TUGAS

ANALISA BEBAN DAN TENAGA

1. Diketahui : 1.Kelandaian ( K ) = 5%2.Koef. Tahanan Gelinding ( r ) = 5%3.Berat Traktor ( W ) = 26 ton4.Berat Scraper ( W ) = 16 ton5.Muatan Scraper = 4 ton

Ditanyakan : Berapa besar tenaga yang dibutuhkan untuk menarik scraper ?

K = 5% Jawab :

Tenaga yang dibutuhkan = Beban Total ( TR )

1. Traktor ( Roda Rantai )

TR = Tahanan Kelandaian (GR) = W x % K = 1.3 ton

2. Scraper ( Roda Karet )

TR = Tahanan Kelandaian (GR) + Tahanan Gelinding (RR) = ( W x % K ) + ( W x % r ) = 2 ton

Jadi tenaga yang dibutuhkan traktor adalah = 3.3 ton

2. Diketahui : 1.Kelandaian ( K ) = 8%2.Harraw ditarik pada datar = 4500 kg3.Berat Bulldozer ( W ) = 18 ton4.Berat Harraw ( W ) = 4 ton5.Koef. Traksi Kritis ( ct ) = 0.65

K = 8% Ditanyakan : Mampukah Bulldozer menarik harraw ?

Jawab :

1. Bulldozer ( Roda Rantai )

TR = Tahanan Kelandaian (GR) = W x % K = 1.44 ton

2. Scraper ( Roda Rantai )

TR = 4500 kg + Tahanan Kelandaian (GR) = 4500 kg + ( W x % K ) = 4.82 ton

Tenaga yang dibutuhkan Bulldozer (TR) = 6.26 ton

Traksi Kritis Bulldozer (TK) = W x ct = 11.7 ton

TK > TR = Mampu

TRAKTOR

SCRAPER

BULLDOZER

HARRAW

Latihan 1

Proyek jalan raya

= 24

STA 00 STA 6000

galian timbunan galian timbunan galian

Diketahui :a. Data Pekerjaan & alat b. Kondisi Tanah

Galian 1. Tanah Biasa = 0.83p = 4000 m 2. Sweel = 20%t = 1.8 m

Timbunanp = 2000 mt = 1.2 m

1. Alat Bulldozer type s =2. Lebar blade = 3.2 m3. Tinggi blade = 1.1 m4. Biaya Pemblian = Rp19,000,000,0005. Nilai Sisa = 10%6. Waktu Investasi = 8 thn7. Masa guna alat = 10000 jam8. Biaya Operasional = Rp900,0009. Biaya Investasi = 18% dari harga pembelian

= Rp3,420,000,000

c. Metode kerja1 Metode kerja = Slot and Dozing2 Waktu kerja 50 menit/jam =3 Operator Pandai = 0.834 V mendorong = 4.5 km/jam = 75 m/menit5 V mundur = 6 km/jam = 100 m/menit6 Bekerja waktu kemarau =7 Durasi 20 hari @ 7 jam = 140 jam8 Perataan timbinan perlapis = 0.3 m

Ditanyakan : 1 Produksi alat dalam 1 jam ( Q )2 Hitung jumlah alat3 Biaya aktual apabila profit 10%4 HSP pekerjaan5 Biaya penawaran dengan pajak 15%6 Jadwal

Jawab : GALIAN● Volume Pekerjaan Galian ( bank ) = 172800● sweel = 20%● Volume Pekerjaan Galian ( loose ) = 207360● Kapasitas Blade ( B ) = 3.872● Jarak Operasi Blade , dengan kedalaman = 60.5 m

