laporan progress mingguan konsultan cv matra griya mandiri (complete worksheet) 1-25
DESCRIPTION
Laporan Konsultan PengawasTRANSCRIPT
Provinsi : Sulawesi Tengah Nama Kegiatan : Pembangunan Gedung Kantor Dispora Kab. Poso
Kabupaten : Poso Jenis Prasarana : Perkantoran
Kecamatan : Poso Kota Utara Jenis Penanganan : Pembangunan Baru
Kelurahan : Kasintuwu Lokasi : Jl. K.S. Tubun, Kel. Kasintuwu
Volume : (10x30)+(13.50x7.50) Meter2
No. Rab : 01
I GEDUNG KANTOR DISPORA KABUPATEN POSO
A BANGUNAN GEDUNG KANTOR DISPORA
1 Pekerjaan Pasangan
1.1 Pek. Dinding Pasangan Batu bata 1:5
- Dinding depan volume = (15*4.23)-(9*0.85*1.85)-(9*0.45*0.85) = 45.855 M2
- Dinding belakang volume = (15*4.23)-(9*0.85*1.85)-(9*0.45*0.85) = 45.855 M2
- Dinding samping volume = (2*0.86*1.85) = 3.182 M2
- Dinding atas volume = (1.00*10.00) = 10.000 M2
Volume total = 45.855 + 45.855 + 3.145 + 10.30 = 104.892 M2
1.2 Pek. Plesteran Dinding + Acian T=1.5 cm
- Dinding depan volume = (45.855*2) = 91.71 M2
- Dinding belakang volume = (45.855*2) = 91.71 M2
- Dinding samping volume = (3.145*2) = 6.29 M2
- Dinding atas volume = (10.30*2) = 20.6 M2
Volume total = 91.71 + 91.71 + 6.29 + 20.60 = 210.31 M2
2 Pekerjaan Tulangan Beton Bertulang
2.1 Pelat Lantai 2 Volume = (1687.64-1175.0) = 512.64 kg
2.2 Tiang Kolom 30 x 30 cm Volume = (504.34-420.0) = 84.34 kg
2.3 Balok Lantai 30 x 45 cm Volume = (1031.2-627.6) = 403.600 kg
Balok Lantai 20 x 30 cm Volume = (269.94-151.0) = 118.940 kg
Volume Total = 512.64 + 84.34 + 403.6 + 118.94 = 1119.52 kg
Total Berat Besi = 1,119.52
Harga Sat. Pek = 19,295.00 x Jumlah Harga Pekerjaan Besi Tulangan
Total Harga Pek 21,601,138.40
Vol. Pek. Dinding = 104.89
Harga Sat. Pek = 112,595.00 x
Total Harga Pek 11,810,314.74
Vol. Pek. Plester = 210.31
Harga Sat. Pek = 34,405.00 x Jumlah Harga Pekerjaan Dinding 1/2 Bata
Total Harga Pek 7,235,715.55
Vol. Pek. Acian = 210.31
Harga Sat. Pek = 12,150.00 x
Total Harga Pek 2,555,266.50
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas/Asisten Teknik Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
PENGHITUNGAN VOLUME PEKERJAAN TAMBAH KURANG (CCO)
21,601,296.79Rp
21,601,138.40Rp
KEGIATAN PEMBANGUNAN GEDUNG KANTOR DISPORA KAB. POSO
21,601,000.00Rp
21,601,000.00Rp
Laporan Konsultan CV Matra Griya Mandiri (Complete Worksheet) 1-25
sloof 46.25
ring 66.43
kolom 30.25
Pek. kosen Pintu (1,64x2,40) 1 unit
Pek. kosen Pintu (1x2,40) 2 unit
Pek. kosen Jendela (1,2x1,40)10 unit
Pek. kosen Jendela (0,5x1,40)2 unit
Pek. Jalus Pintu 2 buah
Pek. Jalus jendela 21 buah
Laporan Konsultan CV Matra Griya Mandiri (Complete Worksheet) 1-25
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 03 April 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 10 April 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR PELAKSANA : CV. Graha Teknika
3 NOMOR KONTRAK KONTRAKTOR PELAKSANA : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK KONSULTAN PENGAWAS : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 0 0 1.000 0.025 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 0 0 44.000 0.208 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.000 Sub Total 0.233 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 0 0 0 0 0 0 54.2
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 0 0 0 0 0 0
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 0 0 0 0 0 0
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 0 0 0 0 0 0
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 0 0 0 0 0 0
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 0 0 0 0 0 0
30,738,969.50Rp 3.081 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 0 0 0 0 0 0
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 1
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 1 Page 3 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 0 0 0 0 0 0
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 0 0 0 0 0 0
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 0 0 0 0 0 0
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 0 0 0 0
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 0 0 0 0
125,053,581.86Rp 12.533 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 0 0 0 0 0 0
2 Pek. Pondasi poor Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 0 0 0 0 0 0
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 0 0 0 0 0 0
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 0 0 0 0 0 0
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 0 0 0 0 0 0
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 0 0 0 0 0 0
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 0 0 0 0 0 0
8 Pek. Sloof Beton 150/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 0 0 0 0 0 0
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 0 0 0 0 0 0
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 0 0 0 0 0 0
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 0 0 0 0 0 0
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 0 0 0 0 0 0
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 0 0 0 0
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 0 0 0 0 0 0
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 0 0 0 0 0 0
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 0 0 0 0 0 0
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 0 0 0 0 0 0
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 0 0 0 0 0 0
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 0 0 0 0 0 0
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 0 0 0 0 0 0
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 0 0 0 0 0 0
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 0 0 0 0
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 0 0 0 0 0 0
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 0 0 0 0 0 0
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 0 0 0 0 0 0
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 0 0 0 0 0 0
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 0 0 0 0 0 0
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 0 0 0 0 0 0
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 0 0 0 0 0 0
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 0 0 0 0 0 0
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 0 0 0 0 0 0
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0 0 0 0 0 0
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 0 0 0 0 0 0
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0 0 0 0 0 0
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 1 Page 4 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 0 0 0 0
323,453,547.04Rp 32.416 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 0 0 0 0
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 0 0 0 0
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 0 0 0 0
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 0 0 0 0
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 0 0 0 0 0 0
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 0 0 0 0 0 0
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 1 Page 5 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 0 0 0 0
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 0 0 0 0 0 0
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 0 0 0 0 0 0
7,701,730.00Rp 0.772 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 0.000 Total 0.233 Total 0.233
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 1 Page 6 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 1 Page 7 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 10 April 2014
LOKASI : Jl. Brigjen Katamso, Kel Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 17 April 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 0 0 20.400 0.056 20.400 0.056
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 0 0 9.600 0.035 9.600 0.035 1.159091
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 0 0 0 0 0 0 1.670251
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 0 0 0 0 0 0
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 0 0 0 0 0 0
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 0 0 1.160 0.018 1.160 0.018
30,738,969.50Rp 3.081 Sub Total 0.000 Sub Total 0.109 Sub Total 0.109
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 0 0 3.630 0.151 3.630 0.151 3.83
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 2
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 2 Page 8 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 0 0 14.800 1.044 14.800 1.044 14.89957
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 0 0 0 0 0 0
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 0 0 0 0 0 0
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 0 0 0 0
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 0 0 0 0
125,053,581.86Rp 12.533 Sub Total 0.000 Sub Total 1.195 Sub Total 1.195
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 0 0 0.280 0.019 0.280 0.019 0.52043
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 0 0 0 0 0 0 0.088
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 0 0 350.000 0.677 350.000 0.677
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 0 0 2.240 0.049 2.240 0.049
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 0 0 0 0 0 0
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 0 0 0 0 0 0
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 0 0 0 0 0 0
8 Pek. Sloof Beton 150/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 0 0 0 0 0 0
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 0 0 0 0 0 0
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 0 0 0 0 0 0
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 0 0 0 0 0 0
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 0 0 0 0 0 0
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 0 0 0 0
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 0 0 0 0 0 0
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 0 0 0 0 0 0
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 0 0 0 0 0 0
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 0 0 0 0 0 0
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 0 0 0 0 0 0
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 0 0 0 0 0 0
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 0 0 0 0 0 0
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 0 0 0 0 0 0
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 0 0 0 0
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 0 0 0 0 0 0
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 0 0 0 0 0 0
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 0 0 0 0 0 0
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 0 0 0 0 0 0
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 0 0 0 0 0 0
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 0 0 0 0 0 0
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 0 0 0 0 0 0
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 0 0 0 0 0 0
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 0 0 0 0 0 0
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0 0 0 0 0 0
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 0 0 0 0 0 0
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0 0 0 0 0 0
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 2 Page 9 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 0 0 0 0
323,453,547.04Rp 32.416 Sub Total 0.000 Sub Total 0.745 Sub Total 0.745
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 0 0 0 0
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 0 0 0 0
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 0 0 0 0
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 0 0 0 0
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 0 0 0 0 0 0
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 0 0 0 0 0 0
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 2 Page 10 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 0 0 0 0
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 0 0 0 0 0 0
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 0 0 0 0 0 0
7,701,730.00Rp 0.772 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 0.233 Total 2.049 Total 2.282
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 2 Page 11 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 2 Page 12 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 17 April 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 24 April 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 20.400 0.056 21.600 0.059 42.000 0.115 54.2
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 9.600 0.035 10.300 0.037 19.900 0.072
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 0 0 5.900 0.008 5.900 0.008
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 0 0 0 0 0 0
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 0 0 0 0 0 0
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 1.160 0.018 1.210 0.019 2.370 0.037
30,738,969.50Rp 3.081 Sub Total 0.109 Sub Total 0.123 Sub Total 0.232
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 3.630 0.151 3.840 0.160 7.470 0.311
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 3
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 3 Page 13 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 14.800 1.044 15.600 1.101 30.400 2.145 15.76153
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 0 0 0 0 0 0
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 0 0 0 0 0 0
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 0 0 0 0
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 0 0 0 0
125,053,581.86Rp 12.533 Sub Total 1.195 Sub Total 1.261 Sub Total 2.456
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 0.280 0.019 0.310 0.021 0.590 0.039 0.558378
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 0 0 1.930 0.253 1.930 0.253
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 350.000 0.677 425.000 0.822 775.000 1.499
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 2.240 0.049 4.360 0.096 6.600 0.146
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 0 0 0.600 0.079 0.600 0.079
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 0 0 120.000 0.232 120.000 0.232
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 0 0 6.600 0.083 6.600 0.083
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 0 0 0 0 0 0
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 0 0 0 0 0 0
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 0 0 0 0 0 0
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 0 0 0 0 0 0
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 0 0 210.000 0.406 210.000 0.406
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 0 0 0 0
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 0 0 0 0 0 0
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 0 0 0 0 0 0
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 0 0 0 0 0 0
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 0 0 0 0 0 0
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 0 0 0 0 0 0
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 0 0 0 0 0 0
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 0 0 0 0 0 0
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 0 0 0 0 0 0
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 0 0 0 0
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 0 0 0 0 0 0
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 0 0 0 0 0 0
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 0 0 0 0 0 0
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 0 0 0 0 0 0
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 0 0 0 0 0 0
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 0 0 0 0 0 0
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 0 0 0 0 0 0
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 0 0 0 0 0 0
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 0 0 0 0 0 0
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0 0 0 0 0 0
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 0 0 0 0 0 0
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0 0 0 0 0 0
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 3 Page 14 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 0 0 0 0
323,453,547.04Rp 32.416 Sub Total 0.745 Sub Total 1.991 Sub Total 2.736
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 0 0 0 0
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 0 0 0 0
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 0 0 0 0
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 0 0 0 0
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 0 0 0 0 0 0
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 0 0 0 0 0 0
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 3 Page 15 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 0 0 0 0
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 0 0 0 0 0 0
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 0 0 0 0 0 0
7,701,730.00Rp 0.772 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 2.282 Total 3.375 Total 5.657
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 3 Page 16 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 3 Page 17 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 24 April 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 01 Mei 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 42.000 0.115 45.600 0.125 87.600 0.241 54.2
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 19.900 0.072 13.580 0.049 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 5.900 0.008 30.400 0.040 36.300 0.048
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 0 0 0 0 0 0
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 0 0 0 0 0 0
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 2.370 0.037 2.880 0.045 5.250 0.083
30,738,969.50Rp 3.081 Sub Total 0.232 Sub Total 0.259 Sub Total 0.492
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 7.470 0.311 9.450 0.393 16.920 0.704 0.88
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 4
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 4 Page 18 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 30.400 2.145 38.800 2.738 69.200 4.883 69.44924
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 0 0 0 0 0 0
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 0 0 0 0 0 0
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 0 0 0 0
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 0 0 0 0
125,053,581.86Rp 12.533 Sub Total 2.456 Sub Total 3.131 Sub Total 5.587
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 0.590 0.039 0.980 0.065 1.570 0.104 0.736192
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 1.930 0.253 3.970 0.521 5.900 0.775
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 775.000 1.499 459.17 0.888 1234.170 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 6.600 0.146 18.250 0.403 24.850 0.548
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 0.600 0.079 2.220 0.291 2.820 0.370
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 120.000 0.232 228.000 0.441 348.000 0.673
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 6.600 0.083 21.600 0.270 28.200 0.353 28.2
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 0 0 0 0 0 0
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 0 0 120.000 0.232 120.000 0.232
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 0 0 0 0 0 0
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 0 0 0 0 0 0
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 210.000 0.406 250.000 0.483 460.000 0.890
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 18.000 0.397 18.000 0.397
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 0 0 0 0 0 0
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 0 0 0 0 0 0
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 0 0 0 0 0 0
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 0 0 0.250 0.033 0.250 0.033
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 0 0 49.000 0.095 49.000 0.095 5.274262
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 0 0 5.200 0.115 5.200 0.115
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 0 0 0 0 0 0
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 0 0 0 0 0 0
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 0 0 0 0
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 0 0 0 0 0 0
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 0 0 0 0 0 0
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 0 0 0 0 0 0
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 0 0 0 0 0 0
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 0 0 0 0 0 0
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 0 0 0 0 0 0
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 0 0 0 0 0 0
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 0 0 0 0 0 0
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 0 0 0 0 0 0
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0 0 0 0 0 0
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 0 0 0 0 0 0
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0 0 0 0 0 0
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 4 Page 19 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 0 0 0 0
323,453,547.04Rp 32.416 Sub Total 2.736 Sub Total 4.234 Sub Total 6.970
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 0 0 0 0
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 0 0 0 0
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 0 0 0 0
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 0 0 0 0
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 0 0 0 0 0 0
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 0 0 0 0 0 0
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 4 Page 20 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 0 0 0 0
