 NO SNI HARGA JUMLAH SATUAN HARGA (Rp) (Rp) K.1 SP L 1 TI TI K PEMASANGAN INST ALAS I (Dari Panel Ke Saklar Lalu Menuju Titik Lampu) 5 . 0 0 0 m ' K a b e l N Y M 3 X 2 , 5 mm 1 3 , 7 7 0 . 0 0 6 8 , 8 5 0 .0 0 5.000 m' K a b e l NYM 3 X 1 , 5 mm 9 , 180.00 45 , 900.00 4 . 0 0 0 b h L .B o w S e k ru p 2 , 2 9 5 . 0 0 9 , 1 8 0 .0 0 10.000 bh S a d e l 8 6 7. 0 0 8 , 6 7 0.00 5 . 0 0 0 b h P e n g g a n tun g 1 , 1 7 3 . 0 0 5 , 8 6 5 .0 0 1.000 bh Inbo w Do s 6,630. 0 0 6,630.00 2 . 0 0 0 b h T - D o s 4 , 8 4 5 . 0 0 9 , 6 9 0 . 0 0 10.000 bh Fi z zer + S ekru p 765.0 0 7 ,6 5 0. 0 0 5 . 0 0 0 b h K a b e l T e e t s 3 5 7 . 0 0 1 , 7 8 5 . 0 0 2.000 Mtr Pip a Sp ir a l 1,275.00 2 ,5 5 0 .0 0 5 . 0 0 0 b h L - B o w 2 , 2 9 5 . 0 0 1 1 , 4 7 5 .0 0 3.000 btg Pip a Clips a l 8,67 0 .0 0 2 6 ,010. 0 0 0 . 2 0 0 b h I s o l a s i 6 , 0 0 0 . 0 0 1 , 2 0 0 .0 0 0.800 o /hr P e ker j a 60,000.00 4 8,000.00 0 .5 0 0 o / h r T u k an g l i s tr i k 7 0 , 0 0 0 . 0 0 3 5, 0 0 0 .0 0 0.080 o /hr M a ndor 9 0 ,0 0 0. 0 0 7, 2 00.00 1 5. 0 0 0 m ' K a b e l N Y M 3 X 2 ,5 mm 1 3 , 7 7 0 .0 0 2 0 6 ,55 0 . 0 0 15.000 m' K a b e l NYM 3 X 6 mm 3 0, 0 90.00 4 51,350.00 2 0 . 0 0 0 m ' K a b e l N Y M 3 X 4 mm 2 0 , 9 1 0 . 0 0 4 1 8 , 2 0 0 . 0 0 25.000 m' K a b e l NYM 4 X 4 mm 2 8, 0 50.00 701,250.00 TITIK LAMPU Juml ah 295,655.00 TITIK STOP KON TAK BIASA 387,455.00 TITIK STOP KONTAK KHU SUS 632,255.00 TITIK EXHO USE 599,105.00 TITIK AXIAL FAN 882,155.00 K.1 SP L 1 BH PEMASANGAN ST OP KONT AK 1 . 0 0 0 b h S t o p K o n t a k N a s i ona l 6 6 , 3 0 0 . 0 0 6 6 , 3 0 0 .0 0 0.250 o /hr Tukang li s trik 7 0, 0 0 0 .0 0 17,5 0 0. 0 0 0 . 1 0 0 o / h r M a n d or 9 0 , 0 0 0 . 0 0 9 , 0 0 0 .0 0 Juml ah 92,800.00 K.1 SPL 1 BH PEMASANGAN S AKELAR TUNGGAL 1.000 bh S a kelar tu n g g al N a sional 56,610.00 56, 6 10.00 0 . 2 5 0 o / h r T u k an g l i s t r i k 7 0 , 0 0 0 . 0 0 1 7 , 5 0 0 .0 0 0.100 o /hr M a ndor 9 0 ,0 0 0. 0 0 9,000.00 Juml ah 83,110.00 K.1 SP L 1 BH PEMASANGAN SAKELAR GAND A 1 . 0 0 0 b h S a k e l ar g a n d a N as i o na l 7 7 , 0 1 0 . 0 0 7 7 , 0 1 0 . 0 0 0.250 o /hr Tukang li s trik 7 0, 0 0 0 .0 0 17,5 0 0. 0 0 0 . 1 0 0 o / h r M a n d or 9 0 , 0 0 0 . 0 0 9 , 0 0 0 .0 0 Juml ah 103,510.00 K.1 SP L 1 BH PEMASANGAN KOT AK KONT AK KHUS US 1 . 0 0 0 b h K o ta k K o n ta k K h usus 9 4 , 8 6 0 . 0 0 9 4 , 8 6 0 . 0 0 0.250 o /hr Tukang li s trik 7 0, 0 0 0 .0 0 17,5 0 0.0 0 0 . 1 0 0 o / h r M a n d or 9 0 , 0 0 0 . 0 0 9 , 0 0 0 .0 0 Juml ah 121,360.00  ANAL ISA BIA YA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

Upload: daengnojengs

Post on 05-Nov-2015

23 views

Category:

Documents


6 download

DESCRIPTION

analisa

TRANSCRIPT

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    K.1 SPL 1 TITIK PEMASANGAN INSTALASI(Dari Panel Ke Saklar Lalu Menuju Titik Lampu)

    5.000 m' Kabel NYM 3 X 2,5 mm 13,770.00 68,850.005.000 m' Kabel NYM 3 X 1,5 mm 9,180.00 45,900.004.000 bh L.Bow Sekrup 2,295.00 9,180.00

    10.000 bh Sadel 867.00 8,670.005.000 bh Penggantung 1,173.00 5,865.001.000 bh Inbow Dos 6,630.00 6,630.002.000 bh T-Dos 4,845.00 9,690.00

    10.000 bh Fizzer + Sekrup 765.00 7,650.005.000 bh Kabel Teets 357.00 1,785.002.000 Mtr Pipa Spiral 1,275.00 2,550.005.000 bh L-Bow 2,295.00 11,475.003.000 btg Pipa Clipsal 8,670.00 26,010.000.200 bh Isolasi 6,000.00 1,200.000.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.080 o/hr Mandor 90,000.00 7,200.00

    15.000 m' Kabel NYM 3 X 2,5 mm 13,770.00 206,550.0015.000 m' Kabel NYM 3 X 6 mm 30,090.00 451,350.0020.000 m' Kabel NYM 3 X 4 mm 20,910.00 418,200.0025.000 m' Kabel NYM 4 X 4 mm 28,050.00 701,250.00

    TITIK LAMPU Jumlah 295,655.00TITIK STOP KONTAK BIASA 387,455.00TITIK STOP KONTAK KHUSUS 632,255.00TITIK EXHOUSE 599,105.00TITIK AXIAL FAN 882,155.00

    K.1 SPL 1 BH PEMASANGAN STOP KONTAK

    1.000 bh Stop Kontak Nasional 66,300.00 66,300.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 92,800.00

    K.1 SPL 1 BH PEMASANGAN SAKELAR TUNGGAL

    1.000 bh Sakelar tunggal Nasional 56,610.00 56,610.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 83,110.00

    K.1 SPL 1 BH PEMASANGAN SAKELAR GANDA

    1.000 bh Sakelar ganda Nasional 77,010.00 77,010.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 103,510.00K.1 SPL 1 BH PEMASANGAN KOTAK KONTAK KHUSUS

    1.000 bh Kotak Kontak Khusus 94,860.00 94,860.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 121,360.00

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    K.1 SPL 1 BH PEMASANGAN LAMPU DOWN LIGHT 225

    1.000 bh Armatur Down Light 225 FBH 057 + Lampu 23 W 234,600.00 234,600.001.000 bh Pelubangan Plafon 7,650.00 7,650.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 268,750.00K.1 SPL 1 BH PEMASANGAN ARMATUR DOWN LIGHT 150

    1.000 bh Armatur Down Light 150 FBH 057 + Lampu 14 W 158,100.00 158,100.001.000 bh Pelubangan Plafon 7,650.00 7,650.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 192,250.00K.1 SPL 1 BH PEMASANGAN ARMATUR BARET

    1.000 bh Armatur Baret TCW 211 + Philips 32 W 1 Set 331,500.00 331,500.004.000 bh Fitser + Sekrup 765.00 3,060.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 361,060.00K.1 SPL 1 BH PEMASANGAN LAMPU SOROT CRESBAY HPI 250 W

    1.000 bh Lampu Sorot Cresbay HPI 250 W 3,315,000.00 3,315,000.008.000 bh Penggantung/Pengikat 1,173.00 9,384.004.000 bh Penggantung Tiang 35,700.00 142,800.000.800 o/hr Pekerja 60,000.00 48,000.001.000 o/hr Tukang listrik 70,000.00 70,000.000.500 o/hr Mandor 90,000.00 45,000.00

    Jumlah 3,630,184.00

    K.1 SPL 1 BH PEMASANGAN RM ALML 2 X 40 W

    1.000 bh Armatur RM ALML TBS 318 2 X 36 W + Lampu 739,500.00 739,500.004.000 bh Pelubangan Plafon 7,650.00 30,600.004.000 bh Penggantung/Pengikat 1,173.00 4,692.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 814,292.00K.1 SPL 1 BH PEMASANGAN ARMATUR LAMPU CERMIN

    1.000 bh Armatur Lampu TCW 090 + Lampu 18 W 249,900.00 249,900.004.000 bh Penggantung/Pengikat 1,173.00 4,692.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 281,092.00K.1 SPL 1 BH PEMASANGAN KRISTAL

    1.000 bh Lampu Kristal 3 Susun 35,700,000.00 35,700,000.008.000 bh Penggantung/Pengikat 1,173.00 9,384.004.000 bh Penggantung Rante 35,700.00 142,800.004.000 o/hr Tukang listrik 70,000.00 280,000.001.000 o/hr Mandor 90,000.00 90,000.00

    Jumlah 36,222,184.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    K.1 SPL 1 BH PEMASANGAN EXHOUSE

    1.000 bh Exhouse Panasonic 433,500.00 433,500.002.000 bh Pelubangan Plafon 7,650.00 15,300.008.000 bh Penggantung/Pengikat 1,173.00 9,384.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 484,684.00K.1 SPL 1 BH PEMASANGAN ARMATUR LAMPU DINDING

    1.000 bh Armatur Lampu Dinding + Lampu 18 W 249,900.00 249,900.008.000 bh Penggantung/Pengikat 1,173.00 9,384.004.000 bh Fitser + Sekrup 765.00 3,060.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 288,844.00K.1 SPL 1 BH PEMASANGAN ARMATUR OUTBOW + LAMPU 18 W

    1.000 bh Armatur outbow + Lampu 23 W 80,070.00 80,070.004.000 bh Fitser + Sekrup 765.00 3,060.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 109,630.00K.1 SPL 1 BH PEMASANGAN LAMPU DOWN LIGHT 175

