TUGAS AKHIR PENERAPAN TOTAL PRODUCTIVE MAINTENANCE (TPM) DALAM PENINGKATAN EFEKTIVITAS KINERJA MESIN GILING (Studi Kasus PT Kebon Agung) Diajukan Sebagai Salah Satu Syarat Untuk Mendapatkan Gelar Sarjana Teknik Pada Jurusan Teknik Industri Universitas Muhammdiyah Malang Disusun Oleh: Nur Wahidah 201510140311103 FAKULTAS TEKNIK JURUSAN TEKNIK INDUSTRI UNIVERSITAS MUHMMADIYAH MALANG 2020

Upload: others

Post on 16-Oct-2021

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TUGAS AKHIR - UMM

TUGAS AKHIR

PENERAPAN TOTAL PRODUCTIVE MAINTENANCE (TPM)

DALAM PENINGKATAN EFEKTIVITAS KINERJA MESIN GILING

(Studi Kasus PT Kebon Agung)

Diajukan Sebagai Salah Satu Syarat Untuk Mendapatkan Gelar Sarjana Teknik Pada

Jurusan Teknik Industri Universitas Muhammdiyah Malang

Disusun Oleh:

Nur Wahidah

201510140311103

FAKULTAS TEKNIK

JURUSAN TEKNIK INDUSTRI

UNIVERSITAS MUHMMADIYAH MALANG

2020

Page 2: TUGAS AKHIR - UMM

1

Page 3: TUGAS AKHIR - UMM

2

Page 4: TUGAS AKHIR - UMM

i

KATA PENGANTAR

Puji serta syukur penulis panjatkan ke hadirat Allah SWT atas segala limpahan

rahmat dan hidayah-Nya, penyusun tugas akhir yang berjudul “PENERAPAN TOTAL

PRODUCTIVE MAINTENANCE (TPM) DALAM PENINGKATAN EFEKTIVITAS

KINERJA MESIN GILING” dapat diselesaikan dengan baik.

Skripsi ini merupakan tugas akhir yang diajukan untuk memenuhi syarat dalam

memperoleh gelar Sarjana Teknik (ST) pada Fakultas Teknik Universitas Muhammadiyah

Malang.

Beberapa kendala yang penyusun hadapi dalam menyelesaikan skripsi ini,

diantaranya terbatas tenaga, sarana dan prasarana. Akan tetapi dari semua itu dapat diatasi

berkat kerjasama dan bantuan dari bantuan dari berbagai pihak.

Penyusunan skripsi ini dapat selesai dengan baik tidak lepas dari dokumen dan

bantuan berbagai pihak, diantaranya yaitu :

1. Bapak Dr. Fauzan, Mpd selaku Rektor Universitas Muhammadiyah Malang.

2. Bapak Dr. Ahmad Mubin, MT selaku Dekan Fakultas Teknik Universitas

Muhammadiyah Malang.

3. Bapak Prof. Ilyas Masudin, ST.,Mlog.SCM.,PhD Selaku Ketua Jurusan Teknik

Industri Universitas Muhmmadiyah Malang.

4. Bapak Prof. Ilyas Masudin, ST.,Mlog.SCM.,PhD selaku dosen pembimbing I yang

telah meluangkan waktu untuk membimbing dan mengarahkan penulis dalam

menyusun skripsi ini.

5. Bapak Rahmad Wisnu Wardana, SPd., M.Eng selaku dosen pembimbing II yang telah

meluangkan waktu untuk membimbing dan mengarahkan penulis dalam menyusun

skripsi ini sampe selesai.

6. Seluruh Bapak dan Ibu Dosen Jurusan Teknik Industri Universitas Muhammadiyah

Malang yang telah member bekal ilmu pengetahuan sehingga penulis dapat

menyelesaikan studi dan menyelesaikan penulisan tugas akhir ini.

7. Bapak Madra’i dan ibu Betsi selaku orang tua penulis serta seluruh keluarga besar

penulis yang sangat banyak memberikan bantuan moril, material, arahan dan selalu

mendoakan keberhasilan dan keselamatan selama menempuh pendidikan.

Page 5: TUGAS AKHIR - UMM

ii

8. Ego Subandira yang banyak meluangkan waktu dan tenaga untuk membimbing dan

memberikan arahan penulis dalam menyelesaikan tugas akhir ini.

