laporan bulanan maret 2014 pu ditjen air

85
Laporan Bulan Maret 2014 i

Upload: bembie83

Post on 21-Dec-2015

247 views

Category:

Documents


43 download

DESCRIPTION

pu

TRANSCRIPT

Laporan Bulan Maret 2014 i

Laporan Bulan Maret 2014 ii

DAFTAR ISI

BAB 1 PENDAHULUAN ..............................................................................................................1

1.1. Outline proyek JUFMP/JEDI....................................................................................................1

1.2. Outline Pengawasan Kontruksi JUFMP ..................................................................................3

1.2.1. Pengawasan Pekerjaan ....................................................................................................3

1.2.2. Pengelolaan Proyek Secara Umum.................................................................................4

1.2.3. Pengelolaan Terhadap Lingkungan ................................................................................4

1.2.4. Rencana Pemukiman Kembali (RPK) ............................................................................4

1.2.5. Ganti - Rugi /Mekanisme Penanganan Keluhan (MPK) ................................................5

1.2.6. Hal lain ...........................................................................................................................5

1.3. Umum .......................................................................................................................................5

BAB 2 OUTLINE PELAYANAN KONSULTASI ......................................................................7

2.1. Kontrak Pelayanan Konsultasi ..................................................................................................7

2.2. Organisasi Proyek ...................................................................................................................10

BAB 3 CATATAN KEGIATAN KONSULTAN.......................................................................14

3.1. Hal – Hal Utama Rapat ..........................................................................................................14

3.2. Kegiatan Kontraktor dan Konsultan Paket 1 Ciliwung – Gunung Sahari dan Waduk Melati 18

3.2.1. Kegiatan Kontraktor selama bulan Maret 2014 ............................................................18

3.2.4. Masalah ........................................................................................................................19

3.2.5. Laporan Progres Finansial Paket 1 ...............................................................................22

3.3. Adhi Karya, Hutama Karya-Jaya Konstruksi-Jv Paket 2A Cengkareng Floodway ................23

3.3.1. Umum ...........................................................................................................................24

3.3.2. Laporan Progres Finansial Paket 2A ...........................................................................25

3.4. Catatan Kegiatan Harian pada paket 2B .................................................................................27

3.4.1. Supervisor Lapangan ....................................................................................................27

3.4.2. Surveyor .......................................................................................................................28

2.4.3. Enumerator ...................................................................................................................29

3.3.4. Lokasi Kontruksi Harian ..............................................................................................29

3.4.5. Laporan .........................................................................................................................33

3.4.6. Kegiatan Kontraktor : ...................................................................................................33

3.4.7. Perkembangan Kontraktor ............................................................................................33

3.4.8. Notulen Rapat ...............................................................................................................35

3.5. Paket 3 Proyek JUFMP/JEDI .................................................................................................41

i

Laporan Bulan Maret 2014 iii

3.5.1. Umum ...........................................................................................................................41

3.5.2. Progres Kegiatan Kontruksi (Paket 3) ..........................................................................41

3.5.3. Kegiatan Anggota Konsultan sampai bulan Maret 2014 ..............................................41

3.6. Penggunaan Tenaga Kerja Bulanan Pegawai/Man-month......................................................42

3.7. Mobilisasi ...............................................................................................................................44

3.8. Laporan ...................................................................................................................................45

3.9. Biaya Pelayanan Konsultasi ....................................................................................................45

3.10 Status Saat ini dan Rencana Konsultan dalam Pengawasan Kontruksi ..................................48

3.10.1. Pendirian Kantor Pusat Konsultan Dan Kantor Lapangan ..........................................48

3.10.2. Mobilisasi Personil Konsultan. .....................................................................................48

BAB 4 KEGIATAN PROYEK ...................................................................................................50

4.1. Umum .....................................................................................................................................50

4.1.1. Sub Proyek DPU-DKI ..................................................................................................50

4.1.2. BBWS Ciliwung-Cisadane Sub Project .......................................................................52

4.1.3. BBWS Ciliwung – Cisadane ........................................................................................53

4.1.4. Sub Proyek Cipta Karya ...............................................................................................54

4.1.5. Ringkasan Perkembangan Pengerukan pada Proyek JUFMP/JEDI ............................55

4.2. Laporan Pelaksanaan Tugas : Spesialis LARAP/RP ..............................................................58

4.2.1. Pelaksanaan Rencana Pemukiman Kembali .................................................................58

4.2.2. Foto di lokasi Waduk Sunter Utara ..............................................................................61

4.3. Pelaksanaan system Keluhan Ganti Rugi / Mekanisme Pelaksanaan Penanganan Keluhan ..68

4.4. Mekanisme Keluhan Ganti Rugi/ Spesialis Penanganan Keluhan ..........................................80

ii

Laporan Bulan Maret 2014 1

BAB 1

PENDAHULUAN

1.1. Outline proyek JUFMP/JEDI

Jakarta adalah adalah pusat kota di Indonesia. Jakarta menjadi sarana komersial utama

di Indonesia dan menyumbangkan sekitar 25% GDP non-minyak Indonesia (GDP

non-minyak diperkirakan sekitar US$571 milyar pada tahun 2009). Urbanisasi daerah

telah berkontribusi menjadikan Jakarta sebagai satu diantara wilayah metropolitan

terbesar di dunia. Daerah Khusus Ibu Kota Jakarta (DKI Jakarta)1

memiliki luas

wilayah sekitar 650 km2

dengan berpenduduk sekitar 9,6 juta pada tahun 2010,

sementara itu penduduk Jabodetabek2 (dengan luas wilayah sekitar 7300 km

2) 27,9

juta3. Rata-rata pertumbuhan penduduk jauh diatas rata-rata nasional dan diperkirakan

lebih dari 35 juta jiwa pada tahun 2020. Diperkirakan Migran desa-kota mencapai

250.000 yang akan pindah ke Jakarta setiap tahunnya, menyumbangkan peningkatan

pemukiman informal (pemukiman liar). Pertumbuhan yang sangat cepat dan

perkembangan pelayanan umum yang tidak memadai menjadi masalah serius yang

menyebabkan banjir terjadi selama bertahun-tahun

Infrastruktur Pengelolaan Banjir di Jakarta. Jabodetabek dikelilingi oleh beberapa

gunung berapi aktif yang lerengnya membentuk Daerah Aliran dari 13 sungai besar

yang mengalir melalui Jakarta ke Laut Jawa. Musim hujan dimulai pada akhir

November dan berakhir pada awal April. Jakarta berada di wilayah basin terendah.

Empat puluh persen wilayah Jakarta berada di bawah permukaan laut, termasuk

sebagian besar Jakarta Utara, yang terancam penurunan tanah yang sangat parah.

Prinsip dasar pengelolaan banjir di Jakarta adalah untuk mengalihkan aliran dari

wilayah hulu sekitar pusat kota, langsung mengalir ke Jakarta Timur dan Jakarta Barat

melalui dua kanal banjir utama yang bermuara ke Teluk Jakarta. Sistem drainase

makro di kota terdiri dari 13 sungai dan sejumlah saluran drainase. Sistem drainase

makro dibagi menjadi beberapa sub sistem yang dilengkapi dengan pintu air. Di

wilayah dataran rendah terdapat polder, yaitu sistem proteksi yang memanfaatkan

waduk retensi/ resapan pada wilayah terendah dan mengatur volume air yang berlebih

dengan memompa keluar sistem. Namun, semula sistem pengelolaan banjir yang

direncanakan masih tidak lengkap dan tidak berfungsi sebagai sistem yang

terintegrasi. Kanal Banjir Timur baru saja selesai dibangun, tetapi belum berfungsi

sepenuhnya. Selain itu, kanal timur-barat belum terhubung dengan sistem pengalihan

terintegrasi, yang akan menjadikan pengelolaan dan kontrol air hujan lebih baik.

Kondisi sistem yang buruk, pelaksanaan operasi dan pemeliharaan yang rendah

(Operation & Maintenance / O&M) dan hasil pengelolaan drainase setempat yang

tidak memadai dengan cepat air hujan menggenang selama musim hujan.

1 Jakarta merupakan provinsi dengan status khusus sebagai ibu kota Indonesia, disebut DKI Jakarta (Daerah Khusus Ibu Kota

Jakarta). 2 Wilayah ini termasuk DKI Jakarta dan wilayah sekitarnya yang terdiri dari Bogor, Depok, Tangerang dan Bekasi (disingkat

„Jabodetabek‟) 3 Lebih dari dua kali lipat penduduk tahun 1980 yang berjumlah 11,9 juta jiwa.

Laporan Bulan Maret 2014 2

Bencana Banjir di Jakarta. Bencana banjir terjadi bertahun-tahun dan bertambah

parah di beberapa wilayah selama dekade terakhir. Banjir pada Januari 1996, Februari

2002, dan Februari 2007 khusus yang terparah. Peristiwa banjir pada Februari 2007

seluas 235 km2

(sekitar 36%) wilayah kota, kedalaman air sampai tujuh meter di

beberapa wilayah. Peristiwa ini merugikan lebih dari 2,6 juta jiwa dan memaksa

340.000 jiwa mengungsi. Lebih dari 70 jiwa meninggal dan lebih dari 200.000 orang

terjangkit penyakit. Kerugian keuangan dan ekonomi ditaksir berjumlah US$900 juta4.

Banjir terus terjadi pada saat musim hujan. Pada tahun 2008, banjir menutup jalan tol

bandara, lebih dari 1000 penerbangan batal dan menyebabkan kerusakan yang serius

untuk kota Jakarta. Bencana banjir pada tahun 2009 juga terjadi dengan intensitas

yang tinggi dan berlanjut pada tahun 2010, yang menjadi tahun tanpa musim kering

karena efek La Nina.

Penyebab banjir di Jakarta. Urbanisasi secara keseluruhan menjadi penyebab utama

banjir di Jakarta. Hal ini memicu kemerosotan di beberapa faktor utama. Gangguan

atau perubahan DAS (Daerah Aliran Sungai) penting menyebabkan limpasan/ luapan

air hujan meningkat dan kurangnya retensi/ resapan air hujan di kota dan DAS di hulu.

Populasi yang bertambah dan pengelolaan limbah padat yang tidak memadai

menyebabkan kanal limbah/ selokan dan banjir kanal tersumbat, diperburuk dengan

pemeliharaan yang tidak memadai dapat memperlemah struktur dan membentuk

sedimen. Beberapa kanal berfungsi kurang dari sepertiga kapasitas aslinya. Penurunan

tanah terus meningkat dengan keadaan yang sangat mengkhawatirkan, yang

disebabkan oleh pengambilan air tanah dalam secara intensif. Kajian terbaru

menemukan rata-rata penurunan tanah 7,5 sampai 10 cm setahun. Penurunan tanah di

area Jakarta Utara berkisar rata-rata 15-25 cm setahun, jika berlanjut, akan

mengakibatkan tanah tersebut tenggelam 4 - 5 m di bawah permukaan laut di tahun

2025. Penurunan tanah mengakibatkan wilayah tersebut rawan banjir karena kapasitas

gravitasi berkurang untuk air mengalir ke laut dan risiko banjir pasang meningkat.

Faktor lainnya digabungkan dengan pengaruh peningkatan perubahan iklim pada

permukaan laut dan peningkatan frekuensi dan intensitas curah hujan mengakibatkan

banjir bertambah parah. Bencana banjir di Jakarta diperkirakan lebih sering terjadi

pada tahun mendatang, dengan pergeseran dari proses alami yang dulunya lambat

dengan frekuensi rendah ke proses berfrekuensi tinggi yang mengakibatkan perubahan

sosial ekonomi yang sangat parah.

Institusi Pengelola Banjir di Jakarta. Tanggung jawab perkembangan dan pengelolaan

infrastruktur banjir di Jakarta dibagi menjadi dua, institusi pemerintah pusat dan

Pemerintah Provinsi DKI Jakarta (DKI) yaitu; Balai Besar Wilayah Sungai Ciliwung –

Cisadane (BBWSCC)5

dibawah Direktorat Jenderal Sumber Daya Air (Directorate

General of Water Resource / DGWR) Kementerian Pekerjaan Umum (Ministry of

Public Works / MoPW); Direktoral Jenderal Cipta Karya Kementerian Pekerjaan

Umum (Directorate General of Human Settlements / DGCK); dan DKI, melalui

4 Sumber Bappenas (Badan Perencanaan Pembangunan Nasional).

5 Badan pengelolaan DAS untutk sungai Ciliwung dan Cisadane, yang merupakan institusi Pemerintah Pusat yang berperan

sebagai badan yang mengatur DAS.

Laporan Bulan Maret 2014 3

kantor Dinas Pekerjaan Umum Provinsi (DPU-DKI)6, bertanggung jawab untuk

menjaga DAS, banjir kanal dan wilayah resapan.

1.2. Outline Pengawasan Kontruksi JUFMP

Ringkasan Kegiatan Utama. Konsultan akan menjalankan kegiatan berikut ini untuk

mencapai tujuan di atas:

1.2.1. Pengawasan Pekerjaan

Memeriksa / mengecek kontrak akhir dengan para kontraktor.

Memeriksa / mengecek Detail Desain dan Gambar Tehnik, metode pelaksanaaan,

spesifikasi, dan jadwal kegiatan, melaksanakan survei tambahan dan investigasi yang

dibutuhkan, serta mengadakan revisi yang dianggap penting untuk mendapatkan

persetujuan oleh CPIU dan PIU terkait.

Mengawasi dan memonitor semua bagian uji laboratorium dari setiap lokasi proyek

oleh kontraktor terhadap material berbahaya sebelum pengerukan. Setelah

penyelesaian kegiatan proyek pembuangan di CDF Ancol, setelah itu mengadakan uji

sample di area Ancol CDF untuk memastikan material yang berbahaya.

Mengawasi dan memonitor semua bagian uji laboratorium dari setiap lokasi proyek

oleh kontraktor terhadap material berbahaya sebelum pengerukan. Setelah

penyelesaian kegiatan proyek pembuangan di CDF Ancol, mengadakan uji sample di

area CDF Ancol untuk memastikan material yang berbahaya.

Mengawasi pelaksanaan proyek, termasuk (tetapi tidak terbatas pada):

Pengerukan (termasuk pemisahan limbah padat dari material galian serta angkutan

dan pembuangan di Tempat Pembuangan Akhir / TPA dan Ancol CDF), tanggul

dan perbaikan kanal, pompa, perbaikan dan pemeliharaan saringan banjir.

Memberikan bantuan kepada PIU untuk proses tagihan pembayaran yang dibuat

oleh para kontraktor dan prosedur pencairan pinjaman serta persiapan Rencana

Kerja Tahunan (Annual Work Plan/ AWP) dan prediksi pencairan pinjaman yang

dibutuhkan.

Mengelola catatan lapangan dan mempersiapkan laporan perkembangan bulanan.

Mempersiapkan pekerjaan seperti gambar dan catatan (record) yang dijalankan,

dan manual operasi dan serah terima pekerjaan yang telah selesai kepada PIU dan

CPIU.

Mempersiapkan Practical Completion and Outstanding Defects Report untuk

setiap kontrak konstruksi yang diawasi.

Mempersiapkan Final Completion and Handover Report untuk setiap kontrak

konstruksi yang diawasi.

Mengawasi dan memonitor kegiatan konstruksi (termasuk menginspeksi kualitas,

6 Dan selanjutnya didukung oleh sub dinas (atau sub departemen di tingkat kotamadya). Secara administrasi, DKI Jakarta

dibagi menjadi lima kotamadya (yaitu, Jakarta Utara, Jakarta Selatan, Jakarta Barat, Jakarta Timur dan Jakarta Pusat) dan

satu wilayah (yaitu, Kepulauan Seribu, yang merupakan kelompok kepulauan kecil yang terletak di Laut Jawa).

Laporan Bulan Maret 2014 4

standar, dan kelengkapan fasilitas yang terbatas) di site Ancol CDF selama pelaksanaan

proyek dan di semua lokasi off-site (di luar lapangan) seperti lokasi sumber pasir dan

tanah laterit yang digunakan untuk pekerjaan reklamasi.

Memberikan bantuan teknis yang diperlukan CPIU dan PIU dari waktu ke waktu. Ini

mungkin termasuk penyediaan dukungan dan saran kepada pihak CPIU mengenai

pelaksanaan pekerjaan proyek, terutama pada aspek teknis, perencanaan keseluruhan,

pengelolaan finansial dan pengadaan Proyek.

1.2.2. Pengelolaan Proyek Secara Umum

Menganjurkan dan membantu CPMU , CPIU dan PIU dengan perencanaan dan

pelaksanaan pada semua komponen dari program JUFMP, memantau dan melaporkan

kemajuan mereka terhadap target pelaksanaan yang disepakati. Membantu

pengelolaan JUFMP dengan mengidentifikasi, mengevaluasi dan mengembangkan

metode dan prosedur yang efisien, efektif dan memenuhi praktik implementasi yang

baik. Membantu CPMU, CPIU dan PIU dengan perencanaan, pengelolaan dan

pengendalian pelaksanaan kegiatan untuk memastikan keberhasilan tujuan program.

Mendukung kerjasama antara CPMU, CPIU dan PIU. Menyediakan bantuan teknis

CPMU , CPIU dan PIU dalam pengelolaan keuangan dan pengadaan laporan proyek,

dan kemajuan proyek lainnya, melaporkan bahwa CPMU, CPIU dan PIU diwajibkan

untuk menyerahkan kepada pihak berwenang atau Bank Dunia . Ini akan mencakup,

tetapi tidak terbatas pada Rencana Kerja Tahunan, Laporan Pemantauan Keuangan (

FMRs ), Rencana Pengadaan dan Laporan, dan pemantauan Proyek dan Laporan

Kemajuan pada setiap PIU , CPIU dan CPMU.

1.2.3. Pengelolaan Terhadap Lingkungan

Memantau dan mengawasi secara konsisten tindakan perlindungan terhadap

lingkungan yang dilakukan untuk mengurangi kerusakan lingkungan akibat kegiatan

konstruksi di lokasi proyek dan di lokasi CDF Ancol. Sesuai dengan :

Pengelolaan Lingkungan dan Rencana Pemantauan ( RKL / RPL ) dari tiap lokasi

kerja serta RKL / RPL Tambahan Laporan (jika ada)

Pengelolaan Lingkungan dan Sosial Framework ( ESMF ) dari Proyek dan

ketentuan lain yang ditetapkan dalam Kontrak Konstruksi.

1.2.4. Rencana Pemukiman Kembali (RPK)

Mengawasi dan mendukung pelaksanaan Rencana Pemukiman Kembali ( RPK ),

sesuai dengan :

Pembebasan Lahan dan Rencana Aksi Pemukiman Kembali

(LARAP) dari masing-masing tempat kerja di mana pemukiman kembali masih

diperlukan.

