ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH TINGGAL DENGAN METODE FULL COSTING DAN METODE VARIABLE COSTING PADA PERUSAHAAN JASA KONSTRUKSI (STUDI PADA CV AYORENOVASI “PROYEK SUNTER” TAHUN 2019) SKRIPSI FERDINAND EKA WIJAYA 11197560262 PROGRAM STUDI STRATA 1 AKUNTANSI SEKOLAH TINGGI EKONOMI INDONESIA KAMPUS E BEKASI 2020

Upload: others

Post on 01-Oct-2021

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …

ANALISIS PERHITUNGAN HARGA POKOK

PRODUKSI RUMAH TINGGAL DENGAN METODE

FULL COSTING DAN METODE VARIABLE COSTING

PADA PERUSAHAAN JASA KONSTRUKSI

(STUDI PADA CV AYORENOVASI “PROYEK SUNTER” TAHUN 2019)

SKRIPSI

FERDINAND EKA WIJAYA

11197560262

PROGRAM STUDI STRATA – 1 AKUNTANSI

SEKOLAH TINGGI EKONOMI INDONESIA – KAMPUS E

BEKASI

2020

Page 2: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …

i

ANALISIS PERHITUNGAN HARGA POKOK

PRODUKSI RUMAH TINGGAL DENGAN METODE

FULL COSTING DAN METODE VARIABLE COSTING

PADA PERUSAHAAN JASA KONSTRUKSI

(STUDI PADA CV AYORENOVASI “PROYEK SUNTER” TAHUN 2019)

SKRIPSI

FERDINAND EKA WIJAYA

11197560262

SKRIPSI INI DIAJUKAN UNTUK MELENGKAPI SEBAGIAN

PERSYARATAN MENJADI SARJANA AKUNTANSI

PROGRAM STUDI STRATA – 1 AKUNTANSI

SEKOLAH TINGGI EKONOMI INDONESIA – KAMPUS E

BEKASI

2020

Page 3: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …
Page 4: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …
Page 5: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …
Page 6: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …
Page 7: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …
Page 8: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …
Page 9: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …

viii

Ferdinand Eka Wijaya Dosen Pembimbing :

NPM 11197560262 Bayu Pratama, SE, M.Ak.

Program Studi S-1 Akuntansi

ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH

TINGGAL DENGAN METODE FULL COSTING DAN METODE

VARIABLE COSTING PADA PERUSAHAAN JASA KONSTRUKSI ABSTRAK

Tujuan penelitian ini yaitu untuk mengetahui perhitungan harga pokok

produksi pembangunan rumah tinggal menggunakan metode full costing dan

variable costing dan metode yang dilakukan oleh CV Ayorenovasi.

Berdasarkan karateristik masalah yang diangkat oleh peneliti, maka

penelitian ini diklasifikasikan sebagai penelitian deskriptif kuantitatif. Data

yang digunakan dalam penelitian ini yaitu data sekunder yang diperoleh

langsung dari pihak perusahaan seperti data laporan keuangan perusahaan

terkhusus pada laporan harga pokok produksi perusahaan ssecara khusus

“Proyek Sunter tahun 2019”. Sedangkan untuk data serta data sekunder yang

lainnya diperoleh dari buku, jurnal, internet atau media lain yang mendukung

penelitian ini.

Dari hasil analisis data, hasil penelitian menunjukkan bahwa

perhitungan harga pokok produksi variable costing memiliki nilai lebih rendah

dibandingkan dengan perhitungan harga pokok produksi dengan menggunakan

metode full costing dan metode yang diterapkan perusahaan. Harga pokok

produksi yang dihitung menggunakan metode full costing yaitu sebesar Rp

2.352.464 /m2, menurut metode variable costing yaitu sebesar Rp. 2.167.326

/m2 dan menurut metode yang diterapkan perusahaan yaitu sebesar Rp.

2.207.783 /m2.