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 0 0 0 0 0 0
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 0 0 0 0 0 0
7,701,730.00Rp 0.772 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 5.657 Total 7.625 Total 13.282
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 4 Page 21 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 4 Page 22 of 150
LAPORAN BULANAN PERTAMA - APRIL 2014
PROGRAM :
Bulan ke
Kamis, 03 April 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Kamis, 01 Mei 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 0 0 1.000 0.025 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 0 0 44.000 0.208 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.000 Sub Total 0.233 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 0 0 87.600 0.241 87.600 0.241 54.2
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 0 0 33.480 0.121 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 0 0 36.300 0.048 36.300 0.048
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 0 0 0 0 0 0
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 0 0 0 0 0 0
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 0 0 5.250 0.083 5.250 0.083
30,738,969.50Rp 3.081 Sub Total 0.000 Sub Total 0.492 Sub Total 0.492
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 0 0 16.920 0.704 16.920 0.704 0.88
03 April 2014
29 September 2014
HARGA SATUAN
SATU
AN
VOLUME
Rp. 1.097.600.000,-
NO. BULAN LALUJUMLAH HARGA BOBOT %
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
BULAN INIPEKERJAANREALISASI BULANAN
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 1
S.D. BULAN INI
PEKERJAAN :
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 1 Page 23 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 0 0 69.200 4.883 69.200 4.883 69.44924
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 0 0 0 0 0 0
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 0 0 0 0 0 0
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 0 0 0 0
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 0 0 0 0
125,053,581.86Rp 12.533 Sub Total 0.000 Sub Total 5.587 Sub Total 5.587
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 0 0 1.570 0.104 1.570 0.104 1.815
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 0 0 5.900 0.775 5.900 0.775
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 0 0 1234.17 2.387 1234.170 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 0 0 24.850 0.548 24.850 0.548
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 0 0 2.820 0.370 2.820 0.370
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 0 0 348.000 0.673 348.000 0.673
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 0 0 28.200 0.353 28.200 0.353 0.3025
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 0 0 0 0 0 0 0.18
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 0 0 120.000 0.232 120.000 0.232 0.4825
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 0 0 0 0 0 0
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 0 0 0 0 0 0
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 0 0 460.000 0.890 460.000 0.890
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 18.000 0.397 18.000 0.397
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 0 0 0 0 0 0
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 0 0 0 0 0 0
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 0 0 0 0 0 0
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 0 0 0.250 0.033 0.250 0.033
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 0 0 49.000 0.095 49.000 0.095 5.274262
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 0 0 5.200 0.115 5.200 0.115
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 0 0 0 0 0 0
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 0 0 0 0 0 0
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 0 0 0 0
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 0 0 0 0 0 0
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 0 0 0 0 0 0
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 0 0 0 0 0 0
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 0 0 0 0 0 0
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 0 0 0 0 0 0
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 0 0 0 0 0 0
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 0 0 0 0 0 0
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 0 0 0 0 0 0
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 0 0 0 0 0 0
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 1 Page 24 of 150
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0 0 0 0 0 0
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 0 0 0 0 0 0
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0 0 0 0 0 0
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 0 0 0 0
323,453,547.04Rp 32.416 Sub Total 0.000 Sub Total 6.970 Sub Total 6.970
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 0 0 0 0
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 0 0 0 0
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 0 0 0 0
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 0 0 0 0
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 0 0 0 0 0 0
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 1 Page 25 of 150
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 0 0 0 0 0 0
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VIII. Pekerjaan Pengecatan
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 0 0 0 0
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 0 0 0 0 0 0
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 0 0 0 0 0 0
7,701,730.00Rp 0.772 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 1 Page 26 of 150
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 0.000 Total 13.282 Total 13.282
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
J U M L A H T O T A L P E K E R J A A N
TOTAL PEKERJAAN AKHIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 1 Page 27 of 150
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 1 Page 28 of 150
1.93
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 1 Page 29 of 150
Program Kegiatan : Peningkatan Sarana dan Prasarana Aparatur
Pekerjaan : Pembangunan Gedung Kantor Dinas Pemuda dan Olahraga Kabupaten Poso
Lokasi : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso
Tahun Anggaran : 2014
Min
ggu
1
Min
ggu
2
Min
ggu
3
Min
ggu
4
Min
ggu
5
Min
ggu
6
Min
ggu
7
Min
ggu
8
Min
ggu
9
Min
ggu
10
Min
ggu
11
Min
ggu
12
Min
ggu
13
Min
ggu
14
Min
ggu
15
Min
ggu
16
Min
ggu
17
Min
ggu
18
Min
ggu
19
Min
ggu
20
Min
ggu
21
Min
ggu
22
Min
ggu
23
Min
ggu
24
Min
ggu
25
I Pekerjaan Pendahuluan 2,326,140.00Rp 0.233 0.23100
0.233 0.000
II Pekerjaan Tanah dan Pasir 30,738,969.50Rp 3.081 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 3.081 0.000
III Pekerjaan Pasangan Batu 125,053,581.86Rp 12.533 2.09 2.09 2.09 2.09 2.09 2.09 12.533 0.000
IV Pekerjaan Cor dan Beton 323,453,547.04Rp 32.416 0.48 0.97 0.48 0.71 1.43 1.25 1.25 1.25 2.86 4.43 4.43 4.43 3.08 1.25 4.12 32.416 0.000
V Pekerjaan Plesteran/Acian dan Keramik 138,242,621.13Rp 13.854 2.31 2.31 2.31 2.31 2.31 2.31 13.854 0.000
VI Pekerjaan Rangka Kap Baja Ringan dan Plafon 230,365,475.85Rp 23.087 3.85 3.85 3.85 3.85 3.85 3.85 50 23.087 0.000
VII Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca 71,463,355.79Rp 7.162 2.15 2.15 2.15 0.72 7.162 0.000
VIII Pekerjaan Pengecatan 38,959,933.07Rp 3.905 1.95 1.95 3.905 0.000
IX Pekerjaan Instalasi Listrik 11,760,000.00Rp 1.179 1.18 1.179 0.000X
X 7,701,730.00Rp 0.772 0.39 0.39 0.772 0.000XI
XI Pekerjaan Kunci dan Penggantung 11,055,869.25Rp 1.108 1.11 1.108
XII 6,700,000.00Rp 0.671 0.34 0.34 0.671 0.000
T O T A L 997,821,223.49Rp 100.000
100.000
RENCANA PER MINGGU % % 0.23 0.87 1.35 2.96 3.19 3.90 3.73 3.73 5.87 5.01 6.58 4.43 4.43 3.08 5.10 7.97 7.34 6.16 6.16 6.16 4.26 4.65 1.10 1.44 0.34
RENCANA KUMULATIF % 0.000 0.23 1.10 2.45 5.41 8.60 12.50 16.22 19.95 25.82 30.83 37.41 41.83 46.26 49.34 54.44 62.40 69.74 75.90 82.05 88.21 92.47 97.12 98.22 99.66 100.0
REALISASI PER MINGGU % 0.23 2.05 3.38 7.62
REALISASI KUMULATIF % 0.000 0.23 2.28 5.66 13.28
DEVIASI % 0.00 +1.18 +3.21 +7.87
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan SupervisiPembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Pekerjaan Sanitasi
Pekerjaan Akhir
April 2014 Mei 2014 Juni 2014 Juli 2014
HARGA PEKERJAAN
SCHEDULE DAN REALISASI PELAKSANAAN PEKERJAAN PEMBANGUNAN GEDUNG KANTOR DISPORA KABUPATEN POSO
NO. U R A I A NBOBOT
(%)
WAKTU PELAKSANAAN
KET.
Agustus 2014 September 2014
6/19/2013 #VALUE!
182 25.57142857 179
12/18/2013 12/15/2013 #VALUE!
0 6/19/2013 6/27/2013 7/4/2013 7/11/2013 7/18/2013 7/25/2013 8/1/2013 8/8/2013 8/15/2013 8/22/2013 8/29/2013 9/5/2013 9/12/2013 9/19/2013 9/26/2013 10/3/2013 10/10/2013 10/17/2013 10/24/2013 10/31/2013 11/7/2013 11/14/2013 11/21/2013 11/28/2013 12/5/2013
6/26/2013 7/3/2013 7/10/2013 7/17/2013 7/24/2013 7/31/2013 8/7/2013 8/14/2013 8/21/2013 8/28/2013 9/4/2013 9/11/2013 9/18/2013 9/25/2013 10/2/2013 10/9/2013 10/16/2013 10/23/2013 10/30/2013 11/6/2013 11/13/2013 11/20/2013 11/27/2013 12/4/2013 12/11/2013
0.18
0.3025
0.965
5.007 1.429
1.25187
#REF!
1.858
Nama Program : Peningkatan Sarana dan Prasarana Aparatur
Nama Kegiatan : Pembangunan Gedung Kantor
Nama Pekerjaan : Renovasi Gedung Kantor Pengadilan Agama Poso Tahap ILokasi : Poso
Tahun Anggaran : 2013
Awal
Proyek
Ming
gu
1
Ming
gu
2
Ming
gu
3
Ming
gu
4
Ming
gu
5
Ming
gu
6
Ming
gu
7
Ming
gu
8
Ming
gu
9
Min
ggu
10
Min
ggu
11
Min
ggu
12
Min
ggu
13
Min
ggu
14
Min
ggu
15
Min
ggu
16
Min
ggu
17
Min
ggu
18
Min
ggu
19
Min
ggu
20
Min
ggu
21
Min
ggu
22
Min
ggu
23
Min
ggu
24
I PEKERJAAN PERSIAPAN 25,573,110.00Rp 2.330Minggu 3 Mei
20131.165 1.165 100%
II PEKERJAAN TANAH DAN PASIR 140,019,786.72Rp 12.757Minggu 1 Juni
20131.595 1.595 1.595 1.595 1.595 1.595 1.595 1.595
III PEKERJAAN PASANGAN 239,058,368.76Rp 21.780Minggu 3 Juni
20132.178 2.178 2.178 2.178 2.178 2.178 2.178 2.178 2.178 2.178
IV PEKERJAAN BETON 686,946,971.63Rp 62.586Minggu 3 Juni
20133.682 3.682 3.682 3.682 3.682 3.682 3.682 3.682 3.682 3.682 3.682 3.682 3.682 3.682 3.682 3.682 3.682
V PEKERJAAN AKHIR DAN PEKERJAAN LAIN-LAIN 6,000,000.00Rp 0.547Minggu 4
Oktober 20130.182 0.182 0.182
TOTAL 1,097,598,237.11Rp 100.000
1.165 1.165 1.595 1.595 7.454 7.454 7.454 7.454 7.454 7.454 5.860 5.860 5.860 5.860 3.682 3.682 3.682 3.682 3.682 3.682 3.682 0.182 0.182 0.182
1.165 2.330 3.925 5.519 12.973 20.428 27.882 35.336 42.790 50.244 56.104 61.963 67.823 73.682 77.364 81.046 84.727 88.409 92.090 95.772 99.453 99.636 99.818 100
1.915 9.024
1.915 10.939
0.000 8.609D e v i a s i
AGUSTUS 2013
Harga Pekerjaan (Rp) Bobot (%)
MEI 2013 OKTOBER 2013
R e n c a n a K u m u l a t i f
0%
R e a l i s a s i p e r M i n g g u
JULI 2013
KET.
R e a l i s a s i K u m u l a t i f
NOP. 2013
TIME SCHEDULE DAN REALISASI PEKERJAAN RENOVASI GEDUNG KANTOR PENGADILAN AGAMA POSO TAHAP IBULAN 1 - MEI 2013
No Jenis Pekerjaan
R e n c a n a p e r M i n g g u
JUNI 2013 SEPTEMBER 2013
Disetujui Oleh:
Pengelola Teknis ProyekBIDANG CIPTA KARYA DINAS PU KAB. POSO
Yoppy Soleman, S.T., M.T.NIP. 19710731 200903 1 001
Diperiksa Oleh:Konsultan Pengawas
CV. MATRA GRIYA MANDIRI
Ir. Zainal Djamal, IPPDirektur/Team Leader
Dibuat Oleh:Kontraktor Pelaksana
CV. BINA PRIMA KARYA
Saadah, S.E.MuchlisDirektur
Direktur/Team Leader
Dibuat Oleh:
Kontraktor PelaksanaCV. BINA PRIMA KARYA
Muchlis Saadah, S.E.Direktur
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 01 Mei 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 08 Mei 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 87.600 0.241 14.920 0.041 102.520 0.282 54.2
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 36.300 0.048 5.300 0.007 41.600 0.055
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 0 0 110.000 1.502 110.000 1.502 37.92097
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 0 0 38.000 0.597 38.000 0.597
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.250 0.083 0.575 0.009 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 0.492 Sub Total 2.156 Sub Total 2.648
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 16.920 0.704 2.303 0.096 19.223 0.800 1.00
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 5
BOBOT %
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
PEKERJAAN :
JUMLAH HARGA
03 April 2014
29 September 2014
HARGA SATUAN
SATU
AN
VOLUME
Rp. 1.097.600.000,-
REALISASI MINGGUAN
NO. MINGGU LALU MINGGU INI S.D. MINGGU INIPEKERJAAN
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 5 Page 37 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 69.200 4.883 9.700 0.684 78.900 5.567 78.9
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 0 0 32.200 0.363 32.200 0.363
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 0 0 5.500 0.069 5.500 0.069
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 0 0 0 0 32.39995
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 0 0 0 0
125,053,581.86Rp 12.533 Sub Total 5.587 Sub Total 1.213 Sub Total 6.800
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.570 0.104 0.245 0.016 1.815 0.120 0
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 5.900 0.775 0.971 0.128 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 24.850 0.548 1.550 0.034 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 2.820 0.370 1.470 0.193 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 348.000 0.673 202.42 0.391 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 28.200 0.353 14.700 0.184 42.900 0.537 42.9
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 0 0 2.256 0.296 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 120.000 0.232 199.08 0.385 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 0 0 37.600 0.471 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 0 0 4.478 0.588 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 460.000 0.890 380.87 0.736 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 18.000 0.397 54.000 1.191 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 0 0 0 0 0 0
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 0 0 0 0 0 0
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 0 0 0 0 0 0
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 0.250 0.033 0 0 0.250 0.033
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 49.000 0.095 0 0 49.000 0.095
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 5.200 0.115 0 0 5.200 0.115
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 0 0 0 0 0 0
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 0 0 0 0 0 0
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 0 0 0 0
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 0 0 0 0 0 0
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 0 0 0 0 0 0
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 0 0 0 0 0 0
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 0 0 0 0 0 0
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 0 0 0 0 0 0
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 0 0 0 0 0 0
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 0 0 0 0 0 0
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 0 0 0 0 0 0
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 0 0 0 0 0 0
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0 0 0.050 0.007 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 0 0 0 0 0 0
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0 0 0 0 0 0
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 5 Page 38 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 0 0 0 0
323,453,547.04Rp 32.416 Sub Total 6.970 Sub Total 4.621 Sub Total 11.591
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 0 0 0 0
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 0 0 0 0
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 0 0 0 0
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 0 0 0 0
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 0 0 0 0 0 0
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 0 0 0 0 0 0
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
TOTAL PEKERJAAN COR DAN BETON
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 5 Page 39 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 0 0 0 0
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 0 0 0 0 0 0
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 0 0 0 0 0 0
7,701,730.00Rp 0.772 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 13.282 Total 7.990 Total 21.272
TOTAL PEKERJAAN AKHIR
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN PENGECATAN
J U M L A H T O T A L P E K E R J A A N
TOTAL PEKERJAAN SANITASI
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 5 Page 40 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 5 Page 41 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 08 Mei 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 15 Mei 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282 54.2
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 41.600 0.055 6.000 0.008 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 110.000 1.502 0 0 110.000 1.502 0
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 38.000 0.597 0 0 38.000 0.597
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 2.648 Sub Total 0.008 Sub Total 2.656
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800 1.00
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 6
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 6 Page 42 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567 78.9
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 32.200 0.363 88.100 0.994 120.300 1.357
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 5.500 0.069 15.000 0.189 20.500 0.258 88.36
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 0 0 0 0 50.4834
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 0 0 0 0
125,053,581.86Rp 12.533 Sub Total 6.800 Sub Total 1.183 Sub Total 7.982
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120 0
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537 42.9
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 0 0 0 0 0 0
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 0 0 0 0 0 0
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 0 0 0 0 0 0
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 0.250 0.033 0.750 0.098 1.000 0.131
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 49.000 0.095 147.000 0.284 196.000 0.379 15.82278
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 5.200 0.115 15.800 0.349 21.000 0.463
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 0 0 0 0 0 0
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 0 0 0 0 0 0
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 0 0 0 0
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 0 0 0 0 0 0
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 0 0 0 0 0 0
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 0 0 0 0 0 0
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 0 0 0 0 0 0
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 0 0 0 0 0 0
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 0 0 0 0 0 0
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 0 0 0 0 0 0
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 0 0 0 0 0 0
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 0 0 0 0 0 0
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 0 0 0 0 0 0
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0 0 0 0 0 0
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 6 Page 43 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 0 0 0 0
323,453,547.04Rp 32.416 Sub Total 11.591 Sub Total 0.731 Sub Total 12.322
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 0 0 0 0
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 0 0 0 0
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 0 0 0 0
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 0 0 0 0
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 0 0 0 0 0 0
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 0 0 0 0 0 0
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 6 Page 44 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 0 0 0 0
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 0 0 0 0 0 0
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 0 0 0 0 0 0
7,701,730.00Rp 0.772 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 21.272 Total 1.922 Total 23.194
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 6 Page 45 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 6 Page 46 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 15 Mei 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 22 Mei 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282 54.2
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 110.000 1.502 0 0 110.000 1.502 0
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 38.000 0.597 0 0 38.000 0.597
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 2.656 Sub Total 0.000 Sub Total 2.656
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800 1.00
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 7
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 7 Page 47 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567 78.9
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 120.300 1.357 47.130 0.532 167.430 1.889 8.00
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 20.500 0.258 8.000 0.101 28.500 0.358 88.36
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 0 0 0 0 26.92448
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 0 0 0 0
125,053,581.86Rp 12.533 Sub Total 7.982 Sub Total 0.632 Sub Total 8.615
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120 0