Kerangka Kebijakan Pemukiman (RPF) dari Proyek.

Memberikan bantuan teknis dan administrasi dalam pembebasan lahan dan proses

Rencana Pembangunan Pemukiman Kembali (RPK).

Laporan Bulan Maret 2014 5

1.2.5. Ganti - Rugi /Mekanisme Penanganan Keluhan (MPK)

- Mengembangkan dan mengoperasikan Mekanisme Penanganan Keluhan yang akan

mencakup namun tidak terbatas pada pemberian keluhan dari Warga Terkena

Proyek (WTP) dengan cara sistematis pada hari ke hari;

- Memperbarui pengaduan yang berada pada website, menginformasikan mereka

tentang status keluhan mereka serta memberikan umpan balik atau tindak lanjut;

- Membantu DKI dalam tindak lanjut atas keluhan yang diterima, memastikan bahwa

keputusan dibuat secara transparan, adil, proses yang independen, dan akuntabel

melalui Sistem Penanganan Keluhan atau Penasehat Penanganan Keluhan.

- Memberikan rekomendasi kepada pihak DKI yang berwenang pada status keluhan,

melalui proses dari masing –masing unit lokasi langsung di tingkat provinsi.

- Memonitor dan melaporkan setiap kegiatan yang terkait di lokasi proyek.

Desain, mengembangkan, dan mengoperasikan sistem laporan proyek komunikasi

berbasis web

1.2.6. Hal lain

Memantau laporan dari berbagai aktivitas dilokasi proyek terkait. Desain

pengembangan dan pengoperasian komunikasi laporan berbasis web.

1.3. Umum

Lokasi Proyek

Laporan Bulan Maret 2014 6

Persetujuan Pinjaman : 8121 ID

Bentuk Pinjaman dari JUFMP sebagai berikut:

Instansi Pelaksana : Direktorat Jenderal Sumber Daya Air,

Kementerian Pekerjaan Umum

Tanggal Masuk Peminjaman: 17 Februari 2012

Tanggal Efektif : 90 HARI SETELAH Penandatanganan

Pinjaman

Tanggal Penutupan : 31 Maret 2017

Jumlah Pinjaman : $ 139.640.000 Dollar

Kategori Pinjaman :

Kategori

Jumlah Pinjaman

Di alokasikan

(dinyatakan dalam

Dollar)

Presentase pengeluaran

yang akan dibiayai

(1) Pengerjaan Proyek

Tahap 1

(1)(a) Pengerjaan Proyek

Tahap 1 untuk proyek

Ditjen. SDA

42.400.000

80%

(1)(b) Pengerjaan Proyek

Tahap 1 untuk proyek

DGHS

17.800.000 80%

(1)(c) Pengerjaan Proyek

Tahap 1 untuk proyek

DKI

69.340.000 67%

(2) Jasa Konsultan, Barang dan

Jasa dan non Konsultasi

dibawah bagian 2 (a) dan

bagian 2 (e) dari sebuah

Proyek.

10.100.000 100%

TOTAL AMOUNT 139.640.000

Laporan Bulan Maret 2014 7

BAB 2

OUTLINE PELAYANAN KONSULTASI

2.1. Kontrak Pelayanan Konsultasi

Laporan Bulan Maret 2014 8

Laporan Bulan Maret 2014 9

Laporan Bulan Maret 2014 10

2.2. Organisasi Proyek

Figure 1 Struktur Organisasi

Table 1 Unit Pengelolaan Proyek Utama/ Central Project Management Unit (CPMU)

No. Tim Official Unit Pengelola (CPMU) – JUFMP Kedudukan dalam Tim

1. Direktur Jenderal Sumber Daya Air Ketua

2. Direktur Pengairan dan Irigasi, Bappenas Wakil Ketua

Merangkap Anggota

3. Direktur Bina Program, Direktorat Jenderal Sumber Daya Air Anggota

4. Direktur Permukiman Perumahan, Bappenas Anggota

5. Direktur Pendanaan Multi Lateral, Bappenas Anggota

6. Kepala Badan Perencanaan Pembangunan, DKI Jakarta Anggota

7. Asisten Pembangunan Sekretaris Daerah, DKI Jakarta Anggota

8. Kepala Biro Administrasi Prasarana Kota, DKI Jakarta Anggota

9. Kepala Biro Perencanaan dan Kerjasama Luar Negeri, PU Anggota

10. Direktur Bina Program, Direktorat Jenderal Cipta Karya Anggota

11. Kepala Sub Direktorat Kelembagaan Infrastruktur Sumber Daya Air,

Bappenas Anggota

Laporan Bulan Maret 2014 11

12. Kepala Sub Direktorat Kerjasama Luar Negeri, Direktorat Bina

Program, Direktorat Jenderal Sumber Daya Air Anggota

13. Kepala Sub Direktorat Program dan Anggaran, Direktorat Bina

Program, Direktorat Jenderal Sumber Daya Air Anggota

14. Kepala Bagian Kerjasama Luar Negeri, Biro Perencanaan dan

Kerjasama Luar Negeri, Sekretariat Jenderal, PU Anggota

15. Kepala Sub Direktorat Kerjasama Luar Negeri, Direktorat Bina

Program, Direktorat Jenderal Cipta Karya Anggota

16. Kepala Bidang Program dan Perencanaan Umum, Balai Besar Wilayah

Sungai Ciliwung Cisadane, Direktorat Jenderal Sumber Daya Air Anggota

17. Kepala Sub Bagian Kerjasama Multi Lateral, Biro Perencanaan dan

Kerjasama Multi Lateral, Sekretariat Jenderal, PU Anggota

18. Kepala Seksi Kerjasama Multi Lateral, Sub Direktorat Kerjasama Luar

Negeri, Direktorat Bina Program, Direktorat Jenderal Sumber Daya Air

19. Kepala Seksi Multi Lateral Kerjasama Luar Negeri, Direktorat Bina

Program, Direktorat Jenderal Cipta Karya Anggota

20. Pejabat Fungsional Perencana Pertama, Bappenas Anggota

Table 2 Unit Pelaksanaan Proyek Utama / Central Project Implementation Unit (CPIU)

No. Tim Official Implementation Unit (CPIU)-JUFMP Kedudukan

dalam Tim

1. Direktur Sungai dan Pantai, Direktorat Jenderal Sumber Daya Air Ketua

2. Kepala Sub Direktorat Wilayah II, Direktorat Sungai dan Pantai Merangkap

Anggota

3. Kepala Balai Besar Wilayah Sungai Ciliwung-Cisadane, Direktorat Jenderal

Sumber Daya Air Anggota

4. Direktur Pengembangan Penyehatan Lingkungan Pemukiman, Direktorat

Jenderal Cipta Karya Anggota

5. Kepala Dinas Pekerjaan Umum, DKI Jakarta Anggota

6. Kepala Bidang Pengelolaan Sumber Daya Air, Dinas Pekerjaan Umum, DKI

Jakarta Anggota

7. Kepala Sub Direktorat Pengembangan Drainase, Direktorat Pengembangan

Penyehatan Lingkungan Pemukiman, Direktorat Jenderal Cipta Karya Anggota

8. Kepala Sub Direktorat Perencanaan Teknis, Direktorat Pengembangan

Penyehatn Lingkungan Pemukiman, Direktorat Jenderal Cipta Karya Anggota

9. Kepala Sub Direktorat Perencanaan Teknis, Direktorat Sungai dan Pantai,

Direktorat Jenderal Sumber Daya Air Anggota

10. Kepala Bidang Pelaksanaan, Balai Besar Wilayah Sungai Ciliwung-Cisadane Anggota

11. Kepala Seksi Bimbingan Perencanaan Teknis Sungai dan Pantai, Direktorat

Sungai dan Pantai Anggota

12. Kepala Seksi Pengendalian Pelaksanaan Sungai dan Pantai, Direktorat Sungai

dan Pantai Anggota

13. Kepala Seksi Perencanaan, Subdit Perencanaan Teknis, Dit.Pengembangan

Penyehatan Lingkungan Permukiman Anggota

14. Kepala Seksi Wilayah II, Dit. Subdit Perencanaan Teknis, Dit. Pengembangan

penyehatan Lingkungan Permukiman Anggota

15. Kepala Seksi PJSA, Balai Besar Wilayah Sungai Ciliwung-Cisadane Anggota

Laporan Bulan Maret 2014 12

Table 3 Tim Sekretariat Unit Pelaksanaan Proyek Utama/Central Project Implementation Unit

(CPIU)

No. Nama/Jabatan/Unit Kerja Kedudukan dalam Tim

1. Ir. Ferdinand Pakpahan, ME Koordinator

2. Kepala Bidang Pelaksanaan, Balai Besar Wilayah Sungai Ciliwung-

Cisadane

Sekretaris merangkap

Anggota

3.

Kepala Seksi Drainase Wilayah 1 Direktorat Pengembangan

Penyehatan Lingkungan Pemukiman, Direktorat Jenderal Cipta

Karya

Anggota

4. Kepala Seksi Perencanaan Tata Air Dinas Pekerjaan Umum, DKI

Jakarta Anggota

5. Kepala Seksi PJSA Balai Besar Wilayah Sungai Ciliwung-Cisadane Anggota

6. Nila Aliefia, ST,MT Anggota

7. Marojohan Lumban Gaol, ST Anggota

8. Veronica Agustina, SE Anggota

2.3 Organisasi Pelaksana Proyek Utama /Organization of Project Implementing Unit

(PIUs)

Berikut ini daftar anggota Unit Pelaksana Proyek yang telah memberikan laporan

Table 4 Unit Pelaksana Proyek (PIUs) of JUFMP

No. Sub-

proyek

Nama FPMO

Ketua

Kepala Unit Kerja

(Satker)

Petugas Pembuat

Komitmen

(PPK)

1. Paket 1 DKI Jakarta Dr. Ir. Rudi

Siahaan Ir. Robert Ir. Robert

2. Paket 2A BBWS

Ciliwung-

Cisadane

Ir. Imam Santosa

Dipl.HE Ir. Parno Ir. Abbor

3. Paket 2B BBWS

Ciliwung-

Cisadane

Ir. Iskandar Ir. Parno Ir. Abbor

4. Paket 3 Direktorat

PLP

Ditjen Cipta

Karya

Ir. Djoko Mursito

Dipl. SE, MM. Ir. Pong Sipularang

Moh. Firman, ST,

MT

Laporan Bulan Maret 2014 13

Gambar 2 Struktur Organisasi Of JUFMP/JEDI

Laporan Bulan Maret 2014 14

BAB 3

CATATAN KEGIATAN KONSULTAN

3.1. Hal – Hal Utama Rapat

Laporan Bulan Maret 2014 15

Laporan Bulan Maret 2014 16

Laporan Bulan Maret 2014 17

Laporan Bulan Maret 2014 18

3.2. Kegiatan Kontraktor dan Konsultan Paket 1 Ciliwung – Gunung Sahari dan

Waduk Melati

3.2.1. Kegiatan Kontraktor selama bulan Maret 2014

3.2.1.1. Ciliwung – Gunung Sahari.

1. Persiapan kerja seperti contoh :

- Akses jalan sementara

- Peninjauan pengelolaan lingkungan

- Laporan akhir tes uji tanah termasuk hasil tes laboratorium

- Tempat pembuangan sementara

2. Pengerukan dan pembuangan material

3. Pengadaan tiang pancang beton pra-tekan bergelombang W-450

- Pengadaan tiang pancang beton pra-tekan bergelombang W-450 L 12 m = 0 btg

- Pengadaan tiang pancang beton pra-tekan bergelombang W450 L 14 m = 6545.10 m

- Pengadaan tiang pancang beton pra-tekan bergelombang W-450 L 17 m = 306 m

- Pengadaan tiang pancang beton 40x40 = 700 m

4. Pemancangan tiang pancang beton pra-tekan bergelombang W-450

- Pemancangan tiang pancang beton pra-tekan bergelombang W-450 L = 12 = 768 m

- Pemancangan tiang pancang beton pra-tekan bergelombang W-450 L = 14 = 9618m

- Pemancangan tiang pancang beton pra-tekan bergelombang W-450 L = 17 = 612 m

5. Pembongkaran dan Pembuangan beton dan pasangan batu yang masih ada

3.2.1.2. Waduk Melati

1. Persiapan kerja sebagai contoh.

- Akses jalan sementara

- Peninjauan pengelolaan lingkungan

- Laporan akhir tes uji tanah termasuk hasil tes laboratorium

- Tempat pembuangan sementara

2. Pengerukan dan pembuangan material

3.2.2. Perkembangan Kontraktor

A. Perkembangan hingga 31 Maret 2014

Rencana : 10,081 %

Progres : 8,610 %

Deviasi : -1,471 %

3.2.3. Kegiatan Konsultan Hingga 31 Maret 2014

1. Pengecekan pemancangan tiang pancang beton W-450 pra-penekanan

bergelombang dan pengawasan pekerjaan pemancangan.

2. Pengecekan Shop drawing dan mutual check paket 1 Ciliwung – Gunung

Sahari dan Waduk Melati

3. Pengecekan dan perkembangan laporan tiap minggu

4. Mengecek hasil survey data topografis dan bergabung dalam survey topogrfis

5. Kunjungan ke lokasi pabrik Tiang pancang di pabrik Adimix Beton di

Cibitung

Laporan Bulan Maret 2014 19

6. Kunjungan ke lokasi uji pembengkokan di serpong dan uji beton

7. Koordinasi rapat dengan PIU dan kontraktor setiap minggu

8. Pengawasan uji coba pengerukan di Waduk Melati dan Ciliwung – Gunung

Sahari dengan pipa penyedot

3.2.4. Masalah

- Hingga sekarang (akhir maret 2014) kontraktor belum memulai pemancangan di

Waduk Melati, dikarenakan kontraktor harus menyelesaikan permasalahan

administrrasi dari JHS, yang memproduksi batang pancang yang berasal dari JHT

karena ketidakpuasan permintaan yang diminta oleh PIU.

- Utilitas PJU dan kabel PLN di Ciliwung – Gunung Sahari STA : 0 + 700

Laporan Bulan Maret 2014 20

Laporan Bulan Maret 2014 21

Laporan Bulan Maret 2014 22

3.2.5. Laporan Progres Finansial Paket 1

Laporan Bulan Maret 2014 23

3.3. Adhi Karya, Hutama Karya-Jaya Konstruksi-Jv Paket 2A Cengkareng Floodway

PANJANG DREDGING 540m + 7840m = 8380m

Sta 7+800

Sta 6+750

Sta 5+000

Sta 3+750

Sta 4+500

Sta 5+875

SHEET PILE 2,100 m

Pekerjaan Hydro- mechanical

SHEET PILE 2,500 m

W325, B 1000, L 14 M

DGWR-CILCIS

PACKAGE 2A

Pekerjaan Hydro-mechanical

540 m KE ARAH LAUT SUDAH DIKERJAKAN

Laporan Bulan Maret 2014 24

3.3.1. Umum

Nama Proyek : ICB Package No. JUFMP-2, Cengkareng Floodway Sub Project,

Jakarta Emergency Dredging Initiative / Jakarta Urgent Flood

Mitigation Project

No. Kontrak : HK.02.03/PPKSP-SNVT PJSACC/XI/315.3

Kontraktor : PT. Adhi Karya-Hutama Karya-Jaya Konstruksi-Joint Venture

Nilai Kontrak : Rp.. 209,808,000,000.00 (Sudah termasuk pajak 10%)

PIU : Satuan Kerja Balai Besar Wilayah Sungai Ciliwung Cisadane,

Direktorat Jenderal Sumber Daya Air , Kementerian Pekerjaan Umum.

3.3.1.1. Progres Kegiatan Kontruksi Paket 2A

A. Kegiatan Kontraktor hingga bulan Maret 2014

1. Melaksanakan Persiapan Pekerjaan

- Peralatan pemancangan sebanyak 2 set pancang dan jasa mobilisasi mesin derek

- Persiapan MC-0 dan shop drawing

2. Melaksanakan uji tes tanah

- Tes Penetrasi Dutch Cone

- Tes Penetrasi Standar

3. Pengadaan Material CCSP W 325 – 14 m

4. Pengerukan Sta : 3+350 hingga Sta : 2+650

3.2.1.2. Progres kontraktor

B. Perkembangan hingga 31 Maret 2014

Rencana : 7,958 %

Progress : 29,450 %

Deviasi : 21,492 %

Piling Works

- CCSP W325 – 14 M = 899 batang

- Pancang persegi = 10 m = 164 batang

12 m = 50 batang

- Pengerukan = 12.005 Mᶾ

- Earthwork/Pemindahan = 8.200 Mᶾ

Material berupa tanah

3.2.2. Kegiatan anggota Konsultan hingga Maret 2014

- 4 Maret : Kunjungan ke lokasi Dinas Pertamanan bersama kontraktor dan

Konsultan

- 7 Maret : Rapat di Kantor Adhi Karya untuk mendiskusikan MCO, detail

gambar dan hasil perkembangan;

- 14 Maret : Percobaan campuran K-300 di Universitas Trisakti pada Paket

2A selama 28 hari

- 14 Maret : Percobaan Pengerukan di lokasi CDF Ancol pada Paket 2A

Laporan Bulan Maret 2014 25

3.3.2. Laporan Progres Finansial Paket 2A

RINGKASAN PEKERJAAN KONTRUKSI DAN PROGRES PENGERUKAN (hingga akhir Maret 2014)

PAKET

KONTRAK PROGRES PEKERJAAN

FINANSIAL PROGRES WAKTU TENGGANG %

TANGGAL

DITANDA

TANGANI

UNTUK

DITERUSKAN PERIODE RENCANA PROGRES DEVIASI KONTRAK PENGELUARAN PRESENTASE

(DAYS)

(HARI)

PAKET 2A

11

NOVEMBER

2013

11

NOVEMBER

2013

730 7.958 29.450 21.492 209,808,000,000 59,601,682,000

148

CENGKARENG

FLOODWAY

JAKARTA URGENT FLOOD MITIGATION PROJECT (JUFMP)

RINGKASAN FINANCIAL REPORT/FISCAL BULAN MARET 2014

PAKET

KONTRAK/ TANGGAL

KONTRAK

PERIODE WAKTU

PERKEMBANGAN PENGELUARAN KETERANGAN DIPA 2013 KONTRAK TENGGANG

(HARI) (HARI)

FISIK FINANSIAL Dec-13 TOTAL

(%) (%)

2A 209,808,000,000

11-Nov-13 730 148 29.450 21.656 59,601,682,000 59,601,682,000

59,610,000,000

Laporan Bulan Maret 2014 26

JAKARTA URGENT FLOOD MITIGATION PROJECT (JUFMP)

JAKARTA EMERGENCY DREDGING INITIATIVE (JEDI) PACKAGE-2A : Ciliwung Gunung Sahari and Waduk Melati

DAILY CONSTRUCTION PHOTOGRAPHS

Day/Date : Maret 2014 Prepared by: Mulyani S

Sheetpile Paket 2A Backpile Paket 2A

Alat berat, Pemancang

Sheetpile Paket 2A

Kunjungan dengan Dinas Pertamanan DKI

Sheetpile Paket 2A

27

3.4. Catatan Kegiatan Harian pada paket 2B

3.4.1. Supervisor Lapangan

Day Date Description of work

Saturday 01 – 03 – 2014 Standby

Sunday 02 – 03 – 2014 Standby

Monday 03 – 03 – 2014 Diskusi dengan Kontraktor dan Direksi masalah pemancangan mini pile serta

ketersediaan lahan untuk dinding banjir

Tuesday 04 – 03 – 2014

Diskusi dengan Kontraktor dan Direksi masalah pemancangan mini pile serta

ketersediaan lahan untuk dinding banjir, dilanjutkan diskusi ke Hang Jebat

(Co TL) dan TL

Wednesday 05 – 03 – 2014 Preliminary justifikasi teknis, menghitung analisa stabilitas berbagai

penampang

Thursday 06 – 03 – 2014 Diskusi dengan kontraktor bersama Co TL tentang masalah expose ke CPIU.