    1.000 bh Armatur Down Light 175 Artolite + Lampu 18 W 153,000.00 153,000.001.000 bh Pelubangan Plafon 7,650.00 7,650.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 187,150.00K.1 SPL 1 BH PEMASANGAN LAMPU DOWN LIGHT 125 + 8 W

    1.000 bh Armatur Down Light 125 Artolite + Lampu 8 W 127,500.00 127,500.001.000 bh Pelubangan Plafon 7,650.00 7,650.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 161,650.00K.1 SPL 1 BH PEMASANGAN LAMPU BARET + LAMPU 20 W

    1.000 bh Armatur Lampu Baret + TL Bundar 20 W 285,600.00 285,600.004.000 bh Fitser + Sekrup 765.00 3,060.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 315,160.00K.1 SPL 1 BH PEMASANGAN LAMPU RM 4 X 20 W

    1.000 bh Armatur RM ALML 4 X 20W + LAMPU 765,000.00 765,000.004.000 bh Pelubangan Plafon 7,650.00 30,600.004.000 bh Penggantung/Pengikat 1,173.00 4,692.000.500 o/hr Tukang listrik 70,000.00 35,000.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 844,292.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    K.1 SPL 1 BH PEMASANGAN LAMPU TCW 090 18 W

    1.000 bh Armatur TCW 090 + Lampu 18 W Lengkap 285,000.00 285,000.004.000 bh Pelubangan Plafon 7,650.00 30,600.004.000 bh Penggantung/Pengikat 1,173.00 4,692.000.500 o/hr Tukang listrik 70,000.00 35,000.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 364,292.00K.1 SPL 1 BH PEMASANGAN LAMPU RM 2 X 20 W

    1.000 bh Armatur RM ALML 2 X 20 W + Lampu 428,400.00 428,400.004.000 bh Pelubangan Plafon 7,650.00 30,600.004.000 bh Penggantung/Pengikat 1,173.00 4,692.000.500 o/hr Tukang listrik 70,000.00 35,000.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 507,692.00K.1 SPL 1 BH PEMASANGAN LAMPU RM 1 X 20 W

    1.000 bh Armatur RM ALML 1 X 20 W + Lampu 331,500.00 331,500.004.000 bh Pelubangan Plafon 7,650.00 30,600.004.000 bh Penggantung/Pengikat 1,173.00 4,692.000.500 o/hr Tukang listrik 70,000.00 35,000.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 410,792.00K.1 SPL 1 BH PEMASANGAN AXIAL FAN KAP. 2 PK

    1.000 bh Axial Fan Kap. 2 PK 3,315,000.00 3,315,000.004.000 bh Pelubangan Plafon/Tembok 7,650.00 30,600.004.000 bh Penggantung/Pengikat 35,700.00 142,800.002.100 o/hr Tukang listrik 70,000.00 147,000.001.800 o/hr Mandor 90,000.00 162,000.00

    Jumlah 3,797,400.00K.1 SPL 1 BH PEMASANGAN AXIAL FAN KAP. 5 PK

    1.000 bh Axial Fan Kap. 5 PK 12,495,000.00 12,495,000.004.000 bh Pelubangan Plafon/Tembok 7,650.00 30,600.004.000 bh Penggantung/Pengikat 35,700.00 142,800.002.800 o/hr Tukang listrik 70,000.00 196,000.001.200 o/hr Mandor 90,000.00 108,000.00

    Jumlah 12,972,400.00K.1 SPL 1 BH PEMASANGAN LAMPU RM 1 X 40 W

    1.000 bh Armatur RM ALML 1 X 40 W + Lampu 453,900.00 453,900.004.000 bh Pelubangan Plafon 7,650.00 30,600.004.000 bh Penggantung/Pengikat 1,173.00 4,692.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 515,692.00K.1 SPL 1 BH PEMASANGAN LAMPU BL 2 X 40 W

    1.000 bh Armatur BL 2 X 40 W + Lampu 326,400.00 326,400.004.000 bh Fitser + Sekrup 765.00 3,060.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 355,960.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    K.1 SPL 1 BH PEMASANGAN LAMPU BL 1 X 40 W

    1.000 bh Armatur BL 1 X 40 W + Lampu 260,100.00 260,100.004.000 bh Fitser + Sekrup 765.00 3,060.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 289,660.00K.1 SPL 1 BH PEMASANGAN LAMPU BL 1 X 20 W

    1.000 bh Armatur BL 1 X 20 W + Lampu 168,300.00 168,300.004.000 bh Fitser + Sekrup 765.00 3,060.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 197,860.00K.1 SPL 1 BH PEMASANGAN ARMATUR LAMPU CERMIN

    1.000 bh Armatur Lampu Cermin + Lampu 40 W 300,900.00 300,900.004.000 bh Fitser + Sekrup 765.00 3,060.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 330,460.00K.1 SPL 1 BH PEMASANGAN ARMATUR LAMPU SOROT

    1.000 bh Armatur Lampu Sorot Philips + Lampu 400 W 3,315,000.00 3,315,000.004.000 bh Fitser + Sekrup 765.00 3,060.004.000 bh Penggantung Rante 35,700.00 142,800.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 3,487,360.00K.1 SPL 1 BH PEMASANGAN AC1 PK

    1.000 bh AC 1 PK ex.Panasonic Lengkap pipa & Acc 3,550,000.00 3,550,000.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung Type B 35,700.00 142,800.000.800 o/hr Tukang listrik 70,000.00 56,000.000.400 o/hr Mandor 90,000.00 36,000.00

    Jumlah 3,790,920.00K.1 SPL 1 BH PEMASANGAN AC 2 PK

    1.000 bh AC 2 PK ex.Panasonic Lengkap pipa & Acc 6,885,000.00 6,885,000.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung Type B 35,700.00 142,800.000.800 o/hr Tukang listrik 70,000.00 56,000.000.400 o/hr Mandor 90,000.00 36,000.00

    Jumlah 7,125,920.00K.1 SPL 1 BH PEMASANGAN AC 5 PK

    1.000 bh AC 5 ex.PK Panasonic Lengkap pipa & Acc 19,635,000.00 19,635,000.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung Type B 35,700.00 142,800.000.950 o/hr Tukang listrik 70,000.00 66,500.000.500 o/hr Mandor 90,000.00 45,000.00

    Jumlah 19,895,420.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    K.1 SPL 1 BH PEMASANGAN INDOOR UNIT 50000 BTUH

    1.000 bh Indoor Unit Kap. 50.000 BTUH 15,810,000.00 15,810,000.008.000 bh Fitser + Sekrup 765.00 6,120.008.000 bh Penggantung Type B 35,700.00 285,600.001.500 o/hr Tukang listrik 70,000.00 105,000.001.200 o/hr Mandor 90,000.00 108,000.00

    Jumlah 16,314,720.00K.1 SPL 1 BH PEMASANGAN AC 10 PK

    1.000 bh AC 10 PK Panasonic Lengkap pipa & Acc 78,030,000.00 78,030,000.008.000 bh Fitser + Sekrup 765.00 6,120.008.000 bh Penggantung Type B 35,700.00 285,600.001.500 o/hr Tukang listrik 70,000.00 105,000.001.200 o/hr Mandor 90,000.00 108,000.00

    Jumlah 78,534,720.00K.1 SPL 1 BH INSTALASI PIPA REFRIGRANT 1 PK & 2 PK & 10 PK

    5.000 Mtr Pipa refrigrant leng. Isolatip 1 & 2 PK 132,600.00 663,000.0015.000 Mtr Pipa refrigrant leng. Isolatip 10 PK 290,700.00 4,360,500.008.000 bh Fitser + Sekrup 765.00 6,120.00

    10.000 bh Penggantung Type B 35,700.00 357,000.000.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.080 o/hr Mandor 90,000.00 7,200.00

    AC 1 & 2 PK Jumlah 1,116,320.00AC 10 PK 5,930,140.00

    K.1 SPL 1 TTK INSTALASI AC 1 PK & 2 PK & 10 PK(Dari Panel Menuju Titik AC)

    4.000 bh L.Bow Sekrup 2,295.00 9,180.0014.000 bh Sadel 867.00 12,138.0014.000 bh Penggantung 1,173.00 16,422.001.000 bh Inbow Dos 6,630.00 6,630.002.000 bh T-Dos 4,845.00 9,690.00

    28.000 bh Fizzer + Sekrup 765.00 21,420.0014.000 bh Kabel Teets 357.00 4,998.007.000 Mtr Pipa Spiral 1,275.00 8,925.005.000 bh L-Bow 2,295.00 11,475.003.000 btg Pipa Clipsal 8,670.00 26,010.000.200 bh Isolasi 6,000.00 1,200.000.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.080 o/hr Mandor 90,000.00 7,200.00

    15.000 m' Kabel NYM 3 X 2,5 mm 13,770.00 206,550.0015.000 m' Kabel NYM 3 X 4 mm 20,910.00 313,650.0015.000 m' Kabel NYY 4 X 10 mm2 + NYM 3 X 2.5 mm2 79,560.00 1,193,400.00

    TITIK AC 1 PK Jumlah 424,838.00TITIK AC 2 PK 531,938.00TITIK AC 10 PK 1,609,058.00

    K.1 SPL 1 M INSTALASI PIPA DRAIN 1 PK & 2 PK

    1.000 Mtr Pipa PVC AW 3/4" 7,535.25 7,535.251.000 Mtr Isolatif 2,295.00 2,295.001.000 Mtr Betelan dan Perapian tembok 22,500.00 22,500.000.250 o/hr Pekerja 60,000.00 15,000.000.120 o/hr Tukang listrik 70,000.00 8,400.000.080 o/hr Mandor 90,000.00 7,200.001.000 Mtr Pipa PVC AW 1" 8,287.50 8,287.50

    PVC AW 3/4" Jumlah 62,930.25PVC AW 1' Jumlah 71,217.75

    K.1 SPL 1 BH DUDUKAN AC 1 PK & 2 PK

    1.000 bh Dudukan AC 117,300.00 117,300.006.000 bh Fitser + Sekrup 765.00 4,590.000.200 Mtr Betelan dan Perapian tembok 22,500.00 4,500.000.250 o/hr Pekerja 60,000.00 15,000.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    0.120 o/hr Tukang listrik 70,000.00 8,400.000.080 o/hr Mandor 90,000.00 7,200.00

    Jumlah 156,990.00K.1 SPL 1 MTR DUCTING EXHOUSE

    1.000 Mtr - ukuran 300(W) x 200(H) mm 129,030.00 129,030.001.000 Mtr - ukuran 200(W) x 200(H) mm 118,320.00 118,320.001.000 Mtr Fleksibel Round Duct dia. 8" 200 mm 81,600.00 81,600.002.000 bh Penggantung Type B 35,700.00 71,400.004.000 bh Fitser + Sekrup 765.00 3,060.000.200 Mtr Betelan dan Perapian tembok 22,500.00 4,500.000.250 o/hr Pekerja 60,000.00 15,000.000.120 o/hr Tukang listrik 70,000.00 8,400.000.080 o/hr Mandor 90,000.00 7,200.00

    ukuran 300 x 200 Jumlah 238,590.00ukuran 200 x 200 Jumlah 227,880.00Fleksibel Round Duct dia. 8" 200 mm Jumlah 191,160.00

