Page 1: 8 Penyajian Rab

PENYAJIAN RAB

S0802-Rencana Anggaran Biaya

Pertemuan 8Ir. Dwi Dinariana,MT

Page 2: 8 Penyajian Rab

RINCIAN PERHITUNGAN RAB“Proyek Rumah Tinggal 1 Lantai”

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

I Pekerjaan Persiapan1 Pembersihan lahan 200.00 m2 915.00Rp 183,000.00Rp 2 Pengukuran dan pemasangan bouwplank 54.00 m' 40,710.00Rp 2,198,340.00Rp

Jumlah 2,381,340.00Rp II Pekerjaan Tanah1 Pek. Galian tanah pondasi 58.60 m3 15,950.00Rp 934,670.00Rp 2 Pek. Urugan tanah kembali 25.10 m3 5,082.00Rp 127,558.20Rp 3 Pek. Urugan pasir bawah pondasi 4.20 m3 96,920.00Rp 407,064.00Rp 4 Pek. Urugan pasir bawah lantai 5.96 m3 96,920.00Rp 577,643.20Rp

Jumlah 2,046,935.40Rp III Pekerjaan Pondasi dan Pasangan 1 Pek. Pondasi batu kali 1:5 29.34 m3 311,300.00Rp 9,133,542.00Rp 2 Pek. Pasangan batu kosong m3 169,164.00Rp -Rp 3 Pek. Pasangan bata 1:5 269.57 m2 46,495.60Rp 12,533,818.89Rp 4 Pek. Pasangan bata 1:2 37.72 m2 51,936.50Rp 1,959,044.78Rp 5 Pek. Plesteran 1:5 539.14 m2 14,594.40Rp 7,868,424.82Rp 6 Pek. Plesteran 1:2 58.48 m2 16,858.40Rp 985,879.23Rp

Jumlah 32,480,709.72Rp IV Pekerjaan Beton1 Pek. Sloof 15/20 2.95 m3 1,204,327.50Rp 3,552,766.13Rp 2 Pek. Ringbalk 15/15 3.29 m3 1,204,327.50Rp 3,962,237.48Rp 3 Pek. Kolom praktis 15/15 2.21 m3 1,204,327.50Rp 2,661,563.78Rp 4 Pek Lantai Kerja 5.95 m3 -Rp

Jumlah 10,176,567.38Rp V Pekerjaan Kusen Pintu dan Jendela 1 Pek. Kusen Pintu & Jend Kmpr Samarinda 0.85 m3 4,314,600.00Rp 3,667,410.00Rp 2 Pek. Daun Pintu panel Kmpr Samarinda 11.60 m2 230,350.00Rp 2,672,060.00Rp 3 Pek. Daun Jendela kaca Kmpr Samarinda 8.16 m2 193,880.00Rp 1,582,060.80Rp 4 Pek. Kaca 5.55 m2 52,379.00Rp 290,703.45Rp

Jumlah 8,212,234.25Rp VI Pekerjaan Lantai dan Dinding Keramik 1 Pek Keramik lantai 30/30 113.00 m2 49,990.00Rp 5,648,870.00Rp 2 Pek Keramik lantai 20/20 6.00 m2 58,240.00Rp 349,440.00Rp 3 Pek Keramik Dinding 20/20 19.00 m2 58,240.00Rp 1,106,560.00Rp

Jumlah 7,104,870.00Rp VII Pekerjaan Plafond1 Pek Rangka Plafond 131.00 m2 47,916.50Rp 6,277,061.50Rp 2 Pek Plafond Triplek 4mm 131.00 m2 19,595.50Rp 2,567,010.50Rp 3 Pek List Plafond 223.00 m' 7,250.00Rp 1,616,750.00Rp

Jumlah 10,460,822.00Rp

DAFTAR RINCIAN RENCANA ANGGARAN BIAYA

Page 3: 8 Penyajian Rab

RINCIAN PERHITUNGAN RAB “Proyek Rumah Tinggal 1 Lantai”

VIII Pekerjaan Penutup Atap & Kuda21 Pek Kuda2 Kayu Borneo 1.40 m3 2,307,700.00Rp 3,230,780.00Rp 2 Pek Penutup Atap genteng 220.00 m2 26,722.00Rp 5,878,840.00Rp 3 Pek Gording 1.00 m3 2,307,700.00Rp 2,307,700.00Rp 4 Pek Rangka Atap (Kaso&reng) 220.00 m2 49,435.00Rp 10,875,700.00Rp 5 Pek Nok 27.00 m' 53,045.00Rp 1,432,215.00Rp

