TUGAS ANALISA BEBAN DAN TENAGA 1. Diketahui : 1.Kelandaian ( K ) = 5% 2.Koef. Tahanan Gelinding ( = 5% 3.Berat Traktor ( W ) = 26 4.Berat Scraper ( W ) = 16 5.Muatan Scraper = 4 Ditanyakan : Berapa besar tenaga yang dibutuhkan untuk K = 5% Jawab : Tenaga yang dibutuhkan = Beban Tota 1. Traktor ( Roda Rantai ) TR = Tahanan Kelandaian (GR) = W x % K = 1.3 ton 2. Scraper ( Roda Karet ) TR = Tahanan Kelandaian (GR) + Tahanan Gelindi = ( W x % K ) + ( W x % r ) = 2 ton Jadi tenaga yang dibutuhkan traktor adalah = 3.3 2. Diketahui : 1.Kelandaian ( K ) = 8% 2.Harraw ditarik pada datar = 4500 3.Berat Bulldozer ( W ) = 18 4.Berat Harraw ( W ) = 4 5.Koef. Traksi Kritis ( ct = 0.65 K = 8% Ditanyakan : Mampukah Bulldozer menarik harraw ? Jawab : 1. Bulldozer ( Roda Rantai ) TR = Tahanan Kelandaian (GR) = W x % K = 1.44 ton 2. Scraper ( Roda Rantai ) TR = 4500 kg + Tahanan Kelandaian (GR) = 4500 kg + ( W x % K ) = 4.82 ton Tenaga yang dibutuhkan Bulldozer (TR) = 6.26 raksi Kritis Bulldozer (TK) = W x ct = 11.7 TK > TR = Mampu TRAKTO R SCRAPER BULLDOZER HARRAW

Upload: put-anton

Post on 24-Jul-2015

2.845 views

Category:

Documents


242 download

TRANSCRIPT

Page 1: Perhitungan Produktifitas Alat Berat

TUGAS

ANALISA BEBAN DAN TENAGA

1. Diketahui : 1.Kelandaian ( K ) = 5%2.Koef. Tahanan Gelinding ( r ) = 5%3.Berat Traktor ( W ) = 26 ton4.Berat Scraper ( W ) = 16 ton5.Muatan Scraper = 4 ton

Ditanyakan : Berapa besar tenaga yang dibutuhkan untuk menarik scraper ?

K = 5% Jawab :

Tenaga yang dibutuhkan = Beban Total ( TR )

1. Traktor ( Roda Rantai )

TR = Tahanan Kelandaian (GR) = W x % K = 1.3 ton

2. Scraper ( Roda Karet )

TR = Tahanan Kelandaian (GR) + Tahanan Gelinding (RR) = ( W x % K ) + ( W x % r ) = 2 ton

Jadi tenaga yang dibutuhkan traktor adalah = 3.3 ton

2. Diketahui : 1.Kelandaian ( K ) = 8%2.Harraw ditarik pada datar = 4500 kg3.Berat Bulldozer ( W ) = 18 ton4.Berat Harraw ( W ) = 4 ton5.Koef. Traksi Kritis ( ct ) = 0.65

K = 8% Ditanyakan : Mampukah Bulldozer menarik harraw ?

Jawab :

1. Bulldozer ( Roda Rantai )

TR = Tahanan Kelandaian (GR) = W x % K = 1.44 ton

2. Scraper ( Roda Rantai )

TR = 4500 kg + Tahanan Kelandaian (GR) = 4500 kg + ( W x % K ) = 4.82 ton

Tenaga yang dibutuhkan Bulldozer (TR) = 6.26 ton

Traksi Kritis Bulldozer (TK) = W x ct = 11.7 ton

TK > TR = Mampu

TRAKTOR

SCRAPER

BULLDOZER

HARRAW

Page 2: Perhitungan Produktifitas Alat Berat

Latihan 1

Proyek jalan raya

= 24

STA 00 STA 6000

galian timbunan galian timbunan galian

Diketahui :a. Data Pekerjaan & alat b. Kondisi Tanah

Galian 1. Tanah Biasa = 0.83p = 4000 m 2. Sweel = 20%t = 1.8 m

Timbunanp = 2000 mt = 1.2 m

1. Alat Bulldozer type s =2. Lebar blade = 3.2 m3. Tinggi blade = 1.1 m4. Biaya Pemblian = Rp19,000,000,0005. Nilai Sisa = 10%6. Waktu Investasi = 8 thn7. Masa guna alat = 10000 jam8. Biaya Operasional = Rp900,0009. Biaya Investasi = 18% dari harga pembelian

