RENCANA ANGGARAN BIAYA (RAB)

KEGIATAN :PEMBANGUNAN GEDUNG PAMERAN

BADAN KETAHANAN PANGAN DAERAHPROPINSI SULAWESI SELATAN

LOKASI :

BENTENG SOMBA OPU, MAKASSAR

2009

KONSULTAN PERENCANA

Page 2: Rab Pos Bii Revisi - Edit

SCHEDULE PELAKSANAAN PEKERJAANPEMBANGUNAN REHABILITASI POS SATPAM KOMPLEKS BI (BANK INDONESIA)

NO. JENIS PEKERJAAN Bobot % BULAN I BULAN II BULAN III

KET1 2 3 4 5 6 7 8 9 10 11 12

I PEKERJAAN PERSIAPAN 1.3061.306 100

II PEKERJAAN TANAH DAN PONDASI 16.1958.098 8.098

III PEK. STRUKTUR BETON 62.86320.954 20.954 20.954

IV PEK. PASANGAN DINDING BATA 5.9331.483 1.483 1.483 1.483

V PEKERJAAN LANTAI DAN KERAMIK DINDING 2.5760.859 0.859 0.859

VI PEK. KOSEN PINTU/JENDELA 11.1263.709 3.709 3.709

50

VII PEKERJAAN KUDA - KUDA DAN GORDING #REF!#REF! #REF!

VIII PEKERJAAN PLAFOND DAN RANGKA #REF!#REF!

IX PEKERJAAN PENGECATAN #REF!#REF! #REF! #REF!

X PEKERJAAN INSTALASI LISTRIK #REF!#REF! #REF!

XI PEKERJAAN INSTALASI AIR BERSIH/KOTOR #REF!#REF!

XII PEKERJAAN FINISHING & LAIN-LAIN #REF!#REF! #REF! #REF! #REF!

0

RENCANA #REF! 9.404 29.052 22.438 22.438 2.342 6.051 4.567 #REF! #REF! #REF! #REF! #REF!

KOMULATIF 0 9.404 38.456 60.894 83.331 85.673 91.724 96.291 #REF! #REF! #REF! #REF! #REF!

Konsultan PerencanaCV. DELI SERDANG JAYA CONSULTANT

ANDI MUH. IRSAN, STDIREKTUR UTAMA

Page 3: Rab Pos Bii Revisi - Edit

REKAPITULASI ANGGARAN BIAYA ( RAB )

PEKERJAAN: PEMBANGUNAN REHABILITASI POS SATPAM KOMPLEKS BI (BANK INDONESIA)

PROPINSI SULAWESI SELATAN

LOKASI : JL. SULTAN ALAUDIN ( KOMP. BI)

TAHUN : 2009

NO. JENIS PEKERJAANJUMLAH HARGA

( Rp )

I PEKERJAAN PERSIAPAN 354,947.50

II PEK. KUSEN PINTU/JENDELA 4,400,185.00

III PEKERJAAN ATAP 17,079,525.80

IV PEKERJAAN PLAFOND 1,612,012.05

V PEKERJAAN PASANGAN 699,912.20

VI PEKERJAAN PENGECATAN 3,022,826.33

SUB TOTAL 27,169,408.88

PPN 10 % 2,716,940.89

TOTAL 29,886,349.77

DIBULATKAN 29,880,000.00

TERBILANG : DUA PULUH DUA JUTA EMPAT PULUH RIBU RUPIAH

Konsultan Perencana

CV. DELI SERDANG JAYA CONSULTANT

Andi Muhammad Irsan, ST

Direktur Utama

Page 4: Rab Pos Bii Revisi - Edit

RENCANA ANGGARAN BIAYA ( RAB )

PEKERJAAN : PEMBANGUNAN REHABILITASI POS SATPAM KOMPLEKS BI (BANK INDONESIA)

PROPINSI SULAWESI SELATAN

LOKASI : JL. SULTAN ALAUDIN ( KOMP. BI)

TAHUN : 2009

NO. JENIS PEKERJAAN SATUAN VOLUME( Rp ) ( Rp )

