7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
1/37
PRIVATE AND CONFIDENTIAL
SATUAN KERJA KHUSUS
PELAKSANA KEGIATAN USAHA HULU MINYAK DAN GAS BUMI
(SKKMIGAS)
PRIVATE AND CONFIDENTIAL
Mekanisme Penghitungan Anggaran dan Realisasi
Lifting dalam
Production Sharing Contract
Solo, 20-22 Agustus 2015
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
2/37
2013SKKMIGAS
Allrightsreserved
AGENDA 1. Production Sharing Contract (PSC)
2. Skema PSC
3. Perhitungan Lifting dan Pelaporan
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
3/37
2013SKKMIGAS
Allrightsreserved
AGENDA 1. Production Sharing Contract
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
4/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Klasifikasi Kontrak Industri Hulu Migas
Sistem
Kontrak Migas
Kontrak
Kontrak Jasa
Kontrak JasaMurni
Kontrak JasaBeresiko
ProductionSharingContract
Konsesi
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
5/37PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Mekanisme Pembagian Kontrak Hulu Migas
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
6/37PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Sejarah Production Sharing Contract Indonesia
Era Kolonial Belanda Era Awal Kemerdekaan Era Industri MigasModern
Penemuan Minyak diTelaga Said, Langkat(1890) oleh Royal Shell -Belanda
Pemberian Hak KonsesipadaStanvac (1925) danCaltex (1936)
UU No. 44 Tahun 1960 tentangPertambangan Minyak dan GasBumi : Perusahaan asing tidaksebagai pemegang konsesi, tapisebagai kontraktor
Penandatanganan Kontrak Karyadengan Pan American Oil tahun1963.
Dalam pelaksanaan, pemerintahmasih memliki keterbatasan
pengawasan dan tidak jelasnyaaspek kepemilikan
Berbagi hasil penjualan, bukanproduksi.
Pemerintah inginberbagi hasil produksi
PenandatangananPSCpertama di dunia, dengaIndependece IndonesianAmerican Oil Company(IIAPCO) tahun 1966
UU No. 8 /1971 tentang
Pertamina sebagai dasarhukum PSC
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
7/37PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Karakter Bisnis Migas
Karakter Bisnis Migas
HighInvestment
High RiskHigh
Technology
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
8/37PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Mengapa PSC?
Penguasaan Sumber Daya Alam tetap berada
pada Pemerintah
Pemerintah tidak akan menanggung resikoatas tidak ditemukannya cadangan migas
Pemerintah tidak menghadapi kesulitan dana, dana selalu tersediakapan saja dan dalam jumlah yang tidak terbatas karena operasiperminyakan menghadapi banyak ketidakpastian
Mengapa PSC ?
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
9/37
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
10/37PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Ketentuan Umum PSC (1)
PSC merupakan Kontrak Bisnisantara Pemerintah(yang diwakili oleh SKK
Migas) dengan KontraktorKontrak Kerjasama;
Manajemen berada ditangan SKK Migas sesuai dengan UU no. 22/2001, PP
no. 42/2002, dll;
Masa ekplorasi 6 tahun(sejak ditandatanganinya kontrak)boleh
diperpanjang untuk masa 4 tahun. Bila hingga masa 10 tahun ternyata
tidak diperoleh cadangan/cadangan yang ditemukan tidak ekonomis untuk
diproduksi maka secara otomatis. Resiko finansial ditanggung kontraktor;
Kontraktor mempunyai kemampuan dalam penyediaan dana (financialability), teknologi/keahlian serta menanggung resiko finansial;
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
11/37PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Ketentuan Umum PSC (2)
Kontraktor berkewajiban menyerahkan migas bagiannya untuk kebutuhandalam negeri (DMO);
Kontraktor mempunyai kewajiban untuk membiayai operasi usaha yang
dapat direcover dari hasil produksinya (Cost Recovery).
Pembagian berdasarkan produksi minyak dan gas bumi.
Perhitungan pembagian hak Pemerintah dan Kontraktor berdasarkan tahun
kalender.
Pemeriksaan/Audit pembukuan dilaksanakan oleh SKK Migas dan Auditor
Pemerintah.
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
12/37PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Incld.
Exploration
Period
Operation/Activities Flow
Exploration (6+4) Exploitation/Production (30)
WP&B AFE FQR WP&B AFE FQRCurrent
Audit
Ops.