Kata kunci :Harga pokok produksi, variable costing, full costing, akuntansi

biaya, biaya konstruksi

Page 10: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …

ix

Ferdinand Eka Wijaya Dosen Pembimbing :

NPM 11197560262 Bayu Pratama, SE, M.Ak.

Program Studi S-1 Akuntansi

ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH

TINGGAL DENGAN METODE FULL COSTING DAN METODE

VARIABLE COSTING PADA PERUSAHAAN JASA KONSTRUKSI ABSTRAK

The purpose of this study is to determine the calculation of the cost of

production of residential construction using the full costing and variable costing

methods and methods used by CV Ayorenovasi.

Based on the characteristics of the problem raised by the researcher, this

research is classified as a quantitative descriptive study. The data used in this

study are secondary data obtained directly from the company, such as the

company's financial report data, especially in the company's production cost

report specifically "Sunter Project 2019". As for data and other secondary data

obtained from books, journals, internet or other media that support this

research.

From the results of data analysis, the results show that the calculation of

the cost of goods manufactured variable costing has a lower value than the

calculation of the cost of goods manufactured using the full costing method and

the method applied by the company. The cost of production calculated using the

full costing method is Rp. 2,352,464 / m2, according to the variable costing

method, which is Rp. 2,167,326 / m2 and according to the method applied by

the company that is Rp. 2,207,783 / m2.

Keywords: Cost of goods manufactured, variable costing, full costing, cost

accounting, construction costs

Page 11: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …

x

DAFTAR ISI

Halaman

HALAMAN JUDUL ...................................................................................... i

HALAMAN PERNYATAAN KEASLIAN SKRIPSI .................................. ii

PERSETUJUAN PEMBIMBING .................................................................. iii

HALAMAN PENGESAHAN ........................................................................ iv

KATA PENGANTAR ................................................................................... v

HALAMAN PERNYATAAN PERSETUJUAN PUBLIKASI SKRIPSI ..... vii

ABSTRAK ..................................................................................................... viii

DAFTAR ISI .................................................................................................. x

DAFTAR TABEL .......................................................................................... xiii

DAFTAR GAMBAR ..................................................................................... xiv

