fydp slide lukman

Upload: apiskai3096

Post on 03-Apr-2018

234 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Fydp Slide Lukman

    1/13

  • 7/28/2019 Fydp Slide Lukman

    2/13

    PROCESS SAFETY AND LOSS

    PREVENTIONHazard and Operability Studies

  • 7/28/2019 Fydp Slide Lukman

    3/13

    HAZOP Analysis

    A Hazard and Operability(HAZOP) study is a systematicexamination to identify andevaluate safety hazards andoperability problems

    which, although might not behazardous.

    Based on guide-words and iscarried out by a multi-disciplinary team (HAZOPteam).

    HAZOP Study Procedures

    TeamDiscussion

    Requirement: PFD P&ID

    SOP

    to identify

    Possible Deviations Causes Consequences

    Action required

  • 7/28/2019 Fydp Slide Lukman

    4/13

    Study Nodes

    Reactor

    Phase

    Separator

    Absorption

    Column

    Study Node

    Study Node

    Study Node

    Node 1: Reactor (R-101)

    Node 2: Distillation Column (C-102)

    Node 3: Heat Exchanger (E-1)

    For this HAZOP study it is limited

    to THREE (3) process lines, in

    which TWO (2) of the process

    lines must be connected to ONE

    (1) major equipment

  • 7/28/2019 Fydp Slide Lukman

    5/13

    Process Section: Reactor R-101

    Node 1: Stream S7

    Process parameter: Flow

    Guide

    word

    Possible causes Possible consequences Required actions

    No Use of fail closedtyped control valve

    Fracture of pipeNo feedstock supplied, no productproduced as no reaction taken

    place

    Reactor shutdown

    Employ fail opened typed control valveInstall emergency shutdown (ESD) valve or shutdownplant immediately

    Less Leakage in pipingBlockage in pumpsControl valve failedpartially

    opened/closed

    position

    Reduced rate of reactionInconsistent production rateReduced amount of process fluids

    to R-101

    Install flow indicatorInstall low flow or low level alarm to R-101Install check valve to stream S-7

    More Control valve failsopen

    Increased amount of processfluids to R-101 and over spillage

    Install flow indicator

    Install high flow alarm and relief valveReverse Backflow due to

    backpressure in

    reactor

    Reduced amount of feedstock,thus reduced yielded product

    Install check valve or flow indicator and alarm toacknowledge the changes in flow

    Regular inspection and maintenance of valve

  • 7/28/2019 Fydp Slide Lukman

    6/13

    PROCESS SAFETY AND LOSS

    PREVENTIONPlant Layout

  • 7/28/2019 Fydp Slide Lukman

    7/13

    Plant Layout

    Main

    road

    Chemical Storage Units

    Reactor System

    Loading

    and

    unloadin

    g bay

    Utility SectionsGate 1Gate 2

    Gate 3

    Flare

    Raw materials

    Future expansion site 2 / Assembly area 2

    Future

    expansion site 1

    / Assembly Area

    1

    Training

    Center/Seminar /

    Conference

    Room

    Administration and Technical Services

    Parking Canteen

    Prayer Hall

    Clinic

    Main Power Supply

    Guard

    House

    Wastewater

    treatment plant

    LaboratoryFuture expansion

    site 3

    Fire station

    Separation SectionMaintenance

    Warehouse

    Control building

    Minor Equipments

    Housing

    Gate 4

    Process Area Non-Process Area

    Cost Operation Maintenance Safety

  • 7/28/2019 Fydp Slide Lukman

    8/13

    Conclusion

    The design of the high purity ethylbenzene with a capacity of 500,000 ton per year is successfully completed.

    Approach to Conceptual Design, Environmental and Safety issues,Process and Mechanical design of equipments, EconomicsEvaluation, Instrumentations and Control is proposed based onliteratures, handbooks and real industry application.

    The plant layout was designed to integrate plant wide controlstrategy. The total capital investment of the plant is approximatelyRM76, 000, 000.

    The proposed plant design is economically justified,operationally feasible and profitable.

  • 7/28/2019 Fydp Slide Lukman

    9/13

    Recommendations

    Ethyl benzene production technologies and processes should bekept recent and economical to optimize the profits.

    Cost reduction program should be introduced from Day 1 of plantoperation.

    Employee Career Development Plan in place to ensure knowledgeprogression in the company.

  • 7/28/2019 Fydp Slide Lukman

    10/13

    MAJOR EQUIPMENTS

  • 7/28/2019 Fydp Slide Lukman

    11/13

    R-101

    C-103

    C-102

    R-102

    C-101

    Unit Operations

  • 7/28/2019 Fydp Slide Lukman

    12/13

    Packed Bed ReactorOperating Pressure 3500 kPa

    OperatingTemperature

    2200C

    Reactor Diameter 3.96 m

    Reactor Height 7.1 m

    Volume 29.12 m3

    Thickness 66 mm

    Number of Baffle 5 baffles

    Number of tube 2215 tubes

    Material of Cons. Shell and Tube - CS

    Grade 2B

  • 7/28/2019 Fydp Slide Lukman

    13/13

    Q&A Session

    Thank you