 4.846 M3

17 Aspal - 16 Beton Balok B8 1.539 M3

18 Cat - 17 Beton Balok B11 4.445 M3

19 Galian - 18 Plat Lantai 25.988 M3

20 Pembersih - Pemasangan Bata Ringan area toilet finish plesteran acian

21 Waterproofing - 19 Lantai 1 Elevasi 75.554 M2

22 Finishing - Pemasangan Bata Ringan area dinding biasa finish plesteran acian

23 Pembantu - 5 5 20 Lantai 1 Elevasi 225.883 M2

24 Pengecoran 3 7 10 Plesteran Acian Beton mu 290

25 Operator Alat Berat 4 21 Lantai Basement 153.944 M2

26 Operator/Driver Lainnya 2 Lantai 2

22 Pipa PVC AW dia.4" (air kotor) merk WAVIN 31.857 M

23 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 40.571 M

T O T A L 143 24 Pipa PV AW dia.1" (Vent) merk WAVIN 76.714 M

Lantai 3

25 Pipa PVC AW dia.4" (air kotor) merk WAVIN 33.429 M

26 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 62.000 M

27 Pipa PV AW dia.1" (Vent) merk WAVIN 88.286 M

Pekerjaan Drainase Hujan

28 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 13.571 M

29 Pipa drainase air hujan horizontal ,PVC AW dia.4" 41.786 M

PT. ADHI KARYA (Persero) Tbk.

Page 17: LH Periode 8 Apr - 14 Apr 2015

Bahan/Alat Yang Masuk Jumlah Bahan/Alat yang dipakai Jumlah

Beton K-300 60.5 M3 Excavator Pc - 200 1

Concrete pump 1 unit Stamper 2

Air compresor 1 unit Mobile Crane 25 Ton 2

Material Bekisting (Plywood) 100 lembar Concrete Pump 1

Air Compresor 1

KEADAAN CUACA HARI INI JAM KERJA

Pagi Cerah Mulai 8:00

Siang Cerah Selesai 17:00

Sore Cerah

Malam Cerah

PERMASALAHAN :

PENYELESAIAN :

Menyetujui, Disusun Oleh,

Kontraktor Pelaksana Manajemen Konstruksi

PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA

Heri Prayono, ST. Hari Sugiarto, ST.

Project Production Manager Supervisi Struktur

Catatan :

TANGGAL REVISI HAL ……… / ……….

Page 18: LH Periode 8 Apr - 14 Apr 2015

DAILY ACTIVITY REPORT

REKAPITULASI LAPORAN HARIANNo. 017/LH/WASNADIPTA/MK/WUJIL/2015

OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "

PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH

Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE

Surat Penyerahan Lapangan 18-Dec-2014 Tanggal MINGGU KE - Awal 8-Apr-2015 SISA HARI

Waktu Pelaksanaan 210 Hr. Kalender 14-Apr-2015 17 ( Tujuh Belas ) Akhir 14-Apr-2015 93

U R A I A N

HARI Rabu Kamis Jumat Sabtu Minggu Senin Selasa

HARI KE - 111 112 113 114 115 116 117

JAM KERJA EFEKTIF ( Jam ) 12 12 12 12 17 12 17

JUMLAH JAM KERJA ( Jam ) 94

TENAGA KERJA JUMLAH TENAGAJUMLAH

RATA-RATA/HARI

MANAJEMEN

1 Project Manager 1 1 1 1 - 1 1 1

2 Project Engineer Manager 1 1 1 1 - 1 1 1

3 Project Production Manager 1 1 1 1 - 1 1 1

4 Project Planning 1 1 1 1 - 1 1 1

5 Project Control 1 1 1 1 - 1 1 1

6 Drafter 2 2 2 2 - 2 2 2

LAPANGAN -

7 Kepala Pelaksana 1 1 1 1 - 1 1 1

8 Pelaksana (P) 3 3 3 3 2 3 3 3

9 Mandor (M) 3 3 3 3 3 3 3 3

10 Surveyor 5 5 5 5 2 5 5 4

-

11 Kayu 48 43 40 34 13 44 40 36

12 Batu - - - - - 0 0 -

13 Besi 24 26 29 24 13 29 31 23

14 Las 7 7 7 7 - 7 7 6

15 Listrik - - - - - - -

16 Plumbing 29 28 22 25 25 25 25 26

17 Aspal - - - - - - - -

18 Cat - - - - - - - -

19 Galian - - - - - - - -

20 Pembersih - - - - - - - -

21 Waterproofing - - - - - - - -

22 Finishing - - - 5 - - - 1

23 Pembantu 5 5 5 10 5 5 5 6

24 Pengecoran 10 10 10 3 10 10 10 9

25 Operator Alat Berat 3 4 3 2 3 3 4 3

26 Operator Lainnya 2 2 2 - 2 2 2 2

T O T A L 147 144 137 129 78 144 143 922

CATATAN : Jumlah Tenaga s/d Minggu Lalu 8,756

Jumlah Tenaga Minggu Ini 922

Jumlah Tenaga s/d Minggu Ini 9,678

Menyetujui, Disusun Oleh,

Kontraktor Pelaksana Manajemen Konstruksi

PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA

Heri Prayono, ST. Hari Sugiarto, ST.

Project Production Manager Supervisi Struktur

TANGGAL REVISI HAL ……… / ……….

PT. ADHI KARYA (Persero) Tbk.