9. Rekan-rekan Mahasiswa Teknik Industri yang telah banyak memberikan masukan

kepada penulis baik selama dalam mengikuti perkuliahan maupun dalam penulisan

tugas akhir ini.

10. Kepada semua pihak yang tidak dapat penulis sebutkan satu persatu yang telah banyak

membantu selama pengerjaan tugas akhir ini.

Akhirnya, dengan segala kerendahan hati penulis menyadari masih banyak terdapat

kekurangan-kekurangan, sehingga penulis mengharapkan adanya saran dan kritik yang

bersifat membangun demi kesempurnaan tugas akhir ini.

28 Oktober 2020

Penulis

Page 6: TUGAS AKHIR - UMM

iii

DAFTAR ISI

BERITA ACARA UJIAN.................................................................................................

SURAT PERNYATAAN KEASLIAN............................................................................

SURAT KETERANGAN DARI PERUSAHAAN.........................................................

KATA PENGANTAR ........................................................................................................ i

ABSTRAK ........................................................................................................................ iii

ABSTRACT ....................................................................................................................... iv

DAFTAR ISI ...................................................................................................................... v

DAFTAR TABEL ............................................................................................................ ix

DAFTAR GAMBAR ......................................................................................................... x

DAFTAR LAMPIRAN .................................................................................................... xi

BAB I .................................................................................................................................. 1

PENDAHULUAN .............................................................................................................. 1

1.1. Latar Belakang ............................................................................................... 1

1.2. Rumusan Masalah .......................................................................................... 2

1.3. Tujuan Peneltian ............................................................................................ 2

1.4. Manfaat Penulisan .......................................................................................... 3

1.5. Batasan Masalah dan Asumsi ........................................................................ 3

BAB II ................................................................................................................................ 4

LANDASAN TEORI ......................................................................................................... 4

2.1. Perawatan (Maintenance) .............................................................................. 4

2.1.1. Tujuan Maintenance ..................................................................................... 4

2.1.2. Jenis –jenis Maintenance............................................................................... 5

2.2. Total Productive Maintenance (TPM) ........................................................... 7

2.2.1. Pengertian Total Productive Maintenance (TPM) ........................................ 7

Page 7: TUGAS AKHIR - UMM

iv

2.2.2. Tujuan Total Productive Maintenance (TPM) .............................................. 8

2.2.3. Target Total Productive Maintenance (TPM) ................................................ 9

2.2.4. Pilar-pilar Total productive Maintenance (TPM) ....................................... 10

2.3. Overall Equipment Effectiveness (OEE) ..................................................... 13

2.3.1. Definisi Overall Equipment Effectiveness (OEE) ...................................... 13

2.3.2. Tujuan Implementasi OEE (Overal Equipment Effectiveness) .................. 14

2.3.3. Perhitungan Nilai OEE Overal Equipment Effectiveness) ......................... 15

2.4. Alat pemecah masalah ................................................................................. 18

BAB III ............................................................................................................................. 22

METOLOGI PENELITIAN .......................................................................................... 22

3.1. Metologi Penelitian ...................................................................................... 22

3.2. Flowchat Penelitian ..................................................................................... 22

3.3. Penjelasan Flowchart Penelitian .................................................................. 23

BAB IV ............................................................................................................................. 30

PENGUMPULAN DAN PENGOLAHAN DATA........................................................ 30

4.1. Tinjauan Perusahaan .................................................................................... 30

4.1.1. Sejarah Perusahaan...................................................................................... 30

4.1.2. Visi Misi PT Kebon Agung ........................................................................ 31

4.1.3. Struktur Organisasi PT Kebon Agung ........................................................ 32

4.1.4. Proses Produksi ........................................................................................... 35

4.2. Pengumpulan Data ....................................................................................... 45

4.2.1. Data Jumlah Produksi ................................................................................. 45

4.2.2. Data Produk Cacat....................................................................................... 45

4.2.3. Data Available Time ................................................................................... 46

Page 8: TUGAS AKHIR - UMM

v

4.2.4. Data Downtime ........................................................................................... 47

4.2.5. Data Planned Downtime ............................................................................. 47

4.3. Pengolahan Data .......................................................................................... 48

4.3.1. Persediaan (Availability Rate) .................................................................... 48

4.3.2. Efektivitas Kinerja (Performance Rate) ...................................................... 50

4.3.3. Tingkat Kualitas Produk (Quality Rate) ..................................................... 54

4.3.4. Overall Equipment Effectiveness (OEE) .................................................... 55

4.4. Six Big Losses ............................................................................................. 55

4.4.1. Equipment Failure Losses ........................................................................... 56

4.4.2. Set up and adjustment losses ....................................................................... 57

4.4.3. Idling and minor stoppage losses ................................................................ 58

4.4.4. Reduced speed losses .................................................................................. 59

4.4.5. Quality Defect and Rework ......................................................................... 60

4.5. Diagram pareto ............................................................................................ 61

BAB V ............................................................................................................................... 62

