RENCANA ANGGARAN BIAYA
DAFTAR HARGA SATUAN
PROGRAM : PENGEMBANGAN KINERJA PENGELOLAAN AIR MINUM DAN AIR LIMBAH
KEGIATAN : PENYEDIAAN PRASARANA DAN SARANA AIR BERSIH/AIR MINUM (PENUNJANG)
PEKERJAAN : PERENCANAAN PRASARANA DAN SARANA AIR BERSIH
LOKASI : KECAMATAN DUSUN TIMUR - KABUPATEN BARITO TIMUR
NO ANALISA SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
1 3 4 5 6 7
I PEKERJAAN PERSIAPAN / SITEWORK
1 Pek. Papan Nama Proyek LS Unit 1.00 250,000.00 250,000.00
2 Pek. Pengukuran LS Lokasi 1.00 3,380,000.00 3,380,000.00
3,630,000.00
II
A. 2.3.1.1. M3 283.20 87,167.70 24,685,892.64
A. 2.3.1.1. M3 976.05 87,167.70 85,080,033.59
LS M1 706.00 150,000.00 105,900,000.00
A.8.4.1.21 M1 1180.00 546,962.47 645,415,715.78
A.8.4.1.20.b M1 5205.60 354,466.18 1,845,209,141.40
A. 2.3.1.9. M3 94.40 64,832.40 6,120,178.56
A. 2.3.1.9. M3 325.35 64,832.40 21,093,221.34
A.8.4.5.5 M1 1180.00 1,840.94 2,172,307.31
A.8.4.5.4.b M1 5205.60 1,769.18 9,209,635.08
2,744,886,125.70
III
A.8.4.3.16.c Bh 2.00 1,326,623.62 2,653,247.25
A.8.4.3.15.d Bh 1.00 1,132,282.57 1,132,282.57
A.8.4.3.16 Bh 1.00 2,706,623.62 2,706,623.62
A.8.4.3.15.b Bh 1.00 1,534,782.57 1,534,782.57
LS Bh 1.00 1,092,500.00 1,092,500.00
A.8.4.3.1.b Bh 2.00 3,793,854.19 7,587,708.37
LS Bh 4.00 2,000,000.00 8,000,000.00
LS Bh 8.00 15,000.00 120,000.00
24,827,144.39
IV
LS Unit 1.00 51,750,000.00 51,750,000.00
LS Unit 3.00 34,500,000.00 103,500,000.00
LS Unit 4.00 2,500,000.00 10,000,000.00
165,250,000.00
V
A. 4.1.1.3. M3 52.95 1,183,509.52 62,666,829.16
62,666,829.16
3,001,260,099.24
RENCANA ANGGARAN DAN BIAYA (RAB)
JENIS PEKERJAAN
2
JUMLAH I
PEKERJAAN PENGADAAN DAN PEMASANGAN PIPA DISTRIBUSI
Galian Tanah Biasa Pipa Ø 8"
Galian Tanah Biasa Pipa Ø 6"
Pembongkaran Aspal Galian Pipa Ø 6"
Pemasangan Pipa HDPE Ø 200 mm (8")
Pemasangan Pipa HDPE Ø 160 mm (6")
Urugan Tanah Kembali Pipa Ø 8"
Urugan Tanah Kembali Pipa Ø 6"
Pengetesan Pipa HDPE Ø 200 mm (8")
Pengetesan Pipa HDPE Ø 160 mm (6")
JUMLAH II
PEKERJAAN PENGADAAN DAN PEMASANGAN AKSESORIS PIPA
JUMLAH I+II+III+IV+V
JUMLAH III
PENGADAAN DAN PEMASANGAN POMPA
Pengadaan Pompa Distribusi Centrifugal 15 KW
Pengadaan Dozing
PEKERJAAN LAINNYA
Cor Jalur Pipa Rabat Beton K-150 Tebal 25 cm
JUMLAH V
Pemasangan Pompa
JUMLAH IV
Karet Packing Ø 160 mm (6")
Mur dan Baut
Bend 90˚ HDPE Ø 200 mm (8")
Bend 90˚ HDPE Ø 160 mm (6")
Tee All Socket HDPE Ø 200 x 160 mm
Tee All Socket HDPE Ø 160 x 160 mm
Reducer HDPE Ø 160 x 110 mm
Air Valve Ø 160 mm (6")
Lampiran Hal - 2
DAFTAR HARGA SATUAN
No. Bahan / Upah Sat H.Satuan
Bahan
KAYU
Kayu Klas III M3 5,200,000.00
Kayu Dolken Btg 15,500.00
BAJA
Besi Beton U-24 Kg 18,342.50
Kawat Beton Kg 21,800.00
Rangka Atap Baja Ringan M2 155,129.00
Tiang Pipa Besi Galvanis Ø 1.5" Tinggi 260 cm M1 200,000.00
Klem / U -Clip Bh 20,000.00
Panel Pagar BRC Ukuran 240 x 240 cm Lbr 825,000.00
Pintu Swing Ganda 250 x 240 Unit 1,750,000.00
BATU, TANAH, PASIR DAN MATERIAL BETON
Batu koral/split 1/2 M3 616,100.00
Pasir beton M3 231,800.00
Pasir pasang M3 231,800.00
Pasir urug M3 66,700.00
Semen PC Kg 1,730.00
Semen warna Kg 2,870.00
