LATIHAN 1

Kegiatan Durasi (D) Predecessor Successor

A 10 - B

B 2 A C

C 10 B,E -

D 5 - F,E

E 9 D C

F 9 D I

G 4 - H

H 12 G I

I 7 H,F -

Berdasarkan tabel tersebut, buatlah suatu diagram CPM dan tentukanlah nilai ES,EF, LS,

LF, Total Float, Free Float untuk masing-masing kegiatan.

Buat pula Barchart berdasarakan Early Event dan Late Event

Jawaban:

Tabel Perhitungan CPM

KegiatanDurasi (D) Early Event Late Event Float

Nama i - j ES EF LS LF TF FFA 1 -- 2 10 0 10 2 12 2 0B 2 -- 5 2 10 12 12 14 2 2C 5 -- 7 10 14 24 14 24 0 0D 1 -- 3 5 0 5 0 5 0 0E 3 -- 5 9 5 14 5 14 0 0F 3 -- 6 9 5 14 8 17 3 2G 1 -- 4 4 0 4 1 5 1 0H 4 -- 6 12 4 16 5 17 1 0I 6 -- 7 7 16 23 17 24 1 1

Pada diagram CPM, terdapat jalur yang berwarna merah. Jalur yang berwarna merah

merupakan jalur kritis. Jalur kritis adalah jalur yang memiliki nilai TF = 0, yang berarti kegiatan

yang dilakukan pada jalur tersebut tidak boleh terlambat karena jika dilakukan terlambat,

proyek keseluruhan juga akan terlambat.

Diagram CPM

Barchart berdasarkan Early Event dan Late Event

Kegiatan Durasi 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

A 10

B 2

C 10

D 5

E 9

F 9

G 4

H 12

I 7

Early Event 3 3 3 3 3 4 4 4 4 4 4 4 3 3 2 2 2 2 2 2 2 2 2 1Akumulasi 3 6 9 12 15 19 23 27 31 35 39 43 46 49 51 53 55 57 59 61 63 65 67 68Late Event 1 2 3 3 3 3 3 3 4 4 4 4 4 4 3 3 3 2 2 2 2 2 2 2Akumulasi 1 3 6 9 12 15 18 21 25 29 33 37 41 45 48 51 54 56 58 60 62 64 66 68

-12

-2

8

18

28

38

48

58

68

Early Event

Late Event

LATIHAN 2

No Nama Kegiatan Durasi (D) Konstrain

1 Project Start 0 -

10 A 3 FS (1-10) = 0

20 B 4 FS (1-20) = 0

30 C 2 FS (10-30) = 1

40 D 2 FS (20-40) = 0

FF (30-40) = 3

50 E 4 FS (20-50) = 0

60 F 6 SS (50-60) = 2

70 G 3 FS (60-70) = 0

80 H 6 FS (40-80) = 0

FS (50-80) = 0

SF (70-80) = 1

90 I 2 FS (80-90) = 0

100 Project Complete 0 FS (90-100) = 0

FS (70-100) = 0

Buatlah diagram PDM dan hitunglah ES, EF, LS, dan LF.

Dan buat juga barchart untuk early dan late eventnya.

Jawaban:

Tabel Perhitungan PDM

No Nama Kegiatan Durasi (D) Konstrain

Early Event Late EventES EF LS LF

1 Project Start 0 - 0 0 0 010 A 3 FS (1-10) = 0 0 3 0 320 B 4 FS (1-20) = 0 0 4 1 530 C 2 FS (10-30) = 1 4 6 4 6

40 D 2FS (20-40) = 0

7 9 7 9FF (30-40) = 3

50 E 4 FS (20-50) = 0 4 8 5 960 F 6 SS (50-60) = 2 6 12 8 1470 G 3 FS (60-70) = 0 12 15 14 17

80 H 6FS (40-80) = 0

9 15 9 15FS (50-80) = 0SF (70-80) = 1

90 I 2 FS (80-90) = 0 15 17 15 17

100 Project Finish 0FS (90-100) = 0

17 17 17 17FS (70-100) = 0

Diagram PDM

Barchart berdasarkan Early Event dan Late Event

Kegiatan Durasi 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Project Start 0

A 3

B 4

C 2

D 2

E 4

F 6

G 3

H 6

I 2

Project Finish 0

Early Event 2 2 2 1 2 2 2 3 2 2 2 2 2 2 2 1 1Akumulasi 2 4 6 7 9 11 13 16 18 20 22 24 26 28 30 31 32Late Event 1 2 2 1 2 2 1 2 3 2 2 2 2 2 2 2 2Akumulasi 1 3 5 6 8 10 11 13 16 18 20 22 24 26 28 30 32

0

4

8

12

16

20

24

28

32

Early EventLate Event