i STUDI EVALUASI HARGA AIR PADA BENDUNGAN WONOGIRI UNTUK PLTA AKIBAT PENGERUKAN SEDIMEN (Studi Kasus Pada Proyek Pengerukan Sedimen Bendungan Wonogiri) Water Price Evaluation of Study Wonogiri Dam Result Sediment Dredging (Case Study For Dredging Wonogiri Project) SKRIPSI Disusun untuk memenuhi persyaratan memperoleh gelar Sarjana Teknik Pada Jurusan Teknik Sipil Fakultas Teknik Universitas Sebelas Maret Disusun Oleh: ARIET SETIAWAN NIM. I1110007 JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK UNIVERSITAS SEBELAS MARET SURAKARTA 2015

Upload: vungoc

Post on 20-Jan-2017

227 views

Category:

Documents


1 download

TRANSCRIPT

i

STUDI EVALUASI HARGA AIR PADA BENDUNGAN

WONOGIRI UNTUK PLTA AKIBAT PENGERUKAN

SEDIMEN

(Studi Kasus Pada Proyek Pengerukan Sedimen Bendungan Wonogiri)

Water Price Evaluation of Study Wonogiri Dam Result Sediment Dredging

(Case Study For Dredging Wonogiri Project)

SKRIPSI

Disusun untuk memenuhi persyaratan memperoleh gelar Sarjana Teknik

Pada Jurusan Teknik Sipil Fakultas Teknik Universitas Sebelas Maret

Disusun Oleh:

ARIET SETIAWAN

NIM. I1110007

JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK

UNIVERSITAS SEBELAS MARET

SURAKARTA

2015

I Sulqulqrued ueso(l

Bp"pued, *::r#;d; #f.-*uadp rnlun ," *"*lTOOOIIII'hIIN

@

(ur8ouorg uuBunpua8 uerulpas uEInra8ued 4e'{or6 BpBd snsex 'OI

NENIOSS NYXfiUsi)Nsd rvflDlv v'L'Id I)nINnruI30No^\Nv3Nf}CNSsYovduIYVStIY}-lISYnlv^gIon!

NYOfnJSSHild NVIAIY'IVH I

200 I z0L86l lzll9s6

1001乙Oι661乙 1608961・ d11ヽ

工囚StL ~~

2〃gllcI Ap■

ずC EDノ

IIdIS l■qo」j IIPSlllltlf

101n80ヽ【~I10N Kpnls un劉801d lenlЭ】

`IマWS08110ン、

1001 1098616乙 806S61 dI)〔

tL囚 `ηSOllus uttqulog・ II

sNll {FDI3J/S,B}I!LfPIIrdrs {FDIoJ uesnmt uzuax

'rnqeleEuaIll " -

100 I Z0L66l tZZjltc - .-' '5SfrT,v-:=E

I00 z 806661 2260 -c - - -- *

@I00 I 808861 LZll!i: - --lu

( " "'. " " "'-*,'\"7" " " " """"""" " )

=・… …■ ……… …)

~1¨… … …

)

■囚 `UЭ Ibじ韓nA」 ■J_lτ 珠 F ■

乙00 1 τO乙 861 1τ II∫ ■ : 二‖ヽ

■lヽ・OIIl=

ifTI「 [1可 |::rln8ua6 -; -

S10乙 IJOttqЭ dシ0:1088110tL

ullIOS: ■r2H

opod l鋼ン、摂アIЭqosゝ ピ上下砥=II ワ IT二

SηlttJ IldIS InO■ 略 ― f lIB屁 評 pIIOd I卜3uЭd IIIII配&熙 Ч Ip配平I‐葛 三 T tH・ 輛二

ん00011

NVAVIユ |

:Ч0101

浄θaタノご′′βθνり 8ν」

8νF=′∂′σ ρ2//∂ ∂∫ηθθレπ7ど ノQJ″りσ′′r3

(:』 IBOuOM u88unpuo8■ oIIIIpOS I10

N■〕罐ICI■SNV】 flu■ 1

】n■NnI】 lr)oNOAヽ NVONnCN■ 81

NVHVS]DNJ(1ヽ `1ヽ V■VH

iv

MOTTO

بسم اهلل الّرحمن الّرحيم

Masa depan itu aku bangun dengan kedua tanganku,aku rancang dengan akalku, dan aku wujudkan dengan pengetahuan, perbuatan, dan

keiklhasanku. (penulis)

Ketika engkau melakukan kesalahan, kemudian engkau menyadari akan

kesalahanmu itu, maka pada saat itulah engkau akan menjadi sosok yang

kuat. (penulis)

Ketika engkau menjalani masa-masa yang penuh dengan kesedihan, ingatlah

bahwa Allah pernah memberimu masa-masa yang penuh dengan kebahagiaan. Dia sedang menguji kesabaran dan kemampuanmu untuk mengingat nikmat

dan kebaikanmu untuk mengingat nikmat dan kebaikan yang telah diberikan-Nya kepadamu. Ucapkanlah :

“Al-hamdu lillaahi ‘ala kulli haal “ ( Segala puji bagi Allah atas kondisi yag bagaimana pun)

(Maha Abul „Izz)

Maka sesungguhnya bersama kesulitan ada kemudahan”.