Air Bersih Ltr 4.80
PAKU DAN MUR
Paku 5-10 Kg 20,300.00
Pasir beton M3 231,800.00
Paku Sekrup Bh 550.00
PENUTUP ATAP
Genteng Metal Lbr 160,000.00
Nok Metal Lbr 35,000.00
PLAFOND
Gypsum 9 mm Lbr 89,800.00
List Profil Gypsum 5 mm M1 20,000.00
Rangka Metal Hollow 40.40.2 mm M1 27,500.00
BAHAN FINISHING
Minyak Bekesting Ltr 5,500.00
Plamur Kg 12,800.00
Cat Dasar Kg 37,500.00
Cat Penutup Kg 37,500.00
DAFTAR HARGA SATUAN BAHAN DAN UPAH
BARITO TIMUR
SEMESTER I TAHUN 2016 (JANUARI - JUNI)
Lampiran Hal - 3
DAFTAR HARGA SATUAN
MATERIAL PERPIPAAN
Pipa HDPE Ø 250 mm (10") Bh 695,200.00
Pipa HDPE Ø 200 mm (8") Bh 447,200.00
Pipa HDPE Ø 160 mm (6") Bh 286,500.00
Dop HDPE Ø 250 mm (10") Bh 400,000.00
Dop HDPE Ø 200 mm (8") Bh 300,000.00
Dop HDPE Ø 160 mm (6") Bh 215,000.00
Bend 90˚ HDPE Ø 250 mm (10") Bh 1,800,000.00
Bend 90˚ HDPE Ø 200 mm (8") Bh 1,100,000.00
Bend 90˚ HDPE Ø 160 mm (6") Bh 950,000.00
Tee All Socket HDPE Ø 250 mm (10") Bh 4,200,000.00
Tee All Socket HDPE Ø 200 mm (8") Bh 2,300,000.00
Tee All Socket HDPE Ø 160 mm (6") Bh 1,300,000.00
Reducer HDPE Ø 160 - 110 mm Bh 950,000.00
Air Valve Ø 250 mm (10") Bh 5,000,000.00
Air Valve Ø 200 mm (8") Bh 4,000,000.00
Air Valve Ø 1600 mm (6") Bh 3,000,000.00
Karet Packing Ø 200 mm (8") Bh 1,200,000.00
Karet Packing Ø 160 mm (6") Bh 1,000,000.00
Mur dan Baut Bh 15,000.00
POMPA AIR
Pengadaan Pompa Distribusi Centrifugal 15 KW Unit 45,000,000.00
Pompa Dosing Unit 30,000,000.00
MATERIAL MEKANIKAL DAN ELEKTRIKAL
Kabel PLN NYY 4x16 M1 80,000.00
Tiang Listrik Besi Galvanis PLN Bh 2,000,000.00
Bensin Ltr 8,000.00
Oli Ltr 35,000.00
Upah Tenaga Kerja
Pekerja OH 95,220.00
Tukang Kayu OH 124,200.00
Tukang Batu OH 124,200.00
Tukang Besi OH 108,900.00
Tukang Cat OH 124,200.00
Tukang Gali OH 95,220.00
Kepala Tukang Kayu OH 130,680.00
Kepala Tukang Batu OH 154,980.00
Kepala Tukang Besi OH 154,980.00
Kepala Tukang Cat OH 154,980.00
Mandor OH 175,320.00
Lampiran Hal - 4
ANALISA HARGA SATUAN
A. 2.3.1.1. Penggalian 1 m3 tanah Biasa sedalam 1 m
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.750 95,220.00 71,415.00
Mandor L.04 OH 0.025 175,320.00 4,383.00
75,798.00
B BAHAN
C PERALATAN
D 75,798.00
E 11,369.70
F 87,167.70
A. 2.3.1.9. Pengurugan kembali 1 m3 galian tanah
Pengurugan kembali 1 3 galian dihitung dari1/3 kali dari koefisien pekerjaan galian
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.5 95,220.00 47,610.000
Mandor L.04 OH 0.1 175,320.00 8,766.000
56,376.00
B BAHAN
C PERALATAN
D 56,376.00
E 8,456.40
F 64,832.40
A. 2.3.1.11. Pengurugan 1 m3 dengan pasir urug
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,220.00 28,566
Mandor L.04 OH 0.010 175,320.00 1,753
30,319
B BAHAN
Pasir Urug M3 1.20 66,700 80,040.00
C PERALATAN
D 110,359.20
E 16,553.88
F 126,913.08 Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah(A+B+C)
Overhead & Profit 15% x D
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
ANALISA HARGA SATUAN PEKERJAAN
PERMEN PU NOMOR : 11 / PRT / M / 2013
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah(A+B+C)
Overhead & Profit 15% x D
