ABSTRAK
Penyusunan laporan ini dilakukan berdasarkan peninjauan suatu proyek
yang sedang berlangsung. Peninjauan dilakukan terhadap proyek Perbaikan
Jembatan Cipameungpeuk yang berlokasi di Kabupaten Sumedang – Jawa Barat.
Tinjauan di fokuskan kepada pekerjaan pembuatan abutment dengan kontraktor
yang menangani PT. Sumber Agung Jaya Abadi.
Dengan memperhatikan perencanaan serta kegiatan dilapangan maka
diperoleh beberapa permasalahan yang muncul, baik berupa teknis maupun non
teknis yang tidak menyebabkan kegiatan pelaksanaan terkendala. Maka dilakukan
kajian terhadap beberapa masalah sebagai solusinya agar kegiatan
pembangunan dilapangan dapat terus berlangsung.
Berdasarkan hasil analisa pada pelaksanaan proyek, abutment pada
jembatan Cipameungpeuk mempunyai permasalahan yang tidak begitu fatal,
kecuali masalah K3 yang benar benar harus dibenahi oleh pihak pelaksana.
Diharapkan K3 proyek benar benar harus diperhatikan karena akan berpengaruh
pada jalannya pekerjaan dan mutu pekerjaan tersebut.
Kata Kunci : abutment, pelaksanaan dan pengawasan.
![Page 2: Abs Trak](https://reader036.vdokumen.com/reader036/viewer/2022082822/5695d1771a28ab9b0296a7d9/html5/thumbnails/2.jpg)
ABSTRACT
This report is created based on reviewing on project that is still on going.
Writters reviewing on a bridge construction that being repaired at
Cipameungpeuk , regency of Sumedang – West Java. The review is focusing on
making Abutment with PT. Sumber Agung Jaya Abadi that handle this
construction project.
The attention is on construction planning and also the activity at the
construction site, then from that, writters can get technic and non technic
problem, There are several problems that writters found but not cause much
problem. The problem on time scheduling of that project, Then the reserach of
some problem is been doing to get the solution of problems, so the activity at
construction site can still on going.
Based on the reseacrh a project implementation result, there are not found
serious problem at Cipemeungpeuk bridge. Except the problem about safety that
really need to overlook again by the management, if not to be overlook again that
problem will cause an effect on time schedule and the quality of construction also
can be dangerous for site worker.
Keywords : Abutment, Attention, Implementation, Problems