ANALISA PEMBAHASAN ........................................................................................... 62

5.1. Analisa Persediaan (Availability Rate) ........................................................ 62

5.2. Analisa Efektifitas Kinerja (Performance Rate) .......................................... 63

5.3. Analisa Tingkat Kualitas Produk (Quality Rate) ......................................... 64

5.4. Analisa Overall Equipment Effectiveness (OEE) ........................................ 65

5.5. Analisa Six Big Losses ................................................................................ 66

5.6. Analisa diagram fishbone ............................................................................. 68

5.6.1. Analisa quality defect and rework............................................................... 68

5.6.2. Analisa Reduced Speed losses ..................................................................... 71

Page 9: TUGAS AKHIR - UMM

vi

5.7. Penerapan Total Productive Maintenance (TPM) ....................................... 74

BAB VI ............................................................................................................................. 77

KESIMPULAN DAN SARAN ....................................................................................... 77

6.1. Kesimpulan .................................................................................................. 77

6.2. Saran ............................................................................................................ 78

Daftar Pustaka ................................................................................................................. 80

LAMPIRAN ..................................................................................................................... 82

Page 10: TUGAS AKHIR - UMM

vii

DAFTAR TABEL

Tabel 3 1 Contoh tabel pengambilan data ......................................................................... 30

Tabel 4 1 Data Jumlah produksi ....................................................................................... 55

Tabel 4 2 Data produk cacat ............................................................................................. 55

Tabel 4 3 Data available Time PT Kebon Agung ............................................................. 56

Tabel 4 4 Data Downtime PT Kebon Agung .................................................................... 57

Tabel 4 5 Data Planned Downtime di PT Kebon Agung .................................................. 57

Tabel 4 6 Hasil perhitungan Loading time ........................................................................ 58

Tabel 4 7 Hasil perhitungan Operation time ..................................................................... 59

Tabel 4 8 Hasil perhitungan Availability rate ................................................................... 60

Tabel 4 9 Hasil perhitungan waktu siklus produksi .......................................................... 61

Tabel 4 10 Hasil perhitungan presentasi waktu kerja ....................................................... 62

Tabel 4 11 Hasil perhitungan Ideal cycle time.................................................................. 63

Tabel 4 12 Hasil perhitungan Performance Rate .............................................................. 63

Tabel 4 13 Hasil perhitungan Quality Rate ....................................................................... 64

Tabel 4 14 Hasil perhitungan nilai OEE ........................................................................... 65

Tabel 4 15 Hasil perhitungan equipment failure losses .................................................... 66

Tabel 4 16 Hasil perhitungan set up and adjustment losses .............................................. 67

Tabel 4 17 Hasil perhitungan Idling and minor stoppage losses ...................................... 68

Tabel 4 18 Hasil perhitungan Reduced speed losses ........................................................ 70

Tabel 4 19 Hasil perhitungan Quality defect & rework .................................................... 71

Tabel 4 20 Kumulatif total time losses ............................................................................. 71

Tabel 5 1 Perhitungan six big losses ................................................................................. 78

Page 11: TUGAS AKHIR - UMM

viii

DAFTAR GAMBAR

Gambar 2 1. 8 pilar TPM .................................................................................................. 17

Gambar 2 2 Contoh Gambar diagram pareto .................................................................... 25

Gambar 2 3 Contoh gambar diagram Fishbone ................................................................ 27

Gambar 3 1 Flowchart Penelitian ...................................................................................... 29

Gambar 4 1 Struktur Organisasi PT Kebon Agung .......................................................... 39

Gambar 4 2 Diagram aliran proses produksi gula ............................................................. 44

Gambar 4 3 Aliran proses penggilingan............................................................................ 47