Control
Siesmic
G&G
Study Expl.
Drilling Production
& Operation
Support
Business &
Commercial Analysis
Well Dev.
Exploration
Audit
Tender
WKP Spending Commitment
Financial Flow
POD
Proses Bisnis Industri Migas
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
13/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIALSumber : http://www.skkmigas.go.id/12-kkks-asing-rugi-rp19-triliun-cari-cadangan-migas-di-laut-dalam-indonesia
Kegagalan Penemuan Cadangan Ekonomis 2009-2013
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
14/37
PRIVATE AND CONFIDENTIAL
2013SKKMIGASAllrightsreserved
AGENDA 2. Skema PSC
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
15/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Alur Perhitungan PSC Indonesia
288
2,861
ContractorEntitlement
361
SKK MigasEntitlement
2,139
DMO
KK Migas Share Contractor Share721
Cost Recovery
2,500
1,500Equity to be Split
1,000
5,000
Total Lifting
FTP - 20%
712
1,779
Assumes
Lifting 5.000 bbl, ICP $40/bbl
Operating costs $100.000, DMO new oil
2.500
288
433-361
2.861
Contractor Entitlement :
1. Rec. Operating Cost - $100.000/$40
2. FTP Share 28.8462%x1.000 bbl
3. Equity Share -28.8462%x1.500 bbl4. (-)DMO -28.8462%x25%x5.000 bbl
5. Total Entitlement
SKK Migas Entitlement :
1. FTP Share 71.1538%x1.000 bbl
2. Equity Share -71.1538%x1.500 bbl
3. (-)DMO -28.8462%x25%x5.000 bbl
4. Total Entitlement
712
1.067
361
2.139
Asumsi:
Split 85/15
Tax 48%
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
16/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
FTP (First Tranche Petroleum)
288
2,861
ContractorEntitlement
361
SKK MigasEntitlement
2,139
DMO
SKK Migas Share Contractor Share721
Cost Recovery
2,500
1,500Equity to be Split
1,000
5,000
Total Lifting
FTP - 20%
712
1,779
FTP adalah pemotonganpertama dari revenue untuk
menjamin adanya bagian
SKK Migas.
Besarnya antara 15% - 20%
dan dibagi antara SKKMigas dan Kontraktor.
PSC terbaru menggunakan
split 10% tetapi seluruhnya
untuk Pemerintah
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
17/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Domestic Market Obligation (DMO)
After commercial production commence, full fill its
obligation toward supply of domestic market in
Indonesia. Contractor agrees to sell and deliver to GOI a
portion of the share of the petroleum to which
contractor is entitled pursuant clauses 6.1.3, 6.2.2 and
6.3.1
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
18/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Domest ic Market Obl igat ion (DMO)
288
2,861
ContractorEntitlement
361
SKK MigasEntitlement
2,139
DMO
KK Migas Share Contractor Share721
Cost Recovery
2,500
1,500Equity to be Split
1,000
5,000Total Lifting
FTP - 20%
712
1,779
Domestic Market Obligation adalah
kewajiban kontraktor untuk
menyerahkan 25% dari
entitlementnya untuk kebutuhan
kilang dalam negeri.
Pemerintah melalui Kemenkeumembayar kontraktor atas
penyerahan tersebut.
Untuk 60 bulan atau 5 tahun pertama
(new field) pemerintah akanmembayar senilai ICP dan
selanjutnya harga 20% ICP, 15% ICP
atau 20 Cent (sesuai PSC).
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
19/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Cost Recovery
Dalam PSC tidak ada istilahcostrecovery, yang ada adalahoperatingcost.
Semua pengeluaran dan kewajibanyang terjadi untuk melaksanakanoperasi perminyakan (PSC Section I,paragraph 1.2.16 dan Exhibit C).
