perhitungan produktifitas alat berat
Post on 24-Jul-2015
2.846 Views
Preview:
TRANSCRIPT
TUGAS
ANALISA BEBAN DAN TENAGA
1. Diketahui : 1.Kelandaian ( K ) = 5%2.Koef. Tahanan Gelinding ( r ) = 5%3.Berat Traktor ( W ) = 26 ton4.Berat Scraper ( W ) = 16 ton5.Muatan Scraper = 4 ton
Ditanyakan : Berapa besar tenaga yang dibutuhkan untuk menarik scraper ?
K = 5% Jawab :
Tenaga yang dibutuhkan = Beban Total ( TR )
1. Traktor ( Roda Rantai )
TR = Tahanan Kelandaian (GR) = W x % K = 1.3 ton
2. Scraper ( Roda Karet )
TR = Tahanan Kelandaian (GR) + Tahanan Gelinding (RR) = ( W x % K ) + ( W x % r ) = 2 ton
Jadi tenaga yang dibutuhkan traktor adalah = 3.3 ton
2. Diketahui : 1.Kelandaian ( K ) = 8%2.Harraw ditarik pada datar = 4500 kg3.Berat Bulldozer ( W ) = 18 ton4.Berat Harraw ( W ) = 4 ton5.Koef. Traksi Kritis ( ct ) = 0.65
K = 8% Ditanyakan : Mampukah Bulldozer menarik harraw ?
Jawab :
1. Bulldozer ( Roda Rantai )
TR = Tahanan Kelandaian (GR) = W x % K = 1.44 ton
2. Scraper ( Roda Rantai )
TR = 4500 kg + Tahanan Kelandaian (GR) = 4500 kg + ( W x % K ) = 4.82 ton
Tenaga yang dibutuhkan Bulldozer (TR) = 6.26 ton
Traksi Kritis Bulldozer (TK) = W x ct = 11.7 ton
TK > TR = Mampu
TRAKTOR
SCRAPER
BULLDOZER
HARRAW
Latihan 1
Proyek jalan raya
= 24
STA 00 STA 6000
galian timbunan galian timbunan galian
Diketahui :a. Data Pekerjaan & alat b. Kondisi Tanah
Galian 1. Tanah Biasa = 0.83p = 4000 m 2. Sweel = 20%t = 1.8 m
Timbunanp = 2000 mt = 1.2 m
1. Alat Bulldozer type s =2. Lebar blade = 3.2 m3. Tinggi blade = 1.1 m4. Biaya Pemblian = Rp19,000,000,0005. Nilai Sisa = 10%6. Waktu Investasi = 8 thn7. Masa guna alat = 10000 jam8. Biaya Operasional = Rp900,0009. Biaya Investasi = 18% dari harga pembelian
= Rp3,420,000,000
c. Metode kerja1 Metode kerja = Slot and Dozing2 Waktu kerja 50 menit/jam =3 Operator Pandai = 0.834 V mendorong = 4.5 km/jam = 75 m/menit5 V mundur = 6 km/jam = 100 m/menit6 Bekerja waktu kemarau =7 Durasi 20 hari @ 7 jam = 140 jam8 Perataan timbinan perlapis = 0.3 m
Ditanyakan : 1 Produksi alat dalam 1 jam ( Q )2 Hitung jumlah alat3 Biaya aktual apabila profit 10%4 HSP pekerjaan5 Biaya penawaran dengan pajak 15%6 Jadwal
Jawab : GALIAN● Volume Pekerjaan Galian ( bank ) = 172800● sweel = 20%● Volume Pekerjaan Galian ( loose ) = 207360● Kapasitas Blade ( B ) = 3.872● Jarak Operasi Blade , dengan kedalaman = 60.5 m
0.02 m ( J )● CT = 1.412 menit● E = 0.82
1 Q = Q' x EQ' = 60 x B
CT = 232.32 = 164.5714
1.412Q = 134.9486 Lm³/jam
2 Durasi Alat = 207360134.948571428571 Lm³/jam
= 1537 Jam
