JADWAL PELAKSANAAN PEKERJAAN
SATUAN KERJA : SATUAN KERJA NON VERTIKAL TERTENTU PEMBANGUNAN JALAN DAN JEMBATAN XYZNAMA PAKET PENINGKATAN JALAN SURGALOKASI : KABUPATEN BANGKA SELATAN
ITEM URAIAN PEKERJAANBOBOT
Volume SAT PEKERJAAAN
1.2Mobilisasi 1.00 Ls 0.361%
2.1Pek.Galian Untuk Selokan Drainase & Saluran Air 2,612.98 M3 0.672%
3.1(1)Galian Biasa 4,117.50 M3 0.891%
3.2(1)Timbunan Biasa Selain Dari Sumber Bahan 300.00 M3 0.148%
3.2(2)Timbunan Pilihan 1,857.39 M3 1.533%
3.3Penyiapan Badan Jalan 36,100.00 M2 1.015%
-
5.1(1)Lapis Pondasi Agregat Kelas A 1,882.50 M3 9.235%
5.1(2)Lapis Pondasi Agregat Kelas B 2,210.00 M3 9.440%
6.1(1)Lapis Resap Pengikat 8,785.00 Liter 0.979%
6.1(2)Lapis Perekat 10,810.50 Liter 1.286%
6.3(3)Lataston Lapis Aus ( HRS - WC) 30,940.00 M2 23.430%
6.3(4)Lataston Lapis Pondasi ( HRS - BASE) 1,297.60 M3 31.422%
6.3(4)a Lataston Lapis Pondasi ( HRS - BASE) Leveling 280.98 Ton 2.904%
7.1(5)Beton K 250 92.40 M3 1.299%
7.1(6)Beton K 175 767.51 M3 8.334%
7.3.1Baja Tulangan U 24 Polos 15,222.56 Kg 2.078%
7.9Pasangan Batu 315.00 M3 2.247%
7.15(1)Pembongkaran Pasangan Batu 91.35 M3 0.130%
-
8.1(1)Lapis Pondasi Agregat Kelas A Untuk Pekerjaan Minor 44.20 M3 0.223%
8.1(5)Campuran Aspal Panas Untuk Pekerjaan Minor 11.79 M3 0.291%
8.2(2)Pembongkaran Dan Pembersihan Tanaman 7500.00 M2 0.169%
8.4.(1)Marka Jalan Thermoplastic 1495.08 M2 1.857%
8.4.(3)a Rambu Jalan Tunggal dengan permukaan Pemantul Engineering Grade 6.00 Buah 0.056%
JUMLAH NILAI PEKERJAAN 100.00%KEMAJUAN PEKERJAAN 0.00%KEMAJUAN PEKERJAAN KUMULATIF 0.00%KEMAJUAN REALISASI PEKERJAAN 0.00%KEMAJUAN REALISASI PEKERJAAN KUMULATIF 0.00%KEMAJUAN PEKERJAAN SETELAH AMANDEMEN 0.00%KEMAJUAN PEKERJAAN KUMULATIF SETELAH AMANDEMEN 0.00%
DisetujuiPejabat Pembuat Komitmen
-
Pembangunan Jalan dan Jembatan .............
NAMA............NIP:...............
Mengetahui Kepala Satuan Kerja Non Vertikal TertentuPembangunan Jalan dan Jembatan Bangka Bel
-
Adwin S.Lontoh. ST.M.SINip.110042087
-
JADWAL PELAKSANAAN PEKERJAAN
: SATUAN KERJA NON VERTIKAL TERTENTU PEMBANGUNAN JALAN DAN JEMBATAN XYZ
24-Feb-10 28-Feb-10 7-Mar-10 14-Mar-10 21-Mar-10 28-Mar-10 4-Apr-10 11-Apr-10 18-Apr-10 25-Apr-10 2-May-10
27-Feb-10 6-Mar-10 13-Mar-10 20-Mar-10 27-Mar-10 3-Apr-10 10-Apr-10 17-Apr-10 24-Apr-10 1-May-10 8-May-10
0.035% 0.035% 0.035% 0.035% 0.035% 0.035%
0.045% 0.045% 0.045% 0.045% 0.045% 0.045% 0.045% 0.045%
0.089% 0.089% 0.089% 0.089% 0.089% 0.089%
0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010%
0.113% 0.113% 0.113% 0.113% 0.113% 0.113% 0.113%
APRILMARETFEBRUARI
-
1.049% 1.049% 1.049% 1.049% 1.049%
0.162% 0.162% 0.162%
0.105% 0.350% 0.250% 0.250% 0.250%
0.324% 0.035% 0.191% 0.191% 0.191%
0.035% 0.035% 0.035%
0.016% 0.016%
-
0.160% 0.015% 0.015% 0.015% 0.015% 0.003%
0.032% 0.090% 0.037% 0.037% 0.037%
0.015% 0.035% 0.049% 0.055% 0.015%
0.035% 0.035% 0.050% 0.115% 0.251% 0.507% 1.796% 1.795% 1.996% 2.012% 2.001%
0.035% 0.070% 0.120% 0.235% 0.486% 0.992% 2.788% 4.584% 6.580% 8.592% 10.593%
0.200.27