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah(A+B+C)
Overhead & Profit 15% x D
Lampiran Hal - 5
ANALISA HARGA SATUAN
A. 4.1.1.1. Membuat 1 m3 Mutu K-100
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 1.650 95,220.00 157,113.00
Tukang Batu 0.275 124,200.00 34,155.00
Kepala Tukang 0.028 154,980.00 4,339.44
Mandor L.04 OH 0.083 175,320.00 14,551.56
210,159.00
B BAHAN
Semen Portland Kg 230.000 1,730.00 397,900
Pasir Pasang Kg 893.000 165.57 147,855
Batu Pecah 1-2 Kg 1,027.000 165.57 170,042
Air Liter 200.000 4.80 960
716,757
C PERALATAN
D 926,916.14
E 139,037.42
F 1,065,953.56
A. 4.1.1.3. Membuat 1 m3 Mutu K-150
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 1.65 95,220.00 157,113.00
Tukang Batu 0.28 124,200.00 34,155.00
Kepala Tukang 0.03 154,980.00 4,339.44
Mandor L.04 OH 0.08 175,320.00 14,551.56
210,159.00
B BAHAN
Semen Portland Kg 299.00 1,730.00 517,270
Pasir Pasang Kg 799.00 165.57 132,292
Batu Pecah 1-2 Kg 1,017.00 165.57 168,386
Air Liter 215.00 4.80 1,032
818,980
C PERALATAN
D 1,029,138.71
E 154,370.81
F 1,183,509.52
A. 4.1.1.28. Membuat 1 m3 Pondasi beton bertulang (200 kg besi + bekisting)
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 5.300 95,220.00 504,666.00
Tukang Batu L.02 OH 0.275 124,200.00 34,155.00
Tukang Kayu L.02 OH 1.300 124,200.00 161,460.00
Tukang Besi L.02 OH 1.050 108,900.00 114,345.00
Kepala Tukang Batu L.03 OH 0.262 154,980.00 40,604.76
Mandor L.04 OH 0.265 175,320.00 46,459.80
901,690.56
B BAHAN
Kayu Kelas III m3 0.200 5,200,000.00 1,040,000.00
Paku 5 Cm - 12 Cm kg 1.500 20,300.00 30,450.00
Minyak bekisting Liter 0.400 5,500.00 2,200.00
Besi Beton polos kg 157.500 18,342.50 2,888,943.75
Kawat Beton kg 2.250 21,800.00 49,050.00
Semen Portland 40 Kg kg 336.000 1,730.00 581,280.00
Pasir Pasang m3 0.540 165.57 89.41
Batu Pecah 1-2 m3 0.810 165.57 134.11
4,592,147.27
C PERALATAN
D 5,493,837.83
E 824,075.67
F 6,317,913.51 Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah(A+B+C)
Overhead & Profit 15% x D
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
A.4.1.1 HARGA SATUAN PEKERJAAN BETON
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah(A+B+C)
Overhead & Profit 15% x D
Jumlah(A+B+C)
Overhead & Profit 15% x D
Harga Satuan Pekerjaan (D+E)
Lampiran Hal - 6
ANALISA HARGA SATUAN
A. 4.1.1.29. Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting)
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 5.650 95,220.00 537,993.00
Tukang Batu L.02 OH 0.275 124,200.00 34,155.00
Tukang Kayu L.02 OH 1.560 124,200.00 193,752.00
Tukang Besi L.02 OH 1.400 108,900.00 152,460.00
Kepala Tukang L.03 OH 0.323 154,980.00 50,058.54
Mandor L.04 OH 0.283 175,320.00 49,615.56
1,018,034.10
B BAHAN
Kayu Kelas III m3 0.270 5,200,000.00 1,404,000.00
Paku 5 Cm - 12 Cm kg 2.000 20,300.00 40,600.00
Minyak bekisting Liter 0.600 5,500.00 3,300.00
Besi Beton polos kg 210.000 18,342.50 3,851,925.00
Kawat Beton kg 3.000 21,800.00 65,400.00
Semen Portland 40 Kg kg 336.000 1,730.00 581,280.00
Pasir Pasang m3 0.540 165.57 89.41
Batu Pecah 1-2 m3 0.810 165.57 134.11
5,946,728.52
C PERALATAN
D 6,964,762.62
E 1,044,714.39