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537 42.9
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 0 0 0 0 0 0
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 0 0 0 0 0 0
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 0 0 0 0 0 0
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.000 0.131 0 0 1.000 0.131
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 196.000 0.379 49.34 0.095 245.340 0.474 0
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 21.000 0.463 0 0 21.000 0.463
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 0 0 0 0 0 0
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 0 0 154.600 0.299 154.600 0.299
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 10.800 0.238 10.800 0.238
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 0 0 0 0 0 0
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 0 0 54.000 0.104 54.000 0.104
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 0 0 2.460 0.054 2.460 0.054
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 0 0 0 0 0 0
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 0 0 0 0 0 0
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 0 0 0 0 0 0
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 0 0 0.220 0.029 0.220 0.029
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 0 0 24.000 0.046 24.000 0.046
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 0 0 3.800 0.084 3.800 0.084
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 0 0 0 0 0 0
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0 0 0 0 0 0
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 7 Page 48 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 0 0 0 0
323,453,547.04Rp 32.416 Sub Total 12.322 Sub Total 0.950 Sub Total 13.273
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 0 0 0 0
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 0 0 0 0
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 0 0 0 0
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 0 0 0 0
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 0 0 1.150 0.693 1.150 0.693
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 0 0 0 0 0 0
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 0.000 Sub Total 0.693 Sub Total 0.693
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 7 Page 49 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 0 0 0 0
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 0 0 10.000 0.043 10.000 0.043
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 0 0 10.000 0.057 10.000 0.057
7,701,730.00Rp 0.772 Sub Total 0.000 Sub Total 0.100 Sub Total 0.100
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 23.194 Total 2.376 Total 25.569
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 7 Page 50 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 7 Page 51 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 22 Mei 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 29 Mei 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282 54.2
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 110.000 1.502 0 0 110.000 1.502 0
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 38.000 0.597 0 0 38.000 0.597
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 2.656 Sub Total 0.000 Sub Total 2.656
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800 1.00
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 8
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 8 Page 52 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567 78.9
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 167.430 1.889 44.100 0.498 211.530 2.387
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 28.500 0.358 9.500 0.119 38.000 0.478
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 0 0 0 0
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 0 0 0 0
125,053,581.86Rp 12.533 Sub Total 8.615 Sub Total 0.617 Sub Total 9.232
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120 0
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537 42.9
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 0 0 0 0 0 0
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 0 0 0 0 0 0
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 0 0 0 0 0 0
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.000 0.131 0.100 0.013 1.100 0.144
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 21.000 0.463 1.800 0.040 22.800 0.503
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 0 0 0 0 0 0
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 154.600 0.299 175.000 0.338 329.600 0.637
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 10.800 0.238 12.240 0.270 23.040 0.508
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 0 0 0 0 0 0
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 54.000 0.104 35.000 0.068 89.000 0.172
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 2.460 0.054 3.200 0.071 5.660 0.125
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 0 0 0 0 0 0
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 0 0 0 0 0 0
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 0 0 0 0 0 0
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 0.220 0.029 0.510 0.067 0.730 0.096
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 24.000 0.046 54.000 0.104 78.000 0.151
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 3.800 0.084 8.600 0.190 12.400 0.274
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 0 0 0 0 0 0
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0 0 0 0 0 0
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 8 Page 53 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 0 0 0 0
323,453,547.04Rp 32.416 Sub Total 13.273 Sub Total 1.161 Sub Total 14.433
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 0 0 0 0
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 0 0 0 0
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 0 0 0 0
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 0 0 0 0
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 1.150 0.693 1.176 0.709 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 0 0 6.000 0.571 6.000 0.571
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 0.693 Sub Total 1.280 Sub Total 1.973
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 8 Page 54 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 0 0 0 0
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 10.000 0.043 0 0 10.000 0.043
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 10.000 0.057 0 0 10.000 0.057
7,701,730.00Rp 0.772 Sub Total 0.100 Sub Total 0.000 Sub Total 0.100
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 25.569 Total 3.058 Total 28.627
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 8 Page 55 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 8 Page 56 of 150
LAPORAN BULANAN KEDUA - MEI 2014
PROGRAM :
Bulan ke
Kamis, 01 Mei 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Kamis, 29 Mei 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 87.600 0 14.920 0.041 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 36.300 0 11.300 0.015 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 0 0 110.000 1.502 110.000 1.502
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 0 0 38.000 0.597 38.000 0.597
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.250 0 0.575 0.009 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 0.492 Sub Total 2.164 Sub Total 2.656
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 16.920 0.704 2.301 0.096 19.221 0.800
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
JUMLAH HARGA BOBOT %REALISASI BULANAN
BULAN LALU BULAN INI S.D. BULAN INI
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 2
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 2 Page 57 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 69.200 4.883 9.700 0.684 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 0 0 211.530 2.387 211.530 2.387
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 0 0 38.000 0.478 38.000 0.478
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 0 0 0 0
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 0 0 0 0
125,053,581.86Rp 12.533 Sub Total 5.587 Sub Total 3.645 Sub Total 9.232
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.570 0.104 0.245 0.016 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 5.900 0.775 0.972 0.128 6.872 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.170 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 24.850 0.548 1.550 0.034 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 2.820 0.370 1.470 0.193 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 348.000 0.673 202.420 0.391 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 28.200 0.353 14.700 0.184 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 0 0 2.256 0.296 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 120.000 0.232 199.080 0.385 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 0 0 37.600 0.471 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 0 0 4.478 0.588 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 460.000 0.890 380.870 0.736 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 18.000 0.397 54.000 1.191 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 0 0 0 0 0 0
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 0 0 0 0 0 0
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 0 0 0 0 0 0
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 0.250 0.033 0.850 0.112 1.100 0.144
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 49.000 0.095 196.340 0.380 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 5.200 0.115 17.600 0.388 22.800 0.503
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 0 0 0 0 0 0
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 0 0 329.600 0.637 329.600 0.637
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 0 0 23.040 0.508 23.040 0.508
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 0 0 0 0 0 0
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 0 0 89.000 0.172 89.000 0.172
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 0 0 5.660 0.125 5.660 0.125
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 0 0 0 0 0 0
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 0 0 0 0 0 0
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 0 0 0 0 0 0
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 0 0 0.730 0.096 0.730 0.096
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 0 0 78.000 0.151 78.000 0.151
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 0 0 12.400 0.274 12.400 0.274
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 2 Page 58 of 150
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0 0 0.050 0.007 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 0 0 0 0 0 0
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0 0 0 0 0 0
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 0 0 0 0
323,453,547.04Rp 32.416 Sub Total 6.970 Sub Total 7.463 Sub Total 14.434
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 0 0 0 0
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 0 0 0 0
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 0 0 0 0
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 0 0 0 0
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 0 0 2.326 1.402 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 2 Page 59 of 150
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 0 0 6.000 0.571 6.000 0.571
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 0.000 Sub Total 1.973 Sub Total 1.973
VIII. Pekerjaan Pengecatan
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 0 0 0 0
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 0 0 10.000 0.043 10.000 0.043
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 0 0 10.000 0.057 10.000 0.057
7,701,730.00Rp 0.772 Sub Total 0.000 Sub Total 0.100 Sub Total 0.100
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 2 Page 60 of 150
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 13.282 Total 15.345 Total 28.627
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
J U M L A H T O T A L P E K E R J A A N
TOTAL PEKERJAAN AKHIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 2 Page 61 of 150
Program Kegiatan : Peningkatan Sarana dan Prasarana Aparatur
Pekerjaan : Pembangunan Gedung Kantor Dinas Pemuda dan Olahraga Kabupaten Poso
Lokasi : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso
Tahun Anggaran : 2014
Min
ggu
1
Min
ggu
2
Min
ggu
3
Min
ggu
4
Min
ggu
5
Min
ggu
6
Min
ggu
7
Min
ggu
8
Min
ggu
9
Min
ggu
10
Min
ggu
11
Min
ggu
12
Min
ggu
13
Min
ggu
14
Min
ggu
15
Min
ggu
16
Min
ggu
17
Min
ggu
18
Min
ggu
19
Min
ggu
20
Min
ggu
21
Min
ggu
22
Min
ggu
23
Min
ggu
24
Min
ggu
25
I Pekerjaan Pendahuluan 2,326,140.00Rp 0.233 0.23100
0.233
II Pekerjaan Tanah dan Pasir 30,738,969.50Rp 3.081 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39 3.081
III Pekerjaan Pasangan Batu 125,053,581.86Rp 12.533 2.09 2.09 2.09 2.09 2.09 2.09 12.533
IV Pekerjaan Cor dan Beton 323,453,547.04Rp 32.416 0.48 0.97 0.48 0.71 1.43 1.25 1.25 1.25 2.86 4.43 4.43 4.43 3.08 1.25 4.12 32.416
V Pekerjaan Plesteran/Acian dan Keramik 138,242,621.13Rp 13.854 2.31 2.31 2.31 2.31 2.31 2.31 13.854
VI Pekerjaan Rangka Kap Baja Ringan dan Plafon 230,365,475.85Rp 23.087 3.85 3.85 3.85 3.85 3.85 3.85 50 23.087
VII Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca 71,463,355.79Rp 7.162 2.15 2.15 2.15 0.72 7.162
VIII Pekerjaan Pengecatan 38,959,933.07Rp 3.905 1.95 1.95 3.905
IX Pekerjaan Instalasi Listrik 11,760,000.00Rp 1.179 1.18 1.179X
X 7,701,730.00Rp 0.772 0.39 0.39 0.772XI
XI Pekerjaan Kunci dan Penggantung 11,055,869.25Rp 1.108 1.11 1.108
XII 6,700,000.00Rp 0.671 0.34 0.34 0.671
T O T A L 997,821,223.49Rp 100.000
100.000
RENCANA PER MINGGU % % 0.23 0.87 1.35 2.96 3.19 3.90 3.73 3.73 5.87 5.01 6.58 4.43 4.43 3.08 5.10 7.97 7.34 6.16 6.16 6.16 4.26 4.65 1.10 1.44 0.34
RENCANA KUMULATIF % 0.000 0.23 1.10 2.45 5.41 8.60 12.50 16.22 19.95 25.82 30.83 37.41 41.83 46.26 49.34 54.44 62.40 69.74 75.90 82.05 88.21 92.47 97.12 98.22 99.66 100.0
REALISASI PER MINGGU % 0.23 2.05 3.38 7.62 7.99 1.92 2.38 3.06
REALISASI KUMULATIF % 0.000 0.23 2.28 5.66 13.28 21.27 23.19 25.57 28.63
DEVIASI % 0.00 +1.18 +3.21 +7.87 +12.68 +10.70 +9.35 +8.68
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan SupervisiPembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Pekerjaan Akhir
SCHEDULE DAN REALISASI PELAKSANAAN PEKERJAAN PEMBANGUNAN GEDUNG KANTOR DISPORA KABUPATEN POSO
NO. U R A I A N HARGA PEKERJAANBOBOT
(%)
WAKTU PELAKSANAAN
KET.
April 2014 Mei 2014 Juni 2014 Juli 2014 Agustus 2014 September 2014
Pekerjaan Sanitasi
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 29 Mei 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 05 Juni 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282 54.2
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 110.000 1.502 0 0 110.000 1.502 0
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 38.000 0.597 0 0 38.000 0.597
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 2.656 Sub Total 0.000 Sub Total 2.656
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800 1.00
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 9
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 9 Page 63 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567 78.9
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 211.530 2.387 83.015 0.937 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 38.000 0.478 12.000 0.151 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 0 0 0 0
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 0 0 0 0
125,053,581.86Rp 12.533 Sub Total 9.232 Sub Total 1.088 Sub Total 10.319
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120 0
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537 42.9
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 0 0 0 0 0 0
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 0 0 106.000 0.205 106.000 0.205
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 0 0 7.400 0.163 7.400 0.163
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.100 0.144 0.151 0.020 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 22.800 0.503 3.600 0.079 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 0 0 7.425 0.975 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 329.600 0.637 298.0 0.576 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 23.040 0.508 48.96 1.080 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 0 0 1.584 0.208 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 89.000 0.172 62.00 0.120 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 5.660 0.125 18.980 0.419 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 0 0 11.764 1.544 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 0 0 1175.000 2.272 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 0 0 70.660 2.642 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 0.730 0.096 0.412 0.054 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 78.000 0.151 42.000 0.081 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 12.400 0.274 6.640 0.146 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 0 0 45.000 0.087 45.000 0.087
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0 0 0 0 0 0
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 9 Page 64 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 0 0 0 0
323,453,547.04Rp 32.416 Sub Total 14.433 Sub Total 10.673 Sub Total 25.106
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 0 0 0 0
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 0 0 0 0
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 0 0 0 0
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 0 0 0 0
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 6.000 0.571 0 0 6.000 0.571
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 1.973 Sub Total 0.000 Sub Total 1.973
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 9 Page 65 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 0 0 0 0
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 10.000 0.043 5.000 0.021 15.000 0.064
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 10.000 0.057 5.000 0.028 15.000 0.085
7,701,730.00Rp 0.772 Sub Total 0.100 Sub Total 0.050 Sub Total 0.149
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 28.627 Total 11.810 Total 40.437
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 9 Page 66 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 9 Page 67 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 05 Juni 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 12 Juni 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282 54.2
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 110.000 1.502 0 0 110.000 1.502 0
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 38.000 0.597 0 0 38.000 0.597
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 2.656 Sub Total 0.000 Sub Total 2.656
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800 1.00
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 10
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 10 Page 68 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567 78.9
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 0 0 0 0
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 0 0 0 0
125,053,581.86Rp 12.533 Sub Total 10.319 Sub Total 0.000 Sub Total 10.319
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120 0
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537 42.9
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 0 0 4.710 0.618 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 106.000 0.205 314.000 0.607 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 7.400 0.163 59.800 1.319 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.251 0.164 0 0 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 45.000 0.087 0 0 45.000 0.087
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0 0 0 0 0 0
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 10 Page 69 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 0 0 0 0
323,453,547.04Rp 32.416 Sub Total 25.106 Sub Total 2.545 Sub Total 27.651
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 0 0 0 0
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 0 0 0 0
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 0 0 0 0
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 0 0 0 0
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 6.000 0.571 0 0 6.000 0.571
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 1.973 Sub Total 0.000 Sub Total 1.973
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 10 Page 70 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 0 0 0 0
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 15.000 0.064 0 0 15.000 0.064
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 15.000 0.085 0 0 15.000 0.085
7,701,730.00Rp 0.772 Sub Total 0.149 Sub Total 0.000 Sub Total 0.149
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 40.437 Total 2.545 Total 42.982
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 10 Page 71 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 10 Page 72 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 12 Juni 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 19 Juni 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282 54.2
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 110.000 1.502 0 0 110.000 1.502 0
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 38.000 0.597 0 0 38.000 0.597