I PEKERJAAN PERSIAPAN

1 Pekerjaan Pembersihan 12.85 6,100.00 78,385.00

2 Pekerjaan Bongkaran 8.85 31,250.00 276,562.50

JUMLAH 354,947.50

II PEK. KUSEN PINTU/JENDELA

1 Pas. Kusen Kayu Kelas I 0.32 9,265,600.00 2,918,664.00

2 Pintu Panil Kayu kelas I 1.68 459,850.00 772,548.00

3 Kaca Mati 5 mm 5.20 85,000.00 442,000.00

4 Engsel Pintu Biasa psg 3.00 36,139.00 108,417.00

5 Kunci Pintu 2 x Putar bh 1.00 158,556.00 158,556.00

JUMLAH 4,400,185.00

III PEKERJAAN ATAP

1 Pek. Kuda-Kuda Kayu Klas I dan Skor Angin 0.86 8,890,000.00 7,645,400.00

2 Pek. Gording Kayu Kelas II 4/6 dan Reng 3/5 16.50 210,030.00 3,465,495.00

3 Pekerjaan Listplank Kayu Kelas I 2x20 23.30 43,130.00 1,004,929.00

4 Pek. Atap Multiroof + Talang Karet 24.15 86,549.00 2,090,158.35

5 Pek. Bubungan Atap Multiroof + Talang karet 15.65 183,613.00 2,873,543.45

JUMLAH 17,079,525.80

IV PEKERJAAN PLAFOND

1 Pek. Rangka Plafon + Gypsum board 9 mm 10.45 100,554.00 1,050,789.30

2 List Profil sudut Plafond 14.75 38,049.00 561,222.75

JUMLAH 1,612,012.05

V PEKERJAAN PASANGAN

1 Pek. Pasangan Batu Bata (tangga keliling) 1.10 157,305.00 173,428.76

2 Pek. Tegel Keramik 20/20 (tangga keliling) 5.88 89,538.00 526,483.44

JUMLAH 699,912.20

VI PEKERJAAN PENGECATAN

1 Pek. Pengecatan Tembok Dinding Dalam 36.88 20,631.00 760,768.13

2 Pek. Pengecatan Tembok Dinding Luar 49.28 20,631.00 1,016,592.53

3 Pek. Pengecatan Plafond 10.45 27,611.50 288,540.18

4 Pek. Pengecatan Kusen & Pintu 8.85 23,710.00 209,833.50

5 Pek. Cat Residu Kuda-kuda kayu 24.15 8,060.00 194,649.00

6 Cat Lisplank 23.30 23,710.00 552,443.00

JUMLAH 3,022,826.33

TOTAL : 27,169,408.88

HARGA SATUAN

JUMLAH HARGA

m2

m3

m3

m2

m2

m3

m2

m1

m2

m1

m2

m1

m3

m2

m2

m2

m2

m2

m2

m2

Page 5: Rab Pos Bii Revisi - Edit

DAFTAR HARGA SATUAN UPAH DAN BAHAN

PEKERJAAN : PEMBANGUNAN REHABILITASI POS SATPAM KOMPLEKS BI (BANK INDONESIA)

PROPINSI SULAWESI SELATAN

LOKASI : JL. SULTAN ALAUDIN ( KOMP. BI)

TAHUN : 2009

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

TENAGA 1 Tukang hari 45,000.00 2 Kepala Tukang hari 55,000.00 3 Pekerja hari 35,000.00 4 Mandor hari 52,000.00 5 Pengawas / Ahli Teknik hari 75,000.00 6 Ahli ukur hari 75,000.00