Jumlah Alat = 1537 Jam140 Jam
Jumlah Alat = 10.97561 ~ 11 UNIT
3 BP● Depresiasi / jam = Rp1,710,000● Investasi / jam = Rp342,000 +
BP = Rp2,052,000 /jam
O = Rp900,000 /jam +
BP & O = Rp2,952,000 /jam
Biaya Aktual = Vol. Loose x BP & OQ
= 207360 x Rp2,952,000134.949
= Rp4,536,000,000Profit 10 % = Rp453,600,000 +Biaya Aktual = Rp4,989,600,000
4 HSP Pekerjaan = Biaya act + profit Rpvol . Bank
= Rp4,989,600,000 Rp172800
m³
Lm³Lm³
Lm³/jam
Lm³
m³
m³
HSP Pekerjaan = Rp28,875 Rp/m³
5 Harga Penawaran = Biaya Actual + Profit + Pajak 15% = Rp4,989,600,000 + Rp748,440,000
Harga Penawaran = Rp5,738,040,000
m
TIMBUNAN● Volume Pekerjaan Galian ( bank ) = 57600● sweel = 20%● Volume Pekerjaan Galian ( loose ) = 69120● Kapasitas Blade ( B ) = 3.872● Jarak Operasi Blade , dengan kedalaman = 4.033 m
0.3 m ( J )● CT = 0.094 menit● E = 0.82
1 Q = Q' x EQ' = 60 x B
CT = 232.32 = 2468.571
0.094Q = 2024.229 Lm³/jam
2 Durasi Alat = 691202024.2285714286 Lm³/jam
= 34 Jam
Jumlah Alat = 34 Jam140 Jam
Jumlah Alat = 0.243902 ~ 1 UNIT
3 BP● Depresiasi / jam = Rp1,710,000● Investasi / jam = Rp342,000
BP = Rp2,052,000
O = Rp900,000
BP & O = Rp2,952,000
Biaya Aktual = Vol. Loose x BP & OQ
= 69120 x Rp2,952,0002024.229
= Rp100,800,000Profit 10 % = Rp10,080,000 +Biaya Aktual = Rp110,880,000
4 HSP Pekerjaan = Biaya act + profit Rpvol . Bank
= Rp110,880,000 Rp57600
m³
Lm³Lm³
Lm³/jam
Lm³
m³
m³
HSP Pekerjaan = Rp1,925 Rp/m³
Pajak 15% 5 Harga Penawaran = Biaya Actual + Profit +Rp748,440,000 = Rp110,880,000 +
Harga Penawaran = Rp127,512,000
+/jam
/jam +/jam
Pajak 15%Rp16,632,000
Latihan 2
4.47 CL4 m
2 : 1
2.5 m
Diketahui : 1. Data alat● Excavator PC 180 =● Kapasitas ( q ' ) = 0.85
2. Data pekerjaan ● panjang galian = 2000 m● tanah biasa ( K ) = 1.1● sweel = 20%● digging condition 60 % = 1● = 15 detik● Koefisien efesiensi ( E ) "good" = 0.83● Durasi 30 hari @ 7 jam kerja = 210 jam● BP & O = Rp1,200,000
Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung jumlah alat3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal
Jawab : 1. Volume pekerjaan galian ( bank ) = 22350Volume pekerjaan galian ( loose ) = 26820
Q = Q ' x E
Q' = 60 x qCT (menit )
q = q ' x K
Q = 46.5630.25
m³
swing angle 70°
m³Lm³
Q = 186.252
2. Durasi alat = 26820186.252 Lm³/jam
= 143.998 Jam
Jumlah Alat = 143.998 Jam210 Jam
Jumlah Alat = 0.6857069224185 ~ 1 UNIT
3. Biaya Aktual = Vol. Loose X BP & OQ
= 26820 X Rp1,200,000186.252
= Rp172,798,144Profit 10% = Rp17,279,814 +Biaya Aktual = Rp190,077,959
4. HSP pekerjaan = Biaya act + profit Rpvol . Bank
= Rp190,077,959 Rp22350