(Al-Insyirah: 5)

“Alloh SWT tidak membebani seseorang melainkan sesuai dengan

kesanggupannya”

(Al-Baqoroh: 286)

v

PERSEMBAHAN

Karya kecil ini kupersembahkan untuk:

Papa dan (alm) yang telah membimbing dan merawatku hingga saat ini

Istriku , Satria anakku yang dengan tanpa mereka sadari telah memberiku motivasi dalam penyusunan skripsi ini. Semoga mereka bisa menjadi lebih dari

yang telah aku capai

Teman-teman mahasiswa sipil semua angkatan

Semua orang yang telah membantuku dengan ikhlas hingga saat ini

vi

Ucapan Terima Kasih

بسم اهلل الّرحمن الّرحيمAkhirna. . selesaie juga Skripsi ini. Ini jg berarti kalo perjalanan panjangku untuk menempuh

gelar sarjana teknik selesai juga. . Alhamdulilah. .

Paling utama aku ucapin terimakasih pada Allah SWT, atas terkabulnya doa2ku hingga aku bisa

mencapai saat ini. Tak lupa juga aku ucapin terimakasih pada orang-orang yg telah bantu aku,

yaitu :

1. Terima kasik Kepada bapak/ibu dosen pembimbing I bapak, Ir. Sugiarto, MT dan II

Bapak Ir. Adi Yusuf Muttaqien, MT skripsi saya, tanpa beliau, saya tidak bisa

menyelesaikan skripsi.

2. Terimakasih bapak/ibu dosen dan staf karyawan UNS, yang telah membantu dalam

membuat skripsi saya.

3. Papa dan (alm) Mama yang dengan keikhlasannya tak pernah bosan doain aku hingga

saat ini. Kasih sayang dan pengorbanan ibu tak ada yang gantiin.

4. Istriku tersayang dan anak ku satria selalu memotivasi agar skripsi aku cepat kelar dan

terimakasih atas doanya

5. Terimakasih kepada teman teman sipil yang mau membantu dalam kelancaran menyusun

laporan ini.

6. Terima kasih kepada orang-orang yang ada di adi karya, telah mau memberi kan data-

data yang aku butuhkan. Dan aku doakan agar proyek nya cepet selesai dan menjadi

perusahaan yang terbaik.

vii

ABSTRAK

Ariet Setiawan, 2015: Studi Evaluasi Harga Air Pada Bendungan Wonogiri Untuk

PLTA Akibat Pengerukan Sedimen (Studi Kasus Pada Proyek Pengerukan Sedimen

Bendungan Wonogiri). Skripsi, Jurusan Teknik Sipil Fakultas Teknik Universitas Sebelas

Maret Surakarta

Bendungan Wonogiri terletak di Kecamatan Wuryorejo, Kabupaten Wonogiri terletak ±10

km disebelah selatan Kota Wonogiri. Akibat banyaknya sedimen yang menumpuk dari

hulu DAS Keduang merupakan masalah yang terjadi pada Bendungan Wonogiri Hal ini

mengakibatkan tampungan air pada bendungan berkurang. Sehingga mengurangi kinerja

pasokan pembangkit listrik tenaga air untuk PT. Indonesia Power.

Studi ini dilakukan untuk mengetahui harga jual air minimal untuk pembangkit listrik yang

harus dibayar oleh PT. Indonesia Power untuk biaya operasional dan pemeliharaan serta

biaya pengerukan. Metode yang digunakan dalam penelitian ini ini adalah deskriptif

evaluatif, penelitian yang menggambarkan kondisi proyek tertentu dengan analisis data-

data yang ada. Studi evaluasi ini mengkaji kelayakan Analisa ekonomi Bendungan

Wonogiri ditinjau terhadap Nilai Rasio Biaya Manfaat (B/C), Selisih Biaya Manfaat (B-C)

atau NPV, Tingkat Pengembalian Internal (IRR) serta Analisa Sensivitas.