Dilanjutkan dengan penyiapan materi pertemuan bersama Kontraktor

Friday 07 – 03 – 2014 Membuat laporan laporan reguler. Dilanjutkan ke Hang Jebat dan ke

Kementerian PU untuk rapat bersama CPIU (Ferdinan Pakpahan)

Saturday 08 – 03 – 2014 Standby

Sunday 09 – 03 – 2014 Standby

Monday 10 – 03 – 2014 Meneruskan membuat jastifikasi teknis, analisi stabilitas. Mengunjungi CDF

Ancol untuk melihat kesiapan di lokasi

Tuesday 11 – 03 – 2014 Finalisasi laporan Jastifikasi Teknis. Kunjungan lapangan ke CDF mengantar

staff CPIU (Pak Ronni)

Wednesday 12 – 03 – 2014

Diskusi kecil dan meninjau persiapan Kontraktor untuk memulai pekerjaan

dredging. Mengunjungi persiapan Kontraktor dalam menyelesaikan Base

camp

Thursday 13 – 03 – 2014 Diskusi kecil dengan Kontraktor mengenai masalah MC0. Ke lapangan

melihat kesiapan pekerjaan pengerukan

Friday 14 – 03 – 2014 Ke Hang Jebat bersama Kontraktor, mendiskusikan masalah Gambar

Konstruksi, untuk pengerukan dan parapet/dinding beton

Saturday 15 – 03 – 2014 Standby

Sunday 16 – 03 – 2014 Standby

Monday 17 – 03 – 2014 Inspeksi bersama Kontraktor untuk memastikan alinyemen dan ketersediaan

ruang untuk pemancangan tiang pancang mini

Tuesday 18 – 03 – 2014 Membuat laporan reguler. Ke lapangan sta +6+700 pekerjaan penegerukan

Wednesday 19 – 03 – 2014 Rapat Koordinasi dengan Kontraktor di Hang Jebat tentang organisasi di

CDF. Dilanjutkan dengan asistensi gambar kerja paket 2B ke Team Leader

Thursday 20 – 03 – 2014 Membuat laporan reguler. Ke lapangan periksa penandaan untuk persiapan

pemancangan tiang pancang mini

Friday 21 – 03 – 2014 Ke lapangan bersama Geodetic engineering, memeriksa kedalaman galian di

Sta 6+700 s/d 6+750

Saturday 22 – 03 – 2014 Membuat laporan laporan rutin (Persiapan laporan bulanan, dsb)

Sunday 23 – 03 – 2014 Standby

Monday 24 – 03 – 2014

Ke lapangan, check pemancangan tiang pancang mini. Sosialisai dengan

kepala Desa Rawa Badak Utara sehubungan dengan akan dimulainya

pekerjaan penggalian endapan diwilayah itu

Tuesday 25 – 03 – 2014

Diskusi kecil dengan Complain handling, MIS dan FS untuk CDF Ancol.

Dilanjutkan ke kantor Kontraktor HK untuk mendiskusikan masalah sosial

dan GPS tracker

Wednesday 26 – 03 – 2014 Membuat laporan laporan reguler. Rapat mingguan di Kantor Kontraktor PT

HUTAMA KARYA

Thursday 27 – 03 – 2014

Membuat laporan laporan rutin. Kunjungan ke lapangan lokasi pemancangan

STA 7+225 dan lokasi penggalian lumpur STA 6+800 - STA 6+911

(Jembatan Kodamar)

Friday 28 – 03 – 2014

Membuat laporan laporan reguler. Ke kantor Pusat di Jl Hang Jebat untuk

menjemput Geodetic Engineer lalu cek kedalaman penggalian lumpur di STA

6+800 - STA 6+911

Saturday 29 – 03 – 2014 Standby

Sunday 30 – 03 – 2014 Standby

Monday 31 – 03 - 2014 Libur Nasional

28

3.4.2. Surveyor

Hari Tanggal Deskripsi Pekerjaan

Saturday 01 – 03 – 2014 Standby

Sunday 02 – 03 – 2014 Standby

Monday 03 – 03 – 2014 Berdiskusi dengan koontraktor mengenai pemancang dan ketersediaan lahan di area

kantor kontraktor

Tuesday 04 – 03 – 2014 Berdikusi dengan kontraktor mengenai pemancang dan ketersediaan lahan di kantor

kontraktor utuk didiskusikan dengan TL dan Co. TL di Hang Jebat

Wednesday 05 – 03 – 2014 Membuat hasil laporan analisisi kalkulasi hasil keseimbangan pada masing-masing

paket

Thursday 06 – 03 – 2014 Rapat Kordinasi kegiatan dengan Konsultan dan Kontraktor PT H.K di ruang Rapat

kantor PT. H.K

Friday 07 – 03 – 2014 Menuju lapangan untuk melihat perkembangan Direktur keet dan persiapan lokasi

pemancang

Saturday 08 – 03 – 2014 Standby

Sunday 09 – 03 – 2014 Standby

Monday 10 – 03 – 2014 Kunjungan ke Ancol untuk melihat Lokasi CDF dengan Dewan Direksi BBWS dan

kontraktor PT PJA

Tuesday 11 – 03 – 2014 Kunjungan ke Ancol untuk melihat lokasi CDF Ancol dengan Staff Bpk. Ronny dari

CPIU

Wednesday 12 – 03 – 2014 Menuju Kantor PT. HK mengenai kordinasi kegiatan tentang Pengukuran Muara Sungai

Thursday 13 – 03 – 2014 Menuju kantor PT.HK kodinasi kegiatan mengenai MC-0 dan Lokasi pancang

Friday 14 – 03 – 2014

Menuju Kantor KECC, kordinasi kegiatan mengenai MC-0 dengan Konsultan dan

Kontraktor

Menuju lokasi Proyek didepan Kodamar (uji coba pengangkutan dan pembuangan

lumpur ke CDF Ancol) jam 22.00 – 04.00 dengan Kontraktor dan Dewan Direksi

BBWS Ciliwung -Cisadane

Saturday 15 – 03 – 2014

Menuju lokasi proyek di depan kodamar (( STA 6 + 950 - STA 7 + 250) pancang dari

titik patok cross section dan STA 6 + 400 - STA 6 + 900 untuk pemasangan patok acuan

pengerukan.

Uji coba pengangkutan dan pembuangan lumpur menuju CDF Ancol pada pukul 22.00 –

04.00 dengan kontraktor dan Dewan Direksi BBWS Ciliwung - Cisadane

Sunday 16 – 03 – 2014 Standby

Monday 17 – 03 – 2014

Menuju lokasi survey dinding penahan didepan Mal Artha Gading

Menuju lokasi Proyek di depan Kodamar ( uji coba pengangkutan dan pembuangan

lumpur menuju CDF Ancol ) pada pukul 22.00 – 04.00 dengan kontraktor dan Dewan

Direksi BBWS Ciliwung - Cisadane

Tuesday 18 – 03 – 2014 Membuat laporan harian pengerukan Paket 2B

Wednesday 19 – 03 – 2014 Membuat laporan kegiatan harian dan lokasi pancang pada STA 7 + 200

Thursday 20 – 03 – 2014 Menuju lokasi proyek PT. HK dan membuat Laporan harian pengerukan

Friday 21 – 03 – 2014 Menuju ke lapangan untuk meninjau dan mengukur level peningkatan lapisan sungai

penampang pada STA 6 + 800 - STA 6 + 911

Saturday 22 – 03 – 2014 Standby

Sunday 23 – 03 – 2014 Standby

Monday 24 – 03 – 2014

Menuju ke lapangan untuk meninjau dan mengukur level peningkatan dasar sungai

penampang pada STA 6 + 800 - STA 6 + 911 dan meninjau pancang dari tiang pancang

mini STA 7 + 250

Tuesday 25 – 03 – 2014

Menuju ke lapangan untuk meninjau dan mengukur level peningkatan lapisan sungai

penampang pada STA 6 + 800 - STA 6 + 911 dan meninjau pancang dari tiang pancang

mini STA 7 + 250

Wednesday 26 – 03 – 2014 Menuju Kantor PT. HK dalam kegiatan rapat mingguan pada Paket 2B Lower Sunter

Floodway

Thursday 27 – 03 – 2014 Menuju lapangan untuk meninju pekerjaan pengerukan Sungai pada STA 6 + 800 - STA

6 dan meninjau pemancang dari tiang pancang mini STA 7 + 250

Friday 28 – 03 – 2014 Menuju Hang Jebat membawa laporan, ke STA 6 + 800 - STA 6 + 911 melaksanakan

pengecekan ulang pada peningkatan bed level

Saturday 29 – 03 – 2014 Standby

Sunday 30 – 03 – 2014 Standby

Monday 31 – 03 - 2014 Standby

29

2.4.3. Enumerator

Day Date Description of work

Saturday 01 – 03 – 2014 Standby

Sunday 02 – 03 – 2014 Standby

Monday 03 – 03 – 2014 Membantu Supervisor lapangan dalam pengetikan laporan

Tuesday 04 – 03 – 2014 Membantu Supervisor lapangan dalam pengetikan laporan

Wednesday 05 – 03 – 2014 Membantu Supervisor lapangan dalam pengetikan laporan

Thursday 06 – 03 – 2014 Membantu Supervisor lapangan dalam pengetikan laporan

Friday 07 – 03 – 2014 Membantu Supervisor lapangan dalam pengetikan laporan

Saturday 08 – 03 – 2014 Standby

Sunday 09 – 03 – 2014 Standby

Monday 10 – 03 – 2014 Membantu Supervisor lapangan dalam pengetikan laporan

Tuesday 11 – 03 – 2014 Membantu Supervisor lapangan dalam pengetikan laporan

Wednesday 12 – 03 – 2014 Membantu Supervisor lapangan dalam pengetikan laporan

Thursday 13 – 03 – 2014 Membantu Supervisor lapangan dalam pengetikan laporan

Friday 14 – 03 – 2014 Membantu Supervisor lapangan dalam pengetikan laporan

Saturday 15 – 03 – 2014 Standby

Sunday 16 – 03 – 2014 Standby

Monday 17 – 03 – 2014 Meninjau pekerjaan pengangkutan dan pembuangan lumpur di lokasi proyek.

Tuesday 18 – 03 – 2014 Meninjau pekerjaan pengangkutan dan pembuangan lumpur di lokasi proyek.

Wednesday 19 – 03 – 2014 Meninjau pekerjaan pengangkutan dan pembuangan lumpur di lokasi proyek.

Thursday 20 – 03 – 2014 Meninjau pekerjaan pengangkutan dan pembuangan lumpur di lokasi proyek.

Friday 21 – 03 – 2014 Meninjau pekerjaan pengangkutan dan pembuangan lumpur di lokasi proyek.

Saturday 22 – 03 – 2014 Standby

Sunday 23 – 03 – 2014 Standby

Monday 24 – 03 – 2014 Meninjau pekerjaan pengangkutan dan pembuangan lumpur di lokasi proyek.

Tuesday 25 – 03 – 2014 Meninjau pekerjaan pengangkutan dan pembuangan lumpur di lokasi proyek.

Wednesday 26 – 03 – 2014 Meninjau pekerjaan pengangkutan dan pembuangan lumpur di lokasi proyek.

Thursday 27 – 03 – 2014 Meninjau pekerjaan pengangkutan dan pembuangan lumpur di lokasi proyek.

Friday 28 – 03 – 2014 Meninjau pekerjaan pengangkutan dan pembuangan lumpur di lokasi proyek.

Saturday 29 – 03 – 2014 Standby

Sunday 30 – 03 – 2014 Standby

Monday 31 – 03 - 2014 Libur Nasional

3.3.4. Lokasi Kontruksi Harian

Hal Umum

- Persiapan Pekerjan

- Akses jalan Sementara

- Temporary Cofferdam dengan Dewatering

- Uji Tes Lingkungan

- Pengawasan dan Pengelolaan Lingkungan

- Tempat Pembuangan Sementara

- Pelacak Kendaran dengan perangkat GPS (Sistem Monitoring) +server

- Sewa Jembatan Timbang

Pekerjaan Pengerukan :

- Pengerukan dan Pembuangan Tipe A

Earthworks / Pekerjaan Pemindahan Material berupa tanah :

- Sewa peralatan di area pembuangan

Pekerjaan Pemancangan:

- Pengadaan tiang pancang beton 20 x 20 x 400 cm

- Pemancangan tiang pancang beton 20 x 20 x 400 cm

30

3.4.5. DOKUMEN LAPORAN

Kegiatan di lapangan pada paket 2B adalah pemancangan di Lower Sunter Floodway

letaknya di Yos Sudarso Kodamar dari STA 7 + 255 hingga ke hulu sebelah kiri.

Kegiatan di lapangan dapat dilihat pada gambar :

Lokasi pemancang pada STA 7 + 255. Penarikan pancang dari tiang pancang mini

oleh mekanik pancang

Proses pemancangan tiang pancang Proses pemancangan tiang pancang

mini mini

Proses pemancangan dari tiang Proses pemancangan dari tiang

pancang mini pancang mini

Kegiatan di lapangan pada paket 2B adalah uji coba pembuangan dan pengerukan

menuju CDF Ancol pada pukul 10.00 malam – 05.00 pagi di Lower Sunter Floodway

dari STA 6 + 800 hingga STA 6 + 911 di sisi sebelah kiri. Kegiatan di lapangan dapat di

lihat pada gambar :

31

Uji coba pengerukan menuju CDF Ancol Uji coba pengerukan menuju CDF Ancol

Uji coba pengerukan menuju CDF Ancol Uji coba pengerukan menuju CDF Ancol

Uji coba pengerukan menuju CDF Ancol Uji coba pengerukan menuju CDF Ancol

32

Kegiatan di lapangan pada paket 2B adalah pengukuran bagian lintasan pada peningkatan

level lapisan di Lower Sunter Floodway dari STA 6 + 800 hingga STA 6 + 911 di bagian

sisi sebelah kiri. Kegiatan di lapangan dapat dilihat pada gambar dibawah ini :

Pengecekan pengukuran pada cross Pengecekan pengukuran pada cross section

section

Pengecekan pengukuran pada cross Pengecekan pengukuran pada cross section

section

33

3.4.5. Laporan

A. Laporan Mingguan :

Perkembangan mingguan hingga akhir Maret 2014

No. Bill Pokok Pekerjaan

Perkembangan %

Minggu ke 1

3 – 9

Minggu ke 2

10 – 16

Minggu ke 3

17 – 23

Minggu ke 4

24 – 31

1 Hal umum 0,285 0,285 0,285 0,285

2 Pekerjaan Pengerukan 2,818 2,818 2,818 2,818

3 Earthworks 0,014 0,014 0,014 0,014

4 Pekerjaan Beton 0 0 0 0

5 Pekerjaan Pemancangan 0,051 0,051 0,051 0,051

6 Pekerjaan Hidromekanikal 0 0 0 0

7 Pekerjaan lain-lain 0 0 0 0

T o t a l 3,169 3,169 3,169 3,169

Rencana 1,560 1,560 1,560 1,560

Deviasi 1,609 1,609 1,609 1,609

B. Laporan Bulanan :

Progres Bulanan hinggaakhir Maret 2014

No. Jenis Pekerjaan Schedule

( %)

Actual

( %) Deviasi

1 Hal umum 2,638 4,057 1,419

2 Pekerjaan Pengerukan 6,191 4,259 1,932

3 Earthworks 0,287 0,014 -0,274

4 Pekerjaan Pembetonan 0 0 0

5 Pekerjaan Pemancangan 0 9.724 9.724

6 Pekerjaan Hidromekanikal 0 0 0

7 Pekerjaan lain-lain 0 0 0

T o t a l 9,117 18,054 8,937

3.4.6. Kegiatan Kontraktor :

Kegiatan kontraktor selama bulan Maret 2014 :

I. Hal Umum :

a. Persiapan Pekerjaan

b. Akses Jalan Sementara

c. Temporary cofferdam dengan Dewatering

d. Uji Lingkungan

e. Pengawasan dan pengelolaan lingkungan

f. Tempat Pembuangan Sementara

g. Kendaran berpelacak dengan perangkat (Sistem Pengawasan) + Server GPS

h. Sewa Jembatan Timbang

II. Pekerjaan Pengerukan:

1. Pengerukan dan Pembuangan Tipe A

III. Pekerjan Pemancangan :

1. Pengadaan tiang pancang beton 20 x 20 x 400 cm

2. Pemancangan tiang pancang beton 20 x 20 x 400 cm

3.4.7. Perkembangan Kontraktor

1. Perkembangan hingga 03 Maret 2014 sampai 30 Maret 2014 (Maret 2014)

34

Rencana : 9,117 %

Progres : 18,054 %

Deviasi : 8,937 %

Hal Umum :

- Persiapan Pekerjaan

- Akses Jalan Sementara

- Temporary cofferdam dengan Dewatering

- Uji Lingkungan

- Pengawasan dan pengelolaan lingkungan

- Tempat Pembuangan Sementara

- Kendaran berpelacak dengan perangkat (Sistem Pengawasan) + Server GPS

- Sewa Jembatan Timbang

Pekerjaan Pengerukan :

- Pengerukan dan Pembuangan Tipe A

Earthworks :

- Sewa Peralatan di area Pembuangan

Pekerjaan Pemancangan :

- Pengadaan Pancang beton 20 x 20 x 400 cm

- Pemancangan tiang pancang beton 20 x 20 x 400 cm

35

3.4.8. Notulen Rapat

a. Notulen Rapat :

Tanggal Tempat Perihal

Kamis, 06

Maret 2014

Kantor HK - Rapat koordinasi /solusi Konsultan dari MC-0

Jum‟at, 07

Maret, 2014

Ruang

rapat

kantor

CPIU

- Tambahan biaya pada paket 2B yaitu Lower Sunter

Floodway Under Jakarta Urgent Flood Mitigation

Project (JUFMP) / Jakarta Emergency Dredging

Initiative (JEDI)

b. Daftar Petunjuk:

Tanggal Perihal

Kamis, 06

Maret 2014

- Shop Drawing.