F 8,009,477.01
A. 4.2.1.21. Pemasangan 1 m2 rangka besi hollow 1x40.40.2 mm, modul 60 x 60 cm, plafon
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.350 95,220.00 33,327.00
Tukang Kayu L.02 OH 0.350 124,200.00 43,470.00
Kepala Tukang Kayu L.03 OH 0.035 154,980.00 5,424.30
Mandor L.04 OH 0.018 175,320.00 3,155.76
85,377.06
B BAHAN
Rangka Metal Hollow 40.40.2 mm m' 4.000 27,500.00 110,000.00
Asesoris ls 100%xrangka 27,500.00 27,500.00
137,500.00
C PERALATAN
D 222,877.06
E 33,431.56
F 256,308.62
A. 4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.1 95,220.00 9,522.00
Tukang Kayu L.02 OH 0.05 124,200.00 6,210.00
Kepala Tukang L.03 OH 0.005 154,980.00 774.90
Mandor L.04 OH 0.005 175,320.00 876.60
17,383.50
B BAHAN
GypsuM Board Lembar 0.364 165,000.00 60,060.00
Paku Sekrup Kg 0.11 27,500.00 3,025.00
63,085.00
C PERALATAN
D 80,468.50
E 12,070.28
F 92,538.78 Harga Satuan Pekerjaan (D+E)
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah(A+B+C)
Overhead & Profit 15% x D
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah(A+B+C)
Overhead & Profit 15% x D
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah(A+B+C)
Overhead & Profit 15% x D
Lampiran Hal - 7
ANALISA HARGA SATUAN
A. 4.5.2.32.b. Pemasangan 1 m2 Atap Zincalume
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.2 95,220.00 19,044.00
Tukang Kayu L.02 OH 0.1 124,200.00 12,420.00
Kepala Tukang L.03 OH 0.01 154,980.00 1,549.80
Mandor L.04 OH 0.001 175,320.00 175.32
33,189.12
B BAHAN
Atap Zincalume Bh 1.02 160,000.00 163,200.00
Paku Metal Kg 0.2 27,500.00 5,500.00
168,700.00
C PERALATAN
D 201,889.12
E 30,283.37
F 232,172.49
A. 4.5.2.36. Pemasangan 1 m' nok Atap Zincalume
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.25 95,220.00 23,805.00
Tukang Kayu L.02 OH 0.15 124,200.00 18,630.00
Kepala Tukang L.03 OH 0.015 154,980.00 2,324.70
Mandor L.04 OH 0.013 175,320.00 2,279.16
47,038.86
B BAHAN
Nok Atap Zincalume Bh 1.1 35,000.00 38,500.00
Paku Metal Kg 0.05 27,500.00 1,375.00
39,875.00
C PERALATAN
D 86,913.86
E 13,037.08
F 99,950.94
A. 4.7.1.10. Pengecetan 1 m2 tembok baru (1 Lapis Plamur, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.200 95,220.00 19,044.00
Tukang Cat L.02 OH 0.063 124,200.00 7,824.60
Kepala Tukang L.03 OH 0.006 154,980.00 976.37
Mandor L.04 OH 0.003 175,320.00 525.96
28,370.93
B BAHAN
Palmur Kg 0.10 12,800.00 1,280.00
Cat Dasar Kg 0.100 37,500.00 3,750.00
Cat Penutup Kg 0.260 37,500.00 9,750.00
14,780.00
C PERALATAN
D 43,150.93
E 6,472.64
F 49,623.57
Overhead & Profit 15% x D
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah(A+B+C)
Overhead & Profit 15% x D
15% x D
Harga Satuan Pekerjaan (D+E)
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah(A+B+C)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah(A+B+C)
Overhead & Profit
Lampiran Hal - 8
ANALISA HARGA SATUAN
A.8.4.1.20.b Pemasangan 1 m pipa HDPE Ø 160 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.062 95,220.00 5,903.64
Tukang pipa L.02 OH 0.031 108,900.00 3,375.90
Mandor L.04 OH 0.006 175,320.00 1,051.92
10,331.46
B BAHAN