    K.1 SPL 1 MTR DUCTING AC SENTRALDucting exhaust air dicat dan glass woll isolasi

    - BJLS 601.000 Mtr - ukuran 800(W) x 350(H) mm 273,870.00 273,870.001.000 Mtr - ukuran 700(W) x 300(H) mm 252,960.00 252,960.001.000 Mtr - ukuran 500(W) x 300(H) mm 175,440.00 175,440.001.000 Mtr - ukuran 400(W) x 250(H) mm 139,230.00 139,230.001.000 Mtr - ukuran 400(W) x 200(H) mm 118,320.00 118,320.001.000 Mtr - ukuran 300(W) x 200(H) mm 100,674.00 100,674.001.000 Mtr - ukuran 200(W) x 200(H) mm 90,066.00 90,066.001.000 Mtr - ukuran 200(W) x 150(H) mm 90,066.00 90,066.001.000 Mtr - ukuran 150(W) x 150(H) mm 72,420.00 72,420.00

    Return Air grille (RAG)1.000 Mtr - ukuran 40 x 40 cm 238,680.00 238,680.00

    Return air plenum box BJLS 100 :1.000 Mtr - ukuran 4100(L) x 900(W) x 450(H) mm 9,876,660.00 9,876,660.001.000 Mtr - ukuran 900(L) x 750(W) x 450(H) mm 3,508,800.00 3,508,800.00

    Exhaust Air Louvre (EAL)1.000 Mtr - ukuran 16" x 12" 242,250.00 242,250.00

    Flexible round duct lengkap dengan isolasi tebal 1"1.000 Mtr - dia 8", 200 81,600.00 81,600.002.000 bh Penggantung Type B 35,700.00 71,400.004.000 bh Fitser + Sekrup 765.00 3,060.000.200 Mtr Betelan dan Perapian tembok 22,500.00 4,500.000.500 o/hr Pekerja 60,000.00 30,000.000.350 o/hr Tukang listrik 70,000.00 24,500.000.120 o/hr Mandor 90,000.00 10,800.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    Jumlah 144,260.00- ukuran 800(W) x 350(H) mm Jumlah 418,130.00- ukuran 700(W) x 300(H) mm Jumlah 397,220.00- ukuran 500(W) x 300(H) mm Jumlah 319,700.00- ukuran 400(W) x 250(H) mm Jumlah 283,490.00- ukuran 400(W) x 200(H) mm Jumlah 262,580.00- ukuran 300(W) x 200(H) mm Jumlah 244,934.00- ukuran 200(W) x 200(H) mm Jumlah 234,326.00- ukuran 200(W) x 150(H) mm Jumlah 234,326.00- ukuran 150(W) x 150(H) mm Jumlah 216,680.00- ukuran 40 x 40 cm Jumlah 382,940.00- ukuran 4100(L) x 900(W) x 450(H) mm Jumlah 10,020,920.00- ukuran 900(L) x 750(W) x 450(H) mm Jumlah 3,653,060.00- ukuran 16" x 12" Jumlah 386,510.00- dia 8", 200 Jumlah 225,860.00

    K.1 SPL 1 MTR TRAY KABEL LISTRIK DAN ELEKTRONIK

    Straight Tray1.000 Mtr Lebar 800 mm 270,045.00 270,045.001.000 Mtr Lebar 300 mm 222,870.00 222,870.001.000 Mtr Lebar 200 mm 205,275.00 205,275.00

    Elbow1.000 Mtr Lebar 300 mm 285,600.00 285,600.001.000 Mtr Lebar 200 mm 234,600.00 234,600.00

    Reducer Tee1.000 Mtr Lebar 300 ke 200 351,900.00 351,900.00

    2.000 bh Penggantung Type B 35,700.00 71,400.004.000 bh Fitser + Sekrup 765.00 3,060.000.200 Mtr Betelan dan Perapian tembok 22,500.00 4,500.000.250 o/hr Pekerja 60,000.00 15,000.000.120 o/hr Tukang listrik 70,000.00 8,400.000.080 o/hr Mandor 90,000.00 7,200.00

    Straight Tray Lebar 800 mm Jumlah 379,605.00Straight Tray Lebar 300 mm Jumlah 332,430.00Straight Tray Lebar 200 mm Jumlah 314,835.00Elbow Lebar 300 mm Jumlah 395,160.00Elbow Lebar 200 mm Jumlah 344,160.00Reducer Lebar 300 ke 200 Jumlah 461,460.00

    K.1 SPL 1 BH PEMASANGAN SAKELAR TUKAR1.000 bh Sakelar Tukar Nasional 66,300.00 66,300.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 92,800.00K.1 SPL 1 BH PEMASANGAN BOX SPEAKER TBSS

    1.000 bh Box Speaker ex.toa Lengkap Ass 408,000.00 408,000.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung Type B 35,700.00 142,800.000.800 o/hr Tukang listrik 70,000.00 56,000.000.200 o/hr Mandor 90,000.00 18,000.00

    Jumlah 630,920.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    K.1 SPL 1 MTR KABEL NYMHY DARI TBSS KE MBSS5.000 m' Kabel NYMHY 3 X 2,5 mm 5,737.50 28,687.508.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Sadel Pipa listrik 765.00 3,060.004.000 bh Kabel Teets 357.00 1,428.001.000 Mtr Pipa Spiral 1,275.00 1,275.001.000 bh L-Bow 2,295.00 2,295.000.500 btg Pipa Clipsal 8,670.00 4,335.000.200 bh Isolasi 6,000.00 1,200.000.250 o/hr Pekerja 60,000.00 15,000.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 89,900.50K.1 SPL 1 BH PEMASANGAN SPEAKER PROFESIONAL

    1.000 bh Speaker Profesional ex.JBL Lengkap Ass 0.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung Type B 35,700.00 142,800.001.000 o/hr Tukang listrik 70,000.00 70,000.000.500 o/hr Mandor 90,000.00 45,000.00

    Jumlah 263,920.00K.1 SPL 1 BH PEMASANGAN OUTLET MIC

    1.000 bh Outlet Mic Panasonic Lengkap Ass 0.008.000 bh Fitser + Sekrup 765.00 6,120.001.000 bh Inbow Dos 6,630.00 6,630.001.000 bh T-Dos 4,845.00 4,845.00

    10.000 bh Fizzer + Sekrup 765.00 7,650.005.000 bh Kabel Teets 357.00 1,785.001.000 Mtr Pipa Spiral 1,275.00 1,275.001.000 bh L-Bow 2,295.00 2,295.001.000 btg Pipa Clipsal 8,670.00 8,670.000.200 bh Isolasi 6,000.00 1,200.000.500 o/hr Tukang listrik 70,000.00 35,000.000.200 o/hr Mandor 90,000.00 18,000.00

    Jumlah 93,470.00K.1 SPL 1 BH PEMASANGAN HIDRANT PILAR

    1.000 bh Hidrant Pilar 2 Mata Lengkap Ass + Box hidrant 6,120,000.00 6,120,000.000.025 m3 Conrete campuran beton 2,500,000.00 62,500.004.000 bh Mur Baut 15,000.00 60,000.001.000 bh Karet silent 55,000.00 55,000.001.200 o/hr Pekerja 60,000.00 72,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 6,409,000.00K.1 SPL 1 BH PEMASANGAN SIEMESE CONNECTION

    1.000 bh Siemese Connection 3,825,000.00 3,825,000.000.125 m3 Conrete campuran beton 2,500,000.00 312,500.004.000 bh Mur Baut 15,000.00 60,000.001.000 bh Karet silent 55,000.00 55,000.001.200 o/hr Pekerja 60,000.00 72,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 4,364,000.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    K.1 SPL 1 BH PEMASANGAN AC 1 PK

    1.000 bh AC 1 PK ex.Panasonic Lengkap pipa & Acc 3,621,000.00 3,621,000.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung Type B 35,700.00 142,800.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 3,809,420.00K.1 SPL 1 BH PEMASANGAN Outlet TLP

    1.000 bh Outlet TLP/Fax/Internet 96,900.00 96,900.008.000 bh Fitser + Sekrup 765.00 6,120.001.000 bh Inbow Dos 6,630.00 6,630.001.000 bh T-Dos 4,845.00 4,845.004.000 bh Fizzer + Sekrup 765.00 3,060.004.000 bh Kabel Teets 357.00 1,428.001.000 Mtr Pipa Spiral 1,275.00 1,275.001.000 bh L-Bow 2,295.00 2,295.001.000 btg Pipa Clipsal 8,670.00 8,670.000.200 bh Isolasi 6,000.00 1,200.000.500 o/hr Tukang listrik 70,000.00 35,000.000.200 o/hr Mandor 90,000.00 18,000.00

    Jumlah 185,423.00K.1 SPL 1 BH PEMASANGAN TERMINAL BOX TLP

    1.000 bh Terminal Box Tlp Lengkap Ass 331,500.00 331,500.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung Type B 35,700.00 142,800.001.000 mtr Ducting Jalur kabel 22,950.00 22,950.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 542,870.00K.1 SPL 1 BH PEMASANGAN OUTLET TV

    1.000 bh Outlet TV 93,330.00 93,330.008.000 bh Fitser + Sekrup 765.00 6,120.001.000 bh Inbow Dos 6,630.00 6,630.001.000 bh T-Dos 4,845.00 4,845.004.000 bh Fizzer + Sekrup 765.00 3,060.004.000 bh Kabel Teets 357.00 1,428.001.000 Mtr Pipa Spiral 1,275.00 1,275.001.000 bh L-Bow 2,295.00 2,295.001.000 btg Pipa Clipsal 8,670.00 8,670.000.200 bh Isolasi 6,000.00 1,200.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 155,353.00K.1 SPL 1 BH PEMASANGAN TERMINAL BOX TV + BOSTER

    1.000 bh Terminal Box TV + Boster 300,900.00 300,900.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung Type B 35,700.00 142,800.001.000 mtr Ducting Jalur kabel 22,950.00 22,950.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 512,270.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    K.1 SPL 1 BH PEMASANGAN MAIN SENTRAL TV1.000 Set Antenna UHF 673,200.00 673,200.001.000 Set Antenna VHF 510,000.00 510,000.001.000 Set TV test point 14" 3,825,000.00 3,825,000.001.000 Set DVD / VCD Player 2,448,000.00 2,448,000.001.000 Set Passive Combiner 16 channel 1,479,000.00 1,479,000.001.000 Set Booster Amplifier 2,397,000.00 2,397,000.001.000 Set Grounding 2,550,000.00 2,550,000.001.000 Set kabel feeder dari antenna lokal 19,890.00 19,890.001.000 Set Spliter 4 way 1,887,000.00 1,887,000.001.000 Set Gantungan TV 459,000.00 459,000.001.000 Set Booster Amplifier 2,397,000.00 2,397,000.00