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 2.656 Sub Total 0.000 Sub Total 2.656
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800 1.00
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 11
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 11 Page 73 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567 78.9
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 25.200 0.284 25.200 0.284
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 3.800 0.048 3.800 0.048
125,053,581.86Rp 12.533 Sub Total 10.319 Sub Total 0.332 Sub Total 10.652
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120 0
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537 42.9
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.251 0.164 0 0 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 45.000 0.087 0 0 45.000 0.087
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0 0 10.000 0.374 10.000 0.374
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 11 Page 74 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 0 0 0 0
323,453,547.04Rp 32.416 Sub Total 27.651 Sub Total 0.374 Sub Total 28.025
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 0 0 0 0
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 0 0 0 0
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 96.400 2.315 96.4000 2.315
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 0 0 0 0
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 2.315 Sub Total 2.315
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 6.000 0.571 0 0 6.000 0.571
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 1.973 Sub Total 0.000 Sub Total 1.973
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 11 Page 75 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 30.000 0.056 30.000 0.056
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 15.000 0.064 0 0 15.000 0.064
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 15.000 0.085 0 0 15.000 0.085
7,701,730.00Rp 0.772 Sub Total 0.149 Sub Total 0.056 Sub Total 0.205
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 42.982 Total 3.077 Total 46.059
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 11 Page 76 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 11 Page 77 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 19 Juni 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 26 Juni 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 110.000 1.502 22.336 0.305 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 38.000 0.597 7.621 0.120 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 2.656 Sub Total 0.425 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 12
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 12 Page 78 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 25.200 0.284 84.100 0.949 109.300 1.233
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 3.800 0.048 12.500 0.157 16.300 0.205
125,053,581.86Rp 12.533 Sub Total 10.652 Sub Total 1.106 Sub Total 11.758
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.251 0.164 0 0 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 45.000 0.087 105.000 0.203 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 10.000 0.374 5.000 0.187 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 0 0 0 0
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 12 Page 79 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0 0 4.500 0.298 4.500 0.298
323,453,547.04Rp 32.416 Sub Total 28.025 Sub Total 0.688 Sub Total 28.713
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 46.500 0.173 46.500 0.173
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 271.400 0.936 271.400 0.936
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 1.109 Sub Total 1.109
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 96.400 2.315 108.840 2.613 205.240 4.928
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 99.700 1.118 99.700 1.118
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 2.315 Sub Total 3.731 Sub Total 6.046
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 6.000 0.571 0 0 6.000 0.571
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 1.973 Sub Total 0.000 Sub Total 1.973
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 12 Page 80 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 30.000 0.056 0 0 30.000 0.056
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 15.000 0.064 0 0 15.000 0.064
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 15.000 0.085 0 0 15.000 0.085
7,701,730.00Rp 0.772 Sub Total 0.205 Sub Total 0.000 Sub Total 0.205
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 46.058 Total 7.060 Total 53.118
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 12 Page 81 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 12 Page 82 of 150
LAPORAN BULANAN KETIGA - JUNI 2014
PROGRAM :
Bulan ke
Kamis, 29 Mei 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Kamis, 26 Juni 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0.000 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 110.000 1.502 22 0.305 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 38.000 0.597 8 0.120 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 2.656 Sub Total 0.425 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.221 0.800 0 0 19.221 0.800
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
JUMLAH HARGA BOBOT %REALISASI BULANAN
BULAN LALU BULAN INI S.D. BULAN INI
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 3
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 3 Page 83 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 211.530 2.387 83.015 0.937 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 38.000 0.478 12.000 0.151 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 0 0 109.300 1.233 109.300 1.233
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 0 0 16.300 0.205 16.300 0.205
125,053,581.86Rp 12.533 Sub Total 9.232 Sub Total 2.526 Sub Total 11.758
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.872 0.902 0 0 6.873 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.170 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 0 0 4.710 0.618 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 0 0 420.000 0.812 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 0 0 67.200 1.483 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.100 0.144 0.152 0.020 1.252 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 22.800 0.503 3.600 0.079 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 0 0 7.425 0.975 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 329.600 0.637 298 0.576 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 23.040 0.508 49 1.080 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 0 0 1.584 0.208 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 89.000 0.172 62.000 0.120 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 5.660 0.125 18.980 0.419 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 0 0 11.764 1.544 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 0 0 1175.000 2.272 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 0 0 70.660 2.642 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 0.730 0.096 0.413 0.054 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 78.000 0.151 42.000 0.081 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 12.400 0.274 6.640 0.146 19.040 0.420
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 3 Page 84 of 150
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 0.000 0.000 150.000 0.290 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 0.000 0.000 15.000 0.561 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0.000 0.000 0 0 0 0
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0.000 0.000 0 0 0 0
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0.000 0.000 0 0 0 0
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 0.000 0.000 4.500 0.298 4.500 0.298
323,453,547.04Rp 32.416 Sub Total 14.434 Sub Total 14.280 Sub Total 28.713
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 0 0 46.500 0.173 46.500 0.173
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 0 0 271.400 0.936 271.400 0.936
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 0 0 0 0
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 0.000 Sub Total 1.109 Sub Total 1.109
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 0 0 205.240 4.928 205.240 4.928
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 0 0 99.700 1.118 99.700 1.118
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 0 0 0 0
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 0 0 0 0
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 0 0 0 0
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0 0 0 0
230,365,475.85Rp 23.087 Sub Total 0.000 Sub Total 6.046 Sub Total 6.046
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0.000 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 3 Page 85 of 150
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 6.000 0.571 0 0 6.000 0.571
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 1.973 Sub Total 0.000 Sub Total 1.973
VIII. Pekerjaan Pengecatan
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 0 0 0 0
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 0 0 30.000 0.056 30.000 0.056
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 10.000 0.043 5.000 0.021 15.000 0.064
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 10.000 0.057 5.000 0.028 15.000 0.085
7,701,730.00Rp 0.772 Sub Total 0.100 Sub Total 0.106 Sub Total 0.205
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 3 Page 86 of 150
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
997,821,223.49Rp 100 Total 28.627 Total 24.492 Total 53.119
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
J U M L A H T O T A L P E K E R J A A N
TOTAL PEKERJAAN AKHIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 3 Page 87 of 150
Program Kegiatan : Peningkatan Sarana dan Prasarana Aparatur
Pekerjaan : Pembangunan Gedung Kantor Dinas Pemuda dan Olahraga Kabupaten Poso
Lokasi : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso
Tahun Anggaran : 2014
Min
ggu
1
Min
ggu
2
Min
ggu
3
Min
ggu
4
Min
ggu
5
Min
ggu
6
Min
ggu
7
Min
ggu
8
Min
ggu
9
Min
ggu
10
Min
ggu
11
Min
ggu
12
Min
ggu
13
Min
ggu
14
Min
ggu
15
Min
ggu
16
Min
ggu
17
Min
ggu
18
Min
ggu
19
Min
ggu
20
Min
ggu
21
Min
ggu
22
Min
ggu
23
Min
ggu
24
Min
ggu
25
I Pekerjaan Pendahuluan 2,326,140.00Rp 0.233 0.23100
II Pekerjaan Tanah dan Pasir 30,738,969.50Rp 3.081 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39
III Pekerjaan Pasangan Batu 125,053,581.86Rp 12.533 2.09 2.09 2.09 2.09 2.09 2.09
IV Pekerjaan Cor dan Beton 323,453,547.04Rp 32.416 0.48 0.97 0.48 0.71 1.43 1.25 1.25 1.25 2.86 4.43 4.43 4.43 3.08 1.25 4.12
V Pekerjaan Plesteran/Acian dan Keramik 138,242,621.13Rp 13.854 2.31 2.31 2.31 2.31 2.31 2.31
VI Pekerjaan Rangka Kap Baja Ringan dan Plafon 230,365,475.85Rp 23.087 3.85 3.85 3.85 3.85 3.85 3.85 50
VII Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca 71,463,355.79Rp 7.162 2.15 2.15 2.15 0.72
VIII Pekerjaan Pengecatan 38,959,933.07Rp 3.905 1.95 1.95
IX Pekerjaan Instalasi Listrik 11,760,000.00Rp 1.179 1.18X
X 7,701,730.00Rp 0.772 0.39 0.39XI
XI Pekerjaan Kunci dan Penggantung 11,055,869.25Rp 1.108 1.11
XII 6,700,000.00Rp 0.671 0.34 0.34
T O T A L 997,821,223.49Rp 100.000
RENCANA PER MINGGU % % 0.23 0.87 1.35 2.96 3.19 3.90 3.73 3.73 5.87 5.01 6.58 4.43 4.43 3.08 5.10 7.97 7.34 6.16 6.16 6.16 4.26 4.65 1.10 1.44 0.34
RENCANA KUMULATIF % 0.000 0.23 1.10 2.45 5.41 8.60 12.50 16.22 19.95 25.82 30.83 37.41 41.83 46.26 49.34 54.44 62.40 69.74 75.90 82.05 88.21 92.47 97.12 98.22 99.66 100.0
REALISASI PER MINGGU % 0.23 2.05 3.38 7.62 7.99 1.92 2.38 3.06 11.81 2.54 3.08 7.06
REALISASI KUMULATIF % 0.000 0.23 2.28 5.66 13.28 21.27 23.19 25.57 28.63 40.44 42.98 46.06 53.12
DEVIASI % 0.00 +1.18 +3.21 +7.87 +12.68 +10.70 +9.35 +8.68 +14.61 +12.15 +8.65 +11.29
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan SupervisiPembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Mei 2014 Juni 2014 Juli 2014 Agustus 2014 September 2014
Pekerjaan Sanitasi
Pekerjaan Akhir
SCHEDULE DAN REALISASI PELAKSANAAN PEKERJAAN PEMBANGUNAN GEDUNG KANTOR DISPORA KABUPATEN POSO
NO. U R A I A N HARGA PEKERJAANBOBOT
(%)
WAKTU PELAKSANAAN
KET.
April 2014
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 26 Juni 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 03 Juli 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 132.336 1.807 0 0 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 45.621 0.717 0 0 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 3.081 Sub Total 0.000 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 13
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 13 Page 89 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 109.300 1.233 55.800 0.630 165.100 1.863
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 16.300 0.205 8.200 0.103 24.500 0.308
125,053,581.86Rp 12.533 Sub Total 11.758 Sub Total 0.733 Sub Total 12.491
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.251 0.164 0 0 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 150.000 0.290 0 0 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 15.000 0.561 0 0 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 1.277 0.168 1.277 0.168
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 13 Page 90 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 125.000 0.242 125.000 0.242
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 22.400 0.494 22.400 0.494
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 4.500 0.298 5.500 0.364 10.000 0.662
323,453,547.04Rp 32.416 Sub Total 28.713 Sub Total 1.268 Sub Total 29.981
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 46.500 0.173 33.000 0.123 79.500 0.297
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 271.400 0.936 192.000 0.662 463.400 1.598
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 185.200 0.226 185.200 0.226
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 1.109 Sub Total 1.011 Sub Total 2.120
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 205.240 4.928 138.600 3.328 343.840 8.256
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 99.700 1.118 162.500 1.822 262.200 2.940
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 42.100 0.312 42.100 0.312
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 26.000 0.228 26.000 0.228
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 96.000 0.950 96.000 0.950
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 0 0 0 0
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 0.310 0.009 0.310 0.009
230,365,475.85Rp 23.087 Sub Total 6.046 Sub Total 6.650 Sub Total 12.696
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 6.000 0.571 0 0 6.000 0.571
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 1.973 Sub Total 0.000 Sub Total 1.973
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 13 Page 91 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 20.000 0.241 20.000 0.241
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 0.241 Sub Total 0.241
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 30.000 0.056 10.000 0.019 40.000 0.074
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 15.000 0.064 5.000 0.021 20.000 0.086
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 15.000 0.085 5.000 0.028 20.000 0.113
7,701,730.00Rp 0.772 Sub Total 0.205 Sub Total 0.068 Sub Total 0.273
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0.400 0.074 0.400 0.074
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.074 Sub Total 0.074
997,821,223.49Rp 100 Total 53.118 Total 10.044 Total 63.163
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 13 Page 92 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 13 Page 93 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 03 Juli 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 10 Juli 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 132.336 1.807 0 0 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 45.621 0.717 0 0 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 3.081 Sub Total 0.000 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 14
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 14 Page 94 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 165.100 1.863 3.178 0.036 168.278 1.899
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 24.500 0.308 0.500 0.006 25.000 0.314
125,053,581.86Rp 12.533 Sub Total 12.491 Sub Total 0.042 Sub Total 12.533
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.251 0.164 0 0 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 150.000 0.290 0 0 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 15.000 0.561 0 0 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 1.277 0.168 0 0 1.277 0.168
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 14 Page 95 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 125.000 0.242 0 0 125.000 0.242
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 22.400 0.494 0 0 22.400 0.494
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 10.000 0.662 0 0 10.000 0.662
323,453,547.04Rp 32.416 Sub Total 29.981 Sub Total 0.000 Sub Total 29.981
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 79.500 0.297 22.700 0.085 102.200 0.381
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 463.400 1.598 133.500 0.460 596.900 2.058
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 185.200 0.226 409.000 0.498 594.200 0.724
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 0 0 0 0
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 0 0 0 0
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 2.120 Sub Total 1.043 Sub Total 3.163
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 343.840 8.256 124.600 2.992 468.440 11.248
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 262.200 2.940 191.200 2.144 453.400 5.084
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 42.100 0.312 28.100 0.208 70.200 0.520
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 26.000 0.228 88.000 0.772 114.000 1.001
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 96.000 0.950 144.000 1.425 240.000 2.376
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 74.000 0.265 74.000 0.265
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0.310 0.009 0 0 0.310 0.009
230,365,475.85Rp 23.087 Sub Total 12.696 Sub Total 7.807 Sub Total 20.503
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 6.000 0.571 4.000 0.381 10.000 0.952
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 1.973 Sub Total 0.381 Sub Total 2.354
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 14 Page 96 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 0 0 0 0
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 0 0 0 0
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 20.000 0.241 12.000 0.144 32.000 0.385
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 0 0 0 0
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.241 Sub Total 0.144 Sub Total 0.385
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 40.000 0.074 0 0 40.000 0.074
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 0 0 0 0
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 0 0 0 0
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 0 0 0 0
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 20.000 0.086 0 0 20.000 0.086
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 20.000 0.113 0 0 20.000 0.113
7,701,730.00Rp 0.772 Sub Total 0.273 Sub Total 0.000 Sub Total 0.273
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 0 0 0 0
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0.400 0.074 0.100 0.019 0.500 0.093
6,700,000.00Rp 0.671 Sub Total 0.074 Sub Total 0.019 Sub Total 0.093
997,821,223.49Rp 100 Total 63.163 Total 9.436 Total 72.598
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 14 Page 97 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 14 Page 98 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Jumat, 10 Juli 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Jumat, 17 Juli 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 132.336 1.807 0 0 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 45.621 0.717 0 0 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 3.081 Sub Total 0.000 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 15
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 15 Page 99 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 168.278 1.899 0 0 168.278 1.899
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 25.000 0.314 0 0 25.000 0.314
125,053,581.86Rp 12.533 Sub Total 12.533 Sub Total 0.000 Sub Total 12.533
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.251 0.164 0 0 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 150.000 0.290 0 0 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 15.000 0.561 0 0 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 1.277 0.168 0 0 1.277 0.168
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 15 Page 100 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 125.000 0.242 0 0 125.000 0.242
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 22.400 0.494 0 0 22.400 0.494
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 10.000 0.662 0 0 10.000 0.662
323,453,547.04Rp 32.416 Sub Total 29.981 Sub Total 0.000 Sub Total 29.981
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 102.200 0.381 26.700 0.100 128.900 0.481
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 596.900 2.058 135.600 0.468 732.500 2.526