Pipa HDPE Ø 160 mm m 1.000 286,500.00 286,500.00
286,500.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.019 600,000.00 11,400.00
11,400.00
D 308,231.46
E 46,234.72
F 354,466.18
A.8.4.1.21 Pemasangan 1 m pipa HDPE Ø 200 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.102 95,220.00 9,712.44
Tukang pipa L.02 OH 0.051 108,900.00 5,553.90
Mandor L.04 OH 0.010 175,320.00 1,753.20
17,019.54
B BAHAN
Pipa HDPE Ø 200 mm m 1.000 447,200.00 447,200.00
447,200.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.019 600,000.00 11,400.00
11,400.00
D 475,619.54
E 71,342.93
F 546,962.47
A.8.4.1.22 Pemasangan 1 m pipa HDPE Ø 250 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.133 95,220.00 12,664.26
Tukang pipa L.02 OH 0.067 108,900.00 7,296.30
Mandor L.04 OH 0.013 175,320.00 2,279.16
B BAHAN
Pipa HDPE Ø 250 mm m 1.000 695,200.00 695,200.00
695,200.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.042 600,000.00 25,200.00
25,200.00
D 720,400.00
E 108,060.00
F 828,460.00
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah (A+B+C)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
Overhead & Profit (Contoh 15 %) 15% x D
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
15% x D
Harga Satuan Pekerjaan (D+E)
15% x D
Harga Satuan Pekerjaan (D+E)
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %)
Overhead & Profit (Contoh 15 %)
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Lampiran Hal - 9
ANALISA HARGA SATUAN
A.8.4.5.4.b Pengetesan 1 m pipa Ø 160 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.008 95,220.00 761.76
Mandor L.04 OH 0.0008 175,320.00 140.26
902.02
B BAHAN
Air test (air bersih) m3
0.018 4,800.00 86.40
Bahan bakar liter 0.060 8,000.00 480.00
Oli liter 0.002 35,000.00 70.00
636.40
C PERALATAN
D 1,538.42
E 230.76
F 1,769.18
A.8.4.5.5 Pengetesan 1 m pipa Ø 200 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.008 95,220.00 761.76
Mandor L.04 OH 0.0008 175,320.00 140.26
902.02
B BAHAN
Air test (air bersih) m3
0.031 4,800.00 148.80
Bahan bakar liter 0.060 8,000.00 480.00
Oli liter 0.002 35,000.00 70.00
698.80
C PERALATAN
D 1,600.82
E 240.12
F 1,840.94
A.8.4.5.6 Pengetesan 1 m pipa Ø 250 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.008 95,220.00 761.76
Mandor L.04 OH 0.0008 175,320.00 140.26
902.02
B BAHAN
Air test (air bersih) m3
0.049 4,800.00 235.20
Bahan bakar liter 0.060 8,000.00 480.00
Oli liter 0.002 35,000.00 70.00
785.20
C PERALATAN
D 1,687.22
E 253.08
F 1,940.30 Harga Satuan Pekerjaan (D+E)
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %) 15% x D
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %) 15% x D
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %) 15% x D
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
Lampiran Hal - 10
ANALISA HARGA SATUAN
A.8.4.3.1.b Pemasangan 1 buah Valve Ø 160 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 1.429 95,220.00 136,069.38
Tukang pipa L.02 OH 0.715 108,900.00 77,863.50
Mandor L.04 OH 0.143 175,320.00 25,070.76
239,003.64
B BAHAN
Valve Ø 160 mm bh 1.000 3,000,000.00 3,000,000.00