    0.250 m3 Dudukan Antene 2,550,000.00 637,500.004.000 bh Kabel Teets 357.00 1,428.008.000 bh Fitser + Sekrup 765.00 6,120.001.000 mtr Setting alat 150,000.00 150,000.004.000 bh Mur Baut 15,300.00 61,200.002.500 o/hr Pekerja 60,000.00 150,000.002.200 o/hr Tukang listrik 70,000.00 154,000.001.250 o/hr Mandor 90,000.00 112,500.00

    Jumlah 635,248.00Antenna UHF Jumlah 1,945,948.00Antenna VHF Jumlah 1,782,748.00TV test point 14" Jumlah 4,460,248.00DVD / VCD Player Jumlah 3,083,248.00Passive Combiner 16 channel Jumlah 2,114,248.00Booster Amplifier Jumlah 3,032,248.00Grounding Jumlah 3,185,248.00kabel feeder dari antenna lokal Jumlah 655,138.00Spliter 4 way Jumlah 2,522,248.00Gantungan TV Jumlah 1,094,248.00Booster Amplifier Jumlah 3,032,248.00

    K.1 SPL 1 MTR KABEL COAXIAL DARI COMBINER KE SPLITER1.000 m' Kabel Coaxial 7c-2v, 75 ohm 28,050.00 28,050.004.000 bh Fitser + Sekrup 765.00 3,060.002.000 bh Sadel Pipa listrik 765.00 1,530.002.000 bh Kabel Teets 357.00 714.000.200 Mtr Pipa Spiral 1,275.00 255.001.000 bh L-Bow 2,295.00 2,295.000.500 btg Pipa Clipsal 8,670.00 4,335.000.200 bh Isolasi 6,000.00 1,200.000.250 o/hr Pekerja 60,000.00 15,000.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 82,939.00K.1 SPL 1 MTR KABEL ITC DARI TBTLP KE MDF

    1.000 m' Kabel ITC 20x2x0,6 mm 26,928.00 26,928.001.000 m' Kabel ITC (40+40)x2x0,6 mm 96,900.00 96,900.001.000 m' Kabel ITC 60x2x0,6 mm 76,500.00 76,500.001.000 m' Kabel ITC (40+20)x2x0,6 mm 87,210.00 87,210.004.000 bh Fitser + Sekrup 765.00 3,060.002.000 bh Sadel Pipa listrik 765.00 1,530.002.000 bh Kabel Teets 357.00 714.000.200 Mtr Pipa Spiral 1,275.00 255.001.000 bh L-Bow 2,295.00 2,295.000.500 btg Pipa Clipsal 8,670.00 4,335.000.200 bh Isolasi 6,000.00 1,200.000.250 o/hr Pekerja 60,000.00 15,000.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Kabel ITC 20x2x0,6 mm Jumlah 81,817.00Kabel ITC (40+40)x2x0,6 mm Jumlah 151,789.00Kabel ITC 60x2x0,6 mm Jumlah 131,389.00Kabel ITC (40+20)x2x0,6 mm Jumlah 142,099.00

    K.1 SPL 1 BH PEMASANGAN PABX

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    1.000 Set PABX 6 CO 70 ext. 56,100,000.00 56,100,000.004.000 bh Press Kabel 15,810.00 63,240.002.000 bh Pengukuran/Injection 765,000.00 1,530,000.004.000 bh Penggantung/Pengikat Type B 35,700.00 142,800.002.000 mtr Ducting Jalur kabel 22,950.00 45,900.00

    24.000 bh Kabel Teets 357.00 8,568.008.000 bh Fitser + Sekrup 765.00 6,120.001.000 mtr Setting alat 1,500,000.00 1,500,000.004.000 bh Mur Baut 15,300.00 61,200.005.000 o/hr Pekerja 60,000.00 300,000.003.500 o/hr Tukang listrik 70,000.00 245,000.002.350 o/hr Mandor 90,000.00 211,500.00

    Jumlah 60,214,328.00K.1 SPL 1 BH PEMASANGAN TELEPON

    1.000 bh Armatur BL 1 X 20 W + Lampu 178,500.00 178,500.004.000 bh Fitser + Sekrup 765.00 3,060.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 208,060.00K.1 SPL 1 BH PEMASANGAN MAIN SENTRAL CCTV

    1.000 Set Digital Video Recorder 32 Channel camera 48,960,000.00 48,960,000.001.000 Set Video Manager 8,160,000.00 8,160,000.001.000 Set Rack Metal 32" 2,550,000.00 2,550,000.001.000 Set LCD monitor 32" 4,182,000.00 4,182,000.001.000 Set Fixed Color camera dome type, CCD, 1/4" Lens, 2,488,800.00 2,488,800.001.000 Set Rotater Color camera dome type, CCD, 1/4" Lens, 3,733,200.00 3,733,200.00

    0.250 m3 Rak Main Central CCTV 2,550,000.00 637,500.004.000 bh Kabel Teets 357.00 1,428.008.000 bh Fitser + Sekrup 765.00 6,120.003.000 mtr Setting alat 150,000.00 450,000.004.000 bh Mur Baut 15,300.00 61,200.002.500 o/hr Pekerja 60,000.00 150,000.002.200 o/hr Tukang listrik 70,000.00 154,000.001.250 o/hr Mandor 90,000.00 112,500.00

    Jumlah 935,248.00Digital Video Recorder 16 Channel camera Jumlah 49,895,248.00Video Manager Jumlah 9,095,248.00Rack Metal 32" Jumlah 3,485,248.00LCD monitor 32" Jumlah 5,117,248.00Fixed Color camera dome type, CCD, 1/4" Lens, Jumlah 3,424,048.00Rotater Color camera dome type, CCD, 1/4" Lens, Jumlah 4,668,448.00

    K.1 SPL 1 BH PEMASANGAN MAIN SOUND SYSTEM

    1.000 Set Power Amplifier 240 W 8,466,000.00 8,466,000.001.000 Set Mixer pre-amplifier 1x240 W 5,049,000.00 5,049,000.001.000 Set Desk Microphone + chime gong 2,295,000.00 2,295,000.001.000 Set speaker selector 10 zones 1,275,000.00 1,275,000.001.000 Set AM/FM tuner/ CD/MP3 + Antenna 4,233,000.00 4,233,000.001.000 Set Rack cabinet c/w accesoris 12,750,000.00 12,750,000.001.000 Set Horn Speaker 15 W 408,000.00 408,000.00

    4.000 bh Kabel Teets 357.00 1,428.008.000 bh Fitser + Sekrup 765.00 6,120.001.000 mtr Setting alat 150,000.00 150,000.004.000 bh Mur Baut 15,300.00 61,200.000.250 o/hr Pekerja 60,000.00 15,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.250 o/hr Mandor 90,000.00 22,500.00

    Jumlah 291,248.00Power Amplifier 240 W 8,757,248.00Mixer pre-amplifier 1x240 W 5,340,248.00Desk Microphone + chime gong 2,586,248.00speaker selector 10 zones 1,566,248.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    AM/FM tuner/ CD/MP3 + Antenna 4,524,248.00Rack cabinet c/w accesoris 13,041,248.00Horn Speaker 15 W 699,248.00

    K.1 SPL 1 BH PEMASANGAN CEILING SPEAKER1.000 bh Ceiling Speaker + box 204,000.00 204,000.001.000 bh Ceiling Speaker Panasonic Lengkap Ass 127,500.00 127,500.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung/Pengikat 1,173.00 4,692.000.500 o/hr Tukang listrik 70,000.00 35,000.000.100 o/hr Mandor 90,000.00 9,000.00

    Ceiling Speaker Jumlah 182,312.00Ceiling Speaker + Box 258,812.00

    K.1 SPL 1 BH PEMASANGAN TONE CONTROL

    1.000 bh Tone Control Panasonic Lengkap Ass 178,500.00 178,500.004.000 bh Penggantung/Pengikat 1,173.00 4,692.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 209,692.00K.1 SPL 1 BH PEMASANGAN ROR (FIRE DETECTOR)

    1.000 bh ROR ex.Gunnebo/Ozeki 127,500.00 127,500.001.000 bh Smoke detector 306,000.00 306,000.001.000 bh Manual break glass 204,000.00 204,000.001.000 bh Alarm bell 255,000.00 255,000.001.000 bh Indicator lamp 127,500.00 127,500.001.000 bh Alat pemadam api ringan 3,5 kg 1,020,000.00 1,020,000.00

    0.200 Mtr Betelan dan Perapian tembok 22,500.00 4,500.004.000 bh Fitser + Sekrup 765.00 3,060.004.000 bh Penggantung/Pengikat 1,173.00 4,692.000.250 o/hr Pekerja 60,000.00 15,000.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    ROR ex.Gunnebo/Ozeki Jumlah 181,252.00Smoke detector 359,752.00Manual break glass 257,752.00Alarm bell 308,752.00Indicator lamp 181,252.00Alat pemadam api ringan 3,5 kg 1,073,752.00

    K.1 SPL 1 BH PEMASANGAN BOX HIDRANT + TERMINAL BOX

    1.000 Set Box Hidrant + Terminal Box + Announciator 10 zona 7,650,000.00 7,650,000.001.000 Set Box Hidrant + Terminal Box + Announciator 40 Zona 16,320,000.00 16,320,000.001.000 Set MCFA 40 Zona 45,900,000.00 45,900,000.00

    4.000 bh Kabel Teets 357.00 1,428.008.000 bh Fitser + Sekrup 765.00 6,120.001.000 mtr Setting alat 500,000.00 500,000.004.000 bh Mur Baut 15,300.00 61,200.003.500 o/hr Pekerja 60,000.00 210,000.002.800 o/hr Tukang listrik 70,000.00 196,000.001.400 o/hr Mandor 90,000.00 126,000.00

    BOX HIDRANT 10 ZONA Jumlah 8,750,748.00BOX HIDRANT 40 ZONA 17,420,748.00MCFA 40 ZONA 47,000,748.00

    K.1 SPL 1 MTR KABEL MULTI PAIR FIRE DETECTOR5.000 m' Kabel NYA 3 X 1,5 mm 4,590.00 22,950.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Fizzer + Sekrup 765.00 3,060.004.000 bh Kabel Teets 357.00 1,428.001.000 Mtr Pipa Spiral 1,275.00 1,275.001.000 bh L-Bow 2,295.00 2,295.000.500 btg Pipa Clipsal 8,670.00 4,335.000.200 bh Isolasi 6,000.00 1,200.000.250 o/hr Pekerja 60,000.00 15,000.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    0.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 84,163.00K.1 SPL 1 BH PEMASANGAN ARMATUR LAMPU EMERGENSI

