asosiasi panas bumi indonesia

Upload: effendi-rahmad

Post on 10-Feb-2018

244 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    1/34

    US-Indonesia Geothermal EducationCapacity Building Padang

    8 October 2012

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    2/34

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    3/34

    VISION

    AGENDA :

    I. BACKGROUNDII. INTRODUCTION API (INAGA)III. GEOTHERMAL INDONESIAIV. THE HUMAN RESOURCE CHALLENGESV. CONCLUSION

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    4/34

    BACKGROUND

    .

    INDONESIA HAS A TOTAL RESOURCES OF 29 GW GEOTHERMAL CAPACITY,

    UNFORTUNATELY JUST 1283.5 MW UTILIZED (4.5 % as of Aug 2012), ANY

    CONTRACTED ADDITIONAL DEVELOPMENTS WERE CEASED AND AGREED

    PPAS WERE CANCELLED DUE TO THE ASIA FINANCIAL CRISIS IN 1997 -

    1998

    UNDER ERA REFORMASI REFFEREDTO THE LAW No. 27/2003, THE

    OWNERSHIP OF RESOURCES WAS MOVED FROM CENTRAL TO LOCAL

    GOVERNMENTS, THE DEVELOPMENT AND OPERATION OF GEOTHERMAL

    FIELDS WHICH WAS UNDER MONOPOLY ARRANGEMENT ON BEHALF OF

    PERTAMINA HAS BEEN CHANGED, NOW MUST COMPETE WITH OTHER

    PUBLIC AND/OR PRIVATE COMPANIES.

    CONSIDERED DECLINING OF FOSSIL FUEL AND REDUCTION OF CO2

    EMISSION, GOI REQUESTED TO ACCELERATE THE RENEWABLE ENERGYDEVELOPMENT PARTICULARLY GEOTHERMAL, 51 WORKING AREAS

    (WKP) HAVE BEEN ESTABLISHED (INCLUDE 15 EXISTING WKPS OWNED BY

    PT PGE) AND COMMITTED TO DEVELOP AN ADDITIONAL CAPACITY OF

    ABOUT 2962 MW IN 2014/15 AND TO BECOME 12.332 MW IN 2025.

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    5/34

    BACKGROUND

    TO OBTAIN AMBISIUS TARGET FROM CURRENT STATUS CAPACITY 1283.5

    MW TO BECOME 4756 MW IN 2014/15, REQUIRED THE EXPLORATIONIST

    AND ENGINEERS OF GEOTHERMAL UP TO APPROX. 4.000 PEOPLES,

    THERE SHOULD BE A PROGRAMME IN THE NATIONAL GEOTHERMALCAPACITY BUILDING AND SUPPORTED BY ALL STAKEHOLDERS.

    THE GEOTHERMAL CAPACITY BUILDING PROGRAMS OBJECTIVES IS TO

    INCREASE THE CAPACITY OF INDONESIA TO DEVELOP AND OPERATE

    GEOTHERMAL FIELDS, TO ADVANCE THE KNOWLEDGE AND SKILL BASE

    OF INDONESIAS CENTRES OF EXCELLENCE REGARDING BESTENGINEERING PRACTICES

    MEANS TO ACHIEVE THE OBJECTIVE TO DEVELOP AND ADMINISTER

    TRAINING IN GEOTHERMAL SUBJECTS AREAS, ENHANCED INDONESIAS

    GEOTHERMAL RESEARCH CAPACITY, ENHANCED AND OPTIMIZED THE

    GEOTHERMAL LOW-MEDIUM ENTHALPY ALSO THE GEOTHERMAL DIRECT

    USED

    ENHANCED THE GEOTHERMAL DATA BASE AS A CENTRE OF NATIONAL

    GEOTHERMAL INFORMATION, DEVELOP THE GEOTHERMAL TECHNOLOGY

    CENTRE AND GEOTHERMAL TRAINING CENTRE

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    6/34

    API is a professional and nonprofit organization, which function as a forumof communication, coordination and consultation in order to improve itscapabilities, understanding, cooperation and responsibility of the role ofgeothermal energy development in Indonesia.

    MEMBERS: there are around 600 members of API which covers: Geothermal Companies: PGE, Chevron, Star Energy, Supreme Energy, Geodipa,

    Medco, Bakrie Power, Indonesia Power, rekayasaIndustri, PLN Geothermal.