HSP pekerjaan = Rp8,505
5. Harga Penawaran = Biaya actual + Profit + = Rp190,077,959 +
Harga Penawaran = Rp218,589,653
Lm³/jam
Lm³
m³
m³Rp/m³
/jam
Pajak 15 %Rp28,511,694
Latuhan 3
Tanah
12 m
12 m
Diketahui : a. Data pekerjaan & alat1 = 138240
2 Bucket Kapasitas ( q ' ) = 3.43 Faktor Bucket ( K ) = 0.954 BP & O = Rp1,250,000 /Jam5 FT = 0.2 menit6 Koefisien efesiensi ( E ) "good" = 0.83
b. Metode kerja1 V shape ,dengan jarak = 12 m2 kecepatan isi = 2.5 km/jam = 41.6673 kecepatan kosong = 4 km/jam = 66.6674 waktu 30 hari @ 7 jam = 210 jam
Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung jumlah alat3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal
Jawab : 1. CT = J1 = J2 = 2J
+ 2J + FTkecp. Isi kecp. Kosong
Pengangkutan tanah dengan Vol. Pekerjaan 2/3 dari hasil galian bulldozer
Lm³
m³
WL
DT
= 0.576 + 0.36 + 0.2 = 1.136 menit
volume pekerjaan ( bank ) = 115200sweel = 20%volume pekerjaan ( loose ) = 138240
Q = Q ' x E
Q' = 60 x qCT (menit )
q = q ' x K
Q = 160.8541.136
Q = 141.597
2. Durasi alat = 138240141.597
= 976.293 jam
Jumlah alat = 976.293 jam210 jam
Jumlah alat = 4.6490144567656 ~ 5
3. Biaya Aktual = Vol. Loose X BP&OQ
= 138240 X Rp1,250,000141.597
= Rp1,220,366,295Profit 10% = Rp122,036,629 +Biaya Aktual = Rp1,342,402,924
4. HSP Pekerjaan = Biaya Act. + profit RpVol. Bank
= Rp1,342,402,924 Rp115200
HSP Pekerjaan = Rp11,653 Rp/jam
5. Harga Penawaran = Biaya Act. + Profit = Rp1,342,402,924
Harga Penawaran = Rp 1,543,763,363
m³
Lm³
Lm³/jam
Lm³Lm³/jam
m³
m³
m/menitm/menit
UNIT
Rp1,250,000
Profit + Pajak 15%Rp1,342,402,924 + Rp 201,360,439
Latihan 4
10%
750 m
600 m
Diketahui : 1. Data Alat● Dump Truck HD 325● Berat Kosong = 27.2 ton● Berat Bermuatan Max = 52.3 ton● Batasan Kacapatan = V max Flat = Isi = 40
Kosong = 60
= = Isi = 20Kosong = 40
● Sewa Dump Truck = Rp2,100,000 /hari = Rp262,500
2. Data Pekerjaan● Volume Pekerjaan = 115200
= 138240● Route Pengangkutan = Membawa sama dengan kembali● Kondisi Jalan = Kering dan kurang terpelihara =● = 1.6● Managemen Baik =● Dumping = Lancar Tanpa Ada Hambatan● Spot & Delay = Lancar Tanpa Ada Hambatan
Ditanyakan : 1 Produksi alat dalam 1 jam ( Q )2 Hitung Durasi3 Biaya aktual apabila profit 10%4 HSP pekerjaan5 Biaya penawaran dengan pajak 15%6 Jadwal
Jawab : 1 CT = T1 + T2 + T3 + T4 + T5Tabel T2 dan T4
T1 = n X CT wheel loader tipe angkutSegmen
V max Turunan/ tanjakan
m³lm³
γ Tanah ton/m³
DUMP TRUCK
n = q DT ( kg )tipe angkut
kondisi
Membawa (isi)Datar
n = (52,3 t - 27,2 t )x 1000 Tanjakan3,4 x 0,95 x 1600 Datar
n = 25100 Datar5168 Turunan