Dari hasil Hasil Analisa sensitivitas sesudah pengerukan dapat diperoleh dan B/C sesudah

pengerukan sebesar 1,48, NPV sesudah pengerukan pengerukan untuk harga air pada suku

bunga 11% yaitu 1,065.,884.078.824, IRR sesudah pengerukan diperoleh hasil 18,055 %,

Titik Impas atau BEP tercapai setelah 34 tahun 5 bulan, dan dapat diambil kesimpulan

pemakaian air untuk PLTA dengan harga jual minimal air Rp. 154,9 per kWh layak dari

sisi ekonomi

Kata Kunci: harga air, PLTA, kelayakan ekonomi, titik impas serta Analisa

Sensitivitas

viii

ABSTRACT

Ariet Setiawan, 2015, Water Price Evaluation of Study Wonogiri Dam Result

Sediment Dredging (Case of Study at Wonogiri Dredging Project) . Final Assignment,

Department of Civil Engineering, Faculty of Engineering, Sebelas Maret University of

Surakarta

Wonogiri dam is located in District Wuryorejo, Wonogiri is ± 10 km in the south of City

Wonogiri. Effect of sediment that accumulates from the upstream watershed Keduang is a

problem that occurs in Wonogiri Dam This resulted in reduced water storage dams. There

reducing the performance of the supply of hydroelectric power of plants.

The method used in this research is descriptive evaluative, research that describes the

condition of a particular project with the analysis of existing data. This evaluation study

examines the economic feasibility analysis.. This evaluation study examines the feasibility

of economic analysis in terms of the value Dam Wonogiri Benefit Cost Ratio (B / C),

Difference in Cost Benefit (B-C) or NPV, Internal Rate Of Return (IRR) and Sensitivity

Analysis, this evaluation study also use to know minimum selling price of water for power

generation for operational costs and maintenance and dredging.

This methods starts with analyzing large existing costs. Which is composed of the initial

construction cost of development, hydropower costs, operating costs and the cost. From the

results of the sensitivity analysis results can be obtained after dredging and B / C after

dredging of 1.48, NPV after dredging dredging for the price of water at the rate of 11% is

1,065.884 078 824, IRR after dredging obtained results 18.055%, BEP is reached after 34

years and 5 months conclude the use of water for hydropower at a minimum price is Rp.

154 .9 per kWh proper from economic feasibility.

Keywords: price of water, hydropower, economic feasibility, breakeven and

Sensitivity Analysis

ix

KATA PENGANTAR

Puji syukur kehadirat allah SWT yang selalu melimpahkan rahmat serta hidayahnya

sehingga penulis dapat menyelesaikan penyusunan skripsi dengan judul “STUDI

EVALUASI HARGA AIR PADA BENDUNGAN WONOGIRI UNTUK PLTA

AKIBAT PENGERUKAN SEDIMEN (Studi Kasus Pada Proyek Pengerukan

Sedimen Bendungan Wonogiri).

Studi ini dilakukan untuk mengetahui berapa rupiah harga jual air untuk pembangkit

listrik yang harus dibayar oleh PT. Indonesia Power untuk biaya operasional dan

pemeliharaan serta pengerukan. Pembahasan dimulai dengan menganalisa besar biaya–

biaya yang ada. Yakni terdiri dari biaya konstruksi awal pembangunan, biaya PLTA, biaya

operasional dan biaya pengerukan

Dalam penulisan skripsi ini, penulis mendapat bantuan dari berbagai pihak, baik

secara langsung maupun tidak langsung. Untuk itu, penulis ingin menyampaikan ucapan

terimakasih kepada: Allah SWT yang telah memberikan nikmat sehat selama pelaksanaan

skripsi. Ir. Sugiarto MT, selaku dosen pembimbing I serta Ir. Adi Yusuf Muttaqien, MT

selaku dosen pembimbing II, serta Ibu Fajar Sri Handayani, ST. MT dan Bapak Setiono,

ST, Msc untuk koreksi dan masukannya selama sidang skipsi

Penulis menyadari bahwa skripsi ini masih jauh dari sempurna. Oleh karena itu,

saran dan kritik yang membangun sangat penulis harapkan untuk kesempurnaan skripsi ini

dan semoga skripsi ini dapat berguna bagi pihak – pihak yang membutuhkan.