Disetujui Diperiksa,Pejabat Pembuat Komitmen Konsultan
-
Pembangunan Jalan dan Jembatan ............. PT. ABC
NAMA............ NAMA..................NIP:............... Site Engineer
Diperiksa,Konsultan
-
------------------------------
-
JADWAL PELAKSANAAN PEKERJAAN
9-May-10 16-May-10 23-May-10 30-May-10 6-Jun-10 13-Jun-10 20-Jun-10 27-Jun-10 4-Jul-10 11-Jul-10 18-Jul-10
15-May-10 22-May-10 29-May-10 5-Jun-10 12-Jun-10 19-Jun-10 26-Jun-10 3-Jul-10 10-Jul-10 17-Jul-10 24-Jul-10
0.045% 0.045% 0.045% 0.045% 0.045% 0.045% 0.045%
0.089% 0.089% 0.089% 0.089%
0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010% 0.010%
0.113% 0.113%
JULIJUNIMEI
-
1.154% 1.154% 1.154% 1.154% 1.154% 1.154% 1.154%
1.049% 1.049% 1.049% 1.049%
0.10% 0.100% 0.100% 0.200%
0.100% 0.125% 0.025% 0.050% 0.200%
0.450% 1.200% 3.800% 4.500%
0.85% 0.95% 0.45% 0.35% 0.30%
0.162% 0.162% 0.162% 0.162% 0.162%
0.280% 0.350% 0.350% 0.350% 0.150% 1.250% 1.200% 1.250% 1.949%
0.191% 0.191% 0.191% 0.191% 0.191% 0.191%
0.035% 0.035% 0.035% 0.437% 0.750% 0.600% 0.150% 0.100%
0.016% 0.016% 0.016% 0.016% 0.016% 0.016%
-
0.058%
2.048% 2.060% 1.947% 2.350% 2.479% 3.266% 3.513% 4.139% 4.878% 5.454% 6.354%
12.641% 14.701% 16.648% 18.998% 21.477% 24.743% 28.257% 32.396% 37.274% 42.728% 49.083%
Diperiksa,Konsultan
-
PT. ABC
NAMA..................Site Engineer
Diperiksa,Konsultan
-
------------------------------
-
JADWAL PELAKSANAAN PEKERJAAN
25-Jul-10 1-Aug-10 8-Aug-10 15-Aug-10 22-Aug-10 29-Aug-10 5-Sep-10 12-Sep-10 19-Sep-10
31-Jul-10 7-Aug-10 14-Aug-10 21-Aug-10 28-Aug-10 4-Sep-10 11-Sep-10 18-Sep-10 21-Sep-10
0.100% 0.051%
0.515% 1.018%
100% 90% 80% 70% 60% 50% 40% 30% 0% 10% 20%
100 %
90 %
90%
SEPTEMBERAGUSTUS
-
1.154%
0.200% 0.100% 0.049% 0.129%
0.180% 0.220% 0.290% 0.035% 0.046% 0.015%
3.00% 3.00% 4.750% 3.750% 5.430% 3.500%
3.300% 5.442% 5.228% 5.002% 2.500%
80%
70%
60%
50%
40%
30%
20%
-
0.929% 0.929%
0.056%
7.834% 8.762% 10.317% 8.916% 7.976% 4.030% 1.947% 1.085% 0.051%
56.917% 65.679% 75.996% 84.912% 92.888% 96.918% 98.864% 99.949% 100.000%
###
Pangkalpinang, 24 Februari 2010Diperiksa, DibuatKonsultan Kontraktor
10%
0%
-
PT. ABC PT. BINA MARGA 2
NAMA.................. ANDRIE,STSite Engineer General Superintendant
Pangkalpinang, 9 Juni 2009KontraktorPT.BUDI BAKTI PRIMA
-
Drs.Joe RahailPimpinan Cabang
-
KOREKSI
0.0036115 0.36115 ### 0.36115
0.0067204 0.67204 ### 0.67204
0.0089092 0.89092 ### 0.89092
0.0014811 0.14811 ### 0.14811
0.0153250 1.53250 ### 1.53250
0.0101509 1.01509 ### 1.01509
-
0.0923465 9.23465 ### 9.23465
0.0944002 9.44002 ### 9.44002
0.0097882 0.97882 ### 0.97882
0.0128592 1.28592 ### 1.28592
0.2342987 23.42987 ### 23.42987
0.3142152 31.42152 ### 31.42152
0.0290436 2.90436 ### 2.90438
0.0129912 1.29912 ### 1.29912
0.0833380 8.33380 ### 8.33380
0.0207801 2.07801 ### 2.07801
0.0224745 2.24745 ### 2.24745
0.0013035 0.13035 ### 0.13035
-
0.0022348 0.22348 ### 0.22348
0.0029102 0.29102 ### 0.29102
0.0016856 0.16856 ### 0.16856
0.0185742 1.85742 ### 1.85742
0.0005589 0.05589 ### 0.05589
1.0000006 100.000
-
Curve-S