= Rp3,420,000,000

c. Metode kerja1 Metode kerja = Slot and Dozing2 Waktu kerja 50 menit/jam =3 Operator Pandai = 0.834 V mendorong = 4.5 km/jam = 75 m/menit5 V mundur = 6 km/jam = 100 m/menit6 Bekerja waktu kemarau =7 Durasi 20 hari @ 7 jam = 140 jam8 Perataan timbinan perlapis = 0.3 m

Ditanyakan : 1 Produksi alat dalam 1 jam ( Q )2 Hitung jumlah alat3 Biaya aktual apabila profit 10%4 HSP pekerjaan5 Biaya penawaran dengan pajak 15%6 Jadwal

Page 3: Perhitungan Produktifitas Alat Berat

Jawab : GALIAN● Volume Pekerjaan Galian ( bank ) = 172800● sweel = 20%● Volume Pekerjaan Galian ( loose ) = 207360● Kapasitas Blade ( B ) = 3.872● Jarak Operasi Blade , dengan kedalaman = 60.5 m

0.02 m ( J )● CT = 1.412 menit● E = 0.82

1 Q = Q' x EQ' = 60 x B

CT = 232.32 = 164.5714

1.412Q = 134.9486 Lm³/jam

2 Durasi Alat = 207360134.948571428571 Lm³/jam

= 1537 Jam

Jumlah Alat = 1537 Jam140 Jam

Jumlah Alat = 10.97561 ~ 11 UNIT

3 BP● Depresiasi / jam = Rp1,710,000● Investasi / jam = Rp342,000 +

BP = Rp2,052,000 /jam

O = Rp900,000 /jam +

BP & O = Rp2,952,000 /jam

Biaya Aktual = Vol. Loose x BP & OQ

= 207360 x Rp2,952,000134.949

= Rp4,536,000,000Profit 10 % = Rp453,600,000 +Biaya Aktual = Rp4,989,600,000

4 HSP Pekerjaan = Biaya act + profit Rpvol . Bank

= Rp4,989,600,000 Rp172800

Lm³Lm³

Lm³/jam

Lm³

Page 4: Perhitungan Produktifitas Alat Berat

HSP Pekerjaan = Rp28,875 Rp/m³

5 Harga Penawaran = Biaya Actual + Profit + Pajak 15% = Rp4,989,600,000 + Rp748,440,000

Harga Penawaran = Rp5,738,040,000

Page 5: Perhitungan Produktifitas Alat Berat

m

Page 6: Perhitungan Produktifitas Alat Berat

TIMBUNAN● Volume Pekerjaan Galian ( bank ) = 57600● sweel = 20%● Volume Pekerjaan Galian ( loose ) = 69120● Kapasitas Blade ( B ) = 3.872● Jarak Operasi Blade , dengan kedalaman = 4.033 m

0.3 m ( J )● CT = 0.094 menit● E = 0.82

1 Q = Q' x EQ' = 60 x B

CT = 232.32 = 2468.571

0.094Q = 2024.229 Lm³/jam

2 Durasi Alat = 691202024.2285714286 Lm³/jam

= 34 Jam

Jumlah Alat = 34 Jam140 Jam

Jumlah Alat = 0.243902 ~ 1 UNIT

3 BP● Depresiasi / jam = Rp1,710,000● Investasi / jam = Rp342,000

BP = Rp2,052,000

O = Rp900,000

BP & O = Rp2,952,000

Biaya Aktual = Vol. Loose x BP & OQ

= 69120 x Rp2,952,0002024.229

= Rp100,800,000Profit 10 % = Rp10,080,000 +Biaya Aktual = Rp110,880,000

4 HSP Pekerjaan = Biaya act + profit Rpvol . Bank

= Rp110,880,000 Rp57600

Lm³Lm³

Lm³/jam

Lm³

Page 7: Perhitungan Produktifitas Alat Berat

HSP Pekerjaan = Rp1,925 Rp/m³

Pajak 15% 5 Harga Penawaran = Biaya Actual + Profit +Rp748,440,000 = Rp110,880,000 +

Harga Penawaran = Rp127,512,000

Page 8: Perhitungan Produktifitas Alat Berat

+/jam

/jam +/jam

Page 9: Perhitungan Produktifitas Alat Berat

Pajak 15%Rp16,632,000

Page 10: Perhitungan Produktifitas Alat Berat

Latihan 2

4.47 CL4 m

2 : 1

2.5 m

Diketahui : 1. Data alat● Excavator PC 180 =● Kapasitas ( q ' ) = 0.85

2. Data pekerjaan ● panjang galian = 2000 m● tanah biasa ( K ) = 1.1● sweel = 20%● digging condition 60 % = 1● = 15 detik● Koefisien efesiensi ( E ) "good" = 0.83● Durasi 30 hari @ 7 jam kerja = 210 jam● BP & O = Rp1,200,000

Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung jumlah alat3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal

Jawab : 1. Volume pekerjaan galian ( bank ) = 22350Volume pekerjaan galian ( loose ) = 26820