0.02 m ( J )● CT = 1.412 menit● E = 0.82

1 Q = Q' x EQ' = 60 x B

CT = 232.32 = 164.5714

1.412Q = 134.9486 Lm³/jam

2 Durasi Alat = 207360134.948571428571 Lm³/jam

= 1537 Jam

Jumlah Alat = 1537 Jam140 Jam

Jumlah Alat = 10.97561 ~ 11 UNIT

3 BP● Depresiasi / jam = Rp1,710,000● Investasi / jam = Rp342,000 +

BP = Rp2,052,000 /jam

O = Rp900,000 /jam +

BP & O = Rp2,952,000 /jam

Biaya Aktual = Vol. Loose x BP & OQ

= 207360 x Rp2,952,000134.949

= Rp4,536,000,000Profit 10 % = Rp453,600,000 +Biaya Aktual = Rp4,989,600,000

4 HSP Pekerjaan = Biaya act + profit Rpvol . Bank

= Rp4,989,600,000 Rp172800

Lm³Lm³

Lm³/jam

Lm³

HSP Pekerjaan = Rp28,875 Rp/m³

5 Harga Penawaran = Biaya Actual + Profit + Pajak 15% = Rp4,989,600,000 + Rp748,440,000

Harga Penawaran = Rp5,738,040,000

m

TIMBUNAN● Volume Pekerjaan Galian ( bank ) = 57600● sweel = 20%● Volume Pekerjaan Galian ( loose ) = 69120● Kapasitas Blade ( B ) = 3.872● Jarak Operasi Blade , dengan kedalaman = 4.033 m

0.3 m ( J )● CT = 0.094 menit● E = 0.82

1 Q = Q' x EQ' = 60 x B

CT = 232.32 = 2468.571

0.094Q = 2024.229 Lm³/jam

2 Durasi Alat = 691202024.2285714286 Lm³/jam

= 34 Jam

Jumlah Alat = 34 Jam140 Jam

Jumlah Alat = 0.243902 ~ 1 UNIT

3 BP● Depresiasi / jam = Rp1,710,000● Investasi / jam = Rp342,000

BP = Rp2,052,000

O = Rp900,000

BP & O = Rp2,952,000

Biaya Aktual = Vol. Loose x BP & OQ

= 69120 x Rp2,952,0002024.229

= Rp100,800,000Profit 10 % = Rp10,080,000 +Biaya Aktual = Rp110,880,000

4 HSP Pekerjaan = Biaya act + profit Rpvol . Bank

= Rp110,880,000 Rp57600

Lm³Lm³

Lm³/jam

Lm³

HSP Pekerjaan = Rp1,925 Rp/m³

Pajak 15% 5 Harga Penawaran = Biaya Actual + Profit +Rp748,440,000 = Rp110,880,000 +

Harga Penawaran = Rp127,512,000

+/jam

/jam +/jam

Pajak 15%Rp16,632,000

Latihan 2

4.47 CL4 m

2 : 1

2.5 m

Diketahui : 1. Data alat● Excavator PC 180 =● Kapasitas ( q ' ) = 0.85

2. Data pekerjaan ● panjang galian = 2000 m● tanah biasa ( K ) = 1.1● sweel = 20%● digging condition 60 % = 1● = 15 detik● Koefisien efesiensi ( E ) "good" = 0.83● Durasi 30 hari @ 7 jam kerja = 210 jam● BP & O = Rp1,200,000

Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung jumlah alat3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal

Jawab : 1. Volume pekerjaan galian ( bank ) = 22350Volume pekerjaan galian ( loose ) = 26820

Q = Q ' x E

Q' = 60 x qCT (menit )

q = q ' x K

Q = 46.5630.25

swing angle 70°

m³Lm³

Q = 186.252

2. Durasi alat = 26820186.252 Lm³/jam

= 143.998 Jam

Jumlah Alat = 143.998 Jam210 Jam

Jumlah Alat = 0.6857069224185 ~ 1 UNIT

3. Biaya Aktual = Vol. Loose X BP & OQ

= 26820 X Rp1,200,000186.252

= Rp172,798,144Profit 10% = Rp17,279,814 +Biaya Aktual = Rp190,077,959

4. HSP pekerjaan = Biaya act + profit Rpvol . Bank

= Rp190,077,959 Rp22350

HSP pekerjaan = Rp8,505

5. Harga Penawaran = Biaya actual + Profit + = Rp190,077,959 +

Harga Penawaran = Rp218,589,653

Lm³/jam

Lm³

m³Rp/m³

/jam

Pajak 15 %Rp28,511,694

Latuhan 3

Tanah

12 m

12 m

Diketahui : a. Data pekerjaan & alat1 = 138240

2 Bucket Kapasitas ( q ' ) = 3.43 Faktor Bucket ( K ) = 0.954 BP & O = Rp1,250,000 /Jam5 FT = 0.2 menit6 Koefisien efesiensi ( E ) "good" = 0.83