    Academic: ITB, UI, UGM, UNILA, Trisakti etc

    Regional Chapter: JatengDIY and Lampung

    Professionals and Individuals

    CONTRIBUTION: API is actively involved in drafting Academic Paper for the several geothermal

    regulation

    Continuously seeking solutions for issues related to geothermal developmentin Indonesia as inputs to the government

    Advocating and facilitating solution for geothermal development

    Provide seminars, luncheon Talk, panel discussion in geothermal development

    API MEMBERS CAPABILITIES: Upstream and Downstream Geothermal Field Development

    Front End Engineering Design

    Engineering, Procurement and Construction

    Training in geothermal development

    INTRODUCING API (INDONESIA GEOTHERMAL ASSOCIATION)

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    7/34

    VISION

    Being a trusted partner of government,

    companies and professionals in thegeothermal energy business, in encouraging

    and facilitating the development of

    Indonesia's geothermal potential as an main

    energy choice in order to support energy

    security and sustainable national economic

    growth and ensure the creation of Indonesia

    as the "Super Power" in the geothermalenergy utilization

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    8/34

    MISSION

    Encouraging conducive investment climate of geothermal

    development through close cooperation and mutual benefit between

    the government and employers and ensure the creation of governmentregulations, both national and local that are sup portive and aligned.

    Overseeing road map of government in the development of

    geothermal energy as a new and renewable energy as the

    implementation of the national energy mix 25/25 policy (25% in 2025).

    To encourage the development of human resources and geothermal

    energy technology development through cooperation with

    governments, educational institutions, companies and professional

    organizations, both national and international, towards the

    independence of Indonesia as a "geothermal center of excellence".

    To socialize and educate the public about the potential, contributions

    and positive values, to support the creation of conducive conditions in

    geothermal development efforts.

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    9/34

    Cadangan Energi Nasional (2011*)

    Minyakbumi9,1 milyar barrels - produksi 387

    juta bbl/tahun ->sisa 28 tahun lagi

    Gas Alam185,8 Trilliun Kaki kubik - produksi

    2,95 TSCF ->sisa 62 tahun

    Batubara19,3 milyar ton -> produksi 340 juta

    ton/tahun ->sisa 120 tahun

    n sbumi29 Gigawatt, 40 dari potensi dunia;tersebar di 276 lokasi --dimanfaatkan 4 (1226MW)-->terbarukaninsyaallah sampai kiamat)*) Rudi Rubiandini (2010) ; Widjajono Partowidagdo(2011) ; Abadi Purnomo (2012)

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    10/34

    10

    Number of Volcanoes : 150

    Potential : 40%of the World potential

    Promising fields : 256 fields, Potential : more than 29,000 MW

    Current Installed Capacity : 1,283.5 MW

    JICA/WestJECICA/WestJEC

    EXPLOITABLE RESOURCE POTENTIAL 50 fields)XPLOITABLE RESOURCE POTENTIAL 50 fields)

    y = 185.08x - 417.83

    R2= 0.9705

    0

    5,000

    10,000

    15,000

    20,000

    25,000

    30,000

    0 20 40 60 80 100 120 140 160

    No. of Volcanoes

    Geo

    thermalpotential(MW

    Indonesia

    USA

    Japan

    Philippines

    Mexico

    Iceland

    New ZealandItaly

    INDONESIA GEOTHERMAL ENERGY POTENTIAL

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    11/34

    STATUS OF GEOTHERMAL DEVELOPMENT

    Indonesia will need approximately 200400 manpower

    per yearREF. NENNY SITB, OCT 2009

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    12/34

    SEBARAN POTENSI PANAS BUMI INDONESIA

    285 Lokasi / 29, 215 MWe

    1 Sumatera 86 13.4702 Jawa 71 9.7173 Bali 5 2964 Nusa Tenggara 22 1.4715 Kalimantan 12 1456 Sulawesi 56 2.9397 Maluku 30 1.051

    8 Papua 3 75

    285

    No. Pulau Jumlah

    Lokasi

    29.215

    Potensi

    (MW)

    Total

    Note:

    SurveyPendahuluan

    SurveyDetail

    Sumber: BadanGeologi KESDM (2010)