Q = Q ' x E

Q' = 60 x qCT (menit )

q = q ' x K

Q = 46.5630.25

swing angle 70°

m³Lm³

Page 11: Perhitungan Produktifitas Alat Berat

Q = 186.252

2. Durasi alat = 26820186.252 Lm³/jam

= 143.998 Jam

Jumlah Alat = 143.998 Jam210 Jam

Jumlah Alat = 0.6857069224185 ~ 1 UNIT

3. Biaya Aktual = Vol. Loose X BP & OQ

= 26820 X Rp1,200,000186.252

= Rp172,798,144Profit 10% = Rp17,279,814 +Biaya Aktual = Rp190,077,959

4. HSP pekerjaan = Biaya act + profit Rpvol . Bank

= Rp190,077,959 Rp22350

HSP pekerjaan = Rp8,505

5. Harga Penawaran = Biaya actual + Profit + = Rp190,077,959 +

Harga Penawaran = Rp218,589,653

Lm³/jam

Lm³

m³Rp/m³

Page 12: Perhitungan Produktifitas Alat Berat

/jam

Page 13: Perhitungan Produktifitas Alat Berat

Pajak 15 %Rp28,511,694

Page 14: Perhitungan Produktifitas Alat Berat

Latuhan 3

Tanah

12 m

12 m

Diketahui : a. Data pekerjaan & alat1 = 138240

2 Bucket Kapasitas ( q ' ) = 3.43 Faktor Bucket ( K ) = 0.954 BP & O = Rp1,250,000 /Jam5 FT = 0.2 menit6 Koefisien efesiensi ( E ) "good" = 0.83

b. Metode kerja1 V shape ,dengan jarak = 12 m2 kecepatan isi = 2.5 km/jam = 41.6673 kecepatan kosong = 4 km/jam = 66.6674 waktu 30 hari @ 7 jam = 210 jam

Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung jumlah alat3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal

Jawab : 1. CT = J1 = J2 = 2J

+ 2J + FTkecp. Isi kecp. Kosong

Pengangkutan tanah dengan Vol. Pekerjaan 2/3 dari hasil galian bulldozer

Lm³

WL

DT

Page 15: Perhitungan Produktifitas Alat Berat

= 0.576 + 0.36 + 0.2 = 1.136 menit

volume pekerjaan ( bank ) = 115200sweel = 20%volume pekerjaan ( loose ) = 138240

Q = Q ' x E

Q' = 60 x qCT (menit )

q = q ' x K

Q = 160.8541.136

Q = 141.597

2. Durasi alat = 138240141.597

= 976.293 jam

Jumlah alat = 976.293 jam210 jam

Jumlah alat = 4.6490144567656 ~ 5

3. Biaya Aktual = Vol. Loose X BP&OQ

= 138240 X Rp1,250,000141.597

= Rp1,220,366,295Profit 10% = Rp122,036,629 +Biaya Aktual = Rp1,342,402,924

4. HSP Pekerjaan = Biaya Act. + profit RpVol. Bank

= Rp1,342,402,924 Rp115200

HSP Pekerjaan = Rp11,653 Rp/jam

5. Harga Penawaran = Biaya Act. + Profit = Rp1,342,402,924

Harga Penawaran = Rp 1,543,763,363

Lm³

Lm³/jam

Lm³Lm³/jam

Page 16: Perhitungan Produktifitas Alat Berat

m/menitm/menit

Page 17: Perhitungan Produktifitas Alat Berat

UNIT

Rp1,250,000

Profit + Pajak 15%Rp1,342,402,924 + Rp 201,360,439

Page 18: Perhitungan Produktifitas Alat Berat

Latihan 4

10%

750 m

600 m

Diketahui : 1. Data Alat● Dump Truck HD 325● Berat Kosong = 27.2 ton● Berat Bermuatan Max = 52.3 ton● Batasan Kacapatan = V max Flat = Isi = 40

Kosong = 60

= = Isi = 20Kosong = 40

● Sewa Dump Truck = Rp2,100,000 /hari = Rp262,500

2. Data Pekerjaan● Volume Pekerjaan = 115200

= 138240● Route Pengangkutan = Membawa sama dengan kembali● Kondisi Jalan = Kering dan kurang terpelihara =● = 1.6● Managemen Baik =● Dumping = Lancar Tanpa Ada Hambatan● Spot & Delay = Lancar Tanpa Ada Hambatan

Ditanyakan : 1 Produksi alat dalam 1 jam ( Q )2 Hitung Durasi3 Biaya aktual apabila profit 10%4 HSP pekerjaan5 Biaya penawaran dengan pajak 15%6 Jadwal

