rab type 70
TRANSCRIPT
-
7/29/2019 RAB TYPE 70
1/6
RENCANA ANGGARAN BEAYA Proyek : Rumah Tinggal Type 70
Lokasi : Sleman Yogyakarta
NO
URAIAN PEKERJAAN
VOLUME SATHARGA SAT JUMLAH HARGA
(Rp) (Rp)A. BANGUNAN UTAMA I Pekerjaan Persiapan
1 Pembersihan lokasi 180.00 m210,000.
001,800,000.00
2 Brak Kerja 12.00 m2300,000.
003,600,000.00
3 Uitzet dan Bauplank 58.00 m215,000.
00870,000.00
4Air Kerja
1.00 ls450,000.
00450,000.00
5Keamanan Proyek
1.00 ls1,200,000.
001,200,000.00
Sub.Jumlah 7,920,000.00
II Pekerjaan Tanah
1 Galian tanah42.21 m3
12,500.00
527,625.00
2 Urugan tanah kembali10.55 m3
3,125.00
32,968.75
3 Urugan pasir bawah pondasi6.03 m3
60,000.00
361,800.00
Sub.Jumlah 922,393.75
III Pekerjaan Beton Bertulang
1 Slof 15/202.01 m3 2,250,000.
004,522,500.00
2 Kolom praktis 15/151.61 m3
2,500,000.00
4,025,000.00
3 Ring Balk 15/151.50 m3
2,500,000.00
3,750,000.00
Sub Jumlah 12,297,500.00
IV. Pekerjaan Pasangan +Plesteran
1 Pas. Batu belah 1Pc : 3Kp : 10Ps18.09 m3
275,000.00
4,974,750.00
2 Pas. Bata trasram 1:237.30 m2
43,943.00
1,639,073.90
3 Pasangan Bata 1Pc :3 Kp:10 Ps107.30 m2 40,940.
004,392,862.00
4 Plesteran dinding 1:374.60 m2
20,500.00
1,529,300.00
5 Plesteran 1: 3 :10214.60 m2
14,600.00
3,133,160.00
6 Sponengan sudut dan ban-banan114.50 m1
2,450.00
280,525.00
7 Sub.Jumlah 15,949,670.90
-
7/29/2019 RAB TYPE 70
2/6
V.Pekerjaan Keramik dan pelapisdinding
1 Keramik lantai ruang56.50 m2
105,000.00
5,932,500.00
2 Keramik lantai teras+selasar Belakang
10.50 m2105,000.