    SiapDikembangkan

    Terpasang

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    13/34

    GEOTHERMAL ENERGY POTENTIAL

    Island

    Resources Reserves

    Speculative

    (MWe)

    Hyphotetical

    (MWe)

    Possible

    (MWe)

    Probable

    (MWe)

    Proven

    (MWe)

    Sumatera 4059 2543 6524 15 380

    Jawa 1710 1826 3708 658 1815

    Bali 70 - 226 - -

    Nusa Tenggara 340 359 757 - 15

    Kalimantan 145 - - - -

    Sulawesi 1287 139 1285 150 78

    Maluku 545 97 409 - -

    Papua 75 - - - -

    Total Lo cat ion:285

    8231 4964 12909 823 2288

    13.195 GW 16.020 GW

    29.215 GW

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    14/34

    NO NON FOSSIL ENERGYRESOURCES

    (SD)

    INSTALLED

    CAPACITY (KT)

    RATIO KT/SD(%)

    1 2 3 4 5 = 4/3

    1 Hydro 75,670 MW 5,705.29 MW 7.54

    2 Geothermal 29,215 MW 1, 283.5 MW 4.36

    3 Mini/Micro Hydro 1,013.5 MW 462.0 MW 46.0

    4 Biomass 49,810 MW 1,618.40 MW 3.25

    5 Solar Energy 4.80 kWh/m2/day 13.5 MW -

    6 Wind Energy 3 6 m/s 1.87 MW -

    7 Uranium3.000 MW

    (e.q. 24,112 ton) for 11 years*)

    *) only in Kalan West Kalimantan

    NO FOSSIL ENERGYRESOURCES

    (SD)

    RESERVES

    (CAD)

    RATIOSD/CAD

    (%)

    PRODUCTION

    (PROD)

    RASIOCAD/PROD

    (YEAR)*)

    1 2 3 4 5 = 4/3 6 7 = 4/6

    1 Oil (billion barrel) 56.6 7.99 **) 14 0.346 23

    2 Gas (TSCF) 334.5 159.64 51 2.9 55

    3 Coal (billion ton) 104.8 20.98 18 0.254 83

    4 Coal Bed Methane/CBM (TSCF) 453 - - - -

    *) with assumption there is no new discovery

    **) Cepu Block is included14

    ENERGYPOTENTI L

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    15/34

    Bit & Pieces

    Jenis Bahan Jumlah Emisi Satuan

    Bakar CO2

    BensinSolar

    Minyak tanah

    Kg/lSumber : DEFRA (2005) dan TheNational Energy Foundation (2005) dalam (Dahlan, 2007)

    Kg/l

    Kg/lKg/l2,31

    2,68

    2,52

    1,51LPG

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    16/34

    No. WKP,Lokasi PLTP

    Kapasitas

    Terpasang

    (MW)

    1 Sibayak Sinabung, SUMUT Sibayak / PGE 12

    2 Cibeureum Parabakti, JABAR Salak / Chevron 377

    3 Pangalengan, JABAR WayangWindu / Star Energy 227

    4 Kamojang Darajat, JABAR Kamojang / PGE 200

    5 Kamojang Darajat, JABAR Darajat / Chevron 270

    6 DataranTinggiDieng, JATENG Dieng / Geo Dipa 60

    7 Lahendong Tompaso, SULUT Lahendong / PGE 80

    8 UluBelu - Lampung Ulu Belu-1 / PGE 55

    9 Mataloko Mataloko / PLN 2,5

    Total 1.283,516

    KAPASITAS PLTP TERPASANG

    Agustus2012

    I (WKP) *)

    54 Wil h K j P B i (WKP) 2012

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    17/34

    I (WKP) *)