    1.000 bh Armatur Lampu Emergensi 20 W Lengkap 663,000.00 663,000.008.000 bh Fitser + Sekrup 765.00 6,120.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 708,620.00K.1 SPL 1 BH PEMASANGAN MCB GROUP + KWH METER

    1.000 bh MCB Grup 3 + Kwh Meter Pembanding 1,275,000.00 1,275,000.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung Type B 35,700.00 142,800.001.000 mtr Ducting Jalur kabel 22,950.00 22,950.002.000 o/hr Tukang listrik 70,000.00 140,000.001.000 o/hr Mandor 90,000.00 90,000.00

    Jumlah 1,676,870.00K.1 SPL 1 BH PEMASANGAN POMPA JOCKY

    3.000 Set Pompa Jocky + Panel Kontrol 9,690,000.00 29,070,000.001.000 Set Heather 5,100,000.00 5,100,000.001.000 Set Pressure Switch 1,275,000.00 1,275,000.000.250 m3 Dudukan Pompa 2,550,000.00 637,500.001.500 M Karet Silent 56,100.00 84,150.008.000 bh Mur Baut 15,300.00 122,400.006.000 o/hr Tukang listrik 70,000.00 420,000.002.000 o/hr Mandor 90,000.00 180,000.00

    Jumlah 36,889,050.00K.1 SPL 1 BH PEMASANGAN POMPA PENGISIAN

    2.000 Set Pompa Pengisian + Panel Kontrol 63,750,000.00 127,500,000.001.000 Set Heather 5,100,000.00 5,100,000.001.000 Set Pressure Switch 1,275,000.00 1,275,000.000.250 m3 Dudukan Pompa 2,550,000.00 637,500.001.500 M Karet Silent 56,100.00 84,150.008.000 bh Mur Baut 15,300.00 122,400.006.000 o/hr Tukang listrik 70,000.00 420,000.002.000 o/hr Mandor 90,000.00 180,000.00

    Jumlah 135,319,050.00K.1 SPL 1 BH PEMASANGAN PANEL LISTRIK MDP

    1.000 bh Panel MDP 1 - 12 MCCB Group 45,900,000.00 45,900,000.0096.000 bh Moff Kabel 229,500.00 22,032,000.0096.000 bh Press Kabel 117,300.00 11,260,800.001.000 bh Pengukuran/Injection 3,213,000.00 3,213,000.000.500 m3 Dudukan Panel dari beton 2,550,000.00 1,275,000.002.000 M Karet Silent 56,100.00 112,200.008.000 bh Mur Baut 15,300.00 122,400.006.000 o/hr Tukang listrik 70,000.00 420,000.003.000 o/hr Mandor 90,000.00 270,000.00

    Jumlah 84,605,400.00K.1 SPL 1 BH PEMASANGAN PANEL LISTRIK SUB MDP TYPE A

    1.000 bh Panel Sub MDP 61 - 90 Grup 35,700,000.00 35,700,000.00120.000 bh Moff Kabel 127,500.00 15,300,000.00120.000 bh Press Kabel 86,700.00 10,404,000.00

    2.000 bh Pengukuran/Injection 1,500,000.00 3,000,000.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung/Pengikat Type B 35,700.00 142,800.002.000 mtr Ducting Jalur kabel 22,950.00 45,900.004.000 o/hr Tukang listrik 70,000.00 280,000.002.000 o/hr Mandor 90,000.00 180,000.00

    Jumlah 65,058,820.00K.1 SPL 1 BH PEMASANGAN PANEL LISTRIK SUB MDP TYPE B

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    1.000 bh Panel MDP 31 - 60 Grup 28,050,000.00 28,050,000.008.000 bh Moff Kabel 86,700.00 693,600.008.000 bh Press Kabel 45,900.00 367,200.002.000 bh Pengukuran/Injection 1,530,000.00 3,060,000.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung/Pengikat Type B 35,700.00 142,800.002.000 mtr Ducting Jalur kabel 22,950.00 45,900.003.000 o/hr Tukang listrik 70,000.00 210,000.001.000 o/hr Mandor 90,000.00 90,000.00

    Jumlah 32,665,620.00K.1 SPL 1 BH PEMASANGAN PANEL LISTRIK SUB MDP TYPE C

    1.000 bh Panel MDP 16 - 30 Grup 18,870,000.00 18,870,000.008.000 bh Moff Kabel 66,300.00 530,400.008.000 bh Press Kabel 35,700.00 285,600.002.000 bh Pengukuran/Injection 1,173,000.00 2,346,000.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung/Pengikat Type B 35,700.00 142,800.002.000 mtr Ducting Jalur kabel 22,950.00 45,900.002.000 o/hr Tukang listrik 70,000.00 140,000.001.000 o/hr Mandor 90,000.00 90,000.00

    Jumlah 22,456,820.00K.1 SPL 1 BH PEMASANGAN PANEL LISTRIK SUB MDP TYPE D

    1.000 bh Panel MDP 0 - 15 Grup 5,610,000.00 5,610,000.008.000 bh Moff Kabel 25,500.00 204,000.008.000 bh Press Kabel 15,810.00 126,480.002.000 bh Pengukuran/Injection 765,000.00 1,530,000.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung/Pengikat Type B 35,700.00 142,800.002.000 mtr Ducting Jalur kabel 22,950.00 45,900.001.000 o/hr Tukang listrik 70,000.00 70,000.000.500 o/hr Mandor 90,000.00 45,000.00

    Jumlah 7,780,300.00K.1 SPL 1 BH PEMASANGAN PANEL LISTRIK POMPA DISTRIBUSI

    1.000 bh Panel MDP 0 - 12 Grup 3,570,000.00 3,570,000.008.000 bh Moff Kabel 25,500.00 204,000.008.000 bh Press Kabel 15,810.00 126,480.002.000 bh Pengukuran/Injection 765,000.00 1,530,000.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung/Pengikat Type B 35,700.00 142,800.002.000 mtr Ducting Jalur kabel 22,950.00 45,900.001.000 Level Control Water & kabel 765,000.00 765,000.001.000 o/hr Tukang listrik 70,000.00 70,000.000.500 o/hr Mandor 90,000.00 45,000.00

    Jumlah 6,505,300.00K.1 SPL 1 BH PEMASANGAN PANEL LISTRIK POMPA AIR BOSTER

    1.000 bh Panel MDP 0 - 15 Grup 428,400.00 428,400.008.000 bh Moff Kabel 25,500.00 204,000.008.000 bh Press Kabel 15,810.00 126,480.002.000 bh Pengukuran/Injection 765,000.00 1,530,000.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung/Pengikat Type B 35,700.00 142,800.001.000 Pressure Switch 1,173,000.00 1,173,000.002.000 mtr Ducting Jalur kabel 22,950.00 45,900.001.000 o/hr Tukang listrik 70,000.00 70,000.000.500 o/hr Mandor 90,000.00 45,000.00

    Jumlah 3,771,700.00K.1 SPL 1 BH PEMASANGAN PENANGKAL PETIR

    1.000 bh Earting Road 2,397,000.00 2,397,000.0050.000 mtr Kabel BC 22,950.00 1,147,500.0022.000 Btg Pipa listrik 8,670.00 190,740.001.000 bh Pengukuran/Injection 433,500.00 433,500.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    110.000 bh Sadel 867.00 95,370.0022.000 bh Penggantung/Pengikat 35,700.00 785,400.00

    220.000 bh Fizzer + Sekrup 765.00 168,300.008.000 Mtr Pipa Spiral 1,275.00 10,200.00

    12.000 bh L-Bow 2,295.00 27,540.001.000 Penangkal Petir ex UFO + Pipa 5,610,000.00 5,610,000.002.500 o/hr Pekerja 60,000.00 150,000.002.100 o/hr Tukang listrik 70,000.00 147,000.001.200 o/hr Mandor 90,000.00 108,000.00

    Jumlah 11,270,550.00K.1 SPL 1 MTR PEMASANGAN PENARIKAN KABEL

    1.000 Meter Kabel N2XSEFGby 3x120 mm 1,275,000.00 1,275,000.001.000 Meter Kabel N2XSY 3x1x95 mm2 892,500.00 892,500.001.000 Meter Penggalian kedalaman 1 meter 78,030.00 78,030.004.000 Bh Pengikat 35,700.00 142,800.002.000 bh Beton pracetak 50X30X10 66,300.00 132,600.000.400 m3 Timbunan 161,364.00 64,545.600.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Kabel N2XSEFGBY 3 X 120 mm2 Jumlah 1,780,475.60Kabel N2XSY 3X1X120 mm2 1,397,975.60

    K.1 SPL 1 MTR PEMASANGAN PENARIKAN KABEL1.000 Meter Kabel NYY 4 X 400 mm2 1,989,000.00 1,989,000.001.000 Meter Penggalian kedalaman 1 meter 78,030.00 78,030.004.000 Bh Pengikat 35,700.00 142,800.002.000 bh Beton pracetak 50X30X10 66,300.00 132,600.000.400 m3 Timbunan 161,364.00 64,545.600.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 2,494,475.60K.1 SPL 1 MTR PEMASANGAN PENARIKAN KABEL

    1.000 Meter Kabel NYY 4 X 240 mm2 1,418,004.00 1,418,004.001.000 Meter Penggalian kedalaman 1 meter 78,030.00 78,030.004.000 Bh Pengikat 35,700.00 142,800.002.000 bh Beton pracetak 50X30X10 66,300.00 132,600.000.400 m3 Timbunan 161,364.00 64,545.600.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 1,923,479.60K.1 SPL 1 MTR PEMASANGAN PENARIKAN KABEL

    1.000 Meter Kabel NYY 4 X 185 mm2 1,083,342.00 1,083,342.001.000 Meter Penggalian kedalaman 1 meter 78,030.00 78,030.004.000 Bh Pengikat 35,700.00 142,800.002.000 bh Beton pracetak 50X30X10 66,300.00 132,600.000.400 m3 Timbunan 161,364.00 64,545.600.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 1,588,817.60K.1 SPL 1 MTR PEMASANGAN PENARIKAN KABEL

    1.000 Meter Kabel NYY 4 X 150 mm2 870,978.00 870,978.001.000 Meter Penggalian kedalaman 1 meter 78,030.00 78,030.004.000 Bh Pengikat 35,700.00 142,800.002.000 bh Beton pracetak 50X30X10 66,300.00 132,600.000.400 m3 Timbunan 161,364.00 64,545.600.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 1,376,453.60

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    K.1 SPL 1 MTR PEMASANGAN PENARIKAN KABEL

    1.000 Meter Kabel NYY 4 X 120 mm2 707,574.00 707,574.001.000 Meter Penggalian kedalaman 1 meter 78,030.00 78,030.004.000 Bh Pengikat 35,700.00 142,800.002.000 bh Beton pracetak 50X30X10 66,300.00 132,600.000.400 m3 Timbunan 161,364.00 64,545.600.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 1,213,049.60K.1 SPL 1 MTR PEMASANGAN PENARIKAN KABEL