b. Metode kerja1 V shape ,dengan jarak = 12 m2 kecepatan isi = 2.5 km/jam = 41.6673 kecepatan kosong = 4 km/jam = 66.6674 waktu 30 hari @ 7 jam = 210 jam

Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung jumlah alat3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal

Jawab : 1. CT = J1 = J2 = 2J

+ 2J + FTkecp. Isi kecp. Kosong

Pengangkutan tanah dengan Vol. Pekerjaan 2/3 dari hasil galian bulldozer

Lm³

WL

DT

= 0.576 + 0.36 + 0.2 = 1.136 menit

volume pekerjaan ( bank ) = 115200sweel = 20%volume pekerjaan ( loose ) = 138240

Q = Q ' x E

Q' = 60 x qCT (menit )

q = q ' x K

Q = 160.8541.136

Q = 141.597

2. Durasi alat = 138240141.597

= 976.293 jam

Jumlah alat = 976.293 jam210 jam

Jumlah alat = 4.6490144567656 ~ 5

3. Biaya Aktual = Vol. Loose X BP&OQ

= 138240 X Rp1,250,000141.597

= Rp1,220,366,295Profit 10% = Rp122,036,629 +Biaya Aktual = Rp1,342,402,924

4. HSP Pekerjaan = Biaya Act. + profit RpVol. Bank

= Rp1,342,402,924 Rp115200

HSP Pekerjaan = Rp11,653 Rp/jam

5. Harga Penawaran = Biaya Act. + Profit = Rp1,342,402,924

Harga Penawaran = Rp 1,543,763,363

Lm³

Lm³/jam

Lm³Lm³/jam

m/menitm/menit

UNIT

Rp1,250,000

Profit + Pajak 15%Rp1,342,402,924 + Rp 201,360,439

Latihan 4

10%

750 m

600 m

Diketahui : 1. Data Alat● Dump Truck HD 325● Berat Kosong = 27.2 ton● Berat Bermuatan Max = 52.3 ton● Batasan Kacapatan = V max Flat = Isi = 40

Kosong = 60

= = Isi = 20Kosong = 40

● Sewa Dump Truck = Rp2,100,000 /hari = Rp262,500

2. Data Pekerjaan● Volume Pekerjaan = 115200

= 138240● Route Pengangkutan = Membawa sama dengan kembali● Kondisi Jalan = Kering dan kurang terpelihara =● = 1.6● Managemen Baik =● Dumping = Lancar Tanpa Ada Hambatan● Spot & Delay = Lancar Tanpa Ada Hambatan

Ditanyakan : 1 Produksi alat dalam 1 jam ( Q )2 Hitung Durasi3 Biaya aktual apabila profit 10%4 HSP pekerjaan5 Biaya penawaran dengan pajak 15%6 Jadwal

Jawab : 1 CT = T1 + T2 + T3 + T4 + T5Tabel T2 dan T4

T1 = n X CT wheel loader tipe angkutSegmen

V max Turunan/ tanjakan

m³lm³

γ Tanah ton/m³

DUMP TRUCK

n = q DT ( kg )tipe angkut

kondisi

Membawa (isi)Datar

n = (52,3 t - 27,2 t )x 1000 Tanjakan3,4 x 0,95 x 1600 Datar

n = 25100 Datar5168 Turunan

n = 4.85681115 ~ 5 Datar

T1 = 5 x 1,136 menit T3 = 0.6T1 = 5.68 menit T5 = 0.15

CT = T1 + T2 + T3 + T4 + T5CT = 8.69 menit

M = CT dtn X CT wl

M = 8.695.68

M = 1.53 ~ 2 unit

Q = Q' x E x M E ( GOOD ) = 0.83Q' = 60 x q DT

CTq DT = n x q L

Q' = 60 x 9 x 3,48.69

Q' = 46.95

Q = 194,48 x 0,83 x 9Q = 77.93

2 Hitung Durasi

Volume ( Bank ) = 115200Sweel = 20%Volume ( Loose ) = 138240

Waktu Pelaksanaan = Vol. looseQ

= 13824077.93

= 1773.88 jam

Waktu Pelaksanaan = 253.41 Hari ~ 254 Hari

3. Biaya Aktual = Vol. Loose x BP & O

q WL x K x γt

Kembali ( kosong )