BAHAN 1 Balok Kelas I sawmil 7,300,000.00 2 Papan Kelas I Sawmil 7,400,000.00 3 Balok Kls II 3,300,000.00 4 Papan Kelas II 3,600,000.00 5 Balok Kelas III 1,850,000.00 6 Papan kelas III 2,100,000.00 7 Teakwood (122 x 244 x 0.3 cm) lbr 96,000.00 8 Cat besi ex Avian kg 45,000.00 9 Cat kayu ex Avian kg 33,000.00 10 Cat tembok ex Metrolite kg 12,600.00 11 Cat tembok/cat polivynyl asetat Ex Dulux kg 55,000.00 12 Cat tembok/cat kilap/cat acrilyc Ex Dulux kg 60,000.00 13 Cat dasar meni besi type A (cepat kering) Jago kg 22,500.00 14 Cat Meni Kayu kg 9,000.00 15 Cat Kayu Residu kg 8,600.00 16 Plamur tembok acrilyc kg 5,500.00 17 Cat Duko kg 35,000.00 18 Minyak cat ltr 18,000.00 19 Thinner ltr 15,000.00 20 Spiritus ltr 6,500.00 21 Ampas lbr 2,500.00 22 Kuas roll bh 15,000.00 23 Kuas ukuran 3,5" bh 8,000.00 24 Kuas ukuran 2,5" bh 5,000.00 25 Soda api kg 15,000.00 26 Tegel warna 30/30 48,000.00 27 Besi beton polos kg 9,800.00 28 Besi strip kg 6,000.00 29 Besi Plat T=3 mm Lbr 65,000.00 30 Paku Biasa kg 17,000.00 31 Paku pancing kg 20,000.00 32 Paku Tripleks kg 18,500.00 33 Pasir urug 80,000.00 34 Pasir pasang 100,000.00 35 Batu merah bj 600.00 36 Sirtu 122,000.00 37 Portland Cement (PC) Tonasa kg 1,100.00 38 Semen putih kg 1,750.00 39 Semen warna kg 2,500.00

40 Kapur pasang 78,000.00

41 Kaca 5 mm 85,000.00 42 Kunci tanam ex Picaso 1 Slag bh 126,000.00 43 Kunci tanam biasa ex Kuda Terbang bh 75,000.00 44 Engsel pintu bh 28,000.00 45 Engsel jendela bh 25,000.00 46 Grendel Kecil bh 21,000.00 47 Grendel Besar bh 28,000.00 48 Hak Angin Besar bh 14,000.00 49 Kait angin bh 5,000.00 50 Atap Multiroof lbr 50,000.00 51 Bubungan Multiroof lbr 45,000.00

52 Karet Talang 18,500.00 53 Paku gypsum kg 25,000.00 54 Tepung Gypsum kg 3,500.00 55 Alkasit kg 300,000.00 56 Gypsum board 9 mm lbr 65,000.00 57 Kasa gypsum roll 12,000.00

58 List profil gypsum lebar sampai 5 cm 20,000.00

59 List profil gypsum lebar sampai 6 - 10 cm 25,000.00

60 List profil gypsum lebar lebih 10 cm 35,000.00

m3 m3 m3 m3 m3 m3

m2

m3 m3

m3

m3

m2

m2

m1

m1

m1

Page 6: Rab Pos Bii Revisi - Edit

ANALISA SNI HARGA SATUAN BAHAN DAN UPAH KERJA

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

PEKERJAAN PENDAHULUAN

SNI 1.0000 Membersihkan lapangan dan perataan6.8 0.1000 org Pekerja @ Rp. 35,000.00 3,500.00

03-2835-2002 0.0500 org Mandor @ Rp. 52,000.00 2,600.00 JUMLAH ( BELUM PPN ) 6,100.00 - 6,100.00

SNI 1.0000 Pengukuran dan pemasangan bouwplank untuk gedung dan saluran

6.4 0.0120 Kayu meranti 5/7 @ Rp. 1,850,000.00 22,200.00 03-2835-2002 0.0200 kg Paku reng @ Rp. 17,000.00 340.00

0.0070 Kayu papan 3/20 @ Rp. 2,100,000.00 14,700.00 0.1000 org Tukang kayu @ Rp. 45,000.00 4,500.00 0.0100 org Kepala tukang kayu @ Rp. 55,000.00 550.00

JUMLAH ( BELUM PPN ) 5,050.00 37,240.00 42,290.00

PEKERJAAN BONGKARAN

AK 1.0000 Membongkar pasangan batu kali 1.0000 org Pekerja @ Rp. 35,000.00 35,000.00