    1.000 Meter Kabel NYY 4 X 95 mm2 565,284.00 565,284.001.000 Meter Penggalian kedalaman 1 meter 19,507.50 19,507.504.000 Bh Pengikat 8,925.00 35,700.002.000 bh Beton pracetak 50X30X10 16,575.00 33,150.000.400 m3 Timbunan 40,341.00 16,136.400.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 757,277.90K.1 SPL 1 MTR PEMASANGAN PENARIKAN KABEL

    1.000 Meter Kabel NYY 4 X 70 mm2 411,162.00 411,162.001.000 Meter Penggalian kedalaman 1 meter 19,507.50 19,507.504.000 Bh Pengikat 8,925.00 35,700.002.000 bh Beton pracetak 50X30X10 16,575.00 33,150.000.400 m3 Timbunan 40,341.00 16,136.400.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 603,155.90K.1 SPL 1 MTR PEMASANGAN PENARIKAN KABEL

    1.000 Meter Kabel NYY 4 X 50 mm2 291,006.00 291,006.001.000 Meter Penggalian kedalaman 1 meter 19,507.50 19,507.502.000 Bh Pengikat 8,925.00 17,850.002.000 bh Beton pracetak 50X30X10 16,575.00 33,150.000.200 m3 Timbunan 40,341.00 8,068.200.500 o/hr Pekerja 60,000.00 30,000.000.250 o/hr Tukang listrik 70,000.00 17,500.000.150 o/hr Mandor 90,000.00 13,500.00

    Jumlah 430,581.70K.1 SPL 1 MTR PEMASANGAN PENARIKAN KABEL

    1.000 Meter Kabel NYY 4 X 35 mm2 213,894.00 213,894.001.000 Meter Penggalian kedalaman 1 meter 19,507.50 19,507.502.000 Bh Pengikat 8,925.00 17,850.002.000 bh Beton pracetak 50X30X10 16,575.00 33,150.000.200 m3 Timbunan 40,341.00 8,068.200.500 o/hr Pekerja 60,000.00 30,000.000.250 o/hr Tukang listrik 70,000.00 17,500.000.150 o/hr Mandor 90,000.00 13,500.00

    Jumlah 353,469.70K.1 SPL 1 MTR PEMASANGAN PENARIKAN KABEL

    1.000 Meter Kabel NYY 4 X 25 mm2 157,182.00 157,182.001.000 Meter Penggalian kedalaman 1 meter 19,507.50 19,507.502.000 Bh Pengikat 8,925.00 17,850.002.000 bh Beton pracetak 50X30X10 16,575.00 33,150.000.200 m3 Timbunan 40,341.00 8,068.200.500 o/hr Pekerja 60,000.00 30,000.000.250 o/hr Tukang listrik 70,000.00 17,500.000.150 o/hr Mandor 90,000.00 13,500.00

    Jumlah 296,757.70

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    K.1 SPL 1 MTR PEMASANGAN PENARIKAN KABEL

    1.000 Meter Kabel NYY 4 X 16 mm2 102,510.00 102,510.001.000 Meter Penggalian kedalaman 1 meter 19,507.50 19,507.502.000 Bh Pengikat 8,925.00 17,850.002.000 bh Beton pracetak 50X30X10 16,575.00 33,150.000.200 m3 Timbunan 40,341.00 8,068.200.500 o/hr Pekerja 60,000.00 30,000.000.250 o/hr Tukang listrik 70,000.00 17,500.000.150 o/hr Mandor 90,000.00 13,500.00

    Jumlah 242,085.70K.1 SPL 1 MTR PEMASANGAN PENARIKAN KABEL

    1.000 Meter Kabel NYY 4 X 10 mm2 65,790.00 65,790.001.000 Meter Penggalian kedalaman 1 meter 19,507.50 19,507.502.000 Bh Pengikat 8,925.00 17,850.002.000 bh Beton pracetak 50X30X10 16,575.00 33,150.000.200 m3 Timbunan 40,341.00 8,068.200.500 o/hr Pekerja 60,000.00 30,000.000.250 o/hr Tukang listrik 70,000.00 17,500.000.150 o/hr Mandor 90,000.00 13,500.00

    Jumlah 205,365.70K.1 SPL 1 TITIK PEMASANGAN INSTALASI TELEPON/FAX

    (Dari Terminal Box Ketitik Telepon)1.000 bh L.Bow Sekrup 2,295.00 2,295.00

    15.000 m' Kabel Telepon 4 X 0,6 mm2 2,295.00 34,425.0030.000 bh Sadel 867.00 26,010.0015.000 bh Penggantung 1,173.00 17,595.001.000 bh Inbow Dos 6,630.00 6,630.002.000 bh T-Dos 4,845.00 9,690.00

    60.000 bh Fizzer + Sekrup 765.00 45,900.0015.000 bh Kabel Teets 357.00 5,355.002.000 Mtr Pipa Spiral 1,275.00 2,550.005.000 bh L-Bow 2,295.00 11,475.006.250 btg Pipa Clipsal 8,670.00 54,187.500.200 bh Isolasi 6,000.00 1,200.000.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.080 o/hr Mandor 90,000.00 7,200.00

    Jumlah 307,512.50K.1 SPL 1 TITIK PEMASANGAN INSTALASI SOUND SYSTEM

    (Dari Terminal Box Sound System ke Tone Control Menuju Titik Speaker)1.000 bh L.Bow Sekrup 2,295.00 2,295.00

    10.000 m' Kabel NYMHY 3 X 1,5 3,825.00 38,250.0020.000 bh Sadel 867.00 17,340.0010.000 bh Penggantung 1,173.00 11,730.001.000 bh Inbow Dos 6,630.00 6,630.002.000 bh T-Dos 4,845.00 9,690.00

    40.000 bh Fizzer + Sekrup 765.00 30,600.0010.000 bh Kabel Teets 357.00 3,570.002.000 Mtr Pipa Spiral 1,275.00 2,550.005.000 bh L-Bow 2,295.00 11,475.004.167 btg Pipa Clipsal 8,670.00 36,125.000.200 bh Isolasi 6,000.00 1,200.000.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.080 o/hr Mandor 90,000.00 7,200.00

    Jumlah 261,655.00K.1 SPL 1 TITIK PEMASANGAN INSTALASI FIRE DETECTOR

    (Dari Terminal Box Ke Titik Fire Detector)1.000 bh L.Bow Sekrup 2,295.00 2,295.00

    10.000 m' Kabel NYA 1,5 mm2 2,295.00 22,950.0020.000 bh Sadel 867.00 17,340.0010.000 bh Penggantung 1,173.00 11,730.001.000 bh Inbow Dos 6,630.00 6,630.002.000 bh T-Dos 4,845.00 9,690.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    40.000 bh Fizzer + Sekrup 765.00 30,600.0010.000 bh Kabel Teets 357.00 3,570.002.000 Mtr Pipa Spiral 1,275.00 2,550.005.000 bh L-Bow 2,295.00 11,475.004.167 btg Pipa Clipsal 8,670.00 36,125.000.200 bh Isolasi 6,000.00 1,200.000.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.080 o/hr Mandor 90,000.00 7,200.00

    Jumlah 246,355.00K.1 SPL 1 TITIK PEMASANGAN INSTALASI CCTV

    (Dari Terminal Box TV ke Boster Kemudian Ke Titik Outlet TV)1.000 bh L.Bow Sekrup 2,295.00 2,295.00

    20.000 m' Kabel RG 59 5,355.00 107,100.0040.000 bh Sadel 867.00 34,680.0020.000 bh Penggantung 1,173.00 23,460.001.000 bh Inbow Dos 6,630.00 6,630.002.000 bh T-Dos 4,845.00 9,690.00

    80.000 bh Fizzer + Sekrup 765.00 61,200.0020.000 bh Kabel Teets 357.00 7,140.002.000 Mtr Pipa Spiral 1,275.00 2,550.005.000 bh L-Bow 2,295.00 11,475.008.333 btg Pipa Clipsal 8,670.00 72,250.000.200 bh Isolasi 6,000.00 1,200.000.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.080 o/hr Mandor 90,000.00 7,200.00

    Jumlah 429,870.00K.1 SPL 1 TITIK PEMASANGAN INSTALASI DATA

    (Dari Terminal Box ke titik outlet data)1.000 bh L.Bow Sekrup 2,295.00 2,295.00

    15.000 m' Kabel Data UTV cat 6e 17,850.00 267,750.0030.000 bh Sadel 867.00 26,010.0015.000 bh Penggantung 1,173.00 17,595.001.000 bh Inbow Dos 6,630.00 6,630.002.000 bh T-Dos 4,845.00 9,690.00

    60.000 bh Fizzer + Sekrup 765.00 45,900.0015.000 bh Kabel Teets 357.00 5,355.002.000 Mtr Pipa Spiral 1,275.00 2,550.005.000 bh L-Bow 2,295.00 11,475.006.250 btg Pipa Clipsal 8,670.00 54,187.500.200 bh Isolasi 6,000.00 1,200.000.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.080 o/hr Mandor 90,000.00 7,200.00

    Jumlah 540,837.50K.1 SPL 1 TITIK PEMASANGAN INSTALASI TV

    (Dari Terminal Box TV ke Boster Kemudian Ke Titik Outlet TV)1.000 bh L.Bow Sekrup 2,295.00 2,295.00

    10.000 m' Kabel RG 8 5,610.00 56,100.0020.000 bh Sadel 867.00 17,340.0010.000 bh Penggantung 1,173.00 11,730.001.000 bh Inbow Dos 6,630.00 6,630.002.000 bh T-Dos 4,845.00 9,690.00

    40.000 bh Fizzer + Sekrup 765.00 30,600.0010.000 bh Kabel Teets 357.00 3,570.002.000 Mtr Pipa Spiral 1,275.00 2,550.005.000 bh L-Bow 2,295.00 11,475.004.167 btg Pipa Clipsal 8,670.00 36,125.000.200 bh Isolasi 6,000.00 1,200.000.800 o/hr Pekerja 60,000.00 48,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.080 o/hr Mandor 90,000.00 7,200.00

    Jumlah 279,505.00K.1 SPL 1 MTR KABEL UTV DARI STAR HUB KE SWITCH HUB

    1.000 m' Kabel UTV cat 6e 15,300.00 15,300.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    2.000 bh Sadel 765.00 1,530.004.000 bh Fizzer + Sekrup 765.00 3,060.004.000 bh Kabel Teets 357.00 1,428.001.000 Mtr Pipa Spiral 1,275.00 1,275.001.000 bh L-Bow 2,295.00 2,295.000.500 btg Pipa Clipsal 8,670.00 4,335.000.200 bh Isolasi 6,000.00 1,200.000.250 o/hr Pekerja 60,000.00 15,000.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Jumlah 71,923.00K.1 SPL 1 BH PERALATAN DATA