288
2,861
ContractorEntitlement
361
SKK MigasEntitlement
2,139
DMO
KK Migas Share Contractor Share721
Cost Recovery
2,500
1,500Equity to be Split
1,000
5,000
Total Lifting
FTP - 20%
712
1,779
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
20/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Cost Recovery
Pengembalian biaya operasi (Operating Cost) yang dikeluarkan olehKontraktor KKS dari hasil produksi migas, setelah kontraktor berhasilmenemukan migas secara komersil
Diberikan dalam bentuk inkind
Operating Cost adalah semua pengeluaran untuk membiayai kegiatan operasihulu migas meliputi kegiatan eksplorasi, pengembangan lapangan, kegiatanproduksi, dan biaya administrasi. Jadi, Operating Cost, ada biaya investasi(eksplorasi dan pengembangan lapangan) dan ada biaya operasi danadministrasi (termasuk untuk membiayai kegiatan penunjang)
Cost Recovery merupakan konsekuensi dari prinsip Pemerintah tidak bolehmengeluarkan investasi dan menanggung resiko (UU No. 22 Tahuan 2001
Pasal 6 (2)c, PP No. 35 Pasal 26 (1), (2), dan PSC)
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
21/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Cost Recovery
Mulai tahun produksi komersial, biaya operasi yang di-recover pada suatutahun terdiri dari: (PSC, Exhibit C,paragraphII-2.1.)
1. Current year Non-Capital : biaya yang dapat diperoleh kembali darihasil produksi tahun berjalan
2. Current years depreciation for Capital Costs :penyusutan biaya capitalyang dapat diperoleh kembali dari hasil produksi tahun berjalan
3. Unrecovered Cost Prior Periode: Biaya operasi tahun yang belumterkembalikan sebagai cost recovery (jika ada)
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
22/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Cost Recovery
Cost Recovery
Exploration Stage (6+4)
Exploitation/Production Stage (the rest of period until 30 year)
Seismic, G&G cost, Explorati on
Dr il li ng Cost, Support Cost
Exploi tation/Production: Devlp.
Dri ll ing, Production & Operation
Cost, Equipment, Suppor t Cost ,I nterest Cost Recovery
Current Year Expl orati on Cost:
Seismic, G&G cost, Explorati on
Dr il li ng Cost, Support Cost
Curr ent Year - Non
Capital
Capital
Depreciation
I nvestment Credit
(Recoverable/Taxable)
Unrecovered Cost
Prior Per iod
d f k
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
23/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Identifikasi Biaya
0-10 th
Tahap Eksplorasi
0-5 th
Tahap Dev
Sisa Tahun Kontrak
Tahap Production
Geological & Geophysical
Seismics
Exploratory Drilling
Other Facilities
Overhead
Development Drilling
Reservoir Studies
Production Facilities
Other Facilities
Overhead
Production Operations
Production Supports
Overhead
Exploration
Development
EXPLORATION EXPLOITATION
0 30 Th
Dev
First Drop
k i b li C R
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
24/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Mekanisme PengembalianCost Recovery
Besaran pengembalian biaya operasi mengacu kepada pada estimasi dalamWP&B yang direaliasasikan dalam tahun berjalan
Kontraktor mendapat migas bagiannya berdasarkan persentase hak kontraktorsementara (provisional entitlement) yang dihitung dari produksi yang dijual(lifting) untuk periode tertentu dan dibukukan secara periodik oleh kontraktor
Di dalam migas bagian kontraktor terdapat unsur pengembalian biaya operasi
Persentase hak kontraktor sementara (provisional entitlement) di-updatedengan munculnya figur aktual setiap bulannya.