Jawab : 1 CT = T1 + T2 + T3 + T4 + T5Tabel T2 dan T4

T1 = n X CT wheel loader tipe angkutSegmen

V max Turunan/ tanjakan

m³lm³

γ Tanah ton/m³

DUMP TRUCK

Page 19: Perhitungan Produktifitas Alat Berat

n = q DT ( kg )tipe angkut

kondisi

Membawa (isi)Datar

n = (52,3 t - 27,2 t )x 1000 Tanjakan3,4 x 0,95 x 1600 Datar

n = 25100 Datar5168 Turunan

n = 4.85681115 ~ 5 Datar

T1 = 5 x 1,136 menit T3 = 0.6T1 = 5.68 menit T5 = 0.15

CT = T1 + T2 + T3 + T4 + T5CT = 8.69 menit

M = CT dtn X CT wl

M = 8.695.68

M = 1.53 ~ 2 unit

Q = Q' x E x M E ( GOOD ) = 0.83Q' = 60 x q DT

CTq DT = n x q L

Q' = 60 x 9 x 3,48.69

Q' = 46.95

Q = 194,48 x 0,83 x 9Q = 77.93

2 Hitung Durasi

Volume ( Bank ) = 115200Sweel = 20%Volume ( Loose ) = 138240

Waktu Pelaksanaan = Vol. looseQ

= 13824077.93

= 1773.88 jam

Waktu Pelaksanaan = 253.41 Hari ~ 254 Hari

3. Biaya Aktual = Vol. Loose x BP & O

q WL x K x γt

Kembali ( kosong )

Lm³/jam

Lm³/jam

Lm³

Page 20: Perhitungan Produktifitas Alat Berat

Qx BP & O

= 138240 x Rp262,50077.931

= Rp465,644,005Profit 10 % = Rp46,564,400 +Biaya Aktual = Rp512,208,405

4. HSP Pekerjaan = Biaya act + profit Rpvol . Bank

= Rp512,208,405 Rp115200

HSP Pekerjaan = Rp4,446 Rp/m³

5. Harga Penawaran = Biaya Actual + Profit = Rp512,208,405

Harga Penawaran = Rp589,039,666

Page 21: Perhitungan Produktifitas Alat Berat

350 m

Km/jam = 667 m/menitKm/jam = 1000 m/menit

Km/jam = 333 m/menitKm/jam = 667 m/menit

/jam

8%

Produksi alat dalam 1 jam ( Q )Hitung DurasiBiaya aktual apabila profit 10%HSP pekerjaanBiaya penawaran dengan pajak 15%Jadwal

Segmen tahanan kecepatanTime

Page 22: Perhitungan Produktifitas Alat Berat

kondisi jarak RR GR TR F Vmax SF V rata2Time

Datar 600 8% 0% 8% 667 0.72 480

1.393443T2Tanjakan 750 8% 10% 18% 333 0.78 260

Datar 350 8% 0% 8% 667 0.72 480Datar 600 8% 0% 8% 1000 0.72 720

0.867347

T4Turunan 750 8% -10% -2% 667 0.78 520

Datar 350 8% 0% 8% 1000 0.72 720

menitmenit

Hitung Durasi

BP & O

Page 23: Perhitungan Produktifitas Alat Berat

BP & O

Rp262,500

Profit + Pajak 15%Rp512,208,405 + Rp76,831,261

Page 24: Perhitungan Produktifitas Alat Berat

Latihan 5Return

Houling

Diketahui : 1. Data Alat● Kapasitas bowel (q ) = 10● Kecp. Digging (VD) = 1.5 km/jam = 25● Kecp. Houling (VH) = 10 km/jam = 166.6667● Kecp. Spreading (VS) = 3 km/jam = 50.00● Kecp. Returning (VR) = 12 km/jam = 200

2. Data Pekerjaan● Jarak Digging (D) = 35 m● Jarak Houling (H) = 175 m● Jarak Spreading (S) = 25 m● Jarak Returning (R) = 200 m● Vulome Galian = 500000● Volume Urugan = 500000● Banyak Alat = 5 Unit● BP & O = Rp1,500,000 per jam● FT = 1

Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung waktu pelaksanaa3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal

Dijawab : 1. CT =

CT = 35 +

175 +

25 +

25 166.67 50.00CT = 4.95 menit

m³m³

digspred

35 m

25 m

175 m

200 m

𝐷𝑉𝐷 + 𝐻𝑉𝐻 + 𝑆𝑉𝑆+ 𝑅𝑉𝑅 + FT

Page 25: Perhitungan Produktifitas Alat Berat

E = E1 X E2 X E3 Dimana : E1 = Waktu Kerja 50m/jE = 1.008 E2 = Operator Baik

E3 = Tanah Biasa

Q' = 60 X qCT

Q' = 6004.95

Q' = 121.2121212 Lm³/jam

Q' = Q' X EQ = 122.1818182 Lm³/jam

2. Volume ( Bank ) = 500000Sweel = 20%Volume ( Loose ) = 600000

Waktu Pelaksanaan = Vol. looseQ

= 600000122.18

= 4910.71 jam / 5 unit = 982.14 per unit

Waktu Pelaksanaan = 140.31 Hari ~ 141

3. Biaya Aktual = Vol. Loose x BP & OQ

= 600000 x Rp1,500,000122.182

= Rp7,366,071,429Profit 10 % = Rp736,607,143 +Biaya Aktual = Rp8,102,678,571

4. HSP Pekerjaan = Biaya act + profit Rpvol . Bank

= Rp8,102,678,571 Rp500000

HSP Pekerjaan = Rp16,205 Rp/m³

5. Harga Penawaran = Biaya Actual + Profit = Rp8,102,678,571

Harga Penawaran = Rp9,318,080,357

Lm³

Page 26: Perhitungan Produktifitas Alat Berat

m/menitm/menitm/menitm/menit

200 + 1

200

𝐷𝑉𝐷 + 𝐻𝑉𝐻 + 𝑆𝑉𝑆+ 𝑅𝑉𝑅 + FT

Page 27: Perhitungan Produktifitas Alat Berat

= 0.84 = 1 = 1.2

Hari

BP & O

Rp1,500,000

Profit + Pajak 15%Rp8,102,678,571 + Rp1,215,401,786

Page 28: Perhitungan Produktifitas Alat Berat

lo

6 L leα

6

6000

Diketahui : 1. Data Alat● Lebar Blade ( L ) = 3.1 m● =● Kecepatan rata2 = 4 km/jam =● BP & O / jam = Rp2,200,000● Jumlah alat = 1 unit

2. Data Pekerjaan● Lebar lapisan = 12 m● Laluan Subgrade (n) = 6 kali● Laluan sub base (n) = 4 kali● Laluan base course (n) = 3 kali● Lebar overlap (lo) = 0.25 m● E faktor ( good ) = 0.83

Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung waktu pelaksanaa3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal

SUBGRADEDijawab : 1. Q = Q' X E

Q' = 60 X V .( le - lo ) le =n le = sin 60 x 3,1

Q' = 60 x 66,67 . ( 2,68 - 0,25 ) le = 2.686

Q' = 97206

Q' = 1620.00

Q = 1620 x 0,83Q = 1344.60

2. Luas Perataan = 72000

Sudut Kerja ( α ) 60 °

sin α x L

m²/jam

Page 29: Perhitungan Produktifitas Alat Berat

Waktu Pelaksanaan = LuasQ

= 720001344.60

= 53.55 jam = 53.55 per unit

Waktu Pelaksanaan = 7.65 Hari ~

3. Biaya Aktual = Luas xQ

= 72000 x1344.600

= Rp117,804,552Profit 10 % = Rp11,780,455 +Biaya Aktual = Rp129,585,007

4. HSP Pekerjaan = Biaya act + profit RpLuas

= Rp129,585,007 Rp72000

HSP Pekerjaan = Rp1,800

5. Harga Penawaran = Biaya Actual + = Rp129,585,007

Harga Penawaran = Rp149,022,758

m²Rp/m²

Page 30: Perhitungan Produktifitas Alat Berat

66.67 m/menit

SUB BASE1. Q =

Q' =sin 60 x 3,1

m Q' =

Q' =

Q' =

Q =Q =

2. Luas Perataan

Page 31: Perhitungan Produktifitas Alat Berat

Waktu Pelaksanaan

8 Hari Waktu Pelaksanaan

BP & O 3. Biaya Aktual

Rp2,200,000

Profit 10 %Biaya Aktual

4. HSP Pekerjaan

HSP Pekerjaan

Profit + Pajak 15% 5. Harga PenawaranRp129,585,007 + Rp19,437,751

Harga Penawaran

Page 32: Perhitungan Produktifitas Alat Berat

Q' X E60 X V .( le - lo ) le =

n le = sin 60 x 3,160 x 66,67 . ( 2,68 - 0,25 ) le = 2.68 m

49720

42430.00

2430 x 0,832016.90

Luas Perataan = 72000

sin α x L

m²/jam

Page 33: Perhitungan Produktifitas Alat Berat

Waktu Pelaksanaan = LuasQ

= 720002016.90

= 35.70 jam = 35.70 per unit

Waktu Pelaksanaan = 5.10 Hari ~ 6 Hari

Biaya Aktual = Luas x BP & OQ

= 72000 x Rp2,200,0002016.900

= Rp78,536,368Profit 10 % = Rp7,853,637 +Biaya Aktual = Rp86,390,004

HSP Pekerjaan = Biaya act + profit RpLuas

= Rp86,390,004 Rp72000

HSP Pekerjaan = Rp1,200

Harga Penawaran = Biaya Actual + Profit + = Rp86,390,004 +

Harga Penawaran = Rp99,348,505

m²Rp/m²

Page 34: Perhitungan Produktifitas Alat Berat

BASE COURSE1. Q = Q' X E

Q' = 60 X V .( le - lo )n

Q' = 60 x 66,67 . ( 2,68 - 0,25 )3

Q' = 97203

Q' = 3240.00

Q = 3240 x 0,83Q = 2689.20

2. Luas Perataan = 72000

m²/jam

Page 35: Perhitungan Produktifitas Alat Berat

Waktu Pelaksanaan = LuasQ

= 720002689.20

= 26.77 = 26.77

Waktu Pelaksanaan = 3.82

3. Biaya Aktual = LuasQ

= 720002689.200

= Rp58,902,276Profit 10 % = Rp5,890,228Biaya Aktual = Rp64,792,503

4. HSP Pekerjaan = Biaya act + profitLuas

= Rp64,792,50372000

HSP Pekerjaan = Rp900

Pajak 15% 5. Harga Penawaran = Biaya ActualRp12,958,501 = Rp64,792,503

Harga Penawaran = Rp74,511,379

Page 36: Perhitungan Produktifitas Alat Berat

le =le = sin 60 x 3,1le = 2.68 m

sin α x L

Page 37: Perhitungan Produktifitas Alat Berat

jamper unit

Hari ~ 4 Hari

Luas x BP & OQ

72000 x Rp2,200,0002689.200

Rp58,902,276Rp5,890,228 +

Rp64,792,503

Biaya act + profit RpLuas

Rp64,792,503 Rp72000Rp900

Biaya Actual + Profit + Pajak 15%Rp64,792,503 + Rp9,718,876

Rp74,511,379

m²Rp/m²

Page 38: Perhitungan Produktifitas Alat Berat

Diketahui : 1. Data Alat● Lebar roda (w) = 2 m● Kecp. Rata2 = 3 km/jam =● Overlap (wo) = 0.3 m● BP & O = Rp2,000,000 /jam

2. Data Pekerjaan● Laluan Subgrade = 4 kali● Laluan Subbase = 3 kali● Laluan Base course = 3 kali

Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung waktu pelaksanaa3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal

SUBGRADEDijawab : 1. Q= Q' X E

Q'= 1000 . V . ( w - Wo )n

Q'= 850004

Q'= 21250

Q= Q' X E E faktor ( good ) =Q= 21250 x 0,83Q= 17637.5

2. Luas Perataan = 72000

Waktu Pelaksanaan = LuasQ

= 7200017637.50

= 4.08 jam = 4.08 per unit

Waktu Pelaksanaan = 0.58 Hari ~

3. Biaya Aktual = Luas xQ

= 72000 x17637.500

= Rp8,164,422

m²/jam

m²/jam

Page 39: Perhitungan Produktifitas Alat Berat

Profit 10 % = Rp816,442 +Biaya Aktual = Rp8,980,865

4. HSP Pekerjaan = Biaya act + profit RpLuas

= Rp8,980,865 Rp72000

HSP Pekerjaan = Rp125

5. Harga Penawaran = Biaya Actual + = Rp8,980,865

Harga Penawaran = Rp10,327,994

m²/m²

Page 40: Perhitungan Produktifitas Alat Berat

50 m/menit

SUB BASE1. Q=

Q'=

Q'=

Q'=

0.83 Q=Q=Q=

2. Luas Perataan

Waktu Pelaksanaan

1 Hari Waktu Pelaksanaan

BP & O 3. Biaya Aktual

Rp2,000,000

Page 41: Perhitungan Produktifitas Alat Berat

Profit 10 %Biaya Aktual

4. HSP Pekerjaan

HSP Pekerjaan

Profit + Pajak 15% 5. Harga PenawaranRp8,980,865 + Rp1,347,130

Harga Penawaran

Page 42: Perhitungan Produktifitas Alat Berat

Q' X E1000 . V . ( w - Wo )