- Penelitian ke lokasi, dan membandingkan volume kontrak per 25 m

dalam bentuk tabel .

- Menjumlahkan volume MC-0, membandingkan dengan volume

kontrak

- Pengecekan ulang secara teracak MC-0 yang dilakukan oleh

kontraktor dan konsultan didukung dengan pengambilan secara

terukur dan sesuai.

- Addendum Plan./ Rencana Kontrak Tambahan

- Pengajuan harga pekerjaan yang baru (jika ada).

- Untuk kenaikan harga pada pekerjaan tambahan baru, harus dibatasi

dan batas maksimalnya 15%

Jum‟at, 07

Maret 2014

- Berdasarkan alokasi pinjaman pada paket 2B Lower Sunter

Floodway, maksimum harga pada paket 2B adalah $ 6,50 juta US

dollar atau Rp. 65 milyar rupiah. Biaya tidak boleh melebihi alokasi

pinjaman. Untuk kontrak tambahan sekarang tidak boleh melebiihi

15% dari kontrak saat ini.

- Kontraktor harus menyelesikan shop drawing dan draft kontak

tambahan berdasarkan mutual check 0 (nol)

- Konsultan akan menyiapkan teknik justifikasi pada desain ulang di

lokasi bahwa gambar kontrak asli tidak bisa dilaksanakan sesuai

dengan kondisi lingkungan.

- Ikut serta dalam penelitian yang telah dilksanakan oleh PIU,

Kontraktor dan Konsultan, pada pengecekan kondisi lokasi dalam

menjalankan gambar kontrak asli.

- Negosiasi antara PIU BBWS Ciliwung Cisadane dan Kontraktor PT

HUTAMA KARYA penting guna penambahan pembayaran barang

walau tidak disebutkan dalam kontrak asli.

- Itu telah diinformasikan selama rapat bahwa CDF Ancol sudah siap

menerima material dari lokasi proyek JUFMP. Konsultan akan

memobilisasi enumerator dalam minggu ini secepat dan sesegera

mungkin.

- Minggu ini kontraktor akan memulai uji coba pengangkutan material

pengerukan dari Lower Sunnter Floodway.

40

JAKARTA URGENT FLOOD MITIGATION PROJECT (JUFMP)

RINGKASAN PEKERJAAN SIPIL DAN PROGRES PENGERUKAN

(Hingga Akhir Maret 2014)

PAKET

Kontrak Progres Pekerjaan (%) Progres Finansial

(Juta Rp.) Waktu

yang

digunakan

(Hari)

Tanggal

Ditanda

Tangani

Untuk

diteruskan

Period

(hari) Rencana

Perkemb

angan

Devia

si Kontrak Pembayaran

Presen

tase

Paket 2B -

Lower Sunter

Floodway

11

November

2013

11

November

2013

730 9,117 18,054 8,937 65.258.477.

570

13.620.882.

000

13,42

0 141

JAKARTA URGENT FLOOD MITIGATION PROJECT (JUFMP)

RINGKASAN LAPORAN FINANSIAL / KEUANGAN BULAN MARET 2014

(Hingga akhir Maret 2014)

Paket Kontrak / DIPA

2013

Tanggal

kontrak

Periode

Kontrak

(hari)

Batas

Waktu

(hari)

Progres Pembayaran

Ket Fisik

(%)

Finansial

(%)

Maret

2014 Total

Paket 2B -

Lower

Sunter

Floodway

65.258.477.570,00 11

November

2013

730 141 18,054 13,420

13.620.8

82.000,0

0

13.620.

882.000

,00

13.620.882.000,00

41

3.5. Paket 3 Proyek JUFMP/JEDI

3.5.1. Umum

Nama Proyek : Paket ICB No. JUFMP-3, Sub Proyek Cideng Thamrin Drain, Jakarta

Emergency Dredging Initiative / Jakarta Urgent Flood Mitigation Project

No. Kontrak. : HK.02.03/JUFMP-FSK/XI/1

Kontraktor : PT. Dutaraya Dinametro,

Jl. Raya Setu No. 17 Setu, Cipayung – Jakarta Timur 13880

Nilai Kontrak : Rp. 48,747,011,000.00 (sudah termasuk pajak 10%)

PIU : Satuan Kerja Pengembangan Penyehatan Lingkungan Permukiman

Jabodetabek Direktorat Pengembangan Penyehatan Lingkungan Pemukiman,

Direktorat Jenderal Cipta Karya, Kementerian Pekerjaan Umum.

3.5.2. Progres Kegiatan Kontruksi (Paket 3)

3.5.2.1. Kegiatan Kontraktor Selama bulan Maret 2014

1. Melaksanakan Persiapan Pekerjaan

a. Menyiapkan Mobilisasi Perlengkapan

b. Menyiapkan MC-0 dan Shop Drawing/detail gambar pekerjaan

2. Melaksanakan Investigasi tanah

a. Tes Penetrasi Dutch cone/ DCPT

b. Tes Penetrasi Standar / SPT

3. Pengadaan material CCSP W 325 - 14 m

4. Uji coba pemancangan tiang pancang

3.5.2.2. Perkembangan Kontraktor

a. Progres hingga 20 Maret 2014

Rencana : 6,400 %

Progress : 11,349 %

Deviasi : 4,959 %

Pekerjaan Pemancangan

a. CCSP W325 - 14 M : 15 batang

3.5.3. Kegiatan Anggota Konsultan sampai bulan Maret 2014

a. 5 Maret : Rapat dengan PIU (Cipta Karya ) di Lokasi Kantor Kontraktor

b. 06 Maret : Kordinasi PIU (Cipta Karya) Kantor Resmi

c. 25 Maret : Rapat singkat di kantor Polisi Daerah (POLDA METRO JAYA )

d. 27 Maret : Rapat koordinasi di PIU ( Cipta Karya) Kantor Resmi dengan PIU,

Konsultan, dan Kontraktor

e. 28 Maret , Uji coba Pemancangan tiang pancang dari ketiga paket

42

3.6. Penggunaan Tenaga Kerja Bulanan Pegawai/Man-month

Penggunaan Tenaga Kerja Bulanan /Pegawai/Man-month

Per 31 Maret 2014

No Nama Jabatan Tanggal

Mobilisasi

Kontra

k

Penggun

aan

Tenaga

Kerja/bu

lan

Saldo

A Internasional Expert:

1 Cheong Byeong Ho Team Leader 20 Nov

2013 60 4,37 55,63

B Nasional Expert:

B.1 Bagian Perlengkapan dan

Pengawasan Pekerjaan

1 Bambang Sigit Suryono Co Team Leader 18 Nov

2013 60 4,43 55,57

2 Hana Effendi Complaint Handling

Specialist 06 Jan 2014 12 2,83 9,17

3 B. Hendarbowo Geodetic Engineer 27 Jan 2014 7 2,13 4,87

4 Isti Cahya Suci Murwati Complaint Handling

Specialist 20 Jan 2014 12 1,83 10,17

5 M. Rafiek Sidik Larap / RP Spesialist 16 Des 2013 6 3,50 2,50

6 Salam Triono Geotechnical Engineer 18 Nov

2013 3 2,43 0,57

7 Sutjahjo Complaint Handling

Specialist 3 Feb 2014 12 1,87 10,13

8 Tjik Mail MIS and Website

Specialist

18 Nov

2013 18 4,43 13,57

B.2 Bagian Perlengkapan

Pendukung CPIU

1 Ahmad Syahroni Budget and Programing to

CPIU 02 Jan 2013 10 2,97 7,03

2 Teguh Ungsiadi Procurement 10 Feb 2013 10 1,40 8,60

B.3 Provision for Field

Supervision

1 Asnawi Marzuki Supervisor lapangan 18 Nov

2013 60 4,43 55,57

2 Asril Syaer Supervisor lapangan 18 Nov

2013 60 4,43 55,57

3 Bambang Supriyanto Supervisor lapangan 25 Nov

2013 60 4,20 55,80

4 Kusnadi Bachrudin Supervisor lapangan 18 Nov

2013 60 4,43 55,57

5 Mangara Siburian Supervisor lapangan 04 Des 2013 60 3,90 56,10

6 Wahyu Husodo Supervisor lapangan 22 Nov

2013 60 4,30 55,70

7 Syamsul Bahri Supervisor lapangan 4 Feb 2014 60 1,80 58,20

8 Fathoni Afriantara Supervisor lapangan 10 Feb 2014 60 1,40 58,60

9 Zurfa Joni Supervisor lapangan

18 Nov

2013 1,7 1,70 0,00

Amiruddin Supervisor lapangan 10 Feb 2014 58,3 1,40 56,90

43

10 Pradityo A B Supervisor lapangan 17 Maret

2014 60 0,47 59,53

C Surveyor:

1 Benny Eka S Surveyor 18 Nov

2013 36 4,43 31,57

2 Imam Mahmudi Surveyor 26 Nov

2013 36 1,17 34,83

3 Mahfuzd Surveyor 18 Nov

2013 36 4,43 31,57

4 Santoso Surveyor 09 Des 2013 36 3,73 32,27

5 Zaki Mubarrak Surveyor 09 Des 2013 36 3,73 32,27

D Enumerator:

1 Adhy Kurnia Enumerator 09 Des 2013 36 3,73 32,27

2 Adi Muamar Enumerator 09 Des 2013 36 3,73 32,27

3 Mulyani S Enumerator 18 Nov

2013 36 4,43 31,57

4 Sudarto Enumerator 18 Nov

2013 36 4,43 31,57

5 Sulaiman Enumerator 09 Des 2013 36 3,73 32,27

6 Fajar Riyanto Enumerator 17 Feb 2013 36 1,47 34,53

7 Eddo Yandara Enumerator 12 Feb 2013 36 1,63 34,37

8 Deni Aditia Enumerator 12 Feb 2013 36 1,63 34,37

9 Iqbal Fathoni Enumerator

01 Des 2013 1,67 1,67 0,00

10 Muhammad Ikbal 12 Feb 2013 34,33 1,63 32,70

11 Junus Adrianus Giri Enumerator 17 Maret

2014 36,00 0,47 35,53

12 Hendry Brata Wijaya Enumerator 24 Maret

2014 36,00 0,23 35,77

D Supporting Staff:

1 Mohammad Fahmi, SE., MM.

Office Manager

25 Nov

2013 3,1 3,10 0,00

Budi Sumartoyo 24 Feb 2014 56,9 1,23 55,67

2 Drs. Sofyan Moezir Accounting Staff 18 Nov

2013 60 4,43 55,57

3 TB. Rizky Rachmadian, A.Md. Operator Computer 18 Nov

2013 60 4,43 55,57

4 Heri Purnomo Operator Computer 18-Feb-13 60 1,43 58,57

5 Ifnu Muhardhi Operator Computer 3-Mar-14 60 0,93 59,07

6 Fauziah Eddyono

Secretary 02 Des 2013 3.17 3,17 0,00

Diah Kurniati 17-Mar-14 56.83 0,47 56,37

7 Jaka Ambara Office Boy 18 Nov

2013 60 4,43 55,57

8 Anwar Driver 25 Nov

2013 60 4,20 55,80

9 Asep Suhendar Driver 16 Des 2013 60 3,50 56,50

10 Karyadi Driver 18 Nov

2013 60 4,43 55,57

11 Nanang Suhiman Driver 20 Jan 2013 60 2,37 57,63

12 Subandi Driver 18 Nov

2013 60 4,43 55,57

13 Supriyatna Driver 18 Nov

2013 60 4,43 55,57

14 Yudi Driver 16 Des 2013 60 3,50 56,50

44

3.7. Mobilisasi

No Nama Posisi Tanggal Mobilisasi

A Internasional Expert:

1 Cheong Byeong Ho Team Leader 20 Nov 2013

B Nasional Expert:

B.1 Bagian Perlengkapan dan

Pengawasan Pekerjaan

1 Bambang Sigit Suryono Co Team Leader 18 Nov 2013

2 Hana Effendi Spesialis Penanganan Keluhan 06 Jan 2014

3 B. Hendarbowo Geodetic Engineer 27 Jan 2014

4 Isti Cahya Suci Murwati Spesialis Penanganan Keluhan 20 Jan 2014

5 M. Rafiek Sidik Spesialis Larap / RP 16 Des 2013

6 Salam Triono Engineering Geotechnical 18 Nov 2013

7 Sutjahjo Spesialis Penanganan Keluhan 3 Feb 2014

8 Tjik Mail Specialist MIS dan Website 18 Nov 2013

B.2 Provision of Support to

CPIU

1 Ahmad Syahroni Budget and Programing to

CPIU 02 Jan 2013

2 Teguh Ungsiadi Procurement 10 Feb 2013

B.3 Provision for Field

Supervision

1 Asnawi Marzuki Supervisor lapangan 18 Nov 2013

2 Asril Syaer Supervisor lapangan 18 Nov 2013

3 Bambang Supriyanto Supervisor lapangan 25 Nov 2013

4 Kusnadi Bachrudin Supervisor lapangan 18 Nov 2013

5 Mangara Siburian Supervisor lapangan 04 Des 2013

6 Wahyu Husodo Supervisor lapangan 22 Nov 2013

7 Syamsul Bahri Supervisor lapangan 4 Feb 2014

8 Fathoni Afriantara Supervisor lapangan 10 Feb 2014

9 Zurfa Joni Supervisor lapangan 18 Nov 2013

10 Amiruddin Supervisor lapangan 10 Feb 2014

11 Pradityo A B Supervisor lapangan 17 Maret 2014

Sub Total

C Surveyor:

1 Benny Eka S Surveyor 18 Nov 2013

2 Imam Mahmudi Surveyor 26 Nov 2013

3 Mahfuzd Surveyor 18 Nov 2013

4 Santoso Surveyor 09 Des 2013

5 Zaki Mubarrak Surveyor 09 Des 2013

Sub Total

45

D Enumerator:

1 Adhy Kurnia Enumerator 09 Des 2013

2 Adi Muamar Enumerator 09 Des 2013

3 Mulyani S Enumerator 18 Nov 2013

4 Sudarto Enumerator 18 Nov 2013

5 Sulaiman Enumerator 09 Des 2013

6 Fajar Riyanto Enumerator 17 Feb 2013

7 Eddo Yandara Enumerator 12 Feb 2013

8 Deni Aditia Enumerator 12 Feb 2013

9 Iqbal Fathoni Enumerator 01 Des 2013

10 Muhammad Ikbal Enumerator 12 Feb 2013

11 Junus Adrianus Giri Enumerator 17 Maret 2014

12 Hendry Brata Wijaya Enumerator 24 Maret 2014

D Supporting Staff:

1 Budi Sumartoyo Office Manager 24 Feb 2014

2 Drs. Sofyan Moezir Accounting Staff 18 Nov 2013

3 TB. Rizky Rachmadian, A.Md Operator Computer 18 Nov 2013

4 Heri Purnomo Operator Computer 18 Feb 2014

5 Ifnu Muhardi Operator Computer 3 Mar 14

6 Diah Kurniati Secretary 17 Mar 14

7 Jaka Ambara Office Boy 18 Nov 2013

8 Anwar Driver 25 Nov 2013

9 Asep Suhendar Driver 16 Des 2013

10 Karyadi Driver 18 Nov 2013

11 Nanang Suhiman Driver 20 Jan 2013

12 Subandi Driver 18 Nov 2013

13 Supriyatna Driver 18 Nov 2013

14 Yudi Driver 16 Des 2013

3.8. Laporan

Laporan bulanan pada bulan Maret 2014.

3.9. Biaya Pelayanan Konsultasi

Rincian Kegiatan Pengeluaran.

Kontrak Asli

KOMPONEN

BIAYA

JUMLAH

(Rp & USD)

PEMBAYARAN

AWAL

TOTAL

PENERIMAAN SALDO

TOTAL USD 2.072.400 207.240 207.240 1.865.160

Dan

TOTAL Rp 38.153.170.000 3.815.317.000 3.815.317.000 34.337.853.000

46

Surat Masuk Yang Tercatat Pada Bulan Maret 2014

No. Diterima No. Surat Tanggal Perusahaan Jabatan Nama Perihal diteruskan

1 4/3/2014 PD.006-

SI/28

2 maret

2014

Kementrian

PU

Kepada

Subdiklat

kepada

bidang

teknik dan

materi

Dr.

Sanusi

Sitorue

Permohonan

Penugasan Ir.