DAFTAR LAMPIRAN .................................................................................. xv

BAB I PENDAHULUAN ........................................................................ 1

1.1 Latar Belakang Masalah ....................................................... 1

1.2 Perumusan Masalah ............................................................. 3

1.3 Tujuan Penelitian ................................................................. 3

1.4 Manfaat Penelitian ............................................................... 3

1.4.1 Manfaat Teoritis ................................................ 3

1.4.2 Manfaat Praktis ................................................. 4

BAB II KAJIAN PUSTAKA .................................................................... 5

2.1 Review Penelitian Terdahulu ............................................... 5

2.2 Landasan Teori ..................................................................... 8

2.2.1 Pengertian Biaya ............................................... 8

2.2.2 Akuntansi Biaya ................................................ 9

2.2.3 Biaya Produksi .................................................. 10

2.2.4 Penentuan Tarif Biaya Overhead Pabrik ........... 15

2.2.5 Pengendalian Biaya ........................................... 21

2.2.6 Harga Pokok Produksi ....................................... 23

Page 12: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …

xi

2.2.7 Metode Penentuan Harga Pokok Produksi ........ 26

2.2.8 Metode Pengumpulan Harga Pokok Produksi .. 30

2.2.9 Activity Based Costing ...................................... 35

2.2.10 Jasa Konstruksi .................................................. 36

2.2.11 Proyek................................................................ 38

2.3 Hubungan Antar Variabel Penelitian ................................... 41

2.3.1 Manfaat Informasi yang Dihasilkan Oleh

Metode Full Costing & Variable Costing ......... 41

2.3.2 Penentuan Harga Pokok Produksi Mengunakan

Metode Full Costing sebagai pengambilan

keputusan manajerial ......................................... 43

2.3.3 Penentuan Harga Pokok Produksi Mengunakan

Metode Variable Costing sebagai pengambilan

keputusan manajerial ......................................... 44

2.4 Kerangka Konseptual Penelitian .......................................... 45

BAB III METODA PENELITIAN ........................................................... 47

3.1 Strategi Penelitian ................................................................ 47

3.2 Populasi dan Sampel ............................................................ 47

3.2.1 Populasi dan Penelitian ..................................... 47

3.2.2 Sampel Penelitian .............................................. 48

3.3 Data dan Metode Pengumpulan Data ................................... 48

3.4 Metoda Analisis Data ........................................................... 49

BAB IV HASIL DAN PEMBAHASAN .................................................... 51

4.1 Profil Perusahaan ................................................................. 51

4.1.1 Pendirian Perusahaan ........................................ 51

4.1.2 Tujuan dan Fungsi Perusahaan .......................... 51

4.1.3 Visi dan Misi Perusahaan .................................. 51

4.1.4 Proses Bisnis Perusahaan .................................. 52

4.2 Analisis Data ........................................................................ 53

4.2.1 Analisis Unsur Unsur Biaya Produksi ............... 53

Page 13: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …

xii

4.2.2 Perhitungan Harga Pokok Konstruksi dengan

Metode yang diterapkan perusahaan ................. 60

4.2.3 Perhitungan Harga Pokok Konstruksi dengan

Metode Full Costing.......................................... 61

4.2.4 Perhitungan Harga Pokok Konstruksi dengan

Metode Variable Costing .................................. 62

4.2.5 Perbandingan Harga Pokok Konstruksi ............ 63

4.3 Pembahasan .......................................................................... 65

BAB V SIMPULAN DAN SARAN ......................................................... 68

4.1 Simpulan .............................................................................. 68

4.2 Saran ..................................................................................... 69

4.3 Keterbatasan dan pengembangan penelitian selanjutnya ..... 70

DAFTAR REFERENSI ................................................................................. 71

LAMPIRAN ................................................................................................... 73

DAFTAR RIWAYAT HIDUP ....................................................................... 81

Page 14: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …

xiii

DAFTAR TABEL

Halaman

Tabel 4.1. Spesifikasi Bahan Baku / Material (Proyek Sunter) ................. 54

Tabel 4.2. Biaya Bahan Baku / Material (Proyek Sunter) ......................... 55

Tabel 4.3. Biaya Tenaga Kerja Langsung (Proyek Sunter) ....................... 56

Tabel 4.4. Biaya Overhead Pabrik Variabel (Proyek Sunter) .................... 57

Tabel 4.5. Biaya Overhead Pabrik Tetap (Proyek Sunter) ........................ 60

Tabel 4.6. Laporan Harga Pokok Produksi Metode Perusahaan ............... 61

Tabel 4.7. Laporan Harga Pokok Produksi Metode Full Costing .............. 62

Tabel 4.8. Laporan Harga Pokok Produksi Metode Variable Costing ...... 63

Tabel 4.9. Perbandingan Metode Perusahaan,

Full Costing & Variable Costing .............................................. 64

Tabel 4.10. Selisih Nilai Metode Perusahaan,

Full Costing & Variable Costing .............................................. 64

Page 15: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …

xiv

DAFTAR GAMBAR

Halaman

Gambar 2.1. Kerangka Konseptual Pemikiran ............................................ 46

Gambar 4.1. Alur Proses Bisnis CV Ayorenovasi ...................................... 52

Page 16: ANALISIS PERHITUNGAN HARGA POKOK PRODUKSI RUMAH …

xv

DAFTAR LAMPIRAN

Halaman

Lampiran 1. Laporan Harga Pokok Proyek Sunter ................................... 73

Lampiran 2. Rincian Kerja & Persyaratan Teknis .................................... 75

Lampiran 3. Rencana Anggaran Biaya Proyek Sunter ............................ 76

Lampiran 4. Denah & Gambar Perencanaan Proyek Sunter .................... 79