n85000

328333.33

Q' X E E faktor ( good ) = 0.8328333,3 x 0,8323516.67

Luas Perataan = 72000

Waktu Pelaksanaan = LuasQ

= 7200023516.67

= 3.06 jam = 3.06 per unit

Waktu Pelaksanaan = 0.44 Hari ~ 1 Hari

Biaya Aktual = Luas x BP & OQ

= 72000 x Rp2,000,00023516.667

= Rp6,123,317

m²/jam

m²/jam

Page 43: Perhitungan Produktifitas Alat Berat

Profit 10 % = Rp612,332 +Biaya Aktual = Rp6,735,648

HSP Pekerjaan = Biaya act + profit RpLuas

= Rp6,735,648 Rp72000

HSP Pekerjaan = Rp94

Harga Penawaran = Biaya Actual + Profit + Pajak 15% = Rp6,735,648 + Rp1,010,347

Harga Penawaran = Rp7,745,996

m²Rp/m²

Page 44: Perhitungan Produktifitas Alat Berat

BASE COURSE1. Q= Q' X E

Q'= 1000 . V . ( w - Wo )n

Q'= 850003

Q'= 28333.33

Q= Q' X E E faktor ( good ) =Q= 28333,3 x 0,83Q= 23516.67

2. Luas Perataan = 72000

Waktu Pelaksanaan = LuasQ

= 7200023516.67

= 3.06 jam = 3.06 per unit

Waktu Pelaksanaan = 0.44 Hari ~

3. Biaya Aktual = Luas xQ

= 72000 x23516.667

= Rp6,123,317

m²/jam

m²/jam

Page 45: Perhitungan Produktifitas Alat Berat

Profit 10 % = Rp612,332 +Biaya Aktual = Rp6,735,648

4. HSP Pekerjaan = Biaya act + profit RpLuas

= Rp6,735,648 Rp72000

HSP Pekerjaan = Rp94

Pajak 15% 5. Harga Penawaran = Biaya Actual +Rp1,010,347 = Rp6,735,648

Harga Penawaran = Rp7,745,996

m²Rp/m²

Page 46: Perhitungan Produktifitas Alat Berat

0.83

1 Hari

BP & O

Rp2,000,000

Page 47: Perhitungan Produktifitas Alat Berat

Profit + Pajak 15%Rp6,735,648 + Rp1,010,347

Page 48: Perhitungan Produktifitas Alat Berat

Diketahui : 1. Data Alat● Lebar roda (w) = 3 m● Kecp. Rata2 = 2.5 km/jam =● BP & O = Rp2,500,000 /jam

2. Data Pekerjaan● Tebal = 5 cm

Ditanyakan : 1. Produksi alat dalam 1 jam ( Q )2. Hitung waktu pelaksanaa3. Biaya aktual apabila profit 10%4. HSP pekerjaan5. Biaya penawaran dengan pajak 15%6. Jadwal

Dijawab : 1. Q = Q' X EQ' = 60 X V X WQ' = 60 X 41,67 X 3Q' = 7500

Q = Q' X E E faktor ( good ) =Q = 7500 X 0,83Q = 6225

2. Luas Permukaan = 72000

Waktu Pelaksanaan = LuasQ

= 720006225.00

= 11.57 jam = 11.57 per unit

Waktu Pelaksanaan = 1.65 Hari ~

3. Biaya Aktual = Luas xQ

= 72000 x6225.000

= Rp28,915,663Profit 10 % = Rp2,891,566 +Biaya Aktual = Rp31,807,229

4. HSP Pekerjaan = Biaya act + profit Rpvol . Bank

= Rp31,807,229 Rp72000

m²/jam

m²/jam

Page 49: Perhitungan Produktifitas Alat Berat

HSP Pekerjaan = Rp442

5. Harga Penawaran = Biaya Actual + = Rp31,807,229

Harga Penawaran = Rp36,578,313

Page 50: Perhitungan Produktifitas Alat Berat

41.66667 m/menit

0.83

2 Hari

BP & O

Rp2,500,000

Page 51: Perhitungan Produktifitas Alat Berat

Profit + Pajak 15%Rp31,807,229 + Rp4,771,084

Page 52: Perhitungan Produktifitas Alat Berat

Pemancangan pada abutmen jembatan dengan data sebagai berikutDiketahui : 1. Data Tiang Pancang

● Ukuran = 14 inchi x 14 inchi● Panjang = 50 Ft● Bj Beton = 150 Cuft/ton● Jumlah 1 abutmen = 36 batang ● Berat Pondasi ( P ) = ton● BP & O = Rp 5,000,000 /jam● Daya dukung pondasi = 40 ton● Faktor keamanan = 1.2

2. Data Hammer● Type Vulcan size 1 (SAS)● Waktu setting = 10 menit● BP & O = Rp 5,000,000 /jam● Berat Hammer (w) = 9700 lbs● Tinggi Jatuh Hammer ( h ) = 36 inches● Faktor Hammer (e) = 0.8● Nilai Restritusi (k) = 0.25

Ditanyakan : 1. Apakah Hammer sudah memadai ? Jika tidak , tentukan hammer yang memadai .2. Hitung waktu untuk memancang tiap batang !3. Hitung untuk semua pek. Pemancangan .4. Hitung biaya pek. Pemancangan .5. Hitung HSP6. Hitung biaya penawaran.