n = 4.85681115 ~ 5 Datar
T1 = 5 x 1,136 menit T3 = 0.6T1 = 5.68 menit T5 = 0.15
CT = T1 + T2 + T3 + T4 + T5CT = 8.69 menit
M = CT dtn X CT wl
M = 8.695.68
M = 1.53 ~ 2 unit
Q = Q' x E x M E ( GOOD ) = 0.83Q' = 60 x q DT
CTq DT = n x q L
Q' = 60 x 9 x 3,48.69
Q' = 46.95
Q = 194,48 x 0,83 x 9Q = 77.93
2 Hitung Durasi
Volume ( Bank ) = 115200Sweel = 20%Volume ( Loose ) = 138240
Waktu Pelaksanaan = Vol. looseQ
= 13824077.93
= 1773.88 jam
Waktu Pelaksanaan = 253.41 Hari ~ 254 Hari
3. Biaya Aktual = Vol. Loose x BP & O
q WL x K x γt
Kembali ( kosong )
Lm³/jam
Lm³/jam
m²
Lm³
Qx BP & O
= 138240 x Rp262,50077.931
= Rp465,644,005Profit 10 % = Rp46,564,400 +Biaya Aktual = Rp512,208,405
4. HSP Pekerjaan = Biaya act + profit Rpvol . Bank
= Rp512,208,405 Rp115200
HSP Pekerjaan = Rp4,446 Rp/m³
5. Harga Penawaran = Biaya Actual + Profit = Rp512,208,405
Harga Penawaran = Rp589,039,666
m³
m³
350 m
Km/jam = 667 m/menitKm/jam = 1000 m/menit
Km/jam = 333 m/menitKm/jam = 667 m/menit
/jam
8%
Produksi alat dalam 1 jam ( Q )Hitung DurasiBiaya aktual apabila profit 10%HSP pekerjaanBiaya penawaran dengan pajak 15%Jadwal
Segmen tahanan kecepatanTime
kondisi jarak RR GR TR F Vmax SF V rata2Time
Datar 600 8% 0% 8% 667 0.72 480
1.393443T2Tanjakan 750 8% 10% 18% 333 0.78 260
Datar 350 8% 0% 8% 667 0.72 480Datar 600 8% 0% 8% 1000 0.72 720
0.867347
T4Turunan 750 8% -10% -2% 667 0.78 520
Datar 350 8% 0% 8% 1000 0.72 720
menitmenit
Hitung Durasi
BP & O
BP & O
Rp262,500
Profit + Pajak 15%Rp512,208,405 + Rp76,831,261
Latihan 5Return
Houling
Diketahui : 1. Data Alat● Kapasitas bowel (q ) = 10● Kecp. Digging (VD) = 1.5 km/jam = 25● Kecp. Houling (VH) = 10 km/jam = 166.6667● Kecp. Spreading (VS) = 3 km/jam = 50.00● Kecp. Returning (VR) = 12 km/jam = 200
2. Data Pekerjaan● Jarak Digging (D) = 35 m● Jarak Houling (H) = 175 m● Jarak Spreading (S) = 25 m● Jarak Returning (R) = 200 m● Vulome Galian = 500000● Volume Urugan = 500000● Banyak Alat = 5 Unit● BP & O = Rp1,500,000 per jam● FT = 1
Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung waktu pelaksanaa3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal
Dijawab : 1. CT =
CT = 35 +
175 +
25 +
25 166.67 50.00CT = 4.95 menit
m³
m³m³
digspred
35 m
25 m
175 m
200 m
𝐷𝑉𝐷 + 𝐻𝑉𝐻 + 𝑆𝑉𝑆+ 𝑅𝑉𝑅 + FT
E = E1 X E2 X E3 Dimana : E1 = Waktu Kerja 50m/jE = 1.008 E2 = Operator Baik
E3 = Tanah Biasa
Q' = 60 X qCT
Q' = 6004.95
Q' = 121.2121212 Lm³/jam
Q' = Q' X EQ = 122.1818182 Lm³/jam
2. Volume ( Bank ) = 500000Sweel = 20%Volume ( Loose ) = 600000
Waktu Pelaksanaan = Vol. looseQ