Bambang Sigit

Suryono menjadi

pengajar

Bambang

Sigit

2 18 Maret

2014

178/BA-

JEDI.1/TE

K/III/2014

18 maret

2014

PT. Brantas

Adipraya

Kepada

Manager

M.Zainul

Fatah,ST

Undangan

Pelaksanaan uji

Kuat tekan beton

Bambang

Sigit

3 18 Maret

2014

179/BA-

JEDI.1/TE

K/III/2014

18 maret

2014

PT. Brantas

Adipraya

Kepada

Manager

M.Zainul

Fatah,ST

Penajuan Pengadaan

CCSP PT. Adhimix

Precast Indonesia

KECC

tembusan

4 20 maret

2014

2399/1799

21

19 maret

2014

Dinas

kebersihan

DKI

Kepala

dinas

kebersihan

DKI jakarta

Sapta

Ediningt

yas

Kusumad

ewi

Undangan

pengangkutan

sampah hasil proyek

JEDI

Bambang

Sigit

5 27 Maret

2014

189/BAP-

JEDI.1/TE

K/III/2014

26 Maret

2014

PT. Brantas

Adipraya

Kepala

Manager

M.Zainul

Fatah,ST

Permohonan Ijin Ke

Instansi Penerangan

jalan Umum

Bambang

Sigit

6 1-Apr-14 127/07951 24 Maret

2014

Provinsi

DKI Jakarta

Kepala Biro

Prasarana

dan Sarana

Kota

Amtha

Undangan

Monitoring

Pelaksanaan Proyek

JUFMP/JEDI

Bambang

Sigit

7 28 Maret

2014

HL02-

BD/95

28 Maret

2014

Kementrian

PU

Koordinator

JUFMP/JE

DI

Ferdinan

d

Pakpaha

n

Mutual Check 0%

dan Pekerjaan

Tambahan

Bambang

Sigit

8 27 Maret

2014

15/ADHI-

HK-

JAKON

JV

27 Maret

2014

ADHI HK

JAYA

KONSTRU

KSI JV

Proyek

Manager

Syahrudd

in

Proposed

Reinforcement Bar

Dr Cheong

Byong Ho

47

Surat Keluar – Maret 2014

No. No. Surat Tanggal Perusahaan Jabatan Nama Perihal Ditanda tangani

1

61/CSC

JUFMP/JED

I/II/2014

3-Mar-14

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

Mr. Mochammad

Mazid, ST.Sp1

Inception

Report

Team Leader/

Cheong Byoung

Ho

2

62/CSC

JUFMP/JED

I/I/2014

3-Mar-14

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

Mr. Mochammad

Mazid, ST.Sp1

Minutes of

Coordination

Meeting 3

Team Leader/

Cheong Byoung

Ho

3

63/CSC

JUFMP/JED

I/I/2014

3-Mar-14

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

Mr. Mochammad

Mazid, ST.Sp1

Minutes of

Inception

Report

Team Leader/

Cheong Byoung

Ho

4

64/CTC

JUFMP/JED

I/III/2014

19-Mar-

14

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

Mr. Mochammad

Mazid, ST.Sp1

Pemberitahuan

Pembuatan

Pemancang

Team Leader/

Cheong Byoung

Ho

7

068/CTC

JUFMP/JED

I/III/2014-

M2

7 Maret

2014

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

SKPPL

Pemukiman

JABODETABEK

rekomendasi

permohonan

addendum dan

laporan hasil

evaluasi

dokumen

cideng

thamrin

Team Leader/

Cheong Byoung

Ho

8

068/CTC

JUFMP/JED

I/III/2014-

M1

7 Maret

2014

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

SKPPL

Pemukiman

JABODETABEK

recommendati

on for

addendum

request and

report result

cideng

thamrin

Team Leader/

Cheong Byoung

Ho

9

069/CTC

JUFMP/JED

I/III/2014-M

11 Maret

2014

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

Ir.S.M Robert

Rajagukguk

Recommendat

ion for

Implementatio

n of

Socialization

Team Leader/

Cheong Byoung

Ho

10

073/CTC

JUFMP/JED

I/III/2014-M

10 Maret

2014

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

Mr. Mochammad

Mazid, ST.Sp1

Mobilisasi

Hendy Brata

Wijaya, Yunus

Team Leader/

Cheong Byoung

Ho

11

073/CTC

JUFMP/JED

I/III/2014

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

Mr. Mochammad

Mazid, ST.Sp1

Proposed

Memorandum

3 of

Adjutment of

Reimbursable

Expenses

Team Leader/

Cheong Byoung

Ho

12

074/CTC

JUFMP/JED

I/III/2014

20 Maret

2014

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

Mr. Mochammad

Mazid, ST.Sp1

Monthly

Progress

Repport III

Team Leader/

Cheong Byoung

Ho

13

074/CTC

JUFMP/JED

I/III/2014-M

25 Maret

2014

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

Mr. Mochammad

Mazid, ST.Sp1

Monthly

Progress

Repport III

Team Leader/

Cheong Byoung

Ho

074/CTC

JUFMP/JED

I/III/2014-

CL

28 Maret

2014

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

Mr. Mochammad

Mazid, ST.Sp1

Coment letter

Enumerator

Team Leader/

Cheong Byoung

Ho

48

14

075//CTC

JUFMP/JED

I/III/2014

2-Apr-14

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

Mr. Mochammad

Mazid, ST.Sp1

Assigment

letter Rikson

paket 2B

Team Leader/

Cheong Byoung

Ho

15

076/CTC

JUFMP/JED

I/III/2014

2-Apr-14

Kementerian

Pekerjaan

Umum

Pejabat

Pembuat

Komitmen

Mr. Mochammad

Mazid, ST.Sp1

Assigment

letter

Hendrawan

Paket 2B

Team Leader/

Cheong Byoung

Ho

3.10 Status Saat ini dan Rencana Konsultan dalam Pengawasan Kontruksi

3.10.1. Pendirian Kantor Pusat Konsultan Dan Kantor Lapangan

Untuk pengajuan jasa pengawasan Kontruksi pada proyek JUFMP /JEDI,. Konsultan

mendirikan kantor Pusat Konsultan di Jl. Hang Jebat VIII No.1 berdekatan dengan kantor

Direktorat Jenderal Sumber daya Air. Kantor tersebut dilengkapi dengan kebutuhan

perlengkapan kantor, telephone, dan jaringan internet , dll. Untuk mengakomodasi mobilisasi

personil dan fasilitas kegiatan pengawasan kontruksi pada JUFMP / JEDI, dua lokasi kantor

pada paket 2A dan 2B telah selesai dibangun dekat lokasi kontruksi supervisor lapangan,

surveyor dan enumerator untuk enam kontrak paket yang tersisa akan segera dibangun

Pendirian Kantor Pusat dan Kantor lapangan

Klasifikasi Alamat Kantor

Kantor Pusat Jl. Hang Jebat VIII No.1, Jakarta Selatan

Paket 2A Jl. Dahlia Raya No. 1, Jakarta Barat

Paket 2B Jl. Sentosa 2 No. 15, Jakarta Utara

Paket 3 Jl. Pejompongan Benhil, Jakarta Pusat

Konsultan berencana membangun 1 tambahan kantor baru di lokasi CDF Ancol dengan

maksud untuk membantu keefisiensian pengawasan dalam pembuangan material pengerukan

dan pengelolaan area yang seharusnya di jaga.

3.10.2. Mobilisasi Personil Konsultan.

Korea Engineering Consultant Corporation ( KECC ) kerjasama dengan PT. Puser

Bumi Mekon bekerjasama dengan PT. Tetira dan PT. Duta Cipta Mandiri, konsultan

pengawasan konstruksi untuk JUFMP / JEDI mulai memobilisasi staf mereka mulai 18

November 2013 untuk paket kontrak 1, 2A, 2B dan 3. Tahap 1 sudah dipilih dan

dipersiapkan kontrak untuk pekerjaan konstruksi dari masing-masing paket secara terus-

menerus. Pada awalnya Team Leader dan Co - Team Leader, Pengawas Lapangan, Surveyor

dan team pendataan/enumerator dimobilisasi untuk membentuk tim pengawas ahli dan

sekaligus untuk membantu kegiatan sebelum kontruksi untuk masing –masing paket kontrak .

Insinyur Geoteknik dan MIS dan Spesialis website juga telah dimobilisasi untuk memberikan

bantuan teknis dalam mereview desain kontrak dan menyiapkan pengelolaan Sistem

Informasi berbasis web (MIS) pada proyek tersebut. Beberapa staf pendukung dan staff teknik

dimobilisasi untuk membantu para ahli untuk merespon tepat waktu guna persyaratan

pengawasan pelaksanaan proyek, yang pertama spesialis LARAP / RP menangani keluhan

atau nasehat penanganan terhadap keluhan mereka, Penambahan supervisor lapangan,

surveyor, enumerator, dan staf pendukung dimobilisasi secara terus menerus terkait pada

masing-masing kontrak paket. Ringkasan personil Konsultan yang telah dimobilisasi sejauh

ini diringkas pada Tabel 3.2 di bawah ini.

Table.1 Personil Konsultan yang di mobilisasi

49

No Nama Posisi Nomor

1 Internasional Experts Team Leader 1

2 Nasional Experts Co Team Leader dan tenaga Ahli 20

3 Surveyors Untuk paket1, 2A, 2B and 3 5

4 Enumerators Untuk paket 1, 2A, 2B and 3 10

5 Supporting Staff Termasuk Drivers 12

50

BAB 4

KEGIATAN PROYEK

4.1. Umum

Menjelang akhir 4 Februari 2014 (empat) pekerjaan telah ditanda tangani yaitu Paket 1

Ciliwung – Gunung Sahari dan Waduk Melati di bawah pengerjaan PIU DKI Jakarta,

Pekerjaan 2A Saluran banjir cengkareng, dan pekerjaan Paket 2B yang berada di Lower

Sunter Floodway dibawah pengerjaan BBWS Cliwung - Cisadane dan paket 3 Cideng –

Thamrin dibawah pengerjaan PIU Cipta Karya.

4.1.1. Sub Proyek DPU-DKI

Paket 1 Ciliwung-Gunung Sahari dan Waduk Melati

CILIWUNG GUNUNG SAHARI DRAIN

ISTIQLAL MOSQUE

SHEET PILE 4,832 m

Dredging : 153,830 m3

Embankment Repair :4.832 m

PACKAGE 1

LENGTHOF DREDGING

5,100 m

DPU-DKI

51

WADUK MELATI(Inc. Saluran GresikAnd Cideng Hulu)

Waduk Melati

Dredging : 98,240m3

Embankment Repair :1,245 m (sheetpiles)

530 m (Collector Drain)130 (Embakment Repair)

SHEET PILE 1,245 m

PACKAGE 1

LENGTHOF DREDGING

1,260 m

LENGTHOF DREDGING

2,004 m

AREAOF DREDGING

4.9 ha

DPU-DKI

a. Kontrak Perjanjian

Surat Persetujuan : No.JUFMP

Lembar Pengesahan : No. 14705/-7.793.2

Kontrak Perjanjian : No. JUFMP 1

52

4.1.2. BBWS Ciliwung-Cisadane Sub Project

Package 2A Cengkareng Floodway

a. Kontrak Perjanjian

Surat Persetujuan : No. JUFMP 2A

Surat Pengesahan/LOA : No.KU.03.01/PPK SP-SNVT PJSA CC/XI/310.1

No. Kontrak. : No.HK.02.03/PPKSP-SNVT PJSA

tanggal 11 November 2013

b. Perkembangan Kegiatan Kontruksi selama bulan Maret 2014

Umum

Nama Proyek : ICB Paket No. JUFMP-2, Sub Proyek Cengkareng Floodway, Jakarta

Emergency Dredging Initiative / Jakarta Urgent Flood Mitigation Project

No. Kontrak : HK.02.03/PPKSP-SNVT PJSACC/XI/315.3

Kontractor : PT. Adhi Karya-Hutama Karya-Jaya Konstruksi-Mitra Kerjasama

Nilai Kontrak : Rp.. 209,808,000,000.00 (sudah termasuk Pajak 10%)

PIU : Satuan Kerja Balai Besar Wilayah Sungai Ciliwung Cisadane, Direktorat

Jenderal Sumber Daya Air , Kementerian Pekerjaan Umum.

CENGKARENGFLOODWAY

Sta 7+800

Sta 6+750

Sta 5+000

Sta 3+750

Dredging : 1,202,990 m3

Embankment Repair :4.600 m

SHEET PILE 2,500 m

SHEET PILE 2,100 m

DGWR-CILCIS

PACKAGE 2A

LENGTHOF DREDGING

8,380 m

53

4.1.3. BBWS Ciliwung – Cisadane

Paket 2B Lower Sunter Floodway

a. Kontrak Persetujuan

1) Surat Persetujuan : No. JUFMP – 2B

2) Surat Pengesahan/LOA : No. KU.03.01/PPKSP.SNVT PJSA.CC/X/302.14

3) No. Kontrak. : HK.02.03/PPKSP-SNVT PJSACC/XI/315.4

Tanggal 11 November 2013

b. Perkembangan Kegiatan Kontruksi pada bulan Maret 2014

Umum

Nama Proyek : ICB Package Nomor JUFMP-2B, Dredging and Embankment of

Lower Sunter Floodway Sub Project, Jakarta Urgent Flood Mitigation

Project / Jakarta Emergency Dredging Initiative (International Bank

For Reconstruction and Development No. 8121-ID)

No Kontrak : HK.02.03/PPKSP-SNVT PJSACC/XI/315.4

Kontractor : PT.Hutama Karya (Persero)

Nilai Kontrak : Rp.65.258.477.570,00 (sudah termasuk pajak 10%)

PIU : Balai Besar Wilayah Sungai Ciliwung Cisadane

Direktorat Jenderal Sumber Daya Air

Kementerian Pekerjaan Umum.

54

Perkembangan Kegiatan Kontruksi pada Paket 2B

Perkembangan Kontraktor

Perkembangan hingga 28 Maret 2014

Rencana : 5,358 %

Progres : 14,009 %

Deviasi : 8,651 %

4.1.4. Sub Proyek Cipta Karya

Paket 3 Cideng – Thamrin Drain

a. Kontrak Perjanjian

Surat Persetujuan : ICB PACKAGE No. JUFMP - 3

Surat Pengesahan/ LOA : No. KU.03.01/JUFMP/01/XI/2013

No. Kontrak. : HK.02.03/JUFMP-FSK/XI/1

Tanggal 15 November 2013

b. Perkembangan Kegiatan Kontruksi selama bulan Maret 2014

Umum

Nama Proyek : Paket ICB No. JUFMP-3, Sub Proyek Cideng Thamrin Drain, Jakarta

Emergency Dredging Initiative / Jakarta Urgent Flood Mitigation

Project

CIPTA KARYA

Dredging : 31,420 m3

Embankment Repair :2,570 m

SHEET PILE 2,570 m

CIDENG THAMRIN DRAIN

LENGTHOF DREDGING

3,330 m

Reinforced Concrete Block

EXISTING

SHEETPILES

NEWSHEETPILES

PACKAGE 3

DPU-DKI

SUB MACRODRAIN

55

No. Kontrak. : HK.02.03/JUFMP-FSK/XI/1

Kontraktor : PT. Dutaraya Dinametro, Jl. Raya Setu No. 17 Setu, Cipayung – Jakarta

Timur 13880

Harga Kontrak : Rp. 48.747.011.000,00 (sudah termasuk pajak 10%)

PIU : Satuan Kerja Pengembangan Penyehatan Lingkungan Permukiman

Jabodetabek, Direktorat Pengembangan Sanitasi Lingkungan, Direktorat

Jenderal Cipta Karya,Kementerian Pekerjaan Umum.

Pemerintah daerah DKI berharap untuk menambah kedalaman penggalian ± 5 m. masalah ini

akan didiskusikan pada saat rapat dengan CPIU, PIU, Konsultan dan Kontraktor.

Hasil rapat pada tanggal 6 Desember 2013 dengan Ditjen. Cipta Karya dan Kontraktor,

disarankan bahwa pihak kontraktor harus melakukan tes uji sondir sepanjang saluran Cideng-

Thamrin, dimana hasil sondir bisa menjadi dasar keputusan dalam usulan tambahan tentang

kedalaman pengerukan.

4.1.5. Ringkasan Perkembangan Pengerukan pada Proyek JUFMP/JEDI

Jakarta Urgent Flood Mitigation Project (JUFMP)/Jakarta Emergency Dredging Initiative Project (JEDIP)

Progres Pekerjaan Pengerukan

Sampai akhir March 2014

Paket 1

Kontrak

Angka

perjalanan

Volume Berat Tanggal

Untuk

diteruskan Period Volume

Berat*)

Ditanda

tangani (days) (m

3)

(%) (m

3) (%) (%)

Paket 1 26 Nov 2013 02 Dec

2013 730 252.069

13,51% - - - -

Paket 2A 11 Nov 2013 11 Nov

2013 730

1.202.95

0 64,48% 702

13.806,0

4 1,15% 0,74%

Paket 2B 11 Nov 2013 11 Nov

2013 730 379.280

20,33% 167

3.003,72 0,79% 0,16%

Paket 3 15 Nov 2013 11 Nov

2013 730 31.420

1,68% - - - -

T O T A L

1.865.71

9 100,00% 869

16.809,7

6 0,90%

catatan:

*) di titik beratkan pada tahap 1

JUFMP

56

JAKARTA URGENT FLOOD MITIGATION PROJECT (JUFMP)

RINGKASAN PEKERJAAN KONTRUKSI DAN PERKEMBANGAN FINANSIAL

PAKET

KONTRAK

PERKEMBANGAN

PEKERJAAN PERKEMBANGAN FINANSIAL

WAKTU

YANG

DIGUNAKAN %

TANGGAL

DI TANDA

TNGANI

CATATAN PERIOD

E

RENCA

NA

PPERKE

MBANG

AN

DEVIA

SI KONTRAK PEMBAYARAN

PRESEN

TASE (HARI)

UNTUK

DITERUSKAN (HARI)

PAKET 1 26

NOVEMBER

2013

02

DESEMBER

2013

730

284.180.000.000

36.500.694.455 12,8% 94

CILIWUNG-

GUNUNG

SAHARI

5,585 6,079 0,494

PAKET 2A 11

NOVEMBER

2013

11

NOVEMBER

2013

730

209.808.000.000

59.601.682.000 28,4% 109 CENGKARENG

FLOODWAY

2,600 26,660 24,060

PAKET 2B 11

NOVEMBER

2013

11

NOVEMBER

2013

730

65.258.477.000 13.620.882.000 20,9% 109 5,358 14,009 8,651

LOWER SUNTER

FLOODWAY

PAKET 3 15

NOVEMBER

2013

15

NOVEMBER

2013

730

48.747.011.000

4.874.701.000 10% 105

CIDENG

THAMRIN

DRAIN

3,456 4,565 1,109

TOTAL

607.993.488.000 14.597.959.455

PERKIRAAN KONTRAK BUDGET

KURS = 1 US $

= 10.000

57

NO DESKRIPSI PIU

BERDASARKAN

PERJANJIAN

PINJAMAN

BERDASARKAN KONTRAK

US $

MILION

RP

(JUTA)

HARGA

KONTRAK

POR

SI

PORSI

PINJAMAN

SALDO

PINJAMAN

KENAIKAN 10%

PORSI

PINJAMAN

KENAIKAN 15%

PORSI

PINJAMAN

1 PAKET 1 DKI

Jakarta 21,28 212.800 284.180.000.000 67% 190.400.600.000 93.779.400.000 209.440.660.000 218.960.690.000

2 PAKET 2 A DJSDA 24,80 248.000 209.808.000.000 80% 167.846.400.000 41.961.600.000 184.631.040.000 193.023.360.000

3 PAKET 2 B DJSDA 6,50 65.000 65.258.447.000 80% 52.206.757.600 13.051.689.400 57.427.433.360 60.037.771.240

4 PAKET 3 DJCK 5,60 56.000 48.747.011.000 80% 38.997.608.800 9.749.402.200 42.897.369.680 44.847.250.120

5 PAKET 4 DKI

Jakarta 27,22 272.200 257.439.035.426 67% 172.484.153.735 84.954.881.691 189.732.569.109 198.356.776.796

6 PAKET 5 DJCK 12,20 122.000 124.260.625.161 80% 99.408.500.129 24.852.125.032 109.349.350.142 114.319.775.148

7 PAKET 6 DJSDA 11,10 111.000 138.750.000.000 80% 111.000.000.000 27.750.000.000 122.100.000.000 127.650.000.000

8 PAKET 7 DKI

Jakarta 20,84 208.400 232.207.971.366 67% 155.579.340.815 76.628.630.551 171.137.274.897 178.916.241.938

Subtotal Component 1

129,54 1.295.400 1.360.651.089.953

987.923.361.079 372.727.728.874 1.086.715.697.187 1.136.111.865.241

58

4.2. Laporan Pelaksanaan Tugas : Spesialis LARAP/RP

4.2.1. Pelaksanaan Rencana Pemukiman Kembali

1. Pendahuluan

Salah satu bantuan teknis yang berperan mendukung adalah Konsultan pengawasan. ini

adalah hal yang utama dan sangat penting dalam membantu PMU, dalam hal pengelolaan

dengan melihat perkembangan pengawasan proyek. SC telah diberi tugas untuk membantu

tugas-tugas penting PMU selama dalam Pelaksanaan pekerjaan, ruang lingkup bantuan

teknis adalah termasuk membantu PMU dan PIU DKI Jakarta dalam pelaksanaan Rencana

Pemukiman Kembali (RPK)

Ruang lingkup pelayanan Konsultan Pengawas adalah sebagai berikut :

1. Mengawasi dan membantu pelaksanaan Rencana Pemukiman Kembali dengan :

mengawasi dan membantu pelaksanaan RPK

Pembebasan lahan dan Rencana Kegiatan Pemukiman Kembali (LARAP) dari

setiap lokasi pekerjaan dimana pemukiman kembali terpaksa harus dilaksanakan

Kebijakan Rencana Pemukiman Kembali

2. Membantu secara teknis dan administratif dalam pembebasan lahan dan proses

pemukiman kembali.

