    Ztop = 13386997.02 mm3

    Zbot = 13548529.41 mm3

    Mg = 500.94 kNm

    Mq = 1512.5 kNm

    Rg = 91.08 kN

    Rq = 45.83 kN

    fct = fcw 16 N/mm2

    fsub=ftop -40.42 N/mm2fint=fbot 145.08 N/mm2

    P = 18245777.83 N

    Pada tengah bentang

    x = 1/2 L

    e = 87.93 mm

    Pada tumpuan

    Mo = 0

    e= -41.89

    Pada 1/4 bentang

    x = 1/4 L 5.5 m

    Mg---->Mx 375.705 kNm

    Mq---->Mx -126.042 kNm

    e= -25.79 mm

    Kebutuhan Tendon

    tendon 34 mm

    teg. Baja 1400 N/mm2

    n 14.36173325

    14 buah

    KEBUTUHAN TULANGAN GESER

    L 22 m

    g 8.28 kN/m

    q 25 kN/m

    Wd 33.28 kN/m

    V 366.08 kN

    fcp 5 N/mm2

    fck 30 N/mm2bw 150 mm

    h 1450 mm

    fy 240 N/mm2

    ft 7.2 N/mm2

    Vc 1323131.642

  • 7/31/2019 Perhitungan Beton Pratekan

    3/10

    X 1450

    d e f q L ftt fct

    500 150 300 25 22 -3 16

    y1 1375 mm2 ya 729.35

    y2 900 mm2 yb 720.65

    y3 250 mm2

    Momen Inersia

    Ix total 9763777174 mm4 I2 28300.8

    Iy 6540625000 mm4

    Z yang digunakan

    13386997.02 mm3

    500940000 Mq = 1512.5 kNm

    1512500000 Nmm

    .zbott

    n = 0.85

  • 7/31/2019 Perhitungan Beton Pratekan

    4/10

    e= 2013440000

    1 11.88 -2.62

    2 39.27 39.27

    3 27.46 129.82

    -6.9 249663333

    3 16.10

  • 7/31/2019 Perhitungan Beton Pratekan

    5/10

    fpe fy fck fcp

    1400 240 30 5 0.85

  • 7/31/2019 Perhitungan Beton Pratekan

    6/10

    a q

    b

    L

    a b c

    650 150 800

    c

    Luas A 97500 mm2

    Luas B 120000 mm2

    Luas C 120000 mm2

    Total 217500 mm2

    0.2175

    d Momen statis terhadap alas

    y = 1123.28 mm

    I1 182812500

    I2 6400000000

    I3 1600000000

    fZtop 36816511.41 mm3

    Zbott 7431114.735 mm3

    Berat sendiri

    g = 5.22 kN/m

    Momen akibat berat sendiri

    Mg = 261 kNm

    Mg/z = 7.09 N/mm2

    Gaya yang terjadi

    ftop >= -10.09 N/mm2

    fbott >= ftw/n (mg+mq)/n

    -3.53 169.69

    fbott >= 166.16 N/mm2

    Gaya Prategang

    P = 4243679.70 N

    e = 256.80 mm

    C

    B

    A

  • 7/31/2019 Perhitungan Beton Pratekan

    7/10

    Batas-batas Tendon

    A = 217500 mm2

    Ztop = 36816511.41 mm3

    Zbot = 7431114.735 mm3

    Mg = 261 kNm

    Mq = 1000 kNmRg = 52.2 kN

    Rq = 33.33 kN

    fct = fcw 16 N/mm2

    fsub=ftop -10.09 N/mm2

    fint=fbot 166.16 N/mm2

    P = 4243679.70 N

    Pada tengah bentang

    x = 1/2 L

    e = 348.38 mm

    Pada tumpuan

    Mo = 0

    e= -1.20

    Pada 1/4 bentang

    x = 1/4 L 5

    Mg---->Mx 195.75 kNm

    Mq---->Mx -83.333 kNme= 29.96101662 mm

    Kebutuhan Tendon

    tendon 34 mm

    teg. Baja 1400 N/mm2

    n 3.340312286

    3 buah

  • 7/31/2019 Perhitungan Beton Pratekan

    8/10

    X 1350

    d e f q L ftt fct fpe

    400 150 300 20 20 -3 16 1300

    y1 1275 mm2 ya 226.72

    y2 800 mm2 yb 1123.28

    y3 200 mm2

    Momen Inersia

    Ix total 8347191810 mm4 I2 38377.89338

    Iy 8182812500 mm4

    Z yang digunakan

    36816511.41 mm3

    261000000 Mq = 1000 kNm

    1.E+09 Nmm

    .zbott

  • 7/31/2019 Perhitungan Beton Pratekan

    9/10

    n = 0.85

    e= 1261000000

    1 28.02 32.96191433

    2 34.16604 34.16604476

    3 61.50 349.5856228

    19.6 1124166673 31.1651471

  • 7/31/2019 Perhitungan Beton Pratekan

    10/10

    fy fck fcp

    240 30 5 0.85