= 600000122.18
= 4910.71 jam / 5 unit = 982.14 per unit
Waktu Pelaksanaan = 140.31 Hari ~ 141
3. Biaya Aktual = Vol. Loose x BP & OQ
= 600000 x Rp1,500,000122.182
= Rp7,366,071,429Profit 10 % = Rp736,607,143 +Biaya Aktual = Rp8,102,678,571
4. HSP Pekerjaan = Biaya act + profit Rpvol . Bank
= Rp8,102,678,571 Rp500000
HSP Pekerjaan = Rp16,205 Rp/m³
5. Harga Penawaran = Biaya Actual + Profit = Rp8,102,678,571
Harga Penawaran = Rp9,318,080,357
m³
Lm³
m³
m³
m/menitm/menitm/menitm/menit
200 + 1
200
𝐷𝑉𝐷 + 𝐻𝑉𝐻 + 𝑆𝑉𝑆+ 𝑅𝑉𝑅 + FT
= 0.84 = 1 = 1.2
Hari
BP & O
Rp1,500,000
Profit + Pajak 15%Rp8,102,678,571 + Rp1,215,401,786
lo
6 L leα
6
6000
Diketahui : 1. Data Alat● Lebar Blade ( L ) = 3.1 m● =● Kecepatan rata2 = 4 km/jam =● BP & O / jam = Rp2,200,000● Jumlah alat = 1 unit
2. Data Pekerjaan● Lebar lapisan = 12 m● Laluan Subgrade (n) = 6 kali● Laluan sub base (n) = 4 kali● Laluan base course (n) = 3 kali● Lebar overlap (lo) = 0.25 m● E faktor ( good ) = 0.83
Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung waktu pelaksanaa3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal
SUBGRADEDijawab : 1. Q = Q' X E
Q' = 60 X V .( le - lo ) le =n le = sin 60 x 3,1
Q' = 60 x 66,67 . ( 2,68 - 0,25 ) le = 2.686
Q' = 97206
Q' = 1620.00
Q = 1620 x 0,83Q = 1344.60
2. Luas Perataan = 72000
Sudut Kerja ( α ) 60 °
sin α x L
m²/jam
m²
Waktu Pelaksanaan = LuasQ
= 720001344.60
= 53.55 jam = 53.55 per unit
Waktu Pelaksanaan = 7.65 Hari ~
3. Biaya Aktual = Luas xQ
= 72000 x1344.600
= Rp117,804,552Profit 10 % = Rp11,780,455 +Biaya Aktual = Rp129,585,007
4. HSP Pekerjaan = Biaya act + profit RpLuas
= Rp129,585,007 Rp72000
HSP Pekerjaan = Rp1,800
5. Harga Penawaran = Biaya Actual + = Rp129,585,007
Harga Penawaran = Rp149,022,758
m²
m²Rp/m²
66.67 m/menit
SUB BASE1. Q =
Q' =sin 60 x 3,1
m Q' =
Q' =
Q' =
Q =Q =
2. Luas Perataan
Waktu Pelaksanaan
8 Hari Waktu Pelaksanaan
BP & O 3. Biaya Aktual
Rp2,200,000
Profit 10 %Biaya Aktual
4. HSP Pekerjaan
HSP Pekerjaan
Profit + Pajak 15% 5. Harga PenawaranRp129,585,007 + Rp19,437,751
Harga Penawaran
Q' X E60 X V .( le - lo ) le =
n le = sin 60 x 3,160 x 66,67 . ( 2,68 - 0,25 ) le = 2.68 m
49720
42430.00
2430 x 0,832016.90
Luas Perataan = 72000
sin α x L
m²/jam
m²
Waktu Pelaksanaan = LuasQ
= 720002016.90
= 35.70 jam = 35.70 per unit
Waktu Pelaksanaan = 5.10 Hari ~ 6 Hari
Biaya Aktual = Luas x BP & OQ
= 72000 x Rp2,200,0002016.900
= Rp78,536,368Profit 10 % = Rp7,853,637 +Biaya Aktual = Rp86,390,004
HSP Pekerjaan = Biaya act + profit RpLuas
= Rp86,390,004 Rp72000
HSP Pekerjaan = Rp1,200