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 0 0 0 0
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 594.200 0.724 367.300 0.447 961.500 1.171
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 12.800 0.217 12.800 0.217
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 32.100 0.545 32.100 0.545
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 3.163 Sub Total 1.777 Sub Total 4.940
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 468.440 11.248 13.696 0.329 482.136 11.577
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 453.400 5.084 28.7356 0.322 482.136 5.407
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 70.200 0.520 0 0 70.200 0.520
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 114.000 1.001 0 0 114.000 1.001
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 240.000 2.376 48.000 0.475 288.000 2.851
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 74.000 0.265 19.000 0.068 93.000 0.333
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 0 0 0 0
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 0 0 0 0
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0.310 0.009 0.150 0.005 0.460 0.014
230,365,475.85Rp 23.087 Sub Total 20.503 Sub Total 1.199 Sub Total 21.702
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 10.000 0.952 0 0 10.000 0.952
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 0 0 0 0
71,463,355.79Rp 7.162 Sub Total 2.354 Sub Total 0.000 Sub Total 2.354
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 15 Page 101 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 344.700 0.797 344.700 0.797
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 314.600 0.727 314.600 0.727
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 1.524 Sub Total 1.524
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 0 0 0 0
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 32.000 0.385 15.000 0.180 47.000 0.565
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 2.000 0.040 2.000 0.040
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 0 0 0 0
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 0 0 0 0
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 0 0 0 0
11,760,000.00Rp 1.179 Sub Total 0.385 Sub Total 0.220 Sub Total 0.605
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 40.000 0.074 10.000 0.019 50.000 0.093
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 4.000 0.011 4.000 0.011
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 3.000 0.208 3.000 0.208
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 1.000 0.248 1.000 0.248
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 20.000 0.086 0 0 20.000 0.086
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 20.000 0.113 0 0 20.000 0.113
7,701,730.00Rp 0.772 Sub Total 0.273 Sub Total 0.485 Sub Total 0.759
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 10.000 0.301 10.000 0.301
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0.500 0.093 0.300 0.056 0.800 0.148
6,700,000.00Rp 0.671 Sub Total 0.093 Sub Total 0.356 Sub Total 0.449
997,821,223.49Rp 100 Total 72.598 Total 5.561 Total 78.160
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 15 Page 102 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 15 Page 103 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Kamis, 17 Juli 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Kamis, 24 Juli 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 132.336 1.807 0 0 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 45.621 0.717 0 0 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 3.081 Sub Total 0.000 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 16
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 16 Page 104 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 168.278 1.899 0 0 168.278 1.899
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 25.000 0.314 0 0 25.000 0.314
125,053,581.86Rp 12.533 Sub Total 12.533 Sub Total 0.000 Sub Total 12.533
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.251 0.164 0 0 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 150.000 0.290 0 0 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 15.000 0.561 0 0 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 1.277 0.168 0 0 1.277 0.168
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 16 Page 105 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 125.000 0.242 0 0 125.000 0.242
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 22.400 0.494 0 0 22.400 0.494
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 10.000 0.662 0 0 10.000 0.662
323,453,547.04Rp 32.416 Sub Total 29.981 Sub Total 0.000 Sub Total 29.981
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 128.900 0.481 5.200 0.019 134.100 0.500
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 732.500 2.526 38.000 0.131 770.500 2.657
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 85.400 0.395 85.400 0.395
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 961.500 1.171 0 0 961.500 1.171
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 12.800 0.217 0 0 12.800 0.217
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 32.100 0.545 0 0 32.100 0.545
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 4.940 Sub Total 0.545 Sub Total 5.485
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 482.136 11.577 0 0 482.136 11.577
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 482.136 5.407 0 0 482.136 5.407
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 70.200 0.520 0 0 70.200 0.520
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 114.000 1.001 0 0 114.000 1.001
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 288.000 2.851 0 0 288.000 2.851
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 93.000 0.333 0 0 93.000 0.333
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 84.000 0.831 84.000 0.831
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 47.000 0.168 47.000 0.168
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0.460 0.014 0.540 0.016 1.000 0.030
230,365,475.85Rp 23.087 Sub Total 21.702 Sub Total 1.016 Sub Total 22.718
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 10.000 0.952 0 0 10.000 0.952
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 5.000 0.225 5.000 0.225
71,463,355.79Rp 7.162 Sub Total 2.354 Sub Total 0.225 Sub Total 2.580
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 16 Page 106 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 344.700 0.797 114.000 0.263 458.700 1.060
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 314.600 0.727 72.00 0.166 386.600 0.893
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 1.524 Sub Total 0.430 Sub Total 1.953
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 1.000 0.251 1.000 0.251
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 47.000 0.565 13.000 0.156 60.000 0.722
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 2.000 0.040 3.000 0.060 5.000 0.100
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 35.000 0.061 35.000 0.061
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 1.000 0.002 1.000 0.002
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 13.000 0.033 13.000 0.033
11,760,000.00Rp 1.179 Sub Total 0.605 Sub Total 0.563 Sub Total 1.168
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 50.000 0.093 0 0 50.000 0.093
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 4.000 0.011 0 0 4.000 0.011
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 3.000 0.208 0 0 3.000 0.208
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 1.000 0.248 0 0 1.000 0.248
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 20.000 0.086 0 0 20.000 0.086
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 20.000 0.113 0 0 20.000 0.113
7,701,730.00Rp 0.772 Sub Total 0.759 Sub Total 0.000 Sub Total 0.759
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 10.000 0.301 0 0 10.000 0.301
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0.800 0.148 0.200 0.037 1.000 0.185
6,700,000.00Rp 0.671 Sub Total 0.449 Sub Total 0.037 Sub Total 0.486
997,821,223.49Rp 100 Total 78.159 Total 2.816 Total 80.976
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 16 Page 107 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 16 Page 108 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Kamis, 24 Juli 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Kamis, 31 Juli 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 132.336 1.807 0 0 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 45.621 0.717 0 0 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 3.081 Sub Total 0.000 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 17
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 17 Page 109 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 168.278 1.899 0 0 168.278 1.899
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 25.000 0.314 0 0 25.000 0.314
125,053,581.86Rp 12.533 Sub Total 12.533 Sub Total 0.000 Sub Total 12.533
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.251 0.164 0 0 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 150.000 0.290 0 0 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 15.000 0.561 0 0 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 1.277 0.168 0 0 1.277 0.168
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 17 Page 110 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 125.000 0.242 0 0 125.000 0.242
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 22.400 0.494 0 0 22.400 0.494
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 10.000 0.662 0 0 10.000 0.662
323,453,547.04Rp 32.416 Sub Total 29.981 Sub Total 0.000 Sub Total 29.981
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 134.100 0.500 0 0 134.100 0.500
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 770.500 2.657 0 0 770.500 2.657
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 85.400 0.395 0 0 85.400 0.395
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 961.500 1.171 0 0 961.500 1.171
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 12.800 0.217 0 0 12.800 0.217
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 32.100 0.545 0 0 32.100 0.545
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 5.485 Sub Total 0.000 Sub Total 5.485
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 482.136 11.577 0 0 482.136 11.577
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 482.136 5.407 0 0 482.136 5.407
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 70.200 0.520 0 0 70.200 0.520
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 114.000 1.001 0 0 114.000 1.001
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 288.000 2.851 0 0 288.000 2.851
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 93.000 0.333 0 0 93.000 0.333
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 84.000 0.831 0 0 84.000 0.831
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 47.000 0.168 0 0 47.000 0.168
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 1.000 0.030 0 0 1.000 0.030
230,365,475.85Rp 23.087 Sub Total 22.718 Sub Total 0.000 Sub Total 22.718
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 10.000 0.952 0 0 10.000 0.952
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 5.000 0.225 0 0 5.000 0.225
71,463,355.79Rp 7.162 Sub Total 2.580 Sub Total 0.000 Sub Total 2.580
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 17 Page 111 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 458.700 1.060 28.000 0.065 486.700 1.125
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 386.600 0.893 0 0 386.600 0.893
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 1.953 Sub Total 0.065 Sub Total 2.018
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 1.000 0.251 0 0 1.000 0.251
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 60.000 0.722 0 0 60.000 0.722
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 5.000 0.100 0 0 5.000 0.100
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 35.000 0.061 3.000 0.005 38.000 0.067
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 1.000 0.002 0 0 1.000 0.002
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 13.000 0.033 0 0 13.000 0.033
11,760,000.00Rp 1.179 Sub Total 1.168 Sub Total 0.005 Sub Total 1.173
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 50.000 0.093 0 0 50.000 0.093
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 4.000 0.011 0 0 4.000 0.011
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 3.000 0.208 0 0 3.000 0.208
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 1.000 0.248 0 0 1.000 0.248
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 20.000 0.086 0 0 20.000 0.086
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 20.000 0.113 0 0 20.000 0.113
7,701,730.00Rp 0.772 Sub Total 0.759 Sub Total 0.000 Sub Total 0.759
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 10.000 0.301 0 0 10.000 0.301
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 1.000 0.185 0 0 1.000 0.185
6,700,000.00Rp 0.671 Sub Total 0.486 Sub Total 0.000 Sub Total 0.486
997,821,223.49Rp 100 Total 80.976 Total 0.070 Total 81.046
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 17 Page 112 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 17 Page 113 of 150
LAPORAN BULANAN KEEMPAT - JULI 2014
PROGRAM :
Bulan ke
Kamis, 31 Juli 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Kamis, 28 Agustus 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 132.336 1.807 0 0 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 45.621 0.717 0 0 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 3.081 Sub Total 0.000 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.221 0.800 0 0 19.221 0.800
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
JUMLAH HARGA BOBOT %REALISASI BULANAN
BULAN LALU BULAN INI S.D. BULAN INI
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 4
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 5 Page 114 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 109.300 1.233 58.978 0.666 168.278 1.899
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 16.300 0.205 8.700 0.109 25.000 0.314
125,053,581.86Rp 12.533 Sub Total 11.758 Sub Total 0.775 Sub Total 12.533
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.873 0.902 0 0 6.875 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.170 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.252 0.164 0 0 1.254 0.165
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 5 Page 115 of 150
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 150.000 0.290 0 0 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 15.000 0.561 0 0 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 0 0 1.277 0.168 1.277 0.168
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 0 0 125.000 0.242 125.000 0.242
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 0 0 22.400 0.494 22.400 0.494
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 4.500 0.298 5.500 0.364 10.000 0.662
323,453,547.04Rp 32.416 Sub Total 28.713 Sub Total 1.268 Sub Total 29.981
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 46.500 0.173 87.600 0.327 134.100 0.500
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 271.400 0.936 499.100 1.721 770.500 2.657
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 0 0 85.400 0.395 85.400 0.395
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 0 0 0 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 0 0 961.500 1.171 961.500 1.171
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 0 0 0 0
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 0 0 0 0
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 0 0 12.800 0.217 12.800 0.217
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 0 0 32.100 0.545 32.100 0.545
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 1.109 Sub Total 4.376 Sub Total 5.485
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 205.240 4.928 277 6.649 482.136 11.577
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 99.700 1.118 382 4.289 482.136 5.407
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 0 0 70.200 0.520 70.200 0.520
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 0 0 114.000 1.001 114.000 1.001
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 0 0 288.000 2.851 288.000 2.851
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 0 0 93.000 0.333 93.000 0.333
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 0 0 84.000 0.831 84.000 0.831
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 0 0 47.000 0.168 47.000 0.168
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 0 0 1.000 0.030 1.000 0.030
230,365,475.85Rp 23.087 Sub Total 6.046 Sub Total 16.672 Sub Total 22.718
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 5 Page 116 of 150
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 6.000 0.571 4.000 0.381 10.000 0.952
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 0 0 5.000 0.225 5.000 0.225
71,463,355.79Rp 7.162 Sub Total 1.973 Sub Total 0.606 Sub Total 2.580
VIII. Pekerjaan Pengecatan
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 0 0 486.700 1.125 486.700 1.125
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 0 0 386.600 0.893 386.600 0.893
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 0.000 Sub Total 2.018 Sub Total 2.018
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 0 0 1.000 0.251 1.000 0.251
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 0 0 60.000 0.722 60.000 0.722
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 0 0 5.000 0.100 5.000 0.100
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 0 0 38.000 0.067 38.000 0.067
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 0 0 1.000 0.002 1.000 0.002
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 0 0 13.000 0.033 13.000 0.033
11,760,000.00Rp 1.179 Sub Total 0.000 Sub Total 1.173 Sub Total 1.173
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 30.000 0.056 20.000 0.037 50.000 0.093
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 0 0 4.000 0.011 4.000 0.011
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 0 0 3.000 0.208 3.000 0.208
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 0 0 1.000 0.248 1.000 0.248
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 15.000 0.064 5.000 0.021 20.000 0.086
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 15.000 0.085 5.000 0.028 20.000 0.113
7,701,730.00Rp 0.772 Sub Total 0.205 Sub Total 0.554 Sub Total 0.759
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 5 Page 117 of 150
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 0 0 10.000 0.301 10.000 0.301
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 1.000 0.185 1.000 0.185
6,700,000.00Rp 0.671 Sub Total 0.000 Sub Total 0.486 Sub Total 0.486
997,821,223.49Rp 100 Total 53.119 Total 27.928 Total 81.046
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
J U M L A H T O T A L P E K E R J A A N
TOTAL PEKERJAAN AKHIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 5 Page 118 of 150
Program Kegiatan : Peningkatan Sarana dan Prasarana Aparatur
Pekerjaan : Pembangunan Gedung Kantor Dinas Pemuda dan Olahraga Kabupaten Poso
Lokasi : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso
Tahun Anggaran : 2014
Min
ggu
1
Min
ggu
2
Min
ggu
3
Min
ggu
4
Min
ggu
5
Min
ggu
6
Min
ggu
7
Min
ggu
8
Min
ggu
9
Min
ggu
10
Min
ggu
11
Min
ggu
12
Min
ggu
13
Min
ggu
14
Min
ggu
15
Min
ggu
16
Min
ggu
17
Min
ggu
18
Min
ggu
19
Min
ggu
20
Min
ggu
21
Min
ggu
22
Min
ggu
23
Min
ggu
24
Min
ggu
25
I Pekerjaan Pendahuluan 2,326,140.00Rp 0.233 0.23100
II Pekerjaan Tanah dan Pasir 30,738,969.50Rp 3.081 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39
III Pekerjaan Pasangan Batu 125,053,581.86Rp 12.533 2.09 2.09 2.09 2.09 2.09 2.09
IV Pekerjaan Cor dan Beton 323,453,547.04Rp 32.416 0.48 0.97 0.48 0.71 1.43 1.25 1.25 1.25 2.86 4.43 4.43 4.43 3.08 1.25 4.12
V Pekerjaan Plesteran/Acian dan Keramik 138,242,621.13Rp 13.854 2.31 2.31 2.31 2.31 2.31 2.31
VI Pekerjaan Rangka Kap Baja Ringan dan Plafon 230,365,475.85Rp 23.087 3.85 3.85 3.85 3.85 3.85 3.85 50
VII Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca 71,463,355.79Rp 7.162 2.15 2.15 2.15 0.72
VIII Pekerjaan Pengecatan 38,959,933.07Rp 3.905 1.95 1.95
IX Pekerjaan Instalasi Listrik 11,760,000.00Rp 1.179 1.18X
X 7,701,730.00Rp 0.772 0.39 0.39XI
XI Pekerjaan Kunci dan Penggantung 11,055,869.25Rp 1.108 1.11
XII 6,700,000.00Rp 0.671 0.34 0.34
T O T A L 997,821,223.49Rp 100.000
RENCANA PER MINGGU % % 0.23 0.87 1.35 2.96 3.19 3.90 3.73 3.73 5.87 5.01 6.58 4.43 4.43 3.08 5.10 7.97 7.34 6.16 6.16 6.16 4.26 4.65 1.10 1.44 0.34
RENCANA KUMULATIF % 0.000 0.23 1.10 2.45 5.41 8.60 12.50 16.22 19.95 25.82 30.83 37.41 41.83 46.26 49.34 54.44 62.40 69.74 75.90 82.05 88.21 92.47 97.12 98.22 99.66 100.0
REALISASI PER MINGGU % 0.23 2.05 3.38 7.62 7.99 1.92 2.38 3.06 11.81 2.54 3.08 7.06 10.04 9.44 5.56 2.82 0.07
REALISASI KUMULATIF % 0.000 0.23 2.28 5.66 13.28 21.27 23.19 25.57 28.63 40.44 42.98 46.06 53.12 63.16 72.60 78.16 80.98 81.05
DEVIASI % 0.00 +1.18 +3.21 +7.87 +12.68 +10.70 +9.35 +8.68 +14.61 +12.15 +8.65 +11.29 +16.90 +23.26 +23.72 +18.57 +11.31
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan SupervisiPembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Mei 2014 Juni 2014 Juli 2014 Agustus 2014 September 2014
Pekerjaan Sanitasi
Pekerjaan Akhir
SCHEDULE DAN REALISASI PELAKSANAAN PEKERJAAN PEMBANGUNAN GEDUNG KANTOR DISPORA KABUPATEN POSO
NO. U R A I A N HARGA PEKERJAANBOBOT
(%)
WAKTU PELAKSANAAN
KET.