Page 19: LH Periode 8 Apr - 14 Apr 2015

WEEKLY ACTIVITY REPORT

REKAPITULASI PEKERJAAN

OWNER MANAJEMEN KONSTRUKSI KONTRAKTOR PELAKSANAPEMBANGUNAN KOMPLEK " THE WUJIL UNGARAN "

PT. INDAH SARI LESTARI CV. Wastu Buana Adi CiptaJALAN SOEKARNO - HATTA KM. 25.5, UNGARAN - JAWA TENGAH

Surat Perintah Mulai Kerja 19-Dec-2014 PERIODE

Surat Penyerahan Lapangan 18-Dec-2014 Tanggal MINGGU KE - Awal SISA HARI

Waktu Pelaksanaan 210 Hr. Kalender Akhir

U R A I A N

NO. ITEM PEKERJAAN VOLUME SATUAN KET.

1 Pekerjaan Struktur

2 Pekerjaan Persiapan 0.179 LS

3 Pekerjaan Beton

4 Beton Basement

5 Kolom Praktis 90.000 M'

6 Beton Lantai 1

7 Kolom Praktis 750.000 M'

8 Beton ring balk dan latai 750.000 M'

9 Kuda-kuda baja ringan galvanish GigaSteel 91.000 M2

10 Beton Lantai 2

11 Kolom K2, K3, K4, K6, K10 15.382 M3

12 Beton Balok B1, B2, B3, B4, B5, B6, B7, B7a, B8, B9, B10, B11, Plat Lantai 21.899 M3

13 Beton Lantai 3

14 Kolom K2, K4, K6, K10 15.060 M3

15 Beton Balok B1, B2, B3, B4, B5, B6, B7, B8, B11, Plat Lantai 60.409 M3

16 Pekerjaan Arsitektur

17 Pekerjaan Pasangan

18 Pemasangan Bata Ringan area toilet finish plesteran acian

19 Lantai 1 Elevasi 528.770 M2

20 Pemasangan Bata Ringan area dinding biasa finish plesteran acian

21 Lantai 1 Elevasi 1581.180 M2

22 Plesteran Acian Beton mu 290

23 Lantai Basement 1077.610 M2

24 Pekerjaan Sistem Air Limbah

25 Lantai 2

26 Pipa PVC AW dia.4" (air kotor) merk WAVIN 223.000 M

27 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 284.000 M

28 Pipa PV AW dia.1" (Vent) merk WAVIN 537.000 M

29 Lantai 3

30 Pipa PVC AW dia.4" (air kotor) merk WAVIN 234.000 M

31 Pipa PVC AW dia.3", 2" (air bekas) merk WAVIN 434.000 M

32 Pipa PV AW dia.1" (Vent) merk WAVIN 618.000 M

33 Pekerjaan Drainase Hujan

34 Pipa drainase air hujan vertikal (down pipe),PVC AW dia.4" 95.000 M

35 Pipa drainase air hujan horizontal ,PVC AW dia.4" 292.500 M

36 Roofdrain (cast iron tipe meshroom) 38.000 Bh

NO. PERMASALAHAN

1

2

PT. ADHI KARYA (Persero) Tbk.

Page 20: LH Periode 8 Apr - 14 Apr 2015

NO. SOLUSI PERMASALAHAN

1

2

CATATAN :

Menyetujui, Disusun Oleh,

Kontraktor Pelaksana Manajemen Konstruksi

PT. ADHI KARYA (Persero) Tbk. CV. WASTU BUANA ADI CIPTA

Yan Arianto, ST. Ir. Edward Siahaan

Project Manager Team Leader

TANGGAL REVISI HAL ……… / ……….

Page 21: LH Periode 8 Apr - 14 Apr 2015

LAPORAN KEGIATAN HARIAN

No. 001/LKH/PRYK-WUJIL/XII/2014

PROYEK : Pembangunan Komplek "THE WUJIL HOTEL UNGARAN"

LOKASI : JL. SOEKARNO HATTA KM 25.5 UNGARAN

KONTRAKTOR : PT. ADHI KARYA (Persero) Tbk. Tanggal : 18-Dec-14

URAIAN

TENAGA KERJA JMLKEGIATAN

HARI INI

MANAJEMEN NO. ITEM PEKERJAAN VOLUME SATUAN KETERANGAN

1 Project Manager 1

2 Project Engineer Manager 1 1 Uitzet dan Bouwplank ls

3 Project Production Manager 1 2 Pembersihan pohon eksisting ls

4 Project Planning 1

5 Project Control 1

6 Administrasi 1

LAPANGAN

7 Kepala Pelaksana 1

8 Pelaksana (P) 2

9 Mandor (M) 1

10 Tukang (T) 1

P M T

Kayu

Batu

Besi

Las

Listrik

Plumbing

Aspal

Cat

Galian

Pembersih 10

Waterproofing

Finishing

Pembantu 8

…………. CUACA

Jumlah GERIMIS HUJAN LEBAT

11 Operator Jam 12.00 s/d jam 14.00 Jam 14.00 s/d jam 16.00

12 Surveyor 1 Jam 17.00 s/d jam 18.00 Jam s/d jam

TOTAL Jam s/d jam Jam s/d jam

Bahan/Alat yang masuk Jumlah Bahan/Alat yang dipakai Jumlah

Masalah yang timbul Penyelesaian Menyetujui Diajukan

Catatan : Laporan harian ini diserahkan 1 (satu) hari berikutnya jam 09.00 dan dibuat dalam rangkap 2

TANGGAL REVISI HAL ……… / ……….

PT. ADHI KARYA (Persero) Tbk.DIVISI KONSTRUKSI VII

Jawa Tengah & DI YogyakartaJl. Pemuda No. 82 Semarang 50133, Telp: 024-354 7455 Fax.

024-355 1911

MENYETUJUI KONSUTAN MKPT. Wastu Buana Adi Cipta

Ir. Edward Siahaan Team Leader

DIAJUKAN OLEH KONTRAKTOR,PT. Adhi Karya (Persero) Tbk.

Yoga Adi Prasetyo, AmdProject Engineer Manager