JUMLAH ( BELUM PPN ) 35,000.00 - 35,000.00

AK 1.0000 Membongkar pasangan batu merah dan membersihkan 0.5000 org Tukang batu @ Rp. 45,000.00 22,500.00 0.2500 org Pekerja @ Rp. 35,000.00 8,750.00

JUMLAH ( BELUM PPN ) 31,250.00 - 31,250.00

AK 1.0000 Membongkar beton bertulang dan membersihkan 0.2000 org Tukang batu @ Rp. 45,000.00 9,000.00 8.0000 org Pekerja @ Rp. 35,000.00 280,000.00 0.1000 org Mandor @ Rp. 52,000.00 5,200.00

JUMLAH ( BELUM PPN ) 294,200.00 - 294,200.00

PEKERJAAN PASANGAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps6.11 70.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 600.00 42,000.00

03-2837-2002 11.5000 kg PC @ Rp. 1,100.00 12,650.00

0.0430 Pasir pasang @ Rp. 100,000.00 4,300.00 0.1000 org Tukang batu @ Rp. 45,000.00 4,500.00 0.0100 org Kepala tukang batu @ Rp. 55,000.00 550.00 0.3200 org Pekerja @ Rp. 35,000.00 11,200.00 0.0150 org Mandor @ Rp. 52,000.00 780.00

JUMLAH ( BELUM PPN ) 17,030.00 58,950.00 75,980.00

SNI 1.0000 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps6.4 140.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 600.00 84,000.00

03-2837-2002 26.4500 kg PC @ Rp. 1,100.00 29,095.00

0.0980 Pasir pasang @ Rp. 100,000.00 9,800.00 0.2000 org Tukang batu @ Rp. 45,000.00 9,000.00 0.0200 org Kepala tukang batu @ Rp. 55,000.00 1,100.00 0.6500 org Pekerja @ Rp. 35,000.00 22,750.00 0.0300 org Mandor @ Rp. 52,000.00 1,560.00

JUMLAH ( BELUM PPN ) 34,410.00 122,895.00 157,305.00

SNI 1.0000 Plesteran 1 Pc : 3 Ps, tebal 15 mm6.3 6.4800 kg PC @ Rp. 1,100.00 7,128.00

03-2837-2002 0.0190 Pasir pasang @ Rp. 100,000.00 1,900.00 0.1500 org Tukang batu @ Rp. 45,000.00 6,750.00 0.0150 org Kepala tukang batu @ Rp. 55,000.00 825.00 0.2000 org Pekerja @ Rp. 35,000.00 7,000.00 0.0100 org Mandor @ Rp. 52,000.00 520.00

JUMLAH ( BELUM PPN ) 15,095.00 9,028.00 24,123.00

Analisa ZAZ 1.0000 Acian dinding bata 3.5000 kg PC @ Rp. 1,100.00 3,850.00 0.0330 org Tukang batu @ Rp. 45,000.00 1,485.00 0.0033 org Kep. Tk. Batu @ Rp. 55,000.00 181.50 0.0700 org Pekerja @ Rp. 35,000.00 2,450.00 0.0035 org Mandor @ Rp. 52,000.00 182.00

JUMLAH ( BELUM PPN ) 4,298.50 3,850.00 8,148.50

AK 1.0000 Pasang tegel keramik 20/20 dan 30/30

1.0000 Tegel keramik (std) @ Rp. 48,000.00 48,000.00 4.0800 kg PC @ Rp. 1,100.00 4,488.00

0.0090 Pasir pasang @ Rp. 100,000.00 900.00 0.6000 kg Semen putih @ Rp. 2,500.00 1,500.00 0.5000 org Tukang batu @ Rp. 45,000.00 22,500.00 0.0500 org Kep. Tk. Batu @ Rp. 55,000.00 2,750.00 0.2500 org Pekerja @ Rp. 35,000.00 8,750.00 0.0125 org Mandor @ Rp. 52,000.00 650.00

JUMLAH ( BELUM PPN ) 34,650.00 54,888.00 89,538.00

SNI 1.0000 Pasang plint keramik ukuran 10 x 30 cm

6.24 0.2300 Keramik 30/30 @ Rp. 48,000.00 11,040.00 1.2000 kg PC @ Rp. 1,100.00 1,320.00