3,000,000.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.100 600,000.00 60,000.00
60,000.00
D 3,299,003.64
E 494,850.55
F 3,793,854.19
A.8.4.3.2 Pemasangan 1 buah Valve Ø 200 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 1.714 95,220.00 163,207.08
Tukang pipa L.02 OH 0.857 108,900.00 93,327.30
Mandor L.04 OH 0.171 175,320.00 29,979.72
286,514.10
B BAHAN
Valve Ø 200 mm bh 1.000 4,000,000.00 4,000,000.00
4,000,000.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.300 600,000.00 180,000.00
180,000.00
D 4,466,514.10
E 669,977.12
F 5,136,491.22
A.8.4.3.3 Pemasangan 1 buah Valve Ø 250 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 1.714 95,220.00 163,207.08
Tukang pipa L.02 OH 0.857 108,900.00 93,327.30
Mandor L.04 OH 0.171 175,320.00 29,979.72
286,514.10
B BAHAN
Valve Ø 250 mm bh 1.000 5,000,000.00 5,000,000.00
5,000,000.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.400 600,000.00 240,000.00
240,000.00
D 5,286,514.10
E 792,977.12
F 6,079,491.22 Harga Satuan Pekerjaan (D+E)
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %) 15% x D
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %) 15% x D
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %) 15% x D
Lampiran Hal - 11
ANALISA HARGA SATUAN
A.8.4.3.15.b Pemasangan 1 buah Tee Ø 160 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.106 95,220.00 10,093.32
Tukang pipa L.02 OH 0.053 108,900.00 5,771.70
Mandor L.04 OH 0.011 175,320.00 1,928.52
17,793.54
B BAHAN
Tee Ø 160 mm bh 1.000 1,300,000.00 1,300,000.00
1,300,000.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.028 600,000.00 16,800.00
16,800.00
D 1,334,593.54
E 200,189.03
F 1,534,782.57
A.8.4.3.15.c Pemasangan 1 buah Dop Ø 160 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.106 95,220.00 10,093.32
Tukang pipa L.02 OH 0.053 108,900.00 5,771.70
Mandor L.04 OH 0.011 175,320.00 1,928.52
17,793.54
B BAHAN
Dop Ø 160 mm bh 1.000 215,000.00 215,000.00
215,000.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.028 600,000.00 16,800.00
16,800.00
D 249,593.54
E 37,439.03
F 287,032.57
A.8.4.3.15.d Pemasangan 1 buah Bend Ø 160 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.106 95,220.00 10,093.32
Tukang pipa L.02 OH 0.053 108,900.00 5,771.70
Mandor L.04 OH 0.011 175,320.00 1,928.52
17,793.54
B BAHAN
Bend Ø 160 mm bh 1.000 950,000.00 950,000.00
950,000.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.028 600,000.00 16,800.00
16,800.00
D 984,593.54
E 147,689.03
F 1,132,282.57
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %) 15% x D
Harga Satuan Pekerjaan (D+E)
JUMLAH HARGA ALAT
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah (A+B+C)
JUMLAH TENAGA KERJA
Harga Satuan Pekerjaan (D+E)
Overhead & Profit (Contoh 15 %) 15% x D
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %) 15% x D
Lampiran Hal - 12
ANALISA HARGA SATUAN
A.8.4.3.16 Pemasangan 1 buah Tee Ø 200 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.216 95,220.00 20,567.52
Tukang pipa L.02 OH 0.108 108,900.00 11,761.20
Mandor L.04 OH 0.022 175,320.00 3,857.04
36,185.76
B BAHAN
Tee Ø 200 mm bh 1.000 2,300,000.00 2,300,000.00