Ditanyakan :→Energi yang dihasilkan hammer

E= e x w x hE= 0,8 x 9700 x 36E= 279360 inch-lb

→Energi yang hilang● akibat pukulan (I)

I = e x w x h x p x w + p

I = 0,8 x 9700 x 36 x 8166,67 x9700 + 8166,67

I = 119711.78 inch-lb

● akibat head tiang pancang (CL)U = daya dukung pondasi x faktor keamananU = 240000 x 1,2

1 - k²

1 - 0,25²

Page 53: Perhitungan Produktifitas Alat Berat

U = 288000

CL = U x C 1 C1 = tekanan izin sementara kepada kepala tiang dan cap2 C1 = 0.01

CL = 288000 x 0,3942

CL = 113385.832

CL = 56692.91

● akibat tiang pancang (PL)PL = U x C 2 C2 = simpanan tiang akibat tekana izin sementara

2 C2 = 0.005PL = 288000 x 0,197

2PL = 56692.91

2.00PL = 28346.46

● akibat ujung tiang pancang (SL)SL = U x C 3 C3 = tekanan izin sementara

2 C3 = 0.003SL = 288000 x 0,118

2SL = 34015.75

2SL = 17007.87

→Energi bersih yang dapat digunakanUS = e x w x h - I - CL - PL - SLUS = 279360 - 119711,78 -56692,91 - 28346,46 - 17007,87

1. US = 57600.98 hammer memadai

S = US / US = 57600,98 / 288000S = 0.200 inchiS = 0.0051 meter

T = Le Le = 2/3 dari LS x V xFo Le = 33.33

T = 10.16 Le = 10.160,0051 x 60 x 0,83 V = 60

T = 40.16 Menit Fo = 0.83

2. →Waktu yang dibutuhkan untuk memancang 1 tiang pancang adalah =

Page 54: Perhitungan Produktifitas Alat Berat

3. →Waktu yang dibutuhkan untuk memancang semua tiang pancang adalah =

4. Biaya pemancangan = waktu pek. Pemancangan X BP&O= 30,10 jam X Rp. 5.000.000/jam= Rp 150,479,886.44

Profit 10% = Rp 15,047,988.64 +Biaya pemancangan = Rp 165,527,875.09

5. HSP Pekerjaan = Biaya act + profit RpJumlah tiang pancang

= Rp165,527,875 Rp36

HSP Pekerjaan = Rp4,597,997 /batang

6. Harga Penawaran = Biaya Actual + = Rp165,527,875

Harga Penawaran = Rp190,357,056

Page 55: Perhitungan Produktifitas Alat Berat

=

= 8166.67 lb

= 240000 lb

Apakah Hammer sudah memadai ? Jika tidak , tentukan hammer yang memadai .

Page 56: Perhitungan Produktifitas Alat Berat

tekanan izin sementara kepada kepala tiang dan capm 0.394 Inchi

simpanan tiang akibat tekana izin sementaram 0.197 Inchi

tekanan izin sementaram 0.118 Inchi

ftmeter

50.16 menit

Page 57: Perhitungan Produktifitas Alat Berat

30.10 jam

Profit + Pajak 15%Rp165,527,875 + Rp24,829,181

Page 58: Perhitungan Produktifitas Alat Berat
Page 59: Perhitungan Produktifitas Alat Berat

UNIT PRICE ANALYSIS

ITEM NUMBER : Sta. 0+000 s/d 20+000

UNIT OF WORK : Cu.m

QUANTITY OF WORK :

DAILY/HOURLY OUTPUT :

NO. DESCRIPTION UNIT ALAT QUANTITY UNIT

A. Pekerjaan Badan Jalan (Subgrade)

A.1 Penggalian Badan Jalan

Buldozer 11 172,800 M3A.2 Pengangkutan Galian

Wheel Loader 5 138,240 M3Dump Truck 10 138,240 M3

A.3 Pemadatan Badan Jalan

Tandem Roller 1 72,000 M3A.4 Perapian Badan Jalan

Motor Grader 1 72,000 M2

Sub TotalB. Pekerjaan Tebing

B.1 Penggalian Tebing

Excavator PC 200 1 22,350 M3

Sub Total

Sub Total = (A + B )

Overhead and Profit

TOTAL Before Tax

Tax

TOTAL

Page 60: Perhitungan Produktifitas Alat Berat

UNIT PRICE ANALYSIS

Q BP & O Real Cost Durasi

(Rp/hour) (Rp/m3) hari

134.95 2,952,000 240,625.00 20.0

141.60 1,250,000 44,139.41 33.577.93 262,500 33,683.74 30.4

17,637.50 2,000,000 113.39 0.7

1,344.60 2,200,000 1,636.17 9.2 320,197.71

186.25 1,200,000 6,442.88 0.76,442.88

326,640.60

% Profit = 15% 48,996.09

375,636.69

% Tax = 15% 56,345.50

431,982.19

( m3/hour)

I21
Author: m2/hour