0.0030 Pasir pasang @ Rp. 100,000.00 300.00 0.1000 kg Semen warna @ Rp. 2,500.00 250.00 0.0300 org Tukang batu @ Rp. 45,000.00 1,350.00 0.0030 org Kepala tukang batu @ Rp. 55,000.00 165.00 0.0600 org Pekerja @ Rp. 35,000.00 2,100.00 0.0030 org Mandor @ Rp. 52,000.00 156.00

JUMLAH ( BELUM TERMASUK PPN ) 3,771.00 12,910.00 16,681.00

PEKERJAAN KAYU

SNI 1.0000 Membuat kusen pintu / jendela kayu kelas I

6.1 1.1000 Kayu Kelas I (Bayam) @ Rp. 7,300,000.00 8,030,000.00 03-3434-2002 20.0000 org Tukang kayu @ Rp. 45,000.00 900,000.00

2.0000 org Kepala tukang kayu @ Rp. 55,000.00 110,000.00 6.0000 org Pekerja @ Rp. 35,000.00 210,000.00 0.3000 org Mandor @ Rp. 52,000.00 15,600.00

JUMLAH ( BELUM PPN ) 1,235,600.00 8,030,000.00 9,265,600.00

m2

m1

m3

m3

m3

m3

m3

m2

m3

m2

m3

m2

m3

m2

m2

m2

m3

m1

m2

m3

m3

m3

Page 7: Rab Pos Bii Revisi - Edit

SNI 1.0000 Mengerjakan daun pintu / jendela panil kayu Kelas I

6.7 0.0400 Kayu jati papan @ Rp. 7,400,000 296,000.00 03-3434-2002 2.5000 org Tukang kayu @ Rp. 45,000 112,500.00

0.2500 org Kepala tukang kayu @ Rp. 55,000 13,750.00 1.0000 org Pekerja @ Rp. 35,000 35,000.00 0.0500 org Mandor @ Rp. 52,000 2,600.00

JUMLAH ( BELUM PPN ) 163,850.00 296,000.00 459,850.00

SNI 1.0000 Pasang konstruksi kuda-kuda kayu Kelas I

6.27 1.1000 Kayu Kayu kelas I @ Rp. 7,300,000.00 8,030,000.00 03-3434-2002 15.0000 kg Besi strip @ Rp. 6,000.00 90,000.00

0.8000 kg Paku biasa 2" - 5" @ Rp. 17,000.00 13,600.00 12.0000 org Tukang kayu @ Rp. 45,000.00 540,000.00 1.2000 org Kepala tukang kayu @ Rp. 55,000.00 66,000.00 4.0000 org Pekerja @ Rp. 35,000.00 140,000.00 0.2000 org Mandor @ Rp. 52,000.00 10,400.00

JUMLAH ( BELUM PPN ) 756,400.00 8,133,600.00 8,890,000.00

AK 1.0000 Pasang Gording dan Reng Kayu Kelas II

0.0120 Kasau kayu Kelas I (4/6) @ Rp. 7,300,000.00 87,600.00

0.0150 Reng Kayu Kelas I (2/3) @ Rp. 7,300,000.00 109,500.00 0.1500 kg Paku usuk @ Rp. 17,000.00 2,550.00 0.1000 kg Paku reng @ Rp. 17,000.00 1,700.00 0.1000 org Tukang kayu @ Rp. 45,000.00 4,500.00 0.0100 org Kep. Tk. Kayu @ Rp. 55,000.00 550.00 0.1000 org Pekerja @ Rp. 35,000.00 3,500.00 0.0025 org Mandor @ Rp. 52,000.00 130.00 JUMLAH ( BELUM PPN ) 8,680.00 201,350.00 210,030.00

SNI 1.0000 Pasang lisplank ukuran 2 x (2 x 20) cm, Kayu Kelas II

0.0086 Kayu Papan Kelas II @ Rp. 3,600,000.00 30,960.00 03-3434-2002 0.0600 kg Paku biasa 2" - 5" @ Rp. 17,000.00 1,020.00