Gambar 4 4 Diagram alir proses pemurnian ..................................................................... 49

Gambar 4 5 Diagram alir proses penguapan ..................................................................... 52

Gambar 4 6 Diagram alir proses masakan ........................................................................ 53

Gambar 4 7 Diagram alir proses puteran .......................................................................... 54

Gambar 4 8 Diagram alir proses pengeringan................................................................... 55

Gambar 5 1 Grafik hasil Perhitungan availability............................................................. 74

Gambar 5 2 Grafik hasil Perhitungan Performance rate ................................................... 75

Gambar 5 3 Grafik hasil Perhitungan Quality rate............................................................ 76

Gambar 5 4 Grafik hasil Perhitungan Overall Equipment Effectiveness (OEE) .............. 77

Gambar 5 5 Diagram pareto six big losses ....................................................................... 79

Gambar 5 6 Diagram fishbone quality defect and rework ................................................ 80

Gambar 5 7 Diagram fishbone Reduced Speed losses ..................................................... 82

Page 12: TUGAS AKHIR - UMM
Page 13: TUGAS AKHIR - UMM

80

DASTAR PUSTAKA

Afif Fahmi, A. R. (2013). the implementation of total productive maintenancetheory

to increase the productivity of kth-8 machine measuring overall equipment

effectiveness method (Study Case PT. Indonesian Tobacco).

Anthony, M. B. (2019). Analisa Penerapan Total Productive Maintenance (TPM)

mengunakan Overall Equipment Efectiveness (OEE) dan Six Big Losses pada

mesin Cold Leveller PT.KPS .

Amrussalam, u. B. (2016). pengukuran dan perbaikantotal productive maintenance

(tpm) menggunakan overall equipment effectiveness (oee ) dan root cause

failure analysis (rcfa).

Assauri, S. (2008). Manajemen Produksi dan Operasi. Jakarta: Lembaga Penerbit

Fakultas Ekonomi Universitas Indonesia.

Assauri, S. (2004). Manajemen Operasi dan Produksi. Jakarta: Lembaga Penerbit

Fakultas Ekonomi Universitas Indonesia.

Badik Yuda Asgara, G. H. (2014). Analisa Efektifitas Mesin Overhead Crane dengan

Metode Overall Equipment Effectiveness (OEE) Di PT.BTU, Divisi Boarding

Bridge , 65.

Corder, A. (1996). Teknik Manajemen Pemeliharaan. Jakarta: Erlangga.

Darminto Pujotomo, R. K. (2007). Analisa Sistem Perawatan Komponen Bearing

Bottom Roller dan V Belt Mesin Ring Frame RY-5 pada Departemen II A (Di PT

Danliris Surakarta).

Daulay, I. N. (2013). Analisa Maintenance Reliability Terhadap MTBF (Mean Time

Between Failures) Facilities Pada Industri Pulp & Paper. Jurnal Ekonomi , 1-18.

Eko Nursubiyantoro, P. d. (2015). Implementasi Total Productive Maintenance

(TPM) dalam Penerapan Overall Equipment Effectiveness (OEE) .

Hery Suliantoro, N. S. (2017). Penerapan Metode Overall Equipment Effectiveness

(OEE) dan Fault Tree Analysis (FTA) untuk mengukur efektifitas mesin reng .

Page 14: TUGAS AKHIR - UMM

81

Muhsin, A. (2016). Analisis Performansi Departemen Machinning Mengunakan

Metode Overall Equipment Effectivenes (OEE) .

Mustajib, N. A. (2013). Sistem Perawatan Terpadu. Yogyakarta: Graha Ilmu.

Nakazima, S. (1988). Introduction to Total Productive Mantenance. Cambridge.

Pyzdek, T. (2002). The Six Sigma Handbook, PanduanLengkap Untuk Greenbelts,

Blackbelts dan Manajer pada Semua Tingkatan. Jakarta: salemba Empat.

Riski Muh Tifani, D. s. (2019). analisa efektifitas mesin air jet loom (ajl) guna

mengurangi breakdown dengan metode overallequipment effectivenees (oee)

dan six big losess di pt.primatexco indonesia.

Sudrajat, A. (2011). Pedoman Praktis : Manajemen Perawatan Mesin Industri.

Bandung.

Venkatesh, J. (2006). Plant Maintenance Resource Center an Introduction to Total

Productive Maintenance (TPM) , 3