April 2014
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Kamis, 31 Juli 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Kamis, 07 Agustus 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 132.336 1.807 0 0 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 45.621 0.717 0 0 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 3.081 Sub Total 0.000 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 18
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 18 Page 120 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 168.278 1.899 0 0 168.278 1.899
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 25.000 0.314 0 0 25.000 0.314
125,053,581.86Rp 12.533 Sub Total 12.533 Sub Total 0.000 Sub Total 12.533
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.251 0.164 0 0 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 150.000 0.290 0 0 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 15.000 0.561 0 0 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 1.277 0.168 0 0 1.277 0.168
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 18 Page 121 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 125.000 0.242 0 0 125.000 0.242
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 22.400 0.494 0 0 22.400 0.494
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 10.000 0.662 0 0 10.000 0.662
323,453,547.04Rp 32.416 Sub Total 29.981 Sub Total 0.000 Sub Total 29.981
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 134.100 0.500 0 0 134.100 0.500
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 770.500 2.657 0 0 770.500 2.657
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 85.400 0.395 0 0 85.400 0.395
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 10.000 0.037 10.000 0.037
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 961.500 1.171 0 0 961.500 1.171
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 147.000 2.560 147.000 2.560
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 0 0 0 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 5.000 0.087 5.000 0.087
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 12.800 0.217 0 0 12.800 0.217
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 32.100 0.545 0 0 32.100 0.545
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 5.485 Sub Total 2.685 Sub Total 8.170
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 482.136 11.577 0 0 482.136 11.577
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 482.136 5.407 0 0 482.136 5.407
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 70.200 0.520 0 0 70.200 0.520
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 114.000 1.001 0 0 114.000 1.001
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 288.000 2.851 0 0 288.000 2.851
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 93.000 0.333 0 0 93.000 0.333
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 84.000 0.831 0 0 84.000 0.831
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 47.000 0.168 0 0 47.000 0.168
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 1.000 0.030 0 0 1.000 0.030
230,365,475.85Rp 23.087 Sub Total 22.718 Sub Total 0.000 Sub Total 22.718
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 10.000 0.952 0 0 10.000 0.952
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 5.000 0.225 0 0 5.000 0.225
71,463,355.79Rp 7.162 Sub Total 2.580 Sub Total 0.000 Sub Total 2.580
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 18 Page 122 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 486.700 1.125 30.000 0.069 516.700 1.194
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 386.600 0.893 0 0 386.600 0.893
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 2.018 Sub Total 0.069 Sub Total 2.087
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 1.000 0.251 0 0 1.000 0.251
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 60.000 0.722 0 0 60.000 0.722
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 5.000 0.100 0 0 5.000 0.100
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 38.000 0.067 0 0 38.000 0.067
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 1.000 0.002 0 0 1.000 0.002
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 13.000 0.033 0 0 13.000 0.033
11,760,000.00Rp 1.179 Sub Total 1.173 Sub Total 0.000 Sub Total 1.173
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 50.000 0.093 0 0 50.000 0.093
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 4.000 0.011 0 0 4.000 0.011
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 3.000 0.208 0 0 3.000 0.208
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 1.000 0.248 0 0 1.000 0.248
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 20.000 0.086 0 0 20.000 0.086
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 20.000 0.113 0 0 20.000 0.113
7,701,730.00Rp 0.772 Sub Total 0.759 Sub Total 0.000 Sub Total 0.759
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 10.000 0.301 0 0 10.000 0.301
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 1.000 0.185 0 0 1.000 0.185
6,700,000.00Rp 0.671 Sub Total 0.486 Sub Total 0.000 Sub Total 0.486
997,821,223.49Rp 100 Total 81.046 Total 2.754 Total 83.800
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 18 Page 123 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 18 Page 124 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Kamis, 07 Agustus 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Kamis, 14 Agustus 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 132.336 1.807 0 0 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 45.621 0.717 0 0 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 3.081 Sub Total 0.000 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 19
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 19 Page 125 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 168.278 1.899 0 0 168.278 1.899
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 25.000 0.314 0 0 25.000 0.314
125,053,581.86Rp 12.533 Sub Total 12.533 Sub Total 0.000 Sub Total 12.533
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.251 0.164 0 0 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 150.000 0.290 0 0 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 15.000 0.561 0 0 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 1.277 0.168 0 0 1.277 0.168
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 19 Page 126 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 125.000 0.242 0 0 125.000 0.242
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 22.400 0.494 0 0 22.400 0.494
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 10.000 0.662 0 0 10.000 0.662
323,453,547.04Rp 32.416 Sub Total 29.981 Sub Total 0.000 Sub Total 29.981
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 134.100 0.500 0 0 134.100 0.500
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 770.500 2.657 0 0 770.500 2.657
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 85.400 0.395 0 0 85.400 0.395
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 10.000 0.037 10.000 0.037 20.000 0.075
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 961.500 1.171 0 0 961.500 1.171
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 147.000 2.560 102.000 1.777 249.000 4.337
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 28.400 0.036 28.400 0.036
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 5.000 0.087 24.000 0.418 29.000 0.505
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 0 0 0 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 12.800 0.217 0 0 12.800 0.217
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 32.100 0.545 0 0 32.100 0.545
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 0 0 0 0
138,242,621.13Rp 13.854 Sub Total 8.170 Sub Total 2.268 Sub Total 10.438
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 482.136 11.577 0 0 482.136 11.577
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 482.136 5.407 0 0 482.136 5.407
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 70.200 0.520 0 0 70.200 0.520
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 114.000 1.001 12.760 0.112 126.760 1.113
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 288.000 2.851 14.260 0.141 302.260 2.992
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 93.000 0.333 5.000 0.018 98.000 0.351
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 84.000 0.831 7.000 0.069 91.000 0.901
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 47.000 0.168 0 0 47.000 0.168
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 1.000 0.030 0 0 1.000 0.030
230,365,475.85Rp 23.087 Sub Total 22.718 Sub Total 0.340 Sub Total 23.058
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 0 0 0 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 0 0 0 0
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 10.000 0.952 0 0 10.000 0.952
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 5.000 0.225 0 0 5.000 0.225
71,463,355.79Rp 7.162 Sub Total 2.580 Sub Total 0.000 Sub Total 2.580
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 19 Page 127 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 516.700 1.194 85.000 0.196 601.700 1.390
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 386.600 0.893 0 0 386.600 0.893
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 0 0 0 0
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 0 0 0 0
38,959,933.07Rp 3.905 Sub Total 2.087 Sub Total 0.196 Sub Total 2.284
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 1.000 0.251 0 0 1.000 0.251
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 60.000 0.722 0 0 60.000 0.722
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 5.000 0.100 0 0 5.000 0.100
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 38.000 0.067 3.000 0.005 41.000 0.072
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 1.000 0.002 0 0 1.000 0.002
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 13.000 0.033 0 0 13.000 0.033
11,760,000.00Rp 1.179 Sub Total 1.173 Sub Total 0.005 Sub Total 1.179
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 50.000 0.093 0 0 50.000 0.093
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 4.000 0.011 0 0 4.000 0.011
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 3.000 0.208 0 0 3.000 0.208
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 1.000 0.248 0 0 1.000 0.248
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 20.000 0.086 0 0 20.000 0.086
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 20.000 0.113 0 0 20.000 0.113
7,701,730.00Rp 0.772 Sub Total 0.759 Sub Total 0.000 Sub Total 0.759
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 0 0 0 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 0 0 0 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 0 0 0 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 0 0 0 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 0 0 0 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.000 Sub Total 0.000
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 10.000 0.301 0 0 10.000 0.301
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 1.000 0.185 0 0 1.000 0.185
6,700,000.00Rp 0.671 Sub Total 0.486 Sub Total 0.000 Sub Total 0.486
997,821,223.49Rp 100 Total 83.800 Total 2.810 Total 86.610J U M L A H T O T A L P E K E R J A A N
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 19 Page 128 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 19 Page 129 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Kamis, 14 Agustus 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Kamis, 21 Agustus 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 132.336 1.807 0 0 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 45.621 0.717 0 0 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 3.081 Sub Total 0.000 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 20
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 20 Page 130 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 168.278 1.899 0 0 168.278 1.899
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 25.000 0.314 0 0 25.000 0.314
125,053,581.86Rp 12.533 Sub Total 12.533 Sub Total 0.000 Sub Total 12.533
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.251 0.164 0 0 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 150.000 0.290 0 0 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 15.000 0.561 0 0 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 1.277 0.168 0 0 1.277 0.168
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 20 Page 131 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 125.000 0.242 0 0 125.000 0.242
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 22.400 0.494 0 0 22.400 0.494
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 10.000 0.662 0 0 10.000 0.662
323,453,547.04Rp 32.416 Sub Total 29.981 Sub Total 0.000 Sub Total 29.981
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 134.100 0.500 15.900 0.059 150.000 0.560
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 770.500 2.657 105.146 0.363 875.646 3.019
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 85.400 0.395 0 0 85.400 0.395
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 20.000 0.075 0 0 20.000 0.075
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 961.500 1.171 0 0 961.500 1.171
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 249.000 4.337 21.400 0.373 270.400 4.710
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 28.400 0.036 32.000 0.041 60.400 0.077
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 29.000 0.505 28.000 0.488 57.000 0.993
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 12.000 0.015 12.000 0.015
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 12.800 0.217 0 0 12.800 0.217
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 32.100 0.545 0 0 32.100 0.545
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 25.000 0.435 25.000 0.435
138,242,621.13Rp 13.854 Sub Total 10.438 Sub Total 1.774 Sub Total 12.212
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 482.136 11.577 0 0 482.136 11.577
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 482.136 5.407 0 0 482.136 5.407
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 70.200 0.520 0 0 70.200 0.520
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 126.760 1.113 0 0 126.760 1.113
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 302.260 2.992 0 0 302.260 2.992
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 98.000 0.351 0 0 98.000 0.351
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 91.000 0.901 0 0 91.000 0.901
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 47.000 0.168 8.000 0.029 55.000 0.197
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 1.000 0.030 0 0 1.000 0.030
230,365,475.85Rp 23.087 Sub Total 23.058 Sub Total 0.029 Sub Total 23.087
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 10.400 0.231 10.400 0.231
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 48.200 2.608 48.200 2.608
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 10.000 0.952 0 0 10.000 0.952
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 5.000 0.225 0 0 5.000 0.225
71,463,355.79Rp 7.162 Sub Total 2.580 Sub Total 2.839 Sub Total 5.419
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 20 Page 132 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 601.700 1.390 280.000 0.647 881.700 2.037
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 386.600 0.893 0 0 386.600 0.893
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 66.480 0.276 66.480 0.276
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 12.480 0.052 12.480 0.052
38,959,933.07Rp 3.905 Sub Total 2.284 Sub Total 0.974 Sub Total 3.258
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 1.000 0.251 0 0 1.000 0.251
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 60.000 0.722 0 0 60.000 0.722
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 5.000 0.100 0 0 5.000 0.100
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 41.000 0.072 0 0 41.000 0.072
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 1.000 0.002 0 0 1.000 0.002
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 13.000 0.033 0 0 13.000 0.033
11,760,000.00Rp 1.179 Sub Total 1.179 Sub Total 0.000 Sub Total 1.179
