    TUGAS AKHIR MANAJEMEN

    PELAKSANAAN

    PEMBANGUNAN JALAN TOLMOJOKERTO KERTOSONO STA. 5+350 STA. 10+350

    DENGAN MENGGUNAKAN PERKERASAN KAKUDI KABUPATEN MOJOKERTO PROVINSI JAWA

    TIMUR

    ZULFIKARJAUHARI

    NRP. 3110040601

    PROGRAM STUDI DIPLOMA 4 TEKNIK SIPIL

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    2/36

    Fakultas Teknik Sipil dan Perencanaan

    Institut Teknologi Sepuluh Nopember

    Surabaya 2012

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    3/36

    STA 10 +350STA 5 +350

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    4/36

    BAGAN ALURMETODELOGI

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    5/36

    GI

    LANJUTANMETODELO

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    6/36

    PETA LOKASI QUARRY

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    7/36

    PETA LOKASI QUARRY

    JARAK LOKASI PROYEK DENGAN LOKASI QUARRY

    ADALAH 32, 4 KM

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    8/36

    PEKERJAAN TANAH

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    9/36

    Pekerjaan Tanah

    Pembersihan dan Pembongkaran

    Galian Konstruksi 0 - 2 m

    Pekerjaan Timbunan

    Lapisan Geotextile

    Penyiapan Badan Jalan

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    10/36

    PEMBERSIHAN & PEMBONGKARAN

    1. Pembongkaran dilakukan pada daerah milikjalan yang telah ditentukan dan atas petunjukdireksi.

    2. Harus dilakukan dengan hati-hati berkaitandengan banyaknya utilitas existing bawahtanah.

    2. Hasil pembongkaran dibuang diluar lokasipekerjaan atau lokasi yang telah ditentukanoleh direksi .

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    11/36

    PEMBERSIHAN & PEMBONGKARAN

    PEMBERSIHAN/PENGUPASAN TOP SOIL, PENGANGKUTAN DAN PERATAAN

    1. Pembersihan permukaan tanah dengan Bulldozer 2. Loading hasil streping ke Dump truck denganExcavator

    3. Galian tanah permukaan + 50 cm dengan Bulldozer 4. Loading hasil galian dengan excavator ke dump truckuntuk dibuang ke disposal area

    50 cm

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    12/36

    PEKERJAAN DRAINASE

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    13/36

    PEKERJAAN GALIAN SALURAN TEPI

    CONTOH TYPE SALURAN

    GALIAN SALURAN

    TEPI 1

    GALIAN SALURAN TEPI 2

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    14/36

    PEKERJAAN GALIAN SALURAN TEPI

    PERSIAPAN

    Rencanakan urutan penggalian, urutan pekerjaan

    U-Ditch, tempat penimbunan tanah hasil galian

    sementara sebelum diangkut keluar dari site.

    PEMBUATAN GALIAN

    Rencana Galian Pondasi

    Galian untuk Pondasi

    1. Siapkan alat-alat yang diperlukan.

    2. Menggali tanah dengan ukuran lebar sama

    dengan lebar bagian bawah dengan kedalamanyang disyaratkan.

    3. Menggali sisi-sisi miringnya, sehingga

    diperoleh sudut kemiringan yang tepat.

    4. Buang tanah sisa galian ketempat yang telah

    ditentukan.

    5. Cek posisi, lebar, kedalaman dan kerapianya,

    sesuai dengan rencana.

    Papan Bouwplank

    Bekas Galian

    Tiang Bouwplank

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    15/36

    PEKERJAAN PEMADATAN

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    16/36

    Dump truck 11 tonMaterial timbuanan

    (Sirtu)

    Bulldozer 150 HP Motor Grader 3.1 m3 Vibrator roller 12 ton Truck tanki air (6000 m3)

    Timbunan lapis 2Timbunan lapis 3

    Timbunan lapis 1

    Muka tanah asli

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    17/36

    PENYIAPAN BADAN JALAN

    1. Pekerjaan pembentukan badan jalan dan perapihan

    serta perataan menggunakan motor grader sehinggamembentuk kemiringan sesuai design

    2. - Vibrator Roller memadatkan permukaan yang telahdiratakan oleh motor grader dgn diberi airsecukupnya

