    ID Task Name Duration Start Finish

    1 PT. NIPPON INDOSARI CORPINDO, Tbk - WWTP PROJECT 1 20 d ay s 0 7/ 09 /1 5 0 4/ 01 /1 6

    2 Preparation 13 days 07/09/15 19/09/15

    3 Pemagaran Area Kerja 3 days 07/09/15 09/09/15

    4 Pembuatan Kantor Lapangan 3 days 08/09/15 10/09/15

    5 Mobilisasi Alat Ringan 2 days 10/09/15 11/09/15

    6 Pengukuran 2 days 11/09/15 12/09/15

    7 Bouwplank 2 days 13/09/15 14/09/15

    8 Clearing Lokasi Kerja 7 days 13/09/15 19/09/15

    9 Pembongkaran Shelter Baja 7 days 13/09/15 19/09/15

    10 Pekerjaan Tanah 43 days 16/09/15 28/10/15

    11 Pembongkaran Lantai Beton 10 days 16/09/15 25/09/15

    12 Penggalian Tanah 7 days 26/09/15 02/10/15

    13 Pembuangan Tanah 7 days 24/09/15 04/10/15

    14 Pemasangan Retaining Wall 6 days 03/10/15 08/10/15

    15 Dewatering 20 days 09/10/15 28/10/15

    16 Pekerjaan Struktur Beton dan Pondasi 58 days 09/10/15 05/12/15

    17 Pembuatan Pondasi 7 days 09/10/15 15/10/15

    18 Pemadatan Tanah 3 days 16/10/15 18/10/15

    19 Pemasangan Pasir Urug t 10cm 1 day 19/10/15 19/10/15

    20 Cor Lantai Kerja T 7.5cm 1 day 20/10/15 20/10/15

    21 Fabrikasi Besi Beton D16 5 days 11/10/15 15/10/15

    22 Fabrikasi Bekisting 7 days 11/10/15 17/10/15

    23 Instal Besi dan Bekisting Plat Lantai 5 days 22/10/15 26/10/15

    24 Pengecoran Lantai Bak 1 day 27/10/15 27/10/15

    25 Instal Besi dan Bekisting Dinding Bak 3 days 02/11/15 04/11/15

    26 Instal Besi Sloof Dinding Pemisah 2 days 02/11/15 03/11/15

    27 Instal Bekisting Sloof Dinding Pemisah 1 day 04/11/15 04/11/15

    28 Pengecoran Dinding dan Sloof 3 days 06/11/15 08/11/15

    29 Pasangan Bata Dinding Pemisah 5 days 13/11/15 17/11/15

    30 Plester Acian Dinding Pemisah 4 days 18/11/15 21/11/15

    31 Pasangan Batu Sludge Hopper 4 days 13/11/15 16/11/15

    32 Pengecoran Lantai Sludge Hopper 1 day 17/11/15 17/11/15

    33 Pekerjaan Waterproofing 6 days 24/11/15 29/11/15

    34 Instal Besi dan Bekisting Plat Penutup 5 days 30/11/15 04/12/15

    35 Pengecoran Plat Lantai Penutup Bak 1 day 05/12/15 05/12/15

    36 Pekerjaan Rumah Blower 2 5 d ay s 1 2/ 11 /1 5 0 6/ 12 /1 5

    37 Penggalian dan Pengecoran Pondasi Tapak 6 days 12/11/15 17/11/15

    38 Pekerjaan Lantai Rumah Blower 2 days 23/11/15 24/11/15

    39 Pembuatan Pondasi Blower 1 day 25/11/15 25/11/15

    40 Pembuatan Rangka Baja 7 days 26/11/15 02/12/15

    41 Pemasangan Atap Spandex 2 days 03/12/15 04/12/15

    42 Fabrikasi dan Pemasangan Pagar dan Pintu 4 days 03/12/15 06/12/15

    43 Pekerjaan Pemipaan Air Blower - WWTP 7 d ays 0 3/ 12 /1 5 0 9/ 12 /1 5

    44 Pembobokan Jalur Pipa Rumah Blower - WWTP 2 days 03/12/15 04/12/15

    4 5 P em as an ga n p ip a U da ra , K im ia , K ab el d ar i R um ah B lo we r- WW TP 3 d ay s 0 5/ 12 /1 5 0 7/ 12 /1 5

    46 Perapihan kembali 2 days 08/12/15 09/12/15

    47 Pekerjaan Pemipaan In-out WWTP 6 d ays 2 3/ 11 /1 5 2 8/ 11 /1 5

    48 Pembobokan/Penggalian Jalur pipa Inlet/Outlet 2 days 23/11/15 24/11/15

    49 Pemasangan Pipa Inlet & Outlet 3 days 25/11/15 27/11/15

    50 Perapihan kembali 1 day 28/11/15 28/11/15

    51 Pekerjaan Pemasangan Peralatan ME 4 0 d ay s 2 6/ 11 /1 5 0 4/ 01 /1 6

    52 Pengadaan dan pemasangan Screen (bar & box screen) 1 day 05/12/15 05/12/15

    53 Pengadaan dan pemasangan Pompa Equalisasi 1 day 05/12/15 05/12/15

    54 Pengadaan dan pemasangan Air Blower 7 days 30/11/15 06/12/15

    55 Pengadaan dan pemasangan Air Diffuser 2 days 06/12/15 07/12/15

    56 Pengadaan dan pemasangan Biomedia 3 days 08/12/15 10/12/15

    5 7 P en ga da an d an p ema sa ng an Ai r L ift & Sc um R em ova l S ys te m 5 d ays 0 1/ 12 /1 5 0 5/ 12 /1 5

    58 Pengadaan dan pemasangan Effluent Pump 1 day 05/12/15 05/12/15

    59 Pengadaan dan pemasangan Chlorine Feeder 1 day 05/12/15 05/12/15

    60 Pengadaan dan pemasangan pH Analyzer & Feeder 2 days 05/12/15 06/12/15

    61 Pengadaan dan pemasangan Interconnecting pipe 10 days 01/12/15 10/12/15

    62 Pengadaan dan pemasangan Water Meter 1 day 11/12/15 11/12/15

    63 Pengadaan dan pemasangan Control Panel & Pengkabelan 16 days 26/11/15 11/12/1564 Test Running Peralatan ME 1 day 12/12/15 12/12/15

    65 Commissioning System WWTP 7 days 13/12/15 19/12/15

    66 Pelatihan Operator 7 days 17/12/15 23/12/15

    67 Test Laboratorium - Inlet/Outlet WWTP 14 days 20/12/15 02/01/16

    68 Pemeriksaan Lapangan 2 days 02/01/16 03/01/16

    69 Serah Terima I 1 day 04/01/16 04/01/16

    S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S 06 Sep '15 13 Sep '15 20 Sep '15 27 Sep '15 04 Oct '15 11 Oct '15 18 Oct '15

    September 2015 October 2015

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Progress

    Deadline

    ENVIRO GREEN - WWTP SARI ROTI PROJECT

    Page 1

    Project: Action Plan Sari Roti- 003Date: 01/09/15

  • 7/23/2019 Working Schedule - WWTP Sari Roti Cibitung Plant

    2/2

    S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W 25 Oct '15 01 Nov '15 08 Nov '15 15 Nov '15 22 Nov '15 29 Nov '15 06 Dec '15 13 Dec '15 20 Dec '15 27 Dec '15 03 Jan '

    November 2015 December 2015

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Progress

    Deadline

    ENVIRO GREEN - WWTP SARI ROTI PROJECT

    Page 2

    Project: Action Plan Sari Roti- 003Date: 01/09/15