00
1,102,500.00
3 Keramik lantai kamar mandi Utama3.00 m2
120,000.00
360,000.00
4 Keramik dinding11.00 m2
115,000.00
1,265,000.00
5 Lstello13.00 bh
17,500.00
227,500.00
6 Keramik meja dapur1.00 m2
92,000.00
92,000.00
7 Pasangan batu alam18.50 m2
185,000.00
3,422,500.00
Sub.Jumlah 12,402,000.00
VI. Pekerjaan Pintu dan Jendela
1 Kusen pintu jendela 6/12 kayu jati70.00 m1
60,000.00
4,200,000.00
2 Pintu double teakwood6.00 bh
600,000.00
3,600,000.00
3 Daun jendela kaca11.00 bh
650,000.00
7,150,000.00
4 Engsel pintu 4"12.00 bh
15,000.00
180,000.00
5 Engsel jendela 3"6.00 bh
12,000.00
72,000.00
6 Handel pintu7.00 ps
200,000.00
1,400,000.00
7 Slot pintu kamar dll12.00 bh 220,000.
002,640,000.00
8 Hak angin jendela42.00 bh
25,000.00
1,050,000.00
9 Grendel jendela3.00 bh
12,500.00
37,500.00
Sub.Jumlah 20,329,500.00
VII. Pekerjaan Plafon dan atap
1 Plafon70.00 m2
70,000.00
4,900,000.00
2 Gunung-gunung33.25 m2
46,000.00
1,529,500.00
3 Nok, murplat, gording, jurai6.48 m3
325,000.00
2,106,000.00
4 Papan talang dan seng15.00 m1
32,000.00
480,000.00
5 Lisplank43.00 m1
45,000.00
1,935,000.00
6 Genteng kodok Godean125.75 m2
25,500.00
3,206,625.00
7 Kerpus /bubungan 35.00 m1 47,200. 1,652,000.00
-
7/29/2019 RAB TYPE 70
3/6
00
Sub.Jumlah 15,809,125.00
VIII. Pekerjaan pipa dan Sanitair
1 Pipa tinja PVC 4" Wavin D6.00 m1
28,500.00
171,000.00
2 Pipa air kotor PVC 3" Wafin D34.00 m1 20,500.
00697,000.00
3 Pipa air bersih PVC 3/4 Wafin AW3.15 m1
11,000.00
34,650.00
4 Pipa air bersih PVC 1/2 " Wafin AW21.00 m1
10,000.00
210,000.00
5 Bak kontrol1.00 bh
150,000.00
150,000.00
6 Sumur dan air bersih1.00 unit
3,000,000.00
3,000,000.00
7 Water torn Penguin 500 l+ Radar1.00 unit
1,100,000.00
1,100,000.00
8 Pompa air Jet Pump1.00 unit
1,200,000.
001,200,000.00
9 Septitank1.00 unit
1,300,000.00
1,300,000.00
10 Peresapan1.00 unit
600,000.00
600,000.00
11 Monoblok INA1.00 unit
1,500,000.00
1,500,000.00
12 Bak Mandi1.00 unit
700,000.00
700,000.00
13 Hand Sower1.00 bh
340,000.00
340,000.00
14 Kran Cabang1.00 bh
425,000.00
425,000.00
15 Kran tembok3.00 bh 130,000.
00390,000.00
16 Floor drain1.00 bh
160,000.00
160,000.00
Sub.Jumlah 11,977,650.00
IX. Pekerjaan Instalasi Listrik
1 Instalasi titik lampu10.00 ttk
110,000.00
1,100,000.00
2 Instalasi titik lampu TL1.00 ttk
165,000.00
165,000.00
3 Sambung Daya 2200 wat1.00 ls
4,000,000.00
4,000,000.00
4 MCB + box1.00 unit
275,000.00
275,000.00
5 Stop kontak Broco6.00 bh
182,500.00
1,095,000.00
6 Saklar tunggal Broco5.00 bh
50,000.00
250,000.00
7 Saklar Doble Broco3.00 bh
55,000.00
165,000.00
Sub.Jumlah 7,050,000.00
-
7/29/2019 RAB TYPE 70
4/6
X. Pekerjaan Cat /finising
1 Cat dinding214.60 m2
20,500.00
4,399,300.00
2 Cat Plafon70.00 m2
20,500.00
1,435,000.00
3 Melamin Kusen70.00 m1 35,000.
002,450,000.00
4 Melamin daun pintu19.20 m2
65,000.00
1,248,000.00
5 Melamin daun jendela9.90 m1
35,000.00
346,500.00
Sub. Jumlah 9,878,800.00
XI. Pekerjaan Lain-lain
1 Pembersihan akir1.00 ls
500,000.00
500,000.00
Sub.Jumlah 500,000.00
XII. Pekerjaan Tambahan
1 Pompa pedorong1.00 unit
850,000.00
850,000.00
2 Carport16.50 m2
42,500.00
701,250.00
Sub.Jumlah 1,551,250.00
Jauhari Arif Pratama
3TGB2/20
-
7/29/2019 RAB TYPE 70
5/6
REKAPITULASI RENCANA ANGGARAN BEAYA
-
7/29/2019 RAB TYPE 70
6/6
Proyek : Rumah Tinggal Type 70
Lokasi : Sleman Yogyakarta
NO URAIAN PEKERJAANJUMLAH HARGA
(RP)
A. BANGUNAN UTAMA
1 Pekerjaan Persiapan 7.920.000.00
2 Pekerjaan Tanah 922.394,00
3 Pekerjaan Beton Bertulang 12.297.500,00
4 Pekerjaan Pasangan +Plesteran 15.949.671,00.
5 Pekerjaan Keramik dan pelapis dinding 12.402.000,00
6 Pekerjaan Pintu dan Jendela 20.329.500,00
7 Pekerjaan Plafon dan atap 15.809.125,00
8 Pekerjaan pipa dan Sanitair 11.977.650,00
9 Pekerjaan Instalasi Listrik 7.050.000,00
10 Pekerjaan Cat/Finishing 9.878.800,00
11 Pekerjaan Lain-lain 500.000,00
11 Pekerjaan Tambahan 1.551.250,00
Jumlah 116.587,890,00
Dibulatkan
Rp 116.587.000,00