Rubber Dam For Jakarta Bay Irwan 1 ,Aswar Amiruddin 2  dan A.Ildha Dwi Puspita 3 1 Students of the Master Program in Civil Department, Hasanuddin University, Makassar, phone number 085399068948, email  [email protected] 2 Students of the Master Program in Civil Department, Hasanuddin University,Makassar phone number 085357722996,email  [email protected] 3 Students of the Master Program in Civil Department, Hasanuddin University,Makassar phone number 085398934670,email  [email protected] Jakarta Bay is the busiest beach area in front Indonesia. Jakarta Bay is receiving export through the sea. There are 11 ports, one of the largest ports of Tanjung Priok which has complete facilities and modern technology-based port information.Except the port also grow several public facilities such as Ancol recreation areas, residential areas, business districts and regional fisheries. Growth of Jakarta Bay will continue. Investor of residence and government are increasingly interested in developing its business towards the sea considering the city of Jakarta has been very full with residence.According to Jakarta’s Master Plan, Jakarta Bay area will be reclaimed for creating residential areas, tourism and the business area. In the Master Plan of Jakarta also planned for the road transport access to new areas in Jakarta Bay.This means a big construction and all possibilities must be planned for Jakarta Bay. Beside the significance of Jakarta bay there is the threat of environmental damage . Since the lost of mangrove ecosystem brings problems puddle that covered the only highway that connects to the Jakarta International Airport which has led to serious problems with the Air Transportation Jakarta. Flood Hazard from the river mouth into Jakarta Bay is also very serious. This happens because discharge of river in Jakarta is too big during the rainy season and receive runoff from of land. Reclamation will further extend the flow of t he river. With the condition of the coastal zone topography is relatively flat and the amount of water that will pass through the river is  big enough then at the same flow rate slows down, it is likely to lead to overflow of water from water bodies. The rubber dam can be made more than one. The Giant Sea Wall should have 3dams. . On the rubber dam will be made bridge.

Upload: aswaramir89

Post on 04-Jun-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

 

Rubber Dam For Jakarta Bay

Irwan1,Aswar Amiruddin

2 dan A.Ildha Dwi Puspita

1Students of the Master Program in Civil Department, Hasanuddin University, Makassar, phone number085399068948, email  [email protected] 

2Students of the Master Program in Civil Department, Hasanuddin University,Makassar phone number

085357722996,email  [email protected] 3Students of the Master Program in Civil Department, Hasanuddin University,Makassar phone number

085398934670,email  [email protected] 

Jakarta Bay is the busiest beach area in front Indonesia. Jakarta Bay is receiving

export through the sea. There are 11 ports, one of the largest ports of Tanjung Priok which

has complete facilities and modern technology-based port information.Except the port also

grow several public facilities such as Ancol recreation areas, residential areas, business

districts and regional fisheries.

Growth of Jakarta Bay will continue. Investor of residence and government are

increasingly interested in developing its business towards the sea considering the city of

Jakarta has been very full with residence.According to Jakarta’s Master Plan,Jakarta Bay area

will be reclaimed for creating residential areas, tourism and the business area. In the Master

Plan of Jakarta also planned for the road transport access to new areas in Jakarta Bay.This

means a big construction and all possibilities must be planned for Jakarta Bay.

Beside the significance of Jakarta bay there is the threat of environmental damage .

Since the lost of mangrove ecosystem brings problems puddle that covered the only highway

that connects to the Jakarta International Airport which has led to serious problems with the

Air Transportation Jakarta. Flood Hazard from the river mouth into Jakarta Bay is also very

serious. This happens because discharge of river in Jakarta is too big during the rainy season

and receive runoff from of land.

Reclamation will further extend the flow of the river. With the condition of the coastal

zone topography is relatively flat and the amount of water that will pass through the river is

 big enough then at the same flow rate slows down, it is likely to lead to overflow of water

from water bodies.

The rubber dam can be made more than one. The Giant Sea Wall should have 3dams.

. On the rubber dam will be made bridge.

 

 

Fig.1 Layout for Rubber DAM Position on Giant Sea Wall

Fig.2 Rubber DAM

Ruber dam on the benefits of land reclamation is able to overcome flood reclaimed

land and maintain the circulation flow of water so as not to be dead. With consideration of the

expensive maintenance costs of the pump of the polder system, the rubber dam system is a

system with a lower cost compared with the pump system.