vol pondasi
DESCRIPTION
tugasTRANSCRIPT
Vol pondasi
Batu kali
Utuh = luas trapesium x panjang
= 0.5 x (d1 + d2) x t x p
= (0.5 x (0.3+0.8) x 0.7) x 87
=33.495 m3
½ = luas trapesium x panjang
= 0.5 x (d1 + d2) x t x p
= (0.5 x (0.225+0.475) x 0.7) x 59
= 14.455 m3
Rollag
Potongan i-i = j-j = p x l x t
= 16 x 0.25 x 0.8
= 3.2 m3
Potongan g-g = p x l x t
= 4.5 x 0.25 x 0.405
= 0.456 m3
Total vol pondasi batu kali = 33.495 + 14.455 + 3.2 +0.456
= 51.606 m3
Vol Pas bata pondasi rollag = p x t
= 20.5 x 0.1
= 2.05 m2
Vol pondasi Footplat = ((vol telapak )+ vol kolom) x jumlah kolom
= ((v1 + v2) + (p x l x t)) x 18
= (((p x l x t) + (0.5 x (d1 + d2) x t x p)) + (p x l x t)) x 18
= (((1.5 x1.5 x 0.2) + 0.5 x (1.5 + 0.3) x 0.1 x 1.5)) + (0.3 x 0.3 x 1.2)) x 18
= (0.45 + 0.135 + 0.108) x 18
= 12.474 m3
Vol astampeng pondasi batu kali
Utuh = luas trapesium x panjang
= 0.5 x (d1 + d2) x t x p
= 0.5 x (1 + 0.92) x 0.2 x 87
= 16.704 m3
½ = luas trapesium x panjang
= 0.5 x (d1 + d2) x t x p
= 0.5 x (0.575 + 0.535) x 0.2 x 59
= 6.549 m3
Rollag = luas trapesium x panjang
= 0.5 x (d1 + d2) x t x p
= 0.5 x (0.45 + 0.37) x 0.2 x 20.5
= 1.681 m3
Total vol astampeng = 16.704 + 6.549 + 1.681
= 24.934 m3
Vol sloof = p x l x t
= 146 x 0.15 x 0.2
= 4.38 m3
Vol pasir urug
Pondasi batu kali
Utuh = luas trapesium x panjang
= 0.5 x (d1 + d2) x t x p
= 0.5 x (0.88 + 0.92) x 0.1 x 87
= 7.83 m3
½ = luas trapesium x panjang
= 0.5 x (d1 + d2) x t x p
= 0.5 x (0.515 + 0.535) x 0.1 x 59
= 3.098 m3
Rollag = luas trapesium x panjang
= 0.5 x (d1 + d2) x t x p
= 0.5 x (0.33 + 0.37) x 0.1 x 20.5
= 0.716 m3
Footplate = luas trapesium x panjang x jumlah pondasi
= (0.5 x (d1 + d2) x t x p) x jumlah pondasi
= (0.5 x (1.66 + 1.62) x 0.1 x 1.66) x 18
= 4.901 m3
Total vol pasir urug (sirtu) = 7.83 + 3.098 + 0.716 + 4.901
= 16.545 m3
Vol lantai kerja pondasi footplate = (0.5 x (d1 + d2) x t x p) x jumlah pondasi
= (0.5 x (1.7 + 1.66) x 0.1 x 1.7) x 18
= 5.141 m3