Hak Pemerintah dan hak Kontraktor yang aktual diketahui pada akhir tahun,dan perbedaan antara hak aktual dan hak sementara diselesaikan oleh para
pihak
K P b li C R
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
25/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Kapan PengembalianCost Recovery
Setelah adanya produksi komersial
Setelah SKK Migas mengambil lebih dahulu persentase tertentu dari hasilproduksi (FTP)
Sebelum hasil produksi dibagi antara SKK Migas dan Kontraktor sesuai splityang ditetapkan di dalam KKS
Kontraktor memperoleh kembali biaya operasi TIDAK dalam bentuk tunaitetapi dalam bentuk inkind
Jumlah inkind yang diperoleh oleh Kontraktor dihitung berdasarkan besaranbiaya operasi yang akan dikembalikan pada tahun tersebut, dibagi harga minyak(berpatokan pada ICP) atau harga jual rata-rata gas
R k
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
26/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Rangkuman
Kontraktor (KKKS) SKK Migas
1. FTP 28.8462%
2. Operating Cost 100%
3. DMO Fee
4. Kontraktor Share 28.8462%
Pengurang :
1. DMO at ICP
2. Corporate & Dividen Tax
1. FTP 71.1538%
2. Govt Share 71.1538%
3. DMO at ICP
4. Corporate & Dividend Tax
Pengurang :
1. Operating Cost 100%
2. DMO Fee
Asumsi:Split 85/15
Tax 48%
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
27/37
PRIVATE AND CONFIDENTIAL
2013SKKMIGAS
Allrightsreserved
AGENDA 3. Mekanisme Perhitungan Lifting & Pelaporan
Hulu Hilir Migas
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
28/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
PEMBORAN SEISMIK
DINAMIT
UNIT ALAT PEREKAMAN
LAPISAN BATUAN
MINYAKBUMI
PEMBORAN SEISMIK
DINAMIT
UNIT ALAT PEREKAMAN
LAPISAN BATUAN
MINYAKBUMI
Produksi
Lifting lewat pipa
Lifting dg Kapal Tujuan Export
Eksplorasi
Refinery
Lifting dg Kapal Tujuan Domestik
Ekploitasi
Lifting
Lifting
Hulu Hilir Migas
Perhitungan Lifting
http://images.google.com/imgres?imgurl=www.mncgnw.com/photos/coastal%2520tanker.jpg&imgrefurl=http://www.mncgnw.com/photos/coastaltanker.htm&h=480&w=640&prev=/images%3Fq%3Dtanker%26svnum%3D10%26hl%3Den%26lr%3D%26ie%3DUTF-8%26oe%3DUTF-8%26sa%3DNhttp://images.google.com/imgres?imgurl=www.mncgnw.com/photos/coastal%2520tanker.jpg&imgrefurl=http://www.mncgnw.com/photos/coastaltanker.htm&h=480&w=640&prev=/images%3Fq%3Dtanker%26svnum%3D10%26hl%3Den%26lr%3D%26ie%3DUTF-8%26oe%3DUTF-8%26sa%3DNhttp://images.google.com/imgres?imgurl=www.mncgnw.com/photos/coastal%2520tanker.jpg&imgrefurl=http://www.mncgnw.com/photos/coastaltanker.htm&h=480&w=640&prev=/images%3Fq%3Dtanker%26svnum%3D10%26hl%3Den%26lr%3D%26ie%3DUTF-8%26oe%3DUTF-8%26sa%3DNhttp://images.google.com/imgres?imgurl=www.mncgnw.com/photos/coastal%2520tanker.jpg&imgrefurl=http://www.mncgnw.com/photos/coastaltanker.htm&h=480&w=640&prev=/images%3Fq%3Dtanker%26svnum%3D10%26hl%3Den%26lr%3D%26ie%3DUTF-8%26oe%3DUTF-8%26sa%3DNhttp://images.google.com/imgres?imgurl=www.mncgnw.com/photos/coastal%2520tanker.jpg&imgrefurl=http://www.mncgnw.com/photos/coastaltanker.htm&h=480&w=640&prev=/images%3Fq%3Dtanker%26svnum%3D10%26hl%3Den%26lr%3D%26ie%3DUTF-8%26oe%3DUTF-8%26sa%3DNhttp://images.google.com/imgres?imgurl=www.algor.com/news_pub/cust_app/enterg/images/tank.jpg&imgrefurl=http://www.algor.com/news_pub/cust_app/enterg/entergy.asp&h=252&w=378&prev=/images%3Fq%3DSTORAGE%2BTANK%26start%3D20%26svnum%3D10%26hl%3Den%26lr%3D%26ie%3DUTF-8%26oe%3DUTF-8%26sa%3DN -
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
29/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Perhitungan Lifting
Dasar perhitungan lifting adalah :
Total Lifting = Price x Quantity Price
Menggunakan Indonesia Crude Oil Price yang dikeluarkan setiap
bulannya oleh Ditjen Migas dalam mata uang Dollar Amerika.
QuantityTotal produksi yang terjual (lifting) dimana dasar pembagiannya
berdasarkan perhitungan entitlement yang sudah
diperhitungkan didalamnya FTP, DMO, Share Parties, Cost
recovery
Indonesia Crude Price
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
30/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Indonesia Crude Price
Dokumen Lifting
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
31/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Dokumen Lifting
Lifting & Entitlement
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
32/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Lifting & Entitlement
ENTITLEMENT
- Hak SKK Migas/Kontraktor atas produksi yang terjual.