Lm³/jam

Lm³/jam

Lm³

Qx BP & O

= 138240 x Rp262,50077.931

= Rp465,644,005Profit 10 % = Rp46,564,400 +Biaya Aktual = Rp512,208,405

4. HSP Pekerjaan = Biaya act + profit Rpvol . Bank

= Rp512,208,405 Rp115200

HSP Pekerjaan = Rp4,446 Rp/m³

5. Harga Penawaran = Biaya Actual + Profit = Rp512,208,405

Harga Penawaran = Rp589,039,666

350 m

Km/jam = 667 m/menitKm/jam = 1000 m/menit

Km/jam = 333 m/menitKm/jam = 667 m/menit

/jam

8%

Produksi alat dalam 1 jam ( Q )Hitung DurasiBiaya aktual apabila profit 10%HSP pekerjaanBiaya penawaran dengan pajak 15%Jadwal

Segmen tahanan kecepatanTime

kondisi jarak RR GR TR F Vmax SF V rata2Time

Datar 600 8% 0% 8% 667 0.72 480

1.393443T2Tanjakan 750 8% 10% 18% 333 0.78 260

Datar 350 8% 0% 8% 667 0.72 480Datar 600 8% 0% 8% 1000 0.72 720

0.867347

T4Turunan 750 8% -10% -2% 667 0.78 520

Datar 350 8% 0% 8% 1000 0.72 720

menitmenit

Hitung Durasi

BP & O

BP & O

Rp262,500

Profit + Pajak 15%Rp512,208,405 + Rp76,831,261

Latihan 5Return

Houling

Diketahui : 1. Data Alat● Kapasitas bowel (q ) = 10● Kecp. Digging (VD) = 1.5 km/jam = 25● Kecp. Houling (VH) = 10 km/jam = 166.6667● Kecp. Spreading (VS) = 3 km/jam = 50.00● Kecp. Returning (VR) = 12 km/jam = 200

2. Data Pekerjaan● Jarak Digging (D) = 35 m● Jarak Houling (H) = 175 m● Jarak Spreading (S) = 25 m● Jarak Returning (R) = 200 m● Vulome Galian = 500000● Volume Urugan = 500000● Banyak Alat = 5 Unit● BP & O = Rp1,500,000 per jam● FT = 1

Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung waktu pelaksanaa3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal

Dijawab : 1. CT =

CT = 35 +

175 +

25 +

25 166.67 50.00CT = 4.95 menit

m³m³

digspred

35 m

25 m

175 m

200 m

𝐷𝑉𝐷 + 𝐻𝑉𝐻 + 𝑆𝑉𝑆+ 𝑅𝑉𝑅 + FT

E = E1 X E2 X E3 Dimana : E1 = Waktu Kerja 50m/jE = 1.008 E2 = Operator Baik

E3 = Tanah Biasa

Q' = 60 X qCT

Q' = 6004.95

Q' = 121.2121212 Lm³/jam

Q' = Q' X EQ = 122.1818182 Lm³/jam

2. Volume ( Bank ) = 500000Sweel = 20%Volume ( Loose ) = 600000

Waktu Pelaksanaan = Vol. looseQ

= 600000122.18

= 4910.71 jam / 5 unit = 982.14 per unit

Waktu Pelaksanaan = 140.31 Hari ~ 141

3. Biaya Aktual = Vol. Loose x BP & OQ

= 600000 x Rp1,500,000122.182

= Rp7,366,071,429Profit 10 % = Rp736,607,143 +Biaya Aktual = Rp8,102,678,571

4. HSP Pekerjaan = Biaya act + profit Rpvol . Bank

= Rp8,102,678,571 Rp500000

HSP Pekerjaan = Rp16,205 Rp/m³

5. Harga Penawaran = Biaya Actual + Profit = Rp8,102,678,571

Harga Penawaran = Rp9,318,080,357

Lm³

m/menitm/menitm/menitm/menit

200 + 1

200

𝐷𝑉𝐷 + 𝐻𝑉𝐻 + 𝑆𝑉𝑆+ 𝑅𝑉𝑅 + FT

= 0.84 = 1 = 1.2

Hari

BP & O

Rp1,500,000

Profit + Pajak 15%Rp8,102,678,571 + Rp1,215,401,786

lo

6 L leα

6

6000

Diketahui : 1. Data Alat● Lebar Blade ( L ) = 3.1 m● =● Kecepatan rata2 = 4 km/jam =● BP & O / jam = Rp2,200,000● Jumlah alat = 1 unit

2. Data Pekerjaan● Lebar lapisan = 12 m● Laluan Subgrade (n) = 6 kali● Laluan sub base (n) = 4 kali● Laluan base course (n) = 3 kali● Lebar overlap (lo) = 0.25 m● E faktor ( good ) = 0.83

Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung waktu pelaksanaa3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal

SUBGRADEDijawab : 1. Q = Q' X E

Q' = 60 X V .( le - lo ) le =n le = sin 60 x 3,1

Q' = 60 x 66,67 . ( 2,68 - 0,25 ) le = 2.686

Q' = 97206

Q' = 1620.00

Q = 1620 x 0,83Q = 1344.60

2. Luas Perataan = 72000

Sudut Kerja ( α ) 60 °

sin α x L

m²/jam

Waktu Pelaksanaan = LuasQ

= 720001344.60

= 53.55 jam = 53.55 per unit

Waktu Pelaksanaan = 7.65 Hari ~

3. Biaya Aktual = Luas xQ

= 72000 x1344.600

= Rp117,804,552Profit 10 % = Rp11,780,455 +Biaya Aktual = Rp129,585,007

4. HSP Pekerjaan = Biaya act + profit RpLuas

= Rp129,585,007 Rp72000

HSP Pekerjaan = Rp1,800

5. Harga Penawaran = Biaya Actual + = Rp129,585,007

Harga Penawaran = Rp149,022,758

m²Rp/m²

66.67 m/menit

SUB BASE1. Q =

Q' =sin 60 x 3,1

m Q' =

Q' =

Q' =

Q =Q =

2. Luas Perataan

Waktu Pelaksanaan

8 Hari Waktu Pelaksanaan

BP & O 3. Biaya Aktual

Rp2,200,000

Profit 10 %Biaya Aktual

4. HSP Pekerjaan

HSP Pekerjaan

Profit + Pajak 15% 5. Harga PenawaranRp129,585,007 + Rp19,437,751

Harga Penawaran

Q' X E60 X V .( le - lo ) le =

n le = sin 60 x 3,160 x 66,67 . ( 2,68 - 0,25 ) le = 2.68 m

49720

42430.00

2430 x 0,832016.90

Luas Perataan = 72000

sin α x L

m²/jam

Waktu Pelaksanaan = LuasQ

= 720002016.90

= 35.70 jam = 35.70 per unit

Waktu Pelaksanaan = 5.10 Hari ~ 6 Hari

Biaya Aktual = Luas x BP & OQ

= 72000 x Rp2,200,0002016.900

= Rp78,536,368Profit 10 % = Rp7,853,637 +Biaya Aktual = Rp86,390,004

HSP Pekerjaan = Biaya act + profit RpLuas

= Rp86,390,004 Rp72000

HSP Pekerjaan = Rp1,200

Harga Penawaran = Biaya Actual + Profit + = Rp86,390,004 +

Harga Penawaran = Rp99,348,505

m²Rp/m²

BASE COURSE1. Q = Q' X E

Q' = 60 X V .( le - lo )n

Q' = 60 x 66,67 . ( 2,68 - 0,25 )3

Q' = 97203

Q' = 3240.00

Q = 3240 x 0,83Q = 2689.20

2. Luas Perataan = 72000

m²/jam

Waktu Pelaksanaan = LuasQ

= 720002689.20

= 26.77 = 26.77

Waktu Pelaksanaan = 3.82

3. Biaya Aktual = LuasQ

= 720002689.200

= Rp58,902,276Profit 10 % = Rp5,890,228Biaya Aktual = Rp64,792,503

4. HSP Pekerjaan = Biaya act + profitLuas

= Rp64,792,50372000

HSP Pekerjaan = Rp900

Pajak 15% 5. Harga Penawaran = Biaya ActualRp12,958,501 = Rp64,792,503

Harga Penawaran = Rp74,511,379

le =le = sin 60 x 3,1le = 2.68 m

sin α x L

jamper unit

Hari ~ 4 Hari

Luas x BP & OQ

72000 x Rp2,200,0002689.200

Rp58,902,276Rp5,890,228 +

Rp64,792,503

Biaya act + profit RpLuas

Rp64,792,503 Rp72000Rp900

Biaya Actual + Profit + Pajak 15%Rp64,792,503 + Rp9,718,876

Rp74,511,379

m²Rp/m²

Diketahui : 1. Data Alat● Lebar roda (w) = 2 m● Kecp. Rata2 = 3 km/jam =● Overlap (wo) = 0.3 m● BP & O = Rp2,000,000 /jam

2. Data Pekerjaan● Laluan Subgrade = 4 kali● Laluan Subbase = 3 kali● Laluan Base course = 3 kali

Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung waktu pelaksanaa3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal

SUBGRADEDijawab : 1. Q= Q' X E

Q'= 1000 . V . ( w - Wo )n

Q'= 850004

Q'= 21250

Q= Q' X E E faktor ( good ) =Q= 21250 x 0,83Q= 17637.5

2. Luas Perataan = 72000

Waktu Pelaksanaan = LuasQ

= 7200017637.50

= 4.08 jam = 4.08 per unit

Waktu Pelaksanaan = 0.58 Hari ~

3. Biaya Aktual = Luas xQ

= 72000 x17637.500

= Rp8,164,422

m²/jam

m²/jam

Profit 10 % = Rp816,442 +Biaya Aktual = Rp8,980,865

4. HSP Pekerjaan = Biaya act + profit RpLuas

= Rp8,980,865 Rp72000

HSP Pekerjaan = Rp125

5. Harga Penawaran = Biaya Actual + = Rp8,980,865

Harga Penawaran = Rp10,327,994

m²/m²

50 m/menit

SUB BASE1. Q=

Q'=

Q'=

Q'=

0.83 Q=Q=Q=

2. Luas Perataan

Waktu Pelaksanaan

1 Hari Waktu Pelaksanaan

BP & O 3. Biaya Aktual

Rp2,000,000

Profit 10 %Biaya Aktual

4. HSP Pekerjaan

HSP Pekerjaan

Profit + Pajak 15% 5. Harga PenawaranRp8,980,865 + Rp1,347,130

Harga Penawaran

Q' X E1000 . V . ( w - Wo )