0.1000 org Tukang kayu @ Rp. 45,000.00 4,500.00 0.0100 org Kepala tukang kayu @ Rp. 55,000.00 550.00 0.1000 org Pekerja @ Rp. 35,000.00 3,500.00 0.0500 org Mandor @ Rp. 52,000.00 2,600.00

JUMLAH ( BELUM PPN ) 11,150.00 31,980.00 43,130.00

SNI 1.0000 Pasang atap Multiroof6.13 1.1000 lbr Multiroof @ Rp. 50,000.00 55,000.00

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 20,000.00 2,400.00

1.1000 Karet talang @ Rp. 18,500.00 20,350.00 0.0700 org Tukang kayu @ Rp. 45,000.00 3,150.00 0.0070 org Kepala tukang kayu @ Rp. 55,000.00 385.00 0.1400 org Pekerja @ Rp. 35,000.00 4,900.00 0.0070 org Mandor @ Rp. 52,000.00 364.00

JUMLAH ( BELUM PPN ) 8,799.00 77,750.00 86,549.00

SNI 1.0000 Pasang bubung Multiroof6.22 1.1000 lbr Bubung Multiroof @ Rp. 45,000.00 49,500.00

03-3436-2002 6.0000 bh Paku sekrup 3,5" @ Rp. 20,000.00 120,000.00

0.2500 Karet talang @ Rp. 18,500.00 4,625.00 0.1250 org Tukang kayu @ Rp. 45,000.00 5,625.00 0.0130 org Kepala tukang kayu @ Rp. 55,000.00 715.00 0.0840 org Pekerja @ Rp. 35,000.00 2,940.00 0.0040 org Mandor @ Rp. 52,000.00 208.00

JUMLAH ( BELUM PPN ) 9,488.00 174,125.00 183,613.00

6.13 1.0000 Langit-langit gypsum board tebal 9 mm, rangka 60 x 120 Kayu Kelas II

0.0130 Kayu Kelas II @ Rp. 3,300,000.00 42,900.00 0.3600 lbr Gypsum board 9 mm @ Rp. 65,000.00 23,400.00 0.0500 roll Kasa gypsum @ Rp. 12,000.00 600.00 0.4500 kg Tepung gypaum @ Rp. 3,500.00 1,575.00 0.0030 kg Alkasit @ Rp. 300,000.00 900.00 0.0500 kg Paku gypsum @ Rp. 25,000.00 1,250.00 0.1200 kg Paku usuk @ Rp. 18,500.00 2,220.00 0.3700 org Tukang kayu @ Rp. 45,000.00 16,650.00 0.0370 org Kepala tukang kayu @ Rp. 55,000.00 2,035.00 0.2400 org Pekerja @ Rp. 35,000.00 8,400.00 0.0120 org Mandor @ Rp. 52,000.00 624.00

JUMLAH ( BELUM PPN ) 27,709.00 72,845.00 100,554.00

AK 1.0000 Pasang list profil cornees gypsum lebar 5 - 10 cm

1.1000 List profil cornees gypsum @ Rp. 25,000.00 27,500.00 0.8750 kg Tepung gypaum @ Rp. 3,500.00 3,062.50 0.0044 kg Alkasit @ Rp. 300,000.00 1,320.00 0.0375 org Tukang kayu @ Rp. 45,000.00 1,687.50 0.0037 org Kepala tukang kayu @ Rp. 55,000.00 203.50 0.1125 org Pekerja @ Rp. 35,000.00 3,937.50 0.0065 org Mandor @ Rp. 52,000.00 338.00

JUMLAH ( BELUM PPN ) 6,166.50 31,882.50 38,049.00

6.2 1.0000 bh Pasang kunci tanam 1.0000 bh Kunci tanam Biasa @ Rp. 126,000.00 126,000.00 0.6000 org Tukang kayu @ Rp. 45,000.00 27,000.00 0.0600 org Kepala tukang kayu @ Rp. 55,000.00 3,300.00 0.0600 org Pekerja @ Rp. 35,000.00 2,100.00 0.0030 org Mandor @ Rp. 52,000.00 156.00