Harga Penawaran = Biaya Actual + Profit + = Rp86,390,004 +
Harga Penawaran = Rp99,348,505
m²
m²Rp/m²
BASE COURSE1. Q = Q' X E
Q' = 60 X V .( le - lo )n
Q' = 60 x 66,67 . ( 2,68 - 0,25 )3
Q' = 97203
Q' = 3240.00
Q = 3240 x 0,83Q = 2689.20
2. Luas Perataan = 72000
m²/jam
Waktu Pelaksanaan = LuasQ
= 720002689.20
= 26.77 = 26.77
Waktu Pelaksanaan = 3.82
3. Biaya Aktual = LuasQ
= 720002689.200
= Rp58,902,276Profit 10 % = Rp5,890,228Biaya Aktual = Rp64,792,503
4. HSP Pekerjaan = Biaya act + profitLuas
= Rp64,792,50372000
HSP Pekerjaan = Rp900
Pajak 15% 5. Harga Penawaran = Biaya ActualRp12,958,501 = Rp64,792,503
Harga Penawaran = Rp74,511,379
le =le = sin 60 x 3,1le = 2.68 m
sin α x L
m²
jamper unit
Hari ~ 4 Hari
Luas x BP & OQ
72000 x Rp2,200,0002689.200
Rp58,902,276Rp5,890,228 +
Rp64,792,503
Biaya act + profit RpLuas
Rp64,792,503 Rp72000Rp900
Biaya Actual + Profit + Pajak 15%Rp64,792,503 + Rp9,718,876
Rp74,511,379
m²
m²Rp/m²
Diketahui : 1. Data Alat● Lebar roda (w) = 2 m● Kecp. Rata2 = 3 km/jam =● Overlap (wo) = 0.3 m● BP & O = Rp2,000,000 /jam
2. Data Pekerjaan● Laluan Subgrade = 4 kali● Laluan Subbase = 3 kali● Laluan Base course = 3 kali
Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung waktu pelaksanaa3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal
SUBGRADEDijawab : 1. Q= Q' X E
Q'= 1000 . V . ( w - Wo )n
Q'= 850004
Q'= 21250
Q= Q' X E E faktor ( good ) =Q= 21250 x 0,83Q= 17637.5
2. Luas Perataan = 72000
Waktu Pelaksanaan = LuasQ
= 7200017637.50
= 4.08 jam = 4.08 per unit
Waktu Pelaksanaan = 0.58 Hari ~
3. Biaya Aktual = Luas xQ
= 72000 x17637.500
= Rp8,164,422
m²/jam
m²/jam
m²
Profit 10 % = Rp816,442 +Biaya Aktual = Rp8,980,865
4. HSP Pekerjaan = Biaya act + profit RpLuas
= Rp8,980,865 Rp72000
HSP Pekerjaan = Rp125
5. Harga Penawaran = Biaya Actual + = Rp8,980,865
Harga Penawaran = Rp10,327,994
m²
m²/m²
50 m/menit
SUB BASE1. Q=
Q'=
Q'=
Q'=
0.83 Q=Q=Q=
2. Luas Perataan
Waktu Pelaksanaan
1 Hari Waktu Pelaksanaan
BP & O 3. Biaya Aktual
Rp2,000,000
Profit 10 %Biaya Aktual
4. HSP Pekerjaan
HSP Pekerjaan
Profit + Pajak 15% 5. Harga PenawaranRp8,980,865 + Rp1,347,130
Harga Penawaran
Q' X E1000 . V . ( w - Wo )
n85000
328333.33
Q' X E E faktor ( good ) = 0.8328333,3 x 0,8323516.67
Luas Perataan = 72000
Waktu Pelaksanaan = LuasQ
= 7200023516.67
= 3.06 jam = 3.06 per unit
Waktu Pelaksanaan = 0.44 Hari ~ 1 Hari
Biaya Aktual = Luas x BP & OQ
= 72000 x Rp2,000,00023516.667
= Rp6,123,317
m²/jam
m²/jam
m²
Profit 10 % = Rp612,332 +Biaya Aktual = Rp6,735,648
HSP Pekerjaan = Biaya act + profit RpLuas