    NAD 2 WKP

    Jaboi: 70 MW

    Seulawah Agam: 130 MW

    SUMUT5 WKP

    Sibayak Sinabung: 130 MW

    SibualBuali: 750 MW

    Sipaholon Ria-ria: 75 MW

    Sorik Marapi: 200 MW

    Simbolon Samosir: 155 MW

    JAMBI 1 WKP

    Sungai Penuh: 70 MW

    SUMSEL 3 WKP

    Lumut Balai: 250 MW

    Rantau Dedap: 106 MW Danau Ranau: 210 MW

    BANTEN 2WKP

    Kaldera Danau Banten: 115 MW

    G. Endut: 80 MW

    SUMBAR 4 WKP

    Bukit Kili: 83 MW

    Gn Talang: 35 MW

    Liki Pinangawan: 400 MW

    Bonjol: 200 MW

    BENGKULU1 WKP

    Tmbg Sawah-Hululais: 873 MW

    LAMPUNG 5 WKP

    Gn.Rajabasa: 91 MW

    Suoh Sekincau: 230 MW

    Waypanas Ulubelu: 556 MW

    Danau Ranau: 210 MW

    Way Ratai: 105 MW

    JABAR 10 WKP

    Ciater - Tgkban Perahu: 60 MW

    CibeureumParabakti: 485 MW

    Cibuni: 140 MW

    Cisolok Cisukarame: 45 MW

    Gn. Tampomas: 50 MW

    Gn. Tgkuban Perahu: 100 MW

    Kamojang-Darajat: 1465 MW

    Karaha Cakrabuana: 725 MW

    Pangalengan: 1106 MW

    G. Ciremai: 150 MW

    JATENG 5WKP

    Baturaden: 175 MW

    Dataran Tinggi Dieng: 780 MW

    Guci: 79 MW

    Gn. Ungaran: 100 MW

    Candi Umbul Telomoyo: 72 MW

    BALI1 WKP

    Tabanan: 276 MW

    NTB1 WKP

    Hu'u Daha: 65 MWNTT 4 WKP

    Atadei: 40 MW

    Sokoria: 30 MW

    Ulumbu: 199 MW

    Mataloko: 63 MW

    MALUKU1 WKP

    Tulehu: 100 MW

    MALUT2 WKP

    Jailolo: 75 MW

    Songa Wayaua: 140 MW

    SULUT2 WKP

    Kotamobagu: 410 MW

    Lahendong-Tompaso: 358 MW

    GORONTALO1 WKP

    Suwawa: 110 MW

    SULTENG 2WKP

    Marana: 35 MW

    Bora Pulu: 123 MW

    JATIM3 WKP

    BlawanIjen: 270 MW

    Gn. Iyang Argopuro: 295 MW

    Telaga Ngebel: 120 MW

    54 Wilayah Kerja Panas Bumi (WKP) 2012

    19 EXISTING WKP + 35 NEW WKP

    Th Ph f G th l D l t

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    18/34

    The Phases of Geothermal Development

    Period 36 mthsLocate and Assess Prospect Desktop data study Regional reconnaissance Geology & geochemistry resource studies Historical drilling data Infrastructure availability

    Lease & Permit Issues Land acquisition Land use laws Water rights & availability Environmental review

    Prepare Bid and Business Model Economic modeling Resource concept modeling Project concept modeling Market analysis Grid availability

    Period 12 yearsRegional Exploration Geochemical Geophysical

    Prospect Exploration Temperature core hole drilling Resource measurement Preliminary modeling

    Permitting

    Environment permits Exploration permits

    Geothermal Resource Permit

    Preliminary Drilling Road & pad construction Rig procurement Target identification Exploration drilling Delineation drilling

    Re-evaluate Business Model Site, scale & technology Resource update Generation update Feasibility Study

    Period 34 yearsProduction Drilling Construction of Roads & Pads Design characteristics Geological structure Drilling targets Engineering requirements Procurement of materials Obtain suitable rig & crew Equity Funding

    Well testing Reservoir management

    Permits Drilling permit Power Purchase Agreement Environmental Permit Water permits Building permits

    Financing Bankable Reservoir Report EPC Contract Viable financial model Lenders engineer Third Party Environmental Review

    Construction EPC Contract

    Period 3040 yearsOperate Facilities Employ & train staff Spare parts Routine maintenance

    Manage Resource Resource modelling Makeup wells Well Workover Reservoir modeling

    Ongoing Development Phases Repeat Exploration &

    Development Phases

    Identification &

    Bidding

    Exploration Development Operation

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    19/34

    GEOTHERM LPOWERPL NTPROJECTSINCLUDEDINCR SHPROGR MPH SEII

    NO.GEOTHERMAL POWER

    PLANT PROJECTSTATUS PROVINCE

    ESTIMATION OF

    CAPACITY (MW)