n85000

328333.33

Q' X E E faktor ( good ) = 0.8328333,3 x 0,8323516.67

Luas Perataan = 72000

Waktu Pelaksanaan = LuasQ

= 7200023516.67

= 3.06 jam = 3.06 per unit

Waktu Pelaksanaan = 0.44 Hari ~ 1 Hari

Biaya Aktual = Luas x BP & OQ

= 72000 x Rp2,000,00023516.667

= Rp6,123,317

m²/jam

m²/jam

Profit 10 % = Rp612,332 +Biaya Aktual = Rp6,735,648

HSP Pekerjaan = Biaya act + profit RpLuas

= Rp6,735,648 Rp72000

HSP Pekerjaan = Rp94

Harga Penawaran = Biaya Actual + Profit + Pajak 15% = Rp6,735,648 + Rp1,010,347

Harga Penawaran = Rp7,745,996

m²Rp/m²

BASE COURSE1. Q= Q' X E

Q'= 1000 . V . ( w - Wo )n

Q'= 850003

Q'= 28333.33

Q= Q' X E E faktor ( good ) =Q= 28333,3 x 0,83Q= 23516.67

2. Luas Perataan = 72000

Waktu Pelaksanaan = LuasQ

= 7200023516.67

= 3.06 jam = 3.06 per unit

Waktu Pelaksanaan = 0.44 Hari ~

3. Biaya Aktual = Luas xQ

= 72000 x23516.667

= Rp6,123,317

m²/jam

m²/jam

Profit 10 % = Rp612,332 +Biaya Aktual = Rp6,735,648

4. HSP Pekerjaan = Biaya act + profit RpLuas

= Rp6,735,648 Rp72000

HSP Pekerjaan = Rp94

Pajak 15% 5. Harga Penawaran = Biaya Actual +Rp1,010,347 = Rp6,735,648

Harga Penawaran = Rp7,745,996

m²Rp/m²

0.83

1 Hari

BP & O

Rp2,000,000

Profit + Pajak 15%Rp6,735,648 + Rp1,010,347

Diketahui : 1. Data Alat● Lebar roda (w) = 3 m● Kecp. Rata2 = 2.5 km/jam =● BP & O = Rp2,500,000 /jam

2. Data Pekerjaan● Tebal = 5 cm

Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung waktu pelaksanaa3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal

Dijawab : 1. Q = Q' X EQ' = 60 X V X WQ' = 60 X 41,67 X 3Q' = 7500

Q = Q' X E E faktor ( good ) =Q = 7500 X 0,83Q = 6225

2. Luas Permukaan = 72000

Waktu Pelaksanaan = LuasQ

= 720006225.00

= 11.57 jam = 11.57 per unit

Waktu Pelaksanaan = 1.65 Hari ~

3. Biaya Aktual = Luas xQ

= 72000 x6225.000

= Rp28,915,663Profit 10 % = Rp2,891,566 +Biaya Aktual = Rp31,807,229

4. HSP Pekerjaan = Biaya act + profit Rpvol . Bank

= Rp31,807,229 Rp72000

m²/jam

m²/jam

HSP Pekerjaan = Rp442

5. Harga Penawaran = Biaya Actual + = Rp31,807,229

Harga Penawaran = Rp36,578,313

41.66667 m/menit

0.83

2 Hari

BP & O

Rp2,500,000

Profit + Pajak 15%Rp31,807,229 + Rp4,771,084

Pemancangan pada abutmen jembatan dengan data sebagai berikutDiketahui : 1. Data Tiang Pancang

● Ukuran = 14 inchi x 14 inchi● Panjang = 50 Ft● Bj Beton = 150 Cuft/ton● Jumlah 1 abutmen = 36 batang ● Berat Pondasi ( P ) = ton● BP & O = Rp 5,000,000 /jam● Daya dukung pondasi = 40 ton● Faktor keamanan = 1.2

2. Data Hammer● Type Vulcan size 1 (SAS)● Waktu setting = 10 menit● BP & O = Rp 5,000,000 /jam● Berat Hammer (w) = 9700 lbs● Tinggi Jatuh Hammer ( h ) = 36 inches● Faktor Hammer (e) = 0.8● Nilai Restritusi (k) = 0.25

Ditanyakan : 1. Apakah Hammer sudah memadai ? Jika tidak , tentukan hammer yang memadai .2. Hitung waktu untuk memancang tiap batang !3. Hitung untuk semua pek. Pemancangan .4. Hitung biaya pek. Pemancangan .5. Hitung HSP6. Hitung biaya penawaran.

