A PEKERJAAN PERSIAPAN/PENDAHULUAN 86.075.000
B 1. PEKERJAAN STRUKTUR 691.557.325
B.1.1. PEKERJAAN STRUKTUR BAWAH ( SUB STRUCTURE )
B.1.1.1 PEKERJAAN PONDASI TIANG PANCANG
B.1.1.2 TEST PDA ( Pile Dynamic Analytics )
B.1.1.3 PEKERJAAN TANAH DAN LANTAI KERJA
B.1.1.4 PEKERJAAN STRUKTUR LANTAI BAWAH
B.1.1.5 PEKERJAAN STRUKTUR LANTAI ATAS 338.864.400
B.1.1.6 PEKERJAAN STRUKTUR LANTAI ATAP 352.692.925
C PEKERJAAN ARSITEKTUR 3.570.568.463
C1 PEK. ARSITEKTUR LT. DASAR DAN LANTAI DUA 3.446.248.463
C2 PEK. ARSITEKTUR LT. ATAP 124.320.000
D PEKERJAAN PLUMBING 259.145.583
D1 PERALATAN UTAMA 55.475.275
D2 INSTALASI PIPA AIR BERSIH 16.917.564
D3 INSTALASI AIR KOTOR & AIR BEKAS 186.752.744
E PEKERJAAN ELEKTRIKAL 532.178.600
E.1 BIAYA PENYAMBUNGAN DAYA PLN
E.2 PEKERJAAN TEGANGAN RENDAH 326.494.600 E.3 PEKERJAAN GENSET
E.4 PEKERJAAN PENANGKAL PETIR 39.300.000
E.5 PEKERJAAN SYSTEM TATA SUARA DAN UDARA 166.384.000
F PEKERJAAN SITE DEVELOPMENT 128.502.900
JUMLAH TOTAL 5.268.027.871
PEMBULATAN 5.268.000.000
-
JUMLAH HARGA (Rp.)NO. URAIAN PEKERJAAN
-
-
-
RENCANA ANGGARAN BIAYA
MESJID BEKASI
STRUKTUR PONDASI DAN BAWAH