2 Penerapan Kebijakan Pemukiman Kembali (RPK)

Salah satu tujuan dari JUFMP adalah melaksanakan kegiatan pemukiman kembali secara

terbuka karena alasan itu RPK disusun berdasarkan Operational Policy 4.12oleh Bank Dunia

yang berisi tentang perkiraan dampak sosial tentang keterpaksaan pemukiman kembali

diantara nya adalah

Jumlah Warga yang Terkena Proyek JUFMP/JEDI, i.

SubProyek JUFMP Cut off date, termasuk (i) Warga yang terkena dampak relokasi

baik yang secara permanen maupun secara temporary/sementara(ii) warga yang

kehilangan tanah ,mereka baik secara permanen maupun sementara(iii) warga yang

kehilangan asetnya berkaitan tanah yang sudah diambil dari dampak proyek (

bangunan, pepohonan, maupun perkebunan dll); dan (iv) warga yang kehilangan

mata pencaharian merekadi tempat tinggal mereka.

Jumlah Warga yang Terkena dampak Proyek (WTP)

Cut – off Date, i.e Tanggal yang digunakan untuk menentukan kelayakan untuk

mendapatkan kompensasi dan bentuk lain dari bantuan sesuai dengan KKPK. cut-

off date menentukan orang-orang yang memenuhi syarat sesuai dengan KKPK yang

menjadi tanggal pengumuman dari hasil jumlah penduduk yang terkena dampak

subproyek JUFMP. Orang yang menempati daerah itu setelah tanggal tersebut tidak

akan berhak mendapatkan konpensasi sesuai dengan KKPK. Cut off date

menentukan tempat tinggal dan struktur lainnya yang memenuhi syarat untuk

kompensasi tanggal dimana struktur diidentifikasi sesuai dengan hasil ;pemetaan

fotografi atau prosedur lainnya, sesuai kondisi berikut: (1) seluruh tanah berpotensi

terkena subproyek telah digambarkan dan diidentifikasi melalui pemetaan dan

fotografi sesuai dengan wilayah yang digambarkan; dan (2) informasi tentang daerah

59

yang telah dipetakan, digambarkan secara efektif, sistematis dan berkesinambungan.

Biaya Pemindahan, i.e biaya penggantian terhadap aset yang hilang dan transaksi

menentukan biaya pergantian penurunan asset dan nilai sisa material yang tidak di

perhitungkan

Kategori WTP dan hak-hak mereka, yaitu Kompensasi atas hilangnya aset selain

tanah , biaya penggantian tempat tinggal, struktur yang bersifat komersial dan

bangunan lainnya, Kompensasi dapat diberikan dalam bentuk subsidi, perumahan

yang terjangkau, Pemilik lahan yang terkena JUFMP berhak atas kompensasi yang

bersifat tunai, bantuan berupa Pemukiman, dukungan Rehabilitasi, tempat relokasi

harus dipilih melalui konsultasi dengan para warga dan masyarakat sekitar, yang

berfungsi, sebagai tempat relokasi dan harus dipilih melalui konsultasi dengan para

warga dan masyarakat sekitar, warga ditawarkan tempat relokasi yang akan

sepenuhnya dikembangkan sebelum WTP pindah..

Kerangka kebijakan Pemukiman kembali (KKPK) akan menjadi petunjuk dalam Persiapan

Rencana Pemukiman kembali.

3. Pelaksanaan dalam Rencana Pemukiman Kembali

Pelaksanan RPK dan yang harus dilakukan oleh Pihak konsultan:

1. Bantuan dari Pihak DKI kepada pihak pengelola dan pelaksanaan Rencana

Pemukiman Kembali dibuat sesuai dengan letak lokasi termasuk memastikan

Kerangka Kebijakan Pemukiman Kembali KKPK) warga terkena dampak proyek

(WTP) yang didukung dengan konsultasi publik yang memuaskan disetiap bagian

proses dari Rencana Pemukiman Kembali.

2. Mengembangkan peninjauan dan laporan peralatan pada Pelaksanaan RPK.

3. Mendukung pengawasan secara regular dan peninjauan laporan ke PIUs atau ( CPIU )

tergantung pada pelaksanaan RPK

4. Mendukung dan berkordinasi dengan pihak DKI, CPIU dan Bank Dunia dalam

pengawasan Pelaksanaan RPK

Pelaksanaan Rencana Pemukiman Kembali melalui beberapa tahapan yaitu :

a. Rencana Pemukiman Kembali akan disiapkan oleh Kelompok kerja (Pokja) Sosial dan

Lingkungan dalam PIU-DKI, melalui Konsultan denganWTP dan dengan bantuan

konsultasi yang diterima oleh PMU. Rencana Pemukiman kembali Sederhana (RPK

Sederhana) akan disiapkan jika

(1) WTP kurang dari 200 orang dipindahkan.

(2) Semua WTP kehilangan asset produktif mereka kurang dari 10% tidak perlu

dipindahkan ke lokasi lain.

(3) Untuk kasus di luar kondisi 1,2 akan dibuatkan RPK lengkap

b. RPK lengkap atau RPK Sederhanadari masing-masing proyek akan di kaji lagi oleh

Manajemen Proyek di Penjaminan Kualitas dalam PIU DKI Jakarta dan PMU yang

berada pada Direktorat Jenderal Sumber daya Air , Kementerian Pekerjaan Umum

sebelum dokumen tersebut diserahkan kepada Bank Dunia untuk pengkajian dan

60

persetujuan. Dan selanjutnya Bank Dunia akan mengeluarkan Surat Persetujuan ( No

Objection Letter ).

c. Rencana Pemukiman Kembali Lengkap dan RPK Sederhana Versi Bahasa Indonesia

yang telah disetujui oleh Bank Dunia akan disediakan untuk publk di POSKO Unit

Penanganan Keluhan di lokasi sub proyek, kantor-kantor proyek (kelurahan) dan di

kantor pada masing-masing Kantor Walikota setempat, selain itu juga akan

dipublikasikan dalam website DKI Jakarta dalam Kementerian Pekerjaan Umum.

Dokumen RPK lengkap dan RPK Sederhanadalam versi Bahasa Inggris dan Bahasa

Indonesia akan dipublikasikan di Pusat Informasi Publik ( Public Information Counter

PIC) Kantor Bank Dunia Jakarta.

4. Kegiatan Pelaksanaan Pengawasan

Kegiatan yang dilaksanakan oleh PIU Jakarta, dibantu oleh Assistan Konsultan yaitu :

A. Meyusun Rencana Pelaksanaan RPK dengan tahap Kegiatannya :

Sosialisasi

Pengkuran patok

Survey social ekonomi

Cut – off Date

Persiapan RPK

Penerbitan No Objection Letter (NOL)/Surat Persetujuan dari Bank Dunia

Pelaksanaan RPK

B. Menolong dan membantu Kelompok Kerja Sosial dan lingkungan dari PIU DKI

Jakarta pada konsultasi dengan WTP dan dengan asisten konsultan yang telah

ditunjuk.

C. Kegiatan dilaksanakan pada 7 lokasi yaitu

1. Sentiong-Sunter Drain (Paket 1/PIU DKI Jakarta)

2. Waduk Sunter Utara (Paket 4/PIU DKI Jakarta)

3. Waduk Sunter Selatan (Paket 4/PIU DKI Jakarta)

4. West Banjir Kanal (Paket 6/PIU DGWR)

5. Upper Sunter (Paket 2B/PIU DGWR)

6. Kali Pakin-Kali Besar-Jelakeng (Paket 7/PIU DKI Jakarta)

7. Kali Krukut Cideng (Paket 7/PIU Jakarta).

61

4.2.2. Foto di lokasi Waduk Sunter Utara

62

63

Persiapan Kegiatan Peninjauan Larap / Rencana Pemukiman Kembali

TAHAP KEGIATAN

PIU/

LOKASI

JUMLAH SOSIALISASI Pengukuran Patok Batas Survey Sosial Ekonomi

PAKET WTP Target Realisasi % Target Realisasi % Target Realisasi %

Yang tercatat (PAPs) (PAPs)

(PAPs) (PAPs)

(PAPs) (PAPs)

DKI/1 Sentiong-Sunter 202 202 202 100 202 0 0 202 202 100

DKI/4 Waduk Sunter Utara 154 154 154 100 154 0 0 154 154 100

DKI/4 Waduk Sunter Selatan 201 201 201 100 201 0 0 201 201 100

DGWR/6 Muara Banjir Kanal Barat 240 240 240 100 240 0 0 240 240 100

DGWR/6 Upper Sunter (Sunter Atas) 111 111 111 100 111 0 0 111 111 100

DKI/7 K.Pakin-K.Besar- Jelangken 64 64 64 100 64 0 0 64 64 100

DKI/7 Kali Krukut Cideng 225 225 225 100 225 0 0 225 225 100

1.197 1.197 1.197 100 1.197 0 0 1.197 1.197 100

64

PERSIAPAN KEGIATAN PENGAWASAN LARAP /RENCANA KEGIATAN PEMUKIMAN KEMBALI (bersambung…)

TAHAP KEGIATAN

PIU/ LOKASI Cut - off Date Persiapan Dokumen PK Masalah pada NOL Pelaksanaan LARAP Informasi

PAKET

Target Realisasi % Target Realisation % Target Realisation % Target Realisation %

(PAPs) (PAPs)

(PAPs) (PAPs)

(PAPs) (PAPs)

(PAPs) (PAPs)

DKI/1 Sentiong-Sunter 202 202 100 202 0 0 202 0 0 202 0 0

PK Akan disiapkan

oleh bagian Sosial dan

Lingkungan

Kelompok Kerja

(ESWG) dari PIU-DKI

Jakarta.

DKI/4 Waduk Sunter

Utara 154 154 100 154 0 0 154 0 0 154 0 0

DKI/4 Waduk Sunter

Selatan 201 201 100 201 0 0 201 0 0 201 0 0

DGWR/6

Muara Banjir

Kanal Barat 240 240 100 240 0 0 240 0 0 240 0 0

DGWR/6

Upper Sunter

(Sunter Atas) 111 111 100 111 0 0 111 0 0 111 0 0

DKI/7 K.Pakin-K.Besar-

Jelangken 64 64 100 64 0 0 64 0 0 64 0 0

DKI/7

Kali Krukut

Cideng 225 225 100 225 0 0 225 0 0 225 0 0

1.197 1.197 100 1.197 0 0 1.197 0 0 1.197 0 0

65

HASIL DATA PARA PEMUKIM

JAKARTA FLOOD PROGRAM (JEDI) – WADUK SUNTER UTARA (WADUK PAPANGGO)

DI KELURAHAN PAPANGGO, KECAMATAN TANJUNG PRIUK, JAKARTA UTARA ( CUT-OFF DATE)

