Metode Konstruksi (Stripping, Cutting, dan Compacting di Samping Gedung 4 Fakultas Teknik UNS Kelompok: Andreas Nur HadiI I0113013 Baggus Prastyo I0113023 Dede Zakiyah I0113031 Fika Giri Aspia I0112052 Himamul A’la I0112075

Upload: himamul-ala

Post on 09-Aug-2015

84 views

Category:

Engineering


16 download

TRANSCRIPT

Page 1: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

Metode Konstruksi (Stripping, Cutting, dan Compacting di Samping Gedung 4

Fakultas Teknik UNS

Kelompok:

Andreas Nur HadiI I0113013

Baggus Prastyo I0113023

Dede Zakiyah I0113031

Fika Giri Aspia I0112052

Himamul A’la I0112075

Page 2: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

Site Plan Kondisi Tanah

Page 3: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS
Page 4: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

Pemilihan ALat

1. Stripping dan Cutting

Bulldozer Crawler CAT D5R

Kapasitas Blade : 4.28 m3

Rata-rata Kecepatan maju : 6.3 km/jam

Rata-rata Kecepatan mundur : 7 km/jam

Produktivitas : 229.1995 m3/jam

Page 5: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

2. Loader

Wheel Loader CAT 938K

Kapasitas Bucket : 4 m3

Produktivitas : 285 m3/jam

Page 6: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

3. Dump Truck

Kapasitas muatan :

18144 kg

Produktivitas : 56.7 m3/jam/truck

Page 7: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

4.Compactor

Soil Compactor 825H

L(lebar efektif) : 1.814 m

V(Kecepatan) : 3 km/jam

Produktivitas : 40.815 m3/jam

Page 8: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

Video Perencanaan Metode Konstruksi

Page 9: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

Perhitungan

VOLUME TANAH:

-Volume Bank : 1251.2 m3

-Volume Stripping: 156.4 m3

-Volume Cutting : 1133.9 m3

-Volume Loose : 1360.68 m3

-Volume Compacting : 963.815 m3

Page 10: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

PEKERJAAN STRIPPING :

ALAT : BULLDOZER D5R

PRODUKTIVITAS : 229.1995 m3/jam

VOLUME STRIPPING : 156.4 m3

WAKTU :

= VOLUME STRIPPING / PRODUKTIVITAS ALAT

= 156.4 m3 / 229.1995 m3/jam

= 0.682 JAM 1 JAM

JUMLAH ALAT : 1 BUAH

Page 11: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

PEKERJAAN CUTTING :

ALAT : BULLDOZER D5R

PRODUKTIVITAS : 229.1995 m3/jam

VOLUME CUTTING : 1133.9 m3

WAKTU :

= VOLUME CUTTING / PRODUKTIVITAS ALAT

= 1133.9 m3/ 229.1995 m3/jam

= 4.95 JAM 5 JAM

JUMLAH ALAT : 1 BUAH

Page 12: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

PEKERJAAN LOADING :

ALAT : Wheel Loader CAT 938K

PRODUKTIVITAS : 285 m3/jam

VOLUME LOOSE : 1360.68 m3

WAKTU :

= VOLUME STRIPPING / PRODUKTIVITAS ALAT

= 1360.68 m3/ 285 m3/jam

= 4.77 JAM 5 JAM

JUMLAH ALAT : 1 BUAH

Page 13: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

MOVING:

ALAT : Dump Truck

PRODUKTIVITAS TRUCK : 56.7 m3/jam

PRODUKTIVITAS LOADER : 285 m3/jam

JUMLAH TRUCK YANG DIBUTUHKAN :

= PRODUKTIVITAS LOADER / PRODUKTIVITAS TRUCK

= 285 m3/jam / 56.7 m3/jam

= 5 TRUCK

Page 14: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

PEKERJAAN COMPACTING :

ALAT : Soil Compactor 825H

PRODUKTIVITAS : 40.815 m3/jam

VOLUME COMPACT : 963.815 m3

WAKTU :

= VOLUME COMPACT / PRODUKTIVITAS ALAT

= 963.815 m3 / 40.815 m3/jam

= 23.614 JAM TIAP COMPACTOR

2 COMPACTOR 12 JAM PENGERJAAN

Page 15: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

Perencanaan Jadwal

Page 16: Metode Konstruksi - Proyek Persiapan Lahan Parkir Jurusan Teknik Sipil UNS

Rencana Anggaran Biaya

NB : Anggaran biaya tersebut belum termasuk konsumsi dan rokok pekerja