    LAMPIRAN 1 –  JAM KERJA EFEKTIF & PRAKIRAAN TOTAL PRODUKSI

    Description Unit Comments 2015 2016 2017 2018 2019 2020 2021 2022 2023 TOT

    WORKING

    HOURS

    Calendar Days Day 365 366 365 365 365 366 365 365 365 3,287

    Calendar Hours Hours 8,760 8,784 8,760 8,760 8,760 8,784 8,760 8,760 8,760 78,888

    Production

    Shutdown Hours 420 420 420 420 432 420 420 420 420 3,792

    Shift Change Hours 12 hr/s.c 324 324 324 324 324 324 324 324 324 2,916

    Independence

    Day Hours 12 12 12 12 12 12 12 12 12 108

    Idul Fitri Hours 24 24 24 24 24 24 24 24 24 216

    Idul Adha Hours 12 12 12 12 12 12 12 12 12 108

    Christmas Hours 24 24 24 24 24 24 24 24 24 216

    Election 12

    New Years Hours 24 24 24 24 24 24 24 24 24 216

    Production

    Delays Hours 2,263.38 2,267.38 2,263.38 2,263.38 2,263.25 2,267.38 2,263.38 2,263.38 2,263.38 20,378

    Daily DS/NS

    change over Hours 15 min/shift 175.75 176.25 175.75 175.75 175.75 176.25 175.75 175.75 175.75 1,583

    Other delay

    (kepentingan

    pribadi) Hours

    75

    min/day min/day456.25 457.50 456.25 456.25 456.25 457.50 456.25 456.25 456.25 4,108.75

    Meals time Hours 1 hr/shift 703.00 705.00 703.00 703.00 703.00 705.00 703.00 703.00 703.00 6,331

  • 8/20/2019 Lampiran 1 - Jam Kerja Efektif.pdf

    2/3

    Fatique

    management Hours 15 min/Nshift 79.38 79.63 79.38 79.38 79.25 79.63 79.38 79.38 79.38 714.75

    Waiting

    Equipment Hours min/day - - - - - - - - - -

    Safety Meeting Hours min/day - - - - - - - - - -

    Blasting Hours hr/day - - - - - - - - - -

    Friday Praying Hours 1.00 hr/week 54.00 54.00 54.00 54.00 54.00 54.00 54.00 54.00 54.00 486.00

    Fasting Month Hours

    2.5

    hr/day hr/day 75.00 75.00 75.00 75.00 75.00 75.00 75.00 75.00 75.00 675.00

    Due to Rain &

    Clean_Up Hours hr/day 720.00 720.00 720.00 720.00 720.00 720.00 720.00 720.00 720.00 6,480.0

    Down Time

    PC 200

    LC-8 hr/Month 1,314 1,318 1,314 1,314 1,314 1,318 1,314 1,314 1,314 11,833.2

    PC 200

    LC-8 hr/Month 1,314 1,318 1,314 1,314 1,314 1,318 1,314 1,314 1,314 11,833.2

    Available Hours

    PC 200

    LC-8 7,026 7,046 7,026 7,026 7,014 7,046 7,026 7,026 7,026 63,263

    PC 200

    LC-8 7,026 7,046 7,026 7,026 7,014 7,046 7,026 7,026 7,026 63,263

    Effective Hours

    PC 200

    LC-8 4,763 4,779 4,763 4,763 4,751 4,779 4,763 4,763 4,763 42,885

    PC 200

    LC-8 4,763 4,779 4,763 4,763 4,751 4,779 4,763 4,763 4,763 42,885

    -

    Effective

    Utilization

    PC 200

    LC-868% 68% 68% 68% 68% 68% 68% 68% 68% 68%

    PC 200

    LC-868% 68% 68% 68% 68% 68% 68% 68% 68% 68%

  • 8/20/2019 Lampiran 1 - Jam Kerja Efektif.pdf

    3/3

     

    Gross Utilization

    PC 200

    LC-854% 54% 54% 54% 54% 54% 54% 54% 54% 54%

    PC 200

    LC-854% 54% 54% 54% 54% 54% 54% 54% 54% 54%

    Production

    Achievable

    PC 200

    LC-8 Bcm/hrs 72 72 72 72 72 72 72 72 7272

    Bcm/year 342,909 344,090 342,909 342,909 342,054 344,090 342,909 342,909 342,909 3,087,688

    PC 200

    LC-8 Bcm/hrs 64 64 64 64 64 64 64 64 6464

    Bcm/year 304,808 305,858 304,808 304,808 304,048 305,858 304,808 304,808 304,808 2,744,611

    Total

    Production

    Forecast BCM647,717 649,947 647,717 647,717 646,102 649,947 647,717 647,717 647,717 5,832,299

    Total

    Production

    Forecast TON404,823 406,217 404,823 404,823 403,814 406,217 404,823 404,823 404,823 3,645,187