DAFTAR ANALISA PEKERJAAN
SNI.DT 91-0012-2007
PEKERJAAN PENUTUP LANTAI DAN DINDING
SNI.DT 91-0012-2007.6.13
Memasang 1 m2 lantai keramik ukuran (60x60) cm
KebutuhanSatuanIndeksHarga satuanHarga satuanJumlah harga bahanJumlah harga upah
BahanLantai keramik 60x60Bh3.100Rp.45,000.00Rp.Rp.139,500.00Rp.
Portland cementkg9.600Rp.1,100.00Rp.Rp.10,560.00Rp.
Pasir pasangm30.045Rp.90,000.00Rp.Rp.4,050.00Rp.
Semen warnakg1.500Rp.3,075.00Rp.Rp.4,612.50Rp.
TenagaPekerjaOh0.240Rp.Rp.Rp.Rp.0.00
Tukang BatuOh0.120Rp.Rp.72,000.00Rp.Rp.8,640.00
Kepala TukangOh0.012Rp.Rp.80,000.00Rp.Rp.960.00
MandorOh0.012Rp.Rp.72,000.00Rp.Rp.864.00
158,722.5010,464.00
Jumlah harga =Rp.169,186.50
Pembulatan=Rp.169,190.00
SNI.DT 91-0012-2007.6.34
Memasang 1 m2 lantai keramik ukuran (40x40) cm
KebutuhanSatuanIndeksHarga satuanHarga satuanJumlah harga bahanJumlah harga upah
BahanLantai keramikBh6.500Rp.8,833.33Rp.Rp.57,416.65Rp.
Portland cementkg8.190Rp.1,100.00Rp.Rp.9,009.00Rp.
Pasir pasangm30.045Rp.90,000.00Rp.Rp.4,050.00Rp.
Semen warnakg1.620Rp.3,075.00Rp.Rp.4,981.50Rp.
TenagaPekerjaOh0.700Rp.Rp.Rp.Rp.0.00
Tukang KayuOh0.350Rp.Rp.72,000.00Rp.Rp.25,200.00
Kepala TukangOh0.035Rp.Rp.80,000.00Rp.Rp.2,800.00
MandorOh0.035Rp.Rp.72,000.00Rp.Rp.2,520.00
75,457.1530,520.00
Jumlah harga =Rp.105,977.15
Pembulatan=Rp.105,980.00
SNI.DT 91-0012-2007.6.35
Memasang 1 m2 lantai keramik ukuran (30x30) cm
KebutuhanSatuanIndeksHarga satuanHarga satuanJumlah harga bahanJumlah harga upah
BahanLantai keramikBh11.500Rp.4,909.09Rp.Rp.56,454.54Rp.
Portland cementkg10.000Rp.1,100.00Rp.Rp.11,000.00Rp.
Pasir pasangm30.045Rp.90,000.00Rp.Rp.4,050.00Rp.
Semen warnakg1.500Rp.3,075.00Rp.Rp.4,612.50Rp.
TenagaPekerjaOh0.700Rp.Rp.50,000.00Rp.Rp.35,000.00
Tukang KayuOh0.350Rp.Rp.72,000.00Rp.Rp.25,200.00
Kepala TukangOh0.035Rp.Rp.80,000.00Rp.Rp.2,800.00
MandorOh0.035Rp.Rp.72,000.00Rp.Rp.2,520.00
76,117.0465,520.00
Jumlah harga =Rp.141,637.04
Pembulatan=Rp.141,640.00
SNI.DT 91-0012-2007.6.36
Memasang 1 m2 lantai keramik ukuran (20x20) cm
KebutuhanSatuanIndeksHarga satuanHarga satuanJumlah harga bahanJumlah harga upah
BahanLantai keramikBh25.000Rp.1,960.00Rp.Rp.49,000.00Rp.
Portland cementkg10.400Rp.1,100.00Rp.Rp.11,440.00Rp.
Pasir pasangm30.045Rp.90,000.00Rp.Rp.4,050.00Rp.
Semen warnakg1.620Rp.3,075.00Rp.Rp.4,981.50Rp.