= Rp6,735,648 Rp72000
HSP Pekerjaan = Rp94
Harga Penawaran = Biaya Actual + Profit + Pajak 15% = Rp6,735,648 + Rp1,010,347
Harga Penawaran = Rp7,745,996
m²
m²Rp/m²
BASE COURSE1. Q= Q' X E
Q'= 1000 . V . ( w - Wo )n
Q'= 850003
Q'= 28333.33
Q= Q' X E E faktor ( good ) =Q= 28333,3 x 0,83Q= 23516.67
2. Luas Perataan = 72000
Waktu Pelaksanaan = LuasQ
= 7200023516.67
= 3.06 jam = 3.06 per unit
Waktu Pelaksanaan = 0.44 Hari ~
3. Biaya Aktual = Luas xQ
= 72000 x23516.667
= Rp6,123,317
m²/jam
m²/jam
m²
Profit 10 % = Rp612,332 +Biaya Aktual = Rp6,735,648
4. HSP Pekerjaan = Biaya act + profit RpLuas
= Rp6,735,648 Rp72000
HSP Pekerjaan = Rp94
Pajak 15% 5. Harga Penawaran = Biaya Actual +Rp1,010,347 = Rp6,735,648
Harga Penawaran = Rp7,745,996
m²
m²Rp/m²
0.83
1 Hari
BP & O
Rp2,000,000
Profit + Pajak 15%Rp6,735,648 + Rp1,010,347
Diketahui : 1. Data Alat● Lebar roda (w) = 3 m● Kecp. Rata2 = 2.5 km/jam =● BP & O = Rp2,500,000 /jam
2. Data Pekerjaan● Tebal = 5 cm
Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung waktu pelaksanaa3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal
Dijawab : 1. Q = Q' X EQ' = 60 X V X WQ' = 60 X 41,67 X 3Q' = 7500
Q = Q' X E E faktor ( good ) =Q = 7500 X 0,83Q = 6225
2. Luas Permukaan = 72000
Waktu Pelaksanaan = LuasQ
= 720006225.00
= 11.57 jam = 11.57 per unit
Waktu Pelaksanaan = 1.65 Hari ~
3. Biaya Aktual = Luas xQ
= 72000 x6225.000
= Rp28,915,663Profit 10 % = Rp2,891,566 +Biaya Aktual = Rp31,807,229
4. HSP Pekerjaan = Biaya act + profit Rpvol . Bank
= Rp31,807,229 Rp72000
m²/jam
m²/jam
m²
m²
m²
HSP Pekerjaan = Rp442
5. Harga Penawaran = Biaya Actual + = Rp31,807,229
Harga Penawaran = Rp36,578,313
m²
41.66667 m/menit
0.83
2 Hari
BP & O
Rp2,500,000
Profit + Pajak 15%Rp31,807,229 + Rp4,771,084
Pemancangan pada abutmen jembatan dengan data sebagai berikutDiketahui : 1. Data Tiang Pancang
● Ukuran = 14 inchi x 14 inchi● Panjang = 50 Ft● Bj Beton = 150 Cuft/ton● Jumlah 1 abutmen = 36 batang ● Berat Pondasi ( P ) = ton● BP & O = Rp 5,000,000 /jam● Daya dukung pondasi = 40 ton● Faktor keamanan = 1.2
2. Data Hammer● Type Vulcan size 1 (SAS)● Waktu setting = 10 menit● BP & O = Rp 5,000,000 /jam● Berat Hammer (w) = 9700 lbs● Tinggi Jatuh Hammer ( h ) = 36 inches● Faktor Hammer (e) = 0.8● Nilai Restritusi (k) = 0.25
Ditanyakan : 1. Apakah Hammer sudah memadai ? Jika tidak , tentukan hammer yang memadai .2. Hitung waktu untuk memancang tiap batang !3. Hitung untuk semua pek. Pemancangan .4. Hitung biaya pek. Pemancangan .5. Hitung HSP6. Hitung biaya penawaran.