    INSTALLED

    CAPACITY

    2014 (MW)

    REQUIRED

    FINANCING

    2014 (US$

    MILLION)1 Sungai Penuh Existing WKP Jambi 2x55 110 330

    2 Hululais Existing WKP Bengkulu 2x55 110 330

    3 Kotamobagu 1 and 2 Existing WKP North Sulawesi 2x20 40 120

    4 Kotamobagu 3 and 4 Existing WKP North Sulawesi 2x20 40 120

    5 Sembalun Open Area West Nusa Tenggara 2x10 20 60

    6 Tulehu Existing WKP Maluku 2x10 20 60

    7 Tangkuban Perahu I New WKP West Java 2x55 110 330

    8 Kamojang 5 and 6 Existing WKP West Java 1 x30 1 x60 90 270

    9 Ijen New WKP East Java 2x55 110 33010 Iyang Argopuro Existing WKP East Java 1 x55 55 165

    11 Ngebel New WKP East Java 3x55 165 495

    12 Gunung Endut New WKP Banten 1 x55 55 165

    13 Rawa Dano New WKP Banten 1 x 110 110 330

    14 Cibuni Existing WKP West Java 1 x 10 10 30

    15 Cisolok-Cisukarame New WKP West Java 1 x50 50 150

    16 Karaha Bodas Existing WKP West Java 1 x30 2x55 140 420

    17 Patuha Existing WKP West Java 3x60 180 540

    18 Tampomas New WKP West Java 1 x45 45 135

    19 Tangkuban Perahu II Existing WKP West Java 2x30 60 180

    20 Wayang Windu Unit 3 and 4 Existing WKP West Java 2x 110 220 660

    21 Gunung Ciremai New WKP West Java 2 x 55 110 330

    22 Baturaden New WKP Central Java 2x 110 220 660

    23 Dieng Existing WKP Central Java 1 x55 1 x60 115 345

    24 Guci New WKP Central Java 1 x55 55 165

    25 Ungaran New WKP Central Java 1 x55 55 165

    26 Seulawah Agam New WKP Aceh 1X55 55 165

    NO.GEOTHERMAL POWER

    PLANT PROJECTSTATUS PROVINCE

    ESTIMATION OF

    CAPACITY (MW)

    INSTALLED

    CAPACITY

    2014 (MW)

    REQUIRED

    FINANCING

    2014 (US$

    MILLION)27 Jaboi New WKP Aceh 2x5 10 30

    28 Sarulla 1 Existing WKP North Sumatera 3x 110 330 990

    29 Sarulla 2 Existing WKP North Sumatera 2x55 110 330

    30 Umbul Telumoyo New WKP Central Java 1 x55 55 165

    31 Simbolon Samosir Open Area North Sumatera 2x55 110 330

    32 Sipoholon Ria-Ria New WKP North Sumatera 1 x55 55 165

    33 Sorik Marapi New WKP North Sumatera 240 (Total) 240 720

    34 Muaralaboh New WKP West Sumatera 2x 110 220 660

    35 Bonjol New WKP West Sumatera 3x55 165 49536 Lumut Balai Existing WKP South Sumatera 4x55 220 660

    37 Rantau Dadap New WKP South Sumatera 2x110 220 660

    38 Rajabasa New WKP Lampung 2x110 220 660

    39 Ulubelu 3 and 4 Existing WKP Lampung 2x55 110 330

    40 Suoh Sekincau New WKP Lampung 4x55 220 660

    41 Wai Ratai Open Area Lampung 1 x55 55 165

    42 Danau Ranau New WKP Lampung 2x55 110 330

    43 Lahendong 5 dan 6 Existing WKP North Sulawesi 2x20 40 120

    44 Bora Open Area Central Sulawesi 1 x5 5 15

    45 Marana/Masaingi New WKP Central Sulawesi 2x10 20 60

    46 Hu'u New WKP West Nusa Tenggara 2x10 20 60

    47 Atadei New WKP East Nusa Tenggara 2 x2,5 5 15

    48 Sokoria New WKP East Nusa Tenggara 3x5 15 45

    49 Mataloko New WKP East Nusa Tenggara 1 x5 5 15

    50 Jailolo New WKP North Maluku 2x5 10 30

    51 Songa Wayaua New WKP North Maluku 1 x5 5 15

    4.925 14.775TOTAL RENCANA KAPASITAS TERPASANG

    (BASEDONMEMR REGULATIONNO. 01/2012)

    Note : Cost to develop 1 MW = US$ 3 Million

    IVESTMENT OPPORTUNITIES

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    20/34

    IVESTMENT OPPORTUNITIES

    - 51 (WKP) were issued for development with a total of 4,925 MW as partof10,000 MW Crash Program Stage II, will require more than US$ 14 Billionfor the investment.