- Periode PerhitunganEntitlementper WKP/PSC adalah JanuariDesember, sehingga
Actual Entitlementbaru dapat diketahui setelah lewat akhir tahun.
LIFTING
Realisasi penjualan produksi dilakukan bisa dengan cara:
Joint Lifting: Lifting dilakukan bersama-sama (SKK Migas & Kontraktor) dan hasilpenjualannya dibagi berdasarkan provisional (estimasi) entitlement masing-masing.
Individual Lifting: masing-masing pihak melakukan lifting berdasarkan provisional(estimasi) entitlement masing-masing.
D P i i l E titl t
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
33/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Dasar Provisional Entitlement
1. LIFTING : SHIPCORD, QAS & BS.16 WP&B
2. HARGA : ICP
3. COST RECOVERABLES : CURRENT OUTLOOK (QAS) / WP&B
4. ENTITLEMENT PERCENTAGES : PSC
PSC Section VII.5:
During any given Calendar Year, the handling of production and the proceed thereof shall be
provisionally dealt with on the basis of the relevant Work Program and Budget of Operating
Costs based upon estimates of quantities of petroleum to be produced, of internal
consumption in Indonesia, of marketing possibilities, of prices and other sale conditions as
well as of any other relevant factor.
Parameter Utama dalam Perhitungan:
Provisional Entitlement
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
34/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Provisional Entitlement
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
35/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
Jan-06 Feb-06Estimate
Mar-Dec
Estimate
Jan-Dec
Price (WAP) US$/Bbl 52.0 52.0 52.0 52.0
Lifting mbbl 540,000 520,000 4,990,000 6,050,000
Cost Recovery MUS$ 5,260 5,260 52,600 63,120
FINANCIAL DATA
KKKS SKK Migas
Tax Rate 48% 28.8462% 71.1538%
Equity Split FTP 1,210 20.0000% 5.7692% 14.2308%SKK Migas 85% DMO 436 7.2115% -7.2115% 7.2115%
Contractor 15% Cost Recovery 1,214 20.0636% 20.0636%
FTP 20% Equity 3,190 52.7249% 15.2091% 44.7273%
DMO 25% Total Lifting 6,050 100.0000% 33.8304% 66.1696%
MONITORING OVER/UNDER LIFTING
DESCRIPTION Act. Lifting O/U Lifting% BBL BBL BBL
Current Month
SKK Migas 66.1696% 701,398 540,000 (161,398)
Contractor 33.8304% 358,602 520,000 161,398
Prov. Ent
% AllocationTotal Bbl
PROV. ENTITLEMENT CULCULATION
Pelaporan & Penagihan Lifting Migas
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
36/37
PRIVATE AND CONFIDENTIALPRIVATE AND CONFIDENTIAL
INPUT
- Tagihan KKKS
- Lifting Document
- Commercial Documents- Dokumen Shipcoord.
Pelaporan & Penagihan Lifting Migas
PROSES
- Evaluasi
- Verifikasi
- Monitoring
1. OUTPUT
- Laporan Lifting Ekspor Oil (A01)- Laporan Lifting Domestik Oil (A02)
- Laporan Ekspor Gas (A03)
- Laporan Lifting Domestik Gas (A04)
- Laporan DMO (A05)
2. OUTPUT
Surat Tagihan kepada:- Pertamina- Penjual yang ditunjuk- KKKSdengan perintah pembayaran ke
rekening pemerintah600.000411980- Instruction- Prov Entt.
- TPAA
SATUAN KERJA KHUSUS
PELAKSANA KEGIATAN USAHA HULU MINYAK DAN GAS BUMI
-
7/25/2019 Mekanisme Penghitungan Anggaran Dan Realisasi Lifting Dalam PSC - Edit 1 Solo
37/37
PRIVATE AND CONFIDENTIAL
PELAKSANA KEGIATAN USAHA HULU MINYAK DAN GAS BUMI(SKK Migas)
KANTOR PUSAT
Wisma Mulia Lantai LG, 21, 22, 23, 27, 28, 29, 30, 31, 33, 35, 36, 37, 38, 39, 40
Jalan Jenderal Gatot Subroto No. 42, Jakarta 12710, INDONESIA
PO BOX 477
Telepon : +62 21 2924 160Faksimile : +62 21 2924 999
top related