    1.000 Set Switch hub + rak dan Setting Program 12,750,000.00 12,750,000.001.000 Set Patch panel 5,610,000.00 5,610,000.001.000 Set Star hub 12 port 1,530,000.00 1,530,000.001.000 Set Wifi Program internet 1,581,000.00 1,581,000.001.000 Set Outlet Data 102,000.00 102,000.001.000 Set Wifi Internet dan Setting 1,581,000.00 1,581,000.000.200 Mtr Betelan dan Perapian tembok 22,500.00 4,500.004.000 bh Fitser + Sekrup 765.00 3,060.004.000 bh Penggantung/Pengikat 1,173.00 4,692.000.250 o/hr Pekerja 60,000.00 15,000.000.250 o/hr Tukang listrik 70,000.00 17,500.000.100 o/hr Mandor 90,000.00 9,000.00

    Outlet Data+Wifi Program Jumlah 155,752.00Switch hub + rak dan Setting Program 12,803,752.00Patch panel 5,663,752.00Star hub 12 port 1,583,752.00Wifi Program internet 1,634,752.00

    K.1 SPL 1 BH PEMASANGAN SETRAL TLP/PABX

    1.000 Set Sentral TLP/PABX 42 CO, 5 Line 145,000,000.00 145,000,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 145,039,500.00K.1 SPL 1 BH PEMASANGAN SETRAL SOUND SYSTEM

    1.000 Set Sentral Sound System 112,500,000.00 112,500,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 112,539,500.00K.1 SPL 1 BH PEMASANGAN SETRAL FIRE ALARM

    1.000 bh Sentral Fire Alarm 36 Line 85,000,000.00 85,000,000.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 85,039,500.00K.1 SPL 1 MTR PEMASANGAN PIPA 3" GIP

    1.000 Meter Pipa 3" 93,500.00 93,500.001.000 Meter Penggalian kedalaman 1 meter 15,500.00 15,500.002.000 Bh Pengikat 35,700.00 71,400.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 219,900.00K.1 SPL 1 MTR PEMASANGAN PIPA 2" GIP

    1.000 Meter Pipa 2" 35,700.00 35,700.001.000 Meter Penggalian kedalaman 1 meter 15,500.00 15,500.002.000 Bh Pengikat 35,700.00 71,400.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 162,100.00K.1 SPL 1 MTR PEMASANGAN PIPA 4" Black Steal

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    1.000 Meter Pipa 4" 116,450.00 116,450.001.000 Meter Penggalian kedalaman 1 meter 15,500.00 15,500.002.000 Bh Pengikat 35,700.00 71,400.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 242,850.00K.1 SPL 1 MTR PEMASANGAN PIPA 3" Black Steal

    1.000 Meter Pipa 3" 93,500.00 93,500.001.000 Meter Penggalian kedalaman 1 meter 15,500.00 15,500.002.000 Bh Pengikat 35,700.00 71,400.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 219,900.00K.1 SPL 1 MTR PEMASANGAN PIPA 2" Black Steal

    1.000 Meter Pipa 2" 76,500.00 76,500.001.000 Meter Penggalian kedalaman 1 meter 15,500.00 15,500.002.000 Bh Pengikat 35,700.00 71,400.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 202,900.00K.1 SPL 1 MTR PEMASANGAN PIPA 1" Black Steal

    1.000 Meter Pipa 1" 53,550.00 53,550.001.000 Meter Penggalian kedalaman 1 meter 15,500.00 15,500.002.000 Bh Pengikat 35,700.00 71,400.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 179,950.00K.1 SPL 1 MTR PEMASANGAN PIPA BLAK STEAL HIDRANT

    1.000 Meter dia 150 mm 212,500.00 212,500.001.000 Meter dia 125 mm 148,835.00 148,835.001.000 Meter dia 100 mm 116,450.00 116,450.001.000 Meter dia 80 mm 93,500.00 93,500.001.000 Meter dia 65 mm 84,150.00 84,150.001.000 Meter dia 50 mm 76,500.00 76,500.001.000 Meter dia 25 mm 53,550.00 53,550.000.500 kali Pengelasan 35,700.00 17,850.001.000 Meter Pengecatan 15,810.00 15,810.000.200 Mtr Betelan dan Perapian tembok 22,500.00 4,500.004.000 bh Fitser + Sekrup 765.00 3,060.002.000 bh Penggantung/Pengikat 35,700.00 71,400.000.350 o/hr Pekerja 60,000.00 21,000.000.350 o/hr Tukang listrik 70,000.00 24,500.000.250 o/hr Mandor 90,000.00 22,500.00

    Jumlah 180,620.00 dia 150 mm Jumlah 393,120.00 dia 125 mm Jumlah 329,455.00 dia 100 mm Jumlah 297,070.00 dia 80 mm Jumlah 274,120.00 dia 65 mm Jumlah 264,770.00 dia 50 mm Jumlah 257,120.00 dia 25 mm Jumlah 234,170.00

    K.1 SPL 1 MTR PEMASANGAN PIPA 4" PVC AW

    1.000 Meter Pipa 4" PVC AW 60,052.50 60,052.501.000 Meter Penggalian kedalaman 1 meter 15,500.00 15,500.002.000 Bh Pengikat + Lem 17,850.00 35,700.000.600 o/hr Tukang listrik 70,000.00 42,000.000.065 o/hr Mandor 90,000.00 5,850.00

    Jumlah 159,102.50

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    K.1 SPL 1 MTR PEMASANGAN PIPA 3" PVC AW

    1.000 Meter Pipa 3" PVC AW 30,982.50 30,982.501.000 Meter Penggalian kedalaman 1 meter 15,500.00 15,500.002.000 Bh Pengikat + Lem 17,850.00 35,700.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 121,682.50K.1 SPL 1 MTR PEMASANGAN PIPA 2" PVC AW

    1.000 Meter Pipa 2" PVC AW 16,447.50 16,447.501.000 Meter Penggalian kedalaman 1 meter 15,500.00 15,500.002.000 Bh Pengikat + Lem 17,850.00 35,700.000.500 o/hr Tukang listrik 70,000.00 35,000.000.060 o/hr Mandor 90,000.00 5,400.00

    Jumlah 108,047.50K.1 SPL 1 MTR PEMASANGAN PIPA 1" PVC AW

    1.000 Meter Pipa 1" PVC AW 8,287.50 8,287.502.000 Bh Pengikat + Lem 17,850.00 35,700.000.400 o/hr Tukang listrik 70,000.00 28,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 76,487.50K.1 SPL 1 MTR PEMASANGAN PIPA 3/4" PVC AW

    1.000 Meter Pipa 3/4" PVC AW 7,535.25 7,535.252.000 Bh Pengikat + Lem 17,850.00 35,700.000.400 o/hr Tukang listrik 70,000.00 28,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 75,735.25K.1 SPL 1 MTR PEMASANGAN PIPA 1/2" PVC AW

    1.000 Meter Pipa 1/2" PVC AW 5,737.50 5,737.502.000 Bh Pengikat + Lem 17,850.00 35,700.000.400 o/hr Tukang listrik 70,000.00 28,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 73,937.50K.1 SPL 1 MTR PEMASANGAN PIPA VENT.

    1.000 Meter Pipa PVC D dia. 65 mm 11,793.75 11,793.751.000 Meter Pipa PVC D dia. 50 mm 8,223.75 8,223.751.000 Meter Pipa PVC D dia. 40 mm 6,693.75 6,693.751.000 Meter Pipa PVC D dia. 32 mm 5,546.25 5,546.25

    2.000 Bh Pengikat + Lem 17,850.00 35,700.000.300 o/hr Tukang listrik 70,000.00 21,000.000.040 o/hr Mandor 90,000.00 3,600.00

    Jumlah 60,300.00Pipa PVC D dia. 65 mm Jumlah 72,093.75Pipa PVC D dia. 50 mm Jumlah 68,523.75Pipa PVC D dia. 40 mm Jumlah 66,993.75Pipa PVC D dia. 32 mm Jumlah 65,846.25

    K.1 SPL 1 BH BOX HIDRANT & GATE VALVE

    1.000 Set Box Hydrant 4,080,000.00 4,080,000.001.000 Meter Gate Valve 2,5" 1,020,000.00 1,020,000.00

    7.000 Mtr Betelan dan Perapian tembok 22,500.00 157,500.008.000 bh Fitser + Sekrup 765.00 6,120.004.000 bh Penggantung/Pengikat 35,700.00 142,800.002.400 o/hr Pekerja 60,000.00 144,000.001.200 o/hr Tukang listrik 70,000.00 84,000.000.850 o/hr Mandor 90,000.00 76,500.00

    Box Hydrant Jumlah 4,690,920.00Gate Valve 2,5" Jumlah 1,630,920.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    K.1 SPL 1 BH SPRINGKLE FLOW SWITCH & GATE VALVE

    1.000 Set Head Splinker 56,610.00 56,610.001.000 Set Flow Switch 2,601,000.00 2,601,000.001.000 Set Gate Valve 1,5" 561,000.00 561,000.00

    0.200 Mtr Betelan dan Perapian tembok 22,500.00 4,500.008.000 bh Fitser + Sekrup 765.00 6,120.002.000 bh Penggantung/Pengikat 35,700.00 71,400.000.500 o/hr Pekerja 60,000.00 30,000.000.350 o/hr Tukang listrik 70,000.00 24,500.000.150 o/hr Mandor 90,000.00 13,500.00

    Head Splinker Jumlah 206,630.00Flow Switch Jumlah 2,751,020.00Gate Valve 1,5" Jumlah 711,020.00

    K.1 SPL 1 BH PEMASANGAN ROOF TANK

    1.000 Set Roof Tank kap. 12 m3 12,750,000.00 12,750,000.000.250 m3 Dudukan Roof Tank 2,550,000.00 637,500.001.500 M Karet Silent 56,100.00 84,150.00

    16.000 bh Mur Baut 15,300.00 244,800.006.000 o/hr Pekerja 60,000.00 360,000.003.000 o/hr Tukang listrik 70,000.00 210,000.001.000 o/hr Mandor 90,000.00 90,000.00

    Jumlah 14,376,450.00K.1 SPL 1 BH PEMASANGAN KRAN STOP

    1.000 Meter Kran Stop 1" 86,700.00 86,700.001.000 Bh Pengikat 35,700.00 35,700.000.500 o/hr Tukang listrik 70,000.00 35,000.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 161,900.00K.1 SPL 1 BH PEMASANGAN CAST IRON ROOF DRAIN

    1.000 Meter Cast Iron Roof Drain 134,130.00 134,130.000.250 o/hr Tukang ME 70,000.00 17,500.000.050 o/hr Mandor 90,000.00 4,500.00

    Jumlah 156,130.00K.1 SPL 1 BH PEMASANGAN PERALATAN KM/WC

    1.000 Set Clossed jongkok 306,000.00 306,000.001.000 Set Clossed duduk monoblok 1,326,000.00 1,326,000.001.000 Set Wash taffel non standar lengkap kran dan ass 1,326,000.00 1,326,000.001.000 Set Urinoir lengkap ass dan kran 1,530,000.00 1,530,000.001.000 Set Shawer bilas 1,530,000.00 1,530,000.001.000 Set Floor Drain 61,200.00 61,200.001.000 Set Clean Out 306,000.00 306,000.001.000 Set Kran shower mandi 1,530,000.00 1,530,000.00