    - International Supports are needed if we want to reach the vision 25/25 or12,000 MW Geothermal Power Plant

    - Foreign ownership in Geothermal Business is allowed up to 95 %;

    - Other business opportunities in geothermal sector:

    Geothermal direct use; Low temperature geothermal potential;

    Small scale power plant;

    CER under CDM Scheme;

    Services company to support the core business of geothermal.

    - In General, all 285 Geothermal locations in Indonesia are open to develop.

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    21/34

    Geothermal Road - map

    (GSDM, 2010, modif okt 2010)

    1000 Mwefor

    30 years465 JutaBarrel oil

    Current Condition

    2006

    852 MW

    (Production)

    2008 2012 2016 2020

    2000 MW 3442 MW 5.171 MW 7.788 MW 12.332 MW

    (Target)

    1148 MW

    Existing WKP

    1442 MW

    Existing WKP

    3977 MW

    Existing WKP +

    New WKP

    2617 MW

    New WKP

    4544 MW

    New WKP

    2025

    1.194 MW

    2014

    5.795 MW

    Plus Crash ProgramScenario Phase II

    5.171 MW

    PERMEN ESDMNo. 15/2010

    4600 MW *9500 MW *

    *) Road Map 2007

    NATIONAL GEOTHERMAL DEVELOPMENT ROAD MAP

    GEOTHERMAL ELECTRICITY THE WORLD

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    22/34

    GEOTHERMAL ELECTRICITYTHE WORLD

    Country 2012 (MWe)

    USA 3086

    Philippines 1994

    Indonesia 1283

    Mexico 959

    Italy 790

    New Zealand 740

    Japan 535

    Iceland 202

    Costa Rica 163

    El Salvador 151

    Kenya 127

    Russia (Kamchatka) 79

    Nicaragua 77

    Guatemala 33

    China 28

    Turkey 20.4

    Others 551

    Total 10,819

    GEOTHERMAL ELECTRICITY THE WORLD C t

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    23/34

    GEOTHERMAL ELECTRICITYTHE WORLD Cont..

    While this 10.8GWe might seem a lot of energy, to put itinto perspective, the electricity generated by Wind Energy

    reached almost 160GWe by the end of 2009

    Also, the 10.8GWe of Geothermal Energy has beendeveloped over a period of 50 years.

    However, Geothermal Electricity now has some moreaggressive growth targets.

    But one of the reasons for this slow early development isthat geothermal, in many respects, is a much morespecialised and challenging technology than wind orother renewable energy.

    CAPACITY BUILDING CHALLENGES

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    24/34

    CAPACITY BUILDING CHALLENGES

    With all of this geothermal development

    suddenly being instituted, what are theconsequences?

    One certain consequence is the lack of

    trained and qualified people to implementsuch plans

    Lets look at the typical life cycle of a

    geothermal field and see the implicationsfor human resource development.

    Th D l t T il

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    25/34

    ConceptDefinition

    FieldInvestigation

    FeasibilityStudy

    DevelopmentPlanning

    InitialConstruction

    Operation

    Maintenance

    Expansion

    Long Term Sustainable Geothermal Development

    PlannersGeologists

    Geochemists

    GeophysicistsReservoir engineers

    Mech. & Elect. EngineersDrilling Engineers

    EconomistsEnvironmentalists

    Accountants

    Financial AnalystsFunding SpecialistsCommunity Relations Specialists

    The Development Trail

    Some Specialised Technologies in Geothermal Development

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    26/34

    Geology & Geochemistry

    Surface Mapping

    Geophysics (MT-TDEM)

    Gravity and Micro-Gravity Surveys

    Core and/or Slim Hole Drilling

    Injection Testing

    Well Targeting

    Initial Production Drilling

    Geological Modeling

    Micro-earthquake Study

    Full Development Production Drilling

    Reservoir Modeling

    Some Specialised Technologies in Geothermal Development

    CAPACITY BUILDING OPPORTUNITIES

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    27/34

    In the past Geothermal Development has been start-stop

    which has resulted in there being no opportunity forstructured career development.