Ditanyakan :→Energi yang dihasilkan hammer
E= e x w x hE= 0,8 x 9700 x 36E= 279360 inch-lb
→Energi yang hilang● akibat pukulan (I)
I = e x w x h x p x w + p
I = 0,8 x 9700 x 36 x 8166,67 x9700 + 8166,67
I = 119711.78 inch-lb
● akibat head tiang pancang (CL)U = daya dukung pondasi x faktor keamananU = 240000 x 1,2
1 - k²
1 - 0,25²
U = 288000
CL = U x C 1 C1 = tekanan izin sementara kepada kepala tiang dan cap2 C1 = 0.01
CL = 288000 x 0,3942
CL = 113385.832
CL = 56692.91
● akibat tiang pancang (PL)PL = U x C 2 C2 = simpanan tiang akibat tekana izin sementara
2 C2 = 0.005PL = 288000 x 0,197
2PL = 56692.91
2.00PL = 28346.46
● akibat ujung tiang pancang (SL)SL = U x C 3 C3 = tekanan izin sementara
2 C3 = 0.003SL = 288000 x 0,118
2SL = 34015.75
2SL = 17007.87
→Energi bersih yang dapat digunakanUS = e x w x h - I - CL - PL - SLUS = 279360 - 119711,78 -56692,91 - 28346,46 - 17007,87
1. US = 57600.98 hammer memadai
S = US / US = 57600,98 / 288000S = 0.200 inchiS = 0.0051 meter
T = Le Le = 2/3 dari LS x V xFo Le = 33.33
T = 10.16 Le = 10.160,0051 x 60 x 0,83 V = 60
T = 40.16 Menit Fo = 0.83
2. →Waktu yang dibutuhkan untuk memancang 1 tiang pancang adalah =
3. →Waktu yang dibutuhkan untuk memancang semua tiang pancang adalah =
4. Biaya pemancangan = waktu pek. Pemancangan X BP&O= 30,10 jam X Rp. 5.000.000/jam= Rp 150,479,886.44
Profit 10% = Rp 15,047,988.64 +Biaya pemancangan = Rp 165,527,875.09
5. HSP Pekerjaan = Biaya act + profit RpJumlah tiang pancang
= Rp165,527,875 Rp36
HSP Pekerjaan = Rp4,597,997 /batang
6. Harga Penawaran = Biaya Actual + = Rp165,527,875
Harga Penawaran = Rp190,357,056
m²
m²
=
= 8166.67 lb
= 240000 lb
Apakah Hammer sudah memadai ? Jika tidak , tentukan hammer yang memadai .
tekanan izin sementara kepada kepala tiang dan capm 0.394 Inchi
simpanan tiang akibat tekana izin sementaram 0.197 Inchi
tekanan izin sementaram 0.118 Inchi
ftmeter
50.16 menit
30.10 jam
Profit + Pajak 15%Rp165,527,875 + Rp24,829,181
UNIT PRICE ANALYSIS
ITEM NUMBER : Sta. 0+000 s/d 20+000
UNIT OF WORK : Cu.m
QUANTITY OF WORK :
DAILY/HOURLY OUTPUT :
NO. DESCRIPTION UNIT ALAT QUANTITY UNIT
A. Pekerjaan Badan Jalan (Subgrade)
A.1 Penggalian Badan Jalan
Buldozer 11 172,800 M3A.2 Pengangkutan Galian
Wheel Loader 5 138,240 M3Dump Truck 10 138,240 M3
A.3 Pemadatan Badan Jalan
Tandem Roller 1 72,000 M3A.4 Perapian Badan Jalan
Motor Grader 1 72,000 M2
Sub TotalB. Pekerjaan Tebing
B.1 Penggalian Tebing
Excavator PC 200 1 22,350 M3
Sub Total
Sub Total = (A + B )
Overhead and Profit
TOTAL Before Tax
Tax
TOTAL
UNIT PRICE ANALYSIS
Q BP & O Real Cost Durasi
(Rp/hour) (Rp/m3) hari
134.95 2,952,000 240,625.00 20.0
141.60 1,250,000 44,139.41 33.577.93 262,500 33,683.74 30.4
17,637.50 2,000,000 113.39 0.7
1,344.60 2,200,000 1,636.17 9.2 320,197.71
186.25 1,200,000 6,442.88 0.76,442.88
326,640.60
% Profit = 15% 48,996.09
375,636.69
% Tax = 15% 56,345.50
431,982.19
( m3/hour)