TenagaPekerjaOh0.700Rp.Rp.50,000.00Rp.Rp.35,000.00
Tukang KayuOh0.350Rp.Rp.72,000.00Rp.Rp.25,200.00
Kepala TukangOh0.035Rp.Rp.80,000.00Rp.Rp.2,800.00
MandorOh0.035Rp.Rp.72,000.00Rp.Rp.2,520.00
69,471.5065,520.00
Jumlah harga =Rp.134,991.50
Pembulatan=Rp.134,990.00
SNI.DT 91-0012-2007.6.36.1
Memasang 1 m2 dinding keramik ukuran (20x25) cm
KebutuhanSatuanIndeksHarga satuanHarga satuanJumlah harga bahanJumlah harga upah
BahanLantai keramikBh20.000Rp.2,250.00Rp.Rp.45,000.00Rp.
Portland cementkg10.400Rp.1,100.00Rp.Rp.11,440.00Rp.
Pasir pasangm30.045Rp.90,000.00Rp.Rp.4,050.00Rp.
Semen warnakg1.620Rp.3,075.00Rp.Rp.4,981.50Rp.
TenagaPekerjaOh0.700Rp.Rp.50,000.00Rp.Rp.35,000.00
Tukang KayuOh0.350Rp.Rp.72,000.00Rp.Rp.25,200.00
Kepala TukangOh0.035Rp.Rp.80,000.00Rp.Rp.2,800.00
MandorOh0.035Rp.Rp.72,000.00Rp.Rp.2,520.00
65,471.5065,520.00
Jumlah harga =Rp.130,991.50
Pembulatan=Rp.130,990.00
SNI.DT 91-0012-2007.6.44
Memasang 1 m2 lantai karpet
KebutuhanSatuanIndeksHarga satuanHarga satuanJumlah harga bahanJumlah harga upah
BahanKarpetm21.050Rp.36,000.00Rp.Rp.37,800.00Rp.
Lemkg0.350Rp.45,000.00Rp.Rp.15,750.00Rp.
TenagaPekerjaOh0.170Rp.Rp.50,000.00Rp.Rp.8,500.00
Tukang KayuOh0.170Rp.Rp.72,000.00Rp.Rp.12,240.00
Kepala TukangOh0.017Rp.Rp.80,000.00Rp.Rp.1,360.00
MandorOh0.009Rp.Rp.72,000.00Rp.Rp.648.00
53,550.0022,748.00
Jumlah harga =Rp.76,298.00
Pembulatan=Rp.76,300.00
SNI.DT 91-0012-2007.6.46
Memasang 1 m2 lantai parquet
KebutuhanSatuanIndeksHarga satuanHarga satuanJumlah harga bahanJumlah harga upah
BahanParquetm21.050Rp.270,000.00Rp.Rp.283,500.00Rp.
Lemkg0.600Rp.45,000.00Rp.Rp.27,000.00Rp.
TenagaPekerjaOh0.700Rp.Rp.50,000.00Rp.Rp.35,000.00
Tukang KayuOh0.350Rp.Rp.72,000.00Rp.Rp.25,200.00
Kepala TukangOh0.035Rp.Rp.80,000.00Rp.Rp.2,800.00
MandorOh0.035Rp.Rp.72,000.00Rp.Rp.2,520.00
310,500.0065,520.00
Jumlah harga =Rp.376,020.00
Pembulatan=Rp.376,020.00
SNI.DT 91-0012-2007.6.47
Memasang 1 m2 lantai kayu (gym floor)
KebutuhanSatuanIndeksHarga satuanHarga satuanJumlah harga bahanJumlah harga upah
BahanGymfloorm21.050Rp.180,000.00Rp.Rp.189,000.00Rp.
Lemkg0.600Rp.45,000.00Rp.Rp.27,000.00Rp.
TenagaPekerjaOh0.700Rp.Rp.50,000.00Rp.Rp.35,000.00
Tukang KayuOh0.350Rp.Rp.72,000.00Rp.Rp.25,200.00
Kepala TukangOh0.035Rp.Rp.80,000.00Rp.Rp.2,800.00
MandorOh0.035Rp.Rp.72,000.00Rp.Rp.2,520.00
216,000.0065,520.00
Jumlah harga =Rp.281,520.00
Pembulatan=Rp.281,520.00
SNI.DT 91-0012-2007.6.57
Memasang 1 m2 dinding batu paras
KebutuhanSatuanIndeksHarga satuanHarga satuanJumlah harga bahanJumlah harga upah
BahanBatu parasm21.100Rp.180,000.00Rp.Rp.198,000.00Rp.