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 50.000 0.093 0 0 50.000 0.093
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 4.000 0.011 0 0 4.000 0.011
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 3.000 0.208 0 0 3.000 0.208
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 1.000 0.248 0 0 1.000 0.248
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 20.000 0.086 0 0 20.000 0.086
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 20.000 0.113 0 0 20.000 0.113
7,701,730.00Rp 0.772 Sub Total 0.759 Sub Total 0.000 Sub Total 0.759
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 0 0 0 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 15.000 0.045 15.000 0.045
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 0 0 0 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 37.000 0.095 37.000 0.095
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0.000 0.000 0.000 0.000
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 37.000 0.148 37.000 0.148
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 37.000 0.146 37.000 0.146
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 4.000 0.048 4.000 0.048
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 0.482 Sub Total 0.482
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 10.000 0.301 0 0 10.000 0.301
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 1.000 0.185 0 0 1.000 0.185
6,700,000.00Rp 0.671 Sub Total 0.486 Sub Total 0.000 Sub Total 0.486
997,821,223.49Rp 100 Total 86.610 Total 6.098 Total 92.708
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 20 Page 133 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 20 Page 134 of 150
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Kamis, 21 Agustus 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Kamis, 28 Agustus 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 132.336 1.807 0 0 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 45.621 0.717 0 0 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 3.081 Sub Total 0.000 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 21
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 21 Page 135 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 168.278 1.899 0 0 168.278 1.899
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 25.000 0.314 0 0 25.000 0.314
125,053,581.86Rp 12.533 Sub Total 12.533 Sub Total 0.000 Sub Total 12.533
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.251 0.164 0 0 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 150.000 0.290 0 0 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 15.000 0.561 0 0 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 1.277 0.168 0 0 1.277 0.168
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 21 Page 136 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 125.000 0.242 0 0 125.000 0.242
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 22.400 0.494 0 0 22.400 0.494
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 10.000 0.662 0 0 10.000 0.662
323,453,547.04Rp 32.416 Sub Total 29.981 Sub Total 0.000 Sub Total 29.981
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 150.000 0.560 0 0 150.000 0.560
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 875.650 3.019 0 0 875.650 3.019
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 85.400 0.395 0 0 85.400 0.395
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 20.000 0.075 0 0 20.000 0.075
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 961.500 1.171 0 0 961.500 1.171
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 270.400 4.710 10.000 0.174 280.400 4.884
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 60.400 0.077 12.000 0.015 72.400 0.093
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 57.000 0.993 8.000 0.139 65.000 1.132
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 12.000 0.015 18.000 0.023 30.000 0.038
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 12.800 0.217 0 0 12.800 0.217
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 32.100 0.545 0 0 32.100 0.545
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 25.000 0.435 0 0 25.000 0.435
138,242,621.13Rp 13.854 Sub Total 12.212 Sub Total 0.352 Sub Total 12.564
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 482.136 11.577 0 0 482.136 11.577
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 482.136 5.407 0 0 482.136 5.407
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 70.200 0.520 0 0 70.200 0.520
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 126.760 1.113 0 0 126.760 1.113
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 302.260 2.992 0 0 302.260 2.992
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 98.000 0.351 0 0 98.000 0.351
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 91.000 0.901 0 0 91.000 0.901
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 55.000 0.197 0 0 55.000 0.197
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 1.000 0.030 0 0 1.000 0.030
230,365,475.85Rp 23.087 Sub Total 23.087 Sub Total 0.000 Sub Total 23.087
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 10.400 0.231 2.600 0.058 13.000 0.289
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 48.200 2.608 12.06 0.653 60.260 3.261
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 10.000 0.952 0 0 10.000 0.952
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 5.000 0.225 0 0 5.000 0.225
71,463,355.79Rp 7.162 Sub Total 5.419 Sub Total 0.710 Sub Total 6.129
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 21 Page 137 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 881.700 2.037 152.000 0.351 1033.700 2.389
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 386.600 0.893 0 0 386.600 0.893
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 66.480 0.276 0 0 66.480 0.276
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 12.480 0.052 0 0 12.480 0.052
38,959,933.07Rp 3.905 Sub Total 3.258 Sub Total 0.351 Sub Total 3.609
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 1.000 0.251 0 0 1.000 0.251
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 60.000 0.722 0 0 60.000 0.722
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 5.000 0.100 0 0 5.000 0.100
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 41.000 0.072 0 0 41.000 0.072
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 1.000 0.002 0 0 1.000 0.002
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 13.000 0.033 0 0 13.000 0.033
11,760,000.00Rp 1.179 Sub Total 1.179 Sub Total 0.000 Sub Total 1.179
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 50.000 0.093 0 0 50.000 0.093
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 4.000 0.011 0 0 4.000 0.011
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 3.000 0.208 0 0 3.000 0.208
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 1.000 0.248 0 0 1.000 0.248
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 20.000 0.086 0 0 20.000 0.086
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 20.000 0.113 0 0 20.000 0.113
7,701,730.00Rp 0.772 Sub Total 0.759 Sub Total 0.000 Sub Total 0.759
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 9.000 0.146 9.000 0.146
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 15.000 0.045 0 0 15.000 0.045
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 4.000 0.341 4.000 0.341
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 37.000 0.095 9.000 0.023 46.000 0.118
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 37.000 0.148 9.000 0.036 46.000 0.184
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 37.000 0.146 9.000 0.035 46.000 0.181
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 4.000 0.048 0 0 4.000 0.048
11,055,869.25Rp 1.108 Sub Total 0.482 Sub Total 0.581 Sub Total 1.063
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 10.000 0.301 0 0 10.000 0.301
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 1.000 0.185 0 0 1.000 0.185
6,700,000.00Rp 0.671 Sub Total 0.486 Sub Total 0.000 Sub Total 0.486
997,821,223.49Rp 100 Total 92.708 Total 1.995 Total 94.703
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 21 Page 138 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 21 Page 139 of 150
LAPORAN BULANAN - AGUSTUS 2014
PROGRAM :
Bulan ke
Kamis, 31 Juli 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Kamis, 28 Agustus 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 132.336 1.807 0 0 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 45.621 0.717 0 0 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 3.081 Sub Total 0.000 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.221 0.800 0 0 19.221 0.800
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 5
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN JUMLAH HARGA BOBOT %REALISASI BULANAN
BULAN LALU BULAN INI S.D. BULAN INI
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 5 Page 140 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 168.278 1.899 0 0 168.278 1.899
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 25.000 0.314 0 0 25.000 0.314
125,053,581.86Rp 12.533 Sub Total 12.533 Sub Total 0.000 Sub Total 12.533
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.875 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.254 0.165 0 0 1.256 0.165
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 150.000 0.290 0 0 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 15.000 0.561 0 0 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 1.277 0.168 0 0 1.277 0.168
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 5 Page 141 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 125.000 0.242 0 0 125.000 0.242
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 22.400 0.494 0 0 22.400 0.494
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 10.000 0.662 0 0 10.000 0.662
323,453,547.04Rp 32.416 Sub Total 29.981 Sub Total 0.000 Sub Total 29.981
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 134.100 0.500 15.900 0.059 150.000 0.560
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 770.500 2.657 105.146 0.363 875.646 3.019
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 85.400 0.395 0 0 85.400 0.395
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 0 0 20.000 0.075 20 0
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 961.500 1.171 0.000 0.000 961.500 1.171
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 0 0 280.400 4.884 280 5
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 0 0 72.400 0.093 72 0
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 0 0 65.000 1.132 65 1
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 0 0 30.000 0.038 30 0
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 12.800 0.217 0.000 0.000 12.800 0.217
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 32.100 0.545 0.000 0.000 32.100 0.545
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 0 0 25.000 0.435 25 0
138,242,621.13Rp 13.854 Sub Total 5.485 Sub Total 7.079 Sub Total 12.564
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 482.136 11.577 0.000 0.000 482.136 11.577
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 482.136 5.407 0.000 0.000 482.136 5.407
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 70.200 0.520 0.000 0.000 70.200 0.520
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 114.000 1.001 12.760 0.112 126.760 1.113
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 288.000 2.851 14.260 0.141 302.260 2.992
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 93.000 0.333 5.000 0.018 98.000 0.351
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 84.000 0.831 7.000 0.069 91.000 0.901
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 47.000 0.168 8.000 0.029 55.000 0.197
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 1.000 0.030 0.000 0.000 1.000 0.030
230,365,475.85Rp 23.087 Sub Total 22.718 Sub Total 0.369 Sub Total 23.087
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0.000 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0.000 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 0 0 13.000 0 13 0
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 0 0 60.260 3 60 3
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0.000 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 10.000 0.952 0.000 0 10.000 0.952
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 5.000 0.225 0.000 0 5.000 0.225
71,463,355.79Rp 7.162 Sub Total 2.580 Sub Total 3.549 Sub Total 6.129
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 5 Page 142 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 486.700 1.125 547.000 1.264 1033.700 2.389
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 386.600 0.893 0.000 0 386.600 0.893
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 0 0 66.480 0.276 66.480 0.276
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 0 0 12.480 0.052 12.480 0.052
38,959,933.07Rp 3.905 Sub Total 2.018 Sub Total 1.591 Sub Total 3.609
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 1.000 0.251 0 0 1.000 0.251
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 60.000 0.722 0 0 60.000 0.722
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 5.000 0.100 0 0 5.000 0.100
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 38.000 0.067 3.000 0.005 41.000 0.072
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 1.000 0.002 0 0 1.000 0.002
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 13.000 0.033 0 0 13.000 0.033
11,760,000.00Rp 1.179 Sub Total 1.173 Sub Total 0.005 Sub Total 1.179
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 50.000 0.093 0 0 50.000 0.093
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 4.000 0.011 0 0 4.000 0.011
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 3.000 0.208 0 0 3.000 0.208
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 1.000 0.248 0 0 1.000 0.248
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 20.000 0.086 0 0 20.000 0.086
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 20.000 0.113 0 0 20.000 0.113
7,701,730.00Rp 0.772 Sub Total 0.759 Sub Total 0.000 Sub Total 0.759
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 9.000 0 9 0
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 0 0 15.000 0 15 0
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 4.000 0 4 0
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 0 0 46.000 0 46 0
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0.000 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 0 0 46.000 0 46 0
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 0 0 46.000 0 46 0
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 0 0 4.000 0 4 0
11,055,869.25Rp 1.108 Sub Total 0.000 Sub Total 1.063 Sub Total 1.063
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0.000 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 10.000 0.301 0.000 0 10.000 0.301
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 1.000 0.185 0.000 0 1.000 0.185
6,700,000.00Rp 0.671 Sub Total 0.486 Sub Total 0.000 Sub Total 0.486
997,821,223.49Rp 100 Total 81.046 Total 13.657 Total 94.703
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
J U M L A H T O T A L P E K E R J A A N
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 5 Page 143 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Month 5 Page 144 of 150
Program Kegiatan : Peningkatan Sarana dan Prasarana Aparatur
Pekerjaan : Pembangunan Gedung Kantor Dinas Pemuda dan Olahraga Kabupaten Poso
Lokasi : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso
Tahun Anggaran : 2014
Min
ggu
1
Min
ggu
2
Min
ggu
3
Min
ggu
4
Min
ggu
5
Min
ggu
6
Min
ggu
7
Min
ggu
8
Min
ggu
9
Min
ggu
10
Min
ggu
11
Min
ggu
12
Min
ggu
13
Min
ggu
14
Min
ggu
15
Min
ggu
16
Min
ggu
17
Min
ggu
18
Min
ggu
19
Min
ggu
20
Min
ggu
21
Min
ggu
22
Min
ggu
23
Min
ggu
24
Min
ggu
25
I Pekerjaan Pendahuluan 2,326,140.00Rp 0.233 0.23100
II Pekerjaan Tanah dan Pasir 30,738,969.50Rp 3.081 0.39 0.39 0.39 0.39 0.39 0.39 0.39 0.39
III Pekerjaan Pasangan Batu 125,053,581.86Rp 12.533 2.09 2.09 2.09 2.09 2.09 2.09
IV Pekerjaan Cor dan Beton 323,453,547.04Rp 32.416 0.48 0.97 0.48 0.71 1.43 1.25 1.25 1.25 2.86 4.43 4.43 4.43 3.08 1.25 4.12
V Pekerjaan Plesteran/Acian dan Keramik 138,242,621.13Rp 13.854 2.31 2.31 2.31 2.31 2.31 2.31