Surakarta, Februari 2015

Penulis

x

DAFTAR ISI

Halaman

HALAMAN JUDUL ................................................................................................ i

LEMBAR PESETUJUAN ....................................................................................... ii

LEMBAR PENGESAHAN ...................................................................................... iii

MOTTO .................................................................................................................... iv

PERSEMBAHAN .................................................................................................... v

ABSTRAK ............................................................................................................... vi

ABSTRACT ............................................................................................................. vii

KATA PENGANTAR .............................................................................................. viii

UCAPAN TERIMA KASIH .................................................................................... ix

DAFTAR ISI ............................................................................................................ x

DAFTAR TABEL .................................................................................................... xi

BAB 1 PENDAHULUAN ........................................................................................ 1

1.1 ..Umum .......................................................................................................... 1

1.2 Latar Belakang ............................................................................................ 2

1.3 Identifikasi Masalah .................................................................................... 3

1.4 Rumusan Masalah ....................................................................................... 4

1.5 Batasan Masalah .......................................................................................... 4

1.6 Tujuan Penelitian ......................................................................................... 5

1.7 Manfaat Penelitian ....................................................................................... 5

BAB 2 LANDASAN TEORI ................................................................................... 6

2.1 Tinjauan Pustaka ......................................................................................... 6

2.2 Dasar Teori .................................................................................................. 7

2.2.1. Pengertian Analisa Proyek ................................................................ 7

2.2.2. Pengertian Harga Air ......................................................................... 8

2.3 Operasi waduk ........................................................................................... 8

2.3.1. Laju Sedimentasi .............................................................................. 9

2.3.2 Usia Guna dan Penentuan Umur Waduk ........................................... 10

2.3.3 Penentuan Usia Guna Waduk ............................................................ 10

2.4. Kebutuhan Air .............................................................................................. 11

xi

2.4.1.Pembangkit Tenaga listrik ................................................................. 11

2.5.Analisa Ekonomi .......................................................................................... 12

2.5.1. Biaya Proyek ................................................................................... 13

2.5.2. Biaya Modal .................................................................................... 14

2.5.3. Biaya Tahunan ................................................................................. 14

2.6. Perbandingan Biaya ..................................................................................... 15

2.61. Biaya Tahunan Konstan ................................................................... 15

2.6.2. Biaya Tahunan yang Bervariasi ....................................................... 15

2.7. Manfaat Proyek .......................................................................................... 15

2.7.1 Hubungan Manfaat & Biaya ............................................................. 16

2.7.2 Nilai Bunga Dalam Analisa Biaya & Manfaat .................................. 17

2.7.3 Bunga Berganda, Majemuk .............................................................. 18

2.7.4 Nilai Uang Dalam Waktu (Time Value of Money) .......................... 18

2.8 Indikator Kelayakan Ekonomi .................................................................... 19

2.8.1 Net Present Value (NPV) ................................................................. 20

2.8.2 Benefit Cost Ratio (BCR) ................................................................. 20

2.8.3 Internal Rate of Return (IRR) ........................................................... 21

2.8.4 Analisis Sensitivitas .......................................................................... 22

BAB 3 METODOLOGI PENELITIAN ............................................................... 23

3.1. Metode Penelitian ........................................................................................ 23

3.2. Daerah Studi ................................................................................................ 23

3.3. Pengumpulan Data ...................................................................................... 25

3.4. Analisa Data ................................................................................................ 26

3.5. Sistem Pembahasan .................................................................................... 27

3.6. Diagram Alir................................................................................................ 29

BAB 4 ANALISIS DATA DAN PEMBAHASAN ................................................. 29

4.1 Pola Oerasi Waduk & Alokasi Air ........................................................... 29

4.2 Data PLTA ................................................................................................ 29

4.3 Kebutuhan Air PLTA ............................................................................... 30

4.3.1 Tabel Perkiraan Produksi Turbin PLTA ......................................... 31

xii

4.3.2 Tabel Pola Operasional Waduk & Alokasi Air Tahun 2011 .......... 32

4.3.2 Tabel Pola Operasional Waduk & Alokasi Air Tahun 2011 .......... 33

4.3.4 Tabel Pola Operasional Waduk & Alokasi Air Tahun 2013 .......... 34

4.3.5 Tabel Laporan Bulanan Operasional Waduk November 2013 ....... 34

4.4 Analisa Ekonomi ......................................................................................... 35

4.4.1 Analisa Biaya ............................................................................................ 37

4.4.2 Analisa Manfaat (Benefit) ......................................................................... 40

4.4.3 Benefit Cost Ratio (BCR) .......................................................................... 42

4.4.4 Net Present Value (NPV) .......................................................................... 42

4.4.5 Internal Rate Of Return (IRR) ................................................................... 46

4.4.6 Break Event Point (BEP) ........................................................................... 47

4.4.7 Analisis Sensitivitas .................................................................................. 49

4.4.8 Pembahasan Hasil Analisa Ekonomi .......................................................... 52

BAB 5 KESIMPULAN DAN SARAN ................................................................... 53

5.1 Kesimpulan .......................................................................................................... 53