    - Sekelompok pekerja akan membantu meratakanbadan jalan dengan alat bantu

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    18/36

    PEKERJAAN TIMBUNAN TANAH BIASA

    1. EXCAVATOR MEMUAT MATERIAL TIMBUNAN

    KEDALAM DUMP TRUCK DI BORROW AREA KE

    MUDIAN DIANGKUT KELOKASI PEKERJAAN

    2. TIBA DILOKASI PEKERJAAN MATERIAL DIDUMPINGDARI DUMP TRUCK KEMUDIAN DILAKUKAN PENGHAMPARAN

    3. PENGHAMPARAN TANAH TIMBUNAN MENGGUNAKAN

    MOTOR GRADER

    4. HAMPARAN MATERIAL DISIRAM AIR SEBELUM DI

    PADATKAN

    -PEMADATAN MATERIAL DILAKUKAN DENGAN MENG

    GUNAKAN ALAT VIBRATOR ROLLER

    WATER TANK TRUCK

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    19/36

    PEKERJAAN TIMBUNAN PILIHAN

    1. EXCAVATOR MEMUAT MATERIAL TIMBUNAN

    PILIHAN KEDALAM DUMP TRUCK DI BORROW

    AREA KE MUDIAN DIANGKUT KELOKASI

    PEKERJAAN

    2. TIBA DILOKASI PEKERJAAN MATERIAL DIDUMPINGDARI DUMP TRUCK KEMUDIAN DILAKUKAN PENGHAMPARAN

    3. PENGHAMPARAN TIMBUNAN PILIHAN MENGGUNAKAN

    MOTOR GRADER

    4. HAMPARAN TIMBUNAN PILIHAN DISIRAM AIR

    SEBELUM DI PADATKAN

    -PEMADATAN MATERIAL DILAKUKAN DENGAN MENG

    GUNAKAN ALAT VIBRATOR ROLLER

    WATER TANK TRUCK

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    20/36

    PEKERJAAN PERKERASAN BERBUTIR

    1. Pendatangan material timbunan dari luar denganmenggunakan Dump Truck

    2. Material di hampar dengan Motor Grader

    3. Proses pemadatan hasil peghamparan denganmenggunakan Vibrator Roller

    4. Prosess pemadatan diikuti pembasahan dengan WaterTank Truck

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    21/36

    PEKERJAAN PERKERASAN BETON

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    22/36

    Rigid PavementPERSYARATAN TEKNIS

    a. Beton Lantai Kendaraan, mutu beton K-400 (umur 28 hari) Lantai Kerja, Mutu beton harus setara dengan beton K-125 (umur 28 hari)

    b. Baja Tulangan

    Diameter > 13 mm : U-39 (ulir) Diameter < 13 mm : U-32 (polos)

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    23/36

    KONSTRUKSIPEKERJAAN PERKERASAN BETON

    FLOWCHART PEKERJAAN K - 40

    START

    MATERIAL KLAS B = 20 CMBY MOTOR GRADER/VIBRO ROLLER/TANKI AIR

    LEAN CONCRETE thick = 5 cmBY TRUCK MIXER

    CONCRETE PAVEMENT

    LEAN CONCRETE t=5 CONCRETE PAVEMENT thick = 27 cmBY TRUCK MIXER

    FINISH

    CONCRETE PAVEMENT

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    24/36

    KONSTRUKSIPEKERJAAN PERKERASAN BETON

    PELAKSANAAN PEKERJAAN SLAB K-400

    1. Pekerjaan Persiapan

    Pekerjaan persiapan yang dilakukan untuk perkerasan beton yaitupenentuan elevasi lean concrete yang akan di cor. Pemasanganbekisting pada sisi jalan untuk pengecoran lean concrete pekerjaan

    pengecoran lean concrete

    2. Pekerjaan pengecoran lean concrete

    3. Pemasangan bekisting sisi jalan yang juga berfungsi sebagai rel dariconcrete paver. Pemasangan pelastik dan kayu yang berfungsi

    sebagai crack inducer4. Pembuatan Dowel, Tie Bar dan Wire Mesh

    Pembuatan dowel, tie bar dan pemasangan wire mesh, dilakukansebelum pekerjaan pengecoran dimulai.

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    25/36

    PEKERJAAN PERKERASAN BETON KONSTRUKSI

    Mulai

    Penyiapan Alat

    Paver

    Pemasangan Rel

    Pemasangan Plastik,

    crack inducer, Dowel &

    Tie Bar

    PERSIAPAN

    Pemasangan

    Wire MeshPerkuatan

    Selesai

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    26/36

    PEKERJAAN PERKERASAN BETON

    Pengukuran/Penentuan Elevasi Lean Concrete

    Pembuatan Dowell dan Tie bar

    26

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    27/36

    26METODE PELAKSANAAN PEKERJAAN RIGID PAVEMENT

    1. Buat Patokan Lean Concrete

    10 Cm

    2. Pengecoran Lapisan Lean Concrete Papan Pijakan Pekerja

    10 Cm

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    28/36

    PEKERJAAN PERKERASAN BETON KONSTRUKSI

    Persiapan

    Membuat Alur

    Pengecoran

    Compound

    Menggelar & Meratakan

    Pembasahan Beton

    PemadatanPemotongan

    Joint

    Meratakan

    Permukaan Pengisian Joint Sealant

    Finish

    ALUR PENGECORAN CONCRETE

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    29/36

    +

    +

    +

    +

    ++

    ++

    ++

    +

    +

    +

    +

    +

    +

    +

    +

    +

    +

    +

    +

    +

    +

    +

    ALUR PENGECORAN CONCRETE

    Oleh karena lebar Jalan 7 m

    Maka lebar penghamparan

    dibuat dua kali masing masing

    Dengan lebar hampar 3.5 m

    2

    3 4 1

    3.50 m

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    30/36

    ++

    +

    3.50 m 3.50 m 3.50 m

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    31/36

    PEKERJAAN PERKERASAN BETON KONSTRUKSI

    1 2

    Pengecoran Penyebaran & Pemadatan

    3 4 5

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    32/36

    Meratakan Permukaan Pembuatan Alur Curing Compound

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    33/36

    PEKERJAAN PERKERASAN BETON KONSTRUKSI

    6 7 8

    Pembasahan Beton Pemotongan Joint Pengisian Joint Sealant

    9

    10

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    34/36

    Perlindungan dengan Tenda Hasil RIGID PAVEMENT

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    35/36

    Manajemen

    Untuk mengetahui bagaimana manajemen yangdipakai, saya menggunakan bantuan program

    MS Project untuk memfasilitasi pengaturanBiaya, Waktu, dan Mutu

    32

  • 7/30/2019 ITS Undergraduate 19573 3110040601 Presentationpdf

    36/36

    32