PROFIL PELAKSANAAN PERIODE (29 SEPTEMBER 2019 27 NOVEMBER 2019) PEKERJAAN REHABILITASI DAN RENOVASI SARANA DAN PRASARANA MADRASAH KOTA JAKARTA BARAT, KOTA JAKARTA SELATAN MIN 7 JAKARTA BARAT

Upload: others

Post on 11-Dec-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROFIL PELAKSANAANprofil pelaksanaan periode (29 september 2019 –27 november 2019) pekerjaan rehabilitasi dan renovasi sarana dan prasarana madrasah kota jakarta barat, kota jakarta

PROFIL PELAKSANAAN PERIODE (29 SEPTEMBER 2019 – 27 NOVEMBER 2019)

PEKERJAAN REHABILITASI DAN RENOVASI SARANA DAN PRASARANA MADRASAH KOTA JAKARTA BARAT, KOTA JAKARTA SELATAN

MIN 7 JAKARTA BARAT

Page 2: PROFIL PELAKSANAANprofil pelaksanaan periode (29 september 2019 –27 november 2019) pekerjaan rehabilitasi dan renovasi sarana dan prasarana madrasah kota jakarta barat, kota jakarta

DATA KONTRAK :

1 Nama ProyekRehabilitasi Dan Renovasi Sarana dan PrasaranaMadrasah Negeri Jakarta Barat dan Jakarta Selatan

2 LokasiMadrasah Ibtidaiah Negeri 7 (MIN N 7 Jakarta )

Jl. Fajar Baru Utara No.34, RT.5/RW.9, Cengkareng Tim., Kecamatan Cengkareng, Kota Jakarta Barat

3 Pemberi Tugas

Kementrian Pekerjaan Umum Dan Perumahan RakyatDirektorat Jendral Cipta KaryaSatker Pelaksanaan Prasarana Pendidikan Olahraga dan PasarJl. Kramat Raya no 63, Jakarta Pusat

4 Konsultan Supervisi PT. INKONEKSI IZI KONSULTAN

SPMK Tanggal 30 September 2019

Kontrak Tanggal 30 September 2019

5 Kontraktor Pelaksana PT. NENCI CITRA PRATAMA

SPMK Tanggal 30 September 2019

Kontrak Tanggal 30 September 2019

6 Tanggal Dimulainya Pekerjaan 30 September 2019

7 Jangka Waktu Pelaksanaan 90 hari kalender

Page 3: PROFIL PELAKSANAANprofil pelaksanaan periode (29 september 2019 –27 november 2019) pekerjaan rehabilitasi dan renovasi sarana dan prasarana madrasah kota jakarta barat, kota jakarta

A Prestasi Pekerjaan

1 Prestasi Dicapai 37 %

2 Prestasi menurut rencana 45,3 %

3 Deviasi Prestasi Komulatif -8,3 %

B Waktu Pelaksanaan

1 Jangka Waktu Pelaksanaan 90 Hari

2 Waktu yang telah berjalan 60 Hari

3 Sisa Waktu Pelaksanaan 30 Hari

PROGRESS DAN WAKTU PELAKSANAAN

Page 4: PROFIL PELAKSANAANprofil pelaksanaan periode (29 september 2019 –27 november 2019) pekerjaan rehabilitasi dan renovasi sarana dan prasarana madrasah kota jakarta barat, kota jakarta

KURVA S

MADRASAH IBTIDAIYAH NEGERI (MIN 7)

JAKARTA BARAT - DKI JAKARTA

No Uraian Pekerjaan BobotOKTOBER NOVEMBER DESEMBER

1 s.d 3 4 s.d 10 11 s.d 17 18 s.d 2425 s.d 31 1 s.d 7 8 s.d 14 15 s.d 21 22 s.d 28 29 S.d 5 6 s.d 12 13 s.d 19 20 s.d 26

I Pekerjaan persiapan & penunjang0.62%

0.048% 0.048% 0.048% 0.048% 0.048% 0.048% 0.048% 0.048% 0.048% 0.048% 0.048% 0.048% 0.048%