    Now the world-wide interest in renewable energy has

    changed the outlook for the Geothermal Industry

    Indonesia could and should be the home of geothermalexploitation and education.

    Over the next 10 years we will see the development of very

    many companies looking for qualified staff in all stages of

    development.

    Excellent opportunities for worldwide careers, since

    experience is very transportable.

    CAPACITY BUILDING OPPORTUNITIES

    CAPACITY BUILDING CHALLENGES 1

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    28/34

    As an indication, a non-rigorous analysis of the development

    of a typical 50MWe geothermal power plant might involve

    something like the following staffing

    Geologists; Geochemists; Geophysicistssay 10

    Electrical, Mechanical, Civil Engineerssay 6

    Procurement, logistics

    say 4 Specialist consultantssay 8

    Financial experts - say 3

    Plannerat least 1

    Environment Engineer

    at least 1 Community Relationssay 2

    Drilling Specialists/Consultantssay 2

    Hence a total of about at least 37 specialized staff

    CAPACITY BUILDING CHALLENGES - 1

    CAPACITY BUILDING CHALLENGES 2

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    29/34

    The obvious conclusion from the last slide is that to achieve

    the Governments goal by 2014/2015we might need morethan 80 times this number of geothermal specialist staff

    some 37004000NOW!

    For reference, what I mean by specialized staff are people

    working in specialized disciplines of geothermal engineering

    for a minimum of 5 years.

    To aggravate this, Indonesia is not alone in thinking to

    develop geothermal resources. Australia is now talking of

    development tens of GWs of electricity from Hot Fractured

    Rock and Deep Sedimentary Aquifer projects. They arealready stealing Indonesian and Philippine engineers. USA

    is undertaking similar development (>7GWe in the

    development pipeline), as are Chile, Nicaragua, Mexico,

    Peru. Kenya .

    CAPACITY BUILDING CHALLENGES - 2

    SOLUTION

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    30/34

    Private industry should increase cooperation withUniversities to provide training facilities and opportunitiesfor work experience etc.long term strong links on a formalbasis.

    Need to develop a more formal program of Internships withprivate companies

    Universities need more Government (or World Bank, ADBetc) and private sector funding to provide specialized coursesand to expand institutional development.

    Universities need to better understand industrysrequirements.

    Universities and international agencies need to coordinatetheir activities to avoid negative competition

    SOLUTION

    SOLUTION

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    31/34

    Use industry-employed specialist staff, both

    Indonesian and foreign, to assist with vocational

    training at Universitiesformalize this to ensure

    that consistent program can be offered.

    Government should require that all operating

    companies provide some level of contribution tothe development of the Industry e.g. Internships,

    Field training of University students, guest

    lecturing, financial contribution (?) etc.

    Provide improved advertising of the potential

    career paths available to ensure that budding

    students are aware of the geothermal option.

    SOLUTION

    CONCLUSION

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    32/34

    Every opportunity presents a challenge, and

    Indonesia has many opportunities andtherefore many challenges

    Improved long term cooperation between

    Universities and Industry Long term careers are available in a clean,

    rewarding environment, with significant long

    term upside potential

    CONCLUSION

    ANNUAL CONFERENCE & EXHIBITION API

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    33/34

    ANNUAL CONFERENCE & EXHIBITION API

    PERTEMUAN ILMIAH TAHUNAN (PIT) ke XII

    ASOSIASI PANAS BUMI INDONESIA0608 November 2012

    GRAND ROYAL PANGHEGAR HOTEL

    BANDUNGJAWA BARAT

    CONFERENCE

    SEMINAR

    TRAININGPANEL DISCUSSION

  • 7/22/2019 Asosiasi Panas Bumi Indonesia

    34/34

    Thanks

    Sekretariat:Ruang Geothermal Lantai 2 Area Kolam Renang

    PERTAMINA SIMPRUG

    Jl. SInabung Terusan II Simprug Jakarta Selatan.Telp:

    021-36844313

    Email: api inaga@yahoo co id Web: www inaga org