Potrland cementkg11.750Rp.1,100.00Rp.Rp.12,925.00Rp.
Pasir pasangm30.035Rp.90,000.00Rp.Rp.3,150.00Rp.
TenagaPekerjaOh0.700Rp.Rp.50,000.00Rp.Rp.35,000.00
Tukang batuOh0.350Rp.Rp.72,000.00Rp.Rp.25,200.00
Kepala TukangOh0.035Rp.Rp.80,000.00Rp.Rp.2,800.00
MandorOh0.035Rp.Rp.72,000.00Rp.Rp.2,520.00
214,075.0065,520.00
Jumlah harga =Rp.279,595.00
Pembulatan=Rp.279,600.00
SNI.DT 91-0012-2007.6.58
Memasang 1 m2 dinding batu tempel hitam
KebutuhanSatuanIndeksHarga satuanHarga satuanJumlah harga bahanJumlah harga upah
BahanBatu tempel hitamm21.100Rp.135,000.00Rp.Rp.148,500.00Rp.
Potrland cementkg11.750Rp.1,100.00Rp.Rp.12,925.00Rp.
Pasir pasangm30.035Rp.90,000.00Rp.Rp.3,150.00Rp.
TenagaPekerjaOh0.700Rp.Rp.50,000.00Rp.Rp.35,000.00
Tukang batuOh0.350Rp.Rp.72,000.00Rp.Rp.25,200.00
Kepala TukangOh0.035Rp.Rp.80,000.00Rp.Rp.2,800.00
MandorOh0.035Rp.Rp.72,000.00Rp.Rp.2,520.00
164,575.0065,520.00
Jumlah harga =Rp.230,095.00
Pembulatan=Rp.230,100.00
SNI.DT 91-0012-2007.6.60
Memasang 1 m2 wall paper
KebutuhanSatuanIndeksHarga satuanHarga satuanJumlah harga bahanJumlah harga upah
BahanWallpaperm22.200Rp.94,000.00Rp.Rp.206,800.00Rp.
Lemkg0.250Rp.45,000.00Rp.Rp.11,250.00Rp.
TenagaPekerjaOh0.350Rp.Rp.50,000.00Rp.Rp.17,500.00
TukangOh0.175Rp.Rp.72,000.00Rp.Rp.12,600.00
Kepala TukangOh0.017Rp.Rp.80,000.00Rp.Rp.1,360.00
MandorOh0.002Rp.Rp.72,000.00Rp.Rp.144.00
218,050.0031,604.00
Jumlah harga =Rp.249,654.00
Pembulatan=Rp.249,650.00
SNI.DT 91-0012-2007.6.61
Memasang 1 m2 floor hardener
KebutuhanSatuanIndeksHarga satuanHarga satuanJumlah harga bahanJumlah harga upah
BahanFloor Hardenerkg5.000Rp.3,500.00Rp.Rp.17,500.00Rp.
TenagaPekerjaOh0.120Rp.Rp.50,000.00Rp.Rp.6,000.00
TukangOh0.120Rp.Rp.72,000.00Rp.Rp.8,640.00
Kepala TukangOh0.012Rp.Rp.80,000.00Rp.Rp.960.00
MandorOh0.006Rp.Rp.72,000.00Rp.Rp.432.00
17,500.0016,032.00
Jumlah harga =Rp.33,532.00
Pembulatan=Rp.33,530.00
SNI.DT 91-0012-2007.6.7
Memasang 1 m2 conblok #6 cm
KebutuhanSatuanIndeksHarga satuanHarga satuanJumlah harga bahanJumlah harga upah
BahanConblok #6cmbh44.000Rp.1,800.00Rp.Rp.79,200.00Rp.
Pasir urugm30.055Rp.73,000.00Rp.Rp.4,015.00Rp.
TenagaPekerjaOh0.300Rp.Rp.50,000.00Rp.Rp.15,000.00
TukangOh0.200Rp.Rp.72,000.00Rp.Rp.14,400.00
Kepala TukangOh0.010Rp.Rp.80,000.00Rp.Rp.800.00
MandorOh0.010Rp.Rp.72,000.00Rp.Rp.720.00
83,215.0030,920.00
Jumlah harga =Rp.114,135.00
Pembulatan=Rp.114,140.00