NO. NAME ALAMAT ASET BERSIH No NAMA ALAMAT ASET BESIH

1 Tidak ada Penghuni RT. 010/08 Rumah kosong 41 Endang RT.010/08

2* Etna RT. 010/08 Rumah Hunian 42 Asmara RT.010/08 Rumah Hunian

3 llmi RT. 010/08 Rumah Hunian 43 Kasbi RT.010/08 Rumah Hunian

4 Heru RT. 010/08 Rumah Hunian 44 Usup Suwinto RT.010/08 Rumah Hunian

5 Rio RT. 010/08 Lahan kosong 45 Pos PK3P RT.010/08 Bangunan Pos

6 Daeng Ngana RT. 010/08 Rumah Hunian 46 Sarifa RT.010/08 Rumah Hunian

7 Feri RT. 010/08 Rumah Hunian 47 Rojianto RT.010/08 Rumah Hunian

8 Kokom RT. 010/08 Rumah Hunian 48 Ibu Rajab RT.010/08 Lahan kosong

9 Madullah RT. 010/08 Rumah Hunian 49 Nadiem RT.010/08 Lahan kosong

10 Munawir RT. 010/08 Rumah Hunian 50 Suherman RT.010/08 Rumah Hunian

11 Somadi RT. 010/08 Rumah Hunian 51 Sayim RT.010/08 Lahan kosong

12 Casmin RT. 010/08 Rumah Hunian 52 iwan RT.010/08 Lahan kosong

13 Sugiarto RT. 010/08 Rumah Hunian 53 Jal Arvan RT.010/08 Lapangan

14 Saprudin RT. 010/08 Rumah Hunian 54 Riyanto RT.010/08 Lahan kosong

15 Hartanto RT. 010/08 Rumah Hunian 55 Sony RT.010/08 Lahan kosong

16 Nana Suryana RT. 010/08 Rumah Hunian 56 Thomas RT.010/08 Kandang kambing

17 Irfan RT. 010/08 Rumah Hunian 57 Paryono RT.010/08 Kandang kambing

18 Samsudin Alfi RT. 010/08 Rumah Hunian 58 Benyamin RT.010/08 Kandang kambing

19 Papa Kembar RT. 010/08 Rumah Hunian 59 Ibu Kiptia RT.010/08 Kandang kambing

20 Ali Akbar RT. 010/08 Lahan kosong 60 Kasim RT.010/08 Kandang kambing

21 Warmo/Sumiati RT. 010/08 Rumah Hunian 61 Teguh RT.010/08 Kandang kambing

22 Suyanto RT. 010/08 Rumah Hunian 62 Pardi RT.010/08 Kandang kambing

23 Gunawan RT. 010/08 Rumah Hunian 63 M-Shaleh Khafi RT.010/08 Kandang kambing

24 Wistara RT. 010/08 Rumah Hunian 64 Atmo RT.010/08 Kandang kambing

25 Jaenal RT. 010/08 Rumah Hunian 65 Saitardi RT.010/08 Kandang kambing

26 Ta'ang RT. 010/08 Rumah Hunian 66 Paryadi RT.010/08 Kandang kambing

27 Ta'ang/Dadi RT. 010/08 Rumah Hunian 67 Posko Kandang Kambing RT.010/08 Pos Satpam

28 Andreas M. RT. 010/08 Rumah Hunian 68 Tabroni RT.010/08 Empang

29 Alex mas'ud RT. 010/08 Lapangan 69 Paeran RT.010/08 Kandang kambing

66

30 Tarto RT. 010/08 Rumah Hunian 70 Parno RT.010/08 Kandang kambing

31 Tasmini RT. 010/08 Rumah Hunian 71 Pahrudin RT.010/08 Kandang kambing

32 Thomas Selan RT. 010/08 Rumah Hunian 72 Surami RT.010/08 Kandang kambing

33 Sugiarti RT. 010/08 Rumah Hunian 73 H. Soleh RT.010/08 Kandang kambing

34 Santa RT. 010/08 Rumah Hunian 74 Bunyamin RT.010/08 Kandang kambing

35 Mursanih RT. 010/08 Rumah Hunian 75 Sriatun RT.010/08 Kandang kambing

36 Wahid RT. 010/08 Rumah Hunian 76 Tukiyah RT.010/08 Kandang kambing

37 Suminto RT. 010/08 Rumah Hunian 77 H. Yatno RT.010/08 Kolam ikan

38 Yuliadi RT. 010/08 Rumah Hunian 78 Martin RT.010/08 Kandang sapi

39 Wahid RT. 010/08 Rumah Hunian 79 Setiawan RT.010/08 Kandang kambing

40 Wahid RT. 010/08 Rumah Hunian 80 Parudin RT.010/08 Kandang kambing

NO. NAME ALAMAT ASET BERSIH No NAMA ALAMAT ASET BESIH

81 Sory RT.010/08 Kandang kambing 121 Bahrudin RT.011/08 Rumah Hunian

82 Tuti RT.010/08 Kandang kambing 122 A. Safrudin RT.011/08 Rumah Hunian

83 Darjo RT.010/08 Kandang kambing 123 Abdul Rauf RT.011/08 Rumah Hunian

84 H. Yatno RT.010/08 Kandang kambing 124 Sriyanto RT.011/08 Kolam ikan

85 Darmo RT.010/08 Kandang kambing 125 Sueb RT.011/08 Rumah Hunian

86 H. Agus RT.010/08 Kolam ikan 126 Titin RT.011/08 Rumah Hunian

87 Ismail RT.010/08 Rumah Hunian 127 Suparno RT.011/08 Rumah Hunian

88 Amat Yani RT.010/08 Rumah Hunian 128 Syarifudin RT.011/08 Rumah Hunian

89 Joko RT.010/08 Peternakan ayam

Kolam ikan

129

Endi RT.011/08 Rumah Hunian

90 Sukarsa RT.013/08 Kolam ikan 130 Kasiman RT.011/08 Rumah Hunian

91 Dahlan Napitupulu RT.013/08 Rumah Hunian 131 Sumar RT.011/08 Rumah Hunian

92 Arsala RT.013/08 Rumah Hunian 132 Imron RT.011/08 Rumah Hunian

93 Ngadi RT.013/08 Kandang kambing 133 Mistu RT.011/08 Rumah Hunian

94 Sutrisno RT.013/08 Tanah kosong 134 Pariyah RT.011/08 Rumah Hunian

95 Maxriuhh Passa RT.013/08 Rumah Hunian 135 Suryadi RT.011/08 Rumah Hunian

96 Jaya Mustofa RT.013/08 Rumah Hunian 136 Herman Kelana RT.011/08 Rumah Hunian

97 Sandi Setiawan RT.013/08 Rumah Hunian 137 Asep RT.011/08 Kolam ikan

98 Ambri Hako RT.013/08 Rumah Hunian 138 Ujang Abdul Muthallo RT.011/08 Kolam ikan

99 Udin RT.013/08 Rumah Hunian 139 Tamail RT.011/08 Rumah Hunian

100 Salim Ayuba RT.013/08 Rumah Hunian 140 Bank Sampah (Astra) RT.011/08 Tempat pembuangan sampah

67

101 Firman RT.013/08 Tempat barang bekas 141 Hj. Ratonah/Alm. Sutara RT.011/08 Kandang ayam

102 Rasminto RT.013/08 Rumah Hunian 142 Hj. Ratonah/Alm. Sutara RT.011/08 Kolam ikan

103 Jumadi RT.013/08 Rumah Hunian 143 Hj. Ratonah/Alm. Sutara RT.011/08 Kebun

104 Marjuki RT.011/08 Rumah Hunian 144 Tarwin RT.001/08 Rumah Hunian

105 Rohim RT.013/08 Rumah Hunian 145 Caca Herlambang RT.001/08 Rumah Hunian

106 Abdul Rauf RT.011/08 Empang Ternak 146 Naryo RT.001/08 Rumah Hunian

107 M.Sani RT.011/08 Rumah Hunian 147 Mariman RT.001/08 Rumah Hunian

108 Jafar RT.011/08 Rumah Hunian 148 Giran Aryanto RT.001/08 Rumah Hunian

109 Yati RT.011/08 Rumah Hunian 149 Tedi RT.001/08 Rumah Hunian

110 Mista RT.011/08 Rumah Hunian 150 Aca RT.001/08 Rumah Hunian

111 Karmin RT.011/08 Rumah Hunian 151 Ros RT.001/08 Rumah Hunian

112 Cawi RT.011/08 Rumah Hunian 152 Jenal RT.001/08 Rumah Hunian

113 Udin Jamaludin RT.011/08 Rumah Hunian 153 Dahlan RT.001/08 Rumah Hunian

114 Mislem RT.011/08 Rumah Hunian 154 Zaenudin RT.001/08 gubuk

115 Rohimin RT.011/08 Rumah Hunian

116 isak RT.011/08 Kandang kambing

117 Raup RT.011/08 Rumah Hunian

118 Karmin RT.011/08 Rumah Hunian

119 Slamet RT.011/08 Rumah Hunian

120 Tabroni RT.011/08 Rumah Hunian

Diketahui

Jakarta, Februari 2014

1. Ketua RW 8 (H.M. SUPARDAL)

Kelurahan Papanggo Kepala Bidang Pengelolaan Sumber

Daya Air

2. Ketua RT 011/08 (UJANG JOHAN)

Dinas Pekerjaan Umum Provinsi DKI

Jakarta

3. Wakil Warga

Selaku

1.RT

012/08

(K A R S I M )

HARAHAP,S.STP Pejabat Pembuat Komitmen

NIP 197885231997021001/128612

cap/ttd

Ir. S.M. Robert Rajagukguk, MT

NIP 196602221997031002

68

4.3. Pelaksanaan system Keluhan Ganti Rugi / Mekanisme Pelaksanaan Penanganan

Keluhan

Tiga anggota bidang penanganan keluhan dan Konsultan Tenaga ahli penanganan keluhan

mulai mengulas dokumen proyek dan informasi persiapan Sistem Penanganan Keluhan (SPK)

untuk segera dioperasikan atau dilaksanakan pada proyek JUFMP/JEDI. Pendekatan dan juga

dukungan adalah hal yang harus diperhatikan, seperti mediasi dalam hal perselisihan atau

keluhan yang suatu saat akan muncul dalam proyek tersebut. Pada prinsipnya, lingkup

pembentukan suatu kelembagaan, pelaksanaan, pengelolaan adalah parameter utama dalam

menanggapi dan mengelola keluhan, seperti halnya yang telah dijelaskan oleh KKPK.

Konsultan akan mengembangkan, menjalankan dan mengatur GR/SPK disetiap wilayah DKI,

SPK/GRS akan dibentuk pada bagian awal Pelaksanaan proyek dan diharapkan bahwa operasi

ini akan di uji dan difungsikan setelah tahap 2 dimulai.

Konsultan akan beroperasi dan mengelola sistem penanganan keluhan MIS berbasis web pada

proyek tersebut yang akan dihubungkan ke website DKI. Ini termasuk ketentuan IT dan

perlengkapan Komunikasi yang dibutuhkan pada setiap unit di masing-masing unit

penanganan keluhan. Unit akan mengelola dokumen dan mengatur alur keluhan dan

tanggapan/ tanggapan dan pemasukan kedalam website penanganan keluhan berbasis real

time. Tim akan memverifikasi keluhan, fasilitas dialog antara orang yang mengadu dan

berselisih sebanyak mungkin di tingkat Posko, Untuk pengaduan yang tidak terpecahkan atau

tidak ada jalan penyelesaian yang ada di tingkat POSKO, ajukan/ berikan data keluhan ke

MCHU dan jika penting bawa ke PCHU. Figures 3.5 berikut menunjukan kelompok

Penanganan keluhan secara, Figures 3.6dan 3.7 Menunjukan prosedur penanganan keluhan

dan sistem pengeloaan keluhan ganti rugi pada Proyek JUFMP/JEDI

Gambar 4.3.1. Tingkatan Kelompok Penanganan Keluhan

CPIU ( Unit Pelaksanaan Proyek Utama )

Unit Penanganan Pengaduan di

tingkat provinsi

Unit Penanganan Keluhan di masing-masing Kota

Unit Penanganan di lokasi Proyek (POSKO)

Warga Terkena Proyek (WTP)

69

Gambar 4.3.2 Sistem Pengelolaan Keluhan Ganti Rugi

Kondisi sesuai yang disetujui

Keluhan sekelompok masyarakat

1. POSKO (Lokasi Proyek) 2. Team Penasehat

Unit Penanganan Keluhan di tingkat Kotamadya

Proses Dokumen Keluhan

(POSKO) 1. Ketatalaksana Dokumen Keluhan

Masyarakat 2. Penanganan Keluhan yang

dilakukan oleh petugas

Keluhan Masyarakat: 1. Surat 2. Form isian 3. SMS Ke nomor ............................ 4. Telephone ke nomor 021

7397522 5. E-mail ([email protected]) 6. Website: www.jufmp.com

Di tanggapi oleh petugas

Unfinish

Finish

Unit Penanganan Keluhan Ditingkat Propinsi

Di tanggapi oleh petugas

Di tanggapi oleh petugas

Finish

Finish

Unfinish

Unfinish

Hukum yang berlaku

70

Gambar 4.3.3 Complaint Handling Management System in CHU (POSKO)

Untuk menolong masyarakat sekitar mengenai keluhan ganti rugi (Warga Terkena Dampak

Proyek WTP) proyek membantu beberapa alternative bagian, diantaranya bisa menyampaikan

keluhannya melalui telephone, SMS, memberikan laporan secara langsung ke Unit

Penanganan Keluhan (CHU), melalui surat maupun melalui Website. Prosedur Penanganan

keluhan selesai pada tahap proyek ditunjukan pada figure 4.3.5, dan 4.3.6 penyelesaian

penanganan keluhan yang dilakukan oleh penasehat dan 4.3.4. Pemeriksaan pada Resolusi

Keluhan. Penyebaran Keluhan akan selesai di papan pengumuman dan kerjasama sosialisasi

dengan kontraktor ketika kontraktor melakukan sosialisasi

Warga Terkena proyek (WTP)

Laporan Masyarakat di POSKO

1. Formulir 2. Disampaikan ke petugas

Tim Penasehat di POSKO 1. Berdiskusi 2. Jawaban/Rekomendasi

Process in CHU(POSKO)

1. Pencatatan dokumen keluhan oleh petugas di pemukiman

2. Mengidentifikasikan masalah dan keluhan ganti

rugi

3. Penyortiran kategori keluhan: 1. Kompensasi; 2. Dampak Kegiatan Proyek; 3. Saran dan Informasi)

Tanggapan oleh petugas

Belum selesai

Finish

UNIT Penanganan Keluhan di tingkat Kotamadya (MCHU)

Tanggapan oleh tim penasehat

Finish

Belum selesai

Website

Website

71

Gambar 4.3.4 Complaint Handling Procedure

Legal Law

Petugas yang berada di POSKO Unit Penanganan Keluhan

(CHU) menerima keluhan melalui telepon, SMS, Email,

Surat, ataupun Laporan langsung

Mengidentifikasi dan Mengklasifikasi:

Keluhan/ campur tangan/ saran dan informasi

menurut daftar kategori keluhan

Verivikasi laporan : data laporan yang sudah

terdaftar

masukan data pelapor ke

aplikasi helpdesk

Laporan yang

sama and

status final

Final/Close

- Laporan berbeda: penerbitan kartu

keluhan baru

- Masukan data laporan ke aplikasi

help desk

Process of complaint handling and conflict:

1. Penanganan oleh petugas cukup untuk Penyelesaian di

POSKO HCU

2. Identifikasi suatu konflik dan masalah yang tidak bisa

diselesaikan di POSKO HCU

Diselesaikan oleh

petugas di tempat POSKO HCU

Final/ Close

Diselesaikan oleh petugas

di HCU Kotamadya HCU ??

Diselesaikan oleh

petugas di tingkat

Propinsi

HCU

The List of Complaint Category:

1. Keluhan yang tertuju pada kompensasi

Kategori keluhan adalah masalah yang

selalu ditemui seseorang / orang yang

terkena proyek yang berkaitan dengan

pemukiman kembali, kompensasi

berupa tanah atau bangunan,

kompensasi aset (tanaman, pohon, dll)

dan hal-hal lain yang berkaitan dengan

pembebasan lahan.

2. Dampak gangguan pada kegiatan

proyek: Kebisingan, polusi udara, bau,

gangguan lalu lintas, asap, dll

Saran dan Informasi

3. Kategori Saran adalah memberikan

masukan proyek JUFMP untuk

meningkatkan kualitas proyek.

Kategori informasi adalah: (i)

menyampaikan informasi pelaksanaan

JUFMP yang berguna untuk proyek; (ii)

layanan informasi yang diminta oleh that

Final/

Close

Final/

Close

YES

NO

YES

YES

YES

YES

NO NO

NO

72

Figure 4.3.5 Penyelesaian Keluhan yang ditangani oleh Penasehat

Penyelesaian Keluhan yang ditangani oleh

Penasehat

buka link kemudian menuju ke aplikasi help desk dengan menggunakan data diri dan password

memverivikasi menu bantuan dari aplikasi helpdesk

denganmengidentifikasi kartu penundaan

Menindak lanjuti apabila dibutuhkan, menindak lanjuti,

persiapan teknis dan memastikan sebuah solusi/

jawabankeluhan

No telp, email, si pengeluhdan sampaikan solusi atau hasil

aksi tindak lanjut

menunjukan data masukan di aplikasi helpdesk dan rubah

status yang tidak bisa dipecahkan(card pending)

menjadi kartu penyelesaian

73

PAKET 1 PEKERJAAN : Dredging and Embankment of

CILIWUNG - GUNUNG SAHARI DRAIN AND WADUK MELATI

LAYANAN KELUHAN

Nomor Telephone : 021 7397522

E-MAIL : [email protected]

WEBSITE : www.jufmp.com

Figure 4.3.6 Verifikasi Resolusi Keluhan

Figure 4.3.7 Papan Pengumuman untuk Sosialisasi Keluhan

Kartu yang telah diselesaikan oleh Ahli Complain Handling

diverifikasi untuk memastikan tindak lanjut atau jawaban yang

disampaikan sudah menyelesaikan keluhan pelapor dengan cara

menghubungi pelapor melalui telepon atau email.

Petugas membuka data Kartu Selesai pada aplikasi help desk

dan memilih Kartu Keluhan untuk ditindaklanjuti

Petugas memastikan keluhan telah diselesaikan dengan cara menelepon kembali pelapor dan menanyakan apakah keluhan yang dihadapi sudah terselesaikan dengan baik;

Apabila keluhan sudah selesai, petugas mengubah status

“Kartu Selesai “ menjadi “Tutup”’

Apabila keluhan belum selesai dengan baik, tetapi timbul

keluhan yang sama, status kartu diubah oleh petugas dari

terselesaikan menjadi belum selesai, atau dari ’solved’ menjadi

’pending’. Jika timbul keluhan baru, petugas membuka Kartu

Baru

74

FORM -1

(CONTOH)

FORM KELUHAN GANTI RUGI(KOMPENSASI)

JAKARTA URGENT FLOOD MITIGATION PROJECT /JUFMP

(Jakarta Emergency Dredging Initiative/JEDI)

Tanggal laporan : ………………………………………………………………

Nama Pelapor : ………………………………………………………………

Alamat : ………………………………………………………………

(Kel, Kecamatan) ………………………………………………………………

No. KTP (DKI) : ………………………………………………………………

Status : ………………………………………………………………

No. Telepon/HP : ………………………………………………………………

Kategori keluhan

1. Tanah

(1) Tanah-1

Land Status : 1) Tanah Negara 2) Tanah milik pribadi 3) Tanah Sewa

Land Size : …………………………………………….. m2

Proof of Ownership : .................................................

Land Price (Agreed) : Rp …………………………………… / m2

(2) Land- 2

Status Tanah : 1) 1) Tanah Negara 2) Tanah milik pribadi 3) Tanah Sewa

Luas Tanah : …………………………………………….. m2

Bukti Kepemilikan : .................................................

Harga Tanah (disetujui) : Rp …………………………………… / m2

(3) Land- 3

Status Tanah : 1) 1) Tanah Negara 2) Tanah milik pribadi 3) Tanah Sewa

Luas Tanah : …………………………………………….. m2

Bukti Kepemilikan : .................................................

Harga Tanah (disetujui) : Rp …………………………………… / m2

2. BANGUNAN

(1) Bangunan 1

Status Tanah : 1) Tanah negara 2) tanah milik pribadi 3) Tanah sewa

Luas tanah : …………………………………………….. m2

Bangunan : 1) Rumah 2) Toko 3) lainnya, (disebutkan)......

Luas Bangunan : …………………………………………….. m2

Jumlah lantai : ............... (1 lantai atau 2 lantai)

Jenis Bangunan : 1) Permanen 2) semi permanen 3) lainnya (disebutkan)......

Status Bangunan : 1) pemilik 1 2) sewa 3) lainnya

Harga Bangunan : Rp …………....………………… / m2

(disetujui)

Nilai Bangunan/Rumah : Rp ........................................ (luas bangunan x harga bangunan)

NOMOR KELUHAN :

75

(2) Bangunan 2

Status Tanah : 1) Tanah negara 2) tanah milik pribadi 3) Tanah sewa

Luas tanah : …………………………………………….. m2

Bangunan : 1) Rumah 2) Toko 3) lainnya, (disebutkan)......

Luas Bangunan : …………………………………………….. m2

Jumlah lantai : ............... (1 lantai atau 2 lantai)

Jenis Bangunan : 1) Permanen 2) semi permanen 3) lainnya (disebutkan)......

Status Bangunan : 1) pemilik 1 2) sewa 3) lainnya

Harga Bangunan : Rp …………....………………… / m2

(disetujui) (3)

Nilai Bangunan/Rumah : Rp ........................................ (luas bangunan x harga bangunan)

(3) Bangunan 3

Status Tanah : 1) Tanah negara 2) tanah milik pribadi 3) Tanah sewa

Luas tanah : …………………………………………….. m2

Bangunan : 1) rumah 2) toko 3) lainnya, (disebutkan)......

Luas Bangunan : …………………………………………….. m2

Jumlah lantai : ............... (1st/2nd)

Jenis Bangunan : 1) Permanen 2) semi permanen 3) lainnya (disebutkan)......

Status Bangunan : 1) pemilik 1 2) sewa 3) lainnya

Harga Bangunan : Rp …………....………………… / m2

(disetujui) (1)

Nilai Bangunan/Rumah : Rp ........................................ (Size of build x unit rate)

3. Tanaman

Macam tanaman : Tanaman akan mendapatkan konpensasi dari setiap tanaman

yang tumbuh di perkebunan ataupun tanaman yang bernilai ekonomi kecuali tanaman

yang tumbuh di dalam pot

No Jenis Tanaman Usia

(tahun)

unit/

ukuran Total

Unit rata-

rata

(Rp 000)

Total

Pengeluaran

(Rp 000)

I Tanaman

Nangka pohon

Mahoni pohon

Lamtoro pohon

Sengon pohon

pohon

pohon

pohon

pohon

pohon

pohon

pohon

II Tumbuhan

Kubis bulan ha

Jagung bulan ha

76

bulan ha

bulan ha

bulan ha

bulan ha

bulan ha

bulan ha

bulan ha

bulan ha

4. Lainnya

(diisi keluhan lainnya, jika ada)

.......................................................................................................................................................

.......................................................................................................................................................

.......................................................................................................................................................

.......................................................................................................................................................

.......................................................................................................................................................

.......................................................................................................................................................

.......................................................................................................................................................

.......................................................................................................................................................

.......................................................................................................................................................

.......................................................................................................................................................

.......................................................................................................................................................

.......................................................................................................................................................

.......................................................................................................................................................

.......................................................................................................................................................

Jakarta, .... ........................... 2014

Pelapor

( .................................................. )

77

FORMULIR KELUHAN

DAMPAK KEGIATAN PROYEK

JAKARTA URGENT FLOOD MITIGATION PROJECT (JUFMP)

JAKARTA EMERGENCY DREDGING INITIATIVE (JEDI)

1. Tanggal laporan : …………………………………………………………

2. Nama Pelapor : …………………………………………………………

3. Alamat : …………………………………………………………

(Kelurahan, Kecamatan) : ….....……….………………………………………..…

4. No. KTP (DKI) : …………………………………………………………

5. Status : …………………………………………………………

6. No. Telepon/HP : …………………………………………………………

JENIS KELUHAN

1. POLUSI UDARA

Kondisi Kualitas udara : 1.Bagus 2.Sedang 3. Jelek

(1) Level polusi udara : ..............................………..