    0.200 Mtr Betelan dan Perapian tembok 22,500.00 4,500.008.000 bh Fitser + Sekrup 765.00 6,120.002.000 bh Penggantung/Pengikat/Lem 35,700.00 71,400.000.500 o/hr Pekerja 60,000.00 30,000.000.350 o/hr Tukang listrik 70,000.00 24,500.000.150 o/hr Mandor 90,000.00 13,500.00

    Jumlah 150,020.00Clossed jongkok Jumlah 456,020.00Clossed duduk monoblok Jumlah 1,476,020.00Wash taffel non standar lengkap kran dan ass Jumlah 1,476,020.00Urinoir lengkap ass dan kran Jumlah 1,680,020.00Shawer bilas Jumlah 1,680,020.00Floor Drain Jumlah 211,220.00Clean Out Jumlah 456,020.00Kran shower mandi Jumlah 1,680,020.00

    K.1 SPL 1 BH PEMASANGAN PANEL LISTRIK LVMDP & ATS

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    1.000 bh Panel LVMDP & ATS 270,300,000.00 270,300,000.0016.000 bh Moff Kabel 255,000.00 4,080,000.0016.000 bh Press Kabel 183,600.00 2,937,600.004.000 bh Pengukuran/Injection 1,173,000.00 4,692,000.000.500 m3 Dudukan Panel dari beton 2,550,000.00 1,275,000.002.000 M Karet Silent 56,100.00 112,200.008.000 bh Mur Baut 15,300.00 122,400.00

    10.000 o/hr Pekerja 60,000.00 600,000.006.000 o/hr Tukang listrik 70,000.00 420,000.003.000 o/hr Mandor 90,000.00 270,000.00

    Jumlah 284,809,200.00K.1 SPL 1 BH PEMASANGAN PANEL LISTRIK MDP

    1.000 bh Panel MDP 137,700,000.00 137,700,000.0032.000 bh Moff Kabel 127,500.00 4,080,000.0032.000 bh Press Kabel 45,900.00 1,468,800.004.000 bh Pengukuran/Injection 1,173,000.00 4,692,000.000.500 m3 Dudukan Panel dari beton 2,550,000.00 1,275,000.002.000 M Karet Silent 56,100.00 112,200.008.000 bh Mur Baut 15,300.00 122,400.00

    10.000 o/hr Pekerja 60,000.00 600,000.006.000 o/hr Tukang listrik 70,000.00 420,000.003.000 o/hr Mandor 90,000.00 270,000.00

    Jumlah 150,740,400.00K.1 SPL 1 BH PEMASANGAN PANEL CAPASITOR BANK

    1.000 bh Panel Capasitor bank & Capasitornya 153,000,000.00 153,000,000.0016.000 bh Moff Kabel 127,500.00 2,040,000.0016.000 bh Press Kabel 45,900.00 734,400.004.000 bh Pengukuran/Injection 1,173,000.00 4,692,000.000.500 m3 Dudukan Panel dari beton 2,550,000.00 1,275,000.002.000 M Karet Silent 56,100.00 112,200.008.000 bh Mur Baut 15,300.00 122,400.00

    10.000 o/hr Pekerja 60,000.00 600,000.006.000 o/hr Tukang listrik 70,000.00 420,000.003.000 o/hr Mandor 90,000.00 270,000.00

    Jumlah 163,266,000.00K.1 SPL 1 MTR PEMASANGAN LAMPU PENERANGAN SITE

    1.000 Set Lampu Jalan 2 Arah 9,741,000.00 9,741,000.001.000 Set Lampu Jalan 1 Arah 5,610,000.00 5,610,000.001.000 Meter Penggalian kedalaman 1 meter 78,030.00 78,030.002.000 Bh Pengikat mur + baut 35,700.00 71,400.000.250 m3 Dudukan dari beton 2,550,000.00 637,500.000.200 m3 Timbunan 161,364.00 32,272.800.500 o/hr Pekerja 60,000.00 30,000.000.250 o/hr Tukang listrik 70,000.00 17,500.000.150 o/hr Mandor 90,000.00 13,500.00

    Jumlah 880,202.80Lampu Jalan 2 Arah Jumlah 10,621,202.80Lampu Jalan 1 Arah Jumlah 6,490,202.80

    K.1 SPL 1 MTR PEMASANGAN LAMPU TAMAN

    1.000 Set Lampu Taman bohlam kaca 647,700.00 647,700.000.500 Meter Penggalian kedalaman 1 meter 78,030.00 39,015.002.000 Bh Pengikat mur + baut 35,700.00 71,400.000.020 m3 Dudukan dari beton 2,550,000.00 51,000.000.100 m3 Timbunan 161,364.00 16,136.400.500 o/hr Pekerja 60,000.00 30,000.000.250 o/hr Tukang listrik 70,000.00 17,500.000.150 o/hr Mandor 90,000.00 13,500.00

    Jumlah 886,251.40K.1 SPL 1 SET PEMASANGAN POMPA HIDRANT

    1.000 Set Jocky Pump CR 5- 18 46,410,000.00 46,410,000.001.000 Set Pompa Hidrant + Mesin Diesel 474,300,000.00 474,300,000.008.000 Bh Pengikat mur + baut 35,700.00 285,600.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    0.040 m3 Dudukan dari beton 2,550,000.00 102,000.000.500 m3 Timbunan 161,364.00 80,682.004.500 o/hr Pekerja 60,000.00 270,000.002.400 o/hr Tukang listrik 70,000.00 168,000.001.700 o/hr Mandor 90,000.00 153,000.00

    Pompa Hidrant + Mesin Diesel Jumlah 475,359,282.00Jocky Pump CR 5- 18 Jumlah 47,469,282.00

    K.1 SPL 1 BH PEMASANGAN ASSESORIS POMPA HIDRANT

    1.000 bh Pressure Tank 15 bar 15,300,000.00 15,300,000.00 - Kapasitas : 500 L - Sertifikat

    1.000 bh Header dia 250 mm 17,340,000.00 17,340,000.001.000 bh PVR dia 150 21,420,000.00 21,420,000.001.000 bh Alarm Gong dia 150 16,320,000.00 16,320,000.000.500 m3 Dudukan dari beton 2,550,000.00 1,275,000.002.000 M Karet Silent 56,100.00 112,200.008.000 bh Mur Baut 15,300.00 122,400.00

    10.000 o/hr Pekerja 60,000.00 600,000.006.000 o/hr Tukang listrik 70,000.00 420,000.003.000 o/hr Mandor 90,000.00 270,000.00

    Jumlah 2,799,600.00Pressure Tank 15 bar Jumlah 18,099,600.00Header dia 250 mm Jumlah 20,139,600.00PVR dia 150 Jumlah 24,219,600.00Alarm Gong dia 150 Jumlah 19,119,600.00

    K.1 SPL 1 SET PEKERJAAN SUMBER AIR BERSIH

    150.000 m Pengeboran sumber air bersih 550,000.00 82,500,000.001.000 Set Pompa Sumur dalam SP 14A-25 + panel 178,500,000.00 178,500,000.00

    150.000 m Casing Sumur dalam Pipa PVC AW 6" 139,102.50 20,865,375.001.000 Set Watel Level Control 5,500,000.00 5,500,000.001.000 bh Izin dan Hasil Lab dari balai POM 3,500,000.00 3,500,000.001.000 m3 Dudukan dari beton 2,550,000.00 2,550,000.002.000 M Karet Silent 56,100.00 112,200.008.000 bh Mur Baut 15,300.00 122,400.00

    10.000 o/hr Pekerja 60,000.00 600,000.006.000 o/hr Tukang listrik 70,000.00 420,000.003.000 o/hr Mandor 90,000.00 270,000.00

    Jumlah 294,939,975.00K.1 SPL 1 SET PEKERJAAN FILTERISASI AIR

    2.000 Set - Pumpa transfer 45,500,000.00 91,000,000.001.000 Set - Carbon filter kap 12m3/jam 12,500,000.00 12,500,000.001.000 Set - Sand filter kap 12 m3/jam 12,500,000.00 12,500,000.001.000 Set - Panel control & WLC 5,500,000.00 5,500,000.001.000 Set - Pemipaan instalasi 3,500,000.00 3,500,000.001.000 m3 Dudukan dari beton 2,550,000.00 2,550,000.006.000 M Karet Silent 56,100.00 336,600.00

    24.000 bh Mur Baut 15,300.00 367,200.0010.000 o/hr Pekerja 60,000.00 600,000.006.000 o/hr Tukang listrik 70,000.00 420,000.003.000 o/hr Mandor 90,000.00 270,000.00

    Jumlah 129,543,800.00K.1 SPL 1 BH PEMASANGAN ASSESORIS POMPA AIR BERSIH

    1.000 bh Pompa Distribusi Type CR 10-6 63,750,000.00 63,750,000.001.000 Set Header dia 6" lengkap assesoris & valve 5,100,000.00 5,100,000.001.000 bh Floating valve 50 mm 2,040,000.00 2,040,000.00

    0.500 m3 Dudukan dari beton 2,550,000.00 1,275,000.002.000 M Karet Silent 56,100.00 112,200.008.000 bh Mur Baut 15,300.00 122,400.00

    10.000 o/hr Pekerja 60,000.00 600,000.006.000 o/hr Tukang listrik 70,000.00 420,000.003.000 o/hr Mandor 90,000.00 270,000.00

  • NO SNI HARGA JUMLAHSATUAN HARGA

    (Rp) (Rp)

    ANALISA BIAYA KONSTRUKSI PEKERJAAN MEKANIKAL & ELEKTRIKAL

    Jumlah 2,799,600.00Pompa Distribusi Type CR 10-6 Jumlah 66,549,600.00Header dia 6" lengkap assesoris & valve Jumlah 6,624,600.00Floating valve 50 mm Jumlah 3,330,000.00

    K.1 SPL 1 SET PEM. PANEL LISTRIK INCOMING, OUTGOING & METRING

    1.000 bh Panel Incoming & Outgoing 255,000,000.00 255,000,000.001.000 bh Panel Metring 87,210,000.00 87,210,000.00

    24.000 bh Press Kabel 183,600.00 4,406,400.006.000 bh Pengukuran/Injection 1,173,000.00 7,038,000.001.500 m3 Dudukan Panel dari beton 2,550,000.00 3,825,000.003.000 M Karet Silent 56,100.00 168,300.00

    24.000 bh Mur Baut 15,300.00 367,200.0012.000 o/hr Pekerja 60,000.00 720,000.006.000 o/hr Tukang listrik 70,000.00 420,000.003.000 o/hr Mandor 90,000.00 270,000.00

    Jumlah 359,424,900.00