5.2 Saran .................................................................................................................... 54

DAFTAR PUSTAKA ................................................................................................ 50

LAMPIRAN .............................................................................................................. xii

xiii

DAFTAR TABEL

Tabel 2.1. Jumlah Bunga dan Modal Setelah n Tahun .......................................... 18

Tabel 4.2. Pola Operasional Waduk & Alokasi Air .................................................. 31

Tabel 4.2.4 Nilai NPV pada Berbagai Tingkat Suku Bunga Sebelum Pengerukan .. 39

Tabel 4.2.5 Nilai NPV pada Berbagai Tingkat Suku Bunga Sesudah Pengerukan ... 41

Tabel 4.5.0 Rekapitulasi Analisis Sensitivitas Sebelum Pengerukan ........................ 45

Tabel 4.5.1 Rekapitulasi Analisis Sensitivitas Sesudah Pengerukan ........................ 46

xiv

DAFTAR NOTASI

1. BCR (Benefit Cost Ratio)= perbandingan antara nilai sekarang (present value) dari

manfaat (benefit) dengan nilai sekarang dari biaya (cost)

2. NPV (Net Present Value) = selisih antara present value dari manfaat dan present value

dari biaya

3. IRR (Internal Rate of Return)= tingkat suku bunga yang membuat manfaat dan biaya

mempunyai nilai yang sama atau B-C = 0 atau tingkat suku bunga yang membuat BCR

= 1

4. Analisis Sensitivitas(Sensitivity of Analysis) = diperkirakan dampak yang akan terjadi

apabila keadaan yang sebenarnya terjadi sesudah proyek tidak sama dengan estimasi

awal.

5. MARR (Minimum Attractive Rate of Return) = Tingkat suku bunga yang menjadi

acuan sebesar 11%

6. Titik Impas (Break Event Point) = Waktu pengembalian modal biaya

xv

DAFTAR RUMUS

Rumus 2.2.3. Perhitungan usia guna waduk .............................................................. 10

Rumus 2.4.1. Daya Pembangkit Listrik Tenaga air ................................................... 11

Rumus 2.7.4 Future Value Factor (Mencari F bila diketahui P) .............................. 18

Rumus 2.7.4 Sinking Fund Factor (Mencari A bila diketahui F) ............................. 19

Rumus 2.7.4 Present Value of Annuity Factor (Mencari P jika diketahui A) ........... 19

Rumus 2.7.4 Capital Recovery Factor (Mencari A bila diketahui P) ....................... 19

Rumus 2.8.1 Rumus untuk perhitungan nilai present value ini ................................ 20

Rumus 2.8.2 Rumus untuk perhitungan BCR ........................................................... 20

Rumus 2.8.3. Rumus Perhitungan IRR ..................................................................... 21

Rumus 2.8.4 Rumus untuk Break Event Point .......................................................... 21

Rumus 2.8.6. Analisa Sensitivitas ............................................................................. 22

xvi

DAFTAR PUSTAKA

Dandekar, M.M dan Sharma, K.N 1991. Pembangkit Listrik Tenaga Air, Jakarta:

Universitas Indonesia.

Giatman, M.2006. Ekonomi Teknik. Jakarta: PT. Raja Grafindo Persada

Kodatie, Robert J. 1995. Analisa Ekonomi Teknik, Andi,Yogyakarta

Kuiper, Edward.1971. Water Reosurces Project Economic, Canada

Mohammad, Nazir. 2003. Metedologi Penelitian. Penerbit Shalia Indonesia, Jakarta.

Mohan, Thomas A.Mc. 1978. Reservoir Capacity and Yield. Elevier.

Nemec, Jaromir.1973. Engineering Hydrology. New Delhi: Tata Mcgrow Hill Publishing

Company Ltd

Priyantoro, Dwi. 1987 Diktat Kuliah Transportasi Sedimen. Fakultas Teknik Universitas

Brawijaya.Tidak diterbitkan

Pudjosumarto, Mulyadi 1985, Evaluasi Proyek Malang: Fakultas Ekonomi Universitas

Brawijaya

Pujawan, I Nyoman. 2009 Ekonomi Teknik. Liberty, Yogyakarta

Sudjarwadi. 1998.Operasi Waduk. Yogyakarta. Pau Ilmu Teknik Universitas Gadjah Mada

Suyanto, Adhi, Trie M Sunaryo dan Roestam Sjarief. 2001. Ekonomi Teknik Sumber Daya

Air; Suatu Pengantar Praktis. Jakarta: Masyarakat Hidrologi Indonesia (MHI)

xvii