(2) Bahan polusi utama : ............... ........................

(3) Kondisi polusi : 1. Diatas rata-rata / sedang / dibawah ambang batas

Gangguan udara yang dirasakan : 1. Debu 2. Penyumbatan 3.Asap 4.lainnya .......

Jarak Gangguan : .........................................m

Efek gangguan : 1. .......................................

2. .......................................

3. .......................................

2. SUARA KEBISINGAN

Lokasi Bising : ......................................................

Sumber bunyi : 1. Peralatan/Mesin yang digunakan di Proyek

2. Peralatan /mesin non-proyek

Noise Level : 1. Sangat berisik 2. Tidak terlalu berisik

Radius disorders : ...................... m

Time Noise : 1. Pagi 2. Siang hari 3.Sore hari 4. Malam hari

3. KERUSAKAN JALAN/BERLUMPUR

Permulaan kondisi proyek : 1. Berfungsi baik 2. Kerusakan fungsi pencahayaan

3. Rusak sedang. 4.Rusak berat

Material yang dirasakan : 1. Lumpur 2. Pasir 3. Kerikil 4. lainnya………..

Gangguan yang dirasakan : 1Jalan berlumpur 2. Berlumpur /licin 3. Jalanan rusak

Causes damage of the road : ……………………………………………..

Panjang kerusakan : ……………………… m

Level Kerusakan : 1.Ringan 2.Sedang 3Berat

FORM - 2

NOMOR KELUHAN

78

4. BAU TAK SEDAP

Sumber bau : ............................

Jarak bau : ............................. m

Waktu dimulai bau tak sedap : ........................................................ (tgl/bulan/tahun,waktu)

Jumlah orang yang terganggu: …………………………… orang

5. Gangguan Kekacauan lalu-lintas

Penyebab kemacetan : ...............................................

................................................

................................................

Waktu : ...............................................

Lama Kemacetan (Durasi) : ............................................... menit/jam

Panjang Antrian Kendaraan : ............................................... m

6. lainnya

(diisi keluhan lainnya, jika ada)

……………………………………………………………………………………………...……

……………………………………………………………………………………………...……

……………………………………………………………………………………………...……

……………………………………………………………………………………………...……

……………………………………………………………………………………………...……

……………………………………………………………………………………………...……

……………………………………………………………………………………………...……

……………………………………………………………………………………………...……

……………………………………………………………………………………………...……

……………………………………………………………………………………………...……

……………………………………………………………………………………………...……

……………………………………………………………………………………………...……

Jakarta, .... ........................... 2014

Pelapor

( .................................................. )

Catatan:

Kata tebal dan bercetak miring diisi oleh petugas

79

FORMULIR KELUHAN

SARAN DAN INFORMASI

JAKARTA URGENT FLOOD MITIGATION PROJECT (JUFMP)

JAKARTA EMERGENCY DREDGING INITIATIVE (JEDI)

7. Tanggal laporan : …………………………………………………………

8. Nama Pelapor : …………………………………………………………

9. Alamat : …………………………………………………………

(Kelurahan, Kecamatan) : ….....……….………………………………………..…

10. No. KTP (DKI) : …………………………………………………………

11. Status : …………………………………………………………

12. No. Telepon/HP : …………………………………………………………

SARAN

(isi saran untuk perkembangan proyek, jika ada)

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

INFORMASI

(isi informasi demi perkembangan proyek, jika ada)

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

…………………………………………………………………………………………………

Jakarta, .... ........................... 2014

Pelapor

( .................................................. )

FORMULIR 3

NOMOR KELUHAN :

80

4.4. Mekanisme Keluhan Ganti Rugi/ Spesialis Penanganan Keluhan

a Kegiatan selama bulan Januari 2014

Menghadiri kordinasi CPIU

Mengembangkan draft Rencana Kegiatan Kerja mengenai keluhan ganti rugi selama

bulan Januari – Desember 2014

Berkonsultasi mengenai permasalahan draft Rencana Kerja dengan Co Team Leader

Berkordinasi dengan supervisor lapangan untuk menentukan kondisi lapangan di

Kantor Pusat

1. Paket 1 ; Ciliwung –Gunung Sahari Floodway, Waduk Melati (Kali Gresik dan \

Lower Cideng )

2. Paket 2A: Cengkareng Floodway

3. Paket 2B: Lower Sunter Floodway

4. Paket 3: Cideng Thamrin Drain

Berkordinasi dengan spesialis LARAP untuk mengetahui gambaran hasil Survey

LARAP

Berkoordinasi dengan Spesialis MIS yang akan di kembangkan pada bentuk Website

Kunjungan ke lapangan dengan supervisor lapangan untuk memperoleh masalah sosial

yang terkait pada pekejaan proyek

1. Paket 1 ; Ciliwung –Gunung Sahari Floodway, Waduk Melati (Kali Gresik dan \

Lower Cideng )

2. Paket 2A: Cengkareng Floodway

3. Paket 2B: Lower Sunter Floodway

4. Paket 3: Cideng Thamrin Drain

Menghadiri sosialisasi proyek pada Paket 2B

Masyarakat di sepanjang sungai berharap agar pihak ketua RT dan RW di libatkan

dalam program pelaksanaan proyek

b. Kegiatan selama bulan Februari 2014 ( hingga 10 Februari 2014 )

Menurut Spesialis LARAP penerimaan daftar WTP ke PIU-DKI Jakarta

Persiapan mekanisme keluhan ganti rugi (draft) dan prosedur penanganan keluhan

melalui bermacam-macam media

Koordinasi dengan Tim Leader tentang penanganan keluhan dan pengadaan telepon

pada kantor lapangan

Kunjungan ke lapangan

1. Paket 3 : Sungai Krukut – Cideng. Memahami kondisi yang sebenarnya dan

permasalahan sosial

2. Paket 2B : Sungai Lower Sunter dan pintu air Kelapa Gading. memahami

Kemacetan pada proses pengerukan estimasi keluhan

3. Paket 4 : Kali Sentiong bagian Kelurahan Galur. Disepanjang sungai banyak

ditemukan rumah pemukiman terapung

4. Paket 2A : Cengkareng Drain. Menghadiri sosialisasi proyek. Penduduk lokal

mengadukan beberapa keluhan mereka seperti kontraktor menebang

beberapa pohon tanpa ijin, siapa yang akan bertanggung jawab pada

kerusakan jalan akibat sisa material pembuangan dampak dari

pekerjaan proyek. Paket ini tidak termasuk dokumen LARAP

81

Hasil

5. Paket 6 : Kampung Nelayan Kali Adem di Muara Angke yang berlokasi di

sepanjang dinding luar, terdapat bangunan kumuh berdiri liar yang didirikan hanya

dengan bamboo dan kayu diatas genangan air banjir. Pada awalnya penduduk lokal

berencana ingin pindah dekat Rusunawa yang didirikan oleh Buddha Tzu Chi

Indonesia akan tetapi belum terealisasi hingga sekarang. Paket 6 diidentifikasi

terdiri dari 240 WTP. Wakil dari nelayan lokal Bpk. Surihman dan Bpk. Tasmara

mengatakan mereka berharap mendapatkan tempat pemukiman di dekat tempat

kerja mereka. Penduduk lokal hanya mempunyai kartu identitas pengenal atau

KTP

c. Kegiatan selama Bulan Maret 2014

1. Rapat Internal

Rapat Internal dengan TL dan Co. TL

2. Koordinasi

Koordinasi dengan supervisor Lapangan pada Paket-1, Paket-2A dan Paket -2B

3. Rapat Koordinasi

Rapat koordinasi di Infrastructur kota (Prakot) DKI Jakarta

Rapat Koordinasi Paket-2B

Rapat Koordinasi Paket-2A

Rapat Rutin di Dinas Pekerjaan Umum (DPU) DKI Jakarta

Koordinasi dan dan Konsultasi dengan Bank Dunia

Rapat koordinasi dengan Dinas Kebersihan DKI Jakarta dalam rangka

Persiapan Pengangkutan sampah ke TPA Bantar Gebang.

4. Sosialisasi

Menghadiri Sosialisasi pada paket-2B (Kelurahan Rawa Badak Utara)

5. Kunjungan Lokasi

Kunjungan lokasi pada paket 2A

Kunjungan lokasi pada paket 2B

Kunjungan lokasi pada paket 1

Kunjungan lokasi ke Kelurahan Papanggo (Sentiong-Sunter floodway)

Kunjungan lokasi ke Kelurahan Sunter Agung (Sentiong-Sunter floodway)

Kunjungan lokasi ke Kelurahan Sunter Jaya (Sentiong-Sunter floodway)

Kunjungan lokasi ke Kelurahan Mangga Dua Selatan (Ciliwung-Gunung

Sahari drain)

Kunjungan lokasi ke Lower Sunter Floodway

Kunjungan lokasi ke Cengkareng floodway

Kunjungan lokasi ke CDF Ancol

Kunjungan lokasi ke Kelurahan Jatinegara Kaum (Upper Sunter),

82

INTERNAL MEMO

Tanggal : 20 Maret 2014

Dari : Sutjahjo

Kepada : Team Leader

CC : Co-Team Leader

Perihal : Hasil Kunjungan ke lokasi

Sosialisasi di Cengkareng Floodway (Paket-2B)

Tempat : Kantor RW 4, Kelurahan Kedaung Kaliangke, Kecamatan Cengkareng pada

10 Februari 2014.

Jumlah peserta : Ketua RW 4, RW 7, Sekretaris KelurahanKedaung Angke, BBWS Cilicis

(PIU), Kontraktor, Konsultan, Perwakilan Masyarakat, Forkabi

Moderator : Sekretaris Kelurahan Kedaung Angke.

Hasil

1. Staff BBWS Ciliwung Cisadane

• Proyek ini dimulai pada akhir 2013

• Kontraktor: Adhi Karya, Hutama Karya, Jasa Kontruksi

• Panjang Saluran: 7,8 Km

• Lokasi : RW 4 merupakan salah satu area proyek

• Pekerjaan: Pengerukan Cengkareng Floodway, disana tidak ada perluasan dan

pengakhiran.

2. Kontraktor

• Pekerjaan ini dimulai dengan Pemancangan tiang pancang dari Kembangan

• Bekerja secara spesifik dari pekerjaan tiang pancang, disana pembersihan disekitar

area

• Pekerjaan pengerukan hanya di RW 4

• Kegiatan pembuangan material pengerukan melalui Daan Mogot – CDF Ancol

• Jika ada bangunan di area pekerjaan, Mereka harus ijin ke pihak berwajib yang terkait

• Maksud dari pekerjaan ini adalah penambahan saluran jadi tidak akan terjadi lagi

kejadian banjir

• Pekerjaan Pengerukan terdiri dari pemancangan dan pemasangan pintu air

3. Tanggung Jawab

a. LPMK

- Berdasarkan pengalaman akhir pengerukan material belum dibersihkan

- Perubahan pohon kelapa dari Dinas Pertamanan

- Kebersihan jalan belum diperhatikan dalam pengerukan

- Siapa yang akan bertanggung jawab pada pintu air? Karena terjadi kerusakan

83

- Banyak pemukim yang masih memelihara ayam dan bebek, jadi bagaimana kita

memberi konpensasinya

Jawaban:

- Material Pengerukan ditempatkan di saluran penyimpanan dan diangkut menuju ke

Ancol

- Didepan truk pembuangan, terdapat spon dengan maksud untuk mengalirkan air

saja

- Tanaman dan ternak di pinggir sungai adalah tugas Kementerian Pekerjaan umum

- Tanggung jawab pintu air adalah urusan DKI yang akan di konsultasikan ke DKI

untuk menjaga pintu air tersebut

- Dampak efek teknis dari kandang dan ternak bisa didiskusikan di lapangan dengan

kotraktor

- Pada Regional Regulasi DKI pada pemindahan pepohonan dengan klasifikasinya

- Penanaman pohon – adalah tanggung jawab kotraktor

b. Ketua RW 7 (Ibu Yeni)

- Pepohonan telah ditebang dan jalan telah berlumpur sebelum kontraktor

berkordinasi dengan pihak terkait

- Kerusakan jalan akibat pekerjaan ini akan diperbaiki

- Letak tiang pancang harus dijaga dengan maksudakar tidak menjadi areal

pembuangan

Jawaban:

- Kontraktor meminta maaf dikarenakan mereka belum membangun kordinasi

sebelumnya akibat banjir

- Disekitar tiang pancang akan ditanam pohon dengan maksud agar tidak menjadi

area pembuangan

- Pada pinggir sebelah kiri sungai adalah pemantauan jalan bukan tugas kementerian

akan tetapi tugas dari BBWS jika terjadi gangguan maka itu akan segera di aspal

c. Ketua RW 4 (Bp. Rusli)

- Jalan diatas floodgate akan terjadi genangan pada musim hujan, Kementerian

Pekerjaan Umum harus menghaluskan jalan tersebut

- Pemindahan pepohonan; pohon yang dalm kondisi bagus akan segera ditebang

Jawaban:

- Jalan harus diperiksa sebelumnya.

- Masyarakat harus mengawasi pekerjaan tersebut. Kontraktor harus membuktikan

kembali kontruksi mereka sesuai dengan ketentuan yang berlaku.

d. Masyarakat setempat (Bp. Margono)

- Saluran air dari Kantor Indosat mengalir langsung dari Pemukiman Masyarakat.

Kanal di Jl. Daan mogot ditransfer ke pemukiman masyarakat oleh Indosat yang

membentuk lembah berbentuk U

e. Sekretaris Kelurahan:

- Harus membuat surat nasehat lengkap dengan gambar yang diajukan kepada Bpk.

Lurah dengan maksud untuk mengingatkan surat nasehat yang diberikan pada saat

Rapat Kordinasi Rutin ( Rakorwil).

84

INTERNAL MEMO

Tanggal : 25 Maret 2014

Dari : Sutjahjo

Kepada : Team Leader

CC : Co-Team Leader

Perihal : Notulen rapat

1. Sosialisasi telah selesai pada tanggal 25 Maret 2014 didukung oleh Dewan Direksi

(BBWS Cilicis) Konsultan Pengawas dengan para Peserta yaitu Lurah Rawa

Badak Utara, Ketua RW03, RW07, RW09, RW11 dan RW12 dan Petugas

keamanan di wilayah Rawa Badak Utara

2. Sosialisasi

Panjang pengerukan di Kali Sunter di Kelurahan Rawa badak sekitar 800 m.

Jalur yang digunakan adalah benar ( ketika kita melihat dari aliran hulu menuju

hilir)

Pengerukan menggunakan Metode secara mekanik, jumlah alat berat yang

digunakan adalah 2 unit. 1 unit beroperasi di air dan 1 unit lagi beroperasi di

tanah. Pengerukan akan disimpan sementara di pinggir pantai, untuk

menungggu kering sebelum diangkut ke tempat pembuangan di CDF Ancol

Masyarakat menerima pekerjaan kontraktor di Area Kelurahan Rawa Badak

Utara mereka mengajukan agar warga local di jadikan petugas keamanan.

Memberikan tanda-tanda petunjuk pengerukan sungai seperti “ Maaf

mengganggu jalan anda di karena kan ada pekerjaan Pengerukan di Kali

Sunter”

Lumpur yang berceceran dijalan hasil dari kurangnya/minimnya

pengangkutan, kotoran luimpur yang harus dibersihkan, dengan maksud untuk

menghindari kejadian yang tidak diinginkan. Hal ini sudah termasuk dalam

rencana kontraktor dan nasehat konsultan sebelumnya

Di Kelurahan Rawa badak Utara terdapat lintasan bisnis dan kapal muatan

hingga 10 unit yang melibatkan masyarakat sebanyak 30 orang, jika

pengerukan berjalan maka ada kemungkinan kegiatan mereka akan berhenti

(bukan kegiatan bisnis) karena itu diharapakan warga tersebut mendapat

kompensasi tersebut

Jika orang bertanya atau yang berkenaan dengan masalah keluhan masyarakat,

harus segera ditanggapi, mohon di informasikan tentang penambahan alamat

masyarakat tersebut ( kepada siapa keluhan/komplain harus disampaikan)

85

Kelurahan (di masing RW beserta Ketua RW) diharapkan dalam pengerjaan di

sungai Sunter agar aman, karena takut terjadinya kekerasan karena kehadiran

masyarakat, terutama anak-anak.

Sungai tidak dilengkapi dengan pagar pengaman atau penghalang. Disamping

itu, dibutuhkannya jembatan perlintasan.

Jakarta, 26 Maret 2014

Sutjahjo

Spesialis Penanganan Keluhan

86

INTERNAL MEMO

Tanggal : March 20, 2014

dari : Sutjahjo

Kepada : Team Leader

CC : Co-Team Leader

Perihal : Hasil Kunjungan Ke lokasi

1. Kunjungan lokasi yang diadakan pada tanggal 19 Maret 2014 pada Paket 1 dan CDF

Ancol, yang turut serta adalah supervisor lapangan Paket 1, Supervisor lapangan CDF

Ancol, CHS dan Enumerator

2. Hasil Kunjungan lokasi Paket-1

Beberapa bangunan berlokasi di penyimpanan Ciliwung – Gunung Sahari telah

dibersihkan.

Secara umum tidak ada keluhan masyarakat dalam pelaksanaan proyek, sama

halnya beberapa keluhan yang harus dihadapi dengan baik

3. Hasil Kunjungan lokasi CDF Ancol

Memiliki 2 unit alat berat dan dozer 1 unit alat pengeruk 1 unit

Disana ada dua alat pengeruk yang beroperasi di lokasi

Jumlah Truk Pengangkut yang berada di CDF Ancol yaitu 4 unit, 3 unit Paket

2B dan 1 unit dari luar JEDI

Ada lembaga lain yang membuang lumpur di lokasi CDF ketika diberitahui

dari PU, PU belum tentu jelas darimana?

Menurut P Ferdinand (Staff PT. Pembangunan Jaya Ancol) Penguncian gate

belum disampaikan kepada Lembaga Konsorsium, belum adanya keamanan

(penjaga), penjagaan sangat dibutuhkan dengan segera

PT. Pembangunan jaya Ancol belum menerima copy uji laboratorium dari

hasil pengerukan

Menurut informasi Paket -2B akan membuang lumpur ke CDF Ancol