Ditanyakan :→Energi yang dihasilkan hammer

E= e x w x hE= 0,8 x 9700 x 36E= 279360 inch-lb

→Energi yang hilang● akibat pukulan (I)

I = e x w x h x p x w + p

I = 0,8 x 9700 x 36 x 8166,67 x9700 + 8166,67

I = 119711.78 inch-lb

● akibat head tiang pancang (CL)U = daya dukung pondasi x faktor keamananU = 240000 x 1,2

1 - k²

1 - 0,25²

U = 288000

CL = U x C 1 C1 = tekanan izin sementara kepada kepala tiang dan cap2 C1 = 0.01

CL = 288000 x 0,3942

CL = 113385.832

CL = 56692.91

● akibat tiang pancang (PL)PL = U x C 2 C2 = simpanan tiang akibat tekana izin sementara

2 C2 = 0.005PL = 288000 x 0,197

2PL = 56692.91

2.00PL = 28346.46

● akibat ujung tiang pancang (SL)SL = U x C 3 C3 = tekanan izin sementara

2 C3 = 0.003SL = 288000 x 0,118

2SL = 34015.75

2SL = 17007.87

→Energi bersih yang dapat digunakanUS = e x w x h - I - CL - PL - SLUS = 279360 - 119711,78 -56692,91 - 28346,46 - 17007,87

1. US = 57600.98 hammer memadai

S = US / US = 57600,98 / 288000S = 0.200 inchiS = 0.0051 meter

T = Le Le = 2/3 dari LS x V xFo Le = 33.33

T = 10.16 Le = 10.160,0051 x 60 x 0,83 V = 60

T = 40.16 Menit Fo = 0.83

2. →Waktu yang dibutuhkan untuk memancang 1 tiang pancang adalah =

3. →Waktu yang dibutuhkan untuk memancang semua tiang pancang adalah =

4. Biaya pemancangan = waktu pek. Pemancangan X BP&O= 30,10 jam X Rp. 5.000.000/jam= Rp 150,479,886.44

Profit 10% = Rp 15,047,988.64 +Biaya pemancangan = Rp 165,527,875.09

5. HSP Pekerjaan = Biaya act + profit RpJumlah tiang pancang

= Rp165,527,875 Rp36

HSP Pekerjaan = Rp4,597,997 /batang

6. Harga Penawaran = Biaya Actual + = Rp165,527,875

Harga Penawaran = Rp190,357,056

=

= 8166.67 lb

= 240000 lb

Apakah Hammer sudah memadai ? Jika tidak , tentukan hammer yang memadai .

tekanan izin sementara kepada kepala tiang dan capm 0.394 Inchi

simpanan tiang akibat tekana izin sementaram 0.197 Inchi

tekanan izin sementaram 0.118 Inchi

ftmeter

50.16 menit

30.10 jam

Profit + Pajak 15%Rp165,527,875 + Rp24,829,181

UNIT PRICE ANALYSIS

ITEM NUMBER : Sta. 0+000 s/d 20+000

UNIT OF WORK : Cu.m

QUANTITY OF WORK :

DAILY/HOURLY OUTPUT :

NO. DESCRIPTION UNIT ALAT QUANTITY UNIT

A. Pekerjaan Badan Jalan (Subgrade)

A.1 Penggalian Badan Jalan

Buldozer 11 172,800 M3A.2 Pengangkutan Galian

Wheel Loader 5 138,240 M3Dump Truck 10 138,240 M3

A.3 Pemadatan Badan Jalan

Tandem Roller 1 72,000 M3A.4 Perapian Badan Jalan

Motor Grader 1 72,000 M2

Sub TotalB. Pekerjaan Tebing

B.1 Penggalian Tebing

Excavator PC 200 1 22,350 M3

Sub Total

Sub Total = (A + B )

Overhead and Profit

TOTAL Before Tax

Tax

TOTAL

UNIT PRICE ANALYSIS

Q BP & O Real Cost Durasi

(Rp/hour) (Rp/m3) hari

134.95 2,952,000 240,625.00 20.0

141.60 1,250,000 44,139.41 33.577.93 262,500 33,683.74 30.4

17,637.50 2,000,000 113.39 0.7

1,344.60 2,200,000 1,636.17 9.2 320,197.71

186.25 1,200,000 6,442.88 0.76,442.88

326,640.60

% Profit = 15% 48,996.09

375,636.69

% Tax = 15% 56,345.50

431,982.19

( m3/hour)

I21
Author: m2/hour