10_4 lampiran (kp)

5
ID Task Name 1 Pre Construction 2 Perizinan 3 Engi neer ing dan Admistasi 4 Pembebasan Lahan 5 Sertifikat Tanah 6 7 Pekerjaan Sipil 8 Mobil isasi dan Demobili sasi 9 Pembersihan Lahan 10 Konstruksi 11 Pek jalan akses ke PLTM Cikandang 12 Pek jal ur waterway dan j alan i nspek si 13 Pek divertion channel 14 Pek intake dan bendung 15 Pek headpond 16 Pek Penstock 17 Pek Powerhouse 18 Pek Tailrace 19 Pek j alan akses ke powerhouse 20 21 Pekerjaan Baja 22 Pint u Penguras di bendung 23 Pi nt u pengur as di sandtr ap 24 Ki si -k isi pada pintu pengambil an 25 Pintu pengambilan 26 Ki si ki si pada intake pi pa pesat 27 Pipa pesat 28 29 Peralatan pembangkitan 30 Turbin generator  31 32 Jalur transmisi 20 kv 33 34 Trafo 20 kv 35 36 Testing dan commisioning January February March April May June July August September October November December  Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Progress Deadline TI ME SCHEDULE PLTM C K ND NG  PLTM Cikandang Lampiran 4 : Time Schedule PLTM Cikandang

Upload: ahmad-sayuti

Post on 18-Feb-2018

226 views

Category:

Documents


0 download

TRANSCRIPT

7/23/2019 10_4 LAMPIRAN (KP)

http://slidepdf.com/reader/full/104-lampiran-kp 1/4

ID Task Name1 Pre Construction

2 Perizinan

3 Eng ineering dan Admistasi

4 Pembebasan Lahan

5 Sertifikat Tanah

6

7 Pekerjaan Sipil

8 Mobi li sasi dan Demobil isasi

9 Pembersihan Lahan

10 Konstruksi

11 Pek jalan akses ke PLTM Cikandang

12 Pek ja lur waterway dan jalan inspeksi

13 Pek divertion channel

14 Pek intake dan bendung

15 Pek headpond

16 Pek Penstock

17 Pek Powerhouse

18 Pek Tailrace

19 Pek jalan akses ke powerhouse

20

21 Pekerjaan Baja

22 Pin tu Penguras di bendung

23 Pintu penguras di sandt rap

24 Kis i-kisi pada pintu pengambi lan

25 Pintu pengambilan

26 Kis i k is i pada intake pipa pesat

27 Pipa pesat

28

29 Peralatan pembangkitan

30 Turbin generator  

31

32 Jalur transmisi 20 kv

33

34 Trafo 20 kv

35

36 Testing dan commisioning

January February March April May June July August September October November December  

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Progress

Deadline

TI ME SCHEDULE

PLTM C K ND NG

 PLTM Cikandang

Lampiran 4 : Time Schedule PLTM Cikandang

7/23/2019 10_4 LAMPIRAN (KP)

http://slidepdf.com/reader/full/104-lampiran-kp 2/4

ID Task Name1 Pre Construction

2 Perizinan

3 Eng ineering dan Admistasi

4 Pembebasan Lahan

5 Sertifikat Tanah

6

7 Pekerjaan Sipil

8 Mobi li sasi dan Demobil isasi

9 Pembersihan Lahan

10 Konstruksi

11 Pek jalan akses ke PLTM Cikandang

12 Pek ja lur waterway dan jalan inspeksi

13 Pek divertion channel

14 Pek intake dan bendung

15 Pek headpond

16 Pek Penstock

17 Pek Powerhouse

18 Pek Tailrace

19 Pek jalan akses ke powerhouse

20

21 Pekerjaan Baja

22 Pin tu Penguras di bendung

23 Pintu penguras di sandt rap

24 Kis i-kisi pada pintu pengambi lan

25 Pintu pengambilan

26 Kis i k is i pada intake pipa pesat

27 Pipa pesat

28

29 Peralatan pembangkitan

30 Turbin generator  

31

32 Jalur transmisi 20 kv

33

34 Trafo 20 kv

35

36 Testing dan commisioning

December January February March April May June July August September October November  

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Progress

Deadline

TI ME SCHEDULE

PLTM C K ND NG

 PLTM Cikandang

7/23/2019 10_4 LAMPIRAN (KP)

http://slidepdf.com/reader/full/104-lampiran-kp 3/4

ID Task Name1 Pre Construction

2 Perizinan

3 Eng ineering dan Admistasi

4 Pembebasan Lahan

5 Sertifikat Tanah

6

7 Pekerjaan Sipil

8 Mobil isasi dan Demobil isasi

9 Pembersihan Lahan

10 Konstruksi

11 Pek jalan akses ke PLTM Cikandang

12 Pek jalur wa terway dan jalan inspeksi

13 Pek divertion channel

14 Pek intake dan bendung

15 Pek headpond

16 Pek Penstock

17 Pek Powerhouse

18 Pek Tailrace

19 Pek jalan akses ke powerhouse

20

21 Pekerjaan Baja

22 Pin tu Penguras di bendung

23 Pintu penguras di sandt rap

24 Kisi-kisi pada pintu pengambilan

25 Pintu pengambilan

26 Kis i k isi pada intake pipa pesat

27 Pipa pesat

28

29 Peralatan pembangkitan

30 Turbin generator  

31

32 Jalur transmisi 20 kv

33

34 Trafo 20 kv

35

36 Testing dan commisioning

November December January February March April May June July August September October  

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Progress

Deadline

TI ME SCHEDULE

PLTM C K ND NG

 PLTM Cikandang

7/23/2019 10_4 LAMPIRAN (KP)

http://slidepdf.com/reader/full/104-lampiran-kp 4/4

ID Task Name1 Pre Construction

2 Perizinan

3 Engineering dan Admistasi

4 Pembebasan Lahan

5 Sertifikat Tanah

6

7 Pekerjaan Sipil

8 Mobil isasi dan Demobi lisasi

9 Pembersihan Lahan

10 Konstruksi

11 Pek jalan akses ke PLTM Cikandang

12 Pek jalu r waterway dan ja lan inspeks i

13 Pek divertion channel

14 Pek intake dan bendung

15 Pek headpond

16 Pek Penstock

17 Pek Powerhouse

18 Pek Tailrace

19 Pek jalan akses ke powerhouse

20

21 Pekerjaan Baja

22 Pintu Penguras di bendung

23 Pintu penguras di sandtrap

24 Kisi-kisi pada pintu pengambilan

25 Pintu pengambilan

26 Kis i k is i pada intake pipa pesat

27 Pipa pesat

28

29 Peralatan pembangkitan

30 Turbin generator  

31

32 Jalur transmisi 20 kv

33

34 Trafo 20 kv

35

36 Testing dan commisioning

October November December January February March April May June July August September  

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Progress

Deadline

TI ME SCHEDULE

PLTM C K ND NG

 PLTM Cikandang