Jumlah 14,615,615.00Rp IX Pekerjaan Kunci dan Penggantung1 Pek Kunci Utama 1.00 bh 256,500.00Rp 256,500.00Rp 2 Pek Kunci Ex Yalle 8.00 bh 96,250.00Rp 770,000.00Rp 3 Pek Kunci Alpha 2.00 bh 71,250.00Rp 142,500.00Rp 4 Pek Engsel Pintu 45.00 bh 11,775.00Rp 529,875.00Rp 5 Pek Engsel Jendela 22.00 bh 7,850.00Rp 172,700.00Rp 6 Pek Hak Angin 11.00 bh 13,700.00Rp 150,700.00Rp 7 Pek Gerendel 11.00 bh 16,000.00Rp 176,000.00Rp

Jumlah 499,400.00Rp X Pekerjaan Sanitasi1 Pek Bak Mandi Fiber 2.00 bh 177,335.00Rp 354,670.00Rp 2 Pek Kloset 2.00 bh 142,720.00Rp 285,440.00Rp 3 Pek Kran air 6.00 bh 50,000.00Rp 300,000.00Rp 4 Pek Kran Bebek 1.00 bh 30,000.00Rp 30,000.00Rp 5 Pek Floordrain 3.00 bh 25,000.00Rp 75,000.00Rp 6 Pek Kitchenzink 1.00 bh 225,000.00Rp 225,000.00Rp 7 Pek Pipa 78.50 m' 21,000.00Rp 1,648,500.00Rp

Jumlah 1,948,500.00Rp XI Pekerjaan Listrik1 Titik Lampu 21.00 ttk 105,000.00Rp 2,205,000.00Rp 2 Stop Kontak 10.00 bh 105,000.00Rp 1,050,000.00Rp 3 Lampu Pijar 16.00 bh 55,000.00Rp 880,000.00Rp 4 Lampu Taman 5.00 bh 175,000.00Rp 875,000.00Rp 5 Saklar Tunggal 19.00 bh 20,000.00Rp 380,000.00Rp 6 Saklar Double 1.00 bh 30,000.00Rp 30,000.00Rp

Jumlah 1,285,000.00Rp XII Pekerjaan Pengecatan

Pek Cat Tembok 539.14 m2 13,376.00Rp 7,211,536.64Rp Pek Cat Plafond 131.00 m2 15,094.00Rp 1,977,314.00Rp Pek Cat Kayu 95.44 m2 24,500.00Rp 2,338,280.00Rp

Jumlah 11,527,130.64Rp

Page 4: 8 Penyajian Rab

REKAPITULASI “Proyek Rumah Tinggal 1 Lantai”

NO URAIAN PEKERJAAN JUMLAH HARGAI PEKERJAAN PERSIAPAN 2,381,340.00Rp II PEKERJAAN TANAH 2,046,935.40Rp III PEKERJAAN PONDASI DAN PASANGAN 32,480,709.72Rp IV PEKERJAAN BETON 10,176,567.38Rp V PEKERJAAN KUSEN PINTU DAN JENDELA 8,212,234.25Rp VI PEKERJAAN LANTAI DAN DINDING KERAMIK 7,104,870.00Rp VII PEKERJAAN PLAFOND 10,460,822.00Rp VIII PEKERJAAN PENUTUP ATAP DAN KUDA2 14,615,615.00Rp IX PEKERJAAN KUNCI DAN PENGGANTUNG 499,400.00Rp X PEKERJAAN SANITASI 1,948,500.00Rp XI PEKERJAAN LISTRIK 1,285,000.00Rp XII PEKERJAAN PENGECATAN 11,527,130.64Rp

102,739,124.39Rp 10,273,912.44Rp

113,013,036.82Rp 5,650,651.84Rp

118,663,688.66Rp 118,663,000.00Rp

TOTALDIBULATKAN

Terbilang : Seratus delapan belas juta enam ratus enampuluh tiga rupiah

REKAPITULASI RENCANA ANGGARAN BIAYA

JUMLAHJASA/FEE 10%

SUB TOTALPAJAK PPN 5%