II Pekerjaan struktur20.21%

0.809% 0.809% 2.527% 2.527% 2.888% 2.888% 2.888% 3.369% 0.356% 1.155%

III Pekerjaan dinding18.74%

1.441% 1.874% 1.874% 2.342% 2.677% 3.747% 3.747% 1.035%

IV Pekerjaan lantai13.70%

3.424% 3.424% 3.424% 3.424%

V Pekerjaan plafond 4.03%

0.806% 0.806% 0.806% 0.806% 0.806%

VI Pekerjaan pintu, jendela & kaca mati 11.56%

0.826% 0.826% 1.156% 2.312% 2.312% 2.312% 1.817%

VII Pekerjaan pengecatan dinding & plafond 3.20%

0.799% 0.799% 0.799% 0.799%

VIII Pekerjaan atap15.63%

2.606% 3.127% 6.254% 3.648%

IX Pekerjaan listrik2.48%

0.496% 0.496% 0.496% 0.496% 0.496%

X Pekerjaan utilitas

9.83%

0.983% 1.404% 3.277% 2.458% 1.709%

Total biaya pekerjaan utilitas 100.00%

Rencana Progres Mingguan 0.05% 0.86% 0.86% 4.02% 4.45% 4.81% 6.10% 10.03% 14.15% 21.52% 16.18% 9.59% 7.39%

Rencana Progres Mingguan Komulatif 0.05% 0.90% 1.76% 5.78% 10.22% 15.03% 21.14% 31.16% 45.32% 66.84% 83.02% 92.61% 100.00%

Realisasi Progres Mingguan 3.12% 0.68% 0.58% 0.74% 4.72% 4.94% 3.78% 8.45% 9.79%

Realisasi Progres Mingguan Komulatif 3.12% 3.80% 4.38% 5.12% 9.84% 14.78% 18.56% 27.01% 36.80% 100.00%

Deviasi 3.07% 2.90% 2.62% -0.66% -0.4% -0.3% -2.6% -4.2% -8.5%

Page 5: PROFIL PELAKSANAANprofil pelaksanaan periode (29 september 2019 –27 november 2019) pekerjaan rehabilitasi dan renovasi sarana dan prasarana madrasah kota jakarta barat, kota jakarta

Pekerjaan yang Sudah Dikerjakan

Item pekerjaan VolRencana

VolRealisasi

Pembesian kolom (35x35) 32 bh 22 bh

Pembesian kolom (20x20) 30 bh 20 bh

Page 6: PROFIL PELAKSANAANprofil pelaksanaan periode (29 september 2019 –27 november 2019) pekerjaan rehabilitasi dan renovasi sarana dan prasarana madrasah kota jakarta barat, kota jakarta

Pekerjaan yang Sudah Dikerjakan

Item pekerjaan VolRencana

VolRealisasi

Pengecoran kolom 35x35 32 bh 22 bh

Pengecoran kolom 20x0 30 bh 20 bh

Page 7: PROFIL PELAKSANAANprofil pelaksanaan periode (29 september 2019 –27 november 2019) pekerjaan rehabilitasi dan renovasi sarana dan prasarana madrasah kota jakarta barat, kota jakarta

Item pekerjaan VolRencana

VolRealisasi

Pengecoran KolomPraktis(15x15)

45 bh 30 bh

Page 8: PROFIL PELAKSANAANprofil pelaksanaan periode (29 september 2019 –27 november 2019) pekerjaan rehabilitasi dan renovasi sarana dan prasarana madrasah kota jakarta barat, kota jakarta

Item pekerjaan VolRencana

VolRealisasi

pemasangan Bata ringan 911.31

m2 729.04 m2

Page 9: PROFIL PELAKSANAANprofil pelaksanaan periode (29 september 2019 –27 november 2019) pekerjaan rehabilitasi dan renovasi sarana dan prasarana madrasah kota jakarta barat, kota jakarta

Item pekerjaan VolRencana

VolRealisasi

Plesteran lantai527.7 m2 369.39 m2

Urugan Peninggian lantai 158.31 m3 134.5635 m3