JUMLAH ( BELUM PPN ) 32,556.00 126,000.00 158,556.00

6.12 1.0000 bh Pasang kunci selot 1.0000 bh Kunci selot @ Rp. 75,000.00 75,000.00 0.2000 org Tukang kayu @ Rp. 45,000.00 9,000.00 0.0200 org Kepala tukang kayu @ Rp. 55,000.00 1,100.00 0.0200 org Pekerja @ Rp. 35,000.00 700.00 0.0010 org Mandor @ Rp. 52,000.00 52.00

JUMLAH ( BELUM PPN ) 10,852.00 75,000.00 85,852.00

6.6 1.0000 bh Pasang engsel pintu 1.0000 bh Engsel pintu @ Rp. 28,000.00 28,000.00 0.1500 org Tukang besi @ Rp. 45,000.00 6,750.00 0.0150 org Kepala tukang besi @ Rp. 55,000.00 825.00 0.0150 org Pekerja @ Rp. 35,000.00 525.00 0.0008 org Mandor @ Rp. 52,000.00 39.00

JUMLAH ( BELUM PPN ) 8,139.00 28,000.00 36,139.00

m2

m3

m3

m3

m2

m1

m1

m1

m3

m2

m2

m1

m2

m2

m3

m1

m1

Page 8: Rab Pos Bii Revisi - Edit

PEKERJAAN CAT-CATAN

SNI 1.0000 Pengecatan tembok BARU (1 lapis cat dasar, 2 lapis cat penutup)6.15 0.1200 kg Cat dasar @ Rp. 55,000.00 6,600.00

0.1800 kg Cat penutup 2 x @ Rp. 60,000.00 10,800.00 0.0420 org Tukang cat @ Rp. 45,000.00 1,890.00 0.0042 org Kepala tukang cat @ Rp. 55,000.00 231.00 0.0280 org Pekerja @ Rp. 35,000.00 980.00 0.0025 org Mandor @ Rp. 52,000.00 130.00

JUMLAH ( BELUM PPN ) 3,231.00 17,400.00 20,631.00

SNI 1.0000 Pengecatan plafon baru (1 lapis alkali, 1 lapis cat dasar, 2 lapis cat penutup)6.14 0.1000 kg Alkali @ Rp. 25,000 2,500.00

0.1000 kg Cat dasar weathershield @ Rp. 55,000 5,500.00 0.2600 kg Cat penutup 2 x @ Rp. 60,000 15,600.00 0.0630 org Tukang cat @ Rp. 45,000.00 2,835.00 0.0063 org Kepala tukang cat @ Rp. 55,000.00 346.50 0.0200 org Pekerja @ Rp. 35,000.00 700.00 0.0025 org Mandor @ Rp. 52,000.00 130.00

JUMLAH ( BELUM PPN ) 4,011.50 23,600.00 27,611.50

SNI 1.0000 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup6.8 0.2000 kg Cat meni @ Rp. 11,000.00 2,200.00

0.1500 kg Plamir @ Rp. 11,000.00 1,650.00 0.1700 kg Cat dasar @ Rp. 30,000.00 5,100.00 0.2600 kg Cat penutup @ Rp. 30,000.00 7,800.00 0.0900 org Tukang cat @ Rp. 45,000.00 4,050.00 0.0060 org Kepala tukang cat @ Rp. 55,000.00 330.00 0.0700 org Pekerja @ Rp. 35,000.00 2,450.00 0.0025 org Mandor @ Rp. 52,000.00 130.00

JUMLAH ( BELUM PPN ) 6,960.00 16,750.00 23,710.00

SNI 1.0000 Pengecatan bidang kayu dengan Residu6.8 0.2000 kg Cat Residu @ Rp. 5,500.00 1,100.00

0.0900 org Tukang cat @ Rp. 45,000.00 4,050.00 0.0060 org Kepala tukang cat @ Rp. 55,000.00 330.00 0.0700 org Pekerja @ Rp. 35,000.00 2,450.00 0.0025 org Mandor @ Rp. 52,000.00 130.00

JUMLAH ( BELUM PPN ) 6,960.00 1,100.00 8,060.00

m2

m2

m2

m2