VI Pekerjaan Rangka Kap Baja Ringan dan Plafon 230,365,475.85Rp 23.087 3.85 3.85 3.85 3.85 3.85 3.85 50
VII Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca 71,463,355.79Rp 7.162 2.15 2.15 2.15 0.72
VIII Pekerjaan Pengecatan 38,959,933.07Rp 3.905 1.95 1.95
IX Pekerjaan Instalasi Listrik 11,760,000.00Rp 1.179 1.18X
X 7,701,730.00Rp 0.772 0.39 0.39XI
XI Pekerjaan Kunci dan Penggantung 11,055,869.25Rp 1.108 1.11
XII 6,700,000.00Rp 0.671 0.34 0.34
T O T A L 997,821,223.49Rp 100.000
RENCANA PER MINGGU % % 0.23 0.87 1.35 2.96 3.19 3.90 3.73 3.73 5.87 5.01 6.58 4.43 4.43 3.08 5.10 7.97 7.34 6.16 6.16 6.16 4.26 4.65 1.10 1.44 0.34
RENCANA KUMULATIF % 0.000 0.23 1.10 2.45 5.41 8.60 12.50 16.22 19.95 25.82 30.83 37.41 41.83 46.26 49.34 54.44 62.40 69.74 75.90 82.05 88.21 92.47 97.12 98.22 99.66 100.0
REALISASI PER MINGGU % 0.23 2.05 3.38 7.62 7.99 1.92 2.38 3.06 11.81 2.54 3.08 7.06 10.04 9.44 5.56 2.82 0.07 2.75 2.81 6.10 1.99
REALISASI KUMULATIF % 0.000 0.23 2.28 5.66 13.28 21.27 23.19 25.57 28.63 40.44 42.98 46.06 53.12 63.16 72.60 78.16 80.98 81.05 83.80 86.61 92.71 94.70
DEVIASI % 0.00 +1.18 +3.21 +7.87 +12.68 +10.70 +9.35 +8.68 +14.61 +12.15 +8.65 +11.29 +16.90 +23.26 +23.72 +18.57 +11.31 +7.91 +4.56 +4.50 +2.23
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan SupervisiPembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Mei 2014 Juni 2014 Juli 2014 Agustus 2014 September 2014
Pekerjaan Sanitasi
Pekerjaan Akhir
SCHEDULE DAN REALISASI PELAKSANAAN PEKERJAAN PEMBANGUNAN GEDUNG KANTOR DISPORA KABUPATEN POSO
NO. U R A I A N HARGA PEKERJAANBOBOT
(%)
WAKTU PELAKSANAAN
KET.
April 2014
LAPORAN MINGGUAN
PROGRAM :
Minggu ke
Kamis, 28 Agustus 2014
LOKASI : Jl. Brigjen Katamso, Kel. Kasintuwu, Kec. Poso Kota Utara, Kab. Poso Kamis, 04 September 2014
TAHUN ANGGARAN : 2014
1 SATUAN KERJA PERANGKAT DAERAH : Badan Perencanaan Pembangunan Daerah (Bappeda) Kabupaten Poso
2 KONTRAKTOR : CV. Graha Teknika
3 NOMOR KONTRAK : 10/KONT-KD/DISPORA/IV/2014
4 TANGGAL KONTRAK :
5 NILAI KONTRAK :
6 KONSULTAN PENGAWAS : CV. Matra Griya Mandiri
7 NOMOR KONTRAK : 08/SPK-KD/PENGAWAS/IV/2014
8 TANGGAL KONTRAK : 21 APRIL 2014
9 NILAI KONTRAK : Rp 40.000.000,-
10 RENCANA PHO :
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
I. Pekerjaan Pendahuluan
1 Pek. Papan Nama Proyek 1.00 Ls 250,000.00Rp 250,000.00Rp 0.025 1.000 0.025 0 0 1.000 0.025
2 Pek. Bouwplank 44.00 m147,185.00Rp 2,076,140.00Rp 0.208 44.000 0.208 0 0 44.000 0.208
2,326,140.00Rp 0.233 Sub Total 0.233 Sub Total 0.000 Sub Total 0.233
II. Pekerjaan Tanah dan Pasir
1 Pek. Galian Tanah Sedalam Kurang < 1 m 102.52 m327,400.00Rp 2,809,048.00Rp 0.282 102.520 0.282 0 0 102.520 0.282
2 Pek. Galian Tanah Sedalam > 1 m (Galian Pondasi Telapak) 33.48 m335,980.00Rp 1,204,610.40Rp 0.121 33.480 0.121 0 0 33.480 0.121
3 Pek. Timbunan Bekas Galian 47.60 m313,135.00Rp 625,226.00Rp 0.063 47.600 0.063 0 0 47.600 0.063
4 Pek. Urugan Tasirtu dibawah Lantai t=60 cm 132.34 m3136,250.00Rp 18,030,780.00Rp 1.807 132.336 1.807 0 0 132.336 1.807
5 Pek. Urugan Pasir dibawah Lantai t=30 cm 45.62 m3156,850.00Rp 7,155,653.85Rp 0.717 45.621 0.717 0 0 45.621 0.717
6 Pek. Urugan Pasir dibawah pondasi 5.83 m3156,850.00Rp 913,651.25Rp 0.092 5.825 0.092 0 0 5.825 0.092
30,738,969.50Rp 3.081 Sub Total 3.081 Sub Total 0.000 Sub Total 3.081
III. Pekerjaan Pasangan Batu
1 Pek. Pasangan Batu Kosong 19.22 m3415,230.00Rp 7,981,758.68Rp 0.800 19.223 0.800 0 0 19.223 0.800
TOTAL PEKERJAAN PENDAHULUAN
TOTAL PEKERJAAN TANAH DAN PASIR
JUMLAH HARGA BOBOT %REALISASI MINGGUAN
MINGGU LALU MINGGU INI S.D. MINGGU INI
03 April 2014
Rp. 1.097.600.000,-
29 September 2014
NO. PEKERJAAN VOLUME
SATU
AN
HARGA SATUAN
Peningkatan Sarana dan Prasarana Aparatur LAPORAN PROGRESS PEKERJAAN
PEKERJAAN :Pembangunan Gedung Kantor Dinas Pemuda dan
Olahraga Kabupaten Poso 22
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 21 Page 146 of 150
2 Pek. Pasangan Batu Kali 1 : 5 78.90 m3704,075.00Rp 55,551,517.50Rp 5.567 78.900 5.567 0 0 78.900 5.567
3 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.I) 294.55 m2112,595.00Rp 33,164,294.28Rp 3.324 294.545 3.324 0 0 294.545 3.324
4 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.I) 50.00 m2125,450.00Rp 6,272,500.00Rp 0.629 50.000 0.629 0 0 50.000 0.629
5 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 5 (Lt.2) 168.28 m2112,595.00Rp 18,947,261.41Rp 1.899 168.278 1.899 0 0 168.278 1.899
6 Pek. Pas. Batu bata 1/2 batu Camp. 1 : 3 (Lt.2) 25.00 m2125,450.00Rp 3,136,250.00Rp 0.314 25.000 0.314 0 0 25.000 0.314
125,053,581.86Rp 12.533 Sub Total 12.533 Sub Total 0.000 Sub Total 12.533
IV. Pekerjaan Cor dan Beton
1 Pek. Cor Lantai Kerja t = 10 cm 1.82 m³ 660,925.00Rp 1,199,578.88Rp 0.120 1.815 0.120 0 0 1.815 0.120
2 Pek. Pondasi Poer Plat 110 x 110 6.87 m³ 1,309,900.00Rp 9,000,683.12Rp 0.902 6.871 0.902 0 0 6.871 0.902
3 Pek. Besi Tulangan 1234.17 Kg 19,295.00Rp 23,813,310.15Rp 2.387 1234.170 2.387 0 0 1234.17 2.387
4 Pek. Bekesting Poor Plat 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
5 Pek. Sloof Beton 20/30 4.29 m³ 1,309,900.00Rp 5,619,471.00Rp 0.563 4.290 0.563 0 0 4.290 0.563
6 Pek. Besi Tulangan 550.42 Kg 19,295.00Rp 10,620,353.90Rp 1.064 550.420 1.064 0 0 550.420 1.064
7 Pek. Bekesting Sloof 20/30 42.90 m² 124,935.00Rp 5,359,711.50Rp 0.537 42.900 0.537 0 0 42.900 0.537
8 Pek. Sloof Beton 15/20 2.26 m³ 1,309,900.00Rp 2,955,134.40Rp 0.296 2.256 0.296 0 0 2.256 0.296
9 Pek. Besi Tulangan 319.08 Kg 19,295.00Rp 6,156,648.60Rp 0.617 319.080 0.617 0 0 319.080 0.617
10 Pek. Bekesting Sloof 15/20 37.60 m² 124,935.00Rp 4,697,556.00Rp 0.471 37.600 0.471 0 0 37.600 0.471
11 Pek. Kolom Beton 30/30 Lantai 1 4.48 m³ 1,309,900.00Rp 5,866,157.92Rp 0.588 4.478 0.588 0 0 4.478 0.588
12 Pek. Besi Tulangan 840.87 Kg 19,295.00Rp 16,224,586.65Rp 1.626 840.870 1.626 0 0 840.870 1.626
13 Pek. Bekesting Kolom 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
14 Pek. Kolom Beton 30/30 lantai 2 4.71 m³ 1,309,900.00Rp 6,169,105.04Rp 0.618 4.710 0.618 0 0 4.710 0.618
15 Pek. Besi Tulangan 504.34 Kg 19,295.00Rp 9,731,240.30Rp 0.975 420.000 0.812 0 0 420.000 0.812
16 Pek. Bekesting Kolom 67.20 m² 220,135.00Rp 14,793,072.00Rp 1.483 67.200 1.483 0 0 67.200 1.483
17 Pek. Kolom Beton 15/15 1.25 m³ 1,309,900.00Rp 1,639,156.46Rp 0.164 1.251 0.164 0 0 1.251 0.164
18 Pek. Besi Tulangan 245.34 Kg 19,295.00Rp 4,733,835.30Rp 0.474 245.340 0.474 0 0 245.340 0.474
19 Pek. Bekesting Kolom 26.40 m² 220,135.00Rp 5,811,564.00Rp 0.582 26.400 0.582 0 0 26.400 0.582
20 Pek. Balok Lantai 30/45 7.43 m³ 1,309,900.00Rp 9,726,007.50Rp 0.975 7.425 0.975 0 0 7.425 0.975
21 Pek. Besi Tulangan 1031.20 Kg 19,295.00Rp 19,897,004.00Rp 1.994 627.600 1.214 0 0 627.600 1.214
22 Pek. Bekesting Balok Lantai 72.00 m² 220,135.00Rp 15,849,720.00Rp 1.588 72.000 1.588 0 0 72.000 1.588
23 Pek. Balok Lantai 20/30 1.58 m³ 1,309,900.00Rp 2,074,881.60Rp 0.208 1.584 0.208 0 0 1.584 0.208
24 Pek. Besi Tulangan 269.94 Kg 19,295.00Rp 5,208,492.30Rp 0.522 151.000 0.292 0 0 151.000 0.292
25 Pek. Bekesting Balok Lantai 24.64 m² 220,135.00Rp 5,424,126.40Rp 0.544 24.640 0.544 0 0 24.640 0.544
26 Pek. Plat Beton Lantai II T = 12cm 11.76 m³ 1,309,900.00Rp 15,409,139.64Rp 1.544 11.764 1.544 0 0 11.764 1.544
27 Pek. Besi Tulangan 1687.64 Kg 19,295.00Rp 32,563,013.80Rp 3.263 1175.000 2.272 0 0 1175.000 2.272
28 Pek. Bekesting Plat Lantai II 70.66 m² 373,135.00Rp 26,365,719.10Rp 2.642 70.660 2.642 0 0 70.660 2.642
29 Pek. Beton Ring Balak Lt. 1 1.142 m³ 1,309,900.00Rp 1,496,429.76Rp 0.150 1.142 0.150 0 0 1.142 0.150
30 Pek. Besi Tulangan 120.000 Kg 19,295.00Rp 2,315,400.00Rp 0.232 120.000 0.232 0 0 120.000 0.232
31 Pek. Bekesting Ring Balak 19.040 m² 220,135.00Rp 4,191,370.40Rp 0.420 19.040 0.420 0 0 19.040 0.420
32 Pek. Plat Beton tangga dan Bordes 2.110 m³ 1,309,900.00Rp 2,763,889.00Rp 0.277 0.050 0.007 0 0 0.050 0.007
33 Pek. Besi Tulangan 150.000 Kg 19,295.00Rp 2,894,250.00Rp 0.290 150.000 0.290 0 0 150.000 0.290
34 Pek. Bekesting Plat Beton Tangga 15.000 m² 373,135.00Rp 5,597,025.00Rp 0.561 15.000 0.561 0 0 15.000 0.561
35 Pek. Ring Balak 15/20 Lt. 2 1.277 m³ 1,309,900.00Rp 1,672,480.32Rp 0.168 1.277 0.168 0 0 1.277 0.168
TOTAL PEKERJAAN PASANGAN BATU
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 21 Page 147 of 150
36 Pek. Besi Tulangan 125.000 Kg 19,295.00Rp 2,411,875.00Rp 0.242 125.000 0.242 0 0 125.000 0.242
37 Pek. Bekesting Ring Balak 22.400 m² 220,135.00Rp 4,931,024.00Rp 0.494 22.400 0.494 0 0 22.400 0.494
38 Pek. Cor Lantai Kasar tebal 5 cm 10.000 m³ 660,925.00Rp 6,609,250.00Rp 0.662 10.000 0.662 0 0 10.000 0.662
323,453,547.04Rp 32.416 Sub Total 29.981 Sub Total 0.000 Sub Total 29.981
V. Pekerjaan Plesteran/Acian dan Keramik
1 Pek. Plesteran Dinding spesi 1 : 3 150.00 m² 37,225.00Rp 5,583,750.00Rp 0.560 150.000 0.560 0 0 150.000 0.560
2 Pek. Plesteran Dinding spesi 1 : 5 875.65 m² 34,405.00Rp 30,126,600.63Rp 3.019 875.650 3.019 0 0 875.650 3.019
3 Pek. Plesteran Beton spesi 1 : 3 123.54 m² 46,130.00Rp 5,698,900.20Rp 0.571 85.400 0.395 0 0 85.400 0.395
4 Pek. Plesteran Kaki pondasi 20.00 m² 37,225.00Rp 744,500.00Rp 0.075 20.000 0.075 0 0 20.000 0.075
5 Pek. Acian dgn PC 1169.19 m² 12,150.00Rp 14,205,609.90Rp 1.424 961.500 1.171 0 0 961.500 1.171
6 Pek. Pas. Tegel Granit 40 x 40 cm LT.1 302.26 m² 173,800.00Rp 52,532,788.00Rp 5.265 270.400 4.710 10.000 0.174 280.400 4.884
7 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 80.00 m¹ 12,780.00Rp 1,022,400.00Rp 0.102 60.400 0.077 12.000 0.015 72.400 0.093
8 Pek. Pas. Tegel Granit 40 x 40 cm LT.2 80.04 m² 173,800.00Rp 13,910,952.00Rp 1.394 57.000 0.993 8.000 0.139 65.000 1.132
9 Pek. Pas. Tegel Plint Kramik 10 x 40 cm 41.50 m¹ 12,780.00Rp 530,370.00Rp 0.053 12.000 0.015 18.000 0.023 30.000 0.038
10 Pek. Pas. Tegel 20 x 20 Lantai KM/WC 16.32 m² 169,470.00Rp 2,765,750.40Rp 0.277 12.800 0.217 0 0 12.800 0.217
11 Pek. Pas. Tegel 20 x 25 Dinding KM/WC 40.00 m² 169,400.00Rp 6,776,000.00Rp 0.679 32.100 0.545 0 0 32.100 0.545
12 Pek. Pas. Tegel Tangga 40 x 40 cm 25.00 m² 173,800.00Rp 4,345,000.00Rp 0.435 25.000 0.435 0 0 25.000 0.435
138,242,621.13Rp 13.854 Sub Total 12.212 Sub Total 0.352 Sub Total 12.564
VI. Pekerjaan Rangka Kap Baja Ringan dan Plafon
1 Pek. Kuda-Kuda Kap Baja Ringan 482.14 m² 239,595.00Rp 115,517,279.08Rp 11.577 482.136 11.577 0 0 482.136 11.577
2 Pek. Pas. Atap Genteng Metal 482.14 m² 111,895.00Rp 53,948,562.96Rp 5.407 482.136 5.407 0 0 482.136 5.407
3 Pek. Bumbungan Atap/Nok Metal 70.20 m¹ 73,955.00Rp 5,191,641.00Rp 0.520 70.200 0.520 0 0 70.200 0.520
4 Pas. Listplank 126.76 m¹ 87,580.00Rp 11,101,640.80Rp 1.113 126.760 1.113 0 0 126.760 1.113
5 Pas. Plafon Tripleks + Rangka Kayu (LT. I) 302.26 m² 98,769.25Rp 29,853,993.51Rp 2.992 302.260 2.992 0 0 302.260 2.992
6 Pek. Pas. Lis Plafon Kayu Profil (LT. I) 98.00 m¹ 35,714.75Rp 3,500,045.50Rp 0.351 98.000 0.351 0 0 98.000 0.351
7 Pas. Plafon Tripleks + Rangka Kayu Lt II 91.00 m² 98,769.25Rp 8,988,001.75Rp 0.901 91.000 0.901 0 0 91.000 0.901
8 Pek. Pas. Lis Plafon Kayu Profil (LT. II) 55.00 m¹ 35,714.75Rp 1,964,311.25Rp 0.197 55.000 0.197 0 0 55.000 0.197
9 Pas. Mur, Baut/Angker dan Plat Kawat 1.00 Ls 300,000.00Rp 300,000.00Rp 0.030 1.000 0.030 0 0 1.000 0.030
230,365,475.85Rp 23.087 Sub Total 23.087 Sub Total 0.000 Sub Total 23.087
VII. Pekerjaan Pintu, Kusen/Jendela + Ventilasi + Kaca
1 Pek. Kosen Jendela/Ventilasi Kayu 2.33 m³ 6,015,500.00Rp 13,990,128.04Rp 1.402 2.326 1.402 0 0 2.326 1.402
2 Pek. Kosen Pintu Aluminium Pintu Depan 12.20 m' 156,250.00Rp 1,906,250.00Rp 0.191 0 0 0 0 0 0
3 Pek. Kaca Mati 5 mm Polos pada Jendela 13.00 m² 221,738.75Rp 2,882,603.75Rp 0.289 10.400 0.231 2.600 0.058 13.000 0.289
4 Pek. Jendela Kaca 5 mm Bingkai Kayu 60.26 m² 539,900.00Rp 32,534,374.00Rp 3.261 48.200 2.608 12.06 0.653 60.260 3.261
5 Pek. Pas. Pintu Kaca t=8mm Bingkai Aluminium 4.00 Buah 2,100,000.00Rp 8,400,000.00Rp 0.842 0 0 0 0 0 0
6 Pek. Pas. Pintu Panel Bingkai Kayu 10.00 Buah 950,000.00Rp 9,500,000.00Rp 0.952 10.000 0.952 0 0 10.000 0.952
7 Pek. Pintu KM/WC (PVC) 5.00 Set 450,000.00Rp 2,250,000.00Rp 0.225 5.000 0.225 0 0 5.000 0.225
71,463,355.79Rp 7.162 Sub Total 5.419 Sub Total 0.710 Sub Total 6.129
VIII. Pekerjaan Pengecatan
TOTAL PEKERJAAN PINTU, KUSEN/JENDELA + VENTILASI + KACA
TOTAL PEKERJAAN COR DAN BETON
TOTAL PEKERJAAN PLESTERAN/ACIAN DAN KERAMIK
TOTAL PEKERJAAN RANGKA KAP BAJA RINGAN DAN PLAFON
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 21 Page 148 of 150
1 Pek. Pengecatan Dinding 1149.19 m² 23,058.00Rp 26,497,930.79Rp 2.656 881.700 2.037 152.000 0.351 1033.700 2.389
2 Pek. Pengecatan Plafon 393.26 m² 23,058.00Rp 9,067,789.08Rp 0.909 386.600 0.893 0 0 386.600 0.893
3 Pek. Pengecatan Listplank Beton 66.48 m² 41,352.50Rp 2,749,114.20Rp 0.276 66.480 0.276 0 0 66.480 0.276
4 Pengecatan Pintu Panel 15.60 m² 41,352.50Rp 645,099.00Rp 0.065 12.480 0.052 0 0 12.480 0.052
38,959,933.07Rp 3.905 Sub Total 3.258 Sub Total 0.351 Sub Total 3.609
IX. Pekerjaan Instalasi Listrik
1 Pek. Pas. Box Panel Lengkap dengan MCB 1.00 Set 2,500,000.00Rp 2,500,000.00Rp 0.251 1.000 0.251 0 0 1.000 0.251
2 Pek.Instalasi Titik Mata Lampu + Kabel 60.00 Ttk 120,000.00Rp 7,200,000.00Rp 0.722 60.000 0.722 0 0 60.000 0.722
3 Pek.Instalasi Titik Mata AC 5.00 Ttk 200,000.00Rp 1,000,000.00Rp 0.100 5.000 0.100 0 0 5.000 0.100
4 Stop Kontak 41.00 Bh 17,500.00Rp 717,500.00Rp 0.072 41.000 0.072 0 0 41.000 0.072
5 Saklar Tunggal 1.00 Bh 17,500.00Rp 17,500.00Rp 0.002 1.000 0.002 0 0 1.000 0.002
6 Saklar Ganda 13.00 Bh 25,000.00Rp 325,000.00Rp 0.033 13.000 0.033 0 0 13.000 0.033
11,760,000.00Rp 1.179 Sub Total 1.179 Sub Total 0.000 Sub Total 1.179
X. Pekerjaan Sanitasi
1 Pek. Pipa Instalasi Air Bersih Pvc 1/2" 50.00 m¹ 18,573.00Rp 928,650.00Rp 0.093 50.000 0.093 0 0 50.000 0.093
2 Kran Air 1/2" 4.00 Bh 32,543.75Rp 130,175.00Rp 0.013 0 0 0 0 0 0
3 Floor Drain 4.00 Bh 27,075.00Rp 108,300.00Rp 0.011 4.000 0.011 0 0 4.000 0.011
4 Kloset Jongkok 3.00 Bh 692,000.00Rp 2,076,000.00Rp 0.208 3.000 0.208 0 0 3.000 0.208
5 Kloset Duduk Lengkap 1.00 Bh 2,472,685.00Rp 2,472,685.00Rp 0.248 1.000 0.248 0 0 1.000 0.248
6 Pek. Pipa Air Kotor (PVC 2") 20.00 m¹ 42,773.00Rp 855,460.00Rp 0.086 20.000 0.086 0 0 20.000 0.086
7 Pek. Pipa Air Kotor (PVC 3") 20.00 m¹ 56,523.00Rp 1,130,460.00Rp 0.113 20.000 0.113 0 0 20.000 0.113
7,701,730.00Rp 0.772 Sub Total 0.759 Sub Total 0.000 Sub Total 0.759
XI. Pekerjaan Kunci dan Penggantung
1 Pek. Pas. Kunci Pintu 9.00 Bh 161,875.00Rp 1,456,875.00Rp 0.146 0 0 9.000 0.146 9.000 0.146
2 Pek. Pas. Engsel Pintu 4 " 15.00 Psg 29,816.75Rp 447,251.25Rp 0.045 15.000 0.045 0 0 15.000 0.045
3 Floor Hinge (Engsel Lantai) 4.00 Psg 850,000.00Rp 3,400,000.00Rp 0.341 0 0 4.000 0.341 4.000 0.341
4 Pek. Engsel Jendela Bingkai Kayu 46.00 Psg 25,570.50Rp 1,176,243.00Rp 0.118 37.000 0.095 9.000 0.023 46.000 0.118
5 Pas. Door Closer 1.00 Bh 450,000.00Rp 450,000.00Rp 0.045 0 0 0 0 0 0
6 Pas. Grendel Jendela 46.00 Bh 40,000.00Rp 1,840,000.00Rp 0.184 37.000 0.148 9.000 0.036 46.000 0.184
7 Pas. Hak Angin Jendela 46.00 Psg 39,250.00Rp 1,805,500.00Rp 0.181 37.000 0.146 9.000 0.035 46.000 0.181
8 Pas. Handel Pintu Stainless 4.00 Psg 120,000.00Rp 480,000.00Rp 0.048 4.000 0.048 0 0 4.000 0.048
11,055,869.25Rp 1.108 Sub Total 0.482 Sub Total 0.581 Sub Total 1.063
XII. Pekerjaan Akhir
1 Pek. Finishing dan Pembersihan Akhir 1.00 Ls 1,850,000.00Rp 1,850,000.00Rp 0.185 0 0 0 0 0 0
2 Pek. Pas. Railing Tangga Stainless 10.00 m' 300,000.00Rp 3,000,000.00Rp 0.301 10.000 0.301 0 0 10.000 0.301
3 Pek. Septic Tank dan Peresapan 1.00 Bh 1,850,000.00Rp 1,850,000.00Rp 0.185 1.000 0.185 0 0 1.000 0.185
6,700,000.00Rp 0.671 Sub Total 0.486 Sub Total 0.000 Sub Total 0.486
997,821,223.49Rp 100 Total 92.708 Total 1.995 Total 94.703J U M L A H T O T A L P E K E R J A A N
TOTAL PEKERJAAN PENGECATAN
TOTAL PEKERJAAN INSTALASI LISTRIK
TOTAL PEKERJAAN SANITASI
TOTAL PEKERJAAN KUNCI DAN PENGGANTUNG
TOTAL PEKERJAAN AKHIR
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 21 Page 149 of 150
Disetujui Oleh: Diperiksa Oleh : Dibuat Oleh :
Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi
Pembangunan Gedung Kantor Dinas Pekerjaan Umum Kab. Poso CV. Matra Griya Mandiri
Mappatunru Usman, S.T. Yoppy Soleman, S.T., M.T. Ir. Zainal Djamal, IPP
NIP. 19700825 200003 1 009 NIP. 19710731 200903 1 001 Direktur
Laporan Konsultan Pengawas CV. Matra Griya Mandiri - Week 21 Page 150 of 150