2,300,000.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.029 600,000.00 17,400.00
17,400.00
D 2,353,585.76
E 353,037.86
F 2,706,623.62
A.8.4.3.16.b Pemasangan 1 buah Dop Ø 200 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.216 95,220.00 20,567.52
Tukang pipa L.02 OH 0.108 108,900.00 11,761.20
Mandor L.04 OH 0.022 175,320.00 3,857.04
36,185.76
B BAHAN
Dop Ø 200 mm bh 1.000 300,000.00 300,000.00
300,000.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.029 600,000.00 17,400.00
17,400.00
D 353,585.76
E 53,037.86
F 406,623.62
A.8.4.3.16.c Pemasangan 1 buah Bend Ø 200 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.216 95,220.00 20,567.52
Tukang pipa L.02 OH 0.108 108,900.00 11,761.20
Mandor L.04 OH 0.022 175,320.00 3,857.04
36,185.76
B BAHAN
Bend Ø 200 mm bh 1.000 1,100,000.00 1,100,000.00
1,100,000.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.029 600,000.00 17,400.00
17,400.00
D 1,153,585.76
E 173,037.86
F 1,326,623.62
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %) 15% x D
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %) 15% x D
Harga Satuan Pekerjaan (D+E)
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %) 15% x D
Lampiran Hal - 13
ANALISA HARGA SATUAN
A.8.4.3.17 Pemasangan 1 buah Tee Ø 250 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.326 95,220.00 31,041.72
Tukang pipa L.02 OH 0.163 108,900.00 17,750.70
Mandor L.04 OH 0.033 175,320.00 5,785.56
54,577.98
B BAHAN
Tee Ø 250 mm bh 1.000 4,200,000.00 4,200,000.00
4,200,000.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.039 600,000.00 23,400.00
23,400.00
D 4,277,977.98
E 641,696.70
F 4,919,674.68
A.8.4.3.17.b Pemasangan 1 buah Dop Ø 250 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.326 95,220.00 31,041.72
Tukang pipa L.02 OH 0.163 108,900.00 17,750.70
Mandor L.04 OH 0.033 175,320.00 5,785.56
54,577.98
B BAHAN
Dop Ø 250 mm bh 1.000 400,000.00 400,000.00
400,000.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.039 600,000.00 23,400.00
23,400.00
D 477,977.98
E 71,696.70
F 549,674.68
A.8.4.3.17.c Pemasangan 1 buah Bend Ø 250 mm
No Uraian Kode Satuan KoefisienHarga Satuan
(Rp.)
Jumlah Harga
(Rp.)
A TENAGA
Pekerja L.01 OH 0.326 95,220.00 31,041.72
Tukang pipa L.02 OH 0.163 108,900.00 17,750.70
Mandor L.04 OH 0.033 175,320.00 5,785.56
54,577.98
B BAHAN
Bend Ø 250 mm bh 1.000 1,800,000.00 1,800,000.00
1,800,000.00
C PERALATAN
Sewa Tripot/Tackel & handle crane 2 T hari 0.039 600,000.00 23,400.00
23,400.00
D 1,877,977.98
E 281,696.70
F 2,159,674.68 Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %) 15% x D
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Overhead & Profit (Contoh 15 %) 15% x D
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
Overhead & Profit (Contoh 15 %) 15% x D
Harga Satuan Pekerjaan (D+E)
JUMLAH TENAGA KERJA
JUMLAH HARGA BAHAN
JUMLAH HARGA ALAT
Jumlah (A+B+C)
Lampiran Hal - 14
DETAIL ENGINEERING DESIGN
Lampiran Hal - 15
DETAIL ENGINEERING DESIGN
Lampiran Hal - 16
FOTO – FOTO KONSTRUKSI
Lampiran Hal - 17
FOTO – FOTO KONSTRUKSI
Lampiran Hal